CPA2023014 BOS REPORT_PART5.PDF

Maricopa County — Formal (2023-12-06)

View PDF Item 22 Meeting page

Extracted text (via pymupdf) 26462 characters
77
WHITE TANK GRAND AVENUE AREA PLAN   |   MARICOPA COUNTY
Figure 24.	Water and Sewer Service Area

78	
CHAPTER 3: PLAN ELEMENTS
Water Resources Analysis 
As future development occurs in the WTGA planning area, 
special consideration must be taken to properly manage 
existing water resources and plan for anticipated water 
resources into the future. These considerations include 
proper land use planning to provide residential, industrial, 
and commercial customers with safe and reliable water 
supplies. Partnerships between municipal and private 
water providers are critical to implement management 
plans for both water consumption and conservation. 
Feedback from residents in the area demonstrated 
that there are concerns about the availability of water 
for existing residents and for future development. The 
recent reduction in water allocated from the Colorado 
River and findings presented in the Phoenix AMA water 
model will have an impact on cities, towns, and private 
water suppliers looking to expand. However, there is still 
a need to identify and supplement non-groundwater 
water rights and the shortage does not negate the need 
to plan for responsible growth and development as the 
WTGA planning area develops.
WATER RESOURCES 
OPPORTUNITIES
A large portion of the WTGA planning area 
does not have infrastructure or service for 
water and sewer. 
Development will be impacted in areas north 
and west of Loop 303 due to lack of assured 
water and limited infrastructure. Unless 
water and sewer service boundaries are 
expanded to the northwest or southeast of 
Wickenburg, future development will likely 
occur at densities that can be supported by 
private wells and septic systems.

79
WHITE TANK GRAND AVENUE AREA PLAN   |   MARICOPA COUNTY
The increase in water usage would not be evenly 
distributed throughout the WTGA planning area. Figure 
25 on page 80 shows the potential relative changes in 
water consumption based on the difference between 
existing land uses and the Future Land Use Map. Notable 
geographical changes in water use include:
	»
The most intense increases in water needs would 
be at the nodes of Regional Commercial and Mixed-
Use Employment located along Loop 303 and east of 
LAFB. These areas are already largely within water 
and sewer distribution systems with infrastructure.
	»
Large areas of increasing water needs are located 
around the White Tank Mountain Regional Park, the 
unincorporated areas on either side of 163rd Avenue 
north of US 60, and potentially the non-residential 
uses that would surround the Luke Auxiliary Field #1 
Airfield. Major investments in water and wastewater 
infrastructure would be needed before growth could 
occur in these areas.
	»
The large areas of rural residential in the 
northwestern reaches of the WTGA planning area 
would have minimal increases in water and sewer 
needs. Wastewater would likely be accommodated 
through personal septic systems.
	»
There is a reduction in water use anticipated as 
agricultural land surrounding LAFB develops into 
commercial or industrial development that is less 
water intensive.
	»
Most of the increased water need falls within the 
MPAs of WTGA planning area jurisdictions, including 
Surprise and Peoria. As annexation occurs, the water 
to serve growth would need to be identified with 
these jurisdictions and connections to municipal 
water systems would be required at that time. Rural 
development in unincorporated Maricopa County 
would continue to be served by private wells.
	»
There would be a proportional increase in the 
demand of sewer capacity for fresh water. Greywater 
reclamation could serve a dual benefit of reducing 
sewer capacity needs and help reduce the use of 
fresh water for landscaping or agricultural irrigation. 
Rainwater harvesting could further reduce the need 
for fresh water for landscaping.
Map of Phoenix Active 
Management Area (AMA), 
ADWR

80	
CHAPTER 3: PLAN ELEMENTS
Figure 25.	Forecasted Change in Water Usage
Note: Water usage rates per acre by land use were taken 
from the 2022 City of Surprise Integrated Water Master 
Plan and applied to a comparison between the existing 
land use map and future land use map to show where 
water usage could increase or decrease over time.

