Capital Projects – Design Phase: 
• 
Wildlife Hazard Perimeter Fence:  City comments received for 30% plans.  ADOT 
environmental clearance received 8/1.  100% ADOT funding at $1,107,500. 
• 
Arizona Pavement Management System:  Grant approved by City Council on 4/28.   
90% ADOT funding at $617,574 with City match of $61,758.  ADOT handling contractor 
procurement. 
 
Capital Projects - Construction Phase: 
• 
Heliport Lighting Replacement:  Limited Notice to Proceed for long lead items 
issued.  Construction kickoff meeting TBD in next two weeks.  City funding at $277,771 
for construction. 
 
Maintenance Projects: 
• 
Fence Repair:  Selective tensioning along perimeter fence 
• 
Landscaping – West Side of Airport Blvd:  Awaiting delivery of decomposed 
granite.  
• 
Ramp/Apron Painting:  Transient parking repainting with new, dedicated lead-in 
lines. 
• 
Flight Planning Room/Pilot Lounge Repairs:  Updated wall planning maps/charts.  
Additional furniture. 
• 
Terminal: Touch-up painting. 
 