CITY OF CHANDLER
CHANGE ORDER NO. 1
DATE — 11/9/2021

Change Order not valid until signed by both the City and the Contractor. Contractor's signature indicates
agreement herewith, including any adjustments in the Contract Price or Contract Time.

Project Name: _ Airport Water Reclamation Facility Headworks Drain Piping

Project No.: WW2003.401

User Dept.: Public Works & Utilities NTP Date: July 13, 2021

TO: Garney Companies, Inc. 4435 E. Holmes Ave., Ste .102, Mesa AZ 85206
(CONTRACTOR) (Address)

(Contractor must make the following changes to this contract: (Detail scope change (Exh. A) / cost
breakdown (Exh. B), if needed)

This change order will replace two of the four 30 inch Ductile Iron Pipe running overhead between
the Headworks Facility and the Pre-Stage Basin at the AWRF Reclamation Facility.

OWNER NAME & DATE APPROVAL: Paul Roy 11/8/2021

Changes result in the following revised contract amount and time:

Original contract amount: $391,070.00
Current contract amount, prior to this Change Order: (incl. previous Change
Orders) $391,070.00
Net change resulting from this Change Order: (if over $50,000 from contract
amount previously approved by Council, Council approval is required) $636,059.26
Revised contract amount, including this Change Order: $244,989.26
Last contract amount approved by Council: $391,070.00
Change Order % of last contract amount approved by Council: (if over 10%
of previous contract amount approved by Council, Council approval is required) 84%
Contract time or completion date prior to this Change Order: (incl.
previous Change Orders) 180 or

Days Date
Net change resulting from this Change Order: 50

Days

Revised contract time OR completion date: 230 or

Days Date

SIGNATURE PAGE TO FOLLOW

Legal approved 9/6/18 Rev. 4/8/2021 WW2003.401 Page 1 of 2
Airport Water Reclamation Facility Headworks Drain Piping CO 1

THE ABOVE IS AGREED TO BY:

Garney Companies, Inc. LhA A 1 7[zoz4

CONTRACTOR Signature Date

Qweveene Cagarney. con
° Signer Emall Address

For Change Orders of $50,000 or more, or 10% or more of last contract amount approved by Council:

Approved by

Council on:
MAYOR Date Date
Recommended By:
Approved as to Form
(initials):
Andrew Goh, CIP City Date
. Engineer
City Attorney by: me
Attest: City Clerk:
Date
E-copy: Owner / Project Mgr. / Orig.- City Clerk
Legal approved 9/6/18 Rev. 4/8/2021 WW2003.401 Page 2 of 2

Airport Water Reclamation Facility Headworks Drain Piping CO 1

Exhibit A

Scope
Airport WRF Emergency Headworks Influent Pipe
Replacement

1. JOC to perform the following project tasks:
a. Mobilize to site
b. Demo and disposal for 123’ of existing 30” ductile iron pipe, including 6” vent lines.
i. Two (2) 30”x20” reducers and flowmeters can be salvaged and returned to the City
of Chandler, upon request.
ii. Existing pipe straps will be salvaged and reinstalled.
iii. Proposal assumes use of owner supplied stop logs to isolate headworks influent
lines as needed.
iv. OSHA safety standards require H2S to be at 5 PPM which is lowerthan current readings
while working in the headworks. No additional costs were included should a
supplemental venting system be needed.
c. Install new flanged 30” ductile iron pipe and 6” Sch80 PVC vent line.
i. Proposal includes 123’ of 30” ductile iron pipe, all connections to be flanged.
ii, Proposal includes 40’ of 6” Sch80 PVC pipe with fittings required for vent connections.
iii. Proposal includes a flexible coupler on each line.
iv. Proposal includes painting the exterior pipe as needed.
Repair any disturbed landscaping in the work area.
. Test Pipe as necessary.
f. The conditions of the existing wall pipes are not known, no costs have been included for
replacement of these, if needed.

