JOB ORDER PROJECT AGREEMENT

Project Name: HAMILTON AQUATIC CENTER SAFETY IMPROVEMENTS - TRENCH
DRAIN REPLACEMENT

Project No. CS2202.401

This JOB ORDER PROJECT AGREEMENT (“Job Order”) is made this day of 2022 (“Effective
Date”), by and between the City of Chandler, an Arizona municipal corporation, (“City”) and Caliente
Construction, Inc., an Arizona corporation, (“JOC Contractor”) and is entered into pursuant to Job Order
Master Agreement No. JOC1904.401 (“JOC Master Agreement”). City and JOC Contractor may be referred to
individually as “Party” or collectively as “Parties”.

City and JOC Contractor, in consideration of the mutual covenants herein set forth, agree as follows:
RECITALS

A. On or about December 17, 2019, the Parties entered into the JOC Master Agreement, which terms and
conditions are made a part of and incorporated into this Job Order Project Agreement by this reference.

B. City proposes to engage JOC Contractor for Hamilton Aquatic Center Safety Improvements - Trench Drain
Replacement as more fully described in Exhibit "A", which is attached to and made a part of this Job Order
by this reference.

C. JOC Contractor is ready, willing, and able to provide the services described in Exhibit “A” for the
compensation and fees set forth and as described in Exhibit "B”, which is attached to and made a part of

this Agreement by this reference.

ARTICLE 1. DESCRIPTION OF WORK

The Parties enter into this Job Order Project Agreement for the HAMILTON AQUATIC CENTER SAFETY
IMPROVEMENTS - TRENCH DRAIN REPLACEMENT, Project Number CS2202.401. The scope of work
consists of safety improvements and trench drain replacement at Hamilton Aquatic Center, all as more
particularly set forth in Exhibit “A” attached hereto and incorporated herein by reference.

The JOC Contractor will not accept any change of scope, or change in contract provisions, unless issued in
writing, as a contract amendment or change order and signed by the authorized signatories for each party.

Performance and Payment Bonds, as set forth in Exhibit “C” and Exhibit “D” respectively attached hereto
and incorporated herein by reference, will be due prior to execution of each Job Order Project Agreement
in the full amount of each Job Order.

City of Chandler Job Order Project Agreement A-1
Public Works & Utilities Department, Capital Projects Division

Project Name: HAMILTON AQUATIC CENTER SAFETY IMPROVEMENTS - TRENCH DRAIN REPLACEMENT

Project No.: CS2202.401

Rev. 9/18/2020

At project completion, JOC Contractor must complete Contractor's Affidavit Regarding Settlement of Claims
and Certificate of Completion, as set forth in Exhibit “E” and Exhibit “F” respectively attached hereto and
incorporated herein by reference.

ARTICLE 2. PROJECT PRICE

City will pay JOC Contractor for completion of the Work in accordance with the JOC Master Agreement a fee
not to exceed the Guaranteed Maximum Price of $83,947.43 Dollars determined and payable as set forth
in JOC Master Agreement and Exhibit “B” attached hereto and made a part hereof by reference.

ARTICLE 3. CONTRACT TIME & SCHEDULE

JOC Contractor agrees to complete all Construction within 60 calendar days from the Notice to Proceed
(NTP) Date.

ARTICLE 4. PARTICIPANTS

CITY: Construction Project Manager: Jason Garcia
Phone: | 480-782-3453
Email: | Jason.garcia@chandleraz.gov

JOC CONTRACTOR: Caliente Construction, Inc.
485 W. Vaughn St.
Tempe, AZ 85283
JOC Contractor Representative: Lorraine Bergman
Phone: | 480-894-5500
Email: | lbergman@calienteconstruction.com

SIGNATURE PAGE TO FOLLOW

City of Chandler Job Order Project Agreement A-1
Public Works & Utilities Department, Capital Projects Division

Project Name: HAMILTON AQUATIC CENTER SAFETY IMPROVEMENTS - TRENCH DRAIN REPLACEMENT

Project No.: CS2202.401

Rev. 9/18/2020

IN WITNESS WHEREOF, the Parties have executed this Job Order as of the Effective Date.

