                   Police Station Main Lobby and Records Renovations CO 1 
CITY OF CHANDLER 
CHANGE ORDER NO. 
1 
 
DATE 
10/11/2021 
 
 
Change Order not valid until signed by both the City and the Contractor.  Contractor’s signature indicates 
agreement herewith, including any adjustments in the Contract Price or Contract Time.   
Project Name: 
Police Station Main Lobby and Records Renovations 
Project No.: 
PD1901.401 
User Dept.: 
Police Department 
NTP Date: 
9/27/21 
 
 
TO: 
Caliente Construction, Inc. 
 
485 W. Vaughn St, Tempe, AZ 85283 
 
(CONTRACTOR) 
 
(Address) 
Contractor must make the following changes to this contract: (Detail scope change (Exh. A) / cost 
breakdown (Exh. B), if needed) 
This change order will install a new fan coil unit associated with the chilled water and make changes 
to the existing duct work in the Men’s Locker Room at the Police Station.      
OWNER NAME & DATE APPROVAL:  
Mike Hollingsworth 10/22/21 
Changes result in the following revised contract amount and time: 
Original contract amount: 
$1,321,730.47 
Current contract amount, prior to this Change Order: (incl. previous Change 
Orders) 
$1,321,730.47 
Net change resulting from this Change Order: (if over $50,000 from contract 
amount previously approved by Council, Council approval is required)  
$96,410.76 
Revised contract amount, including this Change Order: 
$1,418,141.23 
Last contract amount approved by Council:  
$1,321,730.47 
Change Order  % of last contract amount approved by Council: (if over 10% 
of previous contract amount approved by Council, Council approval is required)  
7.3% 
 
Contract time or completion date prior to this Change Order: (incl. 
previous Change Orders) 
180 
or 
      
 
Days 
 
Date 
Net change resulting from this Change Order: 
 
0 
 
 
 
Days 
 
Revised contract time OR completion date: 
180 
or 
      
 
Days 
 
Date 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
SIGNATURE PAGE TO FOLLOW

THE ABOVE IS AGREED TO BY: 
Caliente Construction, Inc. 
11/3/21 
CONTRACTOR 
Date 
Signer Email A 
For Change Orders of $50,000 or more, or 10% or more of last contract amount approved by Council: 
MAYOR 
Approved as to Form 
(initials): 
City Attorney by: 
Attest: City Clerk: -----------
Owner I Project Mgr./ Orig.- City Clerk 
Legal approved 9/6/18 Rev. 4/8/2021 
PD1901.401 
Date 
Recommended By: 
Approved by 
Council on: 
Andrew Goh, CIP City 
Engineer 
Date 
Police Station Main Lobby and Records Renovations CO 1 
-----
Date 
Date 
Page 2 of 2 
11/4/21

One of the Valley’s Healthiest Employers 
485 West Vaughn, Tempe, Arizona 85283-3672  Phone: (480) 894-5500 Fax: (480) 894-2323 
AZ ROC091625  AZ ROC098769  AZ ROC164561   CA 770323   UT 4741522-550 NV 0078132 
ID RCE-28529   NM 85371   CO 233580   MT 159637 
Caliente Construction Inc. 
General Construction - Construction Management - Design/Build - Facilities Management 
   “We build more than structures; we build confidence and relationships that last” 
October 7, 2021 
 
 
 
 
 
Dan Haskins, PE  
 
 
Paul Ahlas, CPII 
Project Manager 
 
 
Construction Manager 
Public Works and Utilities Dept.   
Public Works and Utilities Dept. 
City of Chandler  
 
 
City of Chandler 
215 East Buffalo Street  
 
215 East Buffalo Street 
Chandler, AZ 85225 
 
 
Chandler, AZ 85225 
 
 
RE: 
COC JOC 1910.401 BF2108.401 PD Air Conditioner - Main Police Station – Men’s Locker Room 
 
 
Dear Dan & Paul, 
 
Thank you for the opportunity to provide our proposal for the City of Chandler JOC (1910.401) – BF2108.401 PD Air 
Conditioner - Main Police Station – Men’s Locker Room project. 
 
We have based the attached proposal on Design Documents provided by LSW Engineers dated October 19, 2020 (signed by 
City 08/24/21).  
 
The price is $96,410.76. See attached estimate with bid tabulations and subcontractor back-up for further details. 
 
Please contact me at your convenience should you have any questions.  
 
 
 
 
 
Best Regards, 
 
 
 
 
Justin Miller 
Caliente Construction Inc.

Caliente Construction Inc. 
 
