City of Chandler, Arizona 
Report on Applying Agreed-Upon Procedures 
Biennial Certification of Land Use Assumptions, 
Infrastructure Improvement Plan 
and Impact Fees 
For the Period July 1, 2020 through June 30, 2022

CITY OF CHANDLER, ARIZONA 
TABLE OF CONTENTS 
CONTENTS
PAGE 
Independent Accountant’s Report on Applying Agreed-Upon Procedures 
      1 
Results of Procedures 
      3 
Appendix A – Progress of Infrastructure Improvement Plan Projects  
      7

INDEPENDENT ACCOUNTANT’S REPORT ON 
APPLYING AGREED-UPON PROCEDURES 
Honorable Mayor and Members of the City Council 
City of Chandler, Arizona 
We have performed this agreed-upon procedures engagement to assist management of the City of 
Chandler, Arizona (City), with the requirement set forth in Arizona Revised Statutes (A.R.S.) 
9-463.05.G.2 “to provide for a biennial certified audit of the municipality’s land use assumptions,
infrastructure improvements plan and development fees.” As such, we have performed the
procedures identified below, solely to assist users in evaluating the City’s compliance with the
progress reporting requirements of the infrastructure improvement plan for the period from
July 1, 2020 through June 30, 2022, as specified in A.R.S. 9-463.05.G.2. City of Chandler,
Arizona’s management is responsible for its compliance with those requirements.
City of Chandler, Arizona’s management has agreed to and acknowledged that the procedures 
performed are appropriate to meet the intended purpose of assisting users in determining whether 
the City complied with the specified requirements. This report may not be suitable for any other 
purpose. The procedures performed may not address all the items of interest to a user of this report 
and may not meet the needs of all users of this report and, as such, users are responsible for 
determining whether the procedures performed are appropriate for their purposes. 
We have applied the following procedures:  
The progress of the infrastructure improvements plan. 
a.
Compared growth projections for 2021 and 2022 related to dwelling units, population,
and the various commercial square footage units as reported in the Infrastructure
Improvement Plan (IIP) to actual results for the proportionate 10-year projections. A
list of all variances are reported in the Results of Procedures.
b.
Obtained City-prepared report (see Appendix A) documenting the progress of each
project identified in the Infrastructure Improvement Plan (IIP) and performed the
following procedures:
i.
Agreed expenditures as of June 30, 2022 to the underlying accounting records.
ii.
Agreed amounts reported as estimated cost to complete to underlying
accounting records.
The collection and expenditures of impact fees for each project in the plan. 
c.
Selected a sample of 80 building permits issued and determined fees were charged in
accordance with authorized fee schedules and that each permit holder was charged the
same rate as another equivalent permit holder.
d.
Selected a sample of 50 expenditures and determined that the expenditures were
associated with an approved project in the City’s IIP.
Page 1

Evaluating any inequities in implementing the plan or imposing the impact fee. 
e.
Evaluated any inequities in implementing the plan or imposing the impact fee through
recalculating impact fees at the transaction level for the sample mentioned in procedure
c above.
f.
Determined that there were no instances in which the City waived impact fees, except
as allowed for under A.R.S. 9-499.10.B and A.R.S. 9-500.18.
The accompanying Results of Procedures describes the items we noted. 
We were engaged by City of Chandler, Arizona’s management to perform this agreed-upon 
procedures engagement and conducted our engagement in accordance with attestation standards 
established by the American Institute of Certified Public Accountants.  We were not engaged to 
and did not conduct an examination or review engagement, the objective of which would be the 
expression of an opinion or conclusion, respectively, on compliance with the specified 
requirements. Accordingly, we do not express such an opinion or conclusion.  Had we performed 
additional procedures, other matters might have come to our attention that would have been 
reported to you. 
We are required to be independent of City of Chandler, Arizona and to meet our other ethical 
responsibilities, in accordance with relevant ethical requirements related to our agreed-upon 
procedures engagement.  
This report is intended solely for the information and use of the management of City of Chandler, 
Arizona, and is not intended to be and should not be used by anyone other than these specified 
parties. 
Heinfeld, Meech & Co., P.C. 
Scottsdale, Arizona 
August 24, 2023 
Page 2

