Monthly Construction Report

City of Chandler — Regular Meeting (2023-09-13)

View PDF Meeting page

Extracted text (via pymupdf) 1767 characters
Capital Projects – Design Phase: 
 
Airport Operations Garage: City funded at $1 million.  Programming and conceptual layout 
underway.  Consultant developing estimate of construction cost. 
 
Airport Fuel Tank Relocation: City funded at $610,000.  Kick-off meeting 3/6.  Design for new above 
ground tank underway.  Working toward 100% plans.  
 
Automated Weather Observation System (AWOS) Replacement:  FAA funding for $200,000.  FAA 
environmental clearance received.  Kick-off meeting 2/21.  100% plans in for review.  Project to be 
put out to bid late 2023/early 2024. 
 
Runway End Identifier Light (REIL) Installation Runway 4L-22R– (North Runway)- FAA funding 
for $110,000.  Kick-off meeting 2/21. Plans at 100%. Finalizing construction environmental 
documentation.  Bid TBD. 
 
Runway 4R-22L Rehabilitation (South Runway)— FAA grant for $350,000 for design approved.  
FAA environmental clearance received.  Design contract approved.  Kick-off meeting 4/6. Design 
underway. Survey and geotech completed. Design underway. 
 
Taxiway B Improvements- Phase 1 – ADOT grant for $2,035,000 approved.  Design scope/fee 
proposal received and under review.  Council approval of construction contract. 
 
Capital Projects - Construction Phase: 
 
Wildlife Hazard Perimeter Fence:  100% ADOT funding at $1,107,500.  $796,813 contract with 
Diamond Ridge Development Corporation approved.  Construction Kick-off meeting 6/26. Design 
consultant reviewing shop drawings. Notice to Proceed issued on August 14. 
 
Maintenance Projects: 
 
Ramp/Apron Painting:  Transient parking repainting with new, dedicated lead-in lines - Start TBD. 
 
Terminal: Touch-up painting ongoing. 
Meeting Date:  
Sept. 13, 2023 
Chandler Municipal Airport 
Construction Report