Informational Procurement Council Item – October 2023 Administrative Approvals 
Administrative Approval of Contracts and Agreements for Materials, Services, Equipment and 
Construction Valued Between $50,000 and $99,999 and Professional Services Valued Between $30,000 and 
$99,999  
 
Agreement No.: 4693 
Subject: State Legislative Representation Services 
Contractor: Policy AZ, LLC 
Value: $78,000.00 
Description: Provides for legislative lobbyist services at the state level 
 
Agreement No.: PR2106.205
Subject:  Tumbleweed Park Flo-2d Hydrologic Model
Contractor: Huitt-Zollars Inc
Value: $41,930.86
Description: Design Services for Tumbleweed Park FLO-2D Hydrologic Model.  The analysis will be used to 
request a CLOMR to revise the current effective floodplain between Queen Creek and Germann Road.
 
Agreement No.: WA1903.401 
Subject: Arrowhead Water Production Facility Rehabilitation and Pecos Surface Water Treatment Plant Surge 
System 
Contractor: Achen Gardner Construction LLC. 
Value: $98,000.00 
Description: Change Order #3 Additional funds to replace Owner’s allowance and to include a 90 day time 
extension. 
 
Agreement No.: WA2303.401 
Subject: Hahn Reservoir Main Repair 
Contractor: B & F Contracting Inc. 
Value: $30,666.50 
Description: Initially trenchless rehabilitation project with cured-in-place pipe lining, but due to bends found 
when the water main was excavated, methodology changed to traditional open cut and time extended for 45 
days. 
 
Agreement No.: PD2205.271 
Subject: Police Work Area and Storage Renovation 
Contractor: Arrington Watkins Architects LLC. 
Value: $45,260.00 
Description: Post Design Services for the Chandler Police Department Work Area and Storage Project.  
 
Agreement No.: PD2205.401 
Subject: Police Work Area and Storage Renovation 
Contractor: SDB INC. 
Value: $60,000.00

Description: Change Order #1 to replenish the Owner's allowance and to add 90 calendar days to the existing 
agreement to address unforeseen conditions.   
 
Agreement No.: PR2202.451 
Subject: Arrowhead Meadows Park Tennis and Pickleball Court Replacement 
Contractor: Dibble CM LLC. 
Value: $76,600.00 
Description: Construction Management Services to include Pre-Construction Assistance, Construction 
Management, Construction Inspection, and Utility Coordination. 
 
 
Agreement No.: WW2210.271 
Subject: Price Road Frontage Road Sewer Rehabilitation 
Contractor: Dibble & Associates Consulting Engineers Inc. dba Dibble 
Value: $ 85,520.00 
Description: Post Design Services for the project area location along Price Road Frontage Road from Fairview 
Drive to Elliott Road. 
 
Agreement No.: PE2111.401 
Subject: Chandler Tennis Center Renovations at Tumbleweed 
Contractor: Simpson Walker Contracting Corporation 
Value: $78,425.61 
Description: Change order #2 for work items and contract duration as included in the settlement agreement.   
Net change in calendar days is 251. 
 
Contracts or Agreements with Significant (+50%) Price Changes Valued Between $50,000 and $99,999 
Agreement No.:  
Subject:  
Contractor:  
Value:  
Notes:  
 
Agreement No.:  
Subject:  
Contractor:  
Value:  
Notes: