Pecos Road Relief Sewer Line City Council Study Session May 14, 2026 Lance Webb, City Engineer Tamar Robinson, Real Estate Specialist II Project Background: A 36-inch diameter relief sewer line in Pecos Road 3,395 LF Sewer Line installed in Pecos Road from west of the Roosevelt Water Conservation District Canal to Power Road The Project is planned in accordance with the 2018 Wastewater Master Plan Supports existing infrastructure and increases capacity for development at the ASU Polytechnic Campus Alleviate load on existing system Pecos Road Relief Sewer Line Project limits from East Maricopa Floodway to Power Road Construction begins Fall of 2026 423 SF Sewer Line Easement required on the commercial property Within an existing SRP High Voltage Easement Property is zoned GC- General Commercial, Town of Gilbert Easement Location February 2026-The property owner declined the original offer. April 2026-third-party appraisal completed new offer provided to the owner. Owner requested an alternative to acquiring the easement. Easement Negotiations Requires multiple 30+-foot-deep manholes to be installed Each additional manhole requires additional future maintenance costs Limits capacity for future development Excessive construction costs ALTERNATE DESIGN PROPOSED DESIGN • Seeking authority to use Eminent Domain for acquisition of a Sewer Line Easement • Just Compensation-Property was appraised by third party appraiser • Property owner was provided the appraised offer and attempts to negotiate with the owner are continuing Continuing Acquisition of the Easement Seeking eminent domain authority Questions