BIP FY 2022 NON-STATE DOT DIRECT PLANNING AND CAPITAL GRANT AGREEMENT 
1 of 19
1.
Award No. 
696JJ32340518
2.
Effective Date
See No. 17 Below
3.
Assistance 
Listings No.
20.205
4.
Award To
Maricopa County
2901 West Durango Street
Phoenix, AZ 85009-6398
Unique Entity Id.: YC11KWJKWM97
TIN No.: 86-6000472
5.
Sponsoring Office
U.S. Department of Transportation
Federal Highway Administration
Office of Acquisition & Grants Management
1200 New Jersey Avenue, SE
HCFA-32, Mail Drop E62-204
Washington, DC 20590
6.
Period of Performance
Effective Date of Award – April 30, 
2025
7.
Total Amount
Federal Share:
Recipient Share:
Total:
$421,600.00
$105,400.00
$527,000.00
8.
Type of Agreement
Grant
9.
Authority 
Section 11118(a) of the Infrastructure 
Investment and Jobs Act (Pub. L. 117–58, 
November 15, 2021; also referred to as the 
“Bipartisan Infrastructure Law” or “BIL”); 
codified at 23 U.S.C. § 124
10. Procurement Request No.
HSSP230130PR
11. Federal Funds Obligated
$421,600.00
12. Submit Payment Requests To
See Article 13 of the General Terms and 
Conditions.
13. Payment Office
See Article 13 of the General Terms and 
Conditions.
14. Accounting and Appropriations Data
1550558B50.2022.050V17F500.5201000000.41010.61006600 = $421,600.00
15. Description of Project
“Gila River Bridge – Old US80 – Candidate Assessment Report”
RECIPIENT
16. Signature of Person Authorized to Sign
___________________________________
Signature                                                 Date
Name: 
Title: 
FEDERAL HIGHWAY ADMINISTRATION
17. Signature of Agreement Officer
______________________________________
Signature                                                      Date
Name: Hector Santamaria
Title: Agreement Officer

BIP FY 2022 NON-STATE DOT DIRECT PLANNING AND CAPITAL GRANT AGREEMENT 
2 of 19
FEDERAL HIGHWAY ADMINISTRAITON 
GRANT AGREEMENT UNDER THE
FISCAL YEAR 2022 BRIDGE INVESTMENT PROGRAM 
This agreement is between the Federal Highway Administration (the “FHWA”) and the 
Maricopa County Department of Transportation (MCDOT) through Maricopa County (the 
“Recipient”).
This agreement reflects the selection of the Recipient to receive a Bridge Investment 
Program (“BIP”) Grant for the Gila River Bridge – Old US80 – Candidate Assessment Report. 
The Infrastructure Investment and Jobs Act, Pub. L. No. 117-58 (Nov. 15, 2021), authorized and 
appropriated funds to the FHWA for fiscal year 2022. The funds are available to carry out the 
BIP under 23 U.S.C. 124 by providing assistance to improve bridge condition and the safety, 
efficiency, and reliability of the movement of people and freight over bridges. 
If schedule A to this agreement identifies a Designated Subrecipient, that Designated 
Subrecipient is also a party to this agreement, and the parties want the Designated Subrecipient 
to carry out the project with the Recipient’s assistance and oversight.
The parties therefore agree to the following:
ARTICLE 1
GENERAL TERMS AND CONDITIONS.
1.1
General Terms and Conditions.
(a) In this agreement, “General Terms and Conditions” means the content of the document 
titled “General Terms and Conditions Under the Fiscal Year 2022 Bridge Investment 
Program (BIP) Grant Program” dated January 31, 2023, which is available at 
https://www.fhwa.dot.gov/bridge/bip/FY_2022_BIP_Terms_and_Conditions.pdf . The 
General Terms and Conditions reference the information contained in the schedules A - J 
to this agreement. The General Terms and Conditions are part of this agreement.
(b) The Recipient states that it has knowledge of the General Terms and Conditions.
(c) The Recipient acknowledges that the General Terms and Conditions impose obligations 
on the Recipient and that the Recipient’s non-compliance with the General Terms and 
Conditions may result in remedial action which may include but is not limited to 
terminating the BIP grant, disallowing costs incurred for the Project, requiring the 
Recipient to refund to the FHWA the BIP Grant, and reporting the non-compliance in the 
Federal-government-wide integrity and performance system.