CITY OF CHANDLER, ARIZONA 
RESULTS OF PROCEDURES 
PROCEDURE A  
Compared growth projections for 2021 and 2022 related to dwelling units, population, and the 
various commercial square footage units as reported in the City’s Land Use Assumptions and 
Infrastructure Improvements Plan (IIP) to actual current amounts for the proportionate 10-year 
projections. A list of all variances will be reported. 
Exception: 
Variances were noted for growth projections for dwelling units, population, and the various 
commercial square footage as reported in the Land Use Assumptions and Infrastructure 
Improvements Plan when compared to actual results.  
Management Response: 
Assumptions of equal growth of land development and the resulting fees averaged over a set 
period of time do not reflect the reality of how development occurs. Variances exist due to 
market conditions, demand for various types of land use and structures, the condition of the 
economy, and the availability of capital. The City of Chandler continues to take into account 
annual planning projections, entitled projects, and variations in construction permits to augment 
the equal growth assumptions when forecasting. 
TOTAL SQUARE FOOTAGE 
Note: The cumulative projected amounts for square footage assume equal growth for each year 
of the 10-year period with the incremental cumulative total presented for each year. 
Cumulative Total as of 2021 
 
Projected 
Actual 
 
Variance 
 Variance % 
Industrial 
Citywide 
 37,796,012
 40,508,493
  2,712,481 
7% 
Arterial Streets 
18,013,960
19,747,031
1,733,071 
10% 
Institutional 
Citywide
12,681,430
12,339,915
(341,515)
-3%
Arterial Streets 
6,717,760
7,323,197
605,437 
9%
Office 
Citywide
10,135,991
8,236,624
(1,899,367)
-19%
Arterial Streets 
4,165,269
3,636,165
(529,104)
-13%
Retail 
Citywide
18,918,529
18,870,833
(47,696)
0%
Arterial Streets 
7,850,505
8,256,576
406,071 
5% 
Page 3

CITY OF CHANDLER, ARIZONA 
RESULTS OF PROCEDURES 
PROCEDURE A (Continued) 
TOTAL SQUARE FOOTAGE 
Cumulative Total as of 2022 
 
Projected 
 
Actual 
 
Variance 
 Variance % 
Industrial 
Citywide 
38,693,852  
45,475,860  
6,782,008 
18% 
Arterial Streets 
18,731,017  
24,237,959  
5,506,942 
29% 
Institutional 
Citywide 
12,755,918  
12,407,444  
(348,474) 
-3%
Arterial Streets 
6,794,051  
7,058,323  
264,272 
4%
Office 
Citywide
 
10,608,532  
7,915,915 
(2,692,617) 
-25%
Arterial Streets 
4,398,871  
3,752,388  
(646,483) 
-15%
Retail 
Citywide 
19,081,443  
18,771,901  
(309,542) 
-2%
Arterial Streets 
7,977,417  
7,689,295  
(288,122) 
-4%
TOTAL HOUSING UNITS AND POPULATION BY SERVICE AREA 
Note: The cumulative projected amounts for housing units and population assume equal growth 
for each year of the 10-year period with the incremental cumulative total presented for each 
year. 
Cumulative Total as of 2021 
 
Projected 
 
Actual 
 
Variance 
 Variance % 
Single Family 
Parks Northwest 
 
11,727  
12,211 
484 
4% 
Parks Northeast 
 
34,943  
36,000 
1,057 
3% 
Park Southeast 
 
33,017  
35,611 
2,594 
8% 
Citywide 
 
79,686  
83,822 
4,136 
5% 
Arterial Streets 
 
43,785  
47,732 
3,947 
9% 
MultiFamily 
Parks Northwest 
 
4,982  
5,269 
287 
6% 
Parks Northeast 
 
17,581  
18,049 
468 
3% 
Park Southeast 
 
7,164  
9,381  
2,217 
31% 
Citywide 
 
29,728  
32,699 
2,971 
10% 
Arterial Streets 
 
11,372  
14,584 
3,212 
28% 
Resident Population 
Parks Northwest 
 
42,301  
44,574 
2,273 
5% 
Parks Northeast 
 
131,243  
137,825 
6,582 
5% 
Park Southeast 
 
104,771  
114,730 
9,959 
10% 
Citywide 
 
278,315  
297,129 
18,814 
7% 
Arterial Streets 
144,204 
158,906 
14,702 
10% 
Page 4