“GITY” | “JOC CONTRACTOR”
CITY OF CHANDLER: Caliente Construction, Inc.:

01/11/2022
Date

MAYOR Date

Recommended By: Print Name

Presiden/CEO _
a ee Title
Andrew Goh, P.E.
CIP City Engineer : If Corporation
APPROVED AS TO FORM: 2——
Nel Zw
City Attorney yr
By: ‘
ADDRESS FOR NOTICE
ATTEST:
_ Caliente Construction, Inc. _
485 W. Vaughn St.
City Clerk SEAL

Tempe, AZ 85283

ADDRESS FOR NOTICE
City of Chandler

P.O. Box 4008, Mail Stop 407
Chandler, AZ 85244-4008

City of Chandler Job Order Project Agreement ‘ os AT
Public Works & Utilities Department, Capital Projects Division

Project Name: HAMILTON AQUATIC CENTER SAFETY IMPROVEMENTS - TRENCH DRAIN REPLACEMENT

Project No.: CS2202.401

Rev. 9/18/2020

EXHIBIT. A
SCOPE OF WORK

City of Chandler Job Order Project Agreement - ‘ Sik HOE Dare
Public Works & Utilities Department, Capital Projects: Division a

Project Name: HAMILTON AQUATIC CENTER SAFETY IMPROVEMENTS - TRENCH DRAIN REPLACEMENT
Project No.: CS2202.401

Rev. 9/18/2020

Caliente Construction inc.

General Construction - Construction Management - Design/Build - Facilities Management

Ri December 8, 2021

Ivan Magana, PE

Project Manager

City of Chandler

Public Works and Utilities Dept. - Capital Projects Div.
215 East Buffalo Street

Chandler, AZ 85225

RE: City of Chandler JOC 1904.401 - CS2202.401 Hamilton Aquatics Center Safety Improvements: Trench Drain Replacement R1

Mr. Magana,

Thank you for the opportunity to provide our revised proposal for the CS2202.401 Hamilton Aquatics Center Safety
Improvements: Trench Drain Replacement R11 Project.

We have based the attached proposal on information received, emails and site visit held with the City of Chandler.
The price is $ 83,947.43. See attached estimate with bid tabulations and subcontractor back-up for further details.
Please contact me at your convenience should you have any questions.

Best Regards,

foes

Justin Miller
Caliente Construction Inc.

One of the Valley's Healthiest Employers
485 West Vaughn, Tempe, Arizona 85283-3672 Phone: (480) 894-5500 Fax: (480) 894-2323

Cen a
WBENG £ ey at AZROC091625 AZ ROCO98769 AZ ROC164561 CA 770323 UT 4741522-550 NV 0078132

ID RCE-28529 NM 85371 CO 233580 MT 159637

“We build more than structures; we build confidence and relationships that last”

Caliente Construction Inc.

General Construction - Construction Management - Design/Build - Facilities Management

EXHIBIT A
SCOPE-OF WORK

PROJECT:
City of Chandler JOC 1904.401 - CS2202.402 Hamilton Aquatics Center Safety Improvements: Trench Drain Replacement R1

General Requirements:
1) Provide office support, supervision, overhead/profit, taxes based on MRRA, insurances, and bond.

2) Provide temporary protection as required.

Construction:
1) Saw-Cut and Remove existing Trench Drain at (3) Locations (~150LF) by demo contractor
2) Excavate as required for New Trench Drain
3) Furnish and Install New Trench Drains (Zurn or equal) similar to existing at (3) Locations (~150LF)
4) Concrete for Setting Drains (existing trench drains will be sawcut and removed and the new drains set back, and concrete
tied into adjacent pool deck) by plumbing contractor
5) Site Cleanup

Project Duration:
Proposal based on onsite Project Duration of 1 Week after procurement of materials. Estimated Lead time for drains is 3-4 Weeks

from time of submittal approval/order.

