City of Chandler Job Order Project Agreement 
A-1 
Public Works & Utilities Department, Capital Projects Division  
Project Name: AIRPORT WATER RECLAMATION FACILITY HEADWORKS DRAIN PIPING 
Project No.: WW2003.401 
Rev. 9/18/2020 
 
 
CITY OF CHANDLER 
JOB ORDER PROJECT AGREEMENT  
 
Project Name: AIRPORT WATER RECLAMATION FACILITY HEADWORKS DRAIN PIPING 
Project No. WW2003.401 
 
This JOB ORDER PROJECT AGREEMENT (”Job Order”) is made this ________ day of _________ 2021 (“Effective 
Date”), by and between the City of Chandler, an Arizona municipal corporation, (“City”) and Garney 
Companies, Inc., a Missouri corporation, (“JOC Contractor”) and is entered into pursuant to Job Order 
Master Agreement No. JOC1914.401 (“JOC Master Agreement”). City and JOC Contractor may be referred to 
individually as “Party” or collectively as “Parties”). 
 
City and JOC Contractor, in consideration of the mutual covenants herein set forth, agree as follows:   
 
RECITALS 
 
A. On or about December 17, 2019, the Parties entered into the JOC Master Agreement, which terms and 
conditions are made a part of and incorporated into this Job Order Project Agreement by this reference. 
 
B. City proposes to engage JOC Contractor to provide headworks drain piping at the Airport Water 
Reclamation Facility as more fully described in Exhibit "A", which is attached to and made a part of this 
Job Order by this reference. 
 
C. JOC Contractor is ready, willing, and able to provide the services described in Exhibit “A” for the 
compensation and fees set forth and as described in Exhibit ”B”, which is attached to and made a part of 
this Agreement by this reference. 
 
ARTICLE 1.  DESCRIPTION OF WORK 
 
The Parties enter into this Job Order Project Agreement for the AIRPORT WATER RECLAMATION 
FACILITY HEADWORKS DRAIN PIPING, Project Number WW2003.401.  The scope of work consists of 
providing headworks drain piping at the Airport Water Reclamation Facility, all as more particularly set 
forth in Exhibit “A” attached hereto and incorporated herein by reference. 
 
The JOC Contractor will not accept any change of scope, or change in contract provisions, unless issued in 
writing, as a contract amendment or change order and signed by the authorized signatories for each 
party. 
 
Performance and Payment Bonds, as set forth in Exhibit “C” and Exhibit “D” respectively attached hereto 
and incorporated herein by reference, will be due prior to execution of each Job Order Project Agreement 
in the full amount of each Job Order.

City of Chandler Job Order Project Agreement 
A-1
Public Works & Utilities Department, Capital Projects Division  
Project Name: AIRPORT WATER RECLAMATION FACILITY HEADWORKS DRAIN PIPING 
Project No.: WW2003.401 
Rev. 9/18/2020 
At project completion, JOC Contractor must complete Contractor's Affidavit Regarding Settlement of 
Claims and Certificate of Completion, as set forth in Exhibit “E” and Exhibit “F” respectively attached 
hereto and incorporated herein by reference. 
ARTICLE 2.  PROJECT PRICE 
City will pay JOC Contractor for completion of the Work in accordance with the JOC Master Agreement a 
fee not to exceed the Guaranteed Maximum Price of $391,070 Dollars determined and payable as set 
forth in JOC Master Agreement and Exhibit “B” attached hereto and made a part hereof by reference.  
ARTICLE 3.  CONTRACT TIME & SCHEDULE 
JOC Contractor agrees to complete all Construction within 180 calendar days from the Notice to Proceed 
(NTP) Date.  
ARTICLE 4.  PARTICIPANTS 
CITY: 
Construction Project Manager:  Paul Ahlas 
Phone: 
480-782-3328
Email: 
paul.ahlas@chandleraz.gov 
JOC CONTRACTOR: 
Garney Companies, Inc. 
4435 E. Holmes Ave., Ste. 102 
Mesa, AZ  85206 
JOC Contractor Representative:  Shane O’Brien 
Phone: 
720-375-0988
Email: 
sobrien@garney.com 
SIGNATURE PAGE TO FOLLOW