2. Schedule is based on 3-weeks for procurement/delivery of material and 3-weeks for construction.

3. Specifically excluded from this proposal are: Building Permits, Engineering (including professional
engineered design of pipe system and supports), remediation of contamination and hazardous material
handling.

4. Garney has included an Owner’s Allowance for $25,000.

5. Table Bx —Subconsultants to include Murphy Painting for pipe coatings.

Page 1 of 1

arne 4435 E. Holmes Ave, Suite 102, Mesa AZ 85206
CONSTRUCTION Phone: 602.470.0001

Fax: 602.470.0025
ADVANCING WATER

www.gamey.com
EXHIBIT "B-1"
Job Order Cost Proposal
Summary Sheet
Chandler AWRF Headworks Emergency Influent Pipe Repair

Price of Subcontractor(s) $ 16,950.00

Price of Subconsultant(s) $ =
General Conditions $ 10,269.43
Construction Labor (if applicable) $ 23,871.06
Construction Material and Equipment $ 138,369.16
SUBTOTAL (NEGOTIATED PRICES): $ 189,459.66
Overhead and Profit (Coefficient per Job Order Master Agreement) | 0.08 | $ 15,156.77

SUBTOTAL (NEGOTIATED PRICES + OVERHEAD AND PROFIT): $ 204,616.43

Insurance, Bonds, & Taxes

Sales Tax Percentage (Current Tax Rate) 5.07% $ 10,374.05
General Liability Insurance Percentage (Actual Cost per Job Order) 1.35% $ 2,762.32
Builder's Risk Insurance Percentage (Actual Cost per Job Order) 0.343% $ 701.83
Payment Bond (Actual Cost per Job Order) 0.75% $ 1,534.62
Performance Bond (Actual Cost per Job Order) included $ -

SUBTOTAL (INSURANCE, BONDS, & TAXES): $ 15,372.83
SUBTOTAL (NEGOTIATED PRICES + OVERHEAD AND PROFIT + INSURANCE, BONDS, & TAXES): $ 219,989.26
City's Allowance 0.00% | $ 25,000.00
TOTAL JOB ORDER: $ 244,989.26
Per the Job Order Master Agreement - This Fee Table includes all fees, costs, insurance and bond premiums, allowances,
construction contingency, and taxes of any type necessary to fully, propertly and timely perform and construct the Work. Also per
the Job Order Master Agreement - For any portion of the Work which, either through this Contract, Change Order or otherwise, is
performed and paid for on a cost, or time and materials basis, the costs may be reimbursed to JOC Contractor and chargeable
against the Contract Price will be determined as set forth in MAG 109.5.

Chandler AWRF Headworks Emergency Pipe Repair

19202 TOTALS] 595] [ 28,964] i= 129,775] L 16,950] [ 8,97] [ 4,794] 189,460]
‘Comments. Total T Labor I ‘Materials I ‘Subcontract 1 juipment 1 Other. J
(Spec/Dwg! Description Quantity | Unit MH MH/U_[ Labor Unit | Labor Total | MatlUnit | Mati Total [Sub Unit] SubTotal_| Equip Unit_| Equip Total | Oth Unik] Oth Total | Total Cost
GARNEY INDIRECTS Ee
DONSTRUCTIO! PROJECT MANAGER 2.0 WKS 20.0 10,000 104,60 2,092 0 0 0) 0 2,092
ENERAL SUPERINTENDENT 2.0 WKS 80.0, 40,000 83.68 6,694 0 0 0) 0 6,694
‘TRUCK: ON-HIGHWAY LIGHT DUTY 4X2 GAS 100.0 HRS 12.89 1,289 1,289
SANITARY FACILITY 0.5 MOS. 0.0 0,00 0) 0 0) ) 250.00 125 125
DRINKING WATER 0.5 MOS 0.0 0.00 ° 0 ) 0 150,00 69 69
s - SMALL TOOLS 1.0 LS 0.0 0.00 ) 0 0) 0) 0.00 0 0)
s - MISC. RENTAL 1.0 LS 0.0 0.00 0 0 0 0) 0.00 0 0
s - _ SAFETY\FIRST AID EQUIP 1.0 LS 0.0 0.00 ) ) 0 0 0.00) 0 0
DEMOLITION
REMOVE EXISITNG 30° PIPE 123.0 LF 1538 1.250 44.60 5,486 ° 0 0 0 5,486
SALVALGE FLOW METER 2.0 EA 10.0 5.000 178.40 357 0 0 0 0 357
ROLL-OFF DUMPSTER (30 CY) 3.0 EA 120 4,000 142,72 428 tO) 0 0 1,200.00 3,600 4,028
0 0
EQUIPMENT 0
FORKLIFT: CATERPILLAR TL1055C 80.0 HRS 5,276 % 5,276
BOOM LIFTS 60-80' 2.0 WK 2412 2412
3PEC 09900 PAINTINGS & COATINGS LOLS 0) 0.00 0) ) 16,950.00 16,950 0 0 16,950
0.0 0 0 0 0 0 0
OLS 12.0 | 12,000 523.16 $23 ° 0 0) 0) 523
TEST PIPING 1.0 LS 8.0 8.000 348.77 349 ) 0 0) 0 349
FLUSH & CLEAN PIPING LOLS 16.0 16,000 697.55 698 ) 0 0 0) 698
SUPPLY & INSTALLATION OF BULKHEADS 4.0 BA 100.0 25.000 1,089.92 4,360 500.00 2,000 0 0) 0 6,360
SUPPLY MATERIALS
SUPPLY - DUCTILE IRON PIPING LOLS i) 0.00 0 | 121,653.00 121,653 0 0 0 121,653
SUPPLY - PIPE SUPPORTS, DESIGN, SEISMIC 10 LS 0.0 0.00 0 5,000.00 $,000 0 0 0 5,000
30° 2'0" FLGx PE 401/PC 2.0 EA 25:3) 12.630 550.63 0) 0 0 0 1,101
30°x 9'0" FLGx PE 401/PC_ 1- (6"FBO) 2.0 EA 279 13.950 608.17 0 0 0 0 1,216
30°x 17'6" FLG x FLG 401°C 4.0 EA 58.5 14.630 637,82 0 0 0 0 2,551
30"x 15" 6" FLG x FLG 401/PC 2.0 BA 29.5 14.770 643.92 0 0 0 0) 1,288
30” FLEX COUPLING; NON-REST, CS-FBE.NBR.STD BO! 2.0 EA 25:3. 12.630 $5063 0 0 0 0 1,101
30” FLG 3-HOLE HARNESS LUG, 16.0 EA 0.0 0.00 0) 0 0 0 )
30" FLG 3-HOLE HARNESS ROD 8.0 BA 00 0.00 0 0 0) 0 0
30" FLG HEX B/N SET (A307B-ZN) 28-1-1/4x7.5, 4.0 EA 0.0 0.00 0 0 0) 0 0)
30” FLG HEX BIN SET (A307B-ZN) 28-1-1/4x6.5 6.0 EA 0.0 0.00 0 0 0 0 °
30” FULL FACE FLANGE-TYTE GASKET (SBR) 10.0 EA 0.0 0.00 0 0 0 0 0
06" FLG HEX STUD/NUT SET (A307B-ZN) 8-3/4x3.50" 4.0 EA 0.0 0.00 0 0 ° 0 0
06" FLG HEX BOLT/NUT SET (A307B-ZN) 8-3/4x3,50" 4.0 EA 0.0 0.00 0 0 0) 0 °
06" FULL FACE FLANGE-TYTE GASKET (SBR) 4.0 FT 0.0 0,00 ° 0 o 0 0
PVC $80 06" X 20 FT PIPE PE 40.0 LF 72 785 18.00 720 0 0) 0 1,034
PVC $80 06" FLANGE VAN STONE STYLE 4.0 BA 5.0 $4.50 68.00 212 0) 0 : 0 490
PVC S80 06" 90 BEND SXS 2.0 BA 43 93.73 33.00 70 0 0 0 287
PVC $80 PRIMER 1.0 QT 00 0.00 30.00 30 0 0 0 30
PVC $80 CEMENT 10 QT 0.0 0.00 30.00 30 0) 0 0.00 0 30
FREIGHT COST 1.0 BA 00 0.00 ) 0 0 1,000.00 1,000, 1,000

