FY 2024-25 Budget Workshop #3 Presentation

City of Chandler — Special (2024-03-21)

View PDF Meeting page

Extracted text (via pymupdf) 12523 characters
FY 2024-25 Budget Workshop #3 CIP
City Council Conference Room 
Thursday, March 21, 2024 | 4:00 pm

Making it Happen
Our Brand
A safe, diverse, equitable and inclusive 
community that connects people, chooses 
innovation and inspires excellence
FY 2024-25 Budget Theme

01.
Overview of 
Proposed
 10-Year Capital 
Improvement 
Program (CIP)
04.
Key Budget 
Dates and 
Questions
02.
Chandler Water 
and Wastewater 
Utilities – Major 
Projects and 
Rates
03.
Review List of 
Projects in 
Proposed
 10-Year Capital 
Improvement 
Program (CIP)
Agenda

New Fiscal Year 2024-25 starts 7/1/2024
“Making it Happen”
Council/Resident Process
Staff Process
Chandler Budget Process Timeline

Strategic Framework Guides 
Our Decision Making
Focus Areas 
•Economic Vitality
•Innovation and Technology
•Mobility
•Neighborhoods
•Quality of Life
•Good Governance

Proposed 10-Year
Capital Improvement
Program (CIP)

Fiscal Foundations –
Current 10-Year CIP Council Guidelines
• Minimize increase in property taxes
• Maintain, enhance, or re-imagine existing infrastructure
• Finish planned construction of streets, parks, fiber and 
utility systems
• Prior to adding capital, ensure related ongoing O&M can 
be supported
• Utilize master plans to guide long-term capital 
investment
• Deliver on commitments made to residents through 2021 
bond election
• Balance inflation, workload, and timely completion of 
high-visibility and grant-funded projects

Priorities for One-Time Dollars
1. Reinvest in existing aging 
infrastructure, neighborhoods & 
systems and projects that generate 
ongoing savings
4. New initiatives and capital, 
including sustainability
3. Maintain reserves sufficient to 
meet financial policies
2. Operating and capital 
spending to advance 
Strategic Framework goals 
Paid down large unfunded PSPRS liability to generate ongoing savings 
and continue to maintain payoff status

Summary of City-wide Core Infrastructure
Focus on improving overall quality in rising cost environment

10-Year CIP Overview
•
2025-2034 CIP total is $2,493,804,031 
($529.8M more than the 2024-2033 CIP) 
•
Updated to reflect continued 
inflationary pressures
•
Continued focus on aging infrastructure
•
Includes $299M in key aging 
infrastructure projects for water and 
wastewater 
•
Additional capacity was gained from 
secondary levy growth higher than 
anticipated (+5.3% versus +4%)

10-Year CIP Comparison by Department

Current 10-Year and Next 10-Year CIP 
Comparison –
• Continued planned project cost increases have taken a toll on how and 
when projects are funded
• Example projects with significant increases or new (all funds)
• Airport Hangar Pavement Reconstruction +$10.5M, Rehabilitate Runway 4R/22L 
Pavement +$6.3M
• Traffic Management Center Rehabilitation +$5.6M
• Fire Station #4 Rebuild +$7.3M, Fire Station #12 +$4.9M
• IT Projects including Financial/HR system replacement +$6.5M
• Sustainability (Solar Capital Investment, produces ongoing savings) +$15M
• Mesquite Groves Park +$19.4, Tumbleweed Multi-Gen +$7.1M
• Police Forensic Facility +$15.8M, Main Station Renovations +$7.8M
• Kyrene Rd (Chandler Blvd to 202) +$13.6M
• Price Rd/Queen Creek Intersection +$19.3M
• New- McQueen Rd (Warner to Pecos) $84.9M
• Frye Rd. Protected Bike Lane +$7.8M
• Santan Freeway 66” Sewer line +$40M, Wastewater Capacity Increases +$16.8M
• Main and Valve Replacement +$105M, Production Facility Improvements +$49M

10-Year CIP by Focus Area

GO Bond Authorization History
Need for Bond Election
Bond Authorization usage higher than anticipated and will be exhausted by FY 2025-26 for Parks, Streets and Police, 
and  FY 2029-30 for Fire.  Bond Election needed by Fall of 2025 to continue capital program in these areas.

