FY 2027-2031 CIP Funding Summary

City of Mesa — City Council (2026-06-01)

View PDF Meeting page

Extracted text (via pymupdf) 154116 characters
2027 – 2031 Capital Improvement Program 
Project Summary by Fund 
City of Mesa
i of xii
Proposed Five Year Capital Improvement Program

Aquatics ................................................................................................................ 1 
Red Mountain Aquatic Facility (CP0757) ................................................................ 1 
Southeast Aquatic Facility (CP0756) ...................................................................... 1 
Cemetery .............................................................................................................. 1 
Cemetery SRP Canal Relocation (CP1179) ........................................................... 1 
PRCF – Cemetery North Expansion (CP1310…………………………………………1 
City Facilities/General Government .................................................................... 1 
145 N Centennial Way Building Improvements (CP1296) ...................................... 1 
165 N Centennial Way Building Improvements (CP1297) ...................................... 1 
2025 FY22 Economic Development Downtown HUD Grant (CP1289) ................... 1 
245 N Centennial Way Building Improvements (CP1299) ...................................... 2 
Downtown District Revitalization - ARPA (CP1080) ............................................... 2 
East Mesa Service Center Electric Master Plan (CP1240) ..................................... 2 
FM-Centennial Garage Repairs (CP1306) ............................................................. 2 
FM-Pepper Parking Garage Repairs (CP1307) ...................................................... 2 
Fuel Station Improvements (CP1005) .................................................................... 2 
Mesa City Hall and Council Chambers (CP1137) ................................................... 2 
Restaurant & Food Business Incubator (CP1102) .................................................. 2 
Sirrine Garage (CP1176) ....................................................................................... 3 
The GRID (CP1247)............................................................................................... 3 
Wellness Center-59 S Hibbert (CP1184) ................................................................ 3 
West Mesa Service Center Fleet (CP1364) ............................................................ 3 
West Mesa Service Center Warehouse (CP1360) ................................................. 3 
Wireless Broadband Expansion (CP1124) ............................................................. 3 
Communications .................................................................................................. 4 
Distributed Antenna System for Phoenix Mesa Gateway Airport (CP0839)  ........... 4 
Internet Protocol Network Router Expansion-Mesa Share (CN0052)  .................... 4 
Mesa Share for TOPAZ - Site Expansion #2 (CN0038) .......................................... 4 
City of Mesa
ii of xii
Proposed Five Year Capital Improvement Program

Mesa Share for TOPAZ - Site Expansion #3 (CN0048) .......................................... 4 
Mesa Share for TOPAZ - VHF Sys Coverage Imprvmnt & Chnl Exp (CN0071) ...... 4 
Mesa Share of TOPAZ-P25 Voice Radio Ntwrk Lifecycle Upgrade (CN0114) ........ 4 
Public Safety Fiber - Phase II (CP0696) ................................................................. 4 
TOPAZ Internet Protocol Network Router Expansion (CP0755) ............................. 5 
TOPAZ – Northeast Valley-Wolverine Expansion Site (CP0754) ........................... 5 
TOPAZ – P25 Voice Radio Network Lifecycle Upgrade (CP1359) ......................... 5 
TOPAZ Radio Coverage Impmt for Northern Service Area - MS (CP1345) ............ 5 
TOPAZ – Radio Coverage Improvement for Mesa & Gilbert (CP1344) .................. 5 
TOPAZ – Radio Coverage Improvement for Mesa & Gilbert - MS (CP1346) .......... 5 
TOPAZ – Radio Coverage Improvement for Northern Service Area (CP1343) ....... 5 
TOPAZ – Reloc FS262 Radio Site to AJ Rodeo Grounds (CP1311) ...................... 6 
TOPAZ – Reloc FS262 to Apache Jctn Rodeo Grounds - MS (CP1312) ................ 6 
TOPAZ – Southeast Valley-Queen Creek Expansion Site (CP0779) ...................... 6 
TOPAZ – Tower Maintenance (Infrastructure) (CP1200) ........................................ 6 
TOPAZ - Tower Maintenance (Infrastructure) – Mesa Share (CN0099) ................. 6 
TOPAZ VHF System Coverage Improvement & Channel Expansion (CP0907) ..... 6 
District Cooling .................................................................................................... 6 
FM District Cooling Infrastructure Repairs (CP1264) .............................................. 6 
Electric .................................................................................................................. 7 
Downtown Electric Improvements - New Services (CP0883) ................................. 7 
Electric Distribution Overhead (CP1076) ................................................................ 7 
Electric Distribution Underground (CP1077) ........................................................... 7 
Electric Generation (CP0082) ................................................................................ 7 
Electric Improvements for Sewer Line Relocation (CP1207) .................................. 7 
Electric Metering (CP0435) .................................................................................... 7 
Electric Smart Grid (CP0081) ................................................................................. 7 
Electric Substation Improvements (CP0461) .......................................................... 7 
Electric System Improvements (CP1012) ............................................................... 8 
City of Mesa
iii of xii
Proposed Five Year Capital Improvement Program

Electric Systems Retirements (CP0591) ................................................................ 8 
Electric Transmission (CP1011) ............................................................................. 8 
Install New 69kv Switch at Stapley & University (CP1249) ..................................... 8 
New Electric Services (CP1075) ............................................................................ 8 
Site 17 Electric & Gas Improvements (CP1308) ..................................................... 8 
Smart Cities 69kV Looping (CP1031) ..................................................................... 8 
South Main Street Alley Electrical Improvements (CP1293) ................................... 8 
The Edge on Main (311 W. Main) (CP1204) .......................................................... 9 
Utility Large Scale Generator Project (CP1114) ..................................................... 9 
West Mesa Electric Utility Improvements (424 W. Main) (CP1205) ........................ 9 
Environment and Sustainability .......................................................................... 9 
Electric Vehicle Charging Infrastructure (CP1100) ................................................. 9 
Falcon Field Airport ............................................................................................. 9 
Airport Sustainability Energy Plan (CN0105) .......................................................... 9 
Anzio Taxilane and Ramp Reconstruction (CP0993).............................................. 9 
Citrus Grove Land Conversion (CP1339) ............................................................... 9 
City Owned Buildings and Property Improvements (CP0763) .............................. 10 
Conduct Airport Economic Impact Study Update (CN0113) ................................. 10 
Construct Midfield Taxiway F and Realign Taxiway D3,D4 (CP0994) .................. 10 
Design and Construct West Airport Perimeter Road and Apron (CP1225) ........... 10 
Draft a Title VI Plan & Community Participation Plan (CN0106) ........................... 10 
Eastside Taxilane Design and Construction (C06020) ......................................... 10 
F.A.R. Part 150 Noise & Land Use Compatibility Study (CN0111) ....................... 10 
Holding Bay Apron (CP1222) ............................................................................... 10 
Reconstruct Three Access Apron Areas (CP1259) .............................................. 11 
Rehabilitate Taxiway Echo (CP1261) ................................................................... 11 
City of Mesa
iv of xii
Proposed Five Year Capital Improvement Program

Fire ...................................................................................................................... 11 
Fire Apparatus (CN0055) ..................................................................................... 11 
Fire Fuel Station Tanks (CP1152) ........................................................................ 11 
Fire Station 205: Rebuild (C10120) ...................................................................... 11 
Fire Station 2202 Remodel/Renovation (CP1062) ................................................ 11 
Fire Station 223 (C10124) .................................................................................... 11 
Fire Station 224 (C10128) .................................................................................... 12 
Fire Station Exhaust System (CP1051) ................................................................ 12 
Fire Stations: Land Acquisition for New Stations (CP0103) .................................. 12 
Mesa Fire and Medical Department Response Facilities (CP1241) ...................... 12 
Mesa Fire and Medical Restrooms Remodel (CP1232) ........................................ 12 
MFMD New Apparatus (CN0083)......................................................................... 12 
Hohokam Stadium/Fitch Park ........................................................................... 12 
Hohokam and Fitch Improvements (CP1292) ...................................................... 12 
Intelligent Transportation System .................................................................... 13 
Central Traffic Signal System (CP0655) ............................................................... 13 
ITS Field Network Upgrade (CP0980) .................................................................. 13 
Ped Beacon on Dbsn/Brdwy, Sgnl at Mesa Dr/Cnsld Cnl (CP1110) ..................... 13 
Traffic Management Center Upgrade (CP1278) ................................................... 13 
Traffic Signals - New and Upgrade (CP1067) ...................................................... 13 
Traffic Signals - Public Safety Opticom (CP0702) ................................................ 13 
Library ................................................................................................................ 13 
Dobson Ranch Library Study and Updates (CP1158) .......................................... 13 
Gateway Library (CP0428) ................................................................................... 13 
Main Branch Signage (CP1273) ........................................................................... 14 
Main Library North Lawn Redevelopment (CP1197) ............................................ 14 
MPL Book Locker Expansion (CP1272) ............................................................... 14 
Red Mountain Children’s Room Renovation (CP1170) ......................................... 14 
City of Mesa
v of xii
Proposed Five Year Capital Improvement Program

Red Mountain Library Program Room Renovation (CP1302) ............................... 14 
Saguaro Room Renovation (CP1301) .................................................................. 14 
Mesa Arts Center ............................................................................................... 14 
MAC Arroyo Redevelopment (CP1356) ............................................................... 14 
Mesa Arts Center Box Office Remodel (CP1335) ................................................. 14 
Mesa Arts Center Campus Signage Restoration (CP1336) .................................. 15 
Mesa Arts Center Lighting Control System Replacement (CP1191) ..................... 15 
Museum .............................................................................................................. 15 
idea Museum (Phase 2) (CP1219) ....................................................................... 15 
Natural Gas Growth ........................................................................................... 15 
Arizona Farms Road High Pressure Main & Gate Station (CP0517) .................... 15 
Clausen Gate Station Improvements (CP1244).................................................... 15 
Gantzel Road Projects (CP0519) ......................................................................... 15 
Gas Aging Infrastructure Replacement (CP1073) ................................................ 15 
Gas Construction – POM (CP1255) ..................................................................... 16 
Gas-Customer Upgrades (CP0890) ..................................................................... 16 
Gas Meters: New and Replacement (CP1074)..................................................... 16 
Gas New Mains (CP1071) ................................................................................... 16 
Gas New Services (CP1070) ............................................................................... 16 
Hawes Crossing Gas Extension (Mesquite to Warner) (CP1349) ......................... 16 
High Pressure Gas Main Installation POM (CP1069) ........................................... 16 
Transwestern Gate Station (CP1350) .................................................................. 16 
Natural Gas Replacements ................................................................................ 17 
Gas Line Retirements (CP0563) .......................................................................... 17 
Gas Meters: New and Replacement-RER Funded (CP0496) ............................... 17 
Gas Quarter Sections (CP1112) .......................................................................... 17 
City of Mesa
vi of xii
Proposed Five Year Capital Improvement Program

Regulator Station Security (C10388) .................................................................... 17 
Parks & Recreation ............................................................................................ 17 
Aripine Park Playground Renovation (CP1182).................................................... 17 
Brady Park Dog Park Renovation (CP1304) ........................................................ 17 
Dog Park - Countryside Park (CP0933)................................................................ 17 
Indoor Recreation Center (CP1208) ..................................................................... 18 
Northeast Mesa Regional Trails (CP1210) ........................................................... 18 
Park Renovations (CP1175) ................................................................................. 18 
Pickleball Courts (CP1212) .................................................................................. 18 
Red Mountain Park Community Athletic Fields (CP0932) .................................... 18 
Signal Butte Park Phase 2 (CP0707) ................................................................... 18 
Sirrine House Remodel (CP1171) ........................................................................ 18 
Sloan Park Facility Improvements (CP0723) ........................................................ 18 
Water Conservation (CP1214) ............................................................................. 19 
Police .................................................................................................................. 19 
Central Station Renovation (CP0540) .................................................................. 19 
MFAC Miscellaneous Improvements (CP1288) .................................................... 19 
Northeast Public Safety Facility Covered Parking (CP1284) ................................ 19 
Police Headquarters (CP0204) ............................................................................ 19 
Public Safety Training Facility Building Improvements (CP0098) ......................... 19 
RTCC Flock DJI3 Deployment (CP1303) ............................................................. 19 
Public Safety Support ........................................................................................ 20 
Mesa Public Safety Communications (MPSC) (CP1239) ..................................... 20 
Shared Use Paths .............................................................................................. 20 
Active Transportation (CP1313) ........................................................................... 20 
Downtown Multimodal Pathway, Zone 3 & 4 (CP1353) ........................................ 20 
City of Mesa
vii of xii
Proposed Five Year Capital Improvement Program

Eastern Canal Shared-Use Path Broadway to Baseline (CP0730) ....................... 20 
Eastern Canal Shared-Use Path: Brown to Broadway (CP1060) ......................... 20 
Eastern Canal Shared-Use Path: Brown to Broadway-Signals (CP0673) ............. 20 
L202 Red Mountain Shared-Use Path – Val Vista to Thomas Rd (CP0674) ......... 20 
L202 Red Mountain SUP-Power Rd past Thomas Rd (CP0733) .......................... 21 
Lehi Crossing Pathway Phase II (CP0990) .......................................................... 21 
Lehi Loop Tunnel Wall (CP1194) ......................................................................... 21 
Mesa Gateway Phase 3 Bridge (CP1178) ............................................................ 21 
South Canal from McKellips to McDowell (CP1320) ............................................. 21 
US60 Shared Use Path-Eastern to Consolidated Canal (CP1180) ....................... 21 
Solid Waste ........................................................................................................ 21 
Downtown Trash Compactor (CP1224) ................................................................ 21 
Food to Energy Project (CP0870) ........................................................................ 21 
Joint MRF & Transfer Station (CP1146) ............................................................... 22 
West Mesa Service Center CNG Station Upgrades (CP1061) ............................. 22 
Storm Sewer ....................................................................................................... 22 
Baseline and Signal Butte Drainage (CP1099) ..................................................... 22 
Candlelight Park Drainage-Drywell (CP1294) ...................................................... 22 
Main and Phyllis Storm Drain Improvements (CP1250) ........................................ 22 
Pecos Road Basin and Storm Drain Drainage (CP1230) ..................................... 22 
Recker Road Storm Channel Improvements (CP1266) ........................................ 22 
Southern and Hawes Drainage Improvements (CP1282) ..................................... 22 
Storm Drain Pump Stations (CP0491) .................................................................. 23 
Streets ................................................................................................................ 23 
2nd Street & Beverly Crosswalk (CP1300) ............................................................ 23 
ADOT Block Wall at Hopi Ave & 76th Place (CP1295) .......................................... 23 
AR - Broadway:Spur to Gilbert (CP1324) ............................................................. 23 
ASU Polytechnic Research Park (CP1117) .......................................................... 23 
City of Mesa
viii of xii
Proposed Five Year Capital Improvement Program

Baseline Rd-Greenfield to Power (Gilbert for ST0780) (CP1096) ......................... 23 
Bridge Safety Rehabilitation (CP0780) ................................................................. 23 
Broadway Rd from Stapley to Gilbert-Phase 2 (CP1090) ..................................... 23 
Broadway Road: Lesueur to Spur (CP0666) ........................................................ 24 
Center Street-University Dr to Main St (CP1298) ................................................. 24 
COM Comprehensive Safety Action Plan (CP1144) ............................................. 24 
Crismon Road Connection-Guadalupe Rd to Elliot Rd (CP1291) ......................... 24 
Downtown Traffic Signal Removal (CP1315) ....................................................... 24 
Elliot Road: Ellsworth to Sossaman (CP0982) ..................................................... 24 
Ellsworth Road from City Limits to Ray Road (CP0969) ....................................... 24 
Germann Road and Sossaman Road Intersection Study (CP1098) ..................... 25 
Guard Rail Repairs (CP1355) .............................................................................. 25 
Higley: McKellips to Broadway (CSAP) (CP1332) ................................................ 25 
Lehi – McDowell to Portia (CP1334) .................................................................... 25 
MAG Projects Local Match (CP0109) ................................................................... 25 
McKellips Road from 64th Street to Jasmine (CP1135) ......................................... 25 
Mesa 112 Warner & Sossaman Drainage Improvements (CN0102) ..................... 25 
Mesa Drive: Main Street to Brown Road (CP0664) .............................................. 25 
Mesa Drive Phase II Easements (CP1290) .......................................................... 25 
Mesa Drive: Southern Avenue to US 60 (C01817) ............................................... 26 
Mountain Rd from SR24 to Pecos (CP1136) ........................................................ 26 
Power Road Improvements: East Maricopa Floodway to Loop 202 (CP0104) ..... 26 
Princess Dr & Power Rd Valley Gutter (CP1357) ................................................. 26 
Ray Roads connections at Ellsworth Road (CP0983)........................................... 26 
Reimburse Queen Creek for Signal Butte Rd Impvmts CP0885 (CN0107) ........... 26 
RFFBs at Las Sendas Neighborhood (CP1337) ................................................... 26 
SafeTurn Initiative-SS4A Grant (CP1341) ............................................................ 26 
Signal Butte Road Improvements Segment 2, Pecos to Germann (CP0885) ....... 27 
Southern Avenue & Country Club Drive Roadways (CP0844) .............................. 27 
Stapley Drive and University Drive Intersection (C05041) .................................... 27 
Stapley Drive Sidewalk Installation (CP1160) ...................................................... 27 
City of Mesa
ix of xii
Proposed Five Year Capital Improvement Program