BIP FY 2022 NON-STATE DOT DIRECT PLANNING AND CAPITAL GRANT AGREEMENT 
3 of 19
ARTICLE 2
SPECIAL TERMS AND CONDITIONS.
There are no special terms for this award.

BIP FY 2022 NON-STATE DOT DIRECT PLANNING AND CAPITAL GRANT AGREEMENT 
4 of 19
SCHEDULE A
ADMINISTRATIVE INFORMATION
1.
Application.
Application Title:
Gila River Bridge – Old US80 – Candidate Assessment Report
Application Date:
July 25, 2022
2.
Recipient’s Unique Entity Identifier.
See section 24.3 of the General Terms and Conditions.
3.
Recipient Contact(s).
Denise Lacey
Systems Planning Branch Manager
Engineering Division
Maricopa County Department of Transportation (MCDOT)
2901 West Durango Street
Phoenix, AZ 85009
O: 602.506.6172 ▪ C: 602.359.5393
Denise.Lacey@maricopa.gov
4.
Recipient Key Personnel.
Name
Title or Position
Kimberly Richards
Intergovernmental Coordinator
5.
FHWA Project Contact(s).
Hector Santamaria
Agreement Officer (AO)
Federal Highway Administration
Office of Acquisition and Grants Management
HCFA-33, Mail Stop E62-310
1200 New Jersey Avenue, S.E. 
Washington, DC 20590
202-493-3811
Hector.Santamaria@dot.gov
and
Angela A. Jones
Agreement Specialist (AS)
Office of Acquisition and Grants Management

BIP FY 2022 NON-STATE DOT DIRECT PLANNING AND CAPITAL GRANT AGREEMENT 
5 of 19
HCFA-33, Mail Stop E62-204
1200 New Jersey Avenue, S.E. 
Washington, DC 20590
202-366-4255
Angela.Jones@dot.gov
and
Chad Matty
Agreement Officer Representative (AOR)
Bridge Engineer
Arizona Division
4000 North Central Avenue
Suite 1500 
602-382-8968
chad.matty@dot.gov
6.
Payment System.
USDOT Payment System:
DELPHI eInvoicing
7.
Office for Subaward and Contract Authorization.
USDOT Office for Subaward and Contract Authorization: FHWA Office of Acquisition 
and Grants Management
8.
Federal Award Identification Number.
See section 24.2 of the General Terms and Conditions.
9.
Designated Subrecipient.
Designated Subrecipient:
None
10.
Subawards and Contracts.
Note: See 2 CFR § 200.331, Subrecipient and contractor determinations, for definitions of 
subrecipient (who is awarded a subaward) versus contractor (who is awarded a contract). 
Note: Recipients with a procurement system deemed approved and accepted by the Government 
or by the AO are exempt from the requirements of this clause. See 2 CFR 200.317 through 
200.327. 
(a)
Unless described in the application and funded in the approved award, the Recipient must  
obtain prior written approval from the Agreement Officer (the “AO”) for the subaward, 
transfer, or contracting out of any BIP Planning Grant work under this agreement above 
the Simplified Acquisition Threshold. This provision does not apply to the acquisition of 
supplies, material, equipment, or general support services.

