City of Chandler, Arizona 
Report on Applying Agreed-Upon Procedures 
Biennial Certification of Land Use Assumptions, 
Infrastructure Improvement Plan 
and Impact Fees 
For the Period July 1, 2018 through June 30, 2020

CITY OF CHANDLER, ARIZONA 
TABLE OF CONTENTS 
CONTENTS
PAGE 
Independent Accountant’s Report on Applying Agreed-Upon Procedures 
      1 
Results of Procedures 
     3 
Appendix A – Progress of Infrastructure Improvement Plan Projects  
      7

INDEPENDENT ACCOUNTANT’S REPORT ON 
APPLYING AGREED-UPON PROCEDURES 
Honorable Mayor and Members of the City Council 
City of Chandler, Arizona 
We have performed this agreed-upon procedures engagement to assist management of the City of 
Chandler, Arizona (City), with the requirement set forth in Arizona Revised Statutes (A.R.S.) 
9-463.05.G.2 “to provide for a biennial certified audit of the municipality’s land use assumptions,
infrastructure improvements plan and development fees.” As such, we have performed the
procedures identified below, solely to assist users in evaluating the City’s compliance with the
progress reporting requirements of the infrastructure improvement plan for the period from
July 1, 2018 through June 30, 2020, as specified in A.R.S. 9-463.05.G.2. City of Chandler,
Arizona’s management is responsible for its compliance with those requirements.
City of Chandler, Arizona’s management has agreed to and acknowledged that the procedures 
performed are appropriate to meet the intended purpose of assisting users in determining whether 
the City complied with the specified requirements. This report may not be suitable for any other 
purpose. The procedures performed may not address all the items of interest to a user of this report 
and may not meet the needs of all users of this report and, as such, users are responsible for 
determining whether the procedures performed are appropriate for their purposes. 
We have applied the following procedures:  
The progress of the infrastructure improvements plan. 
a.
Compared growth projections for 2019 and 2020 related to dwelling units, population,
and the various commercial square footage units as reported in the Infrastructure
Improvement Plan (IIP) to actual results for the proportionate 10-year projections. A
list of all variances are reported in the Results of Procedures.
b.
Obtained City-prepared report (see Appendix A) documenting the progress of each
project identified in the Infrastructure Improvement Plan (IIP) and performed the
following procedures:
i.
Agreed expenditures as of June 30, 2020 to the underlying accounting records.
ii.
Agreed amounts reported as estimated cost to complete to underlying
accounting records.
The collection and expenditures of impact fees for each project in the plan. 
c.
Selected a sample of 80 building permits issued and determined fees were charged in
accordance with authorized fee schedules and that each permit holder was charged the
same rate as another equivalent permit holder.
d.
Selected a sample of 50 expenditures and determined that the expenditures were
associated with an approved project in the City’s IIP.
Page 1

Evaluating any inequities in implementing the plan or imposing the impact fee. 
e.
Evaluated any inequities in implementing the plan or imposing the impact fee through
recalculating impact fees at the transaction level for the sample mentioned in procedure
c above.
f.
Determined that there were no instances in which the City waived impact fees, except
as allowed for under A.R.S. 9-499.10.B and A.R.S. 9-500.18.
The accompanying Results of Procedures describes the items we noted. 
We were engaged by City of Chandler, Arizona’s management to perform this agreed-upon 
procedures engagement and conducted our engagement in accordance with attestation standards 
established by the American Institute of Certified Public Accountants.  We were not engaged to 
and did not conduct an examination or review engagement, the objective of which would be the 
expression of an opinion or conclusion, respectively, on compliance with the specified 
requirements. Accordingly, we do not express such an opinion or conclusion.  Had we performed 
additional procedures, other matters might have come to our attention that would have been 
reported to you. 
We are required to be independent of City of Chandler, Arizona’s management and to meet our 
other ethical responsibilities, in accordance with the relevant ethical requirements related to our 
agreed-upon procedures engagement.  
This report is intended solely for the information and use of the management of City of Chandler, 
Arizona, and is not intended to be and should not be used by anyone other than these specified 
parties. 
Heinfeld, Meech & Co., P.C. 
Scottsdale, Arizona 
August 9, 2021 
 