CITY OF CHANDLER, ARIZONA 
RESULTS OF PROCEDURES 
PROCEDURE A (Continued) 
Cumulative Total as of 2022 
 
Projected 
 
Actual 
 
Variance 
 Variance % 
Single Family 
Parks Northwest 
    11,727 
       11,856 
129  
1% 
Parks Northeast 
 
34,943  
33,471  
(1,472) 
-4%
Park Southeast 
 
33,017  
35,611 
2,594 
8%
Citywide 
 
79,686  
80,938 
1,252 
2%
Arterial Streets 
 
43,785  
52,349 
8,564 
20% 
MultiFamily 
Parks Northwest 
 
4,982  
5,624 
642  
13% 
Parks Northeast 
 
17,581  
20,034 
2,453 
14% 
Park Southeast 
 
7,164  
9,381  
2,217  
31% 
Citywide 
 
29,728  
35,039 
5,311 
18% 
Arterial Streets 
 
11,372  
17,828 
6,456 
57% 
Resident Population 
Parks Northwest 
 
42,301  
44,574 
2,273  
5% 
Parks Northeast 
 
131,243  
136,438 
5,194  
4% 
Park Southeast 
 
104,771  
114,730 
9,959  
10% 
Citywide 
 
278,315  
295,741 
17,426  
6% 
Arterial Streets 
144,204 
178,951 
34,747  
24% 
PROCEDURE B 
Obtained City-prepared report (see Appendix A) documenting the progress of each project 
identified in the Infrastructure Improvement Plan (IIP) and performed the following procedures: 
a.
Agreed expenditures as of June 30, 2022 to the underlying accounting records.
b. Agreed amounts reported as estimated cost to complete to underlying accounting
records.
No exceptions noted. 
PROCEDURE C 
Selected a sample of 80 building permits issued and determine fees were charged in accordance 
with authorized fee schedules and that each permit holder is charged the same rate as another 
equivalent permit holder.  
Exception: 
For one of 80 building permits reviewed, the incorrect land use type was utilized for the fee 
calculation. The Retail Commercial land use type was utilized instead of the Public/Institutional 
land use type. This resulted in an overcharge of approximately $14,700.   
Management Response: 
The City agrees with the error identified when a permit pulled for a religious education center 
with office space was assigned the office classification instead of institutional, a refund has 
been issued to the permittee. 
Page 5

CITY OF CHANDLER, ARIZONA 
RESULTS OF PROCEDURES 
 
 
 
 
PROCEDURE D 
Selected a sample of 50 expenditures and determine that the expenditure was associated with an 
approved project in the City’s IIP. 
 
No exceptions noted. 
 
PROCEDURE E 
Evaluated any inequities in implementing the plan or imposing the impact fee through 
recalculating impact fees at the transaction level for the sample mentioned in procedure c above. 
 
No exceptions noted. 
 
PROCEDURE F 
Determined that there were no instances in which the City waived impact fees, except as allowed 
for under A.R.S. 9-499.10.B and A.R.S. 9-500.18 
 
No exceptions noted. 
Page 6

APPENDIX A
PROGRESS OF INFRASTRUCTURE IMPROVEMENT PLAN PROJECTS
Fund
Description
415 Arterial Street Impact Fees
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
2020‐21
2021‐22
 2022‐23 
though 
2031‐32* 
Total
6ST311‐Price Rd and Queen Creek Intersection
‐ 
‐ 
(190,862)
            
‐ 
‐ 
‐ 
‐ 
‐ 
(190,862)
               
6ST478‐McQueen Rd (Queen Creek Rd to Riggs Rd)
401,157
 
722,149
             
542
 
‐ 
‐ 
‐ 
‐ 
‐ 
1,123,848
             
6ST482‐Gilbert Rd (Germann Rd to Queen Creek Rd)
‐ 
‐ 
(127,921)
            
‐ 
‐ 
‐ 
‐ 
‐ 
(127,921)
               
6ST548‐Queen Creek Rd (McQueen Rd to Lindsay Rd)
‐ 
262,288
             
246,143
              
601,762
              
2,100,347
           
153,606
              
‐ 
3,364,147
             
6ST596‐Gilbert Rd (Queen Creek Rd to Riggs Rd)
484,152
 
20,705
                
‐ 
‐ 
‐ 
‐ 
504,857
                
6ST607‐Ocotillo Rd (Arizona Ave to McQueen Rd)
659,940
 
490
 
‐ 
(1,011)
 
