June 2022 Airport Construction Report
Extracted text (via pymupdf)
815 characters
Projects – Design Phase: Wildlife Hazard Perimeter Fence: Environmental/Design phase underway. Environmental documentation submitted to ADOT. Design underway. 100% ADOT funding at $1,107,500. Arizona Pavement Management System: Grant approved by City Council on April 28. Field visit June 13th. 90% ADOT funding at $617,574 with City match of $61,758. ADOT handling contractor procurement. Projects - Construction Phase: Terminal Plumbing Renovation: Construction underway with mainline work and internal plumbing work. Completion date planned for end of June. City funding at $115,771 for construction. Heliport Lighting Replacement: Kickoff meeting TBD. City funding at $277,771 for construction. Meeting Date: June 8, 2022 Chandler Municipal Airport Construction Report