Capital Projects – Design Phase: 
 
Wildlife Hazard Perimeter Fence:  ADOT environmental clearance received 8/1.  
100% ADOT funding at $1,107,500.  Proceeding to 100% plans.  Coordination with 
Arizona Game & Fish Dept. 
 
Arizona Pavement Management System:  Grant approved by City Council on 4/28.   
90% ADOT funding at $617,574 with City match of $61,758.  ADOT handling contractor 
procurement.  Work tentatively scheduled for January 16, 2023 start. 
 
Airport Operations Garage: City funded at $1 million.  Design contract to Council. 
 
Airport Fuel Tank Relocation: City funded at $610,000.  Reviewing revised cost 
proposal. 
 
Automated Weather Observation System (AWOS) Replacement:  FAA funding for 
equipment replacement for $200,000.  Pre-scoping meeting 9/16.  Revised cost 
proposal under review. 
 
Runway End Identifier Light (REIL) Installation Runway 4L-22R– (North Runway)- 
FAA funding for equipment replacement for $110,000.  Pre-scoping meeting 9/16. 
Revised cost proposal under review. 
 
Runway 4R-22L Rehabilitation (South Runway)— Potential FAA funding of 
$350,000 for design.  Project scoping initiated. 
 
Capital Projects - Construction Phase: 
 
Heliport Lighting Replacement:  Limited Notice to Proceed for long lead items 
issued.  Pre-construction meeting held 10/21. Construction kickoff meeting TBD.  City 
funding at $277,771 for construction. 
 
 
Meeting Date:  
November 9, 2022 
Chandler Municipal Airport 
Construction Report

Maintenance Projects: 
 
Fence Repair:  Selective tensioning continuing. 
 
Landscaping – West Side of Airport Blvd:  Decomposed granite installed.  
 
Ramp/Apron Painting:  Transient parking repainting with new, dedicated lead-in 
lines.  Tentatively December/January. 
 
Flight Planning Room/Pilot Lounge Repairs:  Awaiting updated wall planning 
maps/charts.   
 
Terminal: Touch-up painting continuing.