Page 2

CITY OF CHANDLER, ARIZONA 
RESULTS OF PROCEDURES 
PROCEDURE A 
Compared growth projections for 2019 and 2020 related to dwelling units, population, and the 
various commercial square footage units as reported in the City’s Land Use Assumptions and 
Infrastructure Improvements Plan (IIP) to actual current amounts for the proportionate 10-year 
projections. A list of all variances will be reported. 
Exception: 
Variances were noted for growth projections for dwelling units, population, and the various 
commercial square footage as reported in the Land Use Assumptions and Infrastructure 
Improvements Plan when compared to actual results.  
Management Response: 
Assumptions of equal growth of land development and the resulting fees averaged over a set 
period of time do not reflect the reality of how development occurs.  Variances exist due to 
market conditions, demand for various types of land use and structures, the condition of the 
economy, and the availability of capital. The City of Chandler continues to take into account 
annual planning projections, entitled projects, and variations in construction permits to augment 
the equal growth assumptions when forecasting.   
TOTAL SQUARE FOOTAGE 
Note: The cumulative projected amounts for square footage assume equal growth for each year 
of the 10-year period with the incremental cumulative total presented for each year. 
Cumulative Total as of 2019 
 
Projected 
Actual 
 
Variance 
 Variance % 
Industrial 
Citywide
36,000,333
34,985,871
(1,014,462)
-3%
Arterial Streets 
16,579,846
14,944,267
(1,635,579)
-10%
Institutional 
Citywide
12,532,455
11,431,010
(1,101,445)
-9%
Arterial Streets 
6,565,177
6,436,229
(128,948)
-2%
Office 
Citywide
9,190,908
8,834,429
(356,479)
-4%
Arterial Streets 
3,698,064
4,358,388
660,324 
18%
Retail 
Citywide
18,592,700
18,800,613
207,914 
1%
Arterial Streets 
7,596,680
8,224,186
627,506 
8% 
Page 3

CITY OF CHANDLER, ARIZONA 
RESULTS OF PROCEDURES 
PROCEDURE A (Continued) 
TOTAL SQUARE FOOTAGE 
Cumulative Total as of 2020 
 
Projected 
 
Actual 
 
Variance 
 Variance % 
Industrial 
Citywide 
36,898,172  
36,049,567  
(848,605) 
-2%
Arterial Streets 
17,296,903  
15,920,562  (1,376,341) 
-8%
Institutional 
Citywide 
12,606,943  
11,807,767  
(799,176) 
-6%
Arterial Streets 
6,641,469  
6,802,070  
160,601 
2%
Office 
Citywide
 
9,663,449  
9,288,568 
(374,881) 
-4%
Arterial Streets 
3,931,666  
4,691,153  
759,487 
19% 
Retail 
Citywide 
18,755,614  
18,913,407  
157,793 
1% 
Arterial Streets 
7,723,592  
8,311,712  
588,120 
8% 
TOTAL HOUSING UNITS AND POPULATION BY SERVICE AREA 
Note: The cumulative projected amounts for housing units and population assume equal growth 
for each year of the 10-year period with the incremental cumulative total presented for each 
year. 
Cumulative Total as of 2019 
 
Projected 
 
Actual 
 
Variance 
 Variance % 
Single Family 
Parks Northwest 
 
11,709  
11,770 
61 
1% 
Parks Northeast 
 
34,785  
35,113 
328 
1% 
Park Southeast 
 
32,557  
33,148 
592 
2% 
Citywide 
 
79,051  
80,031 
980 
1% 
Arterial Streets 
 
43,345  
50,318 
6,973 
16% 
MultiFamily 
Parks Northwest 
 
4,959  
5,189 
230 
5% 
Parks Northeast 
 
16,256  
17,016 
760 
5% 
Park Southeast 
 
7,164  
7,964 
800  
11% 
Citywide 
 
28,379  
30,169 
1,790 
6% 
Arterial Streets 
 
11,200  
14,613 
3,414 
30% 
Resident Population 
Parks Northwest 
 
42,206  
41,638 
(568) 
-1%
Parks Northeast 
 
128,285  
127,136 
(1,149) 
-1%
Park Southeast 
 
104,771  
104,631 
(140) 
0%
Citywide 
 
275,262  
273,405 
(1,857) 
-1%
Arterial Streets 
142,644 
163,623 
20,979 
15%
Page 4

CITY OF CHANDLER, ARIZONA 
RESULTS OF PROCEDURES 
PROCEDURE A (Continued) 
Cumulative Total as of 2020 
 
