Agreement - Arcadis U.S., Inc.
Extracted text (via pymupdf)
70971 characters
City of Chandler Professional Services Agreement
Page 1
Public Works & Utilities Department, Capital Projects Division
Project Name: HUNT HIGHWAY WATER PRODUCTION FACILITY GROUND SUBSIDENCE MITIGATION
Project No.: WA2107.201
Rev. 4/20/2021
PROFESSIONAL SERVICES AGREEMENT
Design Services
HUNT HIGHWAY WATER PRODUCTION FACILITY GROUND SUBSIDENCE MITIGATION
Project No. WA2107.201
Council Date: June 10, 2021 Item No.
THIS AGREEMENT (“Agreement”) is made and entered into on the ______ day of_________________,
2021 (“Effective Date”), by and between City of Chandler, an Arizona municipal corporation,
("City''), and Arcadis U.S., Inc., a Delaware corporation, ("Consultant") (City and Consultant
may individually be referred to as “Party” and collectively referred to as “Parties”).
RECITALS
A. City proposes to engage Consultant to provide Design Services for HUNT HIGHWAY WATER
PRODUCTION FACILITY GROUND SUBSIDENCE MITIGATION project as more fully described in
Exhibit "A", which is attached to and made a part of this Agreement by this reference.
B. Consultant is ready, willing, and able to provide the services described in Exhibit “A” for
the compensation and fees set forth and as described in Exhibit ”B”, which is attached to
and made a part of this Agreement by this reference.
C. City desires to contract with Consultant to provide these services under the terms and
conditions set forth in this Agreement.
AGREEMENT
NOW, THEREFORE, in consideration of the premises and the mutual promises contained in this
Agreement, City and Consultant agree as follows:
SECTION I--CONSULTANT’S SERVICES
Consultant must perform the services described in Exhibit “A” to City’s satisfaction within the
terms and conditions of this Agreement and within the care and skill that a person who
provides similar services in Chandler, Arizona exercises under similar conditions. All work or
services furnished by Consultant under this Agreement must be performed in a skilled and
workmanlike manner. All fixtures, furnishings, and equipment furnished by Consultant as
part of the work or services under this Agreement must be new, or the latest model, and of
the most suitable grade and quality for the intended purpose of the work or service.
City of Chandler Professional Services Agreement
Page 2
Public Works & Utilities Department, Capital Projects Division
Project Name: HUNT HIGHWAY WATER PRODUCTION FACILITY GROUND SUBSIDENCE MITIGATION
Project No.: WA2107.201
Rev. 4/20/2021
SECTION II--PERIOD OF SERVICE
Consultant must perform the services described in Exhibit “A” for the term of this
Agreement. Unless amended in writing by the Parties, the Agreement term expires 154
calendar days after the Notice to Proceed (NTP) Date.
SECTION III--PAYMENT OF COMPENSATION AND FEES
Unless amended in writing by the Parties, Consultant’s compensation and fees as more fully
described in Exhibit “B” for performance of the services approved and accepted by City
under this Agreement must not exceed $115,594 for the full term of the Agreement.
Consultant may not increase any compensation or fees under this Agreement without the
City’s prior written consent. Consultant must submit monthly requests for payment of
services approved and accepted during the previous billing period and must include, as
applicable, detailed invoices and receipts, a narrative description of the tasks accomplished
during the billing period, a list of any deliverables submitted, and any subconsultant’s or
supplier’s actual requests for payment plus similar narrative and listing of their work.
Consultant must submit an Application and Certification for Payment Sheet with the monthly
request for payment to: CapitalProjects.Payables@chandleraz.gov. Payment for those
services negotiated as a lump sum will be made in accordance with the percentage of the
work completed during the preceding billing period. Services negotiated as a not-to-exceed
fee will be paid in accordance with the work effort expended on the service during the
preceding month. All requests for payment must be submitted to City for review and
approval. City will make payment for approved and accepted services within 30 calendar days
of City’s receipt of the request for payment. Consultant bears all responsibility and liability for
any and all tax obligations that result from Consultant’s performance under this Agreement.
SECTION IV--CITY'S OBLIGATIONS
As part of Consultant’s services under this Agreement, City will provide furnished items,
services, or obligations as detailed in Exhibit “D”.
SECTION V--GENERAL CONDITIONS
5.1 Notices. Unless otherwise provided herein, demands under this Agreement must be in
writing and will be deemed to have been duly given and received either (a) on the date of
service if personally served on the party to whom notice is to be given, or (b) on the third day
after the date of the postmark of deposit by first class United States mail, registered or
certified, postage prepaid and properly addressed as follows:
City of Chandler Professional Services Agreement
Page 3
Public Works & Utilities Department, Capital Projects Division
Project Name: HUNT HIGHWAY WATER PRODUCTION FACILITY GROUND SUBSIDENCE MITIGATION
Project No.: WA2107.201
Rev. 4/20/2021
To City:
City of Chandler
Public Works & Utilities Department
Attn: CIP City Engineer
P.O. Box 4008, Mail Stop 407
Chandler, AZ 85244-4008
Phone: 480-782-3343
Email: andrew.goh@chandleraz.gov
With a Copy to:
Project Manager
City of Chandler
Public Works & Utilities Department
P.O. Box 4008, Mail Stop 407
Chandler, AZ 85244-4008
To Consultant:
Arcadis U.S., Inc.
410 N. 44th St., Ste. 1000, Phoenix, AZ 85008
Statutory Agent Name: CT Corporation System
Statutory Agent Mailing Address:
3800 N. Central Ave., Ste. 460 Phoenix AZ 85012
Statutory Agent Physical Address: (if different than mailing address)
Consultant’s Authorized Project Representative:
Name: Kim A. Tanner, PE
Title:
Mailing Address: 410 N. 44th St., Ste. 1000, Phoenix, AZ 85008
Physical Address: (if different than mailing address)
Phone: 602-797-4636
Email: kim.tanner@arcadis.com
5.2 Records/Audit. Records of Consultant’s direct personnel payroll, reimbursable expenses
pertaining to this Agreement and records of accounts between City and Consultant must be
kept on the basis of generally accepted accounting principles and must be made available to
City and its auditors for up to three years following City’s final acceptance of the services
under this Agreement (this requirement is increased to five years if construction of this
project is federally funded). City, its authorized representative, or any federal agency,
reserves the right to audit Consultant’s records to verify the accuracy and appropriateness of
all cost and pricing data, including data used to negotiate this Agreement and any
amendments. City reserves the right to decrease the total amount of Agreement price or
payments made under this Agreement or request reimbursement from Consultant following
final contract payment on this Agreement if, upon audit of Consultant’s records, the audit
discloses Consultant has provided false, misleading, or inaccurate cost and pricing data.
Consultant will include a similar provision in all of its contracts with subconsultants who
provide services under the Agreement to ensure that City, its authorized representative, or
the appropriate federal agency, has access to the subconsultants’ records to verify the
accuracy of all cost and pricing data. City reserves the right to decrease Contract price or
payments made on this Agreement or request reimbursement from Consultant following
City of Chandler Professional Services Agreement
Page 4
Public Works & Utilities Department, Capital Projects Division
Project Name: HUNT HIGHWAY WATER PRODUCTION FACILITY GROUND SUBSIDENCE MITIGATION
Project No.: WA2107.201
Rev. 4/20/2021
final payment on this Agreement if the above provision is not included in subconsultant
agreements, and one or more subconsultants refuse to allow City to audit their records to
verify the accuracy and appropriateness of all cost and pricing data. If, following an audit of
this Agreement, the audit discloses Consultant has provided false, misleading, or inaccurate
cost and pricing data, and the cost discrepancies exceed 1% of the total Agreement billings,
Consultant will be liable for reimbursement of the reasonable, actual cost of the audit.
