November 2021 Transportation Commission Project Status Update
Extracted text (via pymupdf)
4234 characters
Projects Designer Contractor Status Comments ROADWAY AND TRAFFIC PROJECTS ST1503, Cooper Road Imprv. [Alamosa Drive (aprx. 3,500 ft. north of Chandler Heights Road) to Riggs Road for two through lanes each direction] Entellus Pulice Construction Construction underway. Completion scheduled for mid 2022. Federal funds ST1614, Chandler Heights Road Imprv. [McQueen Road to Gilbert Road for two through lanes each direction] Kimley-Horn tbd Design in progress. Bid scheduled for Fall 2021. Federal funds ST1616, Ocotillo Road Imprv. [Gilbert Road to 148th Street for two through lanes each direction] Ritoch-Powell tbd Design in progress. Bid scheduled for Fall 2021. Federal funds ST1804, Chandler Heights Road Imprv. [Gilbert Road to Val Vista Drive for two through lanes each direction] Kimley-Horn tbd Design in progress. Bid scheduled for Spring 2023. Federal funds ST1908, Bicycle Detection System [40 intersections] n/a n/a Purchase of bicycle detection cameras Federal funds ST1909, Alleyway Rehab PM10 Dust Emission Reduction n/a Cactus Asphalt Construction underway. Federal funds ST2001, Lindsay Road Imprv. [Ocotillo Road to Hunt Highway for two through lanes in each direction] Kimley-Horn tbd Design in progress. Bid scheduled for summer 2023. Federal funds ST2002, Traffic Study of Kyrene Road [Chandler Boulevard to Loop 202] AZTEC n/a Study in progress. ST2003, Gilbert Road Imprv. [Ocotillo Road to Chandler Heights Road for new traffic signals and three through lanes in each direction] Sunrise Engineering Sunland Asphalt Construction complete. ST2004, Alma School Road Imprv. [Pecos Road to Germann Road for three through lanes in each direction to match development imprv.] Wood Sunland Asphalt Construction underway. ST2006, Traffic Signal at Warner Road and Nevada Street Stanley Consultants tbd Design in progress. Bid scheduled for September 2021. ST2007, Hamilton Street Imprv. [Appleby Road to Carob Drive] Nfra Consultants tbd Design in progress. Construction in 2022 ST2009, Dobson Road Imprv. at Intel Driveways #1 and #4 [Price Rd / Market Pl to Chaparral Way] Premier DCS Contracting Design in progress. Funded by 20% from Intel and 80% from State TPT per ARS 42-5032.02 ST2012, Arterial Congestion Monitoring [Install data collection devices at major intersections, and use data to map traffic congestion and mobility.] Y.S. Mantri & Assoc. tbd Design in progress. Grant funds ST2103, Intersection Imprv. at Ray Road and Dobson Road tbd tbd Study to begin in Winter 2021/22. Study only. Future phases tbd. ST2104, Traffic Signal at Ocotillo Road and Pinelake Way Y2K Engineering tbd Design in progress. ST2113, Alley Rehab PM10 Dust Emissions Reduction 2 (FMA Areas 16, 25, 39, and 40) Premier / Olsson tbd Design in progress. Federal funds PEDESTRIAN, BICYCLE, AND TRANSIT PROJECTS ST1612, Chandler Boulevard Bike Lanes [I-10 to 56th Street] Kimley-Horn Combs Construction Construction underway. Completion scheduled for Fall 2021 Federally funded ST1613, Downtown ADA Improvements [Downtown Chandler on Chicago Street, Washington Street, and Boston Street] J2 DNG Phase I construction complete. Phase II construction underway. Completion scheduled for Fall 2021. Locally funded. ST1701, McClintock Drive Bike Lanes [Loop 202 to north of Ray Road] & Kyrene Road Bike Lanes - [Chandler Boulevard to north of Ray Road] Aztec AJP Electric Construction complete. Federally funded ST2011, Study of Price Road, Ocotillo Road, and Chandler Heights Road Separated Bike Lanes TY Lin n/a Study in progress. Study was put on hold temporarily to amend contract to allow for addition of Chandler Heights Road analysis. Awarded design assistance grant for FY2020 ST2016, Park & Ride Shade Canopies, Phase 2 [two parking canopies covering 40 parking spaces & electric vehicle charging station] LEA-Architects TSG Constructors Design complete. Construction scheduled to begin September 2021. Funded with State Lottery Proceeds ST2106, Frye Road Protected Bike Lanes [Paseo Trail to San Marcos Elementary School] Y2K tbd Study completed by Y2K. Design in FY2022. Construction in FY2023. $3.2 Million grant awarded for construction and $400,000 for design. Transportation Project Status November 10, 2021