Page | of 1

1/28/2021

Gaarney

ADVANCING WATER

DESCRIPTION STD RATE OT RATE
SALARY: PROJECT MANAGER $ 104.60 | $ 156.90
SALARY: PROJECT ENGINEER $ 58.56 | $ 87.85
SALARY: SUPERINTENDENT $ 83.68 | $ 125.52
LEAD: FOREMAN / ASSISTANT SUPERINTENDENT $ 59.43 | $ 89.15
OPERATOR: TRACKHOE $ 44.38 | $ 66.57
OPERATOR: FRONT END LOADER $ 39.16 | $ 58.74
OPERATOR: BACKHOE $ 32.20 | $ 48.30
OPERATOR: CRANES $ 50.56 | $ 75.84
LABORER: PIPELAYER $ 39.16 | $ 58.74
LABORER: COMMON $ 32.20 | $ 48.30
CARPENTERS: FORM WORK $ 39.16 | $ 58.74
CARPENTERS: FINISH WORK $ 42.64 | $ 63.96
CARPENTERS: CEMENT FINISHER $ 35.68 | $ 53.52

*RATES ARE PER HOUR

CREW RATE SHEET

1/28/2021

Gaarney

ADVANCING WATER

DESCRIPTION FHWA RATE

EXCAVATOR: CATERPILLAR 390FL $ 381.93
EXCAVATOR: CATERPILLAR 374DL $ 297.96
EXCAVATOR: CATERPILLAR 349F $ 241.86
EXCAVATOR: CATERPILLAR 336F $ 173.30
EXCAVATOR: CATERPILLAR 335FLCR $ 175.56
EXCAVATOR: CATERPILLAR 330FL $ 136.91
EXCAVATOR: CATERPILLAR 325FL $ 113.17
EXCAVATOR: CATERPILLAR 315FL $ 100.14
EXCAVATOR: CATERPILLAR 308ECR $ 56.36
WHEEL LOADER: DEERE 744kIl $ 117.72
WHEEL LOADER: DEERE 644K $ 78.53
WHEEL LOADER: DEERE 624KIl $ 66.45
WHEEL LOADER: DEERE 544KIl $ 59.41
RUBBER TIRE BACKHOE: CATERPILLAR 420F2 IT $ 47.35
RUBBER TIRE BACKHOE: DEERE 310K $ 35.53
FORKLIFT: CATERPILLAR TL1055C $ 65.95
SKID STEER LOADER: CATERPILLAR 299D2 XHP $ 55.90
SKID STEER LOADER: CATERPILLAR 289D $ 46.77
SKID STEER LOADER: CATERPILLAR 262D $ 43.10
TRUCK: ON-HIGHWAY WATER TANKER $ 49.52
TRUCK: ON-HIGHWAY LIGHT DUTY 4X4 DIESEL UTILITY $ 26.37
TRUCK: ON-HIGHWAY LIGHT DUTY 4X2 GAS $ 11.81
COMPACTOR: WACKER RT820 $ 38.88
COMPACTOR: MULTIQUIP MVH158GH $ 5.90
MISCELLANEOUS: PORTABLE LIGHT TOWERS $ 9.89
MISCELLANEOUS: FXT50 400GAL VACUUM EXCAVATOR $ 28.72

*RATES ARE PER HOUR

CREW RATE SHEET

INDUSTRIAL COATINGS, INC.