5.3 Alteration in Character of Work. Whenever an alteration in the character of work results
in a substantial change in this Agreement, thereby materially increasing or decreasing the
scope of services, cost of performance, or Project schedule, the work will be performed as
directed by City. However, before any modified work is started, a written amendment must
be approved and executed by City and Consultant. Such amendment must not be effective
until approved by City. Additions to, modifications, or deletions from this Agreement as
provided herein may be made, and the compensation to be paid to Consultant may
accordingly be adjusted by mutual agreement of the Parties. It is distinctly understood and
agreed that no claim for extra services or materials furnished by Consultant will be allowed
by City except as provided herein, nor must Consultant do any work or furnish any materials
not covered by this Agreement unless such work is first authorized in writing. Any such work
or materials furnished by Consultant without prior written authorization will be at
Consultant’s own risk, cost, and expense, and Consultant hereby agrees that without written
authorization Consultant will make no claim for compensation for such work or materials
furnished.
5.4 Termination. City and Consultant hereby agree to the full performance of the covenants
contained herein, except that City reserves the right, at its discretion and without cause, to
terminate or abandon any service provided for in this Agreement, or abandon any portion of
the Project for which services have been performed by Consultant. In the event City abandons
or suspends the services, or any part of the services as provided in this Agreement, City will
notify Consultant in writing and immediately after receiving such notice, Consultant must
discontinue advancing the work specified under this Agreement. Upon such termination,
abandonment, or suspension, Consultant must deliver to City all drawings, plans,
specifications, special provisions, estimates and other work entirely or partially completed,
together with all unused materials supplied by City. Consultant must appraise the work
Consultant has completed and submit Consultant’s appraisal to City for evaluation. City may
inspect Consultant’s work to appraise the work completed. Consultant will receive
compensation in full for services performed to the date of such termination. The fee will be
paid in accordance with Section Ill of this Agreement, and as mutually agreed upon by
Consultant and City. If there is no mutual agreement on payment, the final determination will
be made in accordance with the "Disputes" provision in this Agreement. However, in no event
may the fee exceed the fee set forth in Section Ill of this Agreement nor as amended in
accordance with Section "Alteration in Character of Work." City will make the final payment
within 60 days after Consultant has delivered the last of the partially completed items and
the Parties agree on the final fee. If City is found to have improperly terminated the
Agreement for cause or default, the termination will be converted to a termination for
convenience in accordance with the provisions of this Agreement.
5.5 Indemnification. To the extent permitted by law, the Consultant ("lndemnitor") must
City of Chandler Professional Services Agreement
Page 5
Public Works & Utilities Department, Capital Projects Division
Project Name: HUNT HIGHWAY WATER PRODUCTION FACILITY GROUND SUBSIDENCE MITIGATION
Project No.: WA2107.201
Rev. 4/20/2021
indemnify, save and hold harmless City and its officers, officials, agents and employees
("lndemnitee") from any and all claims, actions, liabilities, damages, losses or expenses
(including court costs, attorneys' fees and costs of claim processing, investigation and
litigation) ("Claims") caused or alleged to be caused, in whole or in part, by the wrongful,
negligent or willful acts, or errors or omissions of Consultant or any of its owners, officers,
directors, agents, employees, or subconsultants in connection with this Agreement. This
indemnity includes any claim or amount arising out of or recovered under workers'
compensation law or on account of the failure of Consultant to conform to any federal, state
or local law, statute, ordinance, rule, regulation or court decree. Consultant must indemnify
lndemnitee from and against any and all Claims, except those arising solely from
lndemnitee's own negligent or willful acts or omissions. Consultant is responsible for primary
loss investigation, defense and judgment costs where this indemnification applies. In
consideration of the award of this Agreement, Consultant agrees to waive all rights of
subrogation against lndemnitee for losses arising from or related to this Agreement. The
obligations of Consultant under this provision survive the termination or expiration of this
Agreement.
5.6 Insurance Requirements. Consultant must procure insurance under the terms and
conditions and for the amounts of coverage set forth in Exhibit “C” against claims that may
arise from or relate to performance of the work under this Agreement by Consultant and its
agents, representatives, employees, and subconsultants. Consultant and any subconsultant
must maintain this insurance until all of their obligations have been discharged, including any
warranty periods under this Agreement. These insurance requirements are minimum
requirements for this Agreement and in no way limit the indemnity covenants contained in
this Agreement. City in no way warrants that the minimum limits stated in Exhibit “C” are
sufficient to protect Consultant from liabilities that might arise out of the performance of the
work under this Agreement by Consultant, Consultant’s agents, representatives, employees,
or subconsultants. Consultant is free to purchase such additional insurance as may be
determined necessary.
5.7 Cooperation and Further Documentation. Consultant agrees to provide City such other
duly executed documents as may be reasonably requested by City to implement the intent
of this Agreement.
5.8 Successors and Assigns. City and Consultant each bind itself, its partners, successors,
assigns, and legal representatives to the other party to this Agreement and to the partners,
successors, assigns, and legal representatives of such other party in respect to all covenants
of this Agreement. Neither City nor Consultant may assign, sublet, or transfer its interest in
this Agreement without the written consent of the other party. In no event may any
contractual relation be created between any third party and City.
5.9 Disputes. In any dispute arising out of an interpretation of this Agreement or the duties
required not disposed of by agreement between Consultant and City, the final determination
at the administrative level will be made by City Engineer.
5.10 Completeness and Accuracy of Consultant’s Work. Consultant must be responsible for
the completeness and accuracy of Consultant’s services, data, and other work prepared or
City of Chandler Professional Services Agreement
Page 6
Public Works & Utilities Department, Capital Projects Division
Project Name: HUNT HIGHWAY WATER PRODUCTION FACILITY GROUND SUBSIDENCE MITIGATION
Project No.: WA2107.201
Rev. 4/20/2021
compiled under Consultant’s obligation under this Agreement and must correct, at
Consultant’s expense, all willful or negligent errors, omissions, or acts that may be discovered.
Correction of errors disclosed and determined to exist during any construction of the project on
architectural or engineering drawings and specifications must be accomplished by Consultant.
The cost of the design necessary to correct those errors attributable to Consultant and any
damage incurred by City as a result of additional construction costs caused by such engineering
or architectural errors will be chargeable to Consultant and will not be considered a cost of the
Work. The fact that City has accepted or approved Consultant’s work will in no way relieve
Consultant of any of Consultant’s responsibilities.
5.11 Reporting. Written monthly reports, along with updated work schedules, will be made by
Consultant in the format prescribed by City. These reports will be delivered to City per schedule.
When requested by City, Consultant will attend Council meetings and provide finished documents
including correspondence for Council action, supporting charts, graphs, drawings and colored
slides of same.
5.12 Withholding Payment. City reserves the right to withhold funds from Consultant’s
payments up to the amount equal to the claims City may have against Consultant until such
time that a settlement on those claims has been reached.
5.13 City's Right of Cancellation. The Parties acknowledge that this Agreement is subject to
cancellation by City under the provisions of Section 38-511, Arizona Revised Statutes (A.R.S.).
5.14 Independent Consultant. For this Agreement Consultant constitutes an independent
contractor. Any provisions in this Agreement that may appear to give City the right to direct
Consultant as to the details of accomplishing the work or to exercise a measure of control
over the work means that Consultant must follow the wishes of City as to the results of the
work only. These results must comply with all applicable laws and ordinances.