 
              
 
                                                                                                
 
 
 
One of the Valles Healthiest Employers 
485 West Vaughn, Tempe, Arizona 85283-3672 Phone : (480) 894-5500 Fax : (480) 894-2323 
AZ ROC091625  AZ ROC098769  AZ ROC164561   CA 770323   UT 4741522-550 NV 0078132 
ID RCE-28529   NM 85371   CO 233580   MT 159637 
 
   “We build more than structures; we build confidence and relationships that last” 
General Construction - Construction Management - Design/Build - Facilities Management 
EXHIBIT A 
SCOPE-OF WORK 
 
PROJECT:  
City of Chandler JOC (1910.401) – PD1901.401 – Police Station Main Lobby and Records Renovations 
 
General Requirements: 
1) Provide office support, supervision, overhead/profit, taxes based on TPT (Chandler 5.070%), insurances, and bond. 
2) Provide temporary protection and dust protection for interior work. 
3) Dumpster/dump trailer and dump fees. 
4) Provide Final Cleaning of Work Area. 
 
Construction: 
1) Renovation and Remodel of the Men’s Locker Room Air Conditioner system per the design documents. Work to include: 
a) New Fan Coil Unit and associated chilled water 
b) Relocation of existing VAV from Exercise Room to Men’s Locker Room 
c) Ductwork, BMS Controls, Test & Balancing, and Electrical associated with design documents. 
2) Cleanup Site. 
 
Project Duration:   
1) Project duration is (4) Weeks / (28) Calendar Days with on-site construction starting after all materials are procured. 
 
Clarifications/Exclusions:  
1) See attached estimate spreadsheets. 
 
Alternates and Allowances: 
    1)    See attached estimate spreadsheets.

10/7/2021
1
2
3
4
5
6
7
1
2
3
4
5
6
7
1
CONSTRUCTION ALLOWANCE (No Mark-ups - Based on Subtotal of Cost of 
Work)
 $   7,478.90 
Proposal is based on a 4-day work week, night hours 6PM - 5AM, Monday - Thursday. Currently 
there is time included for a full-time superintendent. Lead-times for Fan Coil Units are currently 
between 8-12 weeks. Depending on the length of the pricing approval process and the current lead-
times for the fan coil units, this job may not start until after the PD Lobby and Records project is 
completed. If it does start earlier, we can pro-rate the hours and put the excess into the 
Construction Allowance line item.
Proposal based on water and power for construction to be provided onsite by COC at no cost to 
Caliente.
Painting of new ductwork included. 
Mechanical, Plumbing, Electrical based on exsiting systems being in good working condition.
COC JOC 1910.401 BF2108.401 PD Air Conditioner - Main Police Station - Men's Locker Room
Assumptions / Clarifications
Proposal based on onsite Project Duration of (4) Weeks after procurement of materials.
Allowances (Not Included in Base Bid; No Markups)
Exclusions
HVAC scope includes New Fan Coil Unit and Chilled Water Lines, Relocation of existing VAV Unit, 
any associated Ductwork (insulated), Test & Balance, and BMS controls (MPBAS - Owner Vendor)
Electrical scope includes extending existing 120v circuit to new VAV location and reconnect 
equipment; Furnish/Install new fuses, disconnect, conduit for new Fan Coil Unit; Furnish/Install new 
3P, 15A breaker in existing panel.
Design Services, Permits and/or Permitting Fees
Asbestos Testing and/or Abatement and/or Removal of Hazardous Materials (Current 
Report/Survey to provided by COC prior to start of Demolition).
Low Voltage Wiring for IT, Access Controls, Security, Intrusion Detection, etc.
Modifications, Additions to Exsiting Fire Sprinkler, Plumbing, Fire Alarm systems
Testing or Balancing of any other space other than Mens' Locker Room
Badging or Special Background Checks costs. We are including subs that are on the PD project 
and will already have employees cleared for that project.
Any other work not listed above or on bid tabulation sheets

5424 South 39th Street  
     Phoenix Arizona 85040 
     Office 602-424-3411 
     Fax 602-431-2248                              
Certified SBE, DBE & WBE Contractor 
 
 
Date: 
Friday, October 1, 2021 
 
Proposal to: Caliente Construction Inc. 
Project: COC JOC Air Conditioner PD Main 
Police Sta Men’s Locker
                     485 West Vaughn Street  
                  Tempe, Arizona 85283
250 E. Chicago St  
Chandler, AZ
Attention:    Justin Miller 
Acknowledged Addendum: None 
 
Arizona Professional Painting will perform painting at above location as per plans and 
specifications as follows: 
 
Repaint Drywall Ceilings at Men’s Locker due to Updated AC 
Background Checks 
 
*Does not include walls 
 
Provide labor, material, and equipment for the sum of $2,760.00 
+ Material Sales Tax: $61.00 
+ Textura Fee: $6.00 
 
Exclusions:  
 