‐ 
‐ 
659,419
                
6ST608‐Chandler Heights (Arizona Ave to McQueen Rd)
32,904
 
114,167
             
570,702
              
‐ 
1,182,277
           
2,983
 
‐ 
1,903,033
             
6ST641‐Ocotillo Rd (Cooper Rd to 148th St)
147,647
 
513,530
             
1,670,914
           
‐ 
334,675
              
48,918
                
35,048
                
4,382,277
            
7,133,009
             
6ST675‐Cooper Rd (Queen Creek Rd to Riggs Rd)
13,741
 
27,077
                
160,594
              
‐ 
45,614
                
2,294,623
           
2,644,544
           
596,565
               
5,782,758
             
6ST692‐Chandler Heights Rd (McQueen Rd to Val Vista Dr)
‐ 
‐ 
181,765
              
469,687
              
119,741
              
122,793
              
858,848
              
18,407,675
          
20,160,509
           
6ST693‐Lindsay Rd (Ocotillo Rd to Hunt Hwy)
‐ 
‐ 
‐ 
‐ 
17,915
                
110,764
              
84,842
                
19,713,656
          
19,927,177
           
6ST738‐Gilbert Rd (Ocotillo Rd to Chandler Heights Rd)
‐ 
‐ 
‐ 
‐ 
213,989
              
(213,989)
            
‐ 
‐ 
6ST745‐Alma School Rd (Chandler Blvd to Pecos Rd)
‐ 
‐ 
‐ 
‐ 
‐ 
8,280,000
            
8,280,000
             
6ST746‐Alma School Rd (Pecos Rd to Germann Rd)
‐ 
‐ 
‐ 
‐ 
176,985
              
2,405,803
           
1,214,127
           
200,712
               
3,997,627
             
6ST747‐Alma School Rd (Germann Rd to Queen Creek Rd)
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
4,558,000
            
4,558,000
             
*As programmed in 2022‐2033 CIP
421 Community Park Impact Fees
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
2020‐21
2021‐22
Total
6PR396‐Mesquite Groves Park
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
Note:  This fund was expended and closed as of 6/30/17.
422 Neighborhood Parks Impact Fees
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
2020‐21
2021‐22
Total
6PR039‐Neighborhood Park Land Acquisition
3,087
 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
3,087
 
6PR389‐Homestead North Park Site
‐ 
‐ 
‐ 
22,445
                
72,723
                
95,168
 
6PR400‐Roadrunner Park
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
6PR631‐Centennial Park Site
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
Note:  This fund was expended and closed as of 6/30/20.
424 Park Impact Fees
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
2020‐21
2021‐22
 2022‐23 
though 
2031‐32* 
Total
6PR389‐Homestead North Park Site
‐ 
‐ 
‐ 
27,588
                
25,564
                
55,091
                
684,404
              
2,658,568
            
3,451,215
             
6PR390‐Homestead South Park Site
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
6PR396‐Mesquite Groves Park Site
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
6PR400‐Roadrunner Park Site
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
6PR420‐Veteran's Oasis Park Site
‐ 
‐ 
(59,740)
               
‐ 
‐ 
‐ 
‐ 
‐ 
(59,740)
 
6PR629‐Lantana Ranch Park
347,469
              
242,454
              
‐ 
589,923
                
6PR631‐Centennial Park Site
12,843
 
4,672
 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
17,515
 
6PR638‐Valencia Park Site
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
6PR639‐Citrus Vista Park Site
1,412,990
              
4,995
 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
1,417,985
             
6PR640‐Layton Lakes Park Site
‐ 
141,285
             
1,191,476
           
139,376
              
‐ 
‐ 
‐ 
1,472,137
             
*As programmed in 2022‐2033 CIP
425 Parks NW Impact Fees
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
2020‐21
2021‐22
 2022‐23 
though 
2031‐32* 
Total
None
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
**No growth‐related capital to construct; collecting fees to repay pledged debt
426 Parks NE Impact Fees
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
2020‐21
2021‐22
 2022‐23 
though 
2031‐32* 
Total
None
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
**No growth‐related capital to construct; collecting fees to repay pledged debt
Fiscal Year
Note: Any negative amounts presented are expense recoveries from prior years.
Page 7

