Presentation - Future Fire Station Planning

City of Chandler — Regular Meeting (2023-02-10)

View PDF Meeting page

Extracted text (via pymupdf) 3861 characters
Chandler Fire Station 
Development Plan 
Quality of Life Subcommittee Meeting
February 10, 2023

Fire Station 282
• Approved by voters in the 2021 
Bond Election.
• Total project cost is $12,000,000
• Project includes bringing adjacent 
basin to current standards.
• Project is on schedule with a 
certificate of occupancy projected in 
October of 2023. 
• Once completed, a redeployment of 
resources and staff will occur.

Fire Station 284
A 2018 facility condition assessment conducted by Faithful & Gould identified a need for 
$1.1 million in repairs. Regular maintenance and condition evaluation are ongoing.
The Fire Station 4 project was recommended for reconstruction by the Public Safety 
Bond Subcommittee and approved by voters in the 2021 bond election.
Fire Station 4 was built in 1986 and is the only station remaining that does not have 
separate sleeping quarters for men and women.   
The new station will include current design practices to reduce carcinogen exposure to 
firefighters.
Station design is funded for $680,000 in FY 2028-29, and construction is funded for 
$8,787,000 in FY 2029-30.

Fire Station 
2812
Fire Station 2812 is in the earliest phase of planning.
Chandler Fire Department (CFD) has been assessing building 
development, call volume growth, response times, and other 
factors that impact emergency response.
CFD staff identified a desired area of the City to build Fire Station 
2812, with a general location of Arizona Avenue and Queen 
Creek Road.
CFD and the Public Works and Utilities staff identified a potential 
location for Fire Station 2812 on unused City property located on 
Queen Creek Road between McQueen Road and Arizona 
Avenue.

Call Volume Growth               FY 2019-20 – FY 2021-22
District
FY 2019-20
FY 2020-21
FY 2021-22
Grand Total
Growth
*Station 281
2,114 
2,301 
2,297 
6,712 
8.0%
*Station 2810
1,294 
1,256 
1,439 
3,989 
10.1%
*Station 2811
1,033 
1,070 
1,262 
3,365 
18.1%
Station 282
4,522 
4,443 
4,747 
13,712 
4.7%
Station 283
2,987 
2,774 
3,217 
8,978 
7.1%
Station 284
1,566 
1,707 
1,890 
5,163 
17.1%
*Station 285
2,611 
2,764 
2,937 
8,312 
11.1%
Station 286
2,063 
2,127 
2,195 
6,385 
6.0%
*Station 287
1,474 
1,679 
1,879 
5,032 
21.6%
Station 288
2,787 
2,649 
2,649 
8,085 
-5.2%
Station 289
2,072 
2,046 
2,224 
6,342 
6.8%
*Station directly impacted by Fire Station 2812

District
90th Percentile Response Times
*Station 2811
06:53
*Station 2810
06:33
*Station 281
06:13
*Station 285
06:09
Station 289
06:09
*Station 287
06:01
Station 284
05:48
Station 283
05:34
Station 288
05:31
Station 282
05:28
Station 286
05:22
Response Times 2022

Target Area 
Experiencing 
Reduced Coverage 
&  Redundancy

Location Analysis:
Current 
Responses 
Greater Than 5 
Minutes

Location Analysis:
Incident Volume 
Inside 5-Minute 
Response 
Diamond

Proposed Station Location 
Proposed site-
350’ x 235’ (1.9 acres)

Deployment Impact of Additional Station
District
Current FY 21-22 
Incidents
Possible FY 21-22 
Incidents W/ 2812
Change
Out Of City
1846
1846
0
Station 281
2297
1910
-387
Station 2810
1439
1338
-101
Station 2811
1262
1176
-86
Station 2812
0
1280
1280
Station 282
4747
4747
0
Station 283
3217
3217
0
Station 284
1890
1890
0
Station 285
2937
2231
-706
Station 286
2195
2195
0
Station 287
1879
1879
0
Station 288
2649
2649
0
Station 289
2224
2224
0

Next Steps
• Complete the Fire Station 2 project and 
redeploy response resources.
• Evaluate the timing of the Fire Station 4 
project based on response needs, 
ongoing building condition assessment, 
and fiscal considerations. Continue to 
maintain critical systems until station is 
fully reconstructed.
• Continue to monitor response needs in 
South Chandler and include the design 
and construction of Fire Station 12 in 
years 9 and 10 in the CIP as a 
placeholder, with regular evaluation of 
demand and timing.