Drywall Walls – Doors/Frames - Overtime hours (weekends and nights are excluded) – Touch up or repairs to our 
work due to damage by other trades – Proposal is subject to change if not accepted within 60 days from bid date  
 
 
Respectfully Submitted, 
 
Jessica Santoyo | Estimator 
Cell: 602-881-5656 
Office: 602-424-3411 
E-mail: Jessica@azpropaint.com 
 
Night Work Add    $500.00

P A G E  1  O F  3  
PROJECT PROPOSAL 
S U B M I T T E D  B Y  P U E B L O  M E C H A N I C A L  &  C O N T R O L S   ∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕    
 
 
∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕  W W W . P U E B L O - M E C H A N I C A L . C O M  ∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕ 
 
A Z  R O C  L I C E N S E S  
B - 0 1  # 1 7 3 9 5 3   |   C - 1 1  # 3 2 4 3 6 3   |  C R - 3 7  # 3 2 3 2 0 1  |  C R - 3 9  # 1 7 6 6 4 0   |   C R - 7 4  # 2 6 0 4 6 2     
Project Name: COC JOC Air Conditioner PD 
 
Address: 250 E. Chicago St. Chandler, AZ  
 
Customer: Caliente Construction 
 
Proposal #: 21-004217 
 
Drawings Dated: 7/13/2021 by LSW Engineers   
 
Proposal Date: 9/29/2021 
 
Dear Justin Miller, 
 
Pueblo Mechanical and Controls appreciates the opportunity to look at this project and is pleased to 
provide the following scope for COC JOC Air Conditioner PD 
 
Scope of Work: 
 
 Demo of existing HVAC units / ductwork / devices as shown per plan 
 Furnish and Install (1) total Chilled Water AHU 
 Relocate (1) total VAV 
 Furnish and Install new ductwork as shown on plans; to include insulation as called out on plans.  
 Furnish and install air distribution equal to plan specified. 
 Chilled water piping and insulation as per plans/specs (if provided). No Hot taps assumed. 
 Hot water piping and insulation as per plans/specs. No Hot taps assumed. 
 Furnish and install condensate drains as shown on plans with insulation as specified on 
plans/specs. 
 Does not include duct smoke detectors, none shown on plans 
 Start and test all existing equipment, provide report and estimate of any repairs if found 
 Subcontract MPBAS for installation of EMS / Controls Work – Included. 
 3rd party test and balance.  
 Proposal does not include parking fees and is assumed that parking will be provided at no cost to 
PMC or will be reimbursed via COR.  
 
Project Specific Exclusions: 
 Excludes off hours for controls scope 
 
Clarifications: 
 
 All work proposed using NORMAL WORKDAY hours.  The normal workday shall be defined as 
an eight (8) hour day shift, excluding Saturdays, Sundays, and holidays 
 There is a 3.2% fee associated with our accepting credit cards for payment

P A G E  2  O F  3  
PROJECT PROPOSAL 
S U B M I T T E D  B Y  P U E B L O  M E C H A N I C A L  &  C O N T R O L S   ∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕    
 
 
∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕  W W W . P U E B L O - M E C H A N I C A L . C O M  ∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕ 
 
A Z  R O C  L I C E N S E S  
B - 0 1  # 1 7 3 9 5 3   |   C - 1 1  # 3 2 4 3 6 3   |  C R - 3 7  # 3 2 3 2 0 1  |  C R - 3 9  # 1 7 6 6 4 0   |   C R - 7 4  # 2 6 0 4 6 2     
 If Taxes below are not approved; an AZ Form 5005 will need to be provided 
 This project proposal is valid for 30 days 
 All exclusions listed below 
 Pueblo will not be held liable for Material and Equipment escalation costs after 30 days of 
proposal date. 
 
Material, Service, & Labor Subtotal: 
 
Taxes 
 
 
$
$
42,240.00 
 
2,055.00 
Bonding Included: Yes/No: 
1.50% 
N/A 
 
 
 
Total Cost: 
 $
44,295.00 
 
Add $2,815.00 if project is required to be completed off business hours 
 
We Exclude the Following: 
 
 Taxes, bonds, permits and fees, utility tap fees, site utilities, meters, and fire protection, UNO 
 Davis Bacon / Prevailing wages, UNO 
 Buy Americas / American act 
 Fire or fire/smoke dampers not shown on bid documents. 
 Motor starters, unless they are an integral part of the equipment, we are furnishing 
 Electrical disconnects, unless they are an integral part of the equipment, we are furnishing 
 All overtime and off hours labor rates 
 Shift differential and expedited schedule costs, UNO 
 DDC/BAS/EMS Controls systems, UNO 
 All electrical work 120 volts and higher 
 All electrical materials, labor, panels, conduit, wire, devices, wiring, and interlocks  
 Fire or fire/smoke dampers not shown on bid documents 
 All fire alarm materials, labor, panels, conduit, wire, devices, wiring, interlocks and life safety 
coordination 
 All masonry blockout materials, fabrication and installation 
 Poured or formed concrete work, including housekeeping pads 
 Painting of duct work 
 Domestic cold-water ties into the makeup air unit 
 We exclude all scaffolding 
 Kitchen hoods, fire suppression systems, gas valves and interlocks, UNO 
 Fire suppression systems, UNO 
 Temporary power, lighting and climate control 
 Trash removal from project site 
 Poured or formed concrete work, including housekeeping pads