50-B West Hoover Avenue
Mesa, AZ 85210
Phone (480) 981-0185 - Fax (480) 981-1567 Safety - Pride - Integrity

November 9, 2021

Garney Construction, Inc.
4335 East Holmes, Suite 102
Mesa, AZ 85206

Attention: Alexander Greene, Project Manager/Estimator

Reference: — Airport WRF, Piping Project
Chandler, AZ

Subject: Painting Proposal

The following is Murphy’s scope of work and pricing for the Airport WRF,
Piping Project per the plans and specifications:

Section Description
09900 Painting
Excludes: 1. shop applied coating
2. all buried pipes
3. contact with dissimilar metals coating

Scope:

- Painting 123’ of 30” DIP Pipes and 20’ of 6” PVC Pipes with valve, flanges etc.
- Painting to be performed after pipe installation

Pricing: Labor: $9,635.00 (176 Man Hours)
Material: $3,000.00
Equipment $4,315.00 (includes 40’ manlift)
$16,950.00

(Add 2.% if Performance/Payment Bonds are required)

Excluded from Scope of Work:

Third Party Inspection

- Paint Mock-ups (project too small)

- Pipe I.D.

Concrete painting or coating except as described above.
Taxes on painting/coating material

Page 01 of 02

INDUSTRIAL COATINGS, INC.

50-B West Hoover Avenue
Mesa, AZ 85210
Phone (480) 981-0185 - Fax (480) 981-1567 Safety - Pride - Integrity

Page 02 of 02

Clarifications:
1. New Ferrous Metals to be shop primed "by others" and in accordance with Painting

Section 09900.
2. Grinding of welds to the satisfaction of the inspector is by other.
3. Murphy is QP-1 and QP-2 Certified by SSPC The Society for Protective Coating

Addendums noted: n/a

Subcontractor Listed Information: | AZ License No. 127921, Type L34 (Exp. 10-01-22)

Please call me if you have any questions regarding this proposal.

MURPHY INDUSTRIAL COATINGS, INC.

Gilles Bussieres
Southwest Operations Manager

gilles@murphy.ac

Alexander Greene

a
From: Jeff Cassano <JCassano@cbpiping.com>
Sent: Monday, November 8, 2021 2:35 PM
To: Alexander Greene; Jeff Cassano
Ce: Hunter Thomas
Subject: [EXTERNAL] PEND Release FW: Chandler AWRF Influent As-built Dimensions
Attachments: GAR DRWG Chandler Influent.pdf
Alex,

Math looks good, just will have to change up method of coupling harness from MJ Restraint Gland to 3-Hole Lugs and
Rods, extra long to run span of 2’ 0” and 8’ 10 FLG X PE Spools

LINE _ QUAN _ UNIT DESCRIPTION COMMENTS
ALEX/GARNEY AZ CHANDLER AWRF TEMP

10 2 EA 30"x 2' 0" FLG x PE 401/PC

20 2 EA 30"x 9' 0" FLG x PE 401/PC_ 1- (6"FBO) (1) 06" FBO @ 12:00" 36" FROM PE
30 4 EA 30"x 17' 6" FLG x FLG 401/PC

40 2 EA 30"x 15'6" FLG x FLG 401/PC

50 2 EA 30" FLEX COUPLING; NON-REST, CS-FBE.NBR.STD BOLTS (32.00) — LEADTIIME 2-3 WKS ARO, PPA

60 16 EA 30" FLG 3-HOLE HARNESS LUG, LEADTIME 2-3 WKS ARO, PPA

70 8 EA 30" FLG 3-HOLE HARNESS ROD (1) 1-1/4" X 12' ZINC (4) HVY HEX NUTS
80 4 EA 30" FLG HEX B/N SET (A307B-ZN) 28-1-1/4x7.5 FOR LUG

90 6 EA 30" FLG HEX B/N SET (A307B-ZN) 28-1-1/4x6.5

100 10 EA 30" FULL FACE FLANGE-TYTE GASKET (SBR)

