Capital Projects – Design Phase: 
 
Wildlife Hazard Perimeter Fence:  ADOT environmental clearance received 8/1.  
100% ADOT funding at $1,107,500.  100% plans to go out for bid in February. 
 
Arizona Pavement Management System:  Grant approved by City Council on 4/28.   
90% ADOT funding at $617,574 with City match of $61,758.  ADOT handling contractor 
scheduling.  Work now scheduled for April 2023. 
 
Airport Operations Garage: City funded at $1 million.  Design contract approved.  
Programming underway. 
 
Airport Fuel Tank Relocation: City funded at $610,000.  Contract scheduled for 
February 23rd Council meeting. 
 
Automated Weather Observation System (AWOS) Replacement:  FAA funding for 
equipment replacement for $200,000.  Contract routing.  FAA environmental 
clearance received. 
 
Runway End Identifier Light (REIL) Installation Runway 4L-22R– (North Runway)- 
FAA funding for equipment replacement for $110,000.  Contract executed. 
 
Runway 4R-22L Rehabilitation (South Runway)— Awaiting FAA grant for $350,000 
for design.  FAA environmental clearance received.  Contract scheduled for February 
23rd Council meeting. 
 
Capital Projects - Construction Phase: 
 
Heliport Lighting Replacement:  Underway.  City funding at $277,771 for 
construction.  Substantial completion scheduled for February 3. 
 
Maintenance Projects: 
 
Fence Repair:  Selective tensioning ongoing. 
Meeting Date:  
February 8, 2023 
Chandler Municipal Airport 
Construction Report

 
Ramp/Apron Painting:  Transient parking repainting with new, dedicated lead-in 
lines.  Tentatively January/early February. 
 
Flight Planning Room/Pilot Lounge Repairs:  Awaiting updated wall planning 
maps/charts.   
 
Terminal: Touch-up painting ongoing.