Project Name: CM Services Reclaimed Water Interconnect Facility – GMP 1 Amend 1 
Page 1 
Project No.: WW1901.453
Rev. 5/23/22 
AMENDMENT NO. 1 TO PROFESSIONAL SERVICES AGREEMENT 
Construction Management Services 
Reclaimed Water Interconnect Facility – GMP 2 
Project No. WW1901.453 
Council Date: June 23, 2022         
 Item No. 
THIS AMENDMENT NO. 1 (“Amendment No. 1”) to the agreement for services dated 
December 15, 2021 (the “Agreement”) is made by and between the City of Chandler, an 
Arizona municipal corporation, (“City”) and Wilson Engineers, LLC. (“Consultant”), on this 
______ day of ___________________, 2022 (“Effective Date”).  (City and Consultant may individually 
be referred to as “Party” and collectively referred to as “Parties”). 
RECITALS 
A.
The Parties entered into the Agreement for the following services: Construction
Management Services (“Services”) for Reclaimed Water Interconnect Facility – GMP 1
project.
B.
The Parties have determined that it is necessary and desirable for the Consultant to
perform additional services for the City under the terms and conditions set forth in this
Amendment No. 1 and the Agreement.
AGREEMENT 
NOW, THEREFORE, in consideration of the premises and mutual promises contained in the 
Agreement and this Amendment No. 1, the Parties agree to amend and modify the 
Agreement as follows. 
SECTION I – CONSULTANT’S SERVICES 
The Agreement is amended to add the modified scope of work described in Exhibit “A” 
attached to and made a part of this Amendment No. 1 by this reference.

Project Name: CM Services Reclaimed Water Interconnect Facility – GMP 1 Amend 1 
Page 2 
Project No.: WW1901.453 
Rev. 5/23/22 
SECTION II – PERIOD OF SERVICE 
 
The Agreement is amended to increase the contract time by 460 calendar days for a total 
930 calendar days.   
 
SECTION III – PAYMENT OF COMPENSATION AND FEES 
 
The Agreement is amended to increase the total contract price in an amount not to exceed 
$3,267,780 for a total contract amount of $3,791,430 payable in accordance with Exhibit “B” 
attached to and made a part of this Amendment No. 1 by this reference. 
 
SECTION IV – CONFLICT AMONG DOCUMENTS 
 
The Agreement and this Amendment No. 1 constitute the complete agreement between the 
Parties concerning the subject matter of the Agreement and replace any prior oral or written 
communications between the Parties.   The terms and conditions of the Agreement are 
incorporated into and made a part of this Amendment No. 1. If a conflict or ambiguity arises 
among the Agreement and Amendment No. 1, the instrument in the following order prevails 
and controls: (1) Amendment No. 1; and (2) Agreement.   
 
 
 
 
 
 
 
 
 
 
 
 
SIGNATURE PAGE TO FOLLOW

Project Name: CM Services Reclaimed Water Interconnect Facility – GMP 1 Amend 1 
Page 4 
Project No.: WW1901.453 
Rev. 5/23/22 
 
Amendment No. 1 (cont.) 
Project No. WW1901.453 
 
These changes result in the following adjustments of contract amount and/or time: 
Original Contract amount:  
$ 523,650 
Current Contract amount, prior to this Amendment: (including previous Amendments)  
$ 523,650 
Net change resulting from this Amendment:  
$ 3,267,780 
Revised Contract amount, including this Amendment: 
$3,791,430 
Last Contract amount approved by Council (if applicable): 
$ 523,650 
Amendment % of last Contract amount approved by Council: (if accumulated amount 
over 10% of previous Contract amount approved by Council, Council approval is required) 
624% 
Contract time or completion date prior to this Amendment: (including 
previous amendments) 
470 
or 
      
 
Days 
 
Date 
Net change resulting from this Amendment: 
460 
or 
      
 
Days 
 
Date 
Revised Contract time or completion date: (including this amendment) 
930 
or 
      
 
Days 
 
Date 
 
THIS AMENDMENT No.       does NOT require Council approval: 
      
Amendment is less than 10% of Contract amount last approved by Council  
 
 
THIS AMENDMENT No. 1 does require Council approval: 
X 
Amendment is over 10% of  previous Contract amount approved by Council   
 
 
Amendment No.        Council approval:       Item No.:      , if applicable 
OWNER NAME & DATE APPROVAL:  John Pinkston, 5/25/2022   
 
C:  Project Mgr.          Consultant   Owner      File

Project Name: CM Services Reclaimed Water Interconnect Facility – GMP 1 Amend 1 
Page A-1 
Project No.: WW1901.453 
Rev. 5/23/22 
 
EXHIBIT A 
SCOPE OF WORK

EXHIBIT “A” 
 
CONSTRUCTION MANAGEMENT 
SCOPE OF SERVICES 
RECLAIMED WATER INTERCONNECT FACILITY PROJECT 
 
 
GENERAL DESCRIPTION  
 
The City of Chandler is building Reclaimed Water Interconnect Facility (RWIF) to divert water from the 
SRP canal for treatment and conveyance.  The facility will be located within the Airport WRF Campus 
and treated water will be blended with the reclaimed water from the Airport WRF.  The project will 
allow the City to recharge to obtain credits as well as supply water to City’s large industrial customer. 
The early procurement package (GMP 1) is already executed to procure long lead equipment to 
maintain project schedule.  The design of the facility is essentially complete and submitted to agencies 
for final reviews.  The City is finalizing the remaining construction contract for the RWIF Project (GMP 
2).  This Construction Management scope of work will include effort by Wilson Engineers (Consultant) 
and will involve Project Administration, Engineering and Resident Services during this phase (GMP 2) of 
the Project. 
 
