City Council Report 
 
 
Date:  
May 18, 2026 
To: 
 
City Council 
Through: 
Marc Heirshberg, Assistant City Manager 
From:  
Lance Webb, City Engineer 
 
 
Marc Ahlstrom, Assistant City Engineer 
 
Subject: 
Hohokam Stadium and Fitch Park Improvements 
 
 
City Project No. CP1292HOME 
Council Districts 1 and 4 
 
 
Purpose and Recommendation 
 
The purpose of this report is to present the first Guaranteed Maximum Price (GMP) for 
the Hohokam Stadium and Fitch Park Improvements project (Refer to Exhibit “A” for the 
project location).   
 
Staff recommends that Council award a contract for this project to Mortenson 
Construction in the amount of $7,291,438.00 (GMP) and authorize a change order 
allowance in the amount of $729,144.00 (10%).  
 
Background 
 
Hohokam Stadium and Fitch Park are actively used by Major League Baseball’s Athletics 
and the Parks, Recreation, and Community Facilities Department throughout the year. 
This project addresses the City’s contractual obligations under the 2013 Facility Use 
Agreement for “Scheduled Capital Improvements”. The project includes renovating 
underutilized spaces in Hohokam Stadium for new and updated facilities including sports 
medicine facilities with associated equipment, locker room improvements and updates to 
the team dining area. At Fitch Park the hitting/pitching lab will be expanded to add two 
new lanes.  
 
Discussion 
 
In October 2025 Staff received five (5) “Statements of Qualifications” (SOQ) from 
contractors proposing to act as the CMAR for this project. Based on an evaluation of 
these SOQ’s, Mortenson Construction was recommended as the most qualified CMAR 
and was awarded a pre-construction services contract on January 8, 2026. Mortenson 
Construction has performed pre-construction services during the design development

2
including reviewing the design for constructability, preparing cost estimates, and 
developing the project schedule and phasing.  
 
Community Impact – This project will limit use of the facility during construction but has 
been scheduled around Spring Training events, but will impact normally scheduled event 
managed by Parks, Recreation, and Community Facilities between Spring Training 
Events.  
 
Once underway, construction of this project is anticipated to last no more than 10 months.  
 
Alternatives 
 
An alternative to the approval of this Construction Services contract for the selected 
CMAR would be to construct this project using the traditional Design/Bid/Build method.  
This is not recommended due to the need for the additional services provided by a CMAR 
contractor during the design phase.  The proposed Hohokam Stadium and Fitch Park 
Improvements project required extensive on-site investigation, phasing, construction 
sequencing, constructability analysis, and coordination with the City and Athletics by the 
contractor throughout the design phase and through construction. 
 
Not completing the projects places the City in a position of not complying with it’s 
obligations under the mutually agreed upon Facility Use Agreement.   
 
Fiscal Impact 
 
The total authorized amount recommended for this project is $8,020,582.00, based on a 
GMP of $7,291,438.00 plus an additional $729,144.00 (10%) as a change order 
allowance. This allowance will only be utilized for approved change orders.  
 
This project is funded by the capital budget. 
 
   
Coordinated With 
 
The City Manager’s Office and Parks, Recreation and Community Facilities Department 
concur with this recommendation.