Projected 
 
Actual 
 
Variance 
 Variance % 
Single Family 
Parks Northwest 
 
11,715  
11,780 
65 
1% 
Parks Northeast 
 
34,838  
35,169 
331 
1% 
Park Southeast 
 
32,710  
33,241 
531 
2% 
Citywide 
 
79,263  
80,190 
927 
1% 
Arterial Streets 
 
43,491  
50,466 
6,975 
16% 
MultiFamily 
Parks Northwest 
 
4,967  
5,324 
357 
7% 
Parks Northeast 
 
16,698  
17,151 
453 
3% 
Park Southeast 
 
7,164  
8,389  
1,225  
17% 
Citywide 
 
28,829  
30,864 
2,035 
7% 
Arterial Streets 
 
11,257  
15,173 
3,916 
35% 
Resident Population 
Parks Northwest 
 
42,238  
41,922 
(316) 
-1%
Parks Northeast 
 
129,271  
127,543 
(1,728) 
-1%
Park Southeast 
 
104,771  
105,690 
919  
1%
Citywide 
 
276,280  
275,155 
(1,125) 
0%
Arterial Streets 
143,164 
165,087 
21,923  
15% 
PROCEDURE B 
Obtained City-prepared report (see Appendix A) documenting the progress of each project 
identified in the Infrastructure Improvement Plan (IIP) and performed the following procedures: 
a.
Agreed expenditures as of June 30, 2020 to the underlying accounting records.
b. Agreed amounts reported as estimated cost to complete to underlying accounting
records.
No exceptions noted. 
PROCEDURE C 
Selected a sample of 80 building permits issued and determine fees were charged in accordance 
with authorized fee schedules and that each permit holder is charged the same rate as another 
equivalent permit holder.  
No exceptions noted. 
PROCEDURE D 
Selected a sample of 50 expenditures and determine that the expenditure was associated with an 
approved project in the City’s IIP. 
No exceptions noted. 
Page 5

CITY OF CHANDLER, ARIZONA 
RESULTS OF PROCEDURES 
PROCEDURE E 
Evaluated any inequities in implementing the plan or imposing the impact fee through 
recalculating impact fees at the transaction level for the sample mentioned in procedure c above. 
No exceptions noted. 
PROCEDURE F 
Determined that there were no instances in which the City waived impact fees, except as allowed 
for under A.R.S. 9-499.10.B and A.R.S. 9-500.18 
No exceptions noted. 
Page 6

APPENDIX A
PROGRESS OF INFRASTRUCTURE IMPROVEMENT PLAN PROJECTS
Fund
Description
415 Arterial Street Impact Fees
2013‐14
2014‐15
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
 2020‐21 
though 
2029‐30* 
Total
6ST311‐Price Rd and Queen Creek Intersection
‐ 
‐ 
‐ 
‐ 
(190,862)
             
‐ 
‐ 
‐ 
(190,862)
               
6ST478‐McQueen Rd (Queen Creek Rd to Riggs Rd)
693,261
 
365,149
            
401,157
              
722,149
              
542
 
‐ 
‐ 
‐ 
2,182,258
             
6ST482‐Gilbert Rd (Germann Rd to Queen Creek Rd)
‐ 
‐ 
‐ 
‐ 
(127,921)
             
‐ 
‐ 
‐ 
(127,921)
               
6ST548‐Queen Creek Rd (McQueen Rd to Gilbert Rd)
‐ 
‐ 
‐ 
262,288
              
246,143
              
601,762
              
2,100,347
           
‐ 
3,210,541
             
6ST596‐Gilbert Rd (Queen Creek Rd to Riggs Rd)
8,547,368
               
3,297,428
        
484,152
              
20,705
                
‐ 
‐ 
‐ 
‐ 
12,349,653
           
6ST607‐Ocotillo Rd (Arizona Ave to McQueen Rd)
1,335,663
               
2,245,004
        
659,940
              
490
 
‐ 
(1,011)
 