Clarifications/Exclusions:
See attached estimate.

oo One of the Valles Healthiest Employers
With 485 West Vaughn, Tempe, Arizona 85283-3672 Phone : (480) 894-5500 Fax : (480) 894-2323
Faas p AZROC091625 AZ ROCO98769 AZ ROC164561 CA 770323 UT 4741522-550 NV 0078132 ,™
whe ID RCE-28529 NM 85371 CO 233580 MT 159637 hee’

“We build more than structures; we build confidence and relationships that last”

COC JOC 1904.401 CS2202.402 Hamilton Aquatics Center Safety Improvements: Trench Drain Replacement

Caliente
Construction Inc.

‘Assumptions / Clarifications

1

Proposal based on onsite Project Duration of (1-2 Weeks) after procurement of material (estimated
lead time for drains is 4 weeks from time of submittal approval/order)

2 Proposal based on Normal Working Hours M-F

3. Proposal based on COC Aquatics

4 Proposal based on access to site

5 Proposal based on replacement of (3) Sections identified during walkthrough (~150LF)
Exclusions :

1 Design Services, Permits and/or Permitting Fees

2. Asbestos Testing and/or Abatement and/or Removal of Hazardous Materials (Current

Report/Survey to provided by COC prior to start of Demolition).
3. Badging or Special Background Checks and/or associated costs
4 Excludes Concrete Re-finishing for pool deck

Allowances (Not Included in Base Bid; No Markups)

4

CONSTRUCTION ALLOWANCE $ 6,800.00

EXHIBIT B
FEE SCHEDULE

City of Chandler Job Order Project Agreement

Public Works & Utilities Department, Capital Projects Division

Project Name: HAMILTON AQUATIC CENTER SAFETY IMPROVEMENTS - TRENCH DRAIN REPLACEMENT
Project No.: CS2202.401

Rev. 9/18/2020

B-1

Caliente Construction Inc.

General Construction - Construction Management - Design/Build - Facilities Management

EXHIBIT "B"

COC JOC 1904.401 CS2202.401 Hamilton Aquatics Center Safety Improvements:
Trench Drain Replacement R1

JOB ORDER COST PROPOSAL

SUMMARY SHEET
12/8/2021
Negotiated Prices
Price of Subcontractor(s) $ 61,698.00
Price of Subconsultant(s) $ -
General Conditions $ 6,470.00
Preconstruction Labor (if applicable) $ -
Construction Labor (if applicable) $ -
SUBTOTAL (NEGOTIATED PRICES):| $ 68,168.00
Overhead and Profit (Coefficient per Job Order Master Agreement) 10.00% $ 6,816.80
TOTAL (NEGOTIATED PRICES + OVERHEAD & PROFIT):| $ 74,984.80
Insurance, Bonds, & Taxes
Sales Tax Percentage (Current Tax Rate) MRRA 0.000% $ -
| General Liability Insurance Percentage (Actual Cost per Job Order) 1.00% $ 681.68
| Builder's Risk Insurance Percentage (Actual Cost per Job Order) 0.50% $ 340.84
Payment Bond (Actual Cost per Job Order) 1.50% $ 1,140.11
Performance Bond (Actual Cost per Job Order) INC 0.00% $ -
SUBTOTAL (INSURANCE, BONDS, & TAXES): $ 2,162.63
COMBINED TOTAL (TOTAL + INSURANCE, BONDS, & TAXES):} $ 77,147.43
City's Allowance $ 6,800.00
TOTAL JOB ORDER:| $ 83,947.43

Per the Job Order Master Agreement - [his Fee lable includes all fees, costs, insurance and bond premiums, allowances,
| construction contingency, and taxes of any type necessary to fully, propertly and timely perform and construct the Work.
Also per the Job Order Master Agreement - For any portion of the Work which, either through this Contract, Change Order or
otherwise, is performed and paid for on a cost, or time and materials basis, the costs may be reimbursed to JOC Contractor
and chargeable against the Contract Price will be determined as set forth in MAG 109.5.

