Council Report

City of Mesa — City Council (2026-02-09)

View PDF Meeting page

Extracted text (via pymupdf) 2677 characters
City Council Report 
 
Date:  
February 9, 2026 
To: 
 
City Council 
Through: 
Marc Heirshberg, Assistant City Manager 
From:  
Lance Webb, City Engineer 
Marc Ahlstrom, Assistant City Engineer 
 
Subject: 
Arizona Farms Road High Pressure Gas Line Replacement 
 
 
City Project No. CP0517GAS 
Citywide 
 
 
Purpose and Recommendation 
 
The purpose of this report is to provide information to Council concerning the results of 
the bids received for the Arizona Farms Road High Pressure Gas Line Replacement 
project (See Exhibit “A” for the project location).   
 
Staff recommend that Council award a contract for this project to the lowest responsible 
bidder, Arizona Pipeline Company, in the amount of $5,598,357.15, and authorize a 
change order allowance in the amount of $559,835.72 (10%). 
 
Background 
 
The proposed project will replace approximately 26,000 linear feet (4.9 miles) of a 4-inch 
high-pressure steel gas line installed in the 1960’s with a 12-inch diameter high-pressure 
steel gas line. The project will support system redundancy, and continuing growth within 
the Magma Gas System service area in Pinal County. 
 
Discussion 
 
The pipe replacement project begins at the intersection of Arizona Farms Rd and Attaway 
Road and runs easterly on Arizona Farms Road to the existing Clausen Gate near to 
Cumberland Road. Permits for the construction of this project have been received from 
the Town of Florence and Pinal County. The construction method will utilize the 
combination of open trench method and directional bore. Once underway, construction of 
this project is anticipated to last no more than 8 months.

2
Alternatives 
 
An alternative to this project would be to not construct these improvements. This is not 
recommended due to the need to provide the gas service to existing and future customers 
in Pinal County, Southeast Mesa and Queen Creek. 
 
Fiscal Impact 
 
The total authorized amount recommended for this project is $6,158,192.87, based upon 
the lowest responsible bid of $5,598,357.15, plus an additional $559,835.72 (10%) as a 
change order allowance.  This change order allowance will only be utilized for approved 
change orders.   
 
This project is funded by Utility Systems Revenue Obligations. 
 
Coordinated With 
 
The Energy Resources Department concurs with this recommendation

3
CITY OF MESA 
MESA, ARIZONA 
 
ARIZONA FARMS ROAD HIGH PRESSURE GAS LINE REPLACEMENT 
 
PROJECT NO.  CP0517GAS 
 
Tabulation of Bids Received, Thursday, December 18th, 2025, at 1:00 PM. 
 
 
ENGINEER’S ESTIMATE 
$8,414,339.05 
 
1. ARIZONA PIPELINE COMPANY 
$5,598,357.15 
 
2. WESTERN INDUSTRIAL RESOURCES CORP 
$8,734,773.67