Parks Master Plan

City of Chandler — Work Session (2021-06-07)

View PDF Meeting page

Extracted text (via pymupdf) 10519 characters
Parks Master Plan Update   June 2021

Agenda
Public Support
Park Assessments
Levels of Service/Contribution Strategy and Equity Mapping
Strategic Direction
Questions

www.planchandlersparks.com
Project Website

• Only scientific and defensible method 
to understand community needs
• Administered by mail/phone/web
• Developed in partnership with the 
City
• Methodology allows high return rate 
(25%-35%)
• Total of 652 completed surveys, 95% 
level of confidence with a margin of 
error of +/- 3.8%                         
(Goal was 500)
Statistically-Valid Survey

Public Support

Support for Actions to Improve System

Actions Most Willing to Fund

Park Assessments

In general, the overall impression of the 
Department’s parks are as follows:
• Parks are clean, consistent and well-maintained
• Good variety of types and amenities
• Newer parks have unique character 
• More shade is needed
• Minor drainage and erosion issues
• Parking lots need of resurfacing
• Restrooms are aging
• Vehicular and pedestrian conflicts

In addition, Staff and the consultant 
team inventoried The City’s HOA parks 
and facilities:
• Over 800 Acres of Neighborhood Parks 
were identified and inventoried
• Developed HOA parks provide 36% of 
the total of publicly accessible 
developed park acreage in Chandler
CHANDLER HOA PARKS
AMENITY
QTY
BASKETBALL COURT (LIGHTED)
36
BASKETBALL COURT (NON-LIGHTED)
27
BEAN BAG TOSS (CORNHOLE)
4
BOCCE BALL / SHUFFLEBOARD 
COURT
22
DOG PARK
4
LAKE / POND (AC)
63
MULTIUSE COURT (LIGHTED)
2
MULTIUSE COURT (NON-LIGHTED)
1
OPEN TURF AREA
791
PICKLEBALL COURT
6
PLAYGROUND (NON-SHADED)
135
PLAYGROUND (SHADED)
105
POOL
79
PUTTING COURSE/ GREEN
2
RAMADA/ SHADE STRUCTURE
321
SPRAY PAD
3
TENNIS COURT (LIGHTED)
17
TENNIS COURT (NON-LIGHTED)
3
TRAIL - WALKING PATH
314
VOLLEYBALL COURT
25

Level of Service

Level of Service and Contribution Strategy Methodology
Level of Service population based standards are developed using 
a combination of local, regional and national resources, including:
• Current Level of Service and Utilization 
• Current Inventory and its condition ratings 
• Opportunity to acquire and develop/redevelop park land
• Recreation participation rates 
• Prioritization of Community Need
• Operational and Financial Sustainability

Trail and Conservation Park Assumptions
•
Population based standards are NOT developed for:
o Conservation Park Acreage
o Trail Miles
•
Conservation Park acquisition is based on resource 
location and opportunity to acquire this typology of park 
land rather than City population
•
Trail Miles is based on developing a connected network 
rather than City population

Current Inventory – Parks and Acreage
Recreation Component
City Inventory HOA/Other 
Inventory
Total   
Inventory
Current % 
of 
Inventory 
Provided 
by City
DEVELOPED PARKS
NEIGHBORHOOD PARKS
385.47
         
801.10
       
1,186.57
   
32%
4.26
     
 acres per
1,000
     
COMMUNITY PARKS
417.12
         
417.12
      
100%
1.50
     
 acres per
1,000
     
REGIONAL PARKS
211.10
         
211.10
      
100%
0.76
     
 acres per
1,000
     
SPECIAL USE PARKS
472.56
         
472.56
      
100%
1.70
     
 acres per
1,000
     
Total
1,486.25
     
801.10
     
2,287.35
 
65%
8.22
    
acres per
1,000
    
Current Service Level 
 2020 Inventory 
 Service Levels

Future Needs – Parks and Acreage
Recreation Component
% of Future Inventory 
Recommended to be 
Provided by City to 
Meet Needs
% of Future Inventory 
Recommended to be 
Provided by City to 
Meet Needs
PARKS AND SPECIAL USE FACILITIES
NEIGHBORHOOD PARKS
4.50  acres per
1,000
      