P A G E  3  O F  3  
PROJECT PROPOSAL 
S U B M I T T E D  B Y  P U E B L O  M E C H A N I C A L  &  C O N T R O L S   ∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕    
 
 
∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕  W W W . P U E B L O - M E C H A N I C A L . C O M  ∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕∕ 
 
A Z  R O C  L I C E N S E S  
B - 0 1  # 1 7 3 9 5 3   |   C - 1 1  # 3 2 4 3 6 3   |  C R - 3 7  # 3 2 3 2 0 1  |  C R - 3 9  # 1 7 6 6 4 0   |   C R - 7 4  # 2 6 0 4 6 2     
 Cutting and framing of openings in walls, floors, or roof, UNO 
 Architectural demolition and patching of roof, walls or ceiling 
 Ceiling demolition or replacement 
 Painting 
 General sheet metal, flashing, and trim. 
 Architectural louvers, UNO 
 Seismic restraints. 
 BIM or other CAD related modeling or drawings of any kind. 
 Repair or replacement of any existing device to be found inoperable. 
 Any work not included in scope of work listed above. 
 Formal Commissioning coordination of trades or commissioning agent. 
 Asbestos abatement, testing, reporting. 
 
We look forward to providing this important service. Please call if you have any questions. 
 
Best Regards, 
Peter McGrath 
Senior Project Manager 
 
O: 800.840.9170 
F:  888.473.4374 
C: 602.616.5328 
W: pueblo-mechanical.com 
E:  peterm@pueblo-mechanical.com 
A: 2849 E. Chambers St. Phoenix, Az 85040 
 
Acceptance of Proposal: The above prices, specifications are satisfactory and are 
hereby accepted. Terms & Conditions to be agreed upon in contract documents. You 
are authorized to do the work as specified. 
Name 
Signature 
Date 
 
Due to the high cost of equipment and/or extended nature of this project progress billing may be required; if a 
purchase order is created for this project the owner agrees to accept progress billing for demonstrated and 
verifiable completed work and/or arrival of equipment items pending installation.

Estimated By: Jim Zaborniak            jzaborniak@aspenelectricaz.com 
 
 
 
 
 
 
 
ELECTRICAL PROPOSAL 
 
PREPARED FOR: 
 
 
 
 
 
 
PROJECT: 
COC JOC AIR CONDITIONER PD MAIN POLICE STATION 
MEN’S LOCKER ROOM 
REV 1

Estimated By: Jim Zaborniak            jzaborniak@aspenelectricaz.com 
 
 
 
 
PROPOSAL 
 
To: 
 
Caliente Construction 
Attention: 
LeAnn Close 
Date:   
10-5-21 
Quote #:  
00-21303 
 
 
Project Name: COC JOC Air Conditioner PD Main Police Station Men’s Locker Room Rev 1 
 
Documents 
1. Specifications:             Project documents. 
2. Drawings: 
 
E0.1, E1.1, E2.1, E3.1, E4.1. 
3. Plans Dated:       
7-13-21. 
4. Addendums:                 N/A 
5. Attached Clarifications:     Yes 
 
 
Scope Clarifications 
 
1. Disconnect existing unit P-2-1, extend 120V circuit to new location of P-2-1 and 
reconnect using existing equipment.  
2. Furnish and install fuses, disconnect, conduit and wire for FC-2-1.  
3. Furnish and install (1) new 3P 15A breaker in existing panel “PH2A”. 
 
 
Exclusions 
 
1. All overtime and after hour work. 
2. Liquidated Damages. 
3. Temporary power and lighting. 
4. Furnishing and installing Duct Detectors. 
5. All Fire Caulking. 
6. Furnishing and installing access doors. 
7. HVAC control wiring and starters. 
8. Furnish and install of roof jacks and sealing of all exterior penetrations.  
9. Cutting, repair, patching of sheet rock. 
10. Painting. 
11. ARC Flash and Coordination Studies. 
12. 3rd Party Testing.

