Capital Projects – Design Phase: Wildlife Hazard Perimeter Fence: ADOT environmental clearance received 8/1. 100% ADOT funding at $1,107,500. 100% plans expected to go out for bid in February. Arizona Pavement Management System: Grant approved by City Council on 4/28. 90% ADOT funding at $617,574 with City match of $61,758. ADOT handling contractor scheduling with work tentatively scheduled for late February/early March. Airport Operations Garage: City funded at $1 million. Design contract approved. Airport Fuel Tank Relocation: City funded at $610,000. Design proposal under contract development. Automated Weather Observation System (AWOS) Replacement: FAA funding for equipment replacement for $200,000. Pre-scoping meeting 9/16. Contract routing. FAA environmental clearance received. Runway End Identifier Light (REIL) Installation Runway 4L-22R– (North Runway)- FAA funding for equipment replacement for $110,000. Contract routing. Runway 4R-22L Rehabilitation (South Runway)— Awaiting FAA grant for $350,000 for design. Project scoping initiated. Capital Projects - Construction Phase: Heliport Lighting Replacement: Underway. City funding at $277,771 for construction. Substantial completion projected for last week of January. Maintenance Projects: Fence Repair: Selective tensioning ongoing. Meeting Date: January 11, 2023 Chandler Municipal Airport Construction Report Ramp/Apron Painting: Transient parking repainting with new, dedicated lead-in lines. Tentatively January/early February. Flight Planning Room/Pilot Lounge Repairs: Awaiting updated wall planning maps/charts. Terminal: Touch-up painting ongoing.