81
WHITE TANK GRAND AVENUE AREA PLAN   |   MARICOPA COUNTY
Water Resources Goal #1: 
Balance water availability with growth.
Water Resources Goal #2:
Support efforts to improve regional cooperation and 
communication on water use among WTGA planning 
area jurisdictions.
Water Resources Goal #3 
Increase renewable water use and reduce demand 
through water conservation.
Water Resources Goal #4
Continue to invest in best management practices of 
stormwater to ensure health and safety of residents. 
Water Resources Policy #1
Maricopa County supports appropriately scaled water 
service in potential growth areas that are not currently 
covered by a Community Water System.
Water Resources Policy #2
Maricopa County supports appropriately scaled sewer 
service, greywater reclamation, and rainwater harvesting 
efforts in potential growth areas that are not currently 
covered by existing sewer infrastructure or providers.
Water Resources Policy #3
Maricopa County supports appropriate fees, development 
requirements, and other funding mechanisms to ensure 
that new development pays its fair share of providing 
new services in potential growth areas, such as potable 
water, wastewater, and stormwater drainage. 
Water Resources Policy #4
Maricopa County supports the collaboration of WTGA 
planning area jurisdictions for water planning and 
conservation efforts, particularly during the annexation 
process to accommodate growth that is compliant with 
the Future Land Use Map.
Water Resources Policy #5
Maricopa County supports minimizing water usage 
by new public facilities in the WTGA planning area, 
including on landscaping, parks, artificial lakes, and 
decorative water features through low water use and 
drought tolerant landscaping to mitigate the forecasted 
water availability shortfall.
Water Resources Policy #6
Maricopa County supports the maintenance and 
expansion of major stormwater drainage facilities within 
the WTGA planning area, in partnership with the MCFCD, 
to accommodate the needs of existing and planned 
development to accommodate stormwater that cannot 
be retained in developments in potential growth areas 
and for emergencies.
WATER RESOURCES GOALS AND POLICIES
The following goals and policies are identified to aid in ensuring the water and sewer infrastructure in the WTGA 
planning area can support future development, as planned in the Future Land Use Map.

82	
CHAPTER 3: PLAN ELEMENTS
ENERGY, UTILITIES, & PUBLIC FACILITIES 
ELEMENT
The Energy Element is required by ARS and addresses incentives for efficient use of 
energy and policies and practices for greater use of renewable energy. Additionally, 
this section addresses other utilities and facilities within the WTGA planning area.
Energy and Utilities
The entirety of the WTGA planning area is served by Arizona Public Service (APS) 
for electricity service and Southwest Gas for natural gas service. As the area 
develops, consideration of energy needs is important to sustain the population. 
Because of the existing development profile of the area, energy use is relatively 
low compared to more urbanized areas of Maricopa County. According to the 
U.S. Energy Information Administration, major power infrastructure in the WTGA 
planning area includes:
1.	 Northwest Regional Plant Landfill Gas-to-Energy Plant. Landfill gas is collected 
through wells installed within the landfill to generate up to 3.2 megawatts of 
electricity.
2.	 LAFB Solar Array. This solar installation covers 106 acres of LAFB land and 
generates 15 megawatts of electricity. Typically, LAFB uses 100% of the energy 
produced by the array.
3.	 El Sol Battery Energy Center (currently under construction). This facility is a 
battery electric storage system (BESS), which stores excess power generated 
during off-peak times to supplement the power supply during peak times. The 
facility will be able to handle 200 megawatt-hours of excess power storage.
LAFB Solar Array, LAFB

