Concord Hospitality Memo

City of Chandler — Regular Meeting (2023-05-10)

View PDF Meeting page

Extracted text (via pymupdf) 4357 characters
Subject: 
Airport Conflict Evaluation 
 
Concord Hospitality 
 
Southeast Corner of Cooper Road and Yeager Drive 
 
Recommendation 
Staff recommends the Airport Commission ("Commission") present an Airport Conflict 
Evaluation (ACE) report to the Zoning Administrator and City Council with a finding of "no 
conflict with airport uses" for the proposed Concord Hospitality development. 
 
Background 
The approximately 2.67 acre site is located at the southeast corner of Cooper Road and 
Yeager Drive (Exhibit A - Vicinity Map, Exhibit B - Property Location) and is zoned Planned Area 
Development (PAD).  Adjacent land uses include commercial and hospitality uses. 
 
The site is approximately 0.23 miles north of the Airport property line and is not located 
within the 60ldn noise contour (Exhibit A- Vicinity Map, Exhibit B- Property Location). 
 
The proposed project consists of one 124-room hospitality building totaling approximately 
54,000 square feet (SF) with four stories (Exhibit C - Site Plan).  The building height is slightly 
under 45 feet to the top of parapet. 
 
The City of Chandler General Plan designates the property for Employment.  The 2021 
Chandler Airpark Area Plan (CAAP) designates the property Innovation District (Exhibit D – 
Chandler Airpark Area Plan Land Use Plan). 
 
Analysis and Stipulations 
The proposed development is consistent with the CAAP. Commercial and industrial land 
uses are generally compatible with airport operations.  The property will experience daily 
overflights from aircraft on takeoff and landing (Exhibit E – Flight Tracks).   
 
Based on the proposed building heights, the proposed development does not appear to 
pose a hazard to flight safety or be an airspace obstruction.  The proposed building height 
does not appear to impact the approach and departure surfaces for either runway.  Final 
building structures, including all rooftop objects, must not impact the approach and departure 
surfaces for the Airport’s runways.  
 
The proposed project does not indicate the use of rooftop solar panels.  If solar panels are 
anticipated to be installed, the owner/applicant must complete a solar study and

coordinate with Airport Administration to ensure that glare will not interfere with aircraft 
on approach or takeoff. 
 
The owner/applicant must file a Notice of Proposed Construction (FAA Form 7460-1) with 
the Federal Aviation Administration (FAA) for the final structure heights, including, without 
limitation, all rooftop antennas, parapets, light poles, and other equipment.  The form may 
be submitted online at https://oeaaa.faa.gov/oeaaa/external/portal.jsp.  The FAA-assigned 
numbers for all evaluation cases must be provided to Airport Administration.  The 
owner/applicant and its contractors must coordinate directly with Airport Administration at least 
thirty (30) calendar days before starting vertical construction. 
 
The owner/applicant must ensure that its contractors file a Notice of Proposed 
Construction (FAA Form 7460-1) with the FAA for temporary construction equipment 
including, without limitation, cranes, drilling rigs, concrete boom pumps.  The form may be 
submitted online at https://oeaaa.faa.gov/oeaaa/external/portal.jsp.  The FAA-assigned 
numbers for all evaluation cases must be provided to Airport Administration.  The 
owner/applicant and its contractors must coordinate directly with Airport Administration at least 
thirty (30) calendar days before starting vertical construction. 
 
The proposed project’s building design must not create reflectivity issues with aircraft in 
the traffic pattern and on approach or takeoff (Exhibit F – Building Elevations).  The use of 
non-reflective glazing and non-reflective paint is encouraged.   
 
Findings 
 
     No Conflict 
     High Conflict 
     Moderate Conflict 
     Low Conflict 
    
Specific Area(s) of Conflict: Not applicable. 
 
Recommended Corrective Actions: Not applicable. 
 
Proposed Motion for Regular Agenda 
Move to present an Airport Conflict Evaluation (ACE) report to the Zoning Administrator 
and City Council with a finding of "no conflict with airport uses" for the proposed Concord 
Hospitality development. 
 