‐ 
‐ 
4,240,085
             
6ST608‐Chandler Heights (Arizona Ave to McQueen Rd)
‐ 
3,775
                
32,904
                
114,167
              
570,702
              
‐ 
1,182,277
           
‐ 
1,903,825
             
6ST641‐Ocotillo Rd (Cooper Rd to 148th St)
‐ 
‐ 
147,647
              
513,530
              
1,670,914
           
‐ 
334,675
              
3,050,000
            
5,716,766
             
6ST675‐Cooper Rd (Queen Creek Rd to Riggs Rd)
‐ 
2,830
                
13,741
                
27,077
                
160,594
              
‐ 
45,614
                
‐ 
249,856
                
6ST692‐Chandler Heights Rd (McQueen Rd to Val Vista Dr)
‐ 
‐ 
‐ 
‐ 
181,765
              
469,687
              
119,741
              
19,966,977
          
20,738,170
           
6ST693‐Lindsay Rd (Ocotillo Rd to Hunt Hwy)
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
17,915
                
18,589,500
          
18,607,415
           
6ST738‐Gilbert Rd (Ocotillo Rd to Chandler Heights Rd)
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
213,989
              
‐ 
213,989
                
6ST745‐Alma School Rd (Chandler Blvd to Pecos Rd)
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
2,097,600
            
2,097,600
             
6ST746‐Alma School Rd (Pecos Rd to Germann Rd)
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
176,985
              
2,805,100
            
2,982,085
             
6ST747‐Alma School Rd (Germann Rd to Queen Creek Rd)
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
2,771,600
            
2,771,600
             
*As programmed in 2021‐2030 CIP
421 Community Park Impact Fees
2013‐14
2014‐15
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
Total
6PR396‐Mesquite Groves Park
1,310
 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
1,310
 
Note:  This fund was expended and closed as of 6/30/17.
422 Neighborhood Parks Impact Fees
2013‐14
2014‐15
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
Total
6PR039‐Neighborhood Park Land Acquisition
478
 
869
 
3,087
 
‐ 
‐ 
‐ 
‐ 
4,434
 
6PR389‐Homestead North Park Site
‐ 
‐ 
‐ 
‐ 
‐ 
22,445
                
72,723
                
95,168
 
6PR400‐Roadrunner Park
400,208
 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
400,208
                
6PR631‐Centennial Park Site
68,764
 
11,553
              
‐ 
‐ 
‐ 
‐ 
‐ 
80,317
 
Note:  This fund was expended and closed as of 6/30/20.
424 Park Impact Fees
2013‐14
2014‐15
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
 2020‐21 
though 
2029‐30* 
Total
6PR389‐Homestead North Park Site
‐ 
‐ 
‐ 
‐ 
‐ 
27,588
                
25,564
                
‐ 
53,151
 
6PR390‐Homestead South Park Site
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
6PR396‐Mesquite Groves Park Site
‐ 
3,764
                
‐ 
‐ 
‐ 
‐ 
‐ 
6,056,137
            
6,059,901
             
6PR400‐Roadrunner Park Site
716,453
 
5,872
                
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
722,326
                
6PR420‐Veteran's Oasis Park Site
‐ 
‐ 
‐ 
‐ 
(59,740)
               
‐ 
‐ 
‐ 
(59,740)
 
6PR631‐Centennial Park Site
702,813
 
678,786
            
12,843
                
4,672
 
‐ 
‐ 
‐ 
‐ 
1,399,114
             
6PR638‐Valencia Park Site
545,550
 
817,682
            
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
1,363,232
             
6PR639‐Citrus Vista Park Site
‐ 
278,330
            
1,412,990
           
4,995
 
‐ 
‐ 
‐ 
‐ 
1,696,315
             
6PR640‐Layton Lakes Park Site
‐ 
‐ 
‐ 
141,285
              
1,191,476
           
139,376
              
‐ 
‐ 
1,472,137
             
*As programmed in 2021‐2030 CIP
Fiscal Year
Note: Any negative amounts presented are expense recoveries from prior years.
Page 7

APPENDIX A
PROGRESS OF INFRASTRUCTURE IMPROVEMENT PLAN PROJECTS
Fund
Description
425 Parks NW Impact Fees
2013‐14
2014‐15
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
 2020‐21 
though 
2029‐30** 
Total
None
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
**No growth‐related capital to construct; collecting fees to repay pledged debt
426 Parks NE Impact Fees
2013‐14
2014‐15
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
 2020‐21 
though 
2029‐30** 
Total
None
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
**No growth‐related capital to construct; collecting fees to repay pledged debt
427 Parks SE Impact Fees
2013‐14
2014‐15
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
 2020‐21 
though 
2029‐30* 
Total
6PR396‐Mesquite Groves Park Site
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
4,372,763
            