110 2 EA 06" FLG HEX STUD/NUT SET (A307B-ZN) 8-3/4x3.50" FOR PVC (8) FLAT WASHERS

120 2 EA 06" FLG HEX BOLT/NUT SET (A307B-ZN) 8-3/4x3.50" FOR PVC (8) FLAT WASHERS

130 4 EA 06" FULL FACE FLANGE-TYTE GASKET (SBR)

140

7150 EA FREIGHT COST

160

Jeff Cassano | C&B Piping, Inc.
(602) 828-6742

jcassano@cbpiping.com

From: Alexander Greene <awgreene@garney.com>

Sent: Monday, November 8, 2021 1:37 PM

To: Jeff Cassano <JCassano@cbpiping.com>

Ce: Jim Symonds <jsymonds@garney.com>

Subject: RE: [EXTERNAL] PEND Release FW: Chandler AWRF Influent As-built Dimensions

Jeff,

| show that we would need spools in the following lengths:
- 2 Each 2’-0” FLxPE

- 2 Each 8’-10” FLxPE w/6” FBO

- 4 Each 17’-6” FLxFL

- 2 Each 15’-5 3/8” FLXFL

- 5/8” gap for gaskets, 1” gap at flexible coupling per run

If my math is correct, that runs us 1’-1” past the first column, 0’-9” past the second column for flanged connections and
gives us an overall length of 61’-5”. Let me know if you see any errors in my thoughts.

Thank you,

Alexander W. Greene

Project Manager

GARNEY CONSTRUCTION Advancing Water

CELL: 719.322.3308

ADDRESS: 4435 E. Holmes Avenue, Suite 102, Mesa AZ 85206 GARNEY.COM

From: Jeff Cassano <JCassano@cbpiping.com>

Sent: Monday, November 8, 2021 12:51 PM

To: Alexander Greene <awgreene@garney.com>; Jeff Cassano <JCassano@cbpiping.com>
Ce: Hunter Thomas <hthomas@cbpiping.com>

Subject: [EXTERNAL] PEND Release FW: Chandler AWRF Influent As-built Dimensions

Alex,

C&B has (7) 30” Pipe and plenty of Flanges, will have to order the FBO (Flange Boss Outlets) to complete *shipping from
VA/PPA

| can have the (4) Spools complete in 2 WKS ARO, but will an additional week for the FBO, will have to wait until received
to complete.

Qty-1 30” X FLG X FLG CL53, 401/PC
Qty-1 30” X FLG X FLG CL53, 401/PC
Qty-1 30” X FLG X FLG CL53, 401/PC
Qty-1 30” X FLG X FLG CL53, 401/PC

— ; ls
|

F -

Coy [couf

| [|
. js +—-—_—
i 4” vo is!4" wo" 2a"
Hunter,

can you follow up on the 06” materials Alex is asking about noted below.

Cassano

From: Alexander Greene awgreene@garney.com
Sent: Monday, November 8, 2021 10:31 AM

To: Jeff Cassano JCassano@cbpiping.com
Subject: RE: [EXTERNAL] PEND Release FW: Chandler AWRF Influent As-built Dimensions

Jeff,

How are we sitting on this? Also, | would like to get a firm quantity for the Chandler 6” Ductile Iron as well.

Thank you,

Alexander W. Greene

Project Manager

GARNEY CONSTRUCTION Advancing Water

CELL: 719.322.3308

ADDRESS: 4435 E. Holmes Avenue, Suite 102, Mesa AZ 85206 GARNEY.COM

From: Alexander Greene <awgreene@garney.com>

Sent: Thursday, November 4, 2021 11:47 AM

To: Jeff Cassano <JCassano@cbpiping.com>

Subject: RE: [EXTERNAL] PEND Release FW: Chandler AWRF Influent As-built Dimensions

Jeff,

They are using strap on meters, there is no reduction...straight 30 across the span. We would need to line up joints
around the support piers.