83
WHITE TANK GRAND AVENUE AREA PLAN   |   MARICOPA COUNTY
ENERGY, UTILITIES, & FACILITIES OPPORTUNITIES
	»
Most public facilities are east of Loop 303, in incorporated areas. Additional police or Maricopa County 
Sheriff’s Office (MCSO) stations, fire stations, and schools west of Loop 202 would be necessary as 
the areas continue to grow. 
	»
Due to the potential for solar energy generation, Maricopa County can encourage additional renewable 
energy generation in appropriate locations in the WTGA planning area.
With the Phoenix region experiencing more and more 
days of extreme heat, electricity capacity is being 
increasingly stretched, according to APS. On July 15, 
2023, APS broke its all-time record for the maximum 
amount of electricity consumed at once, 8,191 
megawatts. Accommodating additional clean energy 
production in the WTGA planning area will contribute to 
the area’s ability to provide enough power during peak 
times.
There are three landfills and waste transfer centers 
in the WTGA planning area. The Northwest Regional 
Landfill is located along Deer Valley Road, west of US 60. 
The Morristown Waste Disposal and Recycling Center is 
located southeast of the US 60 and SR 74. The Goodyear 
White Tank Hauling and Transfer Station is located on 
McDowell Road, east of Jackrabbit Trail. Figure 26 on 
page 84 shows solid waste facilities in the area. There 
is also a planned waste transfer station near El Mirage 
Rd. & the 303.
Public Facilities
There are a variety of public facilities in the WTGA 
planning area, including police, fire, education, and 
parks. 
Police services for the area is served by the MCSO, 
Avondale 
Police 
Department, 
Buckeye 
Police 
Department, El Mirage Police Department, Glendale 
Police Department, Goodyear Police Department, 
Peoria Police Department, and City of Surprise Police 
Department. The Maricopa County Sheriff’s Office 
(MCSO) has two stations in the WTGA planning area, 
both along US 60. Currently, average response times for 
MCSO beats within the area are ranging from 10 to 34 
minutes for priority 1 (the most urgent) calls, 9 minutes 
to over 1 hour for priority 2 calls, and five minutes to over 
an hour for priority 3 calls.  
There are twenty-two (22) fire stations in the WTGA 
planning area. Fire protection is provided by Rural Metro, 
City of Surprise Fire-Medical Department, El Mirage Fire 
Department, Sun City Fire and Medical Department, 
Peoria Fire Department, Wittman Fire District, Arizona 
Fire and Medical Authority, and Circle City/ Morristown 
Fire Department. On average, each fire station in the 
plan boundary serves 33 square miles. 
There are eighteen K-12 schools and one post-secondary 
campus (Ottawa University) in the WTGA planning area. 
School districts in the area include:
	»
Agua Fria Union High School
	»
Dysart Unified #89
	»
Liberty #25
	»
Litchfield #79
	»
Morristown #75
	»
Nadaburg Unified #8
	»
Pendergast #92
	»
Peoria #11
	»
Peoria Unified High School
	»
Saddle Mountain Unified #90
	»
Tolleson Unified High School
	»
Wickenburg Unified #9 
The existing educational facilities are primarily located 
east of Loop 303. The average age of school facilities 
is 20 years and the average enrollment for elementary, 
middle, and high schools are 655, 1,755, and 2,300, 
respectively. Public facilities are shown in Figure 26 on 
page 84. 
Sun City Fire and Medical Station, Perlman Architects