5.15 Project Staffing. Prior to the start of any work under this Agreement, Consultant must
submit to City detailed resumes of key personnel that will be involved in performing services
prescribed in the Agreement. City hereby acknowledges its acceptance of such personnel to
perform services under this Agreement. At any time hereafter that Consultant desires to
change key personnel while performing under the Agreement, Consultant must submit the
qualifications of the new personnel to City for prior approval. Key personnel include, but are
not limited to, principals-in-charge, project manager, and project Consultant. Consultant will
maintain an adequate and competent staff of qualified persons, as may be determined by
City, throughout the performance of this Agreement to ensure acceptable and timely
completion of the Scope of Services. If City objects, with reasonable cause, to any of
Consultant’s staff, Consultant must take prompt corrective action acceptable to City and, if
required, remove such personnel from the Project and replace with new personnel agreed to
by City.
5.16 Consultants or Subconsultants. Prior to beginning the work, Consultant must furnish City
for approval the names of consultants or subconsultants to be used under this Agreement.
Any subsequent changes are subject to City’s written prior approval.
City of Chandler Professional Services Agreement
Page 7
Public Works & Utilities Department, Capital Projects Division
Project Name: HUNT HIGHWAY WATER PRODUCTION FACILITY GROUND SUBSIDENCE MITIGATION
Project No.: WA2107.201
Rev. 4/20/2021
5.17 Force Majeure. If either party is delayed or prevented from the performance of any act
required under this Agreement by reason of acts of God or other cause beyond the control
and without fault of the Party (financial inability excepted), performance of that act may be
excused, but only for the period of the delay, if the Party provides written notice to the other
Party within ten days of such act. The time for performance of the act may be extended for a
period equivalent to the period of delay from the date written notice is received by the other
Party.
5.18 Compliance with Federal Laws. Consultant understands and acknowledges the
applicability of the Americans with Disabilities Act, the Immigration Reform and Control Act
of 1986 and the Drug Free Workplace Act of 1989 to it. Consultant agrees to comply with these
laws in performing this Agreement and to permit City to verify such compliance.
5.19 No Israel Boycott. By entering into this Agreement, Consultant certifies that Consultant
is not currently engaged in, and agrees for the duration of the Agreement, not to engage in a
boycott of Israel as defined by state statute.
5.20 Legal Worker Requirements. A.R.S. § 41-4401 prohibits City from awarding a contract to
any consultant who fails, or whose subconsultants fail, to comply with A.R.S. § 23-214(A).
Therefore, Consultant agrees Consultant and each subconsultant it uses warrants their
compliance with all federal immigration laws and regulations that relate to their employees
and their compliance with § 23-214, subsection A. A breach of this warranty will be deemed a
material breach of the Agreement and may be subject to penalties up to and including
termination of the Agreement. City retains the legal right to inspect the papers of any
Consultant’s or subconsultant’s employee who provides services under this Agreement to
ensure that Consultant and subconsultants comply with the warranty under this provision.
5.21 Lawful Presence Requirement. A.R.S. §§ 1-501 and 1-502 prohibit City from awarding a
contract to any natural person who cannot establish that such person is lawfully present in
the United States. To establish lawful presence, a person must produce qualifying
identification and sign a City-provided affidavit affirming that the identification provided is
genuine. This requirement will be imposed at the time of contract award. This requirement
does not apply to business organizations such as corporations, partnerships, or limited
liability companies.
5.22 Covenant Against Contingent Fees. Consultant warrants that no person has been
employed or retained to solicit or secure this Agreement upon an agreement or
understanding for a commission, percentage, brokerage, or contingent fee, and that no
member of the Chandler City Council, or any City employee has any interest, financially, or
otherwise, in Consultant’s firm. For breach or violation of this warrant, City may annul this
Agreement without liability or, at its discretion, to deduct from the Agreement price or
consideration, the full amount of such commission, percentage, brokerage, or contingent fee.
5.23 Non-Waiver Provision. The failure of either Party to enforce any of the provisions of this
Agreement or to require performance of the other Party of any of the provisions hereof must
not be construed to be a waiver of such provisions, nor must it affect the validity of this
Agreement or any part thereof, or the right of either Party to thereafter enforce each and
City of Chandler Professional Services Agreement
Page 8
Public Works & Utilities Department, Capital Projects Division
Project Name: HUNT HIGHWAY WATER PRODUCTION FACILITY GROUND SUBSIDENCE MITIGATION
Project No.: WA2107.201
Rev. 4/20/2021
every provision.
5.24 Disclosure of Information Adverse to City’s Interests. To evaluate and avoid potential
conflicts of interest, Consultant must provide written notice to City, as set forth in this Section,
of any work or services performed by Consultant for third parties that may involve or be
associated with any real property or personal property owned or leased by City. Such notice
must be given 7 business days prior to commencement of the services by Consultant for a
third party, or 7 business days prior to an adverse action as defined below. Written notice
and disclosure must be sent in accordance with Section 6.7 above. An adverse action under
this Agreement includes, but is not limited to: (a) using data as defined in the Agreement
acquired in connection with this Agreement to assist a third party in pursuing administrative
or judicial action against City; or (b) testifying or providing evidence on behalf of any person
in connection with an administrative or judicial action against City; or (c) using data to produce
income for Consultant or its employees independently of performing the services under this
Agreement, without the prior written consent of City. Consultant represents that except for
those persons, entities, and projects identified to City, the services performed by Consultant
under this Agreement are not expected to create an interest with any person, entity, or third
party project that is or may be adverse to City’s interests. Consultant’s failure to provide a
written notice and disclosure of the information as set forth in this Section constitute a
material breach of this Agreement.
5.25 Data Confidentiality and Data Security. As used in the Agreement, "data" means all
information, whether written or verbal, including plans, photographs, studies, investigations,
audits, analyses, samples, reports, calculations, internal memos, meeting minutes, data field
notes, work product, proposals, correspondence and any other similar documents or
information prepared by, obtained by, or transmitted to Consultant or its subconsultants in
the performance of this Agreement. The Parties agree that all data, regardless of form,
including originals, images, and reproductions, prepared by, obtained by, or transmitted to
Consultant or its subconsultants in connection with Consultant’s or its subconsultant’s
performance of this Agreement is confidential and proprietary information belonging to City.
Except as specifically provided in this Agreement, Consultant or its subconsultants must not
divulge data to any third party without City’s prior written consent. Consultant or its
subconsultants must not use the data for any purposes except to perform the services
required under this Agreement. These prohibitions do not apply to the following data
provided to Consultant or its subconsultants have first given the required notice to City: (a)
data which was known to Consultant or its subconsultants prior to its performance under this
Consultant or its subconsultants by a third party, who to the best of Consultant’s or its
subconsultants’ knowledge and belief, had the legal right to make such disclosure and
Consultant or its subconsultants are not otherwise required to hold such data in confidence;
or (c) data which is required to be disclosed by virtue of law, regulation, or court order, to
which Consultant or its subconsultants are subject. In the event Consultant or its
subconsultants are required or requested to disclose data to a third party, or any other
information to which Consultant or its subconsultants became privy as a result of any other
contract with City, Consultant must first notify City as set forth in this Section of the request
or demand for the data. Consultant or its subconsultants must give City sufficient facts so
that City can be given an opportunity to first give its consent or take such action that City may
deem appropriate to protect such data or other information from disclosure. All data must
City of Chandler Professional Services Agreement
Page 9
Public Works & Utilities Department, Capital Projects Division
Project Name: HUNT HIGHWAY WATER PRODUCTION FACILITY GROUND SUBSIDENCE MITIGATION
Project No.: WA2107.201
Rev. 4/20/2021
continue to be subject to the confidentiality agreements of this Agreement. Consultant or its
subconsultants assume all liability to maintain the confidentiality of the data in its possession
and agrees to compensate City if any of the provisions of this Section are violated by
Consultant, its employees, agents or subconsultants. Solely for the purposes of seeking
injunctive relief, it is agreed that a breach of this Section must be deemed to cause irreparable
harm that justifies injunctive relief in court. Consultant agrees that the requirements of this
Section must be incorporated into all subagreements entered into by Consultant. A violation
of this Section may result in immediate termination of this Agreement without notice.