Street Improvement 2020 Cityshare (CN0087)..................................................... 27 
Streetlight Spot Improvements (CP1068) ............................................................. 27 
Thomas Rd Multimodal (CP1322) ........................................................................ 27 
Transportation Building Improvements (CP1149) ................................................. 27 
Val Vista Drive: Pueblo to US 60 (CP0062) .......................................................... 28 
Warner Rd Bridge (CP1330) ................................................................................ 28 
Warner Road: Mountain Rd. to Meridian Rd. (CP1242) ........................................ 28 
West side of Val Vista at South Canal (CP1215) .................................................. 28 
Transit ................................................................................................................. 28 
Bus Stop Improvement and Bus Shelter Construction (CP0992) .......................... 28 
Wastewater Growth............................................................................................ 28 
91st Avenue Water Reclamation Plant (Mesa Share) (CN0076) .......................... 28 
ASU IGA (CN0103) .............................................................................................. 28 
Greenfield Water Reclamation Plant Equipment (CP0898) .................................. 29 
Greenfield Water Reclamation Plant Equipment - Mesa Share (CN0068) ............ 29 
Greenfield Water Reclamation Plant Expansion 4 – Mesa Share (CN0096) ......... 29 
Greenfield Water Reclamation Plant Improvement (CP0897) ............................... 29 
Greenfield Water Reclamation Plant Improvement - Mesa Share (CN0067) ........ 29 
Greenfield Water Reclamation Plant – Phase 4 Expansion (CP1187) .................. 29 
New Lift Stations (CP0617) .................................................................................. 29 
New Sewer Lines - Other Areas (CP0619) ........................................................... 29 
SEWRP Lift Station and Forcemain (CP1229) ..................................................... 30 
Wastewater Replacements ................................................................................ 30 
Chrls Lstr Utilities Bldg Tenant Impr Architectural Concepts (CP1007) ................ 30 
GWRP Major Plant Improvements (CP0625) ....................................................... 30 
GWRP Major Plant Improvements – CP0625 Mesa Share (CN0035) .................. 30 
Lift Station Replacements (CP0958) .................................................................... 30 
Miscellaneous Water & Wastewater Projects (CP0899) ....................................... 30 
City of Mesa
x of xii
Proposed Five Year Capital Improvement Program

Northwest WRP Major Plant Improvements (CP0951) ......................................... 30 
Odor Control Station Replacements (CP0959) ..................................................... 31 
Sewer Line Condition Assessment (CP0957) ....................................................... 31 
Sewer Line Rehabilitation (CP0623) .................................................................... 31 
Sewer Line Replacement (CP0956) ..................................................................... 31 
Southern Avenue Interceptor Condition Assessment-City Share (CN0077) ......... 31 
Water Growth ..................................................................................................... 31 
Central Mesa Reuse Pipeline Project (CP0896) ................................................... 31 
East Mesa Water Interconnect Pipes (CP1050) ................................................... 31 
Fire Hydrant and Water Valve Replacement Program (CP0826) .......................... 32 
New Groundwater Wells (CP0836) ...................................................................... 32 
New Pump Stations (CP0830) ............................................................................. 32 
New Sewer Lines – Southeast Mesa (CP1185).................................................... 32 
Signal Butte Water Treatment Plant Expansion (CP0372) ................................... 32 
Val Vista Water Treatment Plant (Mesa Share) (CN0074) ................................... 32 
Water Extensions and Oversized Mains (CN0075) .............................................. 32 
Water Extensions and Oversized Mains-City Share (CN0064) ............................. 33 
Water Meter Vault Rehab Program (CP0825) ...................................................... 33 
Well Collection Lines (CP0648) ............................................................................ 33 
White Mountain Apache Water Settlement Water Rights (CN0028) ..................... 33 
Water Replacements .......................................................................................... 33 
Advanced Water Purification Facility (CN0110) .................................................... 33 
Brown Road Equipment Replacement (CP0966) ................................................. 33 
BRWTP Main Switchgear and Transformers Replacement (CP1254) .................. 33 
CK Luster Building Emergency Standby Power Upgrade (CP1054) ..................... 34 
Groundwater Well Replacement Program (CP0642) ............................................ 34 
Northwest Major Plant Improvements (CP1202) .................................................. 34 
Pump Station Replacement Program (CP0829) ................................................... 34 
Quarter Section Replacement Program (CP0834) ............................................... 34 
City of Mesa
xi of xii
Proposed Five Year Capital Improvement Program

Reservoir Rehabilitation Program (CP0831) ........................................................ 34 
Smart Metering (CP0900) .................................................................................... 34 
Utility Line Replacement Quarter Section 21D, Clark, Pepper (C10382) .............. 35 
Valves and Hydrant Replacements (CP1059) ...................................................... 35 
Water Line Replacement Program (CP0832) ....................................................... 35 
Water Main Replacement Program (CP1053) ...................................................... 35 
City of Mesa
xii of xii
Proposed Five Year Capital Improvement Program

COUNCIL DISTRICT 5
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2024 Parks Bond
$82,358
$4,720,000
-
$10,000,000
$10,670,000
$8,800,000
-
$34,272,358
O&M
Capital - General Fund
-
-
-
-
-
$1,396,452
-
$1,396,452
General Fund
-
-
-
-
-
$1,405,384
$4,548,566
$5,953,950
Total
$82,358
$4,720,000
-
$10,000,000
$10,670,000
$11,601,836
$4,548,566
$41,622,760
COUNCIL DISTRICT 6
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2024 Parks Bond
$226,341
$4,265,000
$20,000,000
$8,800,000
-
-
-
$33,291,341
O&M
Capital - General Fund
-
-
-
$1,390,391
-
-
-
$1,390,391
General Fund
-
-
-
$1,368,891
$1,419,570
$1,470,771
$4,729,969
$8,989,201
Total
$226,341
$4,265,000
$20,000,000
$11,559,281
$1,419,570
$1,470,771
$4,729,969
$43,670,933
COUNCIL DISTRICT 1
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Cemetery
$35,095
$925,000
-
-
-
-
-
$960,095
Total
$35,095
$925,000
-
-
-
-
-
$960,095
COUNCIL DISTRICT 1
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Cemetery
-
$800,000
-
-
-
-
-
$800,000
O&M
Cemetery
-
-
-
$8,472
$8,657
$8,855
$27,833
$53,816
Total
-
$800,000
-
$8,472
$8,657
$8,855
$27,833
$853,816
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
$659,076
$50,280
-
-
-
-
-
$709,356
Total
$659,076
$50,280
-
-
-
-
-
$709,356
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
$4,090,887
$1,113
-
-
-
-
-
$4,092,000
Total
$4,090,887
$1,113
-
-
-
-
-
$4,092,000
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
$633
$274,608
-
-
-
-
-
$275,241
Grants - Gen. Gov.
-
$300,192
-
-
-
-
-
$300,192
Total
$633
$574,800
-
-
-
-
-
$575,433
Capital Improvement Program Project Funding Summary 
Fiscal Years 2027 - 2031
Aquatics
PRCF - Cemetery North Expansion (CP1310)
Construct a new pool adjacent to Red Mountain Center.
Southeast Aquatic Facility (CP0756)
Expand the cemetery to the North
Red Mountain Aquatic Facility (CP0757)
City Facilities/General Government
145 N Centennial Way Building Improvements (CP1296)
Purchase building and make improvements at 145 N Centennial Way
165 N Centennial Way Building Improvements (CP1297)
Purchase building and make improvements at 165 N Centennial Way
2025 FY22 Economic Development Initiative Downtown HUD Grant 
(CP1289)
HUD grant for downtown initiatives
Cemetery
Cemetery SRP Canal Relocation (CP1179)
Relocate piped irrigation at cemetery
Build a new pool at Eastmark High School in partnership with Queen Creek Schools. Pool amenities will feature competition lanes, diving well, swim lesson 
space, and opportunities for water play.
City of Mesa
Page 1 of 35
Proposed Five Year Capital Improvement Program

COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
$325
$49,675
-
-
-
-
-
$50,000
Total
$325
$49,675
-
-
-
-
-
$50,000
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Special Programs 
Fund
$878,745
$3,593,434
-
-
-
-
-
$4,472,179
Total
$878,745
$3,593,434
-
-
-
-
-
$4,472,179
COUNCIL DISTRICT 5
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
$89,006
$463,612
-
-
-
-
-
$552,618
Total
$89,006
$463,612
-
-
-
-
-
$552,618
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
-
$651,600
-
-
-
-
-
$651,600
Total
-
$651,600
-
-
-
-
-
$651,600
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
-
$587,800
-
-
-
-
-
$587,800
Total
-
$587,800
-
-
-
-
-
$587,800
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
$217,178
$4,279,024
-
-
-
-
-
$4,496,202
Environmental 
Compliance Fee
$1,331,309
$2,720,976
-
-
-
-
-
$4,052,285
Total
$1,548,487
$7,000,000
-
-
-
-
-
$8,548,487
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
$33,563,709
$416,069
-
-
-
-
-
$33,979,778
Total
$33,563,709
$416,069
-
-
-
-
-
$33,979,778
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Relief Fund - ARP
$2,014,173
$2,500,000
-
-
-
-
-
$4,514,173
Total
$2,014,173
$2,500,000
-
-
-
-
-
$4,514,173
Infrastructure repairs at Pepper Garage.
Infrastructure repairs at Centennial Garage
FM-Centennial Garage Repairs (CP1306)
East Mesa Service Center Electrical Master Plan (CP1240)
245 N Centennial Way Building Improvements (CP1299)
Space planning, design, and remodel of building at 245 N Centennial Way.
Downtown District Revitalization-ARPA (CP1080)
Replace building facades in Downtown Mesa-ARPA Funded
Develop a shared commercial kitchen with a public facing dining facility, including procuring a location
Restaurant & Food Business Incubator (CP1102)
Mesa City Hall and Council Chambers (CP1137)
Fuel Station Improvements at various fuel sites citywide.
FM-Pepper Garage Repairs (CP1307)
Develop an Electrical Infrastructure Master Plan at EMSC to support various tenant improvements.
Demo and reconstruct the Northeast corner of Main St & Center with a new council chambers and municipal City hall
Fuel Station Improvements (CP1005)
City of Mesa
Page 2 of 35
Proposed Five Year Capital Improvement Program

COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
-
$1,525,000
-
-
-
-
-
$1,525,000
Total
-
$1,525,000
-
-
-
-
-
$1,525,000
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
$1,382,119
$273,116
-
-
-
-
-
$1,655,235
Local Streets Fund
$49,144
$17,256
-
-
-
-
-
$66,400
Total
$1,431,264
$290,372
-
-
-
-
-
$1,721,636
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Special Programs 
Fund
$103,866
$200,000
-
-
-
-
-
$303,866
Total
$103,866
$200,000
-
-
-
-
-
$303,866
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2026 Public Safety 
Bond
-
$1,848,701
$1,848,700
$16,638,301
$16,638,302
-
-
$36,974,004
Electric Utility 
Revenue Pledge
-
$37,033
$37,901
$348,590
$356,219
-
-
$779,742
Gas Utility Revenue 
Pledge
-
$185,166
$189,504
$1,742,951
$1,781,091
-
-
$3,898,712
Solid Waste Bond 
Construction
-
$1,444,297
$1,478,137
$13,595,021
$13,892,505
-
-
$30,409,959
Wastewater Utility 
Revenue Pledge
-
$74,066
$75,801
$697,180
$712,437
-
-
$1,559,484
Water Utility Revenue 
Pledge
-
$185,166
$189,504
$1,742,951
$1,781,091
-
-
$3,898,712
Total
-
$3,774,429
$3,819,548
$34,764,994
$35,161,644
-
-
$77,520,614
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2026 Public Safety 
Bond
-
$193,499
$193,500
$1,741,500
$1,741,501
-
-
$3,870,000
Electric Utility 
Revenue Pledge
-
$248,077
$253,889
$2,335,123
$2,386,219
-
-
$5,223,308
Gas Utility Revenue 
Pledge
-
$392,788
$401,991
$3,697,278
$3,778,181
-
-
$8,270,238
Solid Waste Bond 
Construction
-
$41,346
$42,315
$389,187
$397,703
-
-
$870,550
Warehouse Internal 
Service
-
$500,000
-
-
-
-
-
$500,000
Water Utility Revenue 
Pledge
-
$165,385
$169,260
$1,556,749
$1,590,814
-
-
$3,482,208
Total
-
$1,541,095
$1,060,955
$9,719,836
$9,894,418
-
-
$22,216,304
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
$724,231
$172,354
-
-
-
-
-
$896,585
Total
$724,231
$172,354
-
-
-
-
-
$896,585
Renovations at West Mesa Service Center Warehouse
Renovations at West Mesa Service Center Fleet
Remodel of 59 Hibbert to Convert into City Staff Use (Wellness Center)
Wellness Center-59 S Hibbert (CP1184)
Infrastructure repairs at Sirrine Garage
Deployment of wireless systems throughout Mesa for broadband use; may include design and construction of poles and other mounting locations for 
equipment, along with associated hardware, software and services.
Wireless Broadband Expansion (CP1124)
West Mesa Service Center Warehouse (CP1360)
West Mesa Service Center Fleet (CP1364)
The GRID (CP1247)
Developer in default.  City needs to complete right of way as designed.  We be utilizing escrow funds to complete project.
Sirrine Garage (CP1176)
City of Mesa
Page 3 of 35
Proposed Five Year Capital Improvement Program

COUNCIL DISTRICT 6
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
$1,500
$125,764
-
-
-
-
-
$127,264
Total
$1,500
$125,764
-
-
-
-
-
$127,264
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
-
$178,822
-
-
-
-
-
$178,822
Total
-
$178,822
-
-
-
-
-
$178,822
COUNCIL DISTRICT 5
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
$1,008,414
$997,688
-
-
-
-
-
$2,006,102
Total
$1,008,414
$997,688
-
-
-
-
-
$2,006,102
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
$1,737
$1,095,124
-
-
-
-
-
$1,096,861
Total
$1,737
$1,095,124
-
-
-
-
-
$1,096,861
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
$8,803
$971,058
-
-
$564,307
$288,609
-
$1,832,777
Total
$8,803
$971,058
-
-
$564,307
$288,609
-
$1,832,777
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2026 Public Safety 
Bond
-
-
$5,025,000
$5,025,000
-
-
-
$10,050,000
Total
-
-
$5,025,000
$5,025,000
-
-
-
$10,050,000
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2018 Public Safety 
Bond
$3,479,213
$2,317,793
-
-
-
-
-
$5,797,006
2024 Public Safety 
Bond
$32,825
$3,682,207
-
-
-
-
-
$3,715,032
Total
$3,512,037
$6,000,000
-
-
-
-
-
$9,512,037
Mesa Share for TOPAZ -  VHF Sys Coverage Imprvmnt & Chnl Exp 
(CN0071)
 
Add VHF coverage for the existing TRWC fire partner coverage area in Mesa, Gilbert, Apache Junction, and Queen Creek.
Mesa Share of TOPAZ-P25 Voice Radio Ntwrk Lifecycle Upgrade 
(CN0114)
Upgrade the existing TOPAZ 800 MHz voice radio network infrastructure which includes equipment at nine simulcast cell radio sites, backup Master Site 
(DSR), and geo-redundant Prime Site.
Public Safety Fiber - Phase II (CP0696)
Install underground fiber to support public safety and other City communication needs and strengthen redundancy.  This is the second phase to complete the 
three rings design to better serve the City's needs.
Mesa's cost share to construct a public safety radio site in the SE valley area to ensure reliable TOPAZ radio coverage. Improvements include land 
acquisition, a radio tower, equipment shelter, emergency generator, radio/network equipment, and services.
Mesa Share for TOPAZ - Site Expansion #3 (CN0048)
Mesa's share to construct a public safety radio site in the far NE area of Mesa to ensure reliable TOPAZ radio coverage. Improvements include land 
acquisition, a radio tower, equipment shelter, emergency generator, radio/network equipment, and services.
Mesa Share for TOPAZ - Site Expansion #2 (CN0038)
Fund Mesa's cost share to install internet protocol routers for the TOPAZ radio sites.  The new routers will provide full network direction/redirection 
capabilities for the TOPAZ radio sites and mitigate unscheduled impairments to the network.
Install an antenna system for the Mesa Gateway Airport to improve public safety radio coverage.
Internet Protocol Network Router Expansion - Mesa Share (CN0052)
Communications
Distributed Antenna System for Mesa Gateway Airport (CP0839)
City of Mesa
Page 4 of 35
Proposed Five Year Capital Improvement Program

CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Topaz Capital 
Programs
-
$208,460
-
-
-
-
-
$208,460
Total
-
$208,460
-
-
-
-
-
$208,460
COUNCIL DISTRICT 5
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Topaz Capital 
Programs
$2,047,768
$1,213,623
-
-
-
-
-
$3,261,391
Total
$2,047,768
$1,213,623
-
-
-
-
-
$3,261,391
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Topaz Capital 
Programs
-
-
$7,675,724
$7,844,082
-
-
-
$15,519,806
Total
-
-
$7,675,724
$7,844,082
-
-
-
$15,519,806
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
-
-
-
-
$897,761
$962,031
-
$1,859,793
Total
-
-
-
-
$897,761
$962,031
-
$1,859,793
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Topaz Capital 
Programs
-
-
-
-
$641,258
$765,252
-
$1,406,510
Total
-
-
-
-
$641,258
$765,252
-
$1,406,510
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
-
-
-
-
$429,643
$512,719
-
$942,362
Total
-
-
-
-
$429,643
$512,719
-
$942,362
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Topaz Capital 
Programs
-
-
-
-
$4,488,806
$4,810,157
-
$9,298,963
Total
-
-
-
-
$4,488,806
$4,810,157
-
$9,298,963
TOPAZ Internet Protocol Network Router Expansion (CP0755)
Purchase and install internet protocol routers for the TOPAZ radio sites.  The new routers will provide full network direction/redirection capabilities for the 
TOPAZ radio sites and mitigate unscheduled impairments to the TOPAZ network.
TOPAZ - Northeast Valley - Wolverine Expansion Site (CP0754)
Construct a public safety radio site in the far northeast area of Mesa to ensure reliable TOPAZ radio coverage. Improvements include land acquisition, a 
radio tower, equipment shelter, emergency generator, radio/network equipment, and services.
TOPAZ - P25 Voice Radio Network Lifecycle Upgrade (CP1359)
Upgrade the existing TOPAZ 800 MHz voice radio network infrastructure which includes equipment at nine simulcast cell radio sites, backup Master Site 
(DSR), and geo-redundant Prime Site.
TOPAZ Radio Coverage Impmt for Northern Service Area - MS 
(CP1345)
(Mesa Share) Radio coverage improvement for the TOPAZ Public Safety network for the northern Service Area (Rio Verde, Fort McDowell Yavapai Nation, 
Fountain Hills).  Current proposed solution is 1-2 additional radio sites.
TOPAZ - Radio Coverage Improvement for Mesa & Gilbert (CP1344)
Radio coverage improvement for the TOPAZ Public Safety network for south central Mesa and northern Gilbert.  Current proposed solution is to relocate the 
radio equipment at MF&MD station FS205 to GF&RD Station FS252.
TOPAZ - Radio Coverage Improvement for Mesa & Gilbert - MS 
(CP1346)
(Mesa Share) Radio coverage improvement for the TOPAZ Public Safety network for south central Mesa and northern Gilbert.  Current proposed solution is 
to relocate the radio equipment at MF&MD station FS205 to GF&RD Station FS252.
TOPAZ - Radio Coverage Improvement for Northern Service Area 
(CP1343)
Radio coverage improvement for the TOPAZ Public Safety network for the northern Service Area (Rio Verde, Fort McDowell Yavapai Nation, Fountain Hills).  
Current proposed solution is 1-2 additional radio sites.
City of Mesa
Page 5 of 35
Proposed Five Year Capital Improvement Program

CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Topaz Capital 
Programs
-
$400,000
$818,744
-
-
-
-
$1,218,744
Total
-
$400,000
$818,744
-
-
-
-
$1,218,744
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
-
$268,000
$548,558
-
-
-
-
$816,558
Total
-
$268,000
$548,558
-
-
-
-
$816,558
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Topaz Capital 
Programs
$2,729
$4,219,711
-
-
-
-
-
$4,222,440
Total
$2,729
$4,219,711
-
-
-
-
-
$4,222,440
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Topaz Capital 
Programs
-
$202,000
$104,390
$104,588
$106,876
$109,322
$343,614
$970,790
Total
-
$202,000
$104,390
$104,588
$106,876
$109,322
$343,614
$970,790
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
-
$137,690
$69,941
$70,074
$71,607
$73,246
$230,221
$652,779
Total
-
$137,690
$69,941
$70,074
$71,607
$73,246
$230,221
$652,779
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Topaz Capital 
Programs
$13,481
$1,320,221
-
-
$855,011
$437,287
-
$2,626,000
Total
$13,481
$1,320,221
-
-
$855,011
$437,287
-
$2,626,000
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
$362,268
$3,117,472
-
-
-
-
-
$3,479,740
Total
$362,268
$3,117,472
-
-
-
-
-
$3,479,740
Construct a public safety radio communication site in the southeast valley area to ensure reliable TOPAZ radio coverage.  Improvements include land 
acquisition, a radio tower, equipment shelter, emergency generator, radio/network equipment, and services.
TOPAZ - Tower Maintenance (Infrastructure) (CP1200)
The TRWC maintains over 15 Public Safety Radio sites.  Each of these sites has one or more radio towers.  Towers are audited annually for structural and 
safety issues.  This program will fund necessary maintenance, replacements, and/or upgrades.
TOPAZ - Tower Maintenance (Infrastructure) - Mesa Share (CN0099)
The TRWC maintains over 15 Public Safety Radio sites.  Each of these sites has one or more radio towers.  Towers are audited annually for structural and 
safety issues.  This program will fund necessary maintenance, replacements, and/or upgrades needed.
TOPAZ VHF System Coverage Improvement & Channel Expansion 
(CP0907)
TOPAZ-Reloc FS262 Radio Site to AJ Rodeo Grounds (CP1311)
Relocate a public safety radio site at Fire Station 262 to the rodeo grounds in Apache Junction.  This is to enhance the accessibility and administrative 
management of this radio site.
TOPAZ-Reloc FS262 to Apache Jctn Rodeo Grounds - MS (CP1312)
Mesa Share - Relocate a public safety radio site at Fire Station 262 to the rodeo grounds in Apache Junction.  This is to enhance the accessibility and 
administrative management of this radio site.
TOPAZ - Southeast Valley - Queen Creek Expansion Site (CP0779)
District Cooling
FM District Cooling Infrastructure Repairs (CP1264)
FM District Cooling infrastructure repairs
 
Add VHF coverage for the existing TRWC fire partner coverage area in Mesa, Gilbert, Apache Junction, and Queen Creek.
City of Mesa
Page 6 of 35
Proposed Five Year Capital Improvement Program

COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Electric Utility 
Revenue Pledge
$386,769
$100,000
$102,343
$104,588
$106,876
$109,322
$343,614
$1,253,512
Total
$386,769
$100,000
$102,343
$104,588
$106,876
$109,322
$343,614
$1,253,512
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Electric Utility 
Revenue Pledge
$1,283,147
$560,000
$573,121
$585,691
$598,507
$612,202
$1,924,237
$6,136,906
Total
$1,283,147
$560,000
$573,121
$585,691
$598,507
$612,202
$1,924,237
$6,136,906
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Electric Utility 
Revenue Pledge
$1,945,023
$550,000
$562,886
$575,233
$587,820
$601,270
$1,889,876
$6,712,108
Total
$1,945,023
$550,000
$562,886
$575,233
$587,820
$601,270
$1,889,876
$6,712,108
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Electric Utility 
Revenue Pledge
$241,445
$150,000
$112,577
$115,047
$117,564
$120,254
$377,975
$1,234,862
Special Programs 
Fund
$100,330
$1,898
-
-
-
-
-
$102,228
Total
$341,775
$151,898
$112,577
$115,047
$117,564
$120,254
$377,975
$1,337,090
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Electric Utility 
Revenue Pledge
-
$300,000
-
-
-
-
-
$300,000
Total
-
$300,000
-
-
-
-
-
$300,000
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Utility Replacement 
Extension and 
Renewal - ELC
$463,354
$500,000
$511,715
$522,939
$534,382
$546,609
$1,718,069
$4,797,067
Total
$463,354
$500,000
$511,715
$522,939
$534,382
$546,609
$1,718,069
$4,797,067
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Electric Utility 
Revenue Pledge
-
$128,208
$131,212
$134,090
$137,024
$140,159
$440,540
$1,111,233
Total
-
$128,208
$131,212
$134,090
$137,024
$140,159
$440,540
$1,111,233
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Electric Utility 
Revenue Pledge
$1,446,244
$728,000
$2,478,125
$4,117,210
$532,244
$358,575
$783,440
$10,443,838
Total
$1,446,244
$728,000
$2,478,125
$4,117,210
$532,244
$358,575
$783,440
$10,443,838
Electric
Downtown Electric Improvements - New Services (CP0883)
Install new service connections in support of downtown development.
Electric Distribution Overhead (CP1076)
Install system enhancements to ensure electric system reliability.  Improvements may include replacement of electrical overhead conductors, transformers, 
distribution poles and devices to increase reliability and reduce operating costs.
Electric Distribution Underground (CP1077)
Provide various system improvements to include underground conductor installation, cable replacement, vault lid replacement and replacement of 
miscellaneous devices. These improvements are planned over several fiscal years.
Electric Generation (CP0082)
Identify power supply resources, including solar power, that can be owned in whole or in part by the City of Mesa. Alternatives are being explored to improve 
the reliability and/or efficiency of the electric utility service.
Electric Improvements for Sewer Line Relocation (CP1207)
Electric's portion of relocation/improvements for 5,300 linear feet of new 12-inch water line in Broadway Road and in South Morris.
Electric Metering (CP0435)
Replace electric service meters based on 20-year lifecycle criteria.  In addition, replace meters based on known issues, such as potential coils that 
improperly register energy consumption.
Electric Smart Grid (CP0081)
Replace obsolete technology to improve system reliability and improve the ability to identify problems quickly and respond efficiently.
Electric Substation Improvements (CP0461)
Construct improvements at electric substations to ensure long-term system reliability.  These improvements will meet safety standards and improve security 
at the facilities.
City of Mesa
Page 7 of 35
Proposed Five Year Capital Improvement Program

COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Electric Utility 
Revenue Pledge
$1,018
$100,000
$102,343
$104,588
$106,876
$109,322
$343,614
$867,761
Total
$1,018
$100,000
$102,343
$104,588
$106,876
$109,322
$343,614
$867,761
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Electric
$158,690
$100,000
$102,343
$104,588
$106,876
$109,322
$343,614
$1,025,433
Total
$158,690
$100,000
$102,343
$104,588
$106,876
$109,322
$343,614
$1,025,433
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Electric Utility 
Revenue Pledge
$16,290
$108,207
$110,742
$113,171
$115,648
$118,294
$371,814
$954,166
Total
$16,290
$108,207
$110,742
$113,171
$115,648
$118,294
$371,814
$954,166
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Electric Utility 
Revenue Pledge
$1,412
$233,359
-
-
-
-
-
$234,771
Total
$1,412
$233,359
-
-
-
-
-
$234,771
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Electric Utility 
Revenue Pledge
$1,401,564
$1,500,000
$1,023,430
$1,045,878
$1,068,763
$1,093,218
$3,436,138
$10,568,990
Total
$1,401,564
$1,500,000
$1,023,430
$1,045,878
$1,068,763
$1,093,218
$3,436,138
$10,568,990
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Electric Utility 
Revenue Pledge
$2,366
$300,000
-
-
-
-
-
$302,366
Gas Utility Revenue 
Pledge
-
$300,000
-
-
-
-
-
$300,000
Total
$2,366
$600,000
-
-
-
-
-
$602,366
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Electric Utility 
Revenue Pledge
$347,298
$1,500,000
$1,432,802
-
-
-
-
$3,280,100
Total
$347,298
$1,500,000
$1,432,802
-
-
-
-
$3,280,100
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Relief Fund - ARP
$59,252
$51,405
-
-
-
-
-
$110,657
Total
$59,252
$51,405
-
-
-
-
-
$110,657
Electric System Improvements (CP1012)
Construct improvements to the electric overhead and underground distribution system. This effort will include conduit extension, switches, sectionalizing, and 
circuit ties.
Electric Systems Retirements (CP0591)
Replace electric system infrastructure to ensure reliability.
Electric Transmission (CP1011)
 
Rebuild the 69kV transmission system.  Install new conductors and poles throughout the system. 
Install New 69kv Switch at Stapley & University (CP1249)
69kv Switch Replacements
New Electric Services (CP1075)
Install new electrical service wires for new customers and provide for system expansion.
Site 17 Electric & Gas Improvements (CP1308)
Site 17 Electric & Gas Improvements
Smart Cities 69kV Looping (CP1031)
Upgrade and reconfigure 69kV system
South Main Street Alley Electrical Improvements (CP1293)
Electrical Improvements in the Alley along South Main to support new development in downtown Mesa
City of Mesa
Page 8 of 35
Proposed Five Year Capital Improvement Program

COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Electric Utility 
Revenue Pledge
$36,348
$1,572,485
$651,464
-
-
-
-
$2,260,297
Total
$36,348
$1,572,485
$651,464
-
-
-
-
$2,260,297
COUNCIL DISTRICT 1
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Electric Utility 
Revenue Pledge
-
$1,851,852
$1,895,241
$1,936,811
$1,979,191
$2,024,477
$6,363,220
$16,050,791
Total
-
$1,851,852
$1,895,241
$1,936,811
$1,979,191
$2,024,477
$6,363,220
$16,050,791
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
$463,124
$1,032,507
-
-
-
-
-
$1,495,631
Electric
-
$672,213
-
-
-
-
-
$672,213
Utility Replacement 
Extension and 
Renewal - ELC
$98,542
$3,695,280
-
-
-
-
-
$3,793,822
Total
$561,667
$5,400,000
-
-
-
-
-
$5,961,667
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
-
$600,000
-
-
-
-
-
$600,000
Environmental 
Compliance Fee
$2,122,679
$1,070,831
-
-
-
-
-
$3,193,510
Local Streets Fund
$195
$25,344
-
-
-
-
-
$25,539
Special Programs 
Fund
-
$2,185,825
-
-
-
-
-
$2,185,825
Total
$2,122,874
$3,882,000
-
-
-
-
-
$6,004,874
COUNCIL DISTRICT 5
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Falcon Field Airport
-
$100,000
-
-
-
-
-
$100,000
Grants - Gen. Gov.
-
$99,000
-
-
-
-
-
$99,000
Special Programs 
Fund
-
$100,000
-
-
-
-
-
$100,000
Total
-
$299,000
-
-
-
-
-
$299,000
COUNCIL DISTRICT 5
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Falcon Field Airport
$1,467
$251,856
-
-
-
-
-
$253,323
Falcon Field Grants
$461,236
$1,335,793
-
-
-
-
-
$1,797,029
Total
$462,704
$1,587,649
-
-
-
-
-
$2,050,353
COUNCIL DISTRICT 5
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Falcon Field Airport
-
$1,423,818
$1,500,893
$1,579,827
$1,662,830
$1,730,038
$5,846,204
$13,743,610
Total
-
$1,423,818
$1,500,893
$1,579,827
$1,662,830
$1,730,038
$5,846,204
$13,743,610
The Edge on Main (311 W. Main) (CP1204)
The proposed development includes two separate mixed-use apartment buildings with an open pedestrian plaza between them.  The buildings and 
pedestrian plaza area will be constructed within the current Morris St right-of-way.
Utility Large Scale Generator Project (CP1114)
Install generation station near Mesa's electric service territory to generate power for the electric utility and offset expensive peak electric market purchases.
West Mesa Electric Utility Improvements (424 W. Main) (CP1205)
Chicanos Por La Causa will be building a brand-new mixed-use property at the corner of Country Club and Main.
Environmental & Sustainability
Electric Vehicle Charging Infrastructure (CP1100)
Install Electric Vehicle Charging Stations Citywide
Falcon Field Airport
Airport Sustainability Energy Plan (CN0105)
Develop an energy audit and sustainability plan to move airport towards a goal of net zero carbon emissions and improve energy supply resilience through 
PV solar microgrid.
Anzio Taxilane and Ramp Reconstruction (CP0993)
Reconstruct taxilane and ramp at Falcon Field Airport.
Citrus Grove Land Conversion (CP1339)
Removal of 149.7 acres of citrus groves on property owned by Falcon Field Airport.  Includes clearing and grubbing, planting of drought tolerant trees 
spacing along all parcel perimeters, roadway shoulder landscaping, drip irrigation and design services.
City of Mesa
Page 9 of 35
Proposed Five Year Capital Improvement Program

COUNCIL DISTRICT 5
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Falcon Field Airport
$1,019,088
$1,017,446
$269,059
$250,312
$377,155
$372,096
$1,251,220
$4,556,376
Total
$1,019,088
$1,017,446
$269,059
$250,312
$377,155
$372,096
$1,251,220
$4,556,376
COUNCIL DISTRICT 5
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Falcon Field Airport
-
$82,693
-
-
-
-
-
$82,693
Total
-
$82,693
-
-
-
-
-
$82,693
COUNCIL DISTRICT 5
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Falcon Field Airport
($80,604)
-
$32,930
$677,929
-
-
-
$630,255
Falcon Field Grants
$4,064,736
-
-
$5,262,309
-
-
-
$9,327,045
Total
$3,984,131
-
$32,930
$5,940,239
-
-
-
$9,957,300
COUNCIL DISTRICT 5
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Falcon Field Airport
$40,130
$300,672
-
-
-
-
-
$340,802
Falcon Field Grants
$83,721
$845,464
-
-
-
-
-
$929,185
Total
$123,850
$1,146,136
-
-
-
-
-
$1,269,986
COUNCIL DISTRICT 5
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Falcon Field Airport
-
$66,724
$7,164
-
-
-
-
$73,888
Total
-
$66,724
$7,164
-
-
-
-
$73,888
COUNCIL DISTRICT 5
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Falcon Field Airport
$16,715
$17,366
-
-
-
-
-
$34,081
Falcon Field Grants
$150,438
$82,634
-
-
-
-
-
$233,072
Total
$167,153
$100,000
-
-
-
-
-
$267,153
COUNCIL DISTRICT 5
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Falcon Field Airport
-
-
-
$711
-
-
-
$711
Falcon Field Grants
-
-
-
$15,197
-
-
-
$15,197
Total
-
-
-
$15,908
-
-
-
$15,908
COUNCIL DISTRICT 5
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Falcon Field Airport
$5,456
$94,158
$408,247
-
-
-
-
$507,861
Falcon Field Grants
$47,523
$850,307
$3,243,494
-
-
-
-
$4,141,324
Total
$52,979
$944,465
$3,651,741
-
-
-
-
$4,649,185
City Owned Buildings and Property Improvements (CP0763)
Construct needed improvements to City-owned buildings and property at Falcon Field.
Conduct Airport Economic Impact Study Update (CN0113)
Update the Airport Economic Impact analysis report last completed using 2018 data as a stand-alone study at the request of the City Manager.
Construct Midfield Taxiway F and Realign Taxiway D3, D4 (CP0994)
Construct midfield Taxiway F and realign taxiways D3 & D4 at Falcon Field Airport
Design and Construct West Airport Perimeter Road and Apron 
(CP1225)
Design and reconstruct for rehabilitation and reconstruction of the West Airport Perimeter Road.  Project will address poor pavement conditions due to 
increased traffic because of new airport development.
Draft a Title VI Plan & Community Participation Plan (CN0106)
Draft a Title VI Plan, Community Participation Plan and internal Standard Operating Procedure to Implement Civil Rights Program at Falcon Field Airport in 
accordance with DOT Order 1000.12C, The Department of Transportation Title VI Program.
Eastside Taxilane Design and Construction (C06020)
Design and construct the taxiway across Roadrunner Drive to provide aircraft access to the land located on the east side of the airport.  This area is currently 
not accessible by aircraft. Improvements include new storm drain lines, and cul-de-sacs.
F.A.R. Part 150 Noise & Land Use Compatibility Study (CN0111)
Complete a FAR Part 150 Community Noise & Land Use Compatibility Study for Falcon Field in accordance with FAA guidelines. This measure is to address 
community requests that the City complete this study and update noise contour mapping in NE Mesa.
Holding Bay Apron (CP1222)
Design & Construct Holding Bay Apron RWY 22L Future Taxilane I
City of Mesa
Page 10 of 35
Proposed Five Year Capital Improvement Program

COUNCIL DISTRICT 5
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Falcon Field Airport
$2,632
$16,234
-
$54,835
$181,757
$313,296
$240,926
$809,681
Falcon Field Grants
$50,529
$153,766
-
-
$1,420,382
$2,291,879
$1,962,714
$5,879,270
Total
$53,161
$170,000
-
$54,835
$1,602,139
$2,605,176
$2,203,640
$6,688,951
COUNCIL DISTRICT 5
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Falcon Field Airport
-
-
-
-
$18,632
$140,934
$1,509,045
$1,668,611
Falcon Field Grants
-
-
-
-
-
$1,281,986
$7,562,353
$8,844,338
Total
-
-
-
-
$18,632
$1,422,920
$9,071,398
$10,512,950
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2022 Public Safety 
Bond
$8,690,445
$356,542
-
-
-
-
-
$9,046,987
2024 Public Safety 
Bond
-
$10,545,242
$7,000,000
$2,900,000
-
-
-
$20,445,242
Capital - General Fund
$1,440,461
$1,279,107
$665,229
$933,219
$748,134
-
-
$5,066,151
Total
$10,130,906
$12,180,891
$7,665,229
$3,833,219
$748,134
-
-
$34,558,379
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
$25,707
$3,900,000
-
-
-
-
-
$3,925,707
Total
$25,707
$3,900,000
-
-
-
-
-
$3,925,707
COUNCIL DISTRICT 2
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2022 Public Safety 
Bond
$1,761,953
$13,800,000
-
-
-
-
-
$15,561,953
Total
$1,761,953
$13,800,000
-
-
-
-
-
$15,561,953
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Public Safety Sales 
Tax Fire Medical
$20,464
$10,500
-
-
-
-
-
$30,964
Total
$20,464
$10,500
-
-
-
-
-
$30,964
COUNCIL DISTRICT 1
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2022 Public Safety 
Bond
$1,885,923
$14,131,411
-
-
-
-
-
$16,017,334
Public Safety Sales 
Tax Fire Medical
$1,422
$668,589
-
-
-
-
-
$670,011
O&M
General Fund
-
$192,164
$196,666
$200,980
$205,378
$210,077
$660,302
$1,665,567
Total
$1,887,345
$14,992,164
$196,666
$200,980
$205,378
$210,077
$660,302
$18,352,913
Reconstruct Three Access Apron Areas (CP1259)
Rehab pavement identified in the worst condition at Falcon Field AIrport based on the 2022 Airport Pavement Maintenance Management Plan as requiring 
reconstruction based on condition. All pavement identified in this project have a PCI score below 47.
Rehabilitate Taxiway Echo (CP1261)
This is a design and construction project for a major rehabilitation of the southern one half of Taxiway E which serves as the parallel access route to Runway 
4L/22R.  This project will be an asphalt mill and overlay project for the taxiway.
Fire
Fire Apparatus (CN0055)
Purchase replacement Fire Apparatus for units that are due for replacement and currently still in service.  These purchases are based off of the Fire 
 
Maintenance apparatus replacement schedule that identifies when replacement is necessary.
Fire Fuel Station Tanks (CP1152)
Convert fuel trailers at fire stations to above ground storage tanks and replace tank at the training facility.
Fire Station 205: Rebuild (C10120)
Rebuild Fire Station 205 to accommodate for current and future Fire and Medical operational needs.
Fire Station 2202 Remodel/Renovation  (CP1062)
 
Remodel and renovation, tenant improvements, at Fire Station 2202  
  
Fire Station 223 (C10124)
Construct a new fire station in Lehi to accommodate for population growth and increased call volumes.
City of Mesa
Page 11 of 35
Proposed Five Year Capital Improvement Program

COUNCIL DISTRICT 6
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2022 Public Safety 
Bond
$7,680,977
$8,000,000
-
-
-
-
-
$15,680,977
O&M
General Fund
-
$197,840
$202,475
$206,916
$211,444
$216,282
$679,806
$1,714,764
Total
$7,680,977
$8,197,840
$202,475
$206,916
$211,444
$216,282
$679,806
$17,395,740
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
$61,627
$104,404
-
-
-
-
-
$166,031
Total
$61,627
$104,404
-
-
-
-
-
$166,031
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2026 Public Safety 
Bond
-
$5,000,000
-
-
-
-
-
$5,000,000
Total
-
$5,000,000
-
-
-
-
-
$5,000,000
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2024 Public Safety 
Bond
-
-
-
-
-
$750,000
$4,007,680
$4,757,680
O&M
Capital - General Fund
-
-
$378,916
-
-
-
-
$378,916
General Fund
-
-
$2,027,700
$1,872,389
$1,966,713
$2,041,256
$6,603,954
$14,512,011
Total
-
-
$2,406,616
$1,872,389
$1,966,713
$2,791,256
$10,611,634
$19,648,607
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
$167,807
$4,700,000
-
-
-
-
-
$4,867,807
Total
$167,807
$4,700,000
-
-
-
-
-
$4,867,807
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Public Safety Sales 
Tax Fire Medical
-
$37,295
-
-
-
-
-
$37,295
Total
-
$37,295
-
-
-
-
-
$37,295
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
$23,687
$6,181,375
-
-
-
-
-
$6,205,062
Restricted Programs 
Fund
$848
$1,881,037
-
-
-
-
-
$1,881,885
Special Programs 
Fund
$4,763
$937,588
-
-
-
-
-
$942,351
Total
$29,298
$9,000,000
-
-
-
-
-
$9,029,298
Fire Station 224 (C10128)
Construct a new fire station at S. 80th St. N. of E. Elliot Rd.
Fire Station Exhaust System (CP1051)
Retro-fit up to 16 fire stations with a direct-source vehicle exhaust capture system - FEMA grant.
Fire Stations: Land Acquisition for New Stations (CP0103)
Acquire land for future fire stations.  The Fire department has identified the need for 3 stations, sites to be determined.
Mesa Fire and Medical Department Response Facilities (CP1241)
Land Acquisition, Design, and Construction/Purchase of future medical response facilities.
Mesa Fire and Medical Restrooms Remodel (CP1232)
Modifying multiple Fire Facilities restrooms. Many station's restroom facilities are outdated and undersized for staff needs.
MFMD New Apparatus (CN0083)
Purchase new apparatus for MFMD
Hohokam Stadium / Fitch Park
Hohokam and Fitch Improvements (CP1292)
Multiple projects at Hohokam and Fitch including lighting, scoreboard replacement & fraise mowing
City of Mesa
Page 12 of 35
Proposed Five Year Capital Improvement Program

CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Local Streets Fund
-
$650,000
-
-
-
-
-
$650,000
O&M
Local Streets Fund
-
-
$40,937
$41,835
$42,751
$43,729
$137,446
$306,697
Total
-
$650,000
$40,937
$41,835
$42,751
$43,729
$137,446
$956,697
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Local Streets Fund
$99,019
$2,050,000
-
-
-
-
-
$2,149,019
Total
$99,019
$2,050,000
-
-
-
-
-
$2,149,019
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Local Streets Fund
$23,767
$196,711
-
-
-
-
-
$220,478
Special Programs 
Fund
$444,032
$283,289
-
-
-
-
-
$727,321
Total
$467,800
$480,000
-
-
-
-
-
$947,800
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Local Streets Fund
$1,037
$3,180,000
-
-
-
-
-
$3,181,037
Total
$1,037
$3,180,000
-
-
-
-
-
$3,181,037
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Local Streets Fund
$2,038,739
$1,999,520
$1,534,654
$1,568,314
$1,602,632
$1,639,302
$5,152,558
$15,535,718
Total
$2,038,739
$1,999,520
$1,534,654
$1,568,314
$1,602,632
$1,639,302
$5,152,558
$15,535,718
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Local Streets Fund
$44,084
$2,095,238
-
-
-
-
-
$2,139,322
O&M
Local Streets Fund
-
-
$97,469
$99,607
$101,787
$104,116
$327,251
$730,230
Total
$44,084
$2,095,238
$97,469
$99,607
$101,787
$104,116
$327,251
$2,869,552
COUNCIL DISTRICT 3
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
$60,004
$1,720,000
-
$209,176
$603,851
-
-
$2,593,031
Total
$60,004
$1,720,000
-
$209,176
$603,851
-
-
$2,593,031
COUNCIL DISTRICT 6
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2018 Library Bond
$14,874,160
$68,540
-
-
-
-
-
$14,942,700
Capital - General Fund
-
$1,688,803
-
-
-
-
-
$1,688,803
Total
$14,874,160
$1,757,343
-
-
-
-
-
$16,631,503
Intelligent Transportation System
Central Traffic Signal System (CP0655)
Replace central traffic signal system for the City's Traffic Management Center.
ITS Field Network Upgrade (CP0980)
Upgrade existing field infrastructure to increase band-width and support emerging technologies
Ped Beacon on Dbsn/Brdwy, Sgnl at Mesa Dr/Cnsld Cnl (CP1110)
Install a new pedestrian beacon on Dobson Rd apprx 1250 S of Broadway and replace Rapid Flash Beacon on Mesa Dr and Consolidated Canal with a 
traffic Signal.
Traffic Management Center Upgrade (CP1278)
This project will replace end-of-life Traffic Management Center (TMC) equipment and redesign the TMC workspace to retain functionality and increase 
workspace efficiency.
Traffic Signals - New and Upgrade (CP1067)
Install new signals and upgrade existing signals.
Traffic Signals - Public Safety Opticom (CP0702)
Upgrade the existing optical-based emergency vehicle preemption system with a new, modernized city-wide solution for all intersections.
Library
Dobson Ranch Library Study and Updates (CP1158)
Conduct feasibility study, renovate bathroom, renovate office space and structural updates.
Gateway Library (CP0428)
Provide library services to the citizens of Southeast Mesa, name changed from Southeast Library to Gateway Library.
City of Mesa
Page 13 of 35
Proposed Five Year Capital Improvement Program

COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
$1,583
$110,000
-
-
-
-
-
$111,583
Total
$1,583
$110,000
-
-
-
-
-
$111,583
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
$65,685
$80,000
-
-
-
-
-
$145,685
Total
$65,685
$80,000
-
-
-
-
-
$145,685
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
$1,320
$180,000
-
-
-
-
-
$181,320
O&M
General Fund
-
$5,000
$5,117
$5,229
$5,344
$5,466
$17,181
$43,337
Total
$1,320
$185,000
$5,117
$5,229
$5,344
$5,466
$17,181
$224,657
COUNCIL DISTRICT 5
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
-
$500,000
-
-
-
-
-
$500,000
O&M
General Fund
-
$562,000
$15,351
$15,688
$16,031
$16,398
$51,542
$677,011
Total
-
$1,062,000
$15,351
$15,688
$16,031
$16,398
$51,542
$1,177,011
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
-
-
$235,389
-
-
-
-
$235,389
O&M
General Fund
-
-
$46,054
-
-
-
-
$46,054
Total
-
-
$281,443
-
-
-
-
$281,443
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
-
$294,500
-
-
-
-
-
$294,500
O&M
General Fund
-
-
$46,054
-
-
-
-
$46,054
Total
-
$294,500
$46,054
-
-
-
-
$340,554
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Arts & Culture Fund
$191
$1,908,121
-
-
-
-
-
$1,908,312
Total
$191
$1,908,121
-
-
-
-
-
$1,908,312
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Arts & Culture Fund
-
$910,000
-
-
-
-
-
$910,000
Total
-
$910,000
-
-
-
-
-
$910,000
Redevelop the Mesa Arts Center Arroyo
Mesa Arts Center Box Office Remodel (CP1335)
Renovate and relocate the Mesa Arts Center Box Office from the North Studio building to the vacant building formerly called The Store.
Red Mountain Children's Room Renovation (CP1170)
Renovation/remodel of the Children's Room at Red Mountain Branch Library.
Red Mountain Library Program Room Renovation (CP1302)
The Program Room at Red Mountain Library is outdated and no longer meets community needs. Planned upgrades will add modern finishes, new tech, and 
natural light, creating a bright, functional hub for events and gatherings.
Saguaro Room Renovation (CP1301)
The Saguaro Room at the Main Library, seating 100+, is outdated. Renovations will modernize finishes, add tech, and bring in natural light, creating a 
welcoming, functional community space.
Mesa Arts Center
MAC Arroyo Redevelopment (CP1356)
Main Branch Signage (CP1273)
This project is to add new MPL signage onto the Main branch building ahead of the new paint work that is planned for 2025. This signage would be installed 
on the Southwest corner of the branch building. Both signs would face the parking lot (south). 
Main Library North Lawn Redevelopment (CP1197)
Design and construction of a redeveloped north lawn at the downtown Main library, activating the space in between the Library and convention center.  
MPL Book Locker Expansion (CP1272)
Add book lockers in parks throughout the City of Mesa.
City of Mesa
Page 14 of 35
Proposed Five Year Capital Improvement Program

COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Arts & Culture Fund
-
$100,000
-
-
-
-
-
$100,000
Total
-
$100,000
-
-
-
-
-
$100,000
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Mesa Arts Center 
Restoration Fee
$144,548
$278,727
-
-
-
-
-
$423,275
Quality of Life Sales 
Tax
$1,245
$6,106,273
-
-
-
-
-
$6,107,518
Total
$145,793
$6,385,000
-
-
-
-
-
$6,530,793
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2018 Parks Bond
$1,442
$391,670
-
-
-
-
-
$393,112
2024 Parks Bond
$4,002
$8,490,289
$9,000,000
$3,400,000
-
-
-
$20,894,291
Capital - General Fund
-
$1,178,983
-
-
-
-
-
$1,178,983
Grants - Gen. Gov.
-
$594,058
-
-
-
-
-
$594,058
O&M
Arts & Culture Fund
-
-
-
$443,025
$461,171
$480,526
$1,561,586
$2,946,309
General Fund
-
-
-
$33,472
$34,205
$34,987
$109,970
$212,634
Total
$5,444
$10,655,000
$9,000,000
$3,876,498
$495,376
$515,513
$1,671,556
$26,219,387
MAGMA
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Gas Utility Revenue 
Pledge
$589,735
$10,000,000
$4,605,434
-
-
-
-
$15,195,170
Total
$589,735
$10,000,000
$4,605,434
-
-
-
-
$15,195,170
MAGMA
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Gas Utility Revenue 
Pledge
$524,524
$1,300,000
-
-
-
-
-
$1,824,524
Total
$524,524
$1,300,000
-
-
-
-
-
$1,824,524
MAGMA
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Gas Utility Revenue 
Pledge
$9,428,159
$11,000,000
-
-
-
-
-
$20,428,159
Total
$9,428,159
$11,000,000
-
-
-
-
-
$20,428,159
MAGMA
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Gas Utility Revenue 
Pledge
$2,470,695
$800,000
$818,744
$836,702
$855,011
$874,574
$2,748,911
$9,404,636
Total
$2,470,695
$800,000
$818,744
$836,702
$855,011
$874,574
$2,748,911
$9,404,636
Gas Aging Infrastructure Replacement (CP1073)
Replace necessary gas system infrastructure identified during the annual survey.
This project will be to support the next phases of renovation at the idea Museum within the Department of Arts and Culture.
Natural Gas Growth
Arizona Farms Road High Pressure Main & Gate Station (CP0517)
Replace aging high pressure steel main along Arizona Farms Road to increase the effective capacity of the Clausen gate station in the Magma service area.  
 