Joel Heimbuck
Director of Operations
Assistant Secretary
3/10/2021

City of Chandler Job Order Project Agreement 
A-1
Public Works & Utilities Department, Capital Projects Division  
Project Name: AIRPORT WATER RECLAMATION FACILITY HEADWORKS DRAIN PIPING 
Project No.: WW2003.401 
Rev. 9/18/2020 
EXHIBIT A 
SCOPE OF WORK

4435 E. Holmes Ave, Suite 102, Mesa AZ 85206 
 
Phone: 602.470.0001 
 
Fax: 602.470.0025 
 
www.garney.com 
 
Page 1 of 1 
 
 
Exhibit A 
 
Scope 
JOC WW2003.401 – Airport WRF Headworks Drain 
 
 
 
1. JOC must perform the following project tasks per Brown and Caldwell plans and specs dated December 
22, 2020 and as modified below:  
a. Mobilize to site 
b. Excavate and Backfill new drain piping, tie-in into existing lift station and restore landscaping to 
existing condition. 
i. Proposal assumes that routing to be modified in the field based on existing 
pipe/supports impeding route. Garney to maintain adequate fall as necessary. 
ii. Proposal assumes that connecting drain lines can be offline during installation/tie-in and 
no temporary bypass pumping is included. 
iii. Proposal assumes use of ½ Sack CLSM in lieu of native backfill material. 
iv. Proposal assumes that existing drain line to be abandoned in place in lieu of removal. 
c. 
Investigate condition of existing pipe penetrations 
d. Temporary installation of Owner supplied stop logs and additional temporary bulkheads, 
nuisance pumping and cleaning of existing channel per the MOPO noted in the documents. 
i. Temporary bypass pumping of the plant influent is not included nor required. 
ii. OSHA safety standards require H2S to be at 5 PPM which is lower than current readings. 
Proposal includes standard push/pull fan system in order to obtain/maintain safe 
working levels. If standard fan system is not adequate to obtain/maintain safe working 
levels, Garney assumes that additional equipment and delays are to be paid by Owner’s 
Allowance. 
e. Demo and dispose of existing mud valves, pipe penetration, flanges, and appurtenances. 
i. Proposal assumes use of owner supplied stop logs to isolate headworks channels as 
needed. 
f. 
Demo/dispose existing exposed drain piping and install new exposed Drain Piping, mud valves, 
supports and penetrations as shown on the drawings 
i. Proposal includes the use/acceptance of Victaulic fittings and couplings in lieu of flange 
fittings. Grooved ends on straight pipe to be completed in the field. 
ii. Proposal includes painting the exterior pipe as needed. 
iii. Proposal includes use of Armorlok PVC liner boots as submitted by Sonco as the Ameron 
PVC T-Lock is no longer available. 
g. 
Install new SST drip tray and supports, 2” PVC drain piping, modify electrical Unistrut as 
necessary and wall coating 
h. Test Pipe as necessary  
2. Allowances included in this Proposal: City Allowance - $45,000 
3. Schedule is based on 3 months for procurement/delivery of material and 2 months for construction 
4. Specifically excluded from this proposal are: Building Permits, Engineering (including professional 
engineered design of pipe system and supports), remediation of contamination and hazardous material 
handling.

EXHIBIT B 
FEE SCHEDULE 
City of Chandler Job Order Project Agreement 
B-1
Public Works & Utilities Department, Capital Projects Division  
Project Name: AIRPORT WATER RECLAMATION FACILITY HEADWORKS DRAIN PIPING 
Project No.: WW2003.401 
Rev. 9/18/2020

4435 E. Holmes Ave, Suite 102, Mesa AZ 85206
Phone: 602.470.0001
Fax: 602.470.0025
www.garney.com
WW2003.401 AIRPORT WATER RECLAMATION FACILITY HEADWORKS DRAIN
Negotiated Prices
56,338
$
 
