TC Project Status Update May 2022

City of Chandler — Regular Meeting (2022-05-18)

View PDF Meeting page

Extracted text (via pymupdf) 5001 characters
Projects
Designer
Contractor
Status
Comments
PROJECT COST 
ESTIMATE 
($MILLIONS)
ROADWAY AND TRAFFIC PROJECTS
ST1503, Cooper Road Imprv. [Alamosa Drive (aprx. 3,500 ft. north of 
Chandler Heights Road) to Riggs Road for two through lanes each direction]
Entellus
Pulice Construction
Construction underway.  Completion scheduled for mid 2022.
Federal funds
$19.3
ST1614, Chandler Heights Road Imprv. [McQueen Road to Gilbert Road for 
two through lanes each direction]
Kimley-Horn
tbd
Construction contract award in February 2022.  Long lead procurement 
NTP Spring 2022.  Start construction Summer 2022.
Federal funds
$20.9
ST1616, Ocotillo Road Imprv. [Gilbert Road to 148th Street for two through 
lanes each direction]
Ritoch-Powell
tbd
Open bids late January 2022.  Construction contract award April 2022.  
Long lead NTP late Spring 2022.  Start construction late Summer 2022.
Federal funds
$6.4
ST1804, Chandler Heights Road Imprv. [Gilbert Road to Val Vista Drive for 
two through lanes each direction]
Kimley-Horn
tbd
Design in progress.  Bid scheduled for Spring 2023.
Federal funds
$20.9
ST1908, Bicycle Detection System  [40 intersections]
n/a
n/a
Purchase of bicycle detection cameras
Federal funds
$1.3
ST1909, Alleyway Rehab PM10 Dust Emission Reduction
n/a
Cactus Asphalt
Construction underway.
Federal funds
$2.1
ST2001, Lindsay Road Imprv. [Ocotillo Road to Hunt Highway for two 
through lanes in each direction]
Kimley-Horn
tbd
Design in progress.  Bid scheduled for summer 2023.
Federal funds
$27.2
ST2002, Traffic Study of Kyrene Road [Chandler Boulevard to Loop 202]
AZTEC
n/a
Study complete.
$0.2
ST2003, Gilbert Road Imprv. [Ocotillo Road to Chandler Heights Road for 
new traffic signals and three through lanes in each direction]
Sunrise Engineering
Sunland Asphalt
Construction complete.
$8.5
ST2004, Alma School Road Imprv. [Pecos Road to Germann Road for three 
through lanes in each direction to match development imprv.]
Wood
Sunland Asphalt
Construction complete.
$3.7
ST2006, Traffic Signal at Warner Road and Nevada Street
Stanley Consultants
tbd
Design complete.  Construction in 2022
$0.8
ST2007, Hamilton Street Imprv. [Appleby Road to Carob Drive]
Nfra Consultants
tbd
Design in progress.  Construction in 2022
$3.4
ST2009, Dobson Road Imprv. at Intel Driveways #1 and #4 [Price Rd / 
Market Pl to Chaparral Way]
Premier
DCS Contracting
Design in progress.
Funded by 20% from Intel and 80% from State TPT per 
ARS 42-5032.02
$0 City Cost (Intel 
Funded)
ST2012, Arterial Congestion Monitoring [Install data collection devices at 
major intersections, and use data to map traffic congestion and mobility.]
Y.S. Mantri & Assoc.
tbd
Design complete.  Installation in 2022
Grant funds
$0.8
ST2103, Intersection Imprv. at Ray Road and Dobson Road
tbd
tbd
Study to begin in Feb 2022.
Study only.  Future phases tbd.
$0.1
ST2104, Traffic Signal at Ocotillo Road and Pinelake Way
Y2K Engineering
tbd
Design in progress.
$0.8
ST2113, Alley Rehab PM10 Dust Emissions Reduction 2 (FMA Areas 16, 25, 
39, and 40)
Premier / Olsson
tbd
Design in progress.
Federal funds
$2.4 (tbc)
PEDESTRIAN, BICYCLE, AND TRANSIT PROJECTS
ST1612, Chandler Boulevard Bike Lanes [I-10 to 56th Street]
Kimley-Horn
Combs Construction
Construction complete.
Federally funded
$1.3
ST1613, Downtown ADA Improvements [Downtown Chandler on Chicago 
Street, Washington Street, and Boston Street]
J2
DNG
Phase I construction complete.  Phase II construction complete.
Locally funded.
$1.5
ST1701, McClintock Drive Bike Lanes [Loop 202 to north of Ray Road] & 
Kyrene Road Bike Lanes - [Chandler Boulevard to north of Ray Road]
Aztec
AJP Electric
Construction complete.
Federally funded
$5.6
ST2011, Study of Price Road, Ocotillo Road, and Chandler Heights Road 
Separated Bike Lanes
TY Lin
n/a
Study complete. 
Federally funded
$0.1
ST2016, Park & Ride Shade Canopies, Phase 2 [two parking canopies 
covering 40 parking spaces & electric vehicle charging station]
LEA-Architects
TSG Constructors
Construction complete.
Funded with State Lottery Proceeds
$0.3
ST2106, Frye Road Protected Bike Lanes [Paseo Trail to San Marcos 
Elementary School]
TY Lin
tbd
Study completed by Y2K.  Design underway.  Construction in fall 2023. 
$3.2 Million grant awarded for construction and $650,000 
for design. 
$6.0
Kyrene Branch and Highline Canal Shared Use Paths
Kimley-Horn
tbd
Study underway.  Design in FY 2022-23.  Construction in 2024-25.
Federal grants have been awarded to fund study, design 
and construction.
$4.0
Ashley and Paseo Trails Connection
Y2K Engineering
tbd
Study underway.  Design in FY 2022-23.  Construction in 2024-25.
Study is federally funded.  Construction and design grant 
funding will be pursued.
$1.0
Price Road Flexible Transit
NA
Via
Study completed in collaboration with Valley Metro.  Contract awarded 
to Via.  Operations scheduled to begin in July 2022.
Awarded $2 Million grant for project startup and two 
years of operations.
$2.1
Transportation Project Status - May 18, 2022