Monthly Construction Report

City of Chandler — Regular Meeting (2023-07-12)

View PDF Meeting page

Extracted text (via pymupdf) 1546 characters
Capital Projects – Design Phase: 
• 
Airport Operations Garage: City funded at $1 million.  Programming and conceptual layout 
underway.  Second layout reviewed.  Awaiting revision. 
• 
Airport Fuel Tank Relocation: City funded at $610,000.  Kick-off meeting 3/6.  Design for new above 
ground tank underway. Initial 30% plan review completed. 60% plans underway. Field visit week of 
July 10. 
• 
Automated Weather Observation System (AWOS) Replacement:  FAA funding for $200,000.  FAA 
environmental clearance received.  Kick-off meeting 2/21.  Proceeding to 100% plans. 
• 
Runway End Identifier Light (REIL) Installation Runway 4L-22R– (North Runway)- FAA funding 
for $110,000.  Kick-off meeting 2/21. Environmental clearance underway.  90% review underway. 
• 
Runway 4R-22L Rehabilitation (South Runway)— FAA grant for $350,000 for design approved.  
FAA environmental clearance received.  Design contract approved.  Kick-off meeting 4/6. Design 
underway. 
• 
Taxiway B Improvements- Phase 1 – ADOT grant for $2,035,000 approved.  Awaiting design 
scope/fee proposal. 
 
Capital Projects - Construction Phase: 
• 
Wildlife Hazard Perimeter Fence:  100% ADOT funding at $1,107,500.  $796,813 contract with 
Diamond Ridge Development Corporation approved.  Construction Kick-off meeting 6/26. 
 
Maintenance Projects: 
• 
Ramp/Apron Painting:  Transient parking repainting with new, dedicated lead-in lines - Start TBD. 
• 
Terminal: Touch-up painting ongoing. 
Meeting Date:  
July 12, 2023 
Chandler Municipal Airport 
Construction Report