This will allow Clausen gate station to be a more effective supply point. 
Clausen Gate Station Improvements (CP1244)
Reconstruct and expand City of Mesa's Clausen Gate Station for additional gas capacity to serve the growing Magma gas system and future large industrial 
customers.
Gantzel Road Projects (CP0519)
Increase the ability of the existing Gantzel Gate Station to feed the northern half of the Magma System.  This second phase of the project will increase the 
 
flow capacity of the high pressure system north on Gantzel to Ocotillo Rd.
Mesa Arts Center Campus Signage Restoration (CP1336)
Mesa Arts Center will be restoring, replacing, and/or upgrading existing signage kiosks and exterior wayfinding signage.
Mesa Arts Center Lighting Control System Replacement (CP1191)
This project will support replacement of Mesa Arts Center's Lighting control system.  The lighting control system supports all four theaters, the Mesa 
Contemporary Arts Museum, and the exterior campus lighting.  
Museum
idea Museum - Renovation Phase 2 (CP1219)
City of Mesa
Page 15 of 35
Proposed Five Year Capital Improvement Program

CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Gas Utility Revenue 
Pledge
$2,014,398
$1,500,000
$1,023,430
$1,045,878
$1,068,763
$1,093,218
$3,436,138
$11,181,825
Total
$2,014,398
$1,500,000
$1,023,430
$1,045,878
$1,068,763
$1,093,218
$3,436,138
$11,181,825
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Natural Gas
$1,079,219
$1,600,000
$614,058
$627,527
$641,258
$655,931
$2,061,683
$7,279,675
Total
$1,079,219
$1,600,000
$614,058
$627,527
$641,258
$655,931
$2,061,683
$7,279,675
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Gas Utility Revenue 
Pledge
$1,026,273
$500,000
$511,715
$522,939
$534,382
$546,609
$1,718,069
$5,359,986
Total
$1,026,273
$500,000
$511,715
$522,939
$534,382
$546,609
$1,718,069
$5,359,986
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Gas Utility Revenue 
Pledge
$6,625,632
$3,100,000
$3,172,633
$3,242,221
$3,313,166
$3,388,974
$10,652,029
$33,494,654
Total
$6,625,632
$3,100,000
$3,172,633
$3,242,221
$3,313,166
$3,388,974
$10,652,029
$33,494,654
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Gas Utility Revenue 
Pledge
$5,532,551
$2,500,000
$2,558,575
$2,614,694
$2,671,908
$2,733,044
$8,590,346
$27,201,117
Total
$5,532,551
$2,500,000
$2,558,575
$2,614,694
$2,671,908
$2,733,044
$8,590,346
$27,201,117
MAGMA
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Gas Utility Revenue 
Pledge
-
$100,000
-
-
-
-
-
$100,000
Total
-
$100,000
-
-
-
-
-
$100,000
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Gas Utility Revenue 
Pledge
$42,430
$900,000
$716,401
$732,114
$748,134
$765,252
$2,405,297
$6,309,629
Total
$42,430
$900,000
$716,401
$732,114
$748,134
$765,252
$2,405,297
$6,309,629
COUNCIL DISTRICT 6
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Gas Utility Revenue 
Pledge
-
$300,000
-
-
-
-
-
$300,000
Total
-
$300,000
-
-
-
-
-
$300,000
Transwestern Gate Station (CP1350)
Construct an interconnect with Transwestern Pipelines new 516-mile expansion from Texas to Arizona to support future growth of the Magma gas system 
while enhancing system redundancy and overall reliability.
Gas New Mains (CP1071)
Extend gas mains and services to new subdivisions.
Gas New Services (CP1070)
Install gas lines in new subdivision developments throughout the City and Magma Service Area.
Hawes Crossing Gas Extension (Mesquite to Warner) (CP1349)
To support new gas growth @ Warner & Hawes for Hawes Crossing Village 4, 5, 6. (6-inch PE Gas Extension)
High Pressure Gas Main Installation (CP1069)
Install high pressure gas main to meet anticipated growth of the City.
Gas Construction - POM (CP1255)
Install new gas mains, services, and meters to new subdivisions in Mesa or Magma.
Gas-Customer Upgrades (CP0890)
Upgrade meters and or services per customer requests
Gas Meters: New and Replacement (CP1074)
Install gas meters citywide.
City of Mesa
Page 16 of 35
Proposed Five Year Capital Improvement Program

CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Natural Gas
$321,599
$223,451
$122,812
$125,505
$128,252
$131,186
$412,337
$1,465,141
Total
$321,599
$223,451
$122,812
$125,505
$128,252
$131,186
$412,337
$1,465,141
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Utility Replacement 
Extension and 
Renewal - GAS
$42,072
$500,000
$511,715
$522,939
$534,382
$546,609
$1,718,069
$4,375,785
Total
$42,072
$500,000
$511,715
$522,939
$534,382
$546,609
$1,718,069
$4,375,785
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Gas Utility Revenue 
Pledge
$3,077,583
-
-
-
$7,279,086
$4,698,270
$856,018
$15,910,958
Total
$3,077,583
-
-
-
$7,279,086
$4,698,270
$856,018
$15,910,958
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Gas Utility Revenue 
Pledge
$9,371
$10,000
$10,234
$10,459
$10,688
$10,932
$34,361
$96,045
Total
$9,371
$10,000
$10,234
$10,459
$10,688
$10,932
$34,361
$96,045
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
-
$29,297
-
-
-
-
-
$29,297
Community 
Development Block 
Grant
-
$340,703
-
-
-
-
-
$340,703
O&M
General Fund
-
$19,425
$19,880
$20,316
$20,761
$21,236
$66,747
$168,365
Total
-
$389,425
$19,880
$20,316
$20,761
$21,236
$66,747
$538,365
COUNCIL DISTRICT 6
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2024 Parks Bond
$42,177
$745,000
-
-
-
-
-
$787,177
Total
$42,177
$745,000
-
-
-
-
-
$787,177
COUNCIL DISTRICT 2
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2018 Parks Bond
$17,149
$498,333
-
-
-
-
-
$515,482
Capital - General Fund
$7,934
$1,667
-
-
-
-
-
$9,601
Total
$25,083
$500,000
-
-
-
-
-
$525,083
Construct a new 1.5 acre dog park expansion at the existing Countryside Dog Park.
 
Assess, design and construct to replace aging gas lines throughout the city.
Regulator Station Security (C10388)
Install on-site security systems to monitor and deter theft and sabotage of regulator station equipment.
Parks & Recreation
Aripine Park Playground Renovation (CP1182)
CP Project for New play equipment install.
Brady Park Dog Park Renovation (CP1304)
Renovate dog park and Brady Park (formerly Monterey Park)
Dog Park - Countryside Park (CP0933)
Natural Gas Replacements
Gas Line Retirements (CP0563)
Remove gas mains and services that are no longer needed to support the natural gas system
Gas Meters: New and Replacement-RER Funded (CP0496)
Install gas meters citywide.
Gas Quarter Sections (CP1112)
City of Mesa
Page 17 of 35
Proposed Five Year Capital Improvement Program

COUNCIL DISTRICT 2
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2024 Parks Bond
$5,055
$4,995,013
$17,000,000
$20,000,000
$10,000,000
-
-
$52,000,068
O&M
Capital - General Fund
-
-
-
-
-
$2,600,193
-
$2,600,193
General Fund
-
-
-
-
-
$2,679,875
$8,691,669
$11,371,544
Total
$5,055
$4,995,013
$17,000,000
$20,000,000
$10,000,000
$5,280,068
$8,691,669
$65,971,805
COUNCIL DISTRICT 5
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2024 Parks Bond
$1,787
$2,370,000
$2,000,000
$500,000
-
-
-
$4,871,787
O&M
Capital - General Fund
-
-
$43,496
$300,825
-
-
-
$344,321
General Fund
-
$153,875
$220,888
$647,368
$683,362
$708,509
$2,290,491
$4,704,492
Total
$1,787
$2,523,875
$2,264,384
$1,448,193
$683,362
$708,509
$2,290,491
$9,920,600
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2024 Parks Bond
$213,647
$5,500,000
-
-
-
-
-
$5,713,647
Total
$213,647
$5,500,000
-
-
-
-
-
$5,713,647
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2024 Parks Bond
-
$4,150,000
$850,000
-
-
-
-
$5,000,000
O&M
Capital - General Fund
-
-
$309,171
$43,579
-
-
-
$352,750
General Fund
-
$61,416
$626,203
$704,092
$729,618
$756,951
$2,450,153
$5,328,433
Total
-
$4,211,416
$1,785,374
$747,671
$729,618
$756,951
$2,450,153
$10,681,183
COUNCIL DISTRICT 5
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2018 Parks Bond
$14,990,696
$120,117
-
-
-
-
-
$15,110,813
Total
$14,990,696
$120,117
-
-
-
-
-
$15,110,813
COUNCIL DISTRICT 6
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2018 Parks Bond
$1,932,950
$5,500,000
-
-
-
-
-
$7,432,950
Total
$1,932,950
$5,500,000
-
-
-
-
-
$7,432,950
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2024 Parks Bond
$62,321
$2,080,000
$2,000,000
-
-
-
-
$4,142,321
Total
$62,321
$2,080,000
$2,000,000
-
-
-
-
$4,142,321
COUNCIL DISTRICT 3
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Cubs Spring Training 
Facility
-
$44,698
-
-
-
-
-
$44,698
Total
-
$44,698
-
-
-
-
-
$44,698
Construct pickleball courts at City parks
Red Mountain Park Community Athletic Fields (CP0932)
Construct 9 lighted soccer fields, lighted parking, pond expansion and restrooms adjacent to Red Mountain Park.
Signal Butte Park Phase 2 (CP0707)
Construct additional park space on land surrounding the water treatment at Elliot Road and Signal Butte.
Sirrine House Remodel (CP1171)
Remodel Sirrine House-includes structural repairs
Sloan Park Facility Improvements (CP0723)
Improve or upgrade Sloan Park and/or the Under Armor Performance Training Center for monument and directional signage around the site.
Indoor Recreation Center (CP1208)
Construct a new community center on 8 acres of land located in central Mesa. Amenities provided and size to mirror what is provided at the Red Mountain 
Center. The Center is to include an area for parking.
Northeast Mesa Regional Trails (CP1210)
Develop the 174 acre BLM Property to a trailhead. The park will maintain its entry from McKellips and will contain the following elements: a parking lot; small 
restroom; benches, picnic tables, and some trail improvements.
Park Renovations (CP1175)
Renovate playgrounds at City parks
Pickleball Courts (CP1212)
City of Mesa
Page 18 of 35
Proposed Five Year Capital Improvement Program

CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2024 Parks Bond
$80,874
$1,925,000
$875,000
$1,125,000
$1,050,000
$375,000
-
$5,430,874
O&M
Capital - General Fund
-
-
-
-
$152,526
-
-
$152,526
General Fund
-
-
-
-
$116,722
$122,095
$401,848
$640,665
Total
$80,874
$1,925,000
$875,000
$1,125,000
$1,319,248
$497,095
$401,848
$6,224,065
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2026 Public Safety 
Bond
-
-
-
$2,775,520
$12,938,640
$12,938,640
-
$28,652,800
Total
-
-
-
$2,775,520
$12,938,640
$12,938,640
-
$28,652,800
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
$490
$129,000
-
-
-
-
-
$129,490
Total
$490
$129,000
-
-
-
-
-
$129,490
COUNCIL DISTRICT 5
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
$436
$1,900,000
-
-
-
-
-
$1,900,436
Total
$436
$1,900,000
-
-
-
-
-
$1,900,436
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2022 Public Safety 
Bond
$7,695,416
$41,500,000
-
-
-
-
-
$49,195,416
Public Safety Sales 
Tax Police
-
$10,300,000
-
-
-
-
-
$10,300,000
O&M
General Fund
-
-
$213,204
$217,880
$222,648
$227,742
$715,827
$1,597,301
Total
$7,695,416
$51,800,000
$213,204
$217,880
$222,648
$227,742
$715,827
$61,092,717
COUNCIL DISTRICT 1
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2022 Public Safety 
Bond
$353,769
$2,798,237
$25,333,638
$3,687,273
-
-
-
$32,172,917
2026 Public Safety 
Bond
-
$1,939,600
$7,413,900
$29,775,205
$22,361,305
-
-
$61,490,010
Capital - General Fund
$6,387
$51,763
-
-
-
-
-
$58,150
O&M
General Fund
-
-
-
$823,629
$40,079
$40,996
$128,855
$1,033,558
Total
$360,156
$4,789,600
$32,747,538
$34,286,107
$22,401,384
$40,996
$128,855
$94,754,635
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
$4,591
$7,294
-
-
-
-
-
$11,885
Total
$4,591
$7,294
-
-
-
-
-
$11,885
Provide shade for vehicles at the Northeast Public Safety Facility.
Police Headquarters (CP0204)
Renovate the Police Department Headquarters to meet operational needs.
Public Safety Training Facility Building Improvements (CP0098)
Renovate and expand public safety training facility including new office space and training classrooms.
RTCC Flock DJI3 Deployment (CP1303)
Add power to the roof of 708 W Baseline, Building 1 for drone equipment.  In addition, ensure stability for the weight of the equipment.
Water Conservation (CP1214)
Reconfigure irrigation, upgrade agricultural, install advanced meters to implement sustainable water practices, and remove non-functional turf.
Police
Central Station Renovation (CP0540)
Refurbish the Central substation to create new work areas and update existing flooring as well as renovate the current pump room.
MFAC Miscellaneous Improvements (CP1288)
Miscellaneous improvements/repairs throughout MFAC.
Northeast Public Safety Facility Covered Parking (CP1284)
City of Mesa
Page 19 of 35
Proposed Five Year Capital Improvement Program

COUNCIL DISTRICT 1
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2024 Public Safety 
Bond
$278,190
$9,400,000
$29,500,000
$15,000,000
-
-
-
$54,178,190
O&M
Capital - General Fund
-
-
-
-
$228,993
-
-
$228,993
General Fund
-
-
-
-
$883,626
$923,758
$2,948,625
$4,756,009
Total
$278,190
$9,400,000
$29,500,000
$15,000,000
$1,112,619
$923,758
$2,948,625
$59,163,192
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Transportation
-
$3,000,000
$3,070,290
$3,137,633
-
-
-
$9,207,922
Total
-
$3,000,000
$3,070,290
$3,137,633
-
-
-
$9,207,922
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2026 Street Bond
-
-
-
$878,459
$11,172,358
-
-
$12,050,817
Total
-
-
-
$878,459
$11,172,358
-
-
$12,050,817
COUNCIL DISTRICT 2
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Transportation
$155,222
$4,000,000
-
-
-
-
-
$4,155,222
Total
$155,222
$4,000,000
-
-
-
-
-
$4,155,222
COUNCIL DISTRICT 2
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Transportation
$77,061
$3,650,000
-
-
-
-
-
$3,727,061
Total
$77,061
$3,650,000
-
-
-
-
-
$3,727,061
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2018 Parks Bond
$1,464,308
$91,646
-
-
-
-
-
$1,555,954
Highway User 
Revenue Fund
-
$88,354
-
-
-
-
-
$88,354
Total
$1,464,308
$180,000
-
-
-
-
-
$1,644,308
COUNCIL DISTRICT 5
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Grants - Gen. Gov.
-
$300,000
-
-
-
-
-
$300,000
Total
-
$300,000
-
-
-
-
-
$300,000
Eastern Canal Shared-Use Path: Brown to Broadway (CP1060)
Construct Shared Use Asphalt path to resolve a missing link in the regional non-motorized system.
Eastern Canal Shared-Use Path: Brown to Broadway-Signals 
(CP0673)
Construct signalized crossings on Eastern Canal and street intersections to improve the function of the non-motorized system.
L202 Red Mountain Shared-Use Path - Val Vista to Thomas Rd 
(CP0674)
Design concept review for a new shared-use path along the South Canal, from Val Vista Dr to Thomas Rd, closing the gap between the existing Lehi Phase 
1 and Red Mountain shared-use paths.
Mesa Public Safety Communications (MPSC) (CP1239)
Build new state-of-the-art 911 public safety communications center, complete with the required infrastructure, floor space, technology, and environmental 
features to provide a reliable, efficient, safe and secure 911 call center.
Shared Use Paths
Active Transportation (CP1313)
Annual program that identifies, designs and constructs new active transportation projects, focusing on closing critical gaps in the regional network.
Downtown Multimodal Pathway, Zone 3 & 4 (CP1353)
This project installs landscaping, tech-integrated shade canopies, and lighting to enhance the pedestrian experience. It bridges the Downtown Convention 
Center and the Mesa Arts Center, drawing visitors directly into the downtown corridor.
Eastern Canal Shared-Use Path Broadway to Baseline (CP0730)
Construct shared-use asphalt path to resolve a missing link in the regional non-motorized system
Public Safety Support
City of Mesa
Page 20 of 35
Proposed Five Year Capital Improvement Program

