TC Set 2022 Project Status Update
Extracted text (via pymupdf)
4910 characters
Projects Designer Contractor Status Comments PROJECT COST ESTIMATE ($MILLIONS) ROADWAY AND TRAFFIC PROJECTS ST1503, Cooper Road Improv. [Alamosa Drive (approx.. 3,500 ft. north of Chandler Heights Road) to Riggs Road for two through lanes each direction] Entellus Pulice Construction Construction underway. Completion scheduled for Winter 2022. Federal funds $19.3 ST1614, Chandler Heights Road Improv. [McQueen Road to Gilbert Road for two through lanes each direction] Kimley-Horn Granite Construction Company Construction underway. Completion scheduled for Winter 2023 Federal funds $20.9 ST1616, Ocotillo Road Improv. [Gilbert Road to 148th Street for two through lanes each direction] Ritoch-Powell Haydon Companies, LLC Construction contract award April 2022. Long lead procurement NTP August 2, 2022. Start construction Winter 2022. Construction complete Fall 2023. Federal funds $6.8 ST1804, Chandler Heights Road Improv. [Gilbert Road to Val Vista Drive for two through lanes each direction] Kimley-Horn tbd Design in progress. Bid scheduled for Summer 2023. Federal funds $20.9 ST1908, Bicycle Detection System [40 intersections] n/a n/a Procurement Complete. Federal funds $1.3 ST1909, Alleyway Rehab PM10 Dust Emission Reduction n/a Cactus Asphalt Construction Complete. Federal funds $2.1 ST2001, Lindsay Road Improv. [Ocotillo Road to Hunt Highway for two through lanes in each direction] Kimley-Horn tbd Design in progress. Bid scheduled for Winter 2023. Federal funds $27.2 ST2002, Traffic Study of Kyrene Road [Chandler Boulevard to Loop 202] AZTEC n/a Study complete. $0.2 ST2003, Gilbert Road Improv. [Ocotillo Road to Chandler Heights Road for new traffic signals and three through lanes in each direction] Sunrise Engineering Sunland Asphalt Construction complete. $8.5 ST2004, Alma School Road Improv. [Pecos Road to Germann Road for three through lanes in each direction to match development improv.] Wood Sunland Asphalt Construction complete. Regional funds $3.7 ST2006, Traffic Signal at Warner Road and Nevada Street Stanley Consultants B&F Contracting Construction contract awarded January 2022. Long lead procurement NTP May 9, 2022. Start construction Fall 2022. $0.6 ST2007, Hamilton Street Improv. [Appleby Road to Carob Drive] Nfra Consultants tbd Design underway. Construction scheduled for Fall 2023 $5.2 ST2009, Dobson Road Improv. at Intel Driveways #1 and #4 [Price Rd / Market Pl to Chaparral Way] Premier DCS Contracting Construction in progress. Completion scheduled for Summer 2023. Funded by 20% from Intel and 80% from State TPT per ARS 42-5032.02 $0 City Cost (Intel Funded) ST2012, Arterial Congestion Monitoring [Install data collection devices at major intersections, and use data to map traffic congestion and mobility.] Y.S. Mantri & Assoc. CS Construction Construction to start Winter 2022. Grant funds $1.3 ST2103, Intersection Improv. at Ray Road and Dobson Road tbd tbd Study underway. Study only. Future phases tbd. $0.1 ST2104, Traffic Signal at Ocotillo Road and Pinelake Way Y2K Engineering tbd Design in progress. $0.8 ST2113, Alley Rehab PM10 Dust Emissions Reduction 2 (FMA Areas 16, 25, 39, and 40) Premier / Olsson tbd Design in progress. Federal funds $2.4 (tbc) PEDESTRIAN, BICYCLE, AND TRANSIT PROJECTS ST2106, Frye Road Protected Bike Lanes [Paseo Trail to San Marcos Elementary School] TY Lin tbd Study completed by Y2K. Design underway. Construction in fall 2023. $3.2 Million grant awarded for construction and $650,000 for design. $6.0 Kyrene Branch and Highline Canal Shared Use Paths Kimley-Horn tbd Study underway. Design in 2023. Construction in 2024-25. Federal grants have been awarded to fund study, design and construction. $4.0 Ashley and Paseo Trails Connection Y2K Engineering tbd Study underway. Design in FY 2023. Construction in 2024-25. Study is federally funded. Construction and design grant funding will be pursued. $1.0 Hunt Highway Bicycle Improvements and Traffic Calming Study Rick Engineering tbd Study underway, to be completed mid 2023. Federally funded. Study will look at a potential shared use path or separated bike lanes along with recommendations for traffic calming between Cooper Rd. and Val Vista Dr. $0.1 Tumbleweed Park ADA Improvements N/A Vincon Construction underway. To be completed fall 2022. Sidewalk and curb ramp improvements throughout and adjacent to park. $0.4 Protected Bike Lanes Study Y2K Engineering tbd Study to kickoff late 2022. Federally funded. Study will prioritize opportunities to install protected bike lanes on arterial and collector streets in Chandler. $0.1 Chandler Flex NA Via Study completed in collaboration with Valley Metro. Contract awarded to Via. Operations began July 11, 2022. Awarded $2 Million grant for project startup and two years of operations. $2.1 Transportation Project Status - September 21, 2022