SUBTOTAL (NEGOTIATED PRICES):
56,338
$
 
Unit Prices
224,099
$
 
SUBTOTAL (NEGOTIATED PRICES):
224,099
$
 
0.08
22,435
$
 
SUBTOTAL (NEGOTIATED PRICES + OVERHEAD AND PROFIT):
302,872
$
 
Sales Tax Percentage (Current Tax Rate)
5.07%
15,356
$
 
General Liability Insurance Percentage (Actual Cost per Job Order)
1.35%
4,089
$
 
Builder's Risk Insurance Percentage (Actual Cost per Job Order)
0.343%
1,039
$
 
Payment Bond (Actual Cost per Job Order)
7.5%
22,715
$
 
Performance Bond (Actual Cost per Job Order)
included 
-
$
 
SUBTOTAL (INSURANCE, BONDS, & TAXES):
43,199
$
 
SUBTOTAL (NEGOTIATED PRICES + OVERHEAD AND PROFIT + INSURANCE, BONDS, & TAXES):
346,070
$
 
City's Allowance
45,000
$
 
TOTAL JOB ORDER:
391,070
$
 
Overhead and Profit (Coefficient per Job Order Master Agreement)
Insurance, Bonds, & Taxes
Per the Job Order Master Agreement - This Fee Table includes all fees, costs, insurance and bond premiums, allowances, 
construction contingency, and taxes of any type necessary to fully, propertly and timely perform and construct the Work.  Also per 
the Job Order Master Agreement - For any portion of the Work which, either through this Contract, Change Order or otherwise, is 
performed and paid for on a cost, or time and materials basis, the costs may be reimbursed to JOC Contractor and chargeable 
against the Contract Price will be determined as set forth in MAG 109.5.
Unit Price (Per Unit Price Attachment)
EXHIBIT "B-1"
Job Order Cost Proposal
Summary Sheet
General Conditions

4435 E. Holmes Ave, Suite 102, Mesa AZ 85206
Phone: 602.470.0001
Fax: 602.470.0025
www.garney.com
UNIT PRICE ATTACHMENT
No.
Description
Est. Qty.
Unit
Extended Price
1
Mobilization
1
LS
$                      7,921 
2
Piping Excavation and Backfill
1
LS
$                    28,407 
3
Landscaping/Gravel Replacement
1
LS
$                      3,695 
4
Investigate Existing Condition of Pipe Penetrations
1
LS
$                         557 
5
Demolish Drain Piping, Fittings, Couplings, Pipe 
Supports, and Appurtenances.
Provide Disposal of Demolished Materials
1
LS
$                    13,246 
6
Demolish Mud Valves, Pipe Penetrations, Flanges, 
and Appurtenances. Provide Disposal of 
Demolished Materials
1
LS
$                    13,723 
7
Purchase and Install Pipe Penetrations in Concrete 
Floor
1
LS
$                    11,302 
8
Purchase and Install Mud Valves, Pipe Boots, and 
Appurtenances
1
LS
$                    23,569 
9
Purchase and Install Exposed Pipe, Fittings 
Couplings, Flanges, and Appurtenances
1
LS
$                    90,464 
10
Purchase and Install Buried Pipe, Fittings 
Couplings, Flanges, and Appurtenances
1
LS
$                    14,505 
11
Purchase and Install Pipe Hangers/ Supports
1
LS
$                      5,316 
12
Purchase and Install Drip Tray and Appurtenances
1
LS
$                      5,039 
13
Testing
1
LS
$                      6,354 
$             5,039 
$             6,354 
BASE BID (Items 1- 13 inclusive)                                                  
$                                224,099 
(In Numbers)
$            13,723 
$            11,302 
$            23,569 
$            90,464 
$            14,505 
$             5,316 
Unit Price
$             7,921 
$            28,407 
$             3,695 
$                557 
$            13,246

EXHIBIT C 
 
City of Chandler Job Order Project Agreement 
C-1 
Public Works & Utilities Department, Capital Projects Division  
Project Name: AIRPORT WATER RECLAMATION FACILITY HEADWORKS DRAIN PIPING 
Project No.: WW2003.401 
Rev. 9/18/2020 
PERFORMANCE BOND 
ARIZONA STATUTORY PERFORMANCE BOND 
PURSUANT TO TITLES 28, 34, AND 41, ARIZONA REVISED STATUTES 
(Penalty of this bond must be 100% of the Contract amount) 
 
KNOW ALL MEN BY THESE PRESENTS THAT:___________________________________________________ 
(hereinafter "Principal"), and __________________________________________________________ (hereinafter "Surety"), a 
corporation organized and existing under the laws of the State of ______________ with its principal office in the City of 
_____________________________, holding a certificate of authority to transact surety business in Arizona issued by the 
Director of Insurance pursuant to Title 20, Chapter 2, Article 1, as Surety, are held and firmly bound unto 
__________________________(hereinafter "Obligee") in the amount of ________________________________________________ 
(Dollars) ($___________), for the payment whereof, Principal and Surety bind themselves, and their heirs, 
administrators, executors, successors and assigns, jointly and severally, firmly by these presents. 
 
