City Council Report 
 
Date:  
April 20, 2026 
To: 
 
City Council 
Through: 
Marc Heirshberg, Assistant City Manager  
 
From:  
Joseph Giudice, Water Resources Director 
 
 
 
Subject: 
SRP-CAP Interconnection Facility (SCIF) Downstream Impact Study 
Intergovernmental Agreement 
 
 
Citywide 
 
Purpose and Recommendation 
 
The purpose of this report is to request authorization to enter into an 
Intergovernmental Agreement (IGA) with the Town of Gilbert and the city of Chandler 
to engage WaterWorks Engineers to study the potential effects of the Salt River 
Project (SRP) Central Arizona Project (CAP Interconnection Facility (SCIF) on 
downstream users. For downstream users, this study will demonstrate impacts to 
water treatment facilities infrastructure and operational parameters. 
 
Staff recommends approval. The Town of Gilbert is scheduled to consider this IGA at 
their council meeting on April 7, 2026, and the City of Chandler is scheduled to 
consider this IGA at their council meeting on April 6, 2026. 
 
Background 
 
The Salt River Project (SRP)/Central Arizona Project (CAP) Interconnection Facility 
(SCIF) project aims to enable SRP water to be pumped into the CAP canal. The 
SCIF would allow the use of existing infrastructure and provide operational flexibility 
for two of the largest water providers in Arizona. If implemented, the SCIF would 
allow water stored in SRP reservoirs to be transported to customers with water 
treatment plants outside SRP’s service territory. Mesa, in cooperation with the Town 
of Gilbert and the City of Chandler, is undertaking this study collaboratively to 
leverage cost efficiencies and shared technical resources due to the cities’ close 
proximity to the SCIF. The Town of Gilbert is acting as the lead agency for this study. 
 
Discussion 
 
The SRP delivers water to the City of Mesa and other downstream users through the 
SRP canal delivery system from the Salt River and Verde River watershed. The CAP 
delivers water to the City of Mesa and other downstream users through the CAP 
canal system from the Colorado River watershed. To improve the ability of Mesa and 
other downstream users to move water more effectively to their respective water 
treatment facilities, SRP and CAP are evaluating a project to build a canal and pump 
system that connects their two separate canal systems through a project entitled the 
SCIF. Water quality from the two different water systems differs, therefore this study

2
is being commissioned by the three municipalities to evaluate and understand how 
this project will affect the infrastructure and operations at individual water treatment 
facilities. The City of Mesa is evaluating for water treatment impacts at its Brown 
Road Facility and Signal Butte Facility. 
 
Alternatives 
 
The Council could choose to take no action. This alternative is not recommended as 
it would require the city of Mesa to be reactive to water quality changes after 
implementation of the SCIF project is complete. This could risk damage to 
infrastructure, poor water quality and the potential for water quality violations from the 
Brown Road and Signal Butte water treatment facilities. 
 
Another alternative is to not sign the agreement and have Mesa conduct its own 
downstream impact study on just the Brown Road Water Treatment Plant, and the 
Signal Butte Water Treatment Plant.  Under this alternative, the City of Mesa would 
bear the full cost of the study rather than sharing the cost with two other cities. 
 
Fiscal Impact 
 
The total cost of the study is $145,840, which will be split evenly amongst the three 
cities.  Funding is available in the Utility Fund.