PROJECT TASKS 
 
1. 
PRE-CONSTRUCTION ASSISTANCE 
A. Task 1.1 Preconstruction Assistance  
i. Not Included  
 
2. 
CONSTRUCTION MANAGEMENT  
A. Task 2.1 Weekly Construction Meetings 
i. Consultant must conduct weekly construction meetings.  Each meeting includes 
agenda and minutes; Request for Information (RFI); Shop Drawing; Request for 
Information (RFI); Field Directive (FD); Material Certification; and Allowance Logs. 
Consultant assumes 108 weekly meetings. 
B. Task 2.2 CPM Schedule 
i. Consultant’s opinions concerning various scheduling documents produced or used 
by the Contractor are for information and not controlling on the Contractor.  It is 
Contractor’s responsibility to continue to exercise it’s independent judgement 
concerning means, methods and sequences of construction it employs.  The 
Contractor remains solely responsible for meeting contract time(s) identified in the 
construction documents. 
ii. Review Progress Schedule: Consultant will review and critique the Contractor’s 
progress schedule in accordance with the construction documents, Consultant will 
examine work sequence, durations, interim milestones, and other appropriate 
scheduling features in accordance with the requirements of the construction 
documents.  Consultant will prepare a summary of the baseline schedule review 
comments and will meet and discuss the schedule comments with the Contractor 
and the City.  Consultant will provide recommendations for acceptance.  
iii. Review Progress schedule updates:  Consultant will review the Contractor's 
progress schedule updates to the construction schedule in accordance with the

2 
 
construction documents. Consultant will perform a review of progress 
accomplished during the period and compare to planned schedule and discuss 
significant discrepancies with the Contractor. Consultant and Contractor will 
establish, based on the data, the percent of Project completion. Consultant will 
meet with Contractor on monthly basis to review and update the schedule data. 
Based upon the schedule update, Consultant will recommend processing progress 
payments. Consultant will identify CPM tasks behind schedule that may affect 
critical path items, project substantial and final completion dates and initiate 
correspondence to City regarding those tasks. Consultant assumes fifteen reviews 
of updated CPM schedule.  
C. Task 2.3 Perform Site Visits 
i. The Consultant’s design staff will make site visits appropriate for the type of 
construction at periods appropriate to the various stages of construction to 
observe, as an experienced qualified professional, the progress and quality of the 
executed work of a Contractor and to determine in general, if such work is 
proceeding in accordance with the design intent. The Consultant’s site visit or site 
presence shall support the inspection needs and requirements established by the 
City. 
D. Task 2.4 Requests for Information (RFI’s) 
i. Consultant will issue necessary interpretations and clarifications of the construction 
documents; have authority, as City’s representative, to require special inspection 
or testing of the work; act as initial interpreter of the requirements of the 
construction documents and judge the acceptability of the work thereunder, and 
make decisions on all claims of City and Contractor(s) relating to  the acceptability 
of the work  or the interpretation of the requirements of  the construction 
documents pertaining to the execution and progress of the work. Consultant will 
render interpretations or decisions in good faith and in accordance with the 
requirements of the construction documents. 
ii. Consultant will respond to the City’s representative and/or Contractor to clarify 
and/or interpret technical or design-related questions. Consultant will respond to 
issues raised during construction regarding interpretation and clarification of the 
contractual administrative and technical requirements of the construction 
documents. Consultant will serve as the City’s advisor in resolution of these issues.  
iii. Consultant will prepare and maintain a submittal log of all RFI’s. Consultant 
assumes a maximum of 300 RFI responses.  
E. Task 2.5 Shop Drawing Submittals 
i. Consultant will receive, review, evaluate, and distribute (or take other appropriate 
action in respect of) shop drawings, samples, test results, and other data which 
Contractor is required to submit. Consultant review shall be for conformance with 
the design concept of the Project and compliance with the information given in the 
construction documents. Such review or other action shall not extend to means, 
methods, sequences, techniques, or procedures of construction selected by 
Contractor(s), or to safety precautions and programs associated thereto. 
Consultant will receive and review (for general contents as required by the 
construction documents) maintenance and operating schedules and instructions, 
operation and maintenance manuals, guarantees, and certificates of inspection, 
which are to be assembled by Contractor(s) in accordance with the construction 
documents. 
ii. Consultant will maintain a submittal log showing dates of submittal, transmittal 
action to other sub-consultants, dates of return, and review action. Copies of the 
log shall be furnished to the City and the Contractor weekly. Consultant will 
promptly and in accordance with Project schedule requirements, review and 
approve, reject or take other appropriate action on the Contractor's request for 
substitutions. Consultant will not approve any proposed substitution unless such 
substitution conforms to the Project design concept and the construction 
documents including the contract price.