#1 Tenant Improvement ContrantocIn Arizona 2006, 2017, 2018 & #1 General Contractor in Avtzone 2017, 2078, 2015
2048 Tempe Business Excebenos Award Winner

Ww

NE 405 Vé. Vituat Stine, Tevee, AZ 5283 / Bea: (420) BIM.£500 J Fave: (420) BM-2323
*) AZROCONIE25, AZ ROCORETH. AZ ACCHEASH! . CA 770923 . UT 47A1502.520
IDRCE26625, MUA NS371 CO 251580. NT 80637. CA 21B676 . WA EOI-190-824

certified

“We build more than structures; we build confidence and relationships that last”

©

Caliente

Construction Inc.
COC JOC 1904.401 CS2202.401 Hamilton
Project: Aquatics Center Safety Improvements:
Trench Drain Replacement R1 400 Building Sq. Ft.
Owner: City of Chandler - Site Sq. Ft.
Architect: N/A 0.00 Site Acres
Bid Date: 12/18/2021 RF\(s): 00000 Permit Set
Taxing Jurisdiction: | Chandler Addendum(s): 00000
MRRA or TPT: MRRA
DESCRIPTION TOTALS
DIVISION 1 GENERAL CONDITIONS $ 6,470.00
DIVISION 2 EXISTING CONDITIONS $ 2,250.00
DIVISION 22 PLUMBING $ 59,448.00
Subtotal of Cost Of Work $ 68,168.00
OVERHEAD/PROFIT 10.00% $ 6,816.80
GENERAL LIABILITY INSURANCE 1.00% $ 681.68
BUILDERS RISK INSURANCE 0.50% $ 340.84
BONDING FEES 1.50% $ 1,140.11
CONSTRUCTION ALLOWANCE LS $ 6,800.00
TAX (Chandler 5.070%) MRRA (by subcontractors) 0.000% $ -
TOTAL COST $ 83,947.43

€

Caliente COC JOC 1904.401 CS2202.402 Hamilton Aquatics Center Safety Improvements: Trench Drain Replacement R1
Construction Inc.

General Conditions

1 Weeks
DATE: 12/8/2021 7 Calendar Days
CODE ITEM QTY TYP RATE SUBTOTAL
GENERAL CONDITIONS $ 5,970.00
00-1040 | Project Manager 0.25 WK $ 4,200.00 | $ 1,050.00
00-1052 | Assistant Project Manager 0.20 WK $ 3,200.00 | $ 640.00
00-1047 | Project Coordinator 0.20 WK $ 2,400.00 | $ 480.00
00-1045 } Superintendent 1.00 WK $ 3,800.00 | $ 3,800.00
GENERAL REQUIREMENTS $ 500.00
00-1096 | Safety / Temp Protection 1.00 LS $ 500.00 | $ 500.00
GENERAL CONDITIONS TOTAL $ 6,470.00

PROJECT:

PO BOX 144
SCOTTSDALE, AZ 85252. ,
(602)510-3540

www. advanceddemolition.net
AZROC - 313039

COC AQUATICS TRENCH DRAIN

ADDRESS CHANDLER, AZ

TO:
ATTN:

CALIENTE

JUSTIN MILLER

PROPOSAL AND
AGREEMENT
DATE: 11/10/2021
BID EXP.: 60 DAYS
BID#: 1645-21
ESTIMATOR: JERRY CHANDLER
CELL PHONE: 602-510-3540

ESTIMATOR E-MAIL: jerry@advanceddemo.net

SCOPE OF WORK: DEMOLITION

ITEM No.