Estimated By: Jim Zaborniak            jzaborniak@aspenelectricaz.com 
 
13. Permits, inspection fees, sales tax, bonds and engineered drawings. 
 
 
 
Bid Clarifications: 
1. We have assumed that the engineered drawings meet code minimum requirements. 
Additional devices, lighting etc. required by an inspector to meet the NEC code 
requirements are not included in this proposal. 
2. All branch & feeder conduit designated for underground install within the building 
footprint will be installed at sub grade prior to AB and pouring of concrete slab.  
 Aspen Electric will make final determination as to which conduits are to be 
installed in this manner with GC coordination.  
3. Aspen Electric is not responsible for any unforeseen delays such as conflicts with other 
trades, weather conditions, product or third-party delays and site schedule delays that will 
add labor or material costs to this Proposal. 
4. All current and existing electrical, and its code compliance and design are the full 
responsibility of the building owner, and NO correction, adjustments, upgrades, or 
changes are included in this proposal. Only new electrical installation is to be agreed 
upon.     
5. All take offs, counts and locations for HVAC, devices and lighting quantities are based 
on drawing sets provided by GC/Owner. Any other sets or changes from different plans 
MAY result in a change order. 
6. We have assumed to use all existing site electrical panels for landing new electrical gear. 
Any panel discrepancies such as labeling, panel sizes, breaker issues or load problems are 
the sole responsibility of the owner and MAY result in a Change Order to correct or 
identify.    
7. We have included single point connections only to all equipment. Controls, internal 
wiring and all shut wiring are by others. 
8. We have utilized MC cable for all branch wiring where allowed by code. Any EMT, 
Rigid, &  IMC conduit called out for in these areas may result in a change order.  
9. Our price is based on a shared neutral with breaker tie per the NEC code for lighting. We 
have not included separate neutrals. 
 
 
 
 
 
 
 
 
General Conditions 
  
1) This proposal and all material pricing is valid for 30 days ONLY from date of proposal. Any 
acceptances, signatures, contract executions or scope changes after date on this proposal MAY 
result in a CO to correct or adjust unprotected pricing commitments. Any additional cost changes 
can be handled as a CO or even a new contract value change as client sees best fit. Any delays of

Estimated By: Jim Zaborniak            jzaborniak@aspenelectricaz.com 
 
site schedule, contract execution that do not allow Aspen Electric 5 business days to start prior to 
agreed schedule MAY result in cost increases. 
2) All / Any Change Orders for this project MUST be in writing to the project site manager assigned 
to your project. No site walks with working staff will be accepted or allowed. Not verbal 
direction on site to perform will be accepted. All items MUST be documented and signed prior 
to consider the CO an agreed upon added change to the execute prime contract. 
3) All Change Orders and dates of that work to be completed must be mutually agreed upon prior 
to acceptance of added work. 
4) Any site inspections for work Aspen is under contract to perform and be responsible for need to 
be mutually agreed upon prior to scheduling.  Any inspections or other related items set with 
Aspen Electrics mutually documented and agreed to scheduling is the sole responsibility of the 
owner.   
5) All inspections and testing of Aspen Electrical scope items require an Aspen Electrical assigned 
project site manager to be present.  No inspections shall be done without our presence to be 
mutually agreeable as a scheduled inspection / test. 
6) Anything (verbal or written) expressed or implied elsewhere, which is contrary to these conditions 
shall be null and void. 
Please reference the proposal number on all purchase orders and correspondence. 
 
PAYMENT TERMS:  
• 
Immediate upon receipt of invoice. 
Sales Tax:  Has not been included.  
 
Proposal Period:  This proposal is valid for 30 days from date of delivery.   
Subject to increases in the Commodities Markets. 
 
A Contract must be received at least one week prior to commencement of work. 
 
Project Scope:  The project scope contained herein is ASPEN Electric understanding and interpretation of 
the subject project. All pricing is based on the project scope. Any change to the project scope will result 
in a change in the pricing 
Additional Work:  Any alterations or deviations from the above specification involving extra cost will be 
executed only upon written orders and will become an extra charge over and above the proposed price. 
 
Job Site Requirements:  Customer will give ASPEN Electric installation and operations personnel full access 
to work areas without undue delay. Any delay will result in extra billing at ASPEN Electrics labor rate. 
ASPEN Electric will remove all job related debris from the job site. All fixtures and furniture moved by 
ASPEN Electrics personnel will be returned to its original position prior to job completion. 
 
Project Schedule:  ASPEN Electric will make all reasonable efforts to observe the dates indicated herein 
for installation or other performance, however ASPEN Electric shall not be liable for delay in performance 
due to unforeseen circumstances or causes beyond its control, including without limitation weather 
conditions, strike, lockout, riot, war, fire, act of God, accident, delays caused by any supplier or by the 
Customer, inability to obtain or substantial rise in the cost of labor or materials or compliance with any

Estimated By: Jim Zaborniak            jzaborniak@aspenelectricaz.com 
 
law, regulation or order. Performance shall be deemed suspended during and extended for such time as 
any such circumstances or causes delay its execution. 
 