3 
 
iii. Task effort is based on receiving an estimated 550 shop drawing submittals. 
Submittal review efforts is based upon a maximum of two (2) reviews per submittal 
and that no more than fifty percent (50%) of the total number of first submittals 
will require two (2) reviews. 
 
F. Task 2.6 Requests for Proposal (RFP) 
i. Consultant must prepare Requests for Proposal (RFP) documents detailing 
requested additional work tasks; review and evaluate Contractor RFP responses 
(cost deviations) with approval recommendations; and prepare and maintain a 
submittal log list of all RFP’s. Consultant assumes fifty (50) RFPs. 
 
G.  Task 2.7 Field Directives (FD’s) 
i. Consultant, without the City’s prior approval, may authorize or direct minor 
changes in the Work which are consistent with the intent of the construction 
contract documents and which do not involve a change in Project cost, time for 
construction, Project scope, aesthetics, or approved design elements. Any such 
minor changes shall be implemented by written field order. Except as provided in 
this paragraph, Consultant shall not have authority to direct or authorize changes 
in the Work without the City’s prior written approval; however, Consultant shall 
provide a copy of any written field order to the City. 
ii. Consultant will prepare and submit change order requests explaining the merits 
for the change and a recommendation for the City’s approval and acceptance. 
iii. Consultant will negotiate an agreement with the Contractor as to scope of work 
and cost, time or both associated with the change in Work. The change order shall 
include a written justification for the cost of the Work. Consultant will administer 
and manage minor changes, change order requests, and change orders on behalf 
of the City. Change orders shall be prepared on a standard form provided by the 
City.  Should a change order request be  accepted by the City in the  absence  of  
an agreement  with the Contractor as to cost, time, or both, Consultant will: 
A)   receive and  maintain all  documentation pertaining  to  the  change  order  
request  required of  the Contractor; 
B)  examine such documentation on the City’s behalf; 
C)  take such other action as may be reasonably necessary or as the City may 
request; and 
D)  make a recommendation to the City concerning any appropriate adjustment in 
the construction cost and/or time, and prepare a change order for Contractor's 
acceptance and City approval. 
iv. Changes and substitutions shall be limited to the scope of the Project as defined 
by the construction documents or additional work as may be requested by the City. 
Consultant will promptly consult with and advise the City concerning, and shall 
administer and manage, all change order requests and change orders. 
v. Consultant will prepare, when requested by the City, required drawings, 
specifications and other supporting data regarding minor changes, change order 
requests, and change orders. Consultant must prepare Field Directive (FD) 
documents detailing requested additional work tasks; review and evaluate 
Contractor FD responses with approval recommendations; and prepare and 
maintain a submittal log list of all FD’s.  Multiple directives may be combined to 
create a field directive. Consultant assumes twenty five (25) FD’s.   
H. Task 2.8 Contractor Payment Applications 
i. Consultant will review, prepare comments, and reach agreement with the 
Contractor on the progress represented in the Contractor's schedule of values. The 
monthly schedule update, schedule of values, in combination with Consultant’s

4 
 
field inspections, and the progress schedule shall be used by Consultant to 
determine the appropriateness of the Contractor's request for payment. 
ii. Consultant, as an experienced and qualified professional, and on review of 
applications for payment and the accompanying data and schedules, determine 
the amounts owed to Contractor and recommend in writing, payments to  
Contractor in such amounts; such recommendations of payment will constitute  a 
representation to City, based on such inspections and review, that; 
A)  the work has progressed to the point indicated; 
B)  to the best of Consultant's knowledge, information and belief, the quality of 
such work is in accordance with the construction documents (subject to an 
evaluation of such work as a functioning Project  upon  Substantial Completion, to  
the  results  of  any  subsequent  tests  called  for  in  the construction documents, 
and to any qualifications stated in the recommendation); and 
C)  payment of the amount recommended is due and owed to the Contractor. 
iii. For unit price work, Consultant’s recommendations for payment will be a 
determination of completed quantities of such work. 
iv. Consultant assumes a maximum of 20 payment applications, with 2 reviews each. 
I. Task 2.9 Use of Allowance and Use of Contingency  
i. The Consultant shall assist the City with the Allowances and Contingencies that 
are identified in the contract.  It is anticipated that the City or the Contractor may 
request the use of the contingency and allowance funds.  The Consultant shall 
maintain all documentation and logs pertaining to the use of any allowances and 
contingencies. It is anticipated that approximately Twenty (20) Use of Allowances 
or Contingency requests. 
J.  Task 2.10 Public Outreach 
i. Not Included 
 