GO Bond Authorization Project Drivers
Parks 
Streets/Transportation  
Increases as high as +30% to +50% in Capital Project costs 
4 Diamond 
Fields
$22.3M + 
Ryan Rd 
5.9M 
Pickleball
$6.6M 
(12 to 18 courts) 
& 3 Tennis 
Cts/Lights 
$2M
Cooper/
Insight Loop
$13.5M
Price/Queen 
Creek 
Intersection
$19.3M (Beg. 
FY 2025-26)
Alma School 
(Germann to QC) 
$10.1M
Cost Changes 
since 2021 
Arterial +19.2%
Intersect. +19.1%
Collectors +21.4%
Public Safety Police
Public Safety Fire
Forensic 
Facility
$64.8M
(incl $9.1 GF)
Station 2 
Rebuild
$10.7M 
(+$1.4M GF)
Station 4 
Rebuild
+$16.8M (beg. 
FY 2028-29)
Regional Park Development Auth $18,074,000, now $61.5M
Multi-Gen 
Expansion
$14.8M 
(gym 
delayed)
Forensic Facility Auth $38,325,000
Fire Stations Auth $15,670,000
Streets Auth $10.9M, now $42.9M
Mesquite 
Groves Ph 1
$10M
 (SDF  
shortfall)

GO Bond Projects 
Additional Bond Authorization Needs 
Parks 
Mesquite Groves Phase II (portion) and III*
AJ Chandler Park Renovation*
Existing Community and Neighborhood Park Improvements*
Folley Pool/Park Renovation*
Tumbleweed gymnasium expansion
Streets/Transportation  
Street Repaving*
Traffic Signal Additions and Repairs*
Kyrene Rd (Chandler Blvd. to Santan 202) (portion)*
Price Rd. Queen Creek Intersection*
McQueen Rd (Warner to Pecos)*
Washington Street Improvements*
Note: Additional projects if Prop 400 does not pass
Public Safety Fire
Fire Station 4 Rebuild (portion)*
Fire Station 12
* = projects included in bond election, but additional bond authorization needed to complete
Public Safety Police
Police Main Station and Criminal Investigation 
Bureau (CIB)/Communications Renovations *
Fire Station #4

Chandler
Water and  
Wastewater Utilities: 
Major Projects and Rates

Utility Rates 
Initial adjustments were made in current 
Fiscal Year to start to be able to address 
additional infrastructure projects
Anticipated rates as shared in FY 2023-24

Major Drivers - Aging infrastructure
Water
•
Total mains 1,228 miles
•
31 operating wells
•
Reactive replacements based on breaks, 
proactive replacements based on risk 
assessment
Wastewater
•
958 miles of sanitary sewer lines
•
19,000 manholes 7,000 need repair
•
Proactive replacements based on physical 
inspections
Decade in which underground infrastructure established

Water and Wastewater Operational Needs
Operating impacts, on top of major projects and debt service, are driving 
revenue requirement increase for Water and Wastewater Utilities
Water
•
Granulated Activated Carbon (GAC) costs +$500k
•
Powdered Activated Carbon (PAC) costs +$2M
•
Increased surface water costs +$1.6M
Wastewater
•
Ocotillo Brine Reduction +$2.3M (revenue offset)
•
Reclaimed Water Interconnect Facility +$877k (revenue offset)
•
Reclaimed Water Utilities Increase +$200k
•
Increased baseline testing costs for WW +$150k

Water Infrastructure

New Infrastructure – Pecos Water Plant 
Improvements
A total of $222M is 
being proposed in the 
new CIP for 
improvements to Water 
Facilities

Aging Infrastructure – 48” Transmission Line
Design was included in 
current CIP of $17.7M 
and proposed CIP has 
the construction of an 
additional $134.5M for 
$152M total
Adds redundancy for this 
single point of failure
Allows for eventual rehab 
on original transmission 
main
Seeking Congressionally 
Designated Funding for 
at least a portion of this 
project

Aging Infrastructure – Water Production Facilities
The use and maintenance of 
ground wells is critical to 
Chandler’s water portfolio
Booster station failures have 
become more of an issue, and 
the cost for rehabilitation is 
higher if earlier remediation is 
not done
Average age of these remote 
facilities is 24-years with the 
newest being 4-years and the 
oldest 40-years

Aging Infrastructure – Watermains
Recommended replacement plan would 
start out averaging 3-5 miles per year, 
escalating to 7.5 miles per year over the 
next 30 years to address all at risk lines. 
Coordination with other projects is vital.
Plan would address these areas

Aging Infrastructure – Water Mains
Water Main Replacement Scenarios
•
20-Year spread average 1% replacement/year covers all moderate to high risk
•
Effect on rates over next five years:
•
30-Year spread (recommended) average 0.6% replacement/year covers all moderate to high risk
•
Effect on rates over next five years:

Water Rate Driver Comparison
Each 1% rate change equates to about $580,000 in revenue
This year’s operating increase is about $3.3M ongoing (5.7% rate increase to fully fund)
This year’s personnel increase is about $400k ongoing (0.7% rate increase to fully fund)