DESCRIPTION:

PRICE:

DEMOLITION

SCOPE OF WORK

|SAWCUT AND REMOVE APPROX. 150 LF OF TRENCH DRAIN IN POOL DECK

2,250.00

2,250.00

[Policy

ADVANCED DEMOLITION, LLC (AD) will furnish all labor, equipment & pay all dumping fees incurred in performing work at the above
referenced address The work area will be kept free of any trash & debris. Any additions or deletions must be in writing and must be
signed by both Owner/GC and AD. This proposal shall become part of the contract documents. All SALVAGE _ rights belong to ADVANCED
DEMOLITION unless otherwise specified. Any overtime, nights, weekends and holidays will be subject to change order unless otherwise
specified. This bid is good for 60 days, unless noted otherwise. Payment terms are 10% down required prior to mobilization. Final
payment due on all invoices with in (30) days of invoice. Balances and retention that was held is due (30) days from the completion of
project. Note: The Owner/GC shall provide AD with an Asbestos Survey prior to any work being done. If asbestos is present it must be
removed according to OSHA, EPA and County Regulations prior to Demolition. Please Note that all Asbestos and Structural Demolition
projects are subjected to a (10) day (NESHAP Notification) waiting period prior to the commencement of project. AD is not responsible for
weather proofing, temporary drying in or anything related to weather or water intrusion or any weather damage caused by our work. AD
is not responsible for any inadvertent damage caused by our work. Within 24 hours of any suspected damage allegedly caused by us, we
must be notified in writing. We have the right to repair any of the said damage by our contractor of choice. Unless there is a schedule in
writing, and both parties have agreed to it, AD will prepare and perform our work in our time frame. It is customary forAdvanced
Demolition to pre-lien all projects prior to the commencement of work. After final completion of the scope of work, and when final
payment has been received, ADVANCED DEMOLITION will issue to Client a final and unconditional lien waver.

Exclusions
All items omitted or not clearly shown on the demolition plans, specification and/or ADVANCED DEMOLITION Proposal. Layout, MP&E

disconnects, capping, make safe, shoring, coring, masonry toothing, mastic to more than 70%, dust barriers, negative air machines,
hazardous materials, permits, bond/ taxes, additional move-ins, temporary power, sanitation facilities, slabs/stems and footings larger

than current code for same construction.

Approval and Signature

JERRY CHANDLER OWNER/ESTIMATOR
ey COE) {HEHE
DATE
Signature:

Owner/GC Approval: DATE

RYAN MECHANICAL COMPANY

aS ee

a 1325 N. Mondel Drive « Gilbert, Arizona 85233 (480) 497-4526 © FAX (480) 497-4527

C-37R 098919 © L-37 080516 ¢ L-39 097541
www.ryanmechanical.com

October 13", 2021
A PLUMBING Proposal For
Hamilton Aquatic Center

Below please find our price for the above listed project. We are providing this bid to
insure that you have coverage. Please contact us to review scheduling before awarding
this project.

PROVIDE & INSTALL: ADDENDA: none
1) Plumbing demolition.
2) Excavate FBO Sawcut Trenches.
3) Install 3 new Trench Drains as indicated.
TOTAL PRICE............ $55,300.00

Bond= + 1.5%

EXCLUSIONS:

1) Permits, fees, taxes & bond.

2) Night Work 5:00PM-3:00AM, (We have early mornings for
demolition/noisy work). We cannot do night work at this time.

3) Material Sales Tax, (add $4,148.00).

4) Sawcut/removal/pourback.

5) Mechanical/HVAC/Fire Risers/Condensates/Gas/Meters or fees.

6) X-raying surfaces.

7) Opening or Patching walls, ceilings, or floor goods; Permanent roof patch.

8) Site Work, Civil Work, Utility Relocation, Rock/Caliche Excavation,
Temporary water, Imported Fills or Spoils Removal

Sincerely,

Joseph P. Ryan
RYAN MECHANICAL CO.