5.26 Personal Identifying Information-Data Security. Personal identifying information,
financial account information, or restricted City information, whether electronic format or
hard copy, must be secured and protected at all times by Consultant or its subconsultants. At
a minimum, Consultant or its subconsultants must encrypt or password-protect electronic
files. This includes data saved to laptop computers, computerized devices, or removable
storage devices. When personal identifying information, financial account information, or
restricted City information, regardless of its format, is no longer necessary, the information
must be redacted or destroyed through appropriate and secure methods that ensure the
information cannot be viewed, accessed, or reconstructed. In the event that data collected or
obtained by Consultant or its subconsultants in connection with this Agreement is believed
to have been compromised, Consultant or its subconsultants must immediately notify City
contact. Consultant agrees to reimburse City for any costs incurred by City to investigate
potential breaches of this data and, where applicable, the cost of notifying individuals who
may be impacted by the breach. Consultant agrees that the requirements of this Section must
be incorporated into all subcontracts entered into by Consultant. It is further agreed that a
violation of this Section must be deemed to cause irreparable harm that justifies injunctive
relief in court. A violation of this Section may result in immediate termination of this
Agreement without notice. The obligations of Consultant or its subconsultants under this
Section must survive the termination of this Agreement.
5.27 Jurisdiction and Venue. This Agreement is made under, and must be construed in
accordance with and governed by the laws of the State of Arizona without regard to the
conflicts or choice of law provisions thereof. Any action to enforce any provision of this
Agreement or to obtain any remedy with respect hereto must be brought in the courts
located in Maricopa County, Arizona, and for this purpose, each Party hereby expressly and
irrevocably consents to the jurisdiction and venue of such court.
5.28 Survival. All warranties, representations, and indemnifications by Consultant must
survive the completion or termination of this Agreement.
5.29 Modification. Except as expressly provided herein to the contrary, no supplement,
modification, or amendment of any term of this Agreement will be deemed binding or
effective unless in writing and signed by the Parties.
5.30 Severability. If any provision of this Agreement or the application to any person or
circumstance may be invalid, illegal or unenforceable to any extent, the remainder of this
Agreement and the application will not be affected and will be enforceable to the fullest
extent permitted by law.
City of Chandler Professional Services Agreement
Page 10
Public Works & Utilities Department, Capital Projects Division
Project Name: HUNT HIGHWAY WATER PRODUCTION FACILITY GROUND SUBSIDENCE MITIGATION
Project No.: WA2107.201
Rev. 4/20/2021
5.31 Integration. This Agreement contains the full agreement of the Parties. Any prior or
contemporaneous written or oral agreement between the Parties regarding the subject
matter is merged and superseded.
5.32 Time is of the Essence. Time of each of the terms, covenants, and conditions of this
Agreement is hereby expressly made of the essence.
5.33 Date of Performance. If the date of performance of any obligation or the last day of any
time period provided for should fall on a Saturday, Sunday, or holiday for City, the obligation
will be due and owing, and the time period will expire, on the first day after which is not a
Saturday, Sunday or legal City holiday. Except as may otherwise be set forth in this
Agreement, any performance provided for herein will be timely made if completed no later
than 5:00 p.m. (Chandler time) on the day of performance.
5.34 Third Party Beneficiary. Nothing under this Agreement will be construed to give any
rights or benefits in the Agreement to anyone other than City and Consultant, and all duties
and responsibilities undertaken pursuant to this Agreement will be for the sole and exclusive
benefit of City and Consultant and not for the benefit of any other party.
5.35 Conflict in Language. All work performed must conform to all applicable City of Chandler
codes, ordinances, and requirements as outlined in this Agreement. If there is a conflict in
interpretation between provisions in this Agreement and those in Exhibit "A", the provisions
in this Agreement prevail.
5.36 Document/Information Release. Documents and materials released to Consultant,
which are identified by City as sensitive and confidential, are City’s property. The
document/material must be issued by and returned to City upon completion of the services
under this Agreement. Consultant secondary distribution, disclosure, copying, or duplication
in any manner is prohibited without City’s prior written approval. The document/material
must be kept secure at all times. This directive applies to all City documents, whether in
photographic, printed, or electronic data format.
5.37 Exhibits. The following exhibits are made a part of this Agreement and are incorporated
by reference:
Exhibit A - Scope of Services / Schedule
Exhibit B - Compensation and Fees
Exhibit C - Insurance Requirements
Exhibit D - Special Conditions
Exhibit E – Federal Requirements (if applicable)
5.38 Special Conditions. As part of the services Consultant provides under this Agreement,
Consultant agrees to comply with and fully perform the special terms and conditions set forth
in Exhibit “D”, which is attached to and made a part of this Agreement.
5.39 Non-Discrimination and Anti-Harassment Laws. Consultant must comply with all
City of Chandler Professional Services Agreement
Page 11
Public Works & Utilities Department, Capital Projects Division
Project Name: HUNT HIGHWAY WATER PRODUCTION FACILITY GROUND SUBSIDENCE MITIGATION
Project No.: WA2107.201
Rev. 4/20/2021
applicable City, state, and federal non-discrimination and anti-harassment laws, rules, and
regulations.
5.40 Licenses and Permits. Beginning with the Effective Date and for the full term of this
Agreement, Consultant must maintain all applicable City, state, and federal licenses and
permits required to fully perform Consultant’s services under this Agreement.
5.41 Warranties. Consultant must furnish a one-year warranty on all work and services
performed under this Agreement. Consultant must furnish, or cause to be furnished, a two-
year warranty on all fixtures, furnishings, and equipment furnished by Consultant,
subconsultants or suppliers under this Agreement. Any defects in design, workmanship, or
materials that do not comply with this Agreement must be corrected by Consultant (including,
but not limited to, all parts and labor) at Consultant’s sole cost and expense. All written
warranties and redlines for as-built conditions must be delivered to City on or before City’s
final acceptance of Consultant’s services under this Agreement.
5.42 Cooperative Purchasing Agreement (S.A.V.E. – Strategic Alliance for Volume
Expenditures). In addition to City of Chandler and with the approval of Consultant, this
Agreement may be extended for use by other municipalities, school districts, and government
agencies of the State. Any such usage by other entities must be in accordance with the
ordinance, charter, or procurement rules and regulations of the respective political entity.
5.43 Budget Approval into Next Fiscal Year. This Agreement will commence on the Effective
Date and continue in full force and effect until it is terminated or expires in accordance with
the provisions of this Agreement. The Parties recognize that the continuation of this
Agreement after the close of the City's fiscal year, which ends on June 30 of each year, is
subject to the City Council's approval of a budget that includes an appropriation for this item
as an expenditure. The City does not represent that this budget item will be actually adopted.
This determination is solely made by the City Council.
SIGNATURE PAGE TO FOLLOW
This Agreement will be in full force and effect only when it has been approved and executed
by the duly authorized City officials.
IN WITNESS WHEREOF, the Parties have executed this Agreement as of the Effective Date.