Thank you,

Alexander W. Greene

Project Manager

GARNEY CONSTRUCTION Advancing Water

CELL: 719.322.3308

ADDRESS: 4435 E. Holmes Avenue, Suite 102, Mesa AZ 85206 GARNEY.COM

From: Jeff Cassano <JCassano@cbpiping.com>

Sent: Thursday, November 4, 2021 10:45 AM

To: Alexander Greene <awgreene@garney.com>; Jeff Cassano <JCassano@cbpiping.com>
Subject: [EXTERNAL] PEND Release FW: Chandler AWRF Influent As-built Dimensions

External Message - Please be cautious when opening links or attachments in email

Alex,

Does the 30” Run 61’ 5”, include the Meter w/Reducers... or is pipe from end to end.
Definitely need to be cautious for spools lengths to avoid flanges hitting the existing columns.
I’m confirming Gilbert Stock now.

From: Alexander Greene <awgreene@garney.com>
Sent: Thursday, November 4, 2021 11:29 AM

To: Jeff Cassano <JCassano@cbpiping.com>

Ce: Jim Symonds <jsymonds@garney.com>

Subject: Chandler AWRF Influent As-built Dimensions

Jeff,

Here are the actual dimensions for the Chandler AWRF Influent Pipe, we would be replacing two of the lines. Based on
the materials on hand, could we get one complete run in the near future and the other when available? We will also
need a 6” flanged weld-o-let added to each line for the vent, this would be at the East end. Let me know, there is one
line that is in worse shape than the other, if we could get enough pipe to replace that, it might buy Chandler some
time. Feel free to contact me with any questions or concerns.

Thank you,

Alexander W. Greene
Project Manager

GARNEY CONSTRUCTION Advancing Water
CELL: 719.322.3308
ADDRESS: 4435 E. Holmes Avenue, Suite 102, Mesa AZ 85206 GARNEY.COM

This e-mail message is intended only for named recipients. It contains information that may be confidential, privileged,
or otherwise exempt from disclosure under applicable law. If you have received this message in error, are not a named
recipient, or are not the employee or agent responsible for delivering this message to a named recipient, be advised that
any review, disclosure, use, dissemination, distribution, or reproduction of this message or its contents is strictly
prohibited. Please notify us immediately that you have received this message in error, and delete the message. Thank
you. Visit us on the web at http://www.Garney.com

This e-mail message is intended only for named recipients. It contains information that may be confidential, privileged,
or otherwise exempt from disclosure under applicable law. If you have received this message in error, are not anamed
recipient, or are not the employee or agent responsible for delivering this message to a named recipient, be advised that
any review, disclosure, use, dissemination, distribution, or reproduction of this message or its contents is strictly
prohibited. Please notify us immediately that you have received this message in error, and delete the message. Thank
you. Visit us on the web at http://www.Garney.com

This e-mail message is intended only for named recipients. It contains information that may be confidential, privileged,
or otherwise exempt from disclosure under applicable law. If you have received this message in error, are not anamed
recipient, or are not the employee or agent responsible for delivering this message to a named recipient, be advised that
any review, disclosure, use, dissemination, distribution, or reproduction of this message or its contents is strictly
prohibited. Please notify us immediately that you have received this message in error, and delete the message. Thank
you. Visit us on the web at http://www.Garney.com

United Rentals’ __||[/IINIINNINIDNIININL

BRANCH J90
215 EAST BASELINE ROAD

RENTAL QUOTE

# 199487644

GILBERT AZ 85233
490-909-9681 FAX Customer # 382816
Betimated out | 10/22/21 07:00
Estimated Out : 1 F AM
hy CHANDLER AIRPORT Estimated In : 11/19/21 07:00 AM
Bal 2380 S STINSON WAY UR Job Loc san S STINSON WAY,
CHANDLER AZ 85286-1728 Oe eee cb ZI
2 Requetted B ALEXA
i ° _ _ : _ _ equeste EXANDER GREENE
HI Office: 303-791-3600 Cell: 719-322-3308 Approved. By” EJ JILES
Salesperson : STEPHANIE DOHM