20%
33
           
Acre(s)
20%
94
           
Acre(s)
COMMUNITY PARKS
1.55  acres per
1,000
      
100%
48
           
Acre(s)
100%
153
         
Acre(s)
REGIONAL PARKS
1.80  acres per
1,000
      
100%
329
         
Acre(s)
100%
451
         
Acre(s)
SPECIAL USE PARKS
0.65  acres per
1,000
      
100%
-
             
Acre(s)
100%
-
             
Acre(s)
Total
8.50 acres per
1,000
     
409
       
Acre(s)
698
       
Acre(s)
 City Contribution Level - Full Build Out 
 Additional Facilities 
Needed (Chandler 
Contribution) 
 Additional Facilities 
Recommended 
 2035 Standards (City Contribution 
Level) 
Recommended Service 
Levels
 Service Levels

Future City of Chandler Parks and Opportunities 
Recreation Component
Current 
Inventory
Strategic 
Changes to 
Existing Park 
System
Future Planned 
Park 
Development
Total Inventory 
After 
Implementation
PARKS AND SPECIAL USE FACILITIES
NEIGHBORHOOD PARKS
1,186.57
       
7.60
                
1,194.17
          
COMMUNITY PARKS
417.12
          
53.27
              
470.39
             
REGIONAL PARKS
211.10
          
235.00
            
98.40
              
544.50
             
SPECIAL USE PARKS
472.56
          
(235.00)
          
237.56
             
Total
2,287.35
     
-
               
159.27
         
2,446.62
       
 Inventory

Future Needs – Athletic Fields
Recreation Component
% of Future Inventory 
Recommended to be 
Provided by City to 
Meet Needs
% of Future Inventory 
Recommended to be 
Provided by City to 
Meet Needs
OUTDOOR AMENITIES
BASEBALL FIELD (LIGHTED)
1.00 Field per 
13,000
    
100%
3
             
Field
100%
8
             
Field
MULTIUSE FIELD (LIGHTED)
1.00 Field per
10,000
    
100%
8
             
Field
100%
15
           
Field
SOFTBALL FIELD  (LIGHTED)
1.00 Field per
25,000
    
100%
3
             
Field
100%
6
             
Field
CRICKET FIELD
1.00 Field per
150,000
  
100%
1
             
Field
100%
1
             
Field
 City Contribution Level - Full Build Out 
 Additional Facilities 
Needed (Chandler 
Contribution) 
 Additional Facilities 
Recommended 
 2035 Standards (City Contribution 
Level) 
Recommended Service 
Levels
 Service Levels

Future Needs – Sport Courts
Recreation Component
% of Future Inventory 
Recommended to be 
Provided by City to 
Meet Needs
% of Future Inventory 
Recommended to be 
Provided by City to 
Meet Needs
OUTDOOR AMENITIES
BASKETBALL COURT (LIGHTED)
1.00 Court per
4,500
      
50%
-
             
Court
50%
3
             
Court
PICKLEBALL COURT
1.00 Court per
12,000
    
50%
5
             
Court
50%
8
             
Court
TENNIS COURT (LIGHTED)
1.00 Court per
7,000
      
70%
1
             
Court
70%
7
             
Court
VOLLEYBALL COURT (SAND/GRASS)
1.00 court per
7,500
      
50%
-
             
Court
50%
-
             
Court
 City Contribution Level - Full Build Out 
 Additional Facilities 
Needed (Chandler 
Contribution) 
 Additional Facilities 
Recommended 
 2035 Standards (City Contribution 
Level) 
Recommended Service 
Levels
 Service Levels

Future Needs – Traditional Amenities
Recreation Component
% of Future Inventory 
Recommended to be 
Provided by City to 
Meet Needs
% of Future Inventory 
Recommended to be 
Provided by City to 
Meet Needs
OUTDOOR AMENITIES
DOG PARK
1.00 Site per
30,000
    