WHEREAS, the Principal has entered into a certain written contract with the Obligee, dated  
 
the ____________ day of _______________________, 20___ for construction of AIRPORT WATER RECLAMATION FACILITY 
HEADWORKS DRAIN PIPING, WW2003.401 which contract is hereby referred to and made a part hereof as fully and 
to the same extent as if copies at length herein. 
 
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION IS SUCH, that if the Principal faithfully performs and 
fulfills all the undertakings, covenants, terms, conditions and agreements of the contract during the original term of 
the contract and any extension of the contract, with or without notice of the Surety, and during the life of any 
guaranty required under the contract, and also performs and fulfills all the undertakings, covenants, terms, 
conditions, and agreements of all duly authorized modifications of the contract that may hereafter be made, notice of 
which modifications to the Surety being hereby waived, the above obligation is void.  Otherwise it remains in full force 
and effect. 
 
PROVIDED, HOWEVER that this bond is executed pursuant to the provisions of Title 34, Chapter 2, Article 2, 
Arizona Revised Statutes, and all liabilities on this bond will be determined in accordance with the provisions of Title 
34, Chapter 2, Article 2, Arizona Revised Statutes, to the same extent as if it were copied at length in this Contract. 
 
The prevailing party in a suit on this bond may recover as part of the judgment reasonable attorney fees that 
may be fixed by a judge of the court. 
 
Witness our hands this ________________ day of ____________________, 20__. 
____________________________________ 
PRINCIPAL         
 
SEAL 
___________________________________ 
             AGENT OF RECORD 
By _________________________________ 
____________________________________ 
SURETY  
 
SEAL 
___________________________________ 
               AGENT ADDRESS

EXHIBIT D 
 
City of Chandler Job Order Project Agreement 
D-1 
Public Works & Utilities Department, Capital Projects Division  
Project Name: AIRPORT WATER RECLAMATION FACILITY HEADWORKS DRAIN PIPING 
Project No.: WW2003.401 
Rev. 9/18/2020 
PAYMENT BOND 
ARIZONA STATUTORY PAYMENT BOND 
PURSUANT TO TITLES 28, 34, AND 41, OF THE ARIZONA REVISED STATUTES 
(Penalty of this Bond must be 100% of the Contract amount) 
 
KNOW ALL MEN BY THESE PRESENTS THAT:________________________________________________  
 
(hereinafter "Principal"), as Principal, and _________________________________________(hereinafter "Surety"), a corporation 
organized and existing under the laws of the State of __________________   with its principal office in the City of 
__________________, holding a certificate of authority to transact surety business in Arizona issued by the Director of the 
Department of Insurance pursuant to Title 20, Chapter 2, Article 1, as Surety, are held and firmly bound unto 
________________________  (hereinafter "Obligee") in the amount of ________________________________________________ 
(Dollars) ($___________), for the payment whereof, the Principal and Surety bind themselves, and their heirs, 
administrators, executors, successors and assigns, jointly and severally, firmly by these presents. 
 
WHEREAS, the Principal has entered into a certain written contract with the Obligee, dated the _________ day of 
_______________________, 20___ for construction of AIRPORT WATER RECLAMATION FACILITY HEADWORKS DRAIN 
PIPING, WW2003.401 which contract is hereby referred to and made a part hereof as fully and to the same extent as 
if copied at length herein. 
 
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION IS SUCH, that if the Principal promptly pays all 
moneys due to all persons supplying labor or materials to the Principal or the Principal's subcontractors in the 
prosecution of the work provided for in said contract, this obligation is void. Otherwise it remains in full force and 
effect. 
 
PROVIDED, HOWEVER that this bond is executed pursuant to the provisions of Title 34, Chapter 2, Article 2 
Arizona Revised Statutes, and all liabilities on this bond will be determined in accordance with the provisions, 
conditions and limitations of Title 34, Chapter 2, Article 2, Arizona Revised Statutes, to the same extent as if it were 
copied at length in this Contract. 
 