"CITY"
CITY OF CHANDLER
Recommended By:
Andrew Goh, P.E.
CIP City Engineer
MAYOR
APPROVED AS TO FORM:
City Attorney
ATTEST:
City Clerk
"CONSULTANT"
Arcadis U.S., Inc.
Seal
-U,_,,,,_-
-1s/2oz t
Date
l<\("Y'\ . F
\ C\1--..ne...r
Print Name
k 1 "" • +o" " e...- @ s,.. c o.. d , .s . c.. ¢
Signer Email Address
City of Chandler Professional Services Agreement
Public Works & Utilities Department, Capital Projects Division
Project Name: HUNT HIGHWAY WATER PRODUCTION FACILITY GROUND SUBSIDENCE MITIGATION
Project No.: WA2107.201
Rev. 4/20/2021
Page 12
City of Chandler Professional Services Agreement – Exhibit “A”
Page A-1
Public Works & Utilities Department, Capital Projects Division
Project Name: HUNT HIGHWAY WATER PRODUCTION FACILITY GROUND SUBSIDENCE MITIGATION
Project No.: WA2107.201
Rev. 4/20/2021
EXHIBIT “A”
SCOPE OF SERVICES/SCHEDULE
Mr. Hafiz Noor
Project Manager
City of Chandler
PO Box 4008, MS 407
215 E Buffalo Street, Suite 101
Chandler, AZ 85244-4008
Subject:
WA2107.201 Hunt Highway WPF Ground Subsidence Mitigation Design
Revised Proposal for Professional Engineering Services
Dear Mr. Noor:
Arcadis is pleased to submit this Revised Proposal to provide professional
engineering services for design of subsidence mitigation Option 3 as Arcadis
presented on February 9, 2021. This Proposal has been revised based on
comments received from the City regarding the prior scope and fee proposal
submitted April 14, 2021.
The Revised Scope of Work is attached as Exhibit A and reflects our approach
which has been modified based on City comments received. Our total proposed
fee for the work presented in Exhibit B is $95,133.00, which includes limited survey
work. In addition, permitting has been moved to Allowances along with the City
requested contingency amounts for a Total Cost for the project of $115,594.00.
Based on City comments and resulting revisions, we anticipate a total schedule
duration of approximately 22 weeks which includes permitting activities if
necessary, and project closeout. The project effort will be led by our Project
Principal Mr. Kim Tanner, PE, our Project Manager/Senior Engineer Mr. Dane
Whitmer, PE, and Arcadis qualified team members. We appreciate this opportunity
to continue working with the City of Chandler. Should you have any questions or
comments, please don’t hesitate to call me at 602-797-4636.
Sincerely,
Arcadis U.S., Inc.
Kim A. Tanner, P.E.
Principal-in-Charge
Enclosures:
Exhibit A - Scope of Work
Exhibit B - Fee Estimate
Exhibit C - Project Schedule
Arcadis U.S., Inc.
410 N. 44th Street
Suite 1000
Phoenix
Arizona 85008 Tel
602 438 0883 Fax
602 438 0102
www.arcadis.com
Date:
April 20, 2021
Contact:
Kim Tanner, P.E.
Phone:
602-797-4636
Email:
kim.tanner@arcadis.com
Our ref:
30043441
Page:
1/1
1
EXHIBIT A
SCOPE OF WORK FOR
PROFESSIONAL ENGINEERING SERVICES
CITY OF CHANDLER
HUNT HIGHWAY WATER PRODUCTION FACILITY
GROUND SUBSIDENCE MITIGATION DESIGN
WA2107.201
INTRODUCTION
The City of Chandler Hunt Highway Water Production Facility (HHWPF), located at
2022 E. Hunt Highway, was designed in 1997 and constructed in 1998 to serve potable
water to Zone 2 of the City’s distribution system. The WPF consists of a 2 million-gallon
steel storage tank and a booster station equipped with 5 vertical turbine pumps. Suction
piping is arranged to pump from the 2 MG tank for discharge to Zone 2.
City staff have noticed over a period of time that subsidence in the vicinity of the booster
station has occurred such that the above-grade discharge piping is visibly displaced, as
well as suction side valve boxes and other appurtenances. Evidence of subsidence has
become more apparent over the last 12-18 months, and may have been exacerbated by a
site flooding event that occurred approximately a year ago. The City now feels that the
booster station may be at risk for leakage, pipe breaks or other failure due to the noted
subsidence.
Arcadis performed a visual investigation along with a subsurface investigation in November
2020 to determine a level of understanding of what components of the facility are potentially at
risk and current operating conditions. These findings were summarized in the November 3,
2020 technical memorandum Hunt Highway Water Production Facility Ground Subsidence
Investigation by Arcadis. Following the City’s acceptance of investigation findings, Arcadis
developed alternatives with associated cost opinions and provided a recommendation for an
alternative design in the February 23, 2021 technical memorandum Hunt Highway Water
Production Facility Ground Recommended System Improvements.
Based on the findings and recommendations as summarized in the Arcadis technical
memoranda, the City has selected Alternative 3 - Excavate and Recompact for detailed design
to correct subsidence issues at the HHWPF. Therefore, the design and construction documents
prepared for this project will cover the following:
• Disassembling the above grade piping and excavating the soils in the impacted booster
station area down to a depth of approximately 7 feet.
2
• Requiring inspection and rehabilitation of the below grade piping as needed and replacing
electrical wiring and conduits back to the electrical building.
• Backfilling and recompacting with acceptable fill materials.
• Constructing new concrete bases and resetting/repositioning pipe supports.
• Rehabilitating and resetting and the above grade piping and valves.
• Resetting above grade electrical conduit supports and retaping.
• Regrading and paving the site to impede further wetting of subgrade soils by significant
storm or maintenance events.
• Testing and disinfecting the pipe for return to service.
The following Scope of Work describes the activities associated with preparing the project design
and related construction documents. Construction documents are anticipated to include drawings
and specifications consistent with the City of Chandler and MAG standards.
SCOPE OF WORK
TASK 1 – PROVIDE PROJECT MANAGEMENT
Arcadis will perform project management activities based on best practices from Project
Management Institute Project Management Body of Knowledge. Arcadis will perform
project management activities in the following areas for Phases 1 and 2 inclusive.
1.1 Initiate Project:
The Kickoff Meeting will serve to schedule the work activities.
1.2 Monitor and Control Project:
Arcadis will report activities through project status calls. Project change
control will involve identification of any requested changes, review and
approval of changes, and application of corrective actions to control the scope,
cost and schedule of the project.
1.3 Closeout Project:
Arcadis will debrief the City and perform closeout activities. Project
closeout activities including archiving of project documents within
Arcadis record files and final turnover of project deliverables in required
format to the City.
Meetings
• One (1) Kickoff Meeting.
• Five (5) monthly status calls.
3
Deliverables
• Kickoff meeting notes.
• Monthly Invoices.
• Monthly Progress Reports.
City Responsibilities
• Participate in status calls.
• Identify meeting attendees and assist with scheduling.
TASK 2 – CONDUCT LIMITED TOPOGRAPHIC SURVEY
As part of the Basis of Design work, a limited verification of site topographic and equipment
elevation information will be completed for confirmation of facility elevations for resetting
piping / valves and re-grading and paving of the site to correct drainage. The field check will
consist of a survey to verify grade elevations, exposed piping, equipment, and components, as
well as comparing the survey data to the Record Drawings and the City’s desired vertical
datum. If necessary, elevation information will be converted to the City’s standard vertical
datum reference used for water facilities. Arcadis will incorporate survey results into the Basis
of Design and Construction Documents described in this SCOPE OF WORK.
City Responsibilities
• Provide access to the Hunt Highway WPF site.
• Provided the City’s standard vertical datum reference used for water facilities.
TASK 3 – PREPARE DESIGN AND CONSTRUCTION DOCUMENTS
Following City approval of the Task 3 Basis of Design, Arcadis will prepare the design,
construction drawings and technical specifications. Construction drawings will be developed
using existing Record Drawings and the Task 2 supplemental survey data. The original facility
Record Drawings are anticipated to be used as screened background for construction drawing
sheets. The construction drawings and specifications will be prepared to the level of a bid
ready package.
Design work will conform to the latest version of the City of Chandler Water & Wastewater
System Design Technical Design Manuals 1&2 and MAG standards. Construction documents
will be submitted for City review at the 60% and 90% levels of completion as described below.
60% Project Completion
At 60% design completion, Arcadis will submit for City review:
• Progress construction drawing set including:
- Civil and mechanical drawings.
4
- Pipeline plan and profile.
- Progress detail sheets for connections & appurtenances.
• Draft of major specification sections, including a ductile iron pipe and gate valve
specifications should these components require replacement based on inspection during
construction.
• Construction cost estimate.
The 60% design will be presented to City staff in one (1) workshop session. Based on City
review comments, revisions will be incorporated into prior to the 90% completion
submittal.
90% Project Completion
The final formal review workshop will be conducted by Arcadis at the 90% design completion
stage, which essentially represents the completion of the design development process. This
workshop will focus on accuracy and completeness of the design product including:
• Verifying that prior City comments on 60% completion submittal have been
incorporated.
• Validating compliance with City standards and requirements.
• Reviewing drawing and specification consistency.
• Addressing operational and constructability considerations.
• Cost estimate refined from 60% level.
Following the workshop, Arcadis will initiate permit review submittals as described under
Task 5 herein.
Final Project Completion
Items identified in the 90% review will be incorporated in the final construction document bid
ready package for City’s use in procuring construction services.
Deliverables
• Review design document sets at each level of completion.
• 60% and 90% workshop agendas
• 60% and 90% workshop notes
• 60% and 90% cost estimates
• One electronic copy of the Final construction documents incorporating City
comments on the 90% set.
5
TASK 4 - ALLOWANCES
Fees for the following are included as Fee Allowances since the required effort is currently
unknown.
Permitting
Following the project Kickoff Meeting, Arcadis will contact Maricopa County Environmental
Services Department (MCESD) for an early determination of whether the Approval to
Construct (ATC) and Approval of Construction (AOC) process will apply to the project. If
this project is considered as system maintenance, MCESD may not require permit review. At
the 90% level of completion, Arcadis will identify, coordinate and prepare permit submittal
documents for MCESD if required.
If the ATC/AOC process applies, the requirements of Chandler Water and Wastewater System
Design Technical Design Manuals 1 & 2 (TDM 1&2), require that construction documents
will bear the approval signature of MCESD prior to approval by the City. Arcadis will route
the request for ATC to the City Engineer through Civil Plan Review. Arcadis will also
respond to MCESD review comments after consulting with City staff and apprise the City of
ATC review status.
In accordance with TDM 1&2, once construction is complete, Arcadis will also prepare and
submit the application for AOC and obtain final sign off through MCSED.
Contractor Coordination / Bidding Assistance
Arcadis will assist the City in coordinating with the City’s JOC for providing clarifications,
responding to requests for information, reviewing contractor pricing, etc., as requested.
Arcadis will provide similar as-requested services should the City deliver the project through
conventional design-bid-build.
Owner’s Contingency
An amount representing approximately 10% of the design fee is included as a contingency for
use at the sole discretion of the City.
SCOPE OF WORK ASSUMPTIONS & EXCLUSIONS
Assumptions
• All work will be within the boundary of the HHWPF site.
• Existing piping, valves, electrical equipment, and instrumentation are assumed to be
reused and not replaced. Only concrete piping supports, electrical conduits and wiring
from the equipment to the electrical building are assumed to be replaced as new.
However, specification sections will be provided for use in furnishing new gate valves
6
and ductile iron piping should the existing components be in unsatisfactory condition as
identified during construction.
• Design drawings will be prepared using existing facility Record Drawings as screened
background.
• Geotechnical information from Phase 1 – Task 2 herein will be the initial geotechnical
reference for design.
• The prior Technical Memoranda prepared under the Ground Subsidence Investigation
project shall serve as the design basis for this design phase and will be submitted with
the ATC application to MCESD if permit review is required.
• The cost estimate based on the construction drawings and specifications at the 90%
level of completion will be an AAEE Class 2 estimate.
• City will review and authorize ALLOWANCE budgets as needed.
• City will pay all permit application fees.
Exclusions
• Construction Administration Services are not part of this Scope of Services and will be
provided to the City if requested in a separate proposal.
• Design and installation of new equipment, piping/valves or instrumentation is excluded.
However, specification sections will be provided for use in furnishing new gate valves
and ductile iron piping should the existing components be in unsatisfactory condition as
identified during construction.
• The storage tank and appurtenances are excluded.
• Site communications and development of P&IDs is excluded.
City of Chandler Professional Services Agreement – Exhibit “B”
Page B-1
Public Works & Utilities Department, Capital Projects Division
Project Name: HUNT HIGHWAY WATER PRODUCTION FACILITY GROUND SUBSIDENCE MITIGATION
Project No.: WA2107.201
Rev. 4/20/2021
EXHIBIT “B”
COMPENSATION AND FEES
WA2107.201
8,068.00
$
Initiate Project
981.00
$
Monitor and Control Project
5,788.00
$
Closeout Project
1,299.00
$
2,611.00
$
Coordinate Survey Subconsultant Work
623.00
$
Review and Interpret Results
1,988.00
$
81,954.00
$
60% Project Completion
68,040.00
$
Workshop
941.00
$
90% Project Completion
8,392.00
$
Workshop
941.00
$
Final Project Completion
3,640.00
$
4. Allowances
20,461.00
$
Permitting (ATC, City, AOC)
8,448.00
$
Contractor Coordination / Bidding Assistance
2,500.00
$
Owner's Contingency (10% of base fee)
9,513.00
$
2,500.00
$
TOTAL COST:
115,594.00
$
3. Design and Constuction Documents
Survey Subconsultant (Task 2)
SUBTOTAL
1. Provide Project Management
EXHIBIT B
HUNT HIGHWAY WPF GROUND SUBSIDENCE MITIGATION DESIGN
TASK DESCRIPTIONS
2. Conduct Limited Topographic Survey
Lump Sum Cost Per Task
Arcadis U.S., Inc.
410 N. 44th Street
Suite 1000
Phoenix
Arizona 85008
Tel 602 438 0883
Fax 602 438 0102
www.arcadis.com
Page 1 of 1
Principal /
Technical
Expert
Sr. Engr.