4,372,763
             
6PR629‐Lantana Ranch Park Site
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
88,854
                
7,955,214
            
8,044,068
             
*As programmed in 2021‐2030 CIP
465 Police Impact Fees
2013‐14
2014‐15
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
 2020‐21 
though 
2029‐30** 
Total
6PD243‐Chandler Heights Subtation
‐ 
‐ 
‐ 
‐ 
(59,740)
               
‐ 
‐ 
‐ 
(59,740)
 
**No growth‐related capital to construct; collecting fees to repay pledged debt
475 Fire Impact Fees
2013‐14
2014‐15
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
 2020‐21 
though 
2029‐30** 
Total
6FI611‐Southeast Fire Station
‐ 
‐ 
797
 
361,261
              
3,579,131
           
295,842
              
‐ 
‐ 
4,237,031
             
6FI638‐Fire Station No. 1 Relocation
‐ 
3,164,000
        
147,100
              
‐ 
‐ 
‐ 
‐ 
‐ 
3,311,100
             
**No growth‐related capital to construct; collecting fees to repay pledged debt
603 Water System Development Fees
2013‐14
2014‐15
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
 2020‐21 
though 
2029‐30** 
Total
6WA029‐Water Master Plan Update
‐ 
6,609
                
‐ 
133,055
              
56,495
                
1,553
 
‐ 
‐ 
197,712
                
6WA034‐Well Construction/Rehabilitation
486,660
 
505,275
            
2,260,447
           
1,807,500
           
894,025
              
718,077
              
1,637,212
           
‐ 
8,309,195
             
6WA076‐Transmission Mains
1,986,478
               
238,624
            
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
2,225,102
             
6WA334‐Joint Water Treatment Plant
‐ 
356
 
‐ 
6,418,629
           
19,857,848
        
1,639,976
           
1,020,748
           
‐ 
28,937,557
           
6WA672‐Water Purchases
‐ 
‐ 
‐ 
9,999,788
           
4,999,940
           
4,999,940
           
14,731,755
        
‐ 
34,731,423
           
**No growth‐related capital to construct; collecting fees to repay pledged debt
604 Water Resource System Development Fees
2013‐14
2014‐15
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
Total
6WW661‐Ocotillo Water Reclamation Facility Expansion
‐ 
‐ 
748,052
              
2,763,414
           
488,533
              
‐ 
‐ 
4,000,000
             
6WA672‐Water Purchases
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
128,827
              
128,827
                
Note:  This fund was expended and closed as of 6/30/20.
Fiscal Year
Page 8

APPENDIX A
PROGRESS OF INFRASTRUCTURE IMPROVEMENT PLAN PROJECTS
Fund
Description
610 Reclaimed Water System Development Fees
2013‐14
2014‐15
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
 2020‐21 
though 
2029‐30* 
Total
6WW189‐Effluent Reuse‐Storage
68,757
 
335,111
            
97,991
                
876,519
              
15,513
                
151,138
              
294,279
              
2,010,000
            
3,849,308
             
6WW192‐Effluent Reuse‐Transmission Mains
441,068
 
464,587
            
1,422,386
           
158,361
              
868,974
              
3,198,432
           
212,433
              
‐ 
6,766,243
             
*As programmed in 2021‐2030 CIP
614 Wastewater System Development Fees
2013‐14
2014‐15
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
 2020‐21 
though 
2029‐30** 
Total
6WW021‐Wastewater Master Plan Update
181,812
 
25,191
              
157,935
              
266,114
              
112,989
              
3,107
 
‐ 
‐ 
747,148
                
6WW022‐Water Reclamation Facility Expansion
3,806,769
               
292,665
            
20,126
                
540
 
‐ 
‐ 
‐ 
‐ 
4,120,101
             
6WW196‐Collection System Facility Improvements
2,447,175
               
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
2,447,175
             
6WW651‐Wastewater Land Acquistion
5,560,271
               
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
5,560,271
             
6WW642‐South Chandler Sewer Line Expansion
2,777
 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
2,777
 
6WW661‐Ocotillo Water Reclamation Facility Expansion
‐ 
6,268,168
        
19,505,029
        
79,677,431
        
14,085,867
        
‐ 
‐ 
‐ 
119,536,496
        
**No growth‐related capital to construct; collecting fees to repay pledged debt
Fiscal Year
Page 9