Monthly Construction Report

City of Chandler — Regular Meeting (2023-05-10)

View PDF Meeting page

Extracted text (via pymupdf) 1864 characters
Capital Projects – Design Phase: 
 
Airport Operations Garage: City funded at $1 million.  Programming and conceptual layout 
underway.  Comments provided for first concepts. Awaiting refined layout. 
 
Airport Fuel Tank Relocation: City funded at $610,000.  Kick-off meeting 3/6.  Design for new above 
ground tank underway. Initial 30% plan review completed. 
 
Automated Weather Observation System (AWOS) Replacement:  FAA funding for $200,000.  FAA 
environmental clearance received.  Kick-off meeting 2/21.  30% plans received and commented. 
 
Runway End Identifier Light (REIL) Installation Runway 4L-22R– (North Runway)- FAA funding 
for $110,000.  Kick-off meeting 2/21. Environmental clearance underway.  30% review underway. 
 
Runway 4R-22L Rehabilitation (South Runway)— Awaiting FAA grant for $350,000 for design.  
FAA environmental clearance received.  Design contract approved.  Kick-off meeting 4/6. Design 
underway. 
 
Taxiway B Improvements- Phase 1 – Awaiting ADOT grant for $2,035,000.  Council authorized 
grant 2/23.  Design proposal received. 
 
Capital Projects - Construction Phase: 
 
Arizona Pavement Management System:  Grant at 90% ADOT funding at $617,574 with City match 
of $61,758.  Final paving scheduled for completion on 5/9 and final striping for early June. 
 
Wildlife Hazard Perimeter Fence:  100% ADOT funding at $1,107,500.  $796,813 contract with 
Diamond Ridge Development Corporation scheduled for 5/25 Council agenda. 
 
Maintenance Projects: 
 
Fence Repair:  Selective tensioning ongoing. 
 
Ramp/Apron Painting:  Transient parking repainting with new, dedicated lead-in lines - Start TBD. 
 
Flight Planning Room/Pilot Lounge Repairs:  Awaiting updated wall planning maps/charts.   
 
Terminal: Touch-up painting ongoing. 
Meeting Date:  
May 10, 2023 
Chandler Municipal Airport 
Construction Report