Warranties; Damage; Liability:  All material is guaranteed to be as specified. All work to be completed in 
a professional manner according to standard installation practices. All material and labor supplied by 
ASPEN Electric will be guaranteed for 1 year. 
 
ASPEN Electrics obligations and Customer's remedies under this warranty are limited to the repair or 
replacement at ASPEN Electrics option, of any materials or labor furnished hereunder which shall be found 
defective during such a 1-year period. ASPEN Electric may reject any warranty claim not promptly reported 
and on any item that has been altered, abused or misused, except by ASPEN Electric.  Damage caused by 
others, pests or normal wear and tear is excluded from this warranty. Any repairs requested by Customer 
which are excluded from terms of this warranty may be performed by ASPEN Electric on a time and 
materials basis at ASPEN Electrics then prevailing rates. 
There are no warranties, which extend beyond the description of the face hereof. In no event shall ASPEN 
Electric be liable to customer for incidental, consequential, special or punitive damages. In no event shall 
ASPEN Electric be liable for damages hereunder, if any, exceed the amounts paid by customer to ASPEN 
Electric for the products and services under this contract. 
 
Confidentiality:  All information including but not limited to descriptions of work to be performed and 
parts lists, contained in this proposal or otherwise provided to the customer in connection with the 
negotiation of performance of this contract is of a proprietary nature, customer shall receive such 
information in confidence and shall not without ASPEN Electric prior written consent disclose such 
information to third parties or use such information for any purpose other than to evaluate the proposal 
contained herein. 
 
 
 
 
 
 
 
 
Quote Ref #00-21303 
 
Pricing Summary 
 
Base Bid Total:                                              $2,324.00 
Adder for After Hour Work:  
 
$   118.00 
Estimated Sales Tax: 
 
 
 
$   105.00

Estimated By: Jim Zaborniak            jzaborniak@aspenelectricaz.com 
 
 
 
 
 
 
           
 
 
 
 
 
By:            Eddie Diliberto                
               By:  
 
 
 
 
Title:           Project Manager                                   Title:   
 
 
 
 
Date:        
10-5-21  
 
 
 
 Date:   
 
 
 
 
 
 
 
 
 
 
                PO#:   
 
 
 
 
ROC # 295017

10/7/2021
Negotiated Prices
52,139.00
$              
-
$                         
22,650.00
$              
-
$                         
-
$                         
SUBTOTAL (NEGOTIATED PRICES):
74,789.00
$             
10.00%
7,478.90
$                
TOTAL (NEGOTIATED PRICES + OVERHEAD & PROFIT):
82,267.90
$              
Sales Tax Percentage (Current Tax Rate)
TPT
5.070%
4,291.28
$                
General Liability Insurance Percentage (Actual Cost per Job Order)
1.00%
747.89
$                   
Builder's Risk Insurance Percentage (Actual Cost per Job Order)
0.50%
373.95
$                   
Payment Bond (Actual Cost per Job Order)
1.50%
1,250.85
$                
Performance Bond (Actual Cost per Job Order)
INC
0.00%
-
$                         
SUBTOTAL (INSURANCE, BONDS, & TAXES):
6,663.96
$               
COMBINED TOTAL (TOTAL + INSURANCE, BONDS, & TAXES):
88,931.86
$              
City's Allowance
7,478.90
$                
TOTAL JOB ORDER:
96,410.76
$      
COC JOC 1910.401 BF2108.401 PD Air Conditioner - Main Police Station - Men's 
Locker Room
General Conditions
Preconstruction Labor (if applicable)
Construction Labor (if applicable)
Overhead and Profit (Coefficient per Job Order Master Agreement)
Insurance, Bonds, & Taxes
Per the Job Order Master Agreement - This Fee Table includes all fees, costs, insurance and bond premiums, allowances, 
construction contingency, and taxes of any type necessary to fully, propertly and timely perform and construct the Work.  Also 
per the Job Order Master Agreement - For any portion of the Work which, either through this Contract, Change Order or 
otherwise, is performed and paid for on a cost, or time and materials basis, the costs may be reimbursed to JOC Contractor 
and chargeable against the Contract Price will be determined as set forth in MAG 109.5.
EXHIBIT "B"
JOB ORDER COST PROPOSAL
SUMMARY SHEET
Price of Subcontractor(s)
Price of Subconsultant(s)