84	
CHAPTER 3: PLAN ELEMENTS
Figure 26.	Public Facilities and Utilities

85
WHITE TANK GRAND AVENUE AREA PLAN   |   MARICOPA COUNTY
Energy, Utilities, and Public Facilities Analysis
Energy and Utilities
As future development occurs in the WTGA planning 
area, expansion of the electric and gas infrastructure will 
be needed to accommodate growth. Figure 27 shows 
locations that are identified as potential growth areas 
or where the Future Land Use Map shows that major 
land use changes could occur, resulting in urbanization. 
These areas include the growth areas along the US 
60 corridor southeast of SR 74 and west of Loop 303 
between Indian School Road and Peoria Avenue, the 
land surrounding the White Tank Mountain Regional 
Park, and either side of 163rd Avenue north of US 60. 
Public Facilities
Ensuring public services maintain their current high 
level of service and adequate response times as the 
area grows is an important and often life-saving goal 
of WTGA planning area residents and stakeholders. 
As development expands into currently vacant land, 
additional fire, police, and educational facilities will be 
needed to support the population. 
The table below shows the number of existing public 
facilities in the two growth areas in identified the Future 
Land Use Map. 
POTENTIAL GROWTH AREAS
FIRE
POLICE
SCHOOL
A. US 60 CORRIDOR SOUTHEAST OF SR 74 
3
0
2
B. WEST OF SR 303 BETWEEN INDIAN SCHOOL AND PEORIA
0
0
0
Areas that are expecting land use changes, shown in blue 
in Figure 27 on page 86, have the potential for increases in 
density before the horizon year of this plan. Many of these 
areas do not have any fire coverage. While these areas 
are unlikely to develop before the identified growth areas, 
they have very limited public facilities in proximity. The 
potential growth surrounding the White Tank Mountain 
Regional Park will require additional public facilities, as 
the area west of the park will be secluded from existing 
development to the east. Additional public facilities will 
also be needed as development occurs along either side 
of 163rd Avenue north of US 60.
Maricopa County Sheriff’s Office, MCSO

86	
CHAPTER 3: PLAN ELEMENTS
Figure 27.	 Future Utility and Facility Needs

87
WHITE TANK GRAND AVENUE AREA PLAN   |   MARICOPA COUNTY
Energy, Utilities, and Public Facilities Goal 
#1
Ensure Maricopa County has adequate infrastructure to 
accommodate utilities and waste disposal before growth 
is permitted in unincorporated areas or encourage 
annexation into WTGA planning area jurisdictions.
Energy, Utilities, and Public Facilities Goal 
#2
Ensure there are adequate public facilities, including 
police, fire, and educational coverage, before growth 
is permitted in unincorporated areas and encourage 
annexation into WTGA planning area jurisdictions.
Energy, Utilities, and Public Facilities Goal 
#3
Remain a leader in alternative energy research and 
development.
Energy, Utilities, and Public Facilities Goal 
#4
Ensure that development adjacent to electrical, gas, 
and other utility corridors is context appropriate and 
environmentally responsible.
Energy, Utilities, and Public Facilities Policy 
#1
Maricopa County supports municipal annexation of a 
development site when urban services are available or 
relatively available in accordance with the Maricopa 
County Comprehensive Plan policy on Urban Services 
for Urban Development.
Energy, Utilities, and Public Facilities Policy 
#2
Maricopa County supports planning for residential, 
commercial, and employment land uses in potential 
growth areas that are proximate to each other rather than 
separated to reduce fuel usage, energy consumption, 
and wear and tear on roads. 
Energy, Utilities, and Public Facilities Policy 
#3
Maricopa 
County 
supports 
intergovernmental 
coordination for the development and implementation 
of strategic energy planning with WTGA planning area 
jurisdictions.
Energy, Utilities, and Public Facilities Policy 
#4
Where feasible and effective, Maricopa County supports 
cooperation with developers to integrate public facilities, 
such as schools and libraries, into neighborhoods rather 
than having them physically separated and located 
on major arterial roadways. Where feasible, joint use 
facilities, such as swimming pools and playgrounds, 
should be incorporated into schools and libraries.
Energy, Utilities, and Public Facilities Policy 
#5
Maricopa County supports partnering with jurisdictions 
in the WTGA planning area and the private sector to 
develop and maintain an integrated approach to solid 
waste management.
Energy, Utilities, and Public Facilities Policy 
#6
Maricopa County supports the development of renewable 
energy generation with safe distancing requirements to 
prevent fire hazards at BESS facilities.
ENERGY, UTILITIES, AND PUBLIC FACILITIES GOALS AND POLICIES
The following goals and policies are identified to aid in improving utilities and facilities as well as incentivizing the 
use of renewable energy for residents and visitors of the WTGA planning area.