APPENDIX A
PROGRESS OF INFRASTRUCTURE IMPROVEMENT PLAN PROJECTS
427 Parks SE Impact Fees
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
2020‐21
2021‐22
 2022‐23 
though 
2031‐32* 
Total
6PR396‐Mesquite Groves Park Site
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
20,519,300
          
20,519,300
           
6PR629‐Lantana Ranch Park Site
‐ 
‐ 
‐ 
‐ 
88,854
                
990,630
              
2,013,331
           
6,769,638
            
9,862,452
             
*As programmed in 2022‐2033 CIP
465 Police Impact Fees
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
2020‐21
2021‐22
 2022‐23 
though 
2031‐32* 
Total
6PD243‐Chandler Heights Subtation
‐ 
‐ 
(59,740)
               
‐ 
‐ 
‐ 
‐ 
‐ 
(59,740)
 
**No growth‐related capital to construct; collecting fees to repay pledged debt
475 Fire Impact Fees
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
2020‐21
2021‐22
 2022‐23 
though 
2031‐32* 
Total
6FI611‐Southeast Fire Station
797
 
361,261
             
3,579,131
           
295,842
              
‐ 
‐ 
‐ 
4,237,031
             
6FI638‐Fire Station No. 1 Relocation
147,100
 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
147,100
                
**No growth‐related capital to construct; collecting fees to repay pledged debt
603 Water System Development Fees
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
2020‐21
2021‐22
 2022‐23 
though 
2031‐32* 
Total
6WA029‐Water Master Plan Update
‐ 
133,055
             
56,495
                
1,553
 
‐ 
‐ 
191,103
                
6WA034‐Well Construction/Rehabilitation
2,260,447
              
1,807,500
          
894,025
              
718,077
              
1,637,212
           
16,503
                
18,132
                
3,081,634
            
10,433,529
           
6WA076‐Transmission Mains
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
6WA334‐Joint Water Treatment Plant
‐ 
6,418,629
          
19,857,848
        
1,639,976
           
1,020,748
           
975,052
               
29,912,253
           
6WA672‐Water Purchases
‐ 
9,999,788
          
4,999,940
           
4,999,940
           
14,731,755
        
‐ 
34,731,423
           
**No growth‐related capital to construct; collecting fees to repay pledged debt
604 Water Resource System Development Fees
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
2020‐21
2021‐22
Total
6WW661‐Ocotillo Water Reclamation Facility Expansion
748,052
 
2,763,414
          
488,533
              
‐ 
‐ 
‐ 
‐ 
4,000,000
             
6WA672‐Water Purchases
‐ 
‐ 
‐ 
‐ 
128,827
              
‐ 
128,827
                
Note:  This fund was expended and closed as of 6/30/20.
610 Reclaimed Water System Development Fees
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
2020‐21
2021‐22
 2022‐23 
though 
2031‐32* 
Total
6WW189‐Effluent Reuse‐Storage
97,991
 
876,519
             
15,513
                
151,138
              
294,279
              
210,689
              
2,171,057
           
833,847
               
4,651,034
             
6WW192‐Effluent Reuse‐Transmission Mains
1,422,386
              
158,361
             
868,974
              
3,198,432
           
212,433
              
1,738
 
241,830
               
6,104,155
             
*As programmed in 2022‐2033 CIP
614 Wastewater System Development Fees
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
2020‐21
2021‐22
 2022‐23 
though 
2031‐32* 
Total
6WW021‐Wastewater Master Plan Update
157,935
 
266,114
             
112,989
              
3,107
 
‐ 
‐ 
‐ 
540,145
                
6WW022‐Water Reclamation Facility Expansion
20,126
 
540
 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
20,666
 
6WW196‐Collection System Facility Improvements
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
6WW651‐Wastewater Land Acquistion
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
6WW642‐South Chandler Sewer Line Expansion
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
6WW661‐Ocotillo Water Reclamation Facility Expansion
19,505,029
            
79,677,431
        
14,085,867
        
‐ 
‐ 
‐ 
‐ 
‐ 
113,268,328
        
**No growth‐related capital to construct; collecting fees to repay pledged debt
Page 8