3. 
CONSTRUCTION INSPECTION 
A. Task 3.1 Inspection Services 
i. The Resident Project Representative (RPR) and various Inspectors will be on-site 
and will act as directed by Consultant, in order to assist Consultant in inspecting 
performance of the work of the Contractor(s). Consultant will endeavor to provide 
further protection for City against deficiencies in the work of Contractor(s) through 
more extensive on-site inspections of the work and field checks of materials and 
equipment by the RPR and Inspectors,. The furnishing of such RPR representation 
will not make Consultant responsible for construction means, methods, techniques, 
sequences or procedures, or for safety precautions or programs, or for 
Contractor(s) failure to perform their work in accordance with the construction 
documents. The Resident Project Representative (RPR) will be at the Project site 
to be knowledgeable about the progress and quality of the work to: 
A)  Conduct on-site inspections of the work in progress to assist Consultant in 
determining if the work is proceeding in accordance with the construction 
documents and that completed work conforms to the construction documents. 
 B)  Report to Consultant whenever it is believed that any work is unsatisfactory, 
faulty, or defective, or does not conform to the construction documents, or does 
not meet the requirements of inspections, tests or approval required to be made, 
or has been damaged prior to final payment; and advise Consultant when it is 
believed work should be corrected or rejected or should be uncovered for 
inspection, or requires special testing, inspection or approval. 
C)  Verify that tests, equipment, and systems start-up and operating and 
maintenance instructions are conducted as required by the construction 
documents and in presence of the required personnel, and that Contractor

5 
 
maintains adequate records thereof; inspect, record and report to Consultant 
appropriate details relative to the test procedures and start-ups. Accompany 
visiting inspectors representing public or other agencies having jurisdiction over 
the Project, record the outcome of these inspections, and report to Consultant. 
The RPR, as Consultant’s agent, will act as directed by and under the supervision 
of Consultant. The RPR's dealings in matters pertaining to the on-site work shall 
in general be only with Consultant and Contractor, and dealings with 
subcontractors shall only be through or with the full knowledge of Contractor. 
Written communication with City will be only through or as directed by Consultant, 
and when appropriate, may be through the RPR. 
ii. Certificates. Maintenance and Operation Manuals: During the course of the work, 
review and determine that certificates, maintenance and operation manuals and 
other data required to be assembled and furnished by Contractor are applicable to 
the items actually installed; and deliver this material to Consultant for review and 
forwarding to City prior to final acceptance of the work. 
 
iii. Start-up Assistance: Start-up services shall be sufficient to transfer finished work 
from a construction status to operating, functional system(s). Such services may 
include review of Contractor's start-up plan, prepare and coordinate a start-up plan 
and procedures for City personnel use, supervise during start-up procedures, and 
assist City personnel during a period of initial operation.  
iv. Special Inspection: During the course of the work, arrange and coordinate Special 
Inspections for structural, mechanical, and electrical work as required by the 
Special Inspection Certificates required by the City.  
 
B. Task 3.2 Landscape / Irrigation Inspection Services     
i. Not Included 
C. Task 3.3 Project Closeout 
i. Following notice from the Contractor, The Consultant will conduct an inspection to 
determine if the Project or the work associated with interim milestones is 
substantially complete in accordance with the construction documents.  If the 
Consultant considers the work substantially complete, the Consultant will deliver 
to the City and the Contractor the Certificate of Substantial Completion and the 
punch list, the date for completion of the punch list, and recommend the division 
of responsibilities between the City and the Contractor.  If the work is not 
substantially complete, the process shall be repeated until the work is substantially 
complete. 
ii. The Consultant, upon completion of the punch list items as notified by the 
Contractor, make final inspection.  The inspection will be to determine if the 
finished work is complete to the standard required by the construction documents, 
and determine whether required inspections and approvals for permit compliance 
are met.  The Consultant will further verify whether the Contractor has fulfilled the 
contractual obligations so that Consultant may recommend, in writing, final 
payment to Contractor and may give written notice to City and the Contractor that 
the work is acceptable, subject to any conditions therein expressed and in 
consultation with the City, whether the work is finally complete.  At or prior to the 
final inspection, the Consultant will request the Contractor prepare and furnish; 
1) Certification that all obligations for payment for labor, materials or equipment 
related to the work have been paid and satisfied; 
2) Certification that all insurance and bonds required of the Contractor beyond 
final payment is in effect and will not be canceled or allowed to expire without 
notice to the City; 
3) Written consent of surety for final payment; 
4) Record document information is complete and submitted;