88	
CHAPTER 3: PLAN ELEMENTS
COST OF DEVELOPMENT ELEMENT
The Cost of Development Element is required by ARS and identifies policies and 
strategies that the County will use to require development to pay its fair share 
toward the cost of additional public service needs generated by new development. 
This section will also identify various mechanisms that are allowed by law and 
can be used to fund and finance additional public services necessary to serve 
developments.  Policies specifically ensure that any mechanisms that are adopted 
by the County result in a beneficial use to development and bear a reasonable 
relationship to the burden imposed on the County to provide the additional 
necessary public services.
Cost of Development
In fast growing areas, capital infrastructure is needed to provide services and 
infrastructure to new residential and commercial developments. Some of the 
funding mechanisms that are allowed by Arizona law include bonding, special 
taxing districts, development impact fees (DIFs), in-lieu fees, facility construction, 
dedications, and service privatization. This section addresses important cost of 
development issues by stressing that new development pay its proportionate share 
of improvements and services without burdening existing taxpayers.  Its important 
to recognize the County does not provide utility services within its jurisdiction 
and relies on the municipalities and private companies to provide these services. 
The County has not adopted development impact fees for non-utility services, 
one of the primary financing tools available to local jurisdictions. The County, 
however, through cooperation with WTGA planning area municipalities, maintains 
the ability to negotiate development agreements and stipulations related to new 
developments that may affect the road system, the area’s floodplains, and other 
services.  
WTGA Service Providers
The WTGA planning area has a large mix of public and private service providers 
and regulatory authorities that include, in addition to Maricopa County, parts of 
eight cities and nine private utility companies.  The number of public and private 
service providers in the WTGA planning area creates a complex maze of fees and 
regulations that developers must negotiate. Maricopa County’s unincorporated 
areas account for a majority of the WTGA planning area. Maricopa County does 
not operate any utility systems and does not impose DIFs on new development. 
Service Providers in WTGA Plan Area
Public Entities
Private Entities 
Maricopa County
Arizona Water Company 
City of Buckeye 
Beardsley Water Company 
City of El Mirage
Brooks Water Utilities 
City of Glendale 
Chaparral Water Company 
City of Goodyear 
Circle City Water Company 
City of Litchfield Park 
EPCOR 
City of Peoria 
Liberty Utilities

89
WHITE TANK GRAND AVENUE AREA PLAN   |   MARICOPA COUNTY
However, it still has regulatory authority through zoning 
and over improvements to the county road system and 
floodplain areas.
Most cities use a wide variety of tools to accommodate 
new developments including development impact fees, 
improvement districts, community facilities districts 
(CFDs), development agreements, and dedication of 
facilities and streets improvements. Five of the cities in 
the area also operate their own water and wastewater 
utility systems in addition to the nine private utility 
companies operating in the area. Most cities also 
impose development impact fees on new development 
for a variety of services and utilities including water, 
sewer, and in some cases, future water resource needs. 
Large private utility providers also require impact fees or 
“hook-up” fees for new water and sewer services while 
smaller utility companies do not charge the fees. 
Cost of Development Analysis
Maricopa County prefers new development projects in 
the WTGA planning area to annex to one of the local 
municipalities.  However, the lack of impact fees in the 
unincorporated areas often causes developers to seek 
zoning through the County rather than the municipality 
and to obtain utility service from one of the private 
utility companies operating in the area. Further, the 
strip annexation of land between Camelback Road and 
Peoria Avenue by Glendale many years ago has led to the 
expansion of service areas by private utility companies. 
EPCOR and Liberty Utilities have since become the 
primary utility providers in much of the WTGA planning 
area. This has at times thwarted the annexation of 
development projects into nearby cities, leaving them 
under the purview of Maricopa County.     
Maricopa County is rightly concerned with the financial 
impacts that new development can have on the County 
and on local governments and taxpayers.  This section 
identifies techniques and methods that the County can 
use to fund additional public services generated from 
new development. The County’s Comprehensive Plan 
provides a discussion of funding methods that are 
specific to funding improvements for new development. 
The methods that are relevant to the WGTA planning 
area and supported by the County include: 
	»
Development agreements for master planned 
communities.
	»
Community improvement districts on a limited basis 
where specific public improvements are considered 
necessary.
	»
Intergovernmental 
agreements 
(IGAs) 
with 
municipalities 
to 
help 
share 
infrastructure 
improvement costs.
	»
Fee for service requirements to ensure the recovery 
of the cost of services in a way that does not unfairly 
burden those most in need of such services.  
While multiple municipalities are included with the 
boundaries of the WTGA Area Plan, this section is only 
intended to apply to new developments that are seeking 
rezoning in the County or are subject to the County’s 
policies and regulations. In most cases, the County 
prefers that new development projects annex into a 
municipality prior to seeking zoning through the County 
and most cities require annexation as a condition of 
providing utility services to a development project. The 
goals and policies that follow are designed to outline 
the County’s position on the important financial equity 
issue that new development pays its proportionate 
share of improvements and services without burdening 
existing taxpayers. The goals and policies recognize 
the County does not provide utility services within its 
jurisdiction and relies on cities, towns, and private 
companies to provide these services.  The County has 
also not adopted development impact fees for non-utility 
services, one of the primary financing tools available to 
local jurisdictions.