BIP FY 2022 NON-STATE DOT DIRECT PLANNING AND CAPITAL GRANT AGREEMENT 
6 of 19
(b)
Approval of each subaward or contract is contingent upon the Recipient’s submittal of a 
written fair and reasonable price determination, and approval by the AO for each proposed 
contractor/sub-recipient. Consent to enter into subawards or contracts will be issued 
through written notification from the AO or a formal amendment to the Agreement.
(c)
The following subawards and contracts are currently approved under the Agreement by the 
AO. This list does not include supplies, material, equipment, or general support services 
which are exempt from the pre-approval requirements of this clause. 
No subawards or contracts have been approved.

BIP FY 2022 NON-STATE DOT DIRECT PLANNING AND CAPITAL GRANT AGREEMENT 
7 of 19
SCHEDULE B
PROJECT ACTIVITIES
1.
General Project Description.
Refer to the application title and date identified in schedule A section 1, which is 
incorporated by reference to this agreement. 
2.
Statement of Work.
Refer to the application title and date identified in schedule A section 1, which is 
incorporated by reference to this agreement.
To support a Candidate Assessment Report (CAR) in order to determine exactly where to 
place a new bridge structure including improvements to the approach roadway, including 
any additional transportation features to accommodate and protect existing utilities, 
waterways and environmental resources. With a modern bridge structure additional 
economic activity is anticipated as the transport of goods would cost less in both time and 
miles traveled.

BIP FY 2022 NON-STATE DOT DIRECT PLANNING AND CAPITAL GRANT AGREEMENT 
8 of 19
SCHEDULE C
AWARD DATES AND PROJECT SCHEDULE
1.
Award Dates.
Budget Period End Date:
April 30, 2025
Period of Performance End Date:
See section 4.5 of the General Terms and 
Conditions
2.
Estimated Project Schedule.
Milestone
Schedule Date
Planned Project Completion Date:
March 30, 2025
3.
Special Milestone Deadlines.
Critical Milestone for Environmental and Environmental Justice Review will be August 
2028. 
None.

BIP FY 2022 NON-STATE DOT DIRECT PLANNING AND CAPITAL GRANT AGREEMENT 
9 of 19
SCHEDULE D
AWARD AND PROJECT FINANCIAL INFORMATION
1.
Award Amount.
BIP Grant Amount:
$421,600.00
2.
Federal Obligation Information.
Federal Obligation Type:
Single
3.
Approved Project Budget.
Eligible Project Costs
Total
BIP Grant Funds:
$421,600.00
Other Federal Funds:
 $0.00
 State Funds: 
$0.00
Local Funds:
$105,400.00
In-Kind Match:
$0.00
Other Funds: 
$0.00
Total:
$527,000.00
4.
Cost Classification Table
Cost Element
Federal Share
Non-Federal Share
Total Budget 
Amount
Direct Labor
$0.00
$0.00
$0.00
Fringe Benefits
$0.00
$0.00
$0.00
Travel
$0.00
$0.00
$0.00
Equipment
$0.00
$0.00
$0.00
Supplies
$0.00
$0.00
$0.00
Contractual/Consultant
$421,600.00
$105,400.00
$527,000.00
Other
$0.00
$0.00
$0.00
Indirect Costs
$0.00
$0.00
$0.00
Total Budget
$0.00
$0.00
$0.00
5.
Approved Pre-award Costs
None. The FHWA has not approved under this award any pre-award costs under 2 C.F.R. 
200.458.

