PUBLIC WORKS CAPITAL IMPROVEMENT &
STREET MAINTENANCE PLAN
FISCAL YEAR 2026-2027
DATE: June 15, 2026
Objectives
➢ 2026 Street Inventory update
➢Overview of FY27 Public Works
Capital Improvement and Street
Maintenance Plan
▪Capital Maintenance Projs. and
New Construction
▪ Projects and Timeframes
➢ Council Discussion/Q&A
Radiance Subdivision
- fog seal May 2026
Street Pavements: Street Rating
Cactus/Auto Center Dr. – Rehabilitation November 2025
Remaining Service Life (RSL)
RSL: 0
RSL: 20
Street Inventory Condition
Broadway Ave. and
Superstition Blvd
- March 2026
1. Goal: > 12-14 average RSL total inventory
▪
Current RSL 13.62, from 14.05 last year
2. Goal: < 5% percent of streets in poor or
worse condition
▪
Currently at 4.0%, from 7% last year
3. Goal: > 70% total inventory in Good to
Excellent Condition
▪
Currently at 72%, up from 70%
FY 2027 CIP & Street
Maintenance Plan
Legend:
FY 2027 CIP & Street
Maintenance Plan
Legend:
FY 2027 Street Maintenance Plan
• Project:
Timeframe:
▪Crack seal
Fall thru Winter 2026/27
▪Fog seal
Spring 2027
▪Slurry seal
Spring 2027
▪Chip seal (rural roads)
Spring 2027
Preservation Maintenance
FY 2027 Street Maintenance Plan (continued)
• Project:
Timeframe:
▪ Old West Highway, Idaho Rd. to
Fall 2026
Tomahawk Rd.
▪ S. Ironwood Dr., Elliot Ave. to Guadelupe Ave. Fall 2026
- Northbound lanes
Rehabilitation (Pavement Overlay)
FY 2027 Street Maintenance Plan (continued)
Reconstruction
• Project:
Timeframe:
▪Lost Dutchman Blvd., Ph. 4 Reconstruction Fall/Winter 2026/27
- Meridian Dr. to Ironwood Dr.
FY 2027 Public Works CIP Plan
Construction:
▪ Delaware Dr./Southern Ave. New Traffic Signal Installation
▪ Ironwood Dr./Baseline Ave. Traffic Signal Improvement
▪ Southern Ave. and Tomahawk Rd. Street and Drainage Improvement
▪ Idaho Rd. and Superstition Blvd. Sidewalk Improvement
▪ Apache Villas Subdivision Sidewalk Ramp Improvements
▪ Meridian Dr./Southern Ave. Drainage Channel Improvements
▪ Traffic Signal Fiber Optic Improvements
Capital Improvement Projects (CIP)
FY 2027 Public Works CIP Plan
• Designs/Studies:
▪ Weekes Wash Regional Detention Design
▪ Tomahawk Rd. Improvements, Southern Ave. to Old West Highway
Design
▪ Public Works/Water Expansion, Complete Design and Start Construction
▪ Complete Engineering Standards Update
▪ Update 2006 Stormwater Master Plan
Capital Improvement Projects (CIP)
FY 2027 Street Capital Improvement &
Maintenance Plan
Questions?
Apache Trail Median Curbs, Phase 5
– July 2025