Transportation Commission Nov Project Status

City of Chandler — Regular Meeting (2022-11-16)

View PDF Meeting page

Extracted text (via pymupdf) 5224 characters
Projects
Designer
Contractor
Status
Comments
PROJECT COST 
ESTIMATE
($MILLIONS)
ST1503, Cooper Road Improv. [Alamosa Drive (approx.. 3,500 ft. north of Chandler Heights 
Road) to Riggs Road for two through lanes each direction]
Entellus
Pulice Construction
Construction underway.  Completion scheduled for Winter 2022.
Federal funds
$19.30
ST1614, Chandler Heights Road Improv. [McQueen Road to Gilbert Road for two through lanes 
each direction]
Kimley-Horn
Granite Construction 
Company
Construction underway.  Completion scheduled for Winter 2023.
Federal funds
$20.90
ST1616, Ocotillo Road Improv. [Gilbert Road to 148th Street for two through lanes each 
direction]
Ritoch-Powell
Haydon Companies, LLC
Construction Starts November/December 2022.  Completion scheduled Fall 2023.
Federal funds
$6.80
ST1804, Chandler Heights Road Improv. [Gilbert Road to Val Vista Drive for
two through lanes each direction]
Kimley-Horn
tbd
Design in progress.  Bid scheduled for Winter 2023.  
Federal funds
$20.90
ST2001, Lindsay Road Improv. [Ocotillo Road to Hunt Highway for two
through lanes in each direction]
Kimley-Horn
tbd
Design in progress.  Bid scheduled for Winter 2023.
Federal funds
$27.20
ST2002, Traffic Study of Kyrene Road [Chandler Boulevard to Loop 202]
AZTEC
n/a
Study complete.
$0.20
ST2006, Traffic Signal at Warner Road and Nevada Street
Stanley Consultants
B&F Contracting
Construction order long-lead materials underway.  Construction scheduled Winter 2022.
$0.60
ST2007, Hamilton Street Improv. [Appleby Road to Carob Drive]
Nfra Consultants
tbd
Design underway.  Construction scheduled for Fall 2023
$5.20
ST2009, Dobson Road Improv. at Intel Driveways #1 and #4 [Price Rd /
Market Pl to Chaparral Way]
Premier
DCS Contracting
Construction in progress.  Completion date extended to coordinate with other projects.
Funded by 20% from Intel and 80% from State TPT per
ARS 42-5032.02
$0 City Cost (Intel
Funded)
ST2012, Arterial Congestion Monitoring [Install data collection devices at major intersections, 
and use data to map traffic congestion and mobility.]
Y.S. Mantri & Assoc.
CS Construction
Construction order long-lead materials November 2022.  Construction scheduled for 
Winter 2022.
Grant funds
$1.30
ST2103, Intersection Improv. at Ray Road and Dobson Road
tbd
tbd
Study almost complete.  Application for grant funding is submitted.  
Study only.  Future phases tbd.
$0.20
ST2104, Traffic Signal at Ocotillo Road and Pinelake Way
Y2K Engineering
tbd
Design in progress.
$0.80
ST2113, Alley Rehab PM10 Dust Emissions Reduction 2 (FMA Areas 16, 25,
39, and 40)
Premier / Olsson
tbd
Design in progress.  Bid scheduled for Spring 2023
Federal funds
$2.4 (tbc)
ST2110, Chandler Video Detection Cameras 
Y.S. Mantri & Assoc.
tbd
Invitation to Bid underway.  
Federally Funded
$1.7(tbc)
ST2209, Chandler Local Detection and Communication Systems(Replaces existing video 
detecting cameras with new video cameras)
tbd
tbd
Design in Progress
Federally Funded
$0.50 
ST2210, Chandler ICM Detection and Communication Systems(Replaces existing video 
detecting cameras near freeways with new video cameras)
tbd
tbd
Design in Progress
Federally Funded
$0.60 
ST2301  Armstrong Way and Hamilton Street Improvement(Improves the south half of 
Armstrong Way and the west half of Hamilton Street)
tbd
tbd
Design scheduled for Spring 2023
$2.00 
ST2303 Cooper Road - Insight Loop Extension(Connects Cooper Road to Insight Way & 
Emmett Dr intersection)
tbd
tbd
Design scheduled for Summer 2023
$9.30 
PEDESTRIAN, BICYCLE, AND TRANSIT PROJECTS
ST2106, Frye Road Protected Bike Lanes [Paseo Trail to San Marcos
Elementary School]
TY Lin
tbd
Study completed by Y2K.  Design underway.  Construction in fall 2023.
$3.2 Million grant awarded for construction and $650,000
for design.
$6.00
TP2202, Kyrene Branch and Highline Canal Shared Use Paths
Kimley-Horn
tbd
Study complete.  Request for Qualifications for a designer to go out November 14, 2022.  
Construction in 2024-25.
Federal grants have been awarded to fund study, design
and construction.
$4.00
Ashley and Paseo Trails Connection
Y2K Engineering
tbd
Study complete.  Design in FY 2023.  Construction in 2024-25.
Study is federally funded.  Construction and design grant
funding will be pursued.
$1.00
Hunt Highway Bicycle Improvements and Traffic Calming Study
Rick Engineering
tbd
Study underway, to be completed mid 2023.
Federally funded.  Study will look at a potential shared use path or 
separated bike lanes along with recommendations for traffic calming 
between Cooper Rd.
and Val Vista Dr.
$0.10
Tumbleweed Park ADA Improvements
N/A
Vincon
Construction complete. 
Sidewalk and curb ramp improvements throughout and
adjacent to park.
$0.40
Protected Bike Lanes Study
Y2K Engineering
tbd
Study to kickoff late 2022.
Federally funded.  Study will prioritize opportunities to
install protected bike lanes on arterial and collector streets in Chandler.
$0.10
Chandler Flex
NA
Via
Study completed in collaboration with Valley Metro.  Contract awarded to Via.  Operations 
began July 11, 2022.
Awarded $2 Million grant for project startup and two years of 
operations.
$2.10
Transportation Project Status - November 16, 2022
ROADWAY AND TRAFFIC PROJECTS