Wastewater Rates

Large Project in current CIP 66” Wastewater pipe
$40.6M: 
Design in FY 
2024-25 and 
Construction 
in FY 2025-26

Aging Infrastructure – Wastewater Mains/Manholes
Recommended replacement plan would 
start out averaging 90-120 manholes per 
year, escalating to 350 per year over the 
next 30 years to address all 7,000 
manholes that have known issues
Plan would 
address these 
areas

Aging Infrastructure – Wastewater Mains/Manholes
Wastewater Scenarios
•
20-Year spread covers all 7,000 moderate and major rehabs needed
•
Effect on rates:
•
30-Year spread (recommended) covers all 7,000 moderate and major rehabs needed 
•
Effect on rates:

Wastewater Rate Driver Comparison
Each 1% rate change equates to about $460,000 in revenue
This year’s operating increase is about $1M ongoing (2.2% rate increase to fully fund)
No new personnel planned in FY 2024-25

Proposed 5-Year Enterprise Fund Balance Projections

City Residential Rate Comparison
Estimated based on Tempe Cost of Service July 2023 results at 10,000 gallons single family residential rates for FY 2023-24 
plus known Water and Wastewater increases across all Cities
Would be 
effective 
January 2026

Cost of Services Allocations – Water / Wastewater
COS rate allocations: 
 
Water 8.5% increase                         
Residential                   3.7%   
Multifamily                  2.5% 
Non-Residential        11.4%
Landscape                 13.7%  
Industrial                   21.3%
Wastewater 8% Increase
Residential                   0.0%
Multifamily                 18.8% 
Non-Residential         14.8%
Multifamily Average Bill Impact
Non-Residential Average Bill Impact

Review List of Projects in 
the Proposed 10-year 
Capital Improvement 
Program (CIP)

Summary of Proposed Key General Government 
Capital Projects in the 1st 5-Years
Technology
•
ERP Modernization/Replacement
Fire
•
Emergency Vehicle Replacements
•
Self Contained Breathing Apparatus Replacements
•
Station #4 Rebuild Design
Police
•
Forensic Services Facility
•
Police Main Stations Renovations
Street/Transportation Projects  
•
Street Repaving Program ($116.7M in first 5-years)
•
Washington Street Improvements
•
Alma School Rd (Germann Rd to Queen Creek Rd)
•
Kyrene Road (Chandler Blvd to San Tan 202)
•
Ray Road/Dobson Road Intersection Improvement
•
Turf to Xeriscape Program
•
Frye Rd Protected Bike Lanes
•
Paseo Trail Crossing Improvements
•
Kyrene  Branch and Highline Canal Shared Use Path
Airport
•
Hanger Area Pavement Reconstruction
•
Runway 4R/22L Extension
Buildings & Facilities
•
Building Renovations and Repairs 
•
Space Utilization Improvements
Community/Regional Park Improvements
•
Tumbleweed Regional Park Expansion
•
A.J. Chandler Park Improvements
•
Existing Community and Neighborhood Park Imp
•
Existing Athletic Field Improvements
•
Mesquite Groves Phases I & II
•
Folley Pool Renovation 
•
Lantana Ranch Park Site
•
Tumbleweed Ranch
Development Services
•
Citywide Fiber Upgrades
•
Traffic Management Center Upgrades

Summary of Proposed Key General Government 
Capital Projects in the 2nd 5-Years
Fire
•
Station #4 Rebuild Construction
•
Station #12 Design and Construction
Police
•
Police Main Stations Renovations continuation
•
Radio Communication Equipment
Street/Transportation Projects  
•
Street Repaving Program
•
Warner Road (Price Rd. to Arizona Ave.)
•
McQueen Road Improvements
•
Ray Road/Dobson Road Intersection Improvement
•
Ocotillo Road Shared Use Path
Airport
•
Heliport Apron Construction
•
Taxiway B Construction
Buildings & Facilities
•
Building Renovations and Repairs 
Community/Regional Park Improvements
•
Existing Neighborhood Park Improvements
•
Mesquite Groves Phase III
•
Tumbleweed Ranch
Development Services
•
Citywide Fiber Upgrades

Budget Event
Date
Council Budget Kickoff 
Completed
Resident Budget Survey with Council Videos 
Completed
Council Workshop #1
Completed
Council Workshop #2
Completed
Council Workshop #3 Capital Improvement Program
Tonight
All Day Budget Briefing
4/26/2024
Council Meetings
Tentative Adoption
05/23/2024
Public Hearing and Final Adoption 
06/13/2024
Adoption of Tax Levy & Fee Action
06/27/2024
Key Budget 
Dates

Questions?