Joe@ryanmechanical.com

EXHIBIT C

PERFORMANCE BOND
ARIZONA STATUTORY PERFORMANCE BOND
PURSUANT TO TITLES 28, 34, AND 41, ARIZONA REVISED STATUTES
(Penalty of this bond must be 100% of the Contract amount)

KNOW ALL MEN BY THESE PRESENTS THAT:
(hereinafter Principal"), and (hereinafter "Surety"), a
corporation organized and existing under the laws of the State of with its principal office in the City of
holding a certificate of authority to transact surety business in Arizona issued by the
Director of Insurance pursuant to Title 20, Chapter 2, Article 1, as Surety, are held and firmly bound unto

(hereinafter "Obligee") in the amount of
(Dollars) ($. ), for the payment whereof, Principal and Surety bind themselves, and their heirs, administrators,
executors, successors and assigns, jointly and severally, firmly by these presents.

WHEREAS, the Principal has entered into a certain written contract with the Obligee, dated

the day of 20__ for construction of HAMILTON AQUATIC CENTER SAFETY
IMPROVEMENTS - TRENCH DRAIN REPLACEMENT, CS2202.401 which contract is hereby referred to and made a part
hereof as fully and to the same extent as if copies at length herein.

NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION IS SUCH, that if the Principal faithfully performs and
fulfills all the undertakings, covenants, terms, conditions and agreements of the contract during the original term of the
contract and any extension of the contract, with or without notice of the Surety, and during the life of any guaranty
required under the contract, and also performs and fulfills all the undertakings, covenants, terms, conditions, and
agreements of all duly authorized modifications of the contract that may hereafter be made, notice of which
modifications to the Surety being hereby waived, the above obligation is void. Otherwise it remains in full force and
effect.

PROVIDED, HOWEVER that this bond is executed pursuant to the provisions of Title 34, Chapter 2, Article 2,
Arizona Revised Statutes, and all liabilities on this bond will be determined in accordance with the provisions of Title 34,
Chapter 2, Article 2, Arizona Revised Statutes, to the same extent as if it were copied at length in this Contract.

The prevailing party in a suit on this bond may recover as part of the judgment reasonable attorney fees that
may be fixed by a judge of the court.

Witness our hands this day of 20_.
PRINCIPAL SEAL
AGENT OF RECORD
By
SURETY SEAL
AGENT ADDRESS
City of Chandler Job Order Project Agreement GE C-1

Public Works & Utilities Department, Capital Projects Division

Project Name: HAMILTON AQUATIC CENTER SAFETY IMPROVEMENTS - TRENCH DRAIN REPLACEMENT
Project No.: CS2202.401

Rev. 9/18/2020

EXHIBIT D

PAYMENT BOND
ARIZONA STATUTORY PAYMENT BOND
PURSUANT TO TITLES 28, 34, AND 41, OF THE ARIZONA REVISED STATUTES
(Penalty of this Bond must be 100% of the Contract amount)

KNOW ALL MEN BY THESE PRESENTS THAT:

(hereinafter "Principal"), as Principal, and (hereinafter "Surety"), a corporation
organized and existing under the laws of the State of with its principal office in the City of
holding a certificate of authority to transact surety business in Arizona issued by the Director of the
Department of Insurance pursuant to Title 20, Chapter 2, Article 1, as Surety, are held and firmly bound unto

(hereinafter "Obligee") in the amount of
(Dollars) ($. ), for the payment whereof, the Principal and Surety bind themselves, and their heirs,
administrators, executors, successors and assigns, jointly and severally, firmly by these presents.

WHEREAS, the Principal has entered into a certain written contract with the Obligee, dated the day of
20__ for construction of HAMILTON AQUATIC CENTER SAFETY IMPROVEMENTS - TRENCH
DRAIN REPLACEMENT, CS2202.401 which contract is hereby referred to and made a part hereof as fully and to the
same extent as if copied at length herein.

NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION IS SUCH, that if the Principal promptly pays all moneys
due to all persons supplying labor or materials to the Principal or the Principal's subcontractors in the prosecution of
the work provided for in said contract, this obligation is void. Otherwise it remains in full force and effect.