6 
 
5) All keys, manuals, required spare parts, guaranties and warranties, and other 
documents necessary for close-out of the work; and 
6) Verification of permit close-out including the Certification of Occupancy. 
If the work is not finally complete, the process will be repeated until the work is 
complete. Promptly after the work is determined to be finally complete and the 
Consultant determines that the Contractor has properly submitted the items 
required for final inspection, the Consultant will determine whether the Contractor 
is entitled to final payment and, if so, will so certify to the City. 
iii. The Consultant certification that the Contractor is entitled to final payment 
constitutes the Consultant representation to the City that; 
1) the work complies with (a) the construction contract documents, (b) applicable 
building codes, rules or regulations of all governmental authorities having 
jurisdiction over the Project, and (c) applicable installation and workmanship 
standards; 
2) The Contractor has submitted proper Final Completion close-out documents; 
and 
3) The Contractor is entitled to final payment. 
The Consultant will provide to the City, at the time it submits a signed final 
payment request from the Contractor, all Final Completion close-out documents. 
Consultant will not be responsible for the acts or omissions of any Contractor, or 
subcontractor, or any of the Contractor(s)' or subcontractor(s)' agents or 
employees or any other persons (except Consultant’s own employees and agents) 
at the site(s) or otherwise performing any of the Contractor(s)' work; 
 
4. 
UTILITY COORDINATION  
A. Task 4.1 Utility Coordination  
i. The Consultant will coordinate with the Maricopa County Department of 
Environmental Services and submit Approval of Construction (AOC) documents for 
review and approval.  The Consultant will also coordinate with the County to approve 
Temporary AOC’s for portions of the work as needed prior to the completion of the 
entire project.  The Consultant will also coordinate County site visits for the 
temporary and final AOCs. 
 
5. 
MATERIALS TESTING 
A. Task 5.1 Quality Control (QC) Test Program 
i. Consultant shall review and verify Contractor’s Quality Control material test type 
and frequencies are consistent with City, and MAG requirements.  
ii. Consultant 
shall 
review 
Contractor’s 
QC 
test 
schedule 
and 
provide 
recommendations on acceptance. 
iii. Consultant shall review all Contractor sampling, test and inspection results for 
conformance with construction documents. 
B. Task 5.2 Quality Assurance (QA) Test Program 
i. Consultant shall prepare and maintain a materials Quality Assurance plan per City, 
and MAG requirements.  
ii. Consultant shall coordinate with Contractor’s testing representative to obtain 
required QA tests and sample. 
iii. Consultant shall complete sampling and compaction testing of subgrade aggregate 
base and asphalt concrete materials in new asphalt concrete pavement areas, 
concrete structures, and underground utilities.

7 
 
 
 
 
6. 
RECORD DRAWINGS  
A. Task 6.1 Record Drawings 
i. The Consultant will prepare a set of record drawings showing those changes made 
during construction.  Record drawing information shall be based on marked-up 
prints, drawings, and other data furnished by Contractor(s) to the Consultant.   
ii. The Consultant will provide stamp/certification on record drawings cover sheet, as 
well as ensure that all required signatures are present on the cover sheet. 
iii. The Consultant will provide and deliver record drawings in mylar, paper and digital 
pdf format to the City as required for as-built submittal process to the City Project 
Manager. 
 
7. 
ALLOWANCES 
A. Task 7.1 Start-up Assistance 
i. The Contractor will be working at an operating wastewater treatment facility.   
There will be shutdowns associated with the new work that needs to be performed 
within the vicinity of existing structures, process areas, channels etc.  Extensive 
coordination is required with the Contractor to keep plant shutdowns and 
disruptions to a minimum. 
ii. The Consultant shall review the Contractor’s proposals for any temporary 
conveyance and/or processing facilities.  For work within the areas of process 
shutdowns, the Consultant shall review list of labor materials, estimation of time, 
and equipment necessary and written description of the work.  
iii. Some new process areas/equipment may come on line as soon as they are installed 
and start up services will need to be completed to bring equipment online.  The 
Consultant shall provide start up assistance services.  Such services will include 
review of contractor’s start-up checklist, coordinate start-up plan and procedures 
for City personnel use, supervise during start up procedures, trouble shoot and 
assist the City staff during the period of initial operation. 
iv. The start-up process will include a planned, systematic approach to verify that 
facility systems operate as intended and there is an orderly transition from 
construction phase to routine operation.  The start-up program will include four 
phases with estimated durations as follows: 
v. Start-up Plan:  Consultant will review a start-up plan and procedures prepared by 
the Contractor with the City staff.  The start-up plan will include identification of 
key milestone activities necessary for orderly start-up of the facilities.  The 
milestone activities will include completion of any construction activities required 
for substantial completion, coordination of required Contractor maintenance 
activities, etc.  The plan shall include the coordination of the activities with the 
equipment vendors, subcontractors, along with the programming subcontractor 
and the plant staff and identify the time required and roles and responsibilities 
during start-up activities.  The start-up of activities shall be coordinated with the 
construction sequencing and MOPO activities. 
vi. The Consultant will assist the Contractor with the start-up and testing of new 
facilities.  Following a sequentially coordinated initial start-up of the facility, the 
facility would be operated continuously. The Consultant will verify that, all 
mechanical equipment, associated valves and control devices, and any other 
components operate properly under actual operating conditions.  This includes the 
verification that all hardwired electrical control interlocks and safeguards are 
functioning properly. The Consultant will verify that all mechanical equipment, and 
instrumentation system components are operating properly under actual operating