Project:
100.00 Building Sq. Ft.
Owner:
City of Chandler
0.00 Site Sq. Ft.
Architect:
LSW Engineers
0.00 Site Acres
Bid Date:
10/7/2021
RFI(s):
00000
Permit Set
Taxing Jurisdiction:
Chandler
Addendum(s): 00000
MRRA or TPT: 
TPT
TOTALS
DIVISION 1
GENERAL CONDITIONS
22,650.00
$                     
DIVISION 9
FINISHES
3,260.00
$                       
DIVISION 9
Painting
3,260.00
$         
DIVISION 23
HEATING, VENTILATING, AND AIR CONDITIONING
46,055.00
$                     
DIVISION 26
ELECTRICAL
2,824.00
$                       
74,789.00
$                     
OVERHEAD/PROFIT
10.00%
7,478.90
$                       
GENERAL LIABILITY INSURANCE
1.00%
747.89
$                          
BUILDERS RISK INSURANCE
0.50%
373.95
$                          
BONDING FEES
1.50%
1,250.85
$                       
CONSTRUCTION ALLOWANCE (No Mark-ups - Based on Subtotal of Cost of Work)
10.00%
7,478.90
$                       
Sales Tax  (TPT Chandler 5.070%)
5.070%
4,291.28
$                       
96,410.76
$              
DESCRIPTION
Subtotal of Cost Of Work
TOTAL COST 
COC JOC 1910.401 BF2108.401 PD Air Conditioner - 
Main Police Station - Men's Locker Room

4 Weeks
DATE:
10/7/2021
20 Calendar Days
CODE
ITEM
QTY
TYP
RATE
SUBTOTAL
GENERAL CONDITIONS
 
20,100.00
$              
00-1040 Project Manager
0.50
WK
4,200.00
$        
2,100.00
$                
00-1052 Assistant Project Manager
0.50
WK
3,200.00
$        
1,600.00
$                
00-1047 Project Coordinator
0.50
WK
2,400.00
$        
1,200.00
$                
00-1045 Superintendent
4.00
WK
3,800.00
$        
15,200.00
$              
TEMPORARY FACILITIES
1,000.00
$                
01-5219
Portable Toilets
4
WK
250.00
$           
1,000.00
$                
GENERAL REQUIREMENTS
1,550.00
$                
01-7410
Dumpster & Fees
1.00
PULL
550.00
$           
550.00
$                   
01-7423
Final Bldg Clean
1
LS
1,000.00
$        
1,000.00
$                
GENERAL CONDITIONS TOTAL 
22,650.00
$        
General Conditions
COC JOC 1910.401 BF2108.401 PD Air Conditioner - Main Police Station - Men's Locker Room

SUB 1
SUB 2
SUB 3
SUB 4
SUB 5
SUB 6
SUB 7
SUB 9
SELECTED SUB
AZ Prof PT
PHP PT
Pete King
Extreme
Riddle Paint
Big Guns PT
Ganado PT
Hernandez
PT
Cos
**NO BID**
**NO BID**
**NO BID**
**NO BID**
**NO BID**
**NO BID**
BASE BID
2,760.00
$          
10,900.00
$        
Painting
Ceilings
X 
X 
Walls
N/A 
X 
Night Work
$              500.00 
$          1,000.00 
SALES TAX
-
$                   
-
$                   
-
$             
-
$             
-
$             
-
$             
-
$             
-
$             
TEXTURA
-
$                   
-
$                   
-
$             
-
$             
-
$             
-
$             
-
$             
-
$             
SUBCONTRACTOR BID
2,760.00
$          
10,900.00
$        
-
$             
-
$             
-
$             
-
$             
-
$             
-
$             
ADD-ONS
500.00
$             
1,000.00
$          
-
$             
-
$             
-
$             
-
$             
-
$             
-
$             
TOTAL BID     
3,260.00
$      
11,900.00
$    
-
$          
-
$          
-
$          
-
$          
-
$          
-
$          
3,260.00
$       
MARK-UPS:
Mark-up on Change Orders
ALTERNATES
1 Add Painting Doors/Frames
1,793.00
$          
2
3
SCHEDULE PROVIDED:
TOTAL BID
5,053.00
$      
11,900.00
$    
-
$          
-
$          
-
$          
-
$          
-
$          
-
$          
3,260.00
$       
Painting
0
0
BID TALLY SHEET
RFI(s):
ADDENDUM(S):
DESCRIPTION
October 7, 2021
BID PACKAGE: 
BID DATE:
COC JOC 1910.401 BF2108.401 PD Air Conditioner - Main Police Station - Men's Locker Room