GARNEY CONST WESTERN REGION
1333 NW VIVION RD
KANSAS CITY MO 64118-4554

This is not an invoice

_ Please do not pay from this document

RENTAL ITEMS:

COMMENTS /NOTES :

CONTACT: ALEXANDER GREENE
CELL#: 719-322-3308

TO SCHEDULE EQUIPMENT FOR PICKUP, CALL 800-UR-RENTS (800-877-3687)
WE ARE AVAILABLE 24/7 TO SUPPLY YOU WITH A CONFIRMATION #
IN ORDER TO CLOSE THIS CONTRACT

Qty _Equipment Description Minimum Day Week Month Estimated Amt.
1 3106526 BOOM 65-70' TELESCOPIC 498.00 513.00 1,206.00 2,423.00 2,423.00
YOU HAVE RENTED A MOBILE ELEVATING WORK PLATFORM (MEWP). SOME OF OUR
MEWPS HAVE BEEN EQUIPPED WITH ACCESSORIES THAT MAY REDUCE THE RISK
OF ENTRAPMENT HAZARDS AND CRUSHING INJURIES. OTHERS CAN HAVE THESE
ACCESSORIES ADDED. FEEL FREE TO DISCUSS THESE ACCESSORIES WITH YOUR
LOCAL BRANCH AND EXPLORE WHETHER YOU WOULD LIKE TO RENT A UNIT
EQUIPPED WITH THIS TECHNOLOGY FOR YOUR PARTICULAR PROJECT.
FOR FURTHER INFORMATION ON MEWP SAFETY, PLEASE WATCH THE FOLLOWING
VIDEO: HTTP: //UNITEDRENTALS . COM/MEWPS-SAFETY
1 3108026 BOOM 76-80' TELESCOPIC 775.00 798.00 1,795.00 4,009.00 4,009.00
YOU HAVE RENTED A MOBILE ELEVATING WORK PLATFORM (MEWP). SOME OF OUR
MEWPS HAVE BEEN EQUIPPED WITH ACCESSORIES THAT MAY REDUCE THE RISK
OF ENTRAPMENT HAZARDS AND CRUSHING INJURIES. OTHERS CAN HAVE THESE
ACCESSORIES ADDED. FEEL FREE TO DISCUSS THESE ACCESSORIES WITH YOUR
LOCAL BRANCH AND EXPLORE WHETHER YOU WOULD LIKE TO RENT A UNIT
EQUIPPED WITH THIS TECHNOLOGY FOR YOUR PARTICULAR PROJECT.
FOR FURTHER INFORMATION ON MEWP SAFETY, PLEASE WATCH THE FOLLOWING
VIDEO: HTTP: //UNITEDRENTALS .COM/MEWPS-SAFETY
Rental Subtotal: 6,432.00
SALES/MISCELLANEOUS ITEMS:
Qty Item Price Unit _of Measure Extended Amt.
1 PROPERTY TAX SURCHARGE ([DRSURAZ/MCTI] 96.480 EACH 96.48
1 DELIVERY CHARGE 85.000 EACH 85.00
1 PICKUP CHARGE 85.000 EACH 85.00
Sales/Misc Subtotal: 266.48
Agreement Subtotal: 6,698.48
Tax: 522.48
Estimated Total: 7,220.96

This proposal may be withdrawn if not accepted within 30 days. The above referenced Rental Protection Plan, environmental, and tax charges are estimates and are subject to change,

Agreement, which are available at https://www.unitedrentals.com/legal/rental-service-terms-US and which are incorporated herein by reference. A COPY OF THE RENTAL AND SERVICE

AGREEMENT TERMS ARE AVAILABLE IN PAPER FORM UPON REQUEST.

Page:

NOTICE: This is not a rental agreement. The rental of equipment and any items listed above is subject to availability and subject to the terms and conditions of the Rental and Service

1