8 
 
conditions.  This includes the verification that all software based electrical/process 
control monitoring, interlocks, automatic control logic, alarms, and report 
generation subroutines. 
vii. The Consultant will maintain documentation of the areas of operational concern 
encountered during the manual start-up phase with a determination of whether 
the item of concern is a Contractor warranty issue or requires a design 
modification.  The Consultant will monitor the documented concerns and promptly 
notify the Contractor of all warranty issues. 
viii. Design modifications that may be necessary, will be promptly evaluated by the 
Consultant and recommendations will be presented to the City for a determination 
of the necessity for implementation. The Consultant will complete the necessary 
check out of the instrumentation system components and initial loading of the 
control software simultaneously computer operation mode can be verified for each 
process 
ix. After completion of the start-up of process units, the Consultant shall coordinate 
with the City and prepare a list of outstanding items that will need to be completed 
by the Contractor. 
 
B. Task 7.2 MOPO Coordination 
i. Consultant shall assist the Contractor the MOPOs and MOPO coordination.  
ii. Consultant shall attend weekly or periodic MOPO meetings during the construction 
phase of the project. 
iii. Consultant shall assist the Contractor with Mock Shutdown(s) as necessary if 
needed to verify current conditions. 
iv. Conduct pre-MOPO walkthrough with the Contractor and all relevant parties (City, 
subcontractors etc) prior to every MOPO to verify all equipment and back up 
contingencies are in place. 
v. Communicate and monitor throughout each MOPO duration and conduct any 
special inspections necessary during each MOPO.  The Consultant shall verify 
workmanship of MOPOs and troubleshoot any issues that come up.   
 
C. Task 7.3 Contractor and Equipment Manufacturer Training Coordination  
 
i. The Consultant will review and coordinate Contractor's training plan and 
instruction materials for compliance with Construction Documents.  Contractor or 
Manufacturer training presentations shall be scheduled and coordinated with City 
and facility operation.   
ii. Consultant will coordinate and monitor the Contractor’s and manufacturer’s 
training of City personnel.  
iii. Discuss the preliminary course and lesson plan development with the Contractor 
and the manufacturer/supplier.  Meet with City’s operational staff and the 
Contractor for these discussions. 
iv. Review and approve lesson plans and course materials, act as a liaison between 
the City and the Contractor, Monitor training sessions, monitor attendance, 
evaluate course, and assist in class room discussions.  After completion of the 
training sessions, follow up with the City to coordinate and discuss with the City if 
additional sessions are necessary to complete the project scope.

9 
 
D. Task 7.4 Systems Training  
 
i. Consultant will provide instruction to City personnel on the Project objectives, 
design intent, and system operational procedures.  Consultant will provide training 
on the design and operation of the major process systems that are part of this 
project to the City prior to substantial completion. 
ii. Specific training services shall consist of the following: 
iii. Prepare training outline, schedule and lesson plan format for review and approval 
by City.  
iv. Review training plans and presentation materials including training guides for the 
major process systems and submit to City for review before finalizing by the 
contractor.  The lesson plans shall include the following subjects; 
1. purpose and design intent of system; 
2. process operations and principles; 
3. system controls and control strategies 
4. specific safety procedures and hazards; 
5. specific sampling, monitoring, and process calculations; and 
6. system orientation and hands-on demonstration. 
v. Conduct training on the major process systems.  Training may consist of classroom 
training for each system, followed by field orientation or hands-on instruction. 
 
E. Task 7.5 Prepare Operations Manual and electronic Operations Manual 
 
i. The Consultant will prepare an Operations Manual for the new facility.  
ii. The content development process for the manual is designed to meet City goals 
and objectives for content that meets user needs and is presented in an 
understandable, easy-to-read style.  The content level of detail, format, and 
organization will comply with format and layout to meet the City’s standard. 
iii. Each chapter for the major systems will consist of the following sections: 
Background, Theory, Operating Strategies, Equipment & Control Description, 
Procedures, Design Criteria, Troubleshooting, Safety, Alarms, Drawings, figures 
and Photographs. These procedures will be field verified by the Consultant with 
assistance from the plant staff. 
iv. Workshop(s) will be held with the City prior to content development activities to 
provide an overview of the content to be developed, to identify key City staff to 
review draft chapters, and to establish a review schedule.  The City will be provided 
with interim deliverables of completed sections as the construction of major areas 
of the facility are completed.  As each chapter is completed, the Consultant will 
submit draft chapters to the City for their review and comment.  The Consultant 
to incorporate comments into the final documents.  
v. Prior to submitting the final version of the manual and transferring to the City, the 
Consultant will conduct a detailed final validation and field verification process.  
Through this important quality control activity, the Consultant will verify that: 
1) Content has been field-verified and checked at the installation. 
2) Photographs are current and are reflective of well-maintained and clean 
conditions. 
3) Relevant documentation, such as scanned documents, figures and drawings are 
appropriately categorized for insertion into the database.