90	
CHAPTER 3: PLAN ELEMENTS
Cost of Development Goal #1: 
Implement policies and procedures that require new 
development to pay its fair share of public infrastructure 
needs generated by the development.
Cost of Development Goal #2: 
Encourage the annexation of new development projects 
to neighboring municipalities to promote more efficient 
development patterns within the WTGA planning area.
Cost of Development Goal #3: 
Plan for the continued funding of new and existing 
facilities and services such as highways and roads, 
public safety, parks, and other community needs within 
the WTGA Planning Area.  
Cost of Development Policy #1:
In the WTGA planning area, Maricopa County supports 
cooperative relationships with municipalities in the 
review of new development projects that may impact 
municipal facilities and services. 
Cost of Development Policy #2:
Where feasible and effective, Maricopa County supports 
using all tools at the County’s disposal including 
development agreements, community improvement 
districts, intergovernmental agreements, and fee for 
service charges to ensure new development pays its fair 
share of infrastructure costs.
Cost of Development Policy #3:
In the WTGA planning area, Maricopa County supports 
working cooperatively with municipalities to align 
projects that address regional issues. 
Cost of Development Policy #4:
Maricopa County supports coordination with utility 
service providers to ensure ongoing and timely notice of 
proposed projects or newly approved projects.
Cost of Development Policy #5:
Maricopa County supports continued planning of future 
growth trends and patterns in the WTGA planning area 
and analysis of the impact on County services.
Cost of Development Policy #6:
Where feasible and effective, Maricopa County supports 
the development of capital improvement plans through 
applicable County departments and other area entities 
that address ongoing infrastructure and service needs 
within the WTGA planning area.
COST OF DEVELOPMENT GOALS AND POLICIES
The following goals and policies are identified to address the cost of development in the WTGA planning area.
Loop 303 I-10 Interchange, ADOT

91
WHITE TANK GRAND AVENUE AREA PLAN   |   MARICOPA COUNTY
THIS PAGE IS INTENTIONALLY LEFT BLANK

» Appendix A: 
	» Appendix B: 
	» Appendix C: 
92	
APPENDICES
Appendices
	» Appendix A: 2000 WTGA Land Uses
	» Appendix B: Community Outreach Materials
	» Appendix C: Development Master Plans (DMPs)
	» Appendix D: Glossary
APPENDICES

93
WHITE TANK GRAND AVENUE AREA PLAN   |   MARICOPA COUNTY
Add Appendices Overview Here
“Transparency does not only 
encompass the mere access to 
information, but also entitlement 
to openness of procedures or even 
outcomes of planning processes 
and their implementation.”
- Jan Polívka and Christa Reicher

94	
APPENDIX A: 2000 WTGA LAND USES
APPENDIX A:  2000 WTGA LAND USES
The following map depicts the future land uses within the WTGA planning area, based both on 2000 WTGA Area Plan 
boundary and/or the comprehensive plan.