Monthly Construction Report

City of Chandler — Regular Meeting (2023-12-13)

View PDF Meeting page

Extracted text (via pymupdf) 1687 characters
Capital Projects – Design Phase: 
 
Airport Operations Garage: City funded at $1 million.  Programming and conceptual layout 
completed.  Requested design proposal. 
 
Airport Fuel Tank Relocation: City funded at $610,000.  Design for new above ground tank 
underway.  Finalizing 60% plans.   
 
Automated Weather Observation System (AWOS) Replacement:  FAA funding for $200,000.  FAA 
environmental clearance received.  Kick-off meeting 2/21.  100% plans finalized.  Project to be put 
out to bid January 2024. 
 
Runway End Identifier Light (REIL) Installation Runway 4L-22R– (North Runway)- FAA funding 
for $110,000.  Kick-off meeting 2/21. Plans at 100%. Finalizing construction environmental 
documentation.  Bid TBD. 
 
Runway 4R-22L Rehabilitation (South Runway) — FAA grant for $350,000 for design approved.  
Kick-off meeting 4/6.  30% plans submitted for review. 
 
Taxiway B Improvements- Phase 1 – ADOT grant for $2,035,000 approved.  Design kick-off 
meeting 10/26.  Survey completed. 
 
Old Heliport Redevelopment- Proceeding with design contract for $30,805 in local funds for new 
fencing and pavement maintenance/tie-down design. 
 
Capital Projects - Construction Phase: 
 
Wildlife Hazard Perimeter Fence:  100% ADOT funding at $1,107,500.  $796,813 contract with 
Diamond Ridge Development Corporation approved.  Final completion 12/1. 
 
Tower Internet Connectivity:  Local Funding. Project kick-off 12/4.  Completion planned late 
January/early February. 
Maintenance Projects: 
 
Ramp/Apron Painting:  Transient parking repainting with new, dedicated lead-in lines underway. 
Meeting Date:  
Nov. 8, 2023 
Chandler Municipal Airport 
Construction Report