10 
 
4) Standard Operating Procedures are accurate and reflect actual “as-operated” 
conditions 
vi. The facility Operations Manual will cover new, or any modified and upgraded 
auxiliary systems included in the Project.  New areas of the facility will be created 
as new sections of the Manual and will be completed in conjunction with the 
specific completion milestones of construction. 
 
F. Task 7.6 Programming Assistance and Coordination  
 
i. The Consultant will assist the Contractor during the system configuration phase of 
the project.  As part of this task the Consultant will assist the contractor in 
implementation of functional requirements outlined as part of the project 
documents.  The Consultant shall conduct weekly meetings with the Contractor 
and the City to clarify and review Contractor’s progress of the work regarding I&C 
and programming work. 
ii. The Consultant will provide assist the Contractor with the PLC Programming and 
Startup Services for the Facility.  The scope of services will include attending 
witness at Factory Acceptance Testing (FAT), witness SCADA interface testing, 
participate in I/O field point-to-point testing, configuration and set-up of any Radio 
communication to the City SCADA system as necessary, and witness calibration 
checks and sign calibration reports. 
iii. The Consultant will participate in loop checks of all communication  
 
ASSUMPTIONS, CLARIFICATIONS, AND EXCLUSIONS 
 
The extent and limitations of the duties, responsibilities, and authority of Consultant as assigned herein 
shall not be modified, except as Consultant may otherwise agree in writing. City’s instructions to 
Contractor(s) shall be issued through Consultant, who shall have authority to act on behalf of the City to 
the extent provided in this Scope of Services, except as otherwise provided in writing.  
Consultant shall not be responsible for the means, methods, techniques, sequences, or procedures of 
construction selected by Contractor, unless otherwise specified in the construction documents or the 
safety precautions and programs incident to the work of Contractor. Consultant efforts shall be directed 
toward providing a greater degree of confidence for the City that the completed work of Contractor shall 
conform to the Contract Documents, but Consultant shall not be responsible for the failure of Contractor 
to perform the work in accordance with the construction documents.  
The Consultant review shall only be for conformance with the design concept of the Project and 
compliance with the information given in the construction documents. Such review or other action shall 
not extend to means, methods, sequences, techniques, or procedures of construction selected by 
Contractor or to safety precautions and programs incident thereto. The Consultant shall receive and 
review (for general contents as required by the construction documents) maintenance and operating 
schedules and instructions, operation and maintenance manuals, guarantees, bonds, and certificates of 
inspection which are to be assembled by Contractor in accordance with the construction documents.  
Consultant shall not be responsible for the acts or omissions of the Contractor, or subcontractor, or any 
of the Contractor's or subcontractor's agents or employees, or any other persons (except Consultant own 
employees and agents) at the site or otherwise performing any of the Contractor's work; 
 
Limitations of Authority: Except upon written instructions, the Consultant:  
 
1. will not authorize any deviation from the Contract Documents or approve any substitute 
materials or equipment; 
2. will not undertake any of the responsibilities of Contractor, subcontractors or Contractor's 
superintendent, or expedite the work;

11 
 
3. will not advise on or issue directions relative to any aspect of the means, methods, 
techniques, sequences or procedures of construction unless such is specifically called for in 
the Construction Documents;  
4. will not advise on or issue directions as to safety precautions and programs in connection 
with the work; and  
5. will not authorize City to occupy the Project in whole or in part.  
 
Reimbursable costs allowance shall be utilized to reimburse for items such as reproduction, delivery, 
and mileage. 
 
Application fees for City reviews and permits will be paid by CITY.  The Owner’s Allowance will only be 
utilized with prior written approval from the City representative. 
 
 
End of Scope of Work

Project Name: CM Services Reclaimed Water Interconnect Facility – GMP 1 Amend 1 
Page B-1 
Project No.: WW1901.453 
Rev. 5/23/22 
EXHIBIT B 
FEE SCHEDULE