SUB 1
SUB 2
SUB 3
SUB 4
SUB 5
SUB 6
SELECTED SUB
RKS HVAC
Pueblo Mech
Tri-Mega
Crawford
Futureway
Northern AZ
**NO BID**
**NO BID**
**NO BID**
**NO BID**
BASE BID
57,700.00
$        
42,240.00
$        
HVAC
Mechanical Make-safe/Demo
 X 
 X 
New chilled water fan coil/hose kit
 X 
 X 
Move existing VAV box from Exercise Room to LR (this 
appears to leave no cooling in Exercise Room)
 X 
 X 
Insulated Ductwork
 X 
 X 
Night Work - HVAC Controls (MPBAS)
 $              500.00  $              500.00 
Night Work - Test & Balance
 $              500.00  $              500.00 
Night Work - HVAC Sub
 NO EXTRA 
 $           2,815.00 
BMS/CONTROLS
MPBAS - Owner Vendor
INCLUDED 
INCLUDED 
Make-safe/Demo
X 
X 
Remove existing VAV controls and save for relocation
 X 
 X 
Connect to existing BAS server
X 
X 
Modify existing graphics
X 
X 
Fan Coil: Connect to existing network router, provide new 
controller, room temp sensor, supply air temp sensor, fan 
status switch, furnish chilled water valve
 X 
 X 
VAV: Relocate existing to existing network router, re-
install existing controller, re-install existing room temp 
sensor, modify program to eliminate HW heat
 X 
 X 
Provide/Install all communication wiring, plenum-rated 
and EMT conduit as required
 X 
 X 
Assit TAB contractor
X 
X 
Commissioning
X 
X 
FA interlock wiring at unit
X 
X 
Owner training
X 
X 
SALES TAX - MRRA
-
$                   
-
$                   
-
$               
-
$               
-
$               
-
$               
TEXTURA
-
$                   
-
$                   
-
$               
-
$               
-
$               
-
$               
SUBCONTRACTOR BID
57,700.00
$        
42,240.00
$        
-
$               
-
$               
-
$               
-
$               
ADD-ONS
1,000.00
$          
3,815.00
$          
-
$               
-
$               
-
$               
-
$               
TOTAL BID     
58,700.00
$    
46,055.00
$    
-
$           
-
$           
-
$           
-
$           
46,055.00
$     
MARK-UPS:
Mark-up on Change Orders
ALTERNATES
1
2
3
SCHEDULE PROVIDED:
TOTAL BID
58,700.00
$    
46,055.00
$    
-
$           
-
$           
-
$           
-
$           
46,055.00
$     
HVAC
0
0
BID TALLY SHEET
RFI(s):
ADDENDUM(S):
DESCRIPTION
October 7, 2021
BID PACKAGE: 
BID DATE:
COC JOC 1910.401 BF2108.401 PD Air Conditioner - Main Police Station - Men's Locker Room

SUB 1
SUB 2
SUB 3
SUB 4
SUB 5
SUB 6
SUB 7
SUB 8
SELECTED SUB
Aspen
Alvarado E
K2 Electric
Crown
LLR Electric
SeaTac
AJP Electric
Hernandez
Electric
Electric
Electric
Cos.
**NO BID**
**NO BID**
**NO BID**
**NO BID**
**NO BID**
BASE BID
2,324.00
$      
3,300.00
$      
3,941.00
$      
Electrical
Make-safe/Demo
 X 
 X 
 X 
Extend 120v circuit to new location 
of VAV P-2-1 and reconnect 
existing equipment
 X 
 X 
 X 
Furnish/Install new fuses, 
disconnect, conduit for new Fan 
Coil
 X 
 X 
 X 
Furnish/Install new 3P, 15A 
breaker in existing panel
 X 
 X 
 X 
Night Work
 $         500.00  $         500.00  $         500.00 
SALES TAX
-
$               
-
$               
-
$               
-
$             
-
$             
-
$                 
-
$             
-
$             
TEXTURA
-
$               
-
$               
-
$               
-
$             
-
$             
-
$                 
-
$             
-
$             
SUBCONTRACTOR BID
2,324.00
$      
3,300.00
$      
3,941.00
$      
-
$             
-
$             
-
$                 
-
$             
-
$             
ADD-ONS
500.00
$         
500.00
$         
500.00
$         
-
$             
-
$             
-
$                 
-
$             
-
$             
TOTAL BID     
2,824.00
$  
3,800.00
$  
4,441.00
$  
-
$          
-
$          
-
$             
-
$          
-
$          
2,824.00
$       
MARK-UPS:
Mark-up on Change Orders
ALTERNATES
1
2
3
SCHEDULE PROVIDED:
TOTAL BID
2,824.00
$  
3,800.00
$  
4,441.00
$  
-
$          
-
$          
-
$             
-
$          
-
$          
2,824.00
$       
BID DATE:
Electrical
0
0
BID TALLY SHEET
RFI(s):
ADDENDUM(S):
DESCRIPTION
October 7, 2021
BID PACKAGE: 
COC JOC 1910.401 BF2108.401 PD Air Conditioner - Main Police Station - Men's Locker Room