2024 Jan Project status

City of Chandler — Regular Meeting (2024-01-17)

View PDF Meeting page

Extracted text (via pymupdf) 4800 characters
ROADWAY AND TRAFFIC PROJECTS
Designer
Contractor
Status
Comments
PROJECT COST 
ESTIMATE
($MILLIONS)
ST1614, Chandler Heights Road Improv. [McQueen Road to Gilbert Road for two 
through lanes each direction]
Kimley-Horn
Granite Construction 
Company
Construction underway.  Completion scheduled for 
Spring 2024.
Federal funds
$20.90
ST1616, Ocotillo Road Improv. [Gilbert Road to 148th Street for two through lanes 
each direction]
Ritoch-Powell
Haydon Companies, LLC
Construction underway.  Completion scheduled 
Winter 2023.
Federal funds
$6.80
ST1804, Chandler Heights Road Improv. [Gilbert Road to Val Vista Drive for
two through lanes each direction]
Kimley-Horn
tbd
Design in progress.  Bid scheduled for Spring 2024
Federal funds
$20.90
ST2001, Lindsay Road Improv. [Ocotillo Road to Hunt Highway for two
through lanes in each direction]
Kimley-Horn
tbd
Design in progress.  Bid scheduled for Summer 
2024
Federal funds
$27.20
ST2007, Hamilton Street Improv. [Appleby Road to Carob Drive]
Nfra Consultants
tbd
Design underway.  Construction scheduled to go 
out to Bid Winter 2023
$5.20
ST2009, Dobson Road Improv. at Intel Driveways #1 and #4 [Price Rd /
Market Pl to Chaparral Way]
Premier
DCS Contracting
Construction in progress.  Completion date 
extended to coordinate with other projects.  
Completion scheduledfor Winter 2024.
Funded by 20% from Intel and 80% from State TPT per
ARS 42-5032.02
$0 City Cost (Intel
Funded)
ST2012, Arterial Congestion Monitoring [Install data collection devices at major 
intersections, and use data to map traffic congestion and mobility.]
Y.S. Mantri & Assoc.
CS Construction
Construction underway.  Completion scheduled for 
Winter 2023.
Grant funds
$1.30
ST2103, Intersection Improv. at Ray Road and Dobson Road
tbd
tbd
Study complete.  Design to begin Winter 2023.
Grant funds & local funds
$11.85
ST2112, Alley Rehab PM10 Dust Emissions Reduction 2 (FMA Areas 16, 25,
39, and 40)
Premier / Olsson
tbd
Design in progress. Construction scheduled for 
Spring 2024
Federal funds
$2.4 (tbc)
ST2110, Chandler Video Detection Cameras 
Y.S. Mantri & Assoc.
tbd
Construction underway.  Completion scheduled for 
Winter 2023.
Federally Funded
$1.7(tbc)
ST2209,  Chandler Local Detection and Communication Systems (Replaces 
existing video detecting cameras with new video cameras)
Kimley-Horn and 
Associates
tbd
Construction in Progress.  
Federally Funded
$0.50 
ST2210, Chandler ICM Detection and Communication Systems (Replaces existing 
video detecting cameras near freeways with new video cameras)
Kimley-Horn and 
Associates
tbd
Construction in Progress.
Federally Funded
$0.60 
ST2301  Armstrong Way and Hamilton Street Improvement (Improves the south 
half of Armstrong Way and the west half of Hamilton Street)
EPS Group, Inc.
tbd
Design underway.  Construction tentatively 
scheduled Summer/Fall 2024.
$2.00 
ST2303 Cooper Road - Insight Loop Extension (Connects Cooper Road to Insight 
Way & Emmett Dr intersection)
tbd
tbd
Pre-design completed July 2023, full design 
scheduled for early 2024.  
$9.30 
PEDESTRIAN, BICYCLE, AND TRANSIT PROJECTS
Designer
Contractor
Status
Comments
PROJECT COST 
ESTIMATE
($MILLIONS)
ST2106, Frye Road Protected Bike Lanes [Paseo Trail to San Marcos
Elementary School]
TY Lin
tbd
Study completed by Y2K.  Design complete. 
Construction in Late 2024.
$7.4 Million grant awarded for construction and $650,000
for design.
$10.00
TP2202, Kyrene Branch and Highline Canal Shared Use Paths
Kimley-Horn
tbd
Study completed by Kimley-Horn.  Design 
underway.  Construction in 2024-25.
Federal grants have been awarded to fund study, design
and construction.
$4.50
Ashley and Paseo Trails Connection
Y2K Engineering
tbd
Study completed by Y2K.  Design underway.  
Construction in 2024-25.
Study is federally funded.  Construction and design are locally 
funded.
$1.00
Hunt Highway Bicycle Improvements and Traffic Calming Study
Rick Engineering
tbd
Study underway, to be completed late 2023.
Federally funded study, looking at a potential shared use path or 
separated bike lanes along with recommendations for traffic 
calming between Cooper Rd. and Val Vista Dr.  Study has been 
delayed due to delayed casino opening.
$0.10
Protected Bike Lanes Study
Y2K Engineering
tbd
Study nearing completion, to be finalized Winter 
2023.
Federally funded.  Study will prioritize opportunities to
install protected bike lanes on arterial and collector streets.
$0.10
Chandler Flex
NA
Via
Initial study completed in collaboration with Valley 
Metro.  New study underway, analyzing potential to 
serve the airpark area and other parts of Southeast 
Chandler/ South Gilbert.  Operations began July 11, 
2022
Awarded $2 Million grant for project startup and two years of 
operations.
$2.10
Transportation Project Status - January 2024