Engr. / I/C /
Data Analyst
Technician /
CAD
Designer /
Project
Assistant
K.Tanner /
Z.Wilsterman
D. Whitmer
J. Emmons
B. Freeman /
J. Morrison
$ 265.00 $ 179.00 $ 159.00 $ 138.00
2
28
2
16
48
Initiate Project
1
4
5
Monitor and Control Project
20
16
36
Closeout Project
1
4
2
7
1
6
8
0
15
Coordinate Survey Subconsultant Work
1
2
3
Review and Interpret Results
4
8
12
6
52
65
440
563
60% Project Completion
4
32
45
392
473
Workshop
1
2
2
5
90% Project Completion
8
16
32
56
Workshop
1
2
2
5
Final Completion
8
16
24
4
40
0
20
64
Permitting (ATC, City, AOC)
32
20
52
Contractor Coordination / Bidding Assistance
4
8
12
Owner's Contingency
13
126
75
476
690
Team Members / Roles
Jacob Emmons - Engineer
Brandon Freeman - Technician
Janet Morrison - Project Assistant
Kim Tanner, PE - Principal, Civil Technical Expert
Zane Wilsterman, PE - Electrical, Instrumentation & Controls Technical Expert
Dane Whitmer, PE - Senior Engineer
TOTAL HOURS:
TASK DESCRIPTIONS
3. Design and Construction Documents
4. Allowances
EXHIBIT "B-2"
1. Provide Project Management (Project Phases 1 & 2 )
2. Conduct Limited Topographic Survey
TOTAL HOURS
PER TASK
< PROJECT
ROLE
< NAME OF
PERSON
< HOURLY
PHASE 1 - INVESTIGATION AND ALTERNATIVES DEVELOPMENT
Arcadis U.S., Inc.
410 N. 44th Street
Suite 1000
Phoenix
Arizona 85008
Tel 602 438 0883
Fax 602 438 0102
www.arcadis.com
Arcadis-Water
City of Chandler
Prepared by: D. Whitmer
Hunt Hwy WPF Rehabilitation
Task Item
Description
TASK 1-Project Management
Billing
Close Out
Kick off Meeting
Contact AHJ
Task 5
Task 2-Limited Topographic Survey
Surveyor Coordination and Site Walk
Site Survey
Survey Document Prep and Delivery
Task 3-Basis of Design Technical Memorandum
Draft Memo
Collect and identify City Standards,
materials, project definition
Workshop
Prepare Presentation and coordinate
meeting, City document review
Final Memo
Incorporate comments
Task 4 - Prepare Design and Construction
Documents
Digitize Record Drawing
Incorporate Survey Drawings
Prepare Base sheets and Specification TOC
Prepare 60% Documents
Civil/Mechanical/Electrical Plans and
Profiles, Progress Detail Sheets, Major
Specifications
Arcadis Internal Review
60% City Review
60% Arcadis Response
60% Workshop
Contact Permitting AHJ
Task 5: Prep discussions with AHJ to
coordinate submissions
Prepare 90% Documents
Incorporate City Comments
Review 60% comments and workshop for
incorporation
Review compliance of City and Industry Standards Includes update of Basis of Design Memo
Finalize details, address operational/constructability
Items
Final Coordination of specs and drawing consistency
90% City Review
90% Arcadis Response
90% Workshop
Prepare, submit to AHJs for permitting, AHJ review
Task 5
Prepare Final Documents
Final document reviews
Document Punch lists completion Incorporate AHJ comments
Submittal to the City
Notes:
Rev 1: 4/14/2021
1. Schedule does not account for Arcadis or City Holidays
Week 14
Exhibit B-3: Project Schedule
Weekending
Week 1
Week 2
Week 3
Week 4
Week 5
Week 6
Week 7
Week 8
Week 9
Week 10
Week 11
Week 12
Week 13
Week 21
Week 22
Week 23
Week 24
Week 15
Week 16
Week 17
Week 18
Week 19
Week 20
City of Chandler Professional Services Agreement – Exhibit “C”
Page C-1
Public Works & Utilities Department, Capital Projects Division
Project Name: HUNT HIGHWAY WATER PRODUCTION FACILITY GROUND SUBSIDENCE MITIGATION
Project No.: WA2107.201
Rev. 4/20/2021
EXHIBIT “C”
INSURANCE REQUIREMENTS
1.
General.
1.1 At the same time as execution of this Agreement, Consultant must furnish City a certificate
of insurance on a standard insurance industry ACORD form. The ACORD form must be
issued by an insurance company authorized to transact business in the State of Arizona
possessing a current A.M. Best, Inc. rating of A-7, or better and legally authorized to do
business in the State of Arizona with policies and forms satisfactory to City. Provided,
however, the A.M. Best rating requirement will not be deemed to apply to required Workers’
Compensation coverage.
1.2 Consultant and any of its subconsultants must procure and maintain, until all of their
obligations have been discharged, including any warranty periods under this Agreement are
satisfied, the insurances set forth below.
1.3 The insurance requirements set forth below are minimum requirements for this Agreement
and in no way limit the indemnity covenants contained in this Agreement.
1.4 City in no way warrants that the minimum insurance limits contained in this Agreement are
sufficient to protect Consultant from liabilities that might arise out of the performance of
the Agreement services under this Agreement by Consultant, its agents, representatives,
employees, subconsultants, and Consultant is free to purchase any additional insurance as
may be determined necessary.
1.5 Failure to demand evidence of full compliance with the insurance requirements in this
Agreement or failure to identify any insurance deficiency will not relieve Consultant from,
nor will it be considered a waiver of its obligation to maintain the required insurance at all
times during the performance of this Agreement.
1.6 Use of subconsultants: If any work is subcontracted in any way, Consultant must execute a
written contract with subconsultant containing the same Indemnification Clause and
Insurance Requirements as City requires of Consultant in this Agreement. Consultant is
responsible for executing the Agreement with the subconsultant and obtaining Certificates
of Insurance and verifying the insurance requirements.
2.
Minimum Scope and Limits of Insurance. Consultant must provide coverage with limits of
liability not less than those stated below.
2.1 Professional Liability. If the Agreement is the subject of any professional services or work
performed by Consultant, or if Consultant engages in any professional services or work
adjunct or residual to performing the work under this Agreement, Consultant must maintain
Professional Liability insurance covering errors and omissions arising out of the work or
services performed by Consultant, or anyone employed by Consultant, or anyone whose
acts, mistakes, errors and omissions Consultant is legally liable, with a liability limit of
$1,000,000 each claim and $2,000,000 all claims. In the event the Professional Liability
City of Chandler Professional Services Agreement – Exhibit “C”
Page C-2
Public Works & Utilities Department, Capital Projects Division
Project Name: HUNT HIGHWAY WATER PRODUCTION FACILITY GROUND SUBSIDENCE MITIGATION
Project No.: WA2107.201
Rev. 4/20/2021
insurance policy is written on a “claims made” basis, coverage must extend for 3 years past
completion and acceptance of the work or services, and Consultant, or its selected Design
Professional will submit Certificates of Insurance as evidence the required coverage is in
effect. The Design Professional must annually submit Certificates of Insurance citing that the
applicable coverage is in force and contains the required provisions for a 3 year period.
2.2 Commercial General Liability-Occurrence Form. Consultant must maintain “occurrence” form
Commercial General Liability insurance with a limit of not less than $2,000,000 for each
occurrence, $4,000,000 aggregate. Said insurance must also include coverage for products
and completed operations, independent contractors, personal injury and advertising injury.
If any Excess insurance is utilized to fulfill the requirements of this paragraph, the Excess
insurance must be “follow form” equal or broader in coverage scope than underlying
insurance.
2.3 Automobile Liability-Any Auto or Owned, Hired and Non-Owned Vehicles
Vehicle Liability: Consultant must maintain Business/Automobile Liability insurance with a
limit of $1,000,000 each accident on Consultant owned, hired, and non-owned vehicles
assigned to or used in the performance of Consultant’s work or services under this
Agreement. If any Excess or Umbrella insurance is utilized to fulfill the requirements of this
paragraph, the Excess or Umbrella insurance must be “follow form” equal or broader in
coverage scope than underlying insurance.