PROVIDED, HOWEVER that this bond is executed pursuant to the provisions of Title 34, Chapter 2, Article 2
Arizona Revised Statutes, and all liabilities on this bond will be determined in accordance with the provisions, conditions
and limitations of Title 34, Chapter 2, Article 2, Arizona Revised Statutes, to the same extent as if it were copied at length
in this Contract.

The prevailing party in a suit on this bond may recover as part of the judgment reasonable attorney fees that
may be fixed by a judge of the court.

Witness our hands this day of 20_.

PRINCIPAL SEAL

AGENT OF RECORD
By

SURETY SEAL

AGENT ADDRESS

City of Chandler Job Order Project Agreement fers D-1
Public Works & Utilities Department, Capital Projects Division

Project Name: HAMILTON AQUATIC CENTER SAFETY IMPROVEMENTS - TRENCH DRAIN REPLACEMENT

Project No.: CS2202.401

Rev. 9/18/2020 all

EXHIBIT E

CONTRACTOR'S AFFIDAVIT REGARDING SETTLEMENT OF CLAIMS

Arizona

Date
Project Name: HAMILTON AQUATIC CENTER SAFETY IMPROVEMENTS - TRENCH DRAIN REPLACEMENT
Project No.: CS2202.401

To the City of Chandler, Arizona
Gentlemen:

This is to certify that all lawful claims for materials, rental of equipment and labor used in connection with
the construction of the above project, whether by subcontractor or claimant in person, have been duly
discharged.

The undersigned, for the consideration of $. , as set out in the final pay estimate, as
full and complete payment under the terms of the contract, hereby waives and relinquishes any and all
further claims or right of lien under, in connection with, or as a result of the above described project. The
undersigned further agrees to indemnify and save harmless the City of Chandler against any and all liens,
claims or liens, suits, actions, damages, charges and expenses whatsoever, which said City may suffer arising
out of the failure of the undersigned to pay for all labor performances and materials furnished for the
performance of said installation.

Signed and dated at , this day of 20.
CONTRACTOR
By
STATE OF ARIZONA )
)SS
COUNTY OF MARICOPA )
The foregoing instrument was subscribed and sworn to before me this day of
20

Notary Public

My Commission Expires

City of Chandler Job Order Project Agreement vt E-1
Public Works & Utilities Department, Capital Projects Division

Project Name: HAMILTON AQUATIC CENTER SAFETY IMPROVEMENTS - TRENCH DRAIN REPLACEMENT

Project No.: CS2202.401

Rev. 9/18/2020

EXHIBIT F

CERTIFICATE OF COMPLETION
Project: HAMILTON AQUATIC CENTER SAFETY IMPROVEMENTS - TRENCH DRAIN
REPLACEMENT
Project No.: CS2202.401

(TO BE COMPLETED BY CONTRACTOR)

| HEREBY CERTIFY THAT ALL GOODS AND/OR SERVICES REQUIRED BY CITY OF CHANDLER PROJECT NO.
CS2202.401 HAVE BEEN DELIVERED IN ACCORDANCE WITH THE CONTRACT DOCUMENTS AND BID
SPECIFICATIONS AND ALL ACTIVITIES REQUIRED BY THE CONTRACTOR UNDER THE CONTRACT HAVE BEEN
COMPLETED AS OF

(Date)
FIRM NAME:
PRINCIPAL:
(Name)
(Signature)
DATE:
(Title)

CERTIFIED BY ENGINEER/CONSULTANT (/F APPLICABLE):

DATE:

(Signature)

(Firm Name)

SE SD EE EET
PROJECT ACCEPTED BY USER DEPARTMENT

DATE:

(Signature)

(Dept. /Div.)
Date of Final Walk-Through

Date As-Built Received

City As-Built Number

City of Chandler Job Order Project Agreement F-1
Public Works & Utilities Department, Capital Projects Division

Project Name: HAMILTON AQUATIC CENTER SAFETY IMPROVEMENTS - TRENCH DRAIN REPLACEMENT

Project No.: CS2202.401

Rev. 9/18/2020