50%
1
             
Site
50%
2
             
Site
PLAYGROUNDS
1.00 Site per
1,050
      
25%
-
             
Site
25%
4
             
Site
RAMADA
1.00 Site per
750
         
33%
-
             
Site
33%
5
             
Site
 City Contribution Level - Full Build Out 
 Additional Facilities 
Needed (Chandler 
Contribution) 
 Additional Facilities 
Recommended 
 2035 Standards (City Contribution 
Level) 
Recommended Service 
Levels
 Service Levels

Future City of Chandler Parks and Opportunities – Impact on Need 
Recreation Component
Meet Standard/
Need Exists
Meet Standard/
Need Exists 
PARKS AND SPECIAL USE FACILITIES
NEIGHBORHOOD PARKS
Need Exists
33
           
Acre(s)
Need Exists
13
            
Acre(s)
COMMUNITY PARKS
Need Exists
48
           
Acre(s)
Meets Standard
-
               
Acre(s)
REGIONAL PARKS
Need Exists
329
         
Acre(s)
Meets Standard
-
               
Acre(s)
SPECIAL USE PARKS
Meets Standard
-
             
Acre(s)
Meets Standard
-
               
Acre(s)
Total
Need Exists
409
       
Acre(s)
Need Exists
13
           
Acre(s)
 2035 Needs BEFORE STRATEGIC 
CHANGES and  FUTURE PLANNED 
PARKLAND DEVELOPMENT 
 2035 Needs AFTER  STRATEGIC 
CHANGES and                        
FUTURE PLANNED PARKLAND 
DEVELOPMENT 
 Additional Facilities 
Recommended  
 Additional Facilities/
Amenities Needed

Equity Mapping

Neighborhood Park Map – City Only

Neighborhood Park Map - HOA

Neighborhood Park Map - Combined

Community Parks

Regional Park

Special Use Parks

Baseball Fields – Lighted

Softball Fields – Lighted

Multi-Purpose Fields Lighted

Outdoor Basketball Courts - Lighted

Tennis Courts - Lighted

Pickleball Courts

Ramadas

Off Leash Dog Parks

Playgrounds

Accessibility and Proximity Standards
PARK TYPE
WALK/BIKE SERVICE AREA
DRIVE TIME SERVICE AREA
Neighborhood
5 to 10-minute walk/bike time;
busstopwithin¼-mile, preferred
Less than 10 minutes
Community
10 to 15-minute walk/bike time
10 to 20-minute drive time
Regional
Greater than 30-minute 
walk/bike time
30 to 60-minute drive time
• Further service delivery analysis should be undertaken to ensure 
equitable access to parks and recreation facilities.
•
Bike and Trails Master Plan

Strategic Direction

Areas of Focus 
•
Improve Access to parks and trails and Maintain Quality
•
Increase Connectivity in alignment with Transportation 
Master Plan
•
Invest in Existing Resources
•
Create an Economic Catalyst
•
Ensure Operational, Environmental and Financial 
Sustainability

Highest Priority Recommendations
• Prioritize lifecycle replacement of assets in parks
• Provide significant renovations at aging parks 
• Complete a renovation of Folley Park 
• Continue improvements to Snedigar Sports Complex

Highest Priority Recommendations
• Consider the development of an updated site-specific master 
plan for Desert Breeze Park
• Continue to implement the master plan for Tumbleweed 
Park
• Complete the development of planned parks (Lantana, 
Mesquite Grove and Homestead North Parks)
• Continue to be a regional partner in Sports Tourism

Other Priority Recommendations
• Consider a pilot project of converting one athletic field to synthetic turf 
• Develop a Bike/Trails Master Plan in alignment with Transportation Master 
Plan
• Conduct a sports tourism feasibility study to include current park assets and 
impact of new facilities being built in surrounding communities 
• Conduct a feasibility study and site-specific master plan for the 
redevelopment of South Chandler Regional Parks
• Consider exploring options with private developers to meet park needs in 
north Chandler and other parts of the City as needed