2.4 Workers Compensation and Employers Liability Insurance: Consultant must maintain Workers
Compensation insurance to cover obligations imposed by federal and state statutes having
jurisdiction of Consultant employees engaged in the performance of work or services under
this Agreement and must also maintain Employers’ Liability insurance of not less than
$1,000,000 for each accident and $1,000,000 disease for each employee.
3.
Additional Policy Provisions Required.
3.1 Self-Insured Retentions or Deductibles. Any self-insured retentions and deductibles must be
declared and approved by City. If not approved, City may require that the insurer reduce or
eliminate any deductible or self-insured retentions with respect to City, its officers, officials,
agents, employees, and volunteers.
3.1.1. Consultant’s insurance must contain broad form contractual liability coverage.
3.1.2. Consultant’s insurance coverage must be primary insurance with respect to City, its
officers, officials, agents, and employees. Any insurance or self-insurance maintained
by City, its officers, officials, agents, and employees will be in excess of the coverage
provided by Consultant and must not contribute to it.
3.1.3. Consultant’s insurance must apply separately to each insured against whom claim is
made or suit is brought, except with respect to the limits of the insurer's liability.
City of Chandler Professional Services Agreement – Exhibit “C”
Page C-3
Public Works & Utilities Department, Capital Projects Division
Project Name: HUNT HIGHWAY WATER PRODUCTION FACILITY GROUND SUBSIDENCE MITIGATION
Project No.: WA2107.201
Rev. 4/20/2021
3.1.4. Coverage provided by Consultant must not be limited to the liability assumed under
the indemnification provisions of this Agreement.
3.1.5. The policies must contain a severability of interest clause and waiver of subrogation
against City, its officers, officials, agents, and employees, for losses arising from Work
performed by Consultant for City.
3.1.6. Consultant, its successors and or assigns, are required to maintain Commercial
General Liability insurance as specified in this Agreement for a minimum period of 3
years following completion and acceptance of the Work. Consultant must submit a
Certificate of Insurance evidencing Commercial General Liability insurance during this
3 year period containing all the Agreement insurance requirements, including naming
City of Chandler, its agents, representatives, officers, directors, officials and
employees as Additional Insured as required.
3.1.7. If a Certificate of Insurance is submitted as verification of coverage, City will
reasonably rely upon the Certificate of Insurance as evidence of coverage but this
acceptance and reliance will not waive or alter in any way the insurance requirements
or obligations of this Agreement.
3.2. Insurance Cancellation During Term of Contract/Agreement.
3.2.1. If any of the required policies expire during the life of this Agreement, Consultant
must forward renewal or replacement Certificates to City within 10 days after the
renewal date containing all the required insurance provisions.
3.2.2. Each insurance policy required by the insurance provisions of this Agreement must
provide the required coverage and must not be suspended, voided or canceled
except after thirty (30) days prior written notice has been given to City, except when
cancellation is for non-payment of premium, then ten (10) days prior notice may be
given. Such notice must be sent directly to Chandler Law-Risk Management
Department, Post Office Box 4008, Mailstop 628, Chandler, Arizona 85225. If any
insurance company refuses to provide the required notice, Consultant or its
insurance broker must notify City of any cancellation, suspension, non-renewal of any
insurance within seven (7) days of receipt of insurers’ notification to that effect.
3.3
City as Additional Insured. The policies are to contain, or be endorsed to contain, the following
provisions:
3.3.1. The Commercial General Liability and Automobile Liability policies are to contain, or
be endorsed to contain, the following provisions: City, its officers, officials, agents,
and employees are additional insureds with respect to liability arising out of activities
performed by, or on behalf of, Consultant including City's general supervision of
Consultant; Products and Completed operations of Consultant; and automobiles
owned, leased, hired, or borrowed by Consultant.
City of Chandler Professional Services Agreement – Exhibit “C”
Page C-4
Public Works & Utilities Department, Capital Projects Division
Project Name: HUNT HIGHWAY WATER PRODUCTION FACILITY GROUND SUBSIDENCE MITIGATION
Project No.: WA2107.201
Rev. 4/20/2021
3.3.2. City, its officers, officials, agents, and employees must be additional insureds to the
full limits of liability purchased by Consultant even if those limits of liability are in
excess of those required by this Agreement.
City of Chandler Professional Services Agreement – Affidavit of Lawful Presence
Page AFF-1
Public Works & Utilities Department, Capital Projects Division
Project Name: HUNT HIGHWAY WATER PRODUCTION FACILITY GROUND SUBSIDENCE MITIGATION
Project No.: WA2107.201
Rev. 11/1/19
EXHIBIT “D”
SPECIAL CONDITIONS
Standard Details and Specifications. Consultant must be familiar with City’s latest revision of
the MAG Specifications and MAG Standard Details as amended by City. City’s current
amendment to the MAG Specifications, part of City’s Unified Development Manual, may be found
and downloaded from City’s website at http://www.chandleraz.gov/udm.
City Ownership of Project Documents. All work products (electronically or manually
generated) including, but not limited to: plans, specifications, cost estimates, field notes,
tracings, studies, investigations, design analyses, original drawings, original mylars, Computer
Aided Drafting and Design (CADD) file diskettes which reflect all final drawings, and other
related documents which are prepared in the performance of this Agreement (collectively
referred to as "Documents") are to be and remain the property of City and are to be delivered
to the Project Manager before the final payment is made to Consultant. In the event these
Documents are altered, modified or adapted without the written consent of Consultant,
which consent Consultant must not unreasonably withhold, City agrees to hold Consultant
harmless to the extent permitted by law from the legal liability arising out of City's alteration,
modification or adaptation of the Documents.
Re-use of Documents. The parties agree the documents, drawings, specifications and designs,
although the property of City, are prepared for this specific project and are not intended nor
represented by Consultant to be suitable for re-use for any other project. Any re-use without
written verification or adaptation by Consultant for the specific purpose intended will be at
City’s sole risk and without liability or legal exposure to Consultant.
Patent Fees and Royalties. Consultant must pay all license fees and royalties and assume all
costs incidental to the use, in the performance of the work or the incorporation in the work
of any invention, design, process, product, or device which is the subject of patent rights or
copyrights held by others. If a particular invention, design, process, product, or device is
specified in the Agreement for use in the performance of the work and if, to the actual
knowledge of City, its use is subject to patent rights or copyrights calling for the payment of
any license fee or royalty to others, the existence of such rights will be disclosed by City in the
Agreement. Consultant must defend, indemnify and hold harmless City and anyone directly
or indirectly employed by City from and against all claims, damages, losses, and expenses
(including attorneys’ fees) arising out of any infringement of patent rights or copyrights
incidental to the use in the performance of the work, or resulting from the incorporation in
the work of any invention, design, process, product, or device not specified in the Agreement,
and must defend all such claims in connection with any alleged infringement of such rights.
License to City for Reasonable Use. With this Agreement, Consultant and its subconsultants
hereby grant a license to City, its agents, employees, and representatives for an indefinite
period of time to reasonably use, make copies, and distribute as appropriate the Documents,
works or deliverables developed or created as a result of the Project and this Agreement. This
license also includes the making of derivative works.
City of Chandler Professional Services Agreement – Affidavit of Lawful Presence
Page AFF-2
Public Works & Utilities Department, Capital Projects Division
Project Name: HUNT HIGHWAY WATER PRODUCTION FACILITY GROUND SUBSIDENCE MITIGATION
Project No.: WA2107.201
Rev. 11/1/19
Documents to Bear Seal. Consultant and its subconsultants must endorse by professional
seal all plans, works, and deliverables prepared by each for this Agreement as required by
state law.