BIP FY 2022 NON-STATE DOT DIRECT PLANNING AND CAPITAL GRANT AGREEMENT 
10 of 19
SCHEDULE E
CHANGES FROM APPLICATION
INSTRUCTIONS FOR COMPLETING SCHEDULE E: Describe all material differences 
between the scope, schedule, and budget described in the application and this agreement.  The 
purpose of this schedule E is to clearly and accurately document the differences in scope, 
schedule, and budget to establish the parties’ knowledge and acceptance of those differences. If 
there are notable changes in aspects of the Project other than scope, schedule, and budget (e.g., 
recipient changes), those changes should also be described. See section 3.1 of the General Terms 
and Conditions.
Scope: No changes.
Schedule: NTP pushed from March 2023 to January 2024. Project duration remains unchanged. 
Schedule change is due to delay in receiving official notification of award.  Procurement for 
Consultant cannot begin until agreement is in place.  Project duration will take the identified 
timeframe once NTP is given.
Budget: No changes.
The table below provides a summary comparison of the Project budget.
Application
Schedule D
Fund Source
$
%
$
%
Previously Incurred Costs
Federal Funds
Non-Federal Funds
Total Previously Incurred Costs
Future Eligible Project Costs
BIP Funds
421,600
80
421,600
80
Other Federal Funds
Non-Federal Funds
105,000
20
105,000
20
Total Future Eligible Project 
Costs
527,000
527,000
Total Project Costs
527,000
527,000
Other:

BIP FY 2022 NON-STATE DOT DIRECT PLANNING AND CAPITAL GRANT AGREEMENT 
11 of 19
SCHEDULE F
BIP PROGRAM DESIGNATIONS
1.
Urban or Rural Designation.
Urban-Rural Designation:
Rural
2.
Historically Disadvantaged Community or Area of Persistent Poverty Designation.
HDC or APP Designation:
[No]
3.
Funding Source.
Funding Source:
General Fund 
4.
Reserved.
5.
Reserved.
6.
Security Risk Designation.
Security Risk Designation:
Low
7.
Capital or Planning Designation.
Capital-Planning Designation:   Planning
8.
Funding Act.
Infrastructure Investment and Jobs Act (Pub. L. 117–58, November 15, 2021):
Highway Trust Funds (IIJA § 11101(b)(1)(A)); and
Highway Infrastructure Program (HIP) General Funds (IIJA, division J, title VIII, 
HIP heading, paragraph (4)).  
9.
Funds Obligation. 
Obligation Deadline:  September 30, 2025, for all sources of FY 2022 BIP funds. 
10.
Cancellation Date. 
Highway Trust Funds: Available until expended
IIJA/BIP General Funds: September 30, 2030

BIP FY 2022 NON-STATE DOT DIRECT PLANNING AND CAPITAL GRANT AGREEMENT 
12 of 19
SCHEDULE G
BIP PERFORMANCE MEASUREMENT INFORMATION
Study Area: The Maricopa Association of Governments (MAG, a metropolitan planning 
organization) has determined a need for a new modern bridge that is able to safely and efficiently 
accommodate the future traffic volumes of the planned Hidden Waters Parkway. The bridge in 
its existing state is structurally-deficient and functionally-obsolete. The structural evaluation 
appraisal, deck geometry appraisal, and approach alignment appraisal are all identified as 
“Intolerable” and replacement is a “high priority” (please see attached NBI Datasheet). In 2010, 
MCDOT completed a parkway feasibility study on the Old US 80 corridor. This planning project 
is a major step towards the Maricopa County Department of Transportation (MCDOT) replacing 
a structurally-deficient and functionally-obsolete bridge over the Gila River in rural Maricopa 
County, Arizona. If this project is awarded BIP Planning Funds then MCDOT will hire a 
consultant team to conduct a Candidate Assessment Report (CAR).
Baseline Measurement Date:
March 2024
Baseline Report Date:
May 2024 
Table 1: Performance Measure Table
Measure
Category and Description
Measurement 
Frequency
Planning Grant
Project eligible to apply for a Large 
Bridge or Bridge grant.
Whether the BIP Planning grant for 
planning, feasibility analysis, and or 
revenue forecasting is associated with the 
development of a project eligible to apply 
for a BIP Large Bridge or Bridge grant.
Annual

BIP FY 2022 NON-STATE DOT DIRECT PLANNING AND CAPITAL GRANT AGREEMENT 
13 of 19
SCHEDULE H
CLIMATE CHANGE AND ENVIRONMENTAL JUSTICE IMPACTS
1.
Consideration of Climate Change and Environmental Justice Impacts.
The Recipient states that rows marked with “X” in the following table are accurate:
The Project directly supports a Local/Regional/State Climate Action Plan that 
results in lower greenhouse gas emissions. (Identify the plan in the supporting 
narrative below.)
The Project directly supports a Local/Regional/State Equitable Development 
Plan that results in lower greenhouse gas emissions. (Identify the plan in the 
supporting narrative below.)
The Project directly supports a Local/Regional/State Energy Baseline Study 
that results in lower greenhouse gas emissions. (Identify the plan in the 
supporting narrative below.)
The Recipient or a project partner used environmental justice tools, such as the 
EJSCREEN, to minimize adverse impacts of the Project on environmental 
justice communities. (Identify the tool(s) in the supporting narrative below.)
The Project supports a modal shift in freight or passenger movement to reduce 
emissions or reduce induced travel demand. (Describe that shift in the 
supporting narrative below.)
The Project utilizes demand management strategies to reduce congestion, 
induced travel demand, and greenhouse gas emissions. (Describe those 
strategies in the supporting narrative below.)
The Project incorporates electrification infrastructure, zero-emission vehicle 
infrastructure, or both. (Describe the incorporated infrastructure in the 
supporting narrative below.)
The Project supports the installation of electric vehicle charging stations. 
(Describe that support in the supporting narrative below.)
The Project promotes energy efficiency. (Describe how in the supporting 
narrative below.)
The Project serves the renewable energy supply chain. (Describe how in the 
supporting narrative below.)
The Project improves disaster preparedness and resiliency (Describe how in the 
supporting narrative below.)

BIP FY 2022 NON-STATE DOT DIRECT PLANNING AND CAPITAL GRANT AGREEMENT 
14 of 19
The Project avoids adverse environmental impacts to air or water quality, 
wetlands, and endangered species, such as through reduction in Clean Air Act 
criteria pollutants and greenhouse gases, improved stormwater management, or 
improved habitat connectivity. (Describe how in the supporting narrative 
below.)
The Project repairs existing dilapidated or idle infrastructure that is currently 
causing environmental harm. (Describe that infrastructure in the supporting 
narrative below.)
The Project supports or incorporates the construction of energy- and location-
efficient buildings. (Describe how in the supporting narrative below.)
The Project includes recycling of materials, use of materials known to reduce 
or reverse carbon emissions, or both. (Describe the materials in the supporting 
narrative below.)
The Recipient has taken other actions to consider climate change and 
environmental justice impacts of the Project. (Describe those actions in the 
supporting narrative below.)
X
The Recipient has not yet taken actions to consider climate change and 
environmental justice impacts of the Project but, before beginning construction 
of the Project, will take relevant actions described in schedule B. (Identify the 
relevant actions from schedule B in the supporting narrative below.)  
X
The Recipient has not taken actions to consider climate change and 
environmental justice impacts of the Project and will not take those actions 
under this award.
2.
Supporting Narrative.
A Candidate Assessment Report (CAR) is needed to determine the location of the new 
bridge and associated improvements.  Upon completion of the CAR, MCDOT will begin 
the environmental review, including the environmental justice review and permitting 
process in addition to preliminary engineering (30% design).  Ultimately, MCDOT 
intends to request BIP Bridge Project funds to assist in the funding of a new high-
capacity bridge over the Gila River once all pre-construction activities are completed.

BIP FY 2022 NON-STATE DOT DIRECT PLANNING AND CAPITAL GRANT AGREEMENT 
15 of 19
SCHEDULE I
RACIAL EQUITY AND BARRIERS TO OPPORTUNITY
1.
Efforts to Improve Racial Equity and Reduce Barriers to Opportunity.
The Recipient states that rows marked with “X” in the following table are accurate:
A racial equity impact analysis has been completed for the Project. (Identify a 
report on that analysis or, if no report was produced, describe the analysis and 
its results in the supporting narrative below.)
The Recipient or a project partner has adopted an equity and inclusion 
program/plan or has otherwise instituted equity-focused policies related to 
project procurement, material sourcing, construction, inspection, hiring, or 
other activities designed to ensure racial equity in the overall delivery and 
implementation of the Project. (Identify the relevant programs, plans, or 
policies in the supporting narrative below.)
The Project includes physical-barrier-mitigating land bridges, caps, lids, linear 
parks, and multimodal mobility investments that either redress past barriers to 
opportunity or that proactively create new connections and opportunities for 
underserved communities that are underserved by transportation. (Identify the 
relevant investments in the supporting narrative below.)
The Project includes new or improved walking, biking, and rolling access for 
individuals with disabilities, especially access that reverses the disproportional 
impacts of crashes on people of color and mitigates neighborhood bifurcation. 
(Identify the new or improved access in the supporting narrative below.)
The Project includes new or improved freight access to underserved 
communities to increase access to goods and job opportunities for those 
underserved communities. (Identify the new or improved access in the 
supporting narrative below.)
The Recipient has taken other actions related to the Project to improve racial 
equity and reduce barriers to opportunity. (Describe those actions in the 
supporting narrative below.)
X
The Recipient has not yet taken actions related to the Project to improve racial 
equity and reduce barriers to opportunity but, before beginning construction of 
the Project, will take relevant actions described in schedule B. (Identify the 
relevant actions from schedule B in the supporting narrative below.)  
X
The Recipient has not taken actions related to the Project to improve racial 
equity and reduce barriers to opportunity and will not take those actions under 
this award.

BIP FY 2022 NON-STATE DOT DIRECT PLANNING AND CAPITAL GRANT AGREEMENT 
16 of 19
2.
Supporting Narrative.
The Planning Level Study, as well as any future Design efforts, will incorporate Title VI 
requirements in Consultant Selection, Public Engagement and all methods per the 
Maricopa County Department of Transportation Title VI Non-Discrimination Plan.
This will be accomplished through Title VI analysis of the area to 

minimize impact to protected classes,

public outreach/educational materials in languages other than English where need 
is identified,

Public Engagement through Public Open Houses/Virtual Meetings/Flyers/Surveys

Any other action identified as needed to meet the needs documented in the Title 
VI analysis.

BIP FY 2022 NON-STATE DOT DIRECT PLANNING AND CAPITAL GRANT AGREEMENT 
17 of 19
SCHEDULE J
LABOR AND WORK
1.
Efforts to Support Good-Paying Jobs and Strong Labor Standards
The Recipient states that rows marked with “X” in the following table are accurate:
The Recipient or a project partner has adopted the use of project labor 
agreements in the overall delivery and implementation of the Project. (Identify 
the relevant agreements and describe the scope of activities they cover in the 
supporting narrative below.)
The Recipient or a project partner has adopted the use of local and economic 
hiring preferences in the overall delivery and implementation of the Project, 
subject to all applicable State and local laws, policies, and procedures. 
(Describe the relevant provisions in the supporting narrative below.)
The Recipient or a project partner has adopted the use of registered 
apprenticeships in the overall delivery and implementation of the Project. 
(Describe the use of registered apprenticeship in the supporting narrative 
below.)
The Recipient or a project partner will provide training and placement 
programs for underrepresented workers in the overall delivery and 
implementation of the Project. (Describe the training programs in the 
supporting narrative below.)
The Recipient or a project partner will support free and fair choice to join a 
union in the overall delivery and implementation of the Project by investing in 
workforce development services offered by labor-management training 
partnerships or setting expectations for contractors to develop labor-management 
training programs. (Describe the workforce development services offered by 
labor-management training partnerships in the supporting narrative below.)
The Recipient or a project partner will provide supportive services and cash 
assistance to address systemic barriers to employment to be able to participate 
and thrive in training and employment, including childcare, emergency cash 
assistance for items such as tools, work clothing, application fees and other 
costs of apprenticeship or required pre-employment training, transportation and 
travel to training and work sites, and services aimed at helping to retain 
underrepresented groups like mentoring, support groups, and peer networking. 
(Describe the supportive services and/or cash assistance provided to trainees 
and employees in the supporting narrative below.)

BIP FY 2022 NON-STATE DOT DIRECT PLANNING AND CAPITAL GRANT AGREEMENT 
18 of 19
The Recipient or a project partner has documented agreements or ordinances in 
place to hire from certain workforce programs that serve underrepresented 
groups. (Identify the relevant agreements and describe the scope of activities 
they cover in the supporting narrative below.) 
X
The Recipient or a project partner participates in a State/Regional/Local 
comprehensive plan to promote equal opportunity, including removing barriers 
to hire and preventing harassment on work sites, and that plan demonstrates 
action to create an inclusive environment with a commitment to equal 
opportunity, including:
a.
affirmative efforts to remove barriers to equal employment 
opportunity above and beyond complying with Federal law;
b. proactive partnerships with the U.S. Department of Labor’s Office 
of Federal Contract Compliance Programs to promote compliance 
with EO 11246 Equal Employment Opportunity requirements;
c.
no discriminatory use of criminal background screens and 
affirmative steps to recruit and include those with former justice 
involvement, in accordance with the Fair Chance Act and equal 
opportunity requirements;
d. efforts to prevent harassment based on race, color, religion, sex, 
sexual orientation, gender identity, and national origin;
e.
training on anti-harassment and third-party reporting procedures 
covering employees and contractors; and
f.
maintaining robust anti-retaliation measures covering employees 
and contractors.
(Describe the equal opportunity plan in the supporting narrative below.)
The Recipient has taken other actions related to the Project to create good-
paying jobs with the free and fair choice to join a union and incorporate strong 
labor standards. (Describe those actions in the supporting narrative below.)
X
The Recipient has not yet taken actions related to the Project to create good-
paying jobs with the free and fair choice to join a union and incorporate strong 
labor standards but, before beginning construction of the Project, will take 
relevant actions described in schedule B. (Identify the relevant actions from 
schedule B in the supporting narrative below.)  
X
The Recipient has not taken actions related to the Project to improving good-
paying jobs and strong labor standards and will not take those actions under 
this award.
2.
Supporting Narrative.
The Planning Level Study, as well as any future Design efforts, will comply with all 
Federal, State, and local laws, local ordinance, and regulation including FHWA 1273 and 
Arizona Revised Statute § 41-4401. See summary that follows.

BIP FY 2022 NON-STATE DOT DIRECT PLANNING AND CAPITAL GRANT AGREEMENT 
19 of 19
MCDOT will comply with FHWA 1273 specification requirements that wages, working 
conditions, and employee benefits shall be established and administered, and personnel 
actions of every type, including hiring, upgrading, promotion, transfer, demotion, layoff, 
and termination, shall be taken without regard to race, color, religion, sex, sexual 
orientation, gender identity, national origin, age or disability. This will include periodic 
inspection requires as outlines in parts 1 through d.
In addition, Consultants must warrant that they are in compliance with Arizona Revised 
Statue 41-4401 with includes:
(1)
CONSULTANT and its subconsultants, if any, warrant their compliance with all 
federal immigration laws and regulations that relate to their employees and their 
compliance with A.R.S. §23-214, subsection A;
(2)
That a breach of a warranty under subsection 1 above, shall be deemed a material 
breach of the contract that is subject to penalties up to and including termination of 
the contracts;
(3)
That the contracting government entity retains the legal right to inspect the papers 
of any CONSULTANT or subconsultant employee who works on the contract to 
ensure that the CONSULTANT or subconsultant is complying with the warranty 
provided under subsection 1 above and that the CONSULTANT agrees to make 
all papers and employment records of said employee(s) available during normal 
working hours in order to facilitate such an inspection.