Task
Cost
1
1.1
-
$                             
-
$                             
2
2.1
226,100.00
$                
2.2
47,020.00
$                  
2.3
Perform Site Visits
138,540.00
$                
2.3
224,280.00
$                
2.4
400,300.00
$                
2.5
50,340.00
$                  
2.6
172,500.00
$                
2.7
41,300.00
$                  
2.8
-
$                             
1,300,380.00
$             
3
3.1
1,114,120.00
$             
3.2
-
$                             
3.3
29,800.00
$                  
1,143,920.00
$             
4
4.1
48,480.00
$                  
48,480.00
$                  
5
5.1
9,580.00
$                    
5.2
25,620.00
$                  
35,200.00
$                  
6
6.1
74,960.00
$                  
74,960.00
$                  
7
7.1
86,450.00
$                  
7.2
125,600.00
$                
7.3
37,430.00
$                  
7.4
60,520.00
$                  
7.5
82,820.00
$                  
7.6
57,320.00
$                  
450,140.00
$                
152,700.00
$                
20,000.00
$                  
15,000.00
$                  
25,000.00
$                  
212,700.00
$                
2,000.00
$                    
-
$                             
2,000.00
$                    
3,267,780.00
$     
RECORD DRAWINGS
SUBCONSULTANTS
ALLOWANCES
Direct Expense Allowance
Record Drawings
ALLOWANCES
SUBTOTAL TASK 4:
Startup Assistance
MOPO Coordination
Contractor and Eqpt Manufacturer Coordination
Systems Training
Prepare Operations Manual
Programming Assistance and Coordination
Gannett Fleming (Structural Services)
Motley Design Group (Architectural Services)
Owner's Allowance
SUBTOTAL ALLOWANCES:
PROJECT TOTAL:
SUBTOTAL TASK 6:
SUBTOTAL SUBCONSULTANTS:
Kennelly & Associates (HVAC Services
RAMM (Qualtiy Assurance Testing)
SUBTOTAL TASK 5:
QA Test Program
Utility Coordination 
QC Test Program
MATERIALS TESTING
SUBTOTAL TASK 4:
Inspection Services
CONSTRUCTION INSPECTION
SUBTOTAL TASK 2:
SUBTOTAL TASK 3:
Landscape/Irrigation Inspection Services (IF APPLICABLE)
Project Closeout
UTILITY COORDINATION
Description
Requests for Proposal (RFP)
CPM Schedule
Requests for Information (RFI)
Shop Drawing Submittals
Pre-Construction Assistance
Weekly Construction Meetings
PRE-CONSTRUCTION ASSISTANCE
CONSTRUCTION MANAGEMENT
SUBTOTAL TASK 1:
Public Outreach
Field Directive (FD)
Contractor Payment Applications
EXHIBIT "B"
CONSTRUCTION MANAGEMENT
SCOPE OF SERVICES
FEE SCHEDULE

Principal
Sr. PM (Design 
ane CA&I)
Sr. Resident 
Project Rep.
Sr. Eng
Project 
Engineer /  
Project Prof.
Lead Const. 
Inspector 
Lead Elec. 
Inspector
Senior CADD 
Tech
Senior Admin
Uday 
Gandhe
Sreeram R., 
Craig R
Dave C
Sri Y., Sean 
Z., Phani P
Kiliegh P.,
 Abhinay S., 
Elvin R, John 
S
Daniel Hickey., 
Earl McClain, 
Toby T
Jason Gilley, 
Evans Polean
Jeremy J., 
Julius C
Brandy Nixon
 $   225.00  $             205.00  $       185.00  $         170.00  $          145.00  $               145.00  $         145.00  $        115.00  $          95.00 
Preconstruction Assistance
0
0
0
0
0
0
0
0
0
0
96
804
760
1220
3900
596
424
120
408
8328
Weekly Construction Meetings
40
248
320
120
240
180
120
0
88
1356
CPM Schedule
0
44
80
0
0
120
40
0
0
284
Perform Site Visits
4
48
0
240
600
0
0
0
0
892
Requests for Information
16
96
80
280
680
80
80
80
80
1472
Shop Drawing Submittals
24
120
0
400
1980
0
0
0
160
2684
Request for Proposals
4
48
120
0
0
56
64
0
0
292
Field Directives
4
160
80
180
400
80
80
40
80
1104
Contractor Payment Applications
4
40
80
0
0
80
40
0
0
244
Public Outreach
0
0
0
0
0
0
0
0
0
0
4
260
1460
300
600
2840
1680
0
276
7420
Inspection Services
0
240
1420
300
600
2760
1640
0
276
7236
Landscaping and Inspection Services (N/A)
0
0
0
0
0
0
0
0
0
0
Project Closeout
4
20
40
0
0
80
40
0
0
184
0
16
0
80
160
0
0
40
40
336
Utility Coordination
0
16
0
80
160
0
0
40
40
336
0
8
56
0
0
120
40
0
0
224
QC Test Program
0
4
16
0
0
40
0
0
0
60
QA Test Program
0
4
40
0
0
80
40
0
0
164
0
16
0
80
160
16
40
160
88
560
Record Drawings
0
16
0
80
160
16
40
160
88
560
20
144
128
400
1120
588
304
96
228
3028
Start up Assistance 
2
20
40
80
180
160
80
0
0
562
MOPO Coordination
4
32
80
80
160
320
120
4
24
824
Contractor and Eqpt Manufacturer Coordination
2
4
4
40
120
24
24
4
40
262
Systesm Training
4
40
4
40
180
80
40
0
4
392
Prepare Operations Manual
4
40
0
80
240
0
0
88
160
612
Programming Assistance and Coordination
4
8
0
80
240
4
40
0
0
376
120
1248
2404
2080
5940
4160
2488
416
1040
19896
4. Utility Coordination
EXHIBIT "B‐2"
Hours and Rates
< PROJECT ROLE
< NAME OF PERSON
 < HOURLY RATES 
TASK DESCRIPTION
TOTAL HOURS
2. Construction Management
3. Construction Inspection
5. Materials Testing
6. Record Drawings
TOTAL HOURS:
7. Allowances