COUNCIL DISTRICT 5
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Grants - Gen. Gov.
$2,827,689
$563,836
-
-
-
-
-
$3,391,525
Transportation
$995,717
$36,164
-
-
-
-
-
$1,031,881
O&M
General Fund
-
$56,400
$57,721
$58,987
$60,278
$61,657
$193,798
$488,843
Total
$3,823,406
$656,400
$57,721
$58,987
$60,278
$61,657
$193,798
$4,912,249
COUNCIL DISTRICT 1
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2026 Street Bond
-
-
-
-
$803,920
$12,120,944
-
$12,924,864
Total
-
-
-
-
$803,920
$12,120,944
-
$12,924,864
COUNCIL DISTRICT 1
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2020 Street Bond
$584,451
$1,809,415
-
-
-
-
-
$2,393,866
Transportation
-
$196,354
-
-
-
-
-
$196,354
Total
$584,451
$2,005,769
-
-
-
-
-
$2,590,220
COUNCIL DISTRICT 6
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2026 Street Bond
-
-
$1,049,360
$10,706,280
-
-
-
$11,755,640
Total
-
-
$1,049,360
$10,706,280
-
-
-
$11,755,640
COUNCIL DISTRICT 1
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Grants - Gen. Gov.
-
$150,000
-
-
-
-
-
$150,000
Total
-
$150,000
-
-
-
-
-
$150,000
COUNCIL DISTRICT 2
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2026 Street Bond
-
$522,080
$12,471,640
-
-
-
-
$12,993,720
Transportation
$144,330
$400,000
-
-
-
-
-
$544,330
Total
$144,330
$922,080
$12,471,640
-
-
-
-
$13,538,050
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Solid Waste
-
$386,629
-
-
-
-
-
$386,629
Total
-
$386,629
-
-
-
-
-
$386,629
COUNCIL DISTRICT 3
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Solid Waste
$2,511,634
$1,380,086
-
-
-
-
-
$3,891,720
Total
$2,511,634
$1,380,086
-
-
-
-
-
$3,891,720
Design & construct 1.6 miles of shared use path on the south side of the US60. This includes 2 enhanced pedestrian crossings.
Solid Waste
Downtown Trash Compactor (CP1224)
Install trash compactor in downtown area. This will be as a result of a study that is going on right now (OT0185TRSH).
Food to Energy Project (CP0870)
Use inhouse resources and consultants to conduct a study to evaluate the technical and financial feasibility of an anaerobic digestion food waste to energy 
program and determine whether to move forward with a pilot scale program.
Lehi Crossing Pathway Phase II (CP0990)
Design and construct approx. 2.5 miles of shared-use path from McDowell to Val Vista bordering the Red Mountain Freeway and connecting to Lehi Phase I 
at both ends.
Lehi Loop Tunnel Wall (CP1194)
To construct a box culvert extension (Tunnel) and retaining walls as related to the Lehi Loop Phase 1 project.
Mesa Gateway Phase 3 Pathway (CP1178)
Design and construct 2 miles of shared-use path from Hawes Rd, where it ties into Phase 2, to Power Rd and tie into Gilbert's path system. This includes a 
bridge over the RWCD canal and resolves a missing link in the regional non-motorized system.
South Canal from McKellips to McDowell (CP1320)
Design concept review for the South Canal, from McKellips to McDowell for a shared-use path along the South Canal
US60 Shared Use Path-Eastern to Consolidated Canal (CP1180)
L202 Red Mountain SUP-Power Rd past Thomas Rd (CP0733)
Design and construct 1.5 miles of shared-use path to resolve a missing link in the regional non-motorized system.
City of Mesa
Page 21 of 35
Proposed Five Year Capital Improvement Program

COUNCIL DISTRICT 6
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital - General Fund
$556,568
$1,972,657
-
-
-
-
-
$2,529,225
Total
$556,568
$1,972,657
-
-
-
-
-
$2,529,225
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Solid Waste
$284,570
$220,000
-
-
-
-
-
$504,570
Total
$284,570
$220,000
-
-
-
-
-
$504,570
COUNCIL DISTRICT 5
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Highway User 
Revenue Fund
$683,696
$19,281
-
-
-
-
-
$702,977
Local Streets Fund
$93,077
$1,058,477
-
-
-
-
-
$1,151,554
Transportation
$494,931
$102,242
-
-
-
-
-
$597,173
Total
$1,271,704
$1,180,000
-
-
-
-
-
$2,451,704
COUNCIL DISTRICT 2
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Environmental 
Compliance Fee
$8,047
$60,000
-
-
-
-
-
$68,047
Total
$8,047
$60,000
-
-
-
-
-
$68,047
COUNCIL DISTRICT 3
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Highway User 
Revenue Fund
$29
$787,849
-
-
-
-
-
$787,878
Total
$29
$787,849
-
-
-
-
-
$787,878
COUNCIL DISTRICT 6
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Local Streets Fund
$502,931
$475,000
-
-
-
-
-
$977,931
Total
$502,931
$475,000
-
-
-
-
-
$977,931
COUNCIL DISTRICT 2
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Local Streets Fund
$82,224
$3,204,200
-
-
-
-
-
$3,286,424
Transit Fund
$1,900
$28,494
-
-
-
-
-
$30,394
Total
$84,124
$3,232,694
-
-
-
-
-
$3,316,818
COUNCIL DISTRICT 5
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Environmental 
Compliance Fee
$829
$370,000
-
-
-
-
-
$370,829
Total
$829
$370,000
-
-
-
-
-
$370,829
Main and Phyllis Storm Drain Improvements (CP1250)
Strom Drain improvements at Main and Phyllis.  Reimbursement from Maricopa County Flood Control District.
Pecos Road Basin and Storm Drain Drainage (CP1230)
In coordination with the Flood Control District of Maricopa County (FCDMC), the City of Mesa Engineering Department will select a consultant for studying 
the drainage and proposed system in Pecos Road
Recker Road Storm Channel Improvements (CP1266)
Restore the channel's functionality and enhance transportation infrastructure including new sidewalks, roadway improvements, curb and gutter installations, 
and upgraded transit stops.
Southern and Hawes Drainage Improvement (CP1282)
Right of way roadside repair to improve drainage at Fountain of the Sun subdivision's Southern Ave. property wall, whose residents are at risk of flooding. 
Landscaping debris are clogging the grates, blocking grates from working effectively.
West Mesa Service Center CNG Station Upgrades (CP1061)
Upgrade CNG Station at WMSC
Storm Sewer
Baseline and Signal Butte Drainage (CP1099)
Construct storm drainage improvements to prevent neighborhood flooding.
Candlelight Park Drainage-Drywell (CP1294)
Installation of Maxwell Drywell System to address standing water concern at Candlelight Park.
Joint MRF & Transfer Station (CP1146)
Construction of a Materials Recovery Facility and Transfer Station in Southeast Mesa.
City of Mesa
Page 22 of 35
Proposed Five Year Capital Improvement Program

CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Environmental 
Compliance Fee
$45,472
$692,666
-
-
-
-
-
$738,138
Local Streets Fund
$887,946
$2,500,000
$1,535,145
$1,568,816
$1,603,145
$1,639,826
$5,154,207
$14,889,086
Total
$933,418
$3,192,666
$1,535,145
$1,568,816
$1,603,145
$1,639,826
$5,154,207
$15,627,224
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Special Programs 
Fund
$10,599
$300,000
-
-
-
-
-
$310,599
Total
$10,599
$300,000
-
-
-
-
-
$310,599
COUNCIL DISTRICT 5
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Local Streets Fund
$13,572
$200,000
-
-
-
-
-
$213,572
Total
$13,572
$200,000
-
-
-
-
-
$213,572
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2026 Street Bond
-
$446,784
$7,704,320
-
-
-
-
$8,151,104
Total
-
$446,784
$7,704,320
-
-
-
-
$8,151,104
COUNCIL DISTRICT 6
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Local Streets Fund
-
$5,023,810
$4,605,434
-
-
-
-
$9,629,244
Total
-
$5,023,810
$4,605,434
-
-
-
-
$9,629,244
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Transportation
-
-
$2,599,532
-
-
-
-
$2,599,532
Total
-
-
$2,599,532
-
-
-
-
$2,599,532
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Local Streets Fund
$499,177
$804,328
$311,458
$318,290
$325,255
$332,697
$1,045,713
$3,636,917
Total
$499,177
$804,328
$311,458
$318,290
$325,255
$332,697
$1,045,713
$3,636,917
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2026 Street Bond
-
-
$10,632,720
-
-
-
-
$10,632,720
Gas Utility Revenue 
Pledge
$71,771
$2,844,451
$727,774
-
-
-
-
$3,643,997
Total
$71,771
$2,844,451
$11,360,494
-
-
-
-
$14,276,717
ASU Polytechnic Research Park (CP1117)
Roadway improvements at ASU Polytechnic Research Park.
Baseline Rd-Greenfield to Power (Gilbert for ST0780) (CP1096)
City will be partnering with Gilbert for the construction of the joint ALCP project Baseline Road - Greenfield to Power Rds
Bridge Safety Rehabilitation (CP0780)
Address maintenance items and rehabilitation work needing to be performed on numerous existing bridges through the City as identified during bridge 
inspections performed by ADOT.
Broadway Rd from Stapley to Gilbert-Phase 2 (CP1090)
Reconstruct Broadway Rd from Stapley to Gilbert Rd.  Includes utilities.
Storm Drain Pump Stations (CP0491)
Rehabilitate aging storm drain pump stations.
Streets
2nd Street & Beverly Crosswalk (CP1300)
Adding crosswalk striping and expanding curbs to enhance safety on 2nd Street & Beverly.
ADOT Block Wall at Hopi Ave & 76th Place (CP1295)
Installation of block wall and heavy-duty gate to replace existing chain link fence that is being cut by trespassers.
AR - Broadway: Spur to Gilbert (CP1324)
Reconstruct arterial street segments that are at the end of their life cycle and can no longer be maintained by conventional means.  Concurrent work will 
include upgrades to any concrete ramps, driveways and sidewalks to current ADA standards.
City of Mesa
Page 23 of 35
Proposed Five Year Capital Improvement Program

COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2020 Street Bond
$1,353,473
$26,757,132
-
-
-
-
-
$28,110,605
Electric Utility 
Revenue Pledge
$671,323
$14,300,082
$1,042,236
-
-
-
-
$16,013,641
Gas Utility Revenue 
Pledge
$829,269
$3,321,559
$377,709
-
-
-
-
$4,528,537
Water Utility Revenue 
Pledge
$1,819,586
$13,155,546
$1,406,287
-
-
-
-
$16,381,419
Total
$4,673,651
$57,534,319
$2,826,232
-
-
-
-
$65,034,202
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2024 Public Safety 
Bond
$6,695
$690,000
-
-
-
-
-
$696,695
Total
$6,695
$690,000
-
-
-
-
-
$696,695
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Grants - Gen. Gov.
$691,490
$3,500
-
-
-
-
-
$694,990
Local Streets Fund
$200,717
$14,000
-
-
-
-
-
$214,717
Total
$892,207
$17,500
-
-
-
-
-
$909,707
COUNCIL DISTRICT 6
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Grants - Gen. Gov.
-
$427,660
$3,633,156
-
-
-
-
$4,060,816
Local Streets Fund
$12,783
$282,640
$1,557,067
-
-
-
-
$1,852,490
O&M
Environmental 
Compliance Fee
-
-
-
$732
$748
$765
$2,405
$4,651
Local Streets Fund
-
-
-
$14,538
$14,856
$15,196
$47,762
$92,352
Total
$12,783
$710,300
$5,190,222
$15,270
$15,604
$15,961
$50,168
$6,010,308
COUNCIL DISTRICT 1
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Local Streets Fund
-
$1,500,000
-
-
-
-
-
$1,500,000
Total
-
$1,500,000
-
-
-
-
-
$1,500,000
COUNCIL DISTRICT 6
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2020 Street Bond
$777,920
$268,792
-
-
-
-
-
$1,046,712
Grants - Gen. Gov.
$2,402,603
$7,347,396
$17,171,742
-
-
-
-
$26,921,741
Local Streets Fund
$1,387,383
$3,711,209
$5,151,522
-
-
-
-
$10,250,114
O&M
Environmental 
Compliance Fee
-
-
-
$6,589
$6,733
$6,887
$21,648
$41,857
Local Streets Fund
-
-
-
$123,727
$126,435
$129,328
$406,495
$785,985
Total
$4,567,906
$11,327,397
$22,323,264
$130,316
$133,168
$136,215
$428,143
$39,046,409
COUNCIL DISTRICT 6
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2020 Street Bond
$7,191,411
$10,700,000
-
-
-
-
-
$17,891,411
Transportation
$381,929
$11,748,489
-
-
-
-
-
$12,130,418
O&M
Local Streets Fund
-
-
$225,871
$230,825
$235,876
$241,273
$758,356
$1,692,201
Total
$7,573,340
$22,448,489
$225,871
$230,825
$235,876
$241,273
$758,356
$31,714,030
This project will improve traffic flow and pedestrian safety in Downtown Mesa by strategically removing unwarranted traffic signals at low-volume 
intersections.
Elliot Road: Ellsworth to Sossaman (CP0982)
Roadway project that will build out the ultimate street cross section and includes intersection improvements and new traffic signals.
Ellsworth Road from City Limits to Ray Road (CP0969)
Roadway project that will build out the ultimate street cross section. This includes pavement replacement.
Roadway project to mitigate traffic delays, congestion and enhance safety. This also includes intersection improvements, pavement replacement, and 3 new 
pedestrian crossings.
Center Street-University Dr to Main St (CP1298)
Roadway project to enhance mobility and accessibility for pedestrians and cyclists. Includes wider sidewalks, separated bike lanes and will maximize on-
street parking.
COM Comprehensive Safety Action Plan (CP1144)
Develop a plan to incorporate Safe System Approach principles and specifically identify how to best utilize the state and regional safety and transportation 
strategies by developing programs and projects to address the needs of all Mesa communities.
Crismon Road Connection-Guadalupe Rd to Elliot Rd (CP1291)
Roadway project to close a gap in Mesa's transportation network. This will complete a regionally significant roadway connection.
Downtown Traffic Signal Removal (CP1315)
Broadway Road: Lesueur to Spur (CP0666)
City of Mesa
Page 24 of 35
Proposed Five Year Capital Improvement Program

COUNCIL DISTRICT 6
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Transportation
$140
$490,000
-
-
-
-
-
$490,140
Total
$140
$490,000
-
-
-
-
-
$490,140
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Local Streets Fund
$498
$10,000
-
-
-
-
-
$10,498
Total
$498
$10,000
-
-
-
-
-
$10,498
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2026 Street Bond
-
-
-
-
$925,744
$9,460,880
-
$10,386,624
Total
-
-
-
-
$925,744
$9,460,880
-
$10,386,624
COUNCIL DISTRICT 1
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Transportation
-
-
-
$390,740
$4,051,682
-
-
$4,442,422
Total
-
-
-
$390,740
$4,051,682
-
-
$4,442,422
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Local Streets Fund
-
$790,275
$406,302
$415,213
$424,299
$434,007
$1,364,147
$3,834,243
Total
-
$790,275
$406,302
$415,213
$424,299
$434,007
$1,364,147
$3,834,243
COUNCIL DISTRICT 5
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Transportation
-
$71,164
$736,038
-
-
-
-
$807,202
O&M
Local Streets Fund
-
-
-
$16,943
$17,314
$17,710
$55,665
$107,633
Total
-
$71,164
$736,038
$16,943
$17,314
$17,710
$55,665
$914,835
COUNCIL DISTRICT 6
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Transportation
-
$182,500
-
-
-
-
-
$182,500
Total
-
$182,500
-
-
-
-
-
$182,500
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2026 Street Bond
-
-
$3,640,000
$16,171,485
-
-
-
$19,811,485
Local Streets Fund
-
-
-
$32,056,666
-
-
-
$32,056,666
Total
-
-
$3,640,000
$48,228,151
-
-
-
$51,868,151
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Local Streets Fund
$6,276
$25,724
-
-
-
-
-
$32,000
Total
$6,276
$25,724
-
-
-
-
-
$32,000
Roadway project that will build out the ultimate street cross section and close a sidewalk gap.
Mesa 112 Warner & Sossaman Drainage Improvements (CN0102)
Cost sharing on proposed interim solution for the Excess Flows that would bring the depth and speed of the water crossing the intersection into compliance 
with City Standards. Per Development Agreement DA24-00005.
Mesa Drive; Main Street to Brown Road (CP0664)
Roadway project to mitigate traffic delays, congestion and enhance safety.
Mesa Drive Phase II Easements (CP1290)
Easements for Mesa Drive Phase II
Transportation is addressing safety concerns related to damaged guard rails. The required repairs exceed in-house capabilities and must be completed 
through the Engineering Department via the JOC process.
Higley: McKellips to Broadway (CSAP) (CP1332)
Roadway project to increase safety for all users. Includes the installation of raised medians.
Lehi - McDowell to Portia (CP1334)
This project involves the comprehensive reconstruction of pavement, sidewalks, and curbs from McDowell Road to Portia Street, incorporating significant 
storm drain improvements and right-of-way acquisitions for drainage infrastructure.
MAG Projects Local Match (CP0109)
Fund the local match for transportation projects that are eligible for regional funding.
McKellips Road from 64th Street to Jasmine  (CP1135)
Germann Road and Sossaman Road Intersection Study (CP1098)
Participate in a design concept report to evaluate the traffic impacts of the intersection of Germann and Sossaman Road.  IGA with MCDOT & Queen Creek.
Guard Rail Repairs (CP1355)
City of Mesa
Page 25 of 35
Proposed Five Year Capital Improvement Program

COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Transportation
-
$477,069
-
-
-
-
-
$477,069
Total
-
$477,069
-
-
-
-
-
$477,069
COUNCIL DISTRICT 6
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Transportation
$644,091
$6,814,623
$4,093,720
-
-
-
-
$11,552,433
Total
$644,091
$6,814,623
$4,093,720
-
-
-
-
$11,552,433
COUNCIL DISTRICT 6
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Transportation
$1,041,944
$1,209,216
-
-
-
-
-
$2,251,160
Total
$1,041,944
$1,209,216
-
-
-
-
-
$2,251,160
COUNCIL DISTRICT 5
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Highway User 
Revenue Fund
$824
$103,500
-
-
-
-
-
$104,324
Total
$824
$103,500
-
-
-
-
-
$104,324
COUNCIL DISTRICT 6
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2013 Street Bond
$8,182,598
$4,000,000
-
-
-
-
-
$12,182,598
O&M
Highway User 
Revenue Fund
-
-
$1,740
$1,778
$1,817
$1,858
$5,841
$13,035
Local Streets Fund
-
-
$101,831
$104,065
$106,342
$103,965
$341,667
$757,870
Total
$8,182,598
$4,000,000
$103,571
$105,843
$108,159
$105,823
$347,508
$12,953,502
COUNCIL DISTRICT 6
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Local Streets Fund
-
-
-
-
$7,481,343
-
-
$7,481,343
Total
-
-
-
-
$7,481,343
-
-
$7,481,343
COUNCIL DISTRICT 6
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Transportation
$24,988
$1,470,000
-
-
-
-
-
$1,494,988
Total
$24,988
$1,470,000
-
-
-
-
-
$1,494,988
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Grants - Gen. Gov.
-
$281,600
$2,924,205
-
-
-
-
$3,205,805
Local Streets Fund
-
$70,400
$731,051
-
-
-
-
$801,451
Total
-
$352,000
$3,655,257
-
-
-
-
$4,007,257
Reimburse Queen Creek for Signal Butte Rd Impvmts CP0885 
(CN0107)
Reimbursement to Town of Queen Creek for Signal Butte Road Improvements CP0885
RFFBs at Las Sendas Neighborhood (CP1337)
Installation of five Rectangular Rapid Flashing Beacons (RRFBs) for the Las Sendas Neighborhood to increase pedestrian visibility.
SafeTurn Initiative-SS4A Grant (CP1341)
Modernize eight intersections with protected left-turn signals to reduce traffic fatalities and serious injuries.  This project is funded by a USDOT Safe Streets 
grant.
Add additional lanes and dual left turn lanes to ease traffic congestion and enhance safety.
Mountain Rd from SR24 to Pecos  (CP1136)
Roadway project that will build out the ultimate street cross section.
Power Road Improvements: East Maricopa Floodway to Loop 202 
(CP0104)
Roadway project that will build out the ultimate street cross section and includes intersection improvements.  This is a joint project with the Town of Gilbert 
and Maricopa County.
Princess Dr & Power Rd Valley Gutter (CP1357)
Install new valley gutter across Princess Dr to redirect some of the water flow down southbound Power Rd instead of westbound Princess Dr.
Ray Roads connections at Ellsworth Road (CP0983)
Roadway project that realigns Ray Road at Ellsworth Road and includes a new traffic signal.
Mesa Drive: Southern Avenue to US 60 (C01817)
City of Mesa
Page 26 of 35
Proposed Five Year Capital Improvement Program

COUNCIL DISTRICT 6
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Transportation
-
$540,931
-
-
-
-
-
$540,931
Total
-
$540,931
-
-
-
-
-
$540,931
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Gas Utility Revenue 
Pledge
$112,366
$1,750,000
-
-
-
-
-
$1,862,366
Transportation
$518,901
$10,849,808
$3,070,290
-
-
-
-
$14,438,999
Wastewater Utility 
Revenue Pledge
$28,925
$98,477
$112,956
$14,708
-
-
-
$255,066
Total
$660,192
$12,698,285
$3,183,246
$14,708
-
-
-
$16,556,431
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2020 Street Bond
$647,039
$878,046
-
-
-
-
-
$1,525,085
Total
$647,039
$878,046
-
-
-
-
-
$1,525,085
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Special Programs 
Fund
$118,019
$380,000
-
-
-
-
-
$498,019
Total
$118,019
$380,000
-
-
-
-
-
$498,019
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Transportation
-
$1,817,500
-
-
-
-
-
$1,817,500
Total
-
$1,817,500
-
-
-
-
-
$1,817,500
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Local Streets Fund
$1,562,661
$1,263,000
$255,857
$261,469
$267,191
$273,304
$859,035
$4,742,518
Total
$1,562,661
$1,263,000
$255,857
$261,469
$267,191
$273,304
$859,035
$4,742,518
COUNCIL DISTRICT 5
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2026 Street Bond
-
-
-
-
$1,457,040
$15,500,160
-
$16,957,200
Total
-
-
-
-
$1,457,040
$15,500,160
-
$16,957,200
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Local Streets Fund
$623,596
$179,905
-
-
-
-
-
$803,501
Transportation
$64,014
$120,095
-
-
-
-
-
$184,109
Total
$687,610
$300,000
-
-
-
-
-
$987,610
Streetlight Spot Improvements (CP1068)
Install streetlights in various locations citywide. To fulfill requests from residents and the Police Department for additional street lights and new street lights in 
areas where there are no street lights as funds allow.
Thomas Rd Multimodal (CP1322)
Roadway project to enhance mobility and accessibility for pedestrians and cyclists and create a connection to the new Power Road SUP. Limits are from 
Thomas between Power and Higley, south to Longbow Parkway, east to Recker and back north to Thomas.
Transportation Building Improvements (CP1149)
Renovation of East Mesa Service Center and West Yard office areas based on Space Planning Study by Gensler AZ completed October 2022.
Reconstruct two major arterials where pavement is failing.  The two segments are Southern; Alma School to Center and Country Club; US 60 to 1st Ave.
Stapley Drive and University Drive Intersection (C05041)
Roadway and intersection improvements to mitigate traffic delays, congestion and enhance safety. This also includes pavement replacement.
Stapley Drive Sidewalk Installation (CP1160)
Install sidewalks for public safety on the west side of Stapley Drive south of Main.
Street Improvement 2020 Cityshare (CN0087)
Fund the City's participation in the cost share of widening of streets and the installation of new street lights that are built in conjunction with development 
projects.
Signal Butte Road Improvements Segment 2, Pecos to Germann 
(CP0885)
Construct a 2 lane roadway (built in the east side of the ultimate 4 lane roadway section) and will have curb, and gutter only in the east side
Southern Avenue & Country Club Drive Roadways (CP0844)
City of Mesa
Page 27 of 35
Proposed Five Year Capital Improvement Program

COUNCIL DISTRICT 2
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2020 Street Bond
$2,750,997
$12,279,053
-
-
-
-
-
$15,030,050
Gas Utility Revenue 
Pledge
$733,035
$800,000
-
-
-
-
-
$1,533,035
Water Utility Revenue 
Pledge
$7,238
$49,836
-
-
-
-
-
$57,074
Total
$3,491,270
$13,128,889
-
-
-
-
-
$16,620,159
COUNCIL DISTRICT 6
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
2026 Street Bond
-
$3,279,536
$13,567,998
-
-
-
-
$16,847,534
Local Streets Fund
-
-
$21,036,446
-
-
-
-
$21,036,446
Total
-
$3,279,536
$34,604,444
-
-
-
-
$37,883,980
COUNCIL DISTRICT 6
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Transportation
$11,859
$1,985,300
-
-
-
-
-
$1,997,159
O&M
Environmental 
Compliance Fee
-
-
$743
$759
$776
$794
$2,495
$5,567
Local Streets Fund
-
-
$19,436
$19,862
$20,297
$20,761
$65,256
$145,612
Total
$11,859
$1,985,300
$20,179
$20,622
$21,073
$21,555
$67,750
$2,148,338
COUNCIL DISTRICT 1
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Transportation
-
-
$336,299
$3,143,385
-
-
-
$3,479,684
O&M
Highway User 
Revenue Fund
-
-
-
-
$214
$219
$687
$1,120
Local Streets Fund
-
-
-
-
$2,779
$2,842
$8,934
$14,555
Total
-
-
$336,299
$3,143,385
$2,993
$3,061
$9,621
$3,495,359
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Local Streets Fund
$1,084
$16,454
-
-
-
-
-
$17,538
Transit Fund
$308,183
$725,381
-
-
-
-
-
$1,033,564
Total
$309,267
$741,835
-
-
-
-
-
$1,051,102
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Wastewater Utility 
Revenue Pledge
$19,356,394
$21,224,605
$28,988,640
$31,591,630
$39,631,501
$42,941,876
$85,903,457
$269,638,103
Total
$19,356,394
$21,224,605
$28,988,640
$31,591,630
$39,631,501
$42,941,876
$85,903,457
$269,638,103
COUNCIL DISTRICT 6
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Wastewater Utility 
Revenue Pledge
-
-
-
-
$7,490,762
-
-
$7,490,762
Total
-
-
-
-
$7,490,762
-
-
$7,490,762
Wastewater Growth
91st Avenue Water Reclamation Plant (Mesa Share) (CN0076)
Fund the City's portion of the capital improvement cost of the 91st Avenue Water Reclamation Plant. 
ASU IGA (CN0103)
Provide for necessary wastewater infrastructure improvements to handle projected flows in Southeast Mesa and to maintain service reliability in the area.
Warner Rd Bridge (CP1330)
Constructs a bridge crossing over the EMF and RWCD canals east of Power Road, establishing the ultimate street footprint and configuration.
Warner Road: Mountain Rd. to Meridian Rd. (CP1242)
Roadway widening on the south side of Warner to build out the ultimate street cross section.
West side of Val Vista at South Canal (CP1215)
Roadway widening on the west side of Val Vista between Virginia and the South Canal to build out the ultimate street cross section.
Transit
Bus Stop Improvement and Bus Shelter Construction (CP0992)
Improve and construct bus stops across the City to accommodate shelters, seating, and create better accessibility to transit.
Val Vista Drive: Pueblo to US 60 (CP0062)
Roadway and intersection improvements to mitigate traffic delays, congestion and enhance safety.
City of Mesa
Page 28 of 35
Proposed Five Year Capital Improvement Program

CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital Programs
$3,785,302
$891,511
-
-
-
-
-
$4,676,813
Total
$3,785,302
$891,511
-
-
-
-
-
$4,676,813
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Wastewater Utility 
Revenue Pledge
$1,734,046
$2,185,657
-
-
-
-
-
$3,919,703
Total
$1,734,046
$2,185,657
-
-
-
-
-
$3,919,703
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Wastewater Utility 
Revenue Pledge
$144,326
$494,404
$288,267
$940,187
$4,920,956
$10,493,372
$4,658,410
$21,939,923
Total
$144,326
$494,404
$288,267
$940,187
$4,920,956
$10,493,372
$4,658,410
$21,939,923
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital Programs
$4,030,055
$3,115,708
$101,861
-
-
-
-
$7,247,624
Total
$4,030,055
$3,115,708
$101,861
-
-
-
-
$7,247,624
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Wastewater Utility 
Revenue Pledge
$1,908,784
$1,623,595
$53,080
-
-
-
-
$3,585,459
Total
$1,908,784
$1,623,595
$53,080
-
-
-
-
$3,585,459
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital Programs
$587,770
$2,067,363
$2,551,690
$8,322,357
$43,559,342
$92,885,296
$41,235,336
$191,209,154
Total
$587,770
$2,067,363
$2,551,690
$8,322,357
$43,559,342
$92,885,296
$41,235,336
$191,209,154
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Wastewater Utility 
Capacity Fee Revenue 
Pledge
$226,234
$3,000,000
$2,455,132
-
-
-
-
$5,681,366
O&M
Wastewater
-
-
$427,818
$426,743
$436,081
$446,059
$1,402,027
$3,138,728
Total
$226,234
$3,000,000
$2,882,950
$426,743
$436,081
$446,059
$1,402,027
$8,820,094
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Highway User 
Revenue Fund
$119
$62,997
-
-
-
-
-
$63,116
Wastewater Utility 
Capacity Fee Revenue 
Pledge
$4,887,814
$6,982,412
-
-
-
-
-
$11,870,226
Total
$4,887,934
$7,045,409
-
-
-
-
-
$11,933,343
Construct additional treatment capacity to meet the increasing wastewater flows to the Greenfield Water Reclamation Plant. The Greenfield plant is a joint 
venture between the City of Mesa, Town of Gilbert and Town of Queen Creek.
New Lift Stations (CP0617)
Construct new wastewater lift stations to serve projected growth in currently undeveloped areas that cannot be totally served by a gravity sewer system.
New Sewer Lines - Other Areas (CP0619)
Construct new sewer lines in undeveloped areas other than southeast Mesa to serve projected growth and areas currently served by on-site septic systems.
Replace minor equipment that has reached the end of its useful life at the Greenfield Water Reclamation Plant.
Greenfield Water Reclamation Plant Expansion 4 - Mesa Share 
(CN0096)
Construct additional treatment capacity to meet the increasing wastewater flows to the Greenfield Water Reclamation Plant. The Greenfield plant is a joint 
venture between the City of Mesa, Town of Gilbert and Town of Queen Creek.
Greenfield Water Reclamation Plant Improvement (CP0897)
Modify and/or rehabilitate existing systems, install new or upgraded systems and replace major equipment that has reached its useful life.
Greenfield Water Reclamation Plant Improvement - Mesa Share 
(CN0067)
Modify and/or rehabilitate existing systems, install new or upgraded systems and replace major equipment that has reached its useful life.
Greenfield Water Reclamation Plant - Phase 4 Expansion (CP1187)
Greenfield Water Reclamation Plant Equipment (CP0898)
Replace minor equipment that has reached the end of its useful life at the Greenfield Water Reclamation Plant.
Greenfield Water Reclamation Plant Equipment - Mesa Share 
(CN0068)
City of Mesa
Page 29 of 35
Proposed Five Year Capital Improvement Program

COUNCIL DISTRICT 6
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Wastewater Utility 
Revenue Pledge
$264,810
$2,453,783
$617,567
$15,017,415
$6,815,810
$1,634,814
$244,634
$27,048,833
Total
$264,810
$2,453,783
$617,567
$15,017,415
$6,815,810
$1,634,814
$244,634
$27,048,833
COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Electric
$837,709
$212,437
$307,029
-
-
-
-
$1,357,175
Natural Gas
$789,512
$237,533
$307,029
-
-
-
-
$1,334,074
Wastewater
$1,308,284
$386,185
$507,621
-
-
-
-
$2,202,090
Water
$1,314,486
$357,612
$507,621
-
-
-
-
$2,179,719
Total
$4,249,991
$1,193,767
$1,629,300
-
-
-
-
$7,073,058
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Capital Programs
$7,070,016
$14,521,631
$12,817,692
$2,203,394
$1,638,033
-
-
$38,250,766
Total
$7,070,016
$14,521,631
$12,817,692
$2,203,394
$1,638,033
-
-
$38,250,766
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Wastewater Utility 
Revenue Pledge
$3,235,077
$7,567,222
$6,679,299
$1,148,188
$853,578
-
-
$19,483,365
Total
$3,235,077
$7,567,222
$6,679,299
$1,148,188
$853,578
-
-
$19,483,365
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Wastewater Utility 
Revenue Pledge
$794,320
$2,792,393
$4,198,259
$9,032,047
$4,294,068
$333,735
-
$21,444,822
Total
$794,320
$2,792,393
$4,198,259
$9,032,047
$4,294,068
$333,735
-
$21,444,822
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Water Utility Capacity 
Fee Revenue Pledge
-
$755,000
-
-
-
-
-
$755,000
Total
-
$755,000
-
-
-
-
-
$755,000
COUNCIL DISTRICT 3
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Wastewater Utility 
Revenue Pledge
$7,770,174
$4,592,317
-
-
-
-
$60,323,138
$72,685,629
Total
$7,770,174
$4,592,317
-
-
-
-
$60,323,138
$72,685,629
Miscellaneous Water & Wastewater Projects (CP0899)
Odor control improvement program, including other miscellaneous water & wastewater system projects.
Northwest WRP Major Plant Improvements (CP0951)
Construct, rehabilitate, modify, upgrade or replace major assets and infrastructure at the Northwest Water Reclamation Plant.
Explore conceptual modifications to the Utilities Building at 640 N. Mesa Drive as part of a tenant improvement.
GWRP Major Plant Improvements (CP0625)
Replace and/or modify major equipment or systems to improve plant performance and ensure compliance with regulatory requirements.
GWRP Major Plant Improvements - CP0625 Mesa Share (CN0035)
Replace and/or modify major equipment or systems to improve plant performance and ensure compliance with regulatory requirements.
Lift Station Replacements (CP0958)
Rehabilitate, upgrade, modify and/or replace equipment and systems at sewer lift stations.
SEWRP Lift Station and Forcemain (CP1229)
Design and construct new lift station and sewer force main to pump all sewer flows from the Southeast drainage basin to the Greenfield Water Reclamation 
Plant (GWRP) for treatment.
Wastewater Replacements
Chrls Lstr Utilities Bldg Tenant Impr Architectural Concepts 
(CP1007)
City of Mesa
Page 30 of 35
Proposed Five Year Capital Improvement Program

CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Wastewater
-
$37,868
-
-
-
-
-
$37,868
Wastewater Utility 
Revenue Pledge
$463,501
$81,264
$180,130
$1,907,674
-
-
-
$2,632,569
Total
$463,501
$119,132
$180,130
$1,907,674
-
-
-
$2,670,437
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Wastewater Utility 
Revenue Pledge
$2,453,088
$2,293,170
$1,228,116
$1,255,053
$1,282,516
$1,311,861
$5,497,821
$15,321,625
Total
$2,453,088
$2,293,170
$1,228,116
$1,255,053
$1,282,516
$1,311,861
$5,497,821
$15,321,625
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Wastewater Utility 
Revenue Pledge
$798,112
$2,430,768
$2,739,389
$421,024
-
-
-
$6,389,294
Total
$798,112
$2,430,768
$2,739,389
$421,024
-
-
-
$6,389,294
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Wastewater Utility 
Revenue Pledge
$23,256,375
$27,334,366
$28,830,210
$6,488,915
$11,537,810
$7,645,319
$18,220,395
$123,313,390
Total
$23,256,375
$27,334,366
$28,830,210
$6,488,915
$11,537,810
$7,645,319
$18,220,395
$123,313,390
COUNCIL DISTRICT 3
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Wastewater Utility 
Revenue Pledge
$3,995,984
$1,488,614
$3,478,996
$3,274,259
$3,215,769
$2,060,322
$64,811
$17,578,754
Total
$3,995,984
$1,488,614
$3,478,996
$3,274,259
$3,215,769
$2,060,322
$64,811
$17,578,754
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Water Utility Revenue 
Pledge
$172,687,305
$22,604,038
-
-
-
-
-
$195,291,343
O&M
Wastewater
-
$264,000
$270,185
$276,112
$282,154
$288,609
$907,141
$2,288,201
Total
$172,687,305
$22,868,038
$270,185
$276,112
$282,154
$288,609
$907,141
$197,579,543
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Water Utility Capacity 
Fee Revenue Pledge
$20,099
$9,941,950
$5,079,334
-
-
-
-
$15,041,383
Total
$20,099
$9,941,950
$5,079,334
-
-
-
-
$15,041,383
East Mesa Water Interconnect Pipes (CP1050)
Interconnect pipes would help the city meet the growing demand and leverage existing production capacity from one area of the city to meet demands in 
another.
Sewer Line Rehabilitation (CP0623)
Rehabilitate and/or replace defective pipe in the wastewater collection system to prevent catastrophic failures and maintain a high level of service.  These 
defective lines were identified through the wastewater asset management program.
Sewer Line Replacement (CP0956)
Construct, rehabilitate, and/or replace existing sewer lines.
Southern Avenue Interceptor Condition Assessment-City Share 
(CN0077)
 
Fund the City's share of the Southern Avenue Interceptor (SAI) condition assessment. A joint project with the City of Tempe. 
Water Growth
Central Mesa Reuse Pipeline Project (CP0896)
Construct a reclaimed water line from Northwest Water Reclamation Plant to Southeast Water Reclamation Plant.
Odor Control Station Replacements (CP0959)
Rehabilitate, upgrade, modify and/or replace equipment and systems at odor control stations.
Sewer Line Condition Assessment (CP0957)
 
Perform inspections and condition assessments of existing sewer lines. 
City of Mesa
Page 31 of 35
Proposed Five Year Capital Improvement Program

CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Water Utility Revenue 
Pledge
$5,463,774
$2,189,200
$2,046,860
$2,091,755
$2,137,527
$2,186,435
$6,872,277
$22,987,827
O&M
Utility Replacement 
Extension and 
Renewal - WTR
-
-
$1,909,208
-
-
-
-
$1,909,208
Water
-
-
-
$573,907
$536,814
$558,687
$1,819,899
$3,489,306
Total
$5,463,774
$2,189,200
$3,956,068
$2,665,662
$2,674,341
$2,745,122
$8,692,175
$28,386,341
COUNCIL DISTRICT 6
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Water Utility Capacity 
Fee Revenue Pledge
$1,955,586
$1,589,157
$2,289,413
$13,433,252
$9,753,534
$1,023,252
$1,292,315
$31,336,507
Water Utility Revenue 
Pledge
$9,669,716
-
-
-
$611,333
$10,974,837
-
$21,255,886
O&M
Water
-
-
-
-
$442,506
$1,032,037
$4,016,705
$5,491,248
Total
$11,625,301
$1,589,157
$2,289,413
$13,433,252
$10,807,373
$13,030,126
$5,309,020
$58,083,641
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Water Utility Capacity 
Fee Revenue Pledge
$597,693
$325,000
$92,109
$472,241
$6,517,201
$1,777,685
-
$9,781,929
Total
$597,693
$325,000
$92,109
$472,241
$6,517,201
$1,777,685
-
$9,781,929
COUNCIL DISTRICT 6
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Wastewater Utility 
Capacity Fee Revenue 
Pledge
$183,700
$405,520
$14,030,507
$4,778,176
$701,109
$447,693
$14,123,311
$34,670,016
O&M
Wastewater
-
-
-
-
$361,127
$343,699
$1,837,186
$2,542,012
Total
$183,700
$405,520
$14,030,507
$4,778,176
$1,062,235
$791,392
$15,960,497
$37,212,028
COUNCIL DISTRICT 6
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Water Utility Capacity 
Fee Revenue Pledge
$16,486,700
$63,916,358
$5,484,090
-
-
-
-
$85,887,148
O&M
Environmental 
Compliance Fee
-
$121,044
$126,963
$132,998
$139,345
$146,168
$483,462
$1,149,980
Water
-
$2,040,718
$2,100,318
$2,204,951
$2,313,404
$2,428,379
$8,048,424
$19,136,194
Total
$16,486,700
$66,078,120
$7,711,370
$2,337,949
$2,452,750
$2,574,547
$8,531,886
$106,173,322
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Water Utility Revenue 
Pledge
$23,252,832
$6,513,760
$3,021,316
$8,249,305
$32,932,244
$24,890,880
$68,722,766
$167,583,104
Total
$23,252,832
$6,513,760
$3,021,316
$8,249,305
$32,932,244
$24,890,880
$68,722,766
$167,583,104
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Water Utility Revenue 
Pledge
$740,388
$112,000
-
-
-
-
-
$852,388
Total
$740,388
$112,000
-
-
-
-
-
$852,388
New Sewer Lines - Southeast Mesa (CP1185)
Construct new sewer lines in the area bounded by Elliot, Power, Germann, and Meridian Roads to serve development in Southeast Mesa
Signal Butte Water Treatment Plant Expansion (CP0372)
Construct additional treatment capacity at the plant to meet growth demands in Southeast Mesa.
Val Vista Water Treatment Plant (Mesa Share) (CN0074)
 
Fund the City's portion of the capital improvement cost of the Val Vista Water Treatment Plant.
Water Extensions and Oversized Mains (CN0075)
Fund the City's share for developer constructed waterlines that are larger than 16-inch diameter.
Fire Hydrant And Water Valve Replacement Program (CP0826)
Replace fire hydrants and water valves.
New Groundwater Wells (CP0836)
 
Design and construct new groundwater well facilities and collection lines to meet water demands from new growth.
New Pump Stations (CP0830)
Design and construct new pump station facilities to meet water demands from new growth.
City of Mesa
Page 32 of 35
Proposed Five Year Capital Improvement Program

CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Utility Replacement 
Extension and 
Renewal - WTR
-
$50,000
-
-
-
-
-
$50,000
Water Utility Revenue 
Pledge
-
$50,000
-
-
-
-
-
$50,000
Total
-
$100,000
-
-
-
-
-
$100,000
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Water Utility Revenue 
Pledge
$4,042,494
$3,626,533
$1,875,236
$902,670
$480,432
-
-
$10,927,364
Total
$4,042,494
$3,626,533
$1,875,236
$902,670
$480,432
-
-
$10,927,364
COUNCIL DISTRICT 6
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Water Utility Capacity 
Fee Revenue Pledge
$5,515
$274,200
$664,728
$10,813,845
$10,276,373
$2,036,769
$503,187
$24,574,617
Total
$5,515
$274,200
$664,728
$10,813,845
$10,276,373
$2,036,769
$503,187
$24,574,617
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Water Utility Revenue 
Pledge
-
-
-
$3,869,747
$3,954,434
-
-
$7,824,181
Total
-
-
-
$3,869,747
$3,954,434
-
-
$7,824,181
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Water Utility Revenue 
Pledge
-
$1,030,000
$691,839
-
-
-
-
$1,721,839
Total
-
$1,030,000
$691,839
-
-
-
-
$1,721,839
COUNCIL DISTRICT 5
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Water Utility Revenue 
Pledge
$377,378
$510,000
-
-
-
-
-
$887,378
Total
$377,378
$510,000
-
-
-
-
-
$887,378
COUNCIL DISTRICT 5
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Water Utility Revenue 
Pledge
$19,560
$1,000,000
$2,252,273
$480,360
-
-
$37,611,260
$41,363,454
Total
$19,560
$1,000,000
$2,252,273
$480,360
-
-
$37,611,260
$41,363,454
Advanced Water Purification Facility (CN0110)
Fund Mesa's participation in a regional study, led by the City of Phoenix, to evaluate the feasibility of constructing an advanced water purification facility near 
the 91st Avenue Wastewater Treatment Plant.
Brown Road Equipment Replacement (CP0966)
 
Modify, upgrade or replace equipment or systems at the Brown Road Water Treatment Plant. 
 
BRWTP Main Switchgear and Transformers Replacement (CP1254)
The purpose of this project is to replace the BRWTP main electrical switchgear and transformers which are deteriorating and in need of replacement, due to 
age and usage in order to maintain service reliability at the plant.
Fund the City's cost share for developer constructed waterlines that are larger than 16-inch diameter.
Water Meter Vault Rehab Program (CP0825)
 
Remove and relocate existing commercial water meters in underground vaults to meet OSHA confined space regulations.
Well Collection Lines (CP0648)
Construct water lines to convey water from the well to the reservoir.
White Mountain Apache Water Settlement Water Rights (CN0028)
Lease Central Arizona Project (CAP) canal water rights from the White Mountain Apache Tribe for 100 years.  Long-term leasing of the water rights will help 
ensure the City's water supply.
Water Replacements
Water Extensions and Oversized Mains - City Share (CN0064)
City of Mesa
Page 33 of 35
Proposed Five Year Capital Improvement Program

COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Wastewater Utility 
Revenue Pledge
$10,014
$510,488
-
-
-
-
-
$520,502
Water Utility Revenue 
Pledge
$15,074
$169,000
-
-
-
-
-
$184,074
Total
$25,088
$679,488
-
-
-
-
-
$704,576
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Water Utility Revenue 
Pledge
$6,494,500
$3,742,685
$10,792,086
$11,538,887
$2,833,719
$7,947,692
$17,458,926
$60,808,494
Total
$6,494,500
$3,742,685
$10,792,086
$11,538,887
$2,833,719
$7,947,692
$17,458,926
$60,808,494
COUNCIL DISTRICT 3
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Wastewater Utility 
Revenue Pledge
$297,567
$4,730,000
$3,760,891
$4,497,274
$4,531,556
-
-
$17,817,288
Total
$297,567
$4,730,000
$3,760,891
$4,497,274
$4,531,556
-
-
$17,817,288
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Utility Replacement 
Extension and 
Renewal - WTR
$381,521
$2,063,880
-
-
-
-
-
$2,445,401
Water Utility Revenue 
Pledge
-
$770,000
$644,761
-
-
-
-
$1,414,761
Total
$381,521
$2,833,880
$644,761
-
-
-
-
$3,860,162
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Water Utility Revenue 
Pledge
$5,223,974
-
-
$437,530
$2,582,843
$10,146,982
$5,486,186
$23,877,516
Total
$5,223,974
-
-
$437,530
$2,582,843
$10,146,982
$5,486,186
$23,877,516
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Water Utility Revenue 
Pledge
$2,459,511
$70,000
-
-
-
$218,644
$2,813,278
$5,561,433
Total
$2,459,511
$70,000
-
-
-
$218,644
$2,813,278
$5,561,433
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Electric Utility 
Revenue Pledge
$4,529,070
$1,249,813
-
-
-
-
-
$5,778,883
Gas Utility Revenue 
Pledge
$16,817,307
$5,675,140
-
-
-
-
-
$22,492,447
Utility Replacement 
Extension and 
Renewal - ELC
$64,799
$43,688
-
-
-
-
-
$108,487
Water Utility Revenue 
Pledge
$47,508,696
$18,234,615
-
-
-
-
-
$65,743,311
O&M
Water
-
$83,000
$84,945
$86,808
$88,707
$90,737
$285,199
$719,396
Total
$68,919,872
$25,286,256
$84,945
$86,808
$88,707
$90,737
$285,199
$94,842,524
Reservoir Rehabilitation Program (CP0831)
Assess and rehabilitate aging reservoirs and associated equipment.
Smart Metering (CP0900)
Upgrade utility meter infrastructure, including related communications network and data management systems.  A Smart Cities Initiative.
Groundwater Well Replacement Program (CP0642)
Rehabilitate or replace groundwater well facilities.
Northwest Major Plant Improvements (CP1202)
Construct, rehabilitate, modify, upgrade or replace major assets and infrastructure at the Northwest Water Reclamation Plant.
Pump Station Replacement Program (CP0829)
 
Rehabilitate or replace aging pump station facilities.
Quarter Section Replacement Program (CP0834)
 
Assess, design and construct to replace aging water distribution mains throughout the city.
CK Luster Building Emergency Standby Power Upgrade (CP1054)
Upgrade the emergency standby power system in the Charles K Luster building, including generator, distribution, and Uninterruptible Power Supply (UPS).
City of Mesa
Page 34 of 35
Proposed Five Year Capital Improvement Program

COUNCIL DISTRICT 4
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Water Utility Revenue 
Pledge
-
-
-
-
-
$163,561
$10,191,900
$10,355,461
Total
-
-
-
-
-
$163,561
$10,191,900
$10,355,461
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Water Utility Revenue 
Pledge
$597,197
$708,363
$511,715
$522,939
$534,382
$546,609
$1,718,069
$5,139,273
Total
$597,197
$708,363
$511,715
$522,939
$534,382
$546,609
$1,718,069
$5,139,273
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Water Utility Revenue 
Pledge
$36,753,841
$5,857,132
$8,997,116
$5,959,290
$5,291,402
$5,462,343
$16,497,553
$84,818,679
Total
$36,753,841
$5,857,132
$8,997,116
$5,959,290
$5,291,402
$5,462,343
$16,497,553
$84,818,679
CITYWIDE
Fund
Estimated Exp 
Through FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
Future Years 
(3)
Total
Capital
Gas Utility Revenue 
Pledge
$46,092
$2,700,000
-
-
-
-
-
$2,746,092
Utility Replacement 
Extension and 
Renewal - WTR
$3,049
$95,854
-
-
-
-
-
$98,903
Water Utility Revenue 
Pledge
$2,618,665
$1,550,414
$1,537,224
$2,668,482
$4,680,936
$621,824
-
$13,677,547
Total
$2,667,806
$4,346,268
$1,537,224
$2,668,482
$4,680,936
$621,824
-
$16,522,542
Water Line Replacement Program (CP0832)
Replace aging waterlines in various locations.
Water Main Replacement Program (CP1053)
Replace aging water mains in various locations throughout the City.
Utility Line Replacement Quarter Section 21D, Clark, Pepper 
(C10382)
Replace aging main and service lines in plat quarter section 21D.
Valves and Hydrant Replacements (CP1059)
Replacement of water valves and hydrants utilizing third-party contractors.
City of Mesa
Page 35 of 35
Proposed Five Year Capital Improvement Program