The prevailing party in a suit on this bond may recover as part of the judgment reasonable attorney fees that 
may be fixed by a judge of the court. 
 
Witness our hands this ________________ day of ____________________, 20__. 
____________________________________ 
PRINCIPAL         
 
SEAL 
___________________________________ 
                 AGENT OF RECORD 
By _________________________________ 
____________________________________ 
SURETY  
 
SEAL 
___________________________________ 
                  AGENT ADDRESS

EXHIBIT E 
 
City of Chandler Job Order Project Agreement 
E-1 
Public Works & Utilities Department, Capital Projects Division  
Project Name: AIRPORT WATER RECLAMATION FACILITY HEADWORKS DRAIN PIPING 
Project No.: WW2003.401 
Rev. 9/18/2020 
CONTRACTOR'S AFFIDAVIT REGARDING SETTLEMENT OF CLAIMS 
 
________________________, Arizona 
 
Date ____________________________ 
Project Name: AIRPORT WATER RECLAMATION FACILITY HEADWORKS DRAIN PIPING 
Project No.:  
WW2003.401 
To the City of Chandler, Arizona 
Gentlemen: 
This is to certify that all lawful claims for materials, rental of equipment and labor used in connection with 
the construction of the above project, whether by subcontractor or claimant in person, have been duly 
discharged. 
 
The undersigned, for the consideration of $________________________, as set out in the final pay estimate, as 
full and complete payment under the terms of the contract, hereby waives and relinquishes any and all 
further claims or right of lien under, in connection with, or as a result of the above described project.  The 
undersigned further agrees to indemnify and save harmless the City of Chandler against any and all liens, 
claims or liens, suits, actions, damages, charges and expenses whatsoever, which said City may suffer 
arising out of the failure of the undersigned to pay for all labor performances and materials furnished for 
the performance of said installation. 
 
Signed and dated at ________________, this _________ day of _______________ 20_____. 
 
 
__________________________________ 
                       CONTRACTOR 
 
By _______________________________ 
STATE OF ARIZONA 
 
) 
) SS 
COUNTY OF MARICOPA 
) 
 
The foregoing instrument was subscribed and sworn to before me this __________ day of __________________ 
20 _________. 
 
___________________________________ 
 
 
 
 
 
                         Notary Public 
 
                     
 
___________________________________ 
 
 
 
 
 
                         My Commission Expires

EXHIBIT F 
 
City of Chandler Job Order Project Agreement 
F-1 
Public Works & Utilities Department, Capital Projects Division  
Project Name: AIRPORT WATER RECLAMATION FACILITY HEADWORKS DRAIN PIPING 
Project No.: WW2003.401 
Rev. 9/18/2020 
 
CERTIFICATE OF COMPLETION 
 
Project: 
AIRPORT WATER RECLAMATION FACILITY HEADWORKS DRAIN PIPING   
Project No.: 
WW2003.401 
 
 
(TO BE COMPLETED BY CONTRACTOR) 
 
I HEREBY CERTIFY THAT ALL GOODS AND/OR SERVICES REQUIRED BY CITY OF CHANDLER PROJECT NO. 
WW2003.401 HAVE BEEN DELIVERED IN ACCORDANCE WITH THE CONTRACT DOCUMENTS AND BID 
SPECIFICATIONS AND ALL ACTIVITIES REQUIRED BY THE CONTRACTOR UNDER THE CONTRACT HAVE BEEN 
COMPLETED AS OF ____________________________. 
 
 
                       (Date) 
FIRM NAME: 
________________________________ 
 
PRINCIPAL: 
________________________________ 
         (Name) 
 
________________________________ 
      (Signature) 
 
________________________________ DATE: ___________________ 
          (Title) 
 
CERTIFIED BY ENGINEER/CONSULTANT (IF APPLICABLE): 
 
_________________________________ 
 
DATE: ____________________ 
      (Signature) 
 
_________________________________ 
 
        (Firm Name) 
  
PROJECT ACCEPTED BY USER DEPARTMENT 
 
_________________________________ 
 
DATE: ____________________ 
         (Signature) 
 
_________________________________ 
 
          (Dept. /Div.) 
_______________ Date of Final Walk-Through 
 
_______________ Date As-Built Received 
 
_______________ City As-Built Number