4.2024 Monthly Construction Report

City of Chandler — Regular Meeting (2024-04-10)

View PDF Meeting page

Extracted text (via pymupdf) 1620 characters
Capital Projects – Design Phase: 
 
Airport Operations Garage: City funded at $1 million.  Programming and conceptual layout 
completed.  Design underway. 
 
Airport Fuel Tank Relocation: City funded at $610,000.  Design for new above ground tank.  Job-
order contract selection underway. 
 
Automated Weather Observation System (AWOS) Replacement:  FAA funding for $200,000.  FAA 
environmental clearance received.  Kick-off meeting 2/21.  100% plans finalized.  Bid closing April 
9th. 
 
Runway End Identifier Light (REIL) Installation Runway 4L-22R– (North Runway)- FAA funding 
for $110,000.  Kick-off meeting 2/21. Plans at 100%.  Bid TBD.  Additional environmental documents 
requested by FAA and submitted. 
 
Runway 4R-22L Rehabilitation (South Runway) — FAA grant for $350,000 for design approved.  
Kick-off meeting 4/6.  90% plan submittal expected April 20th. 
 
Taxiway B Improvements- Phase 1 – ADOT grant for $2,035,000 approved.  Design kick-off 
meeting 10/26.  Survey completed.  30% plans received and environmental catex documents 
underway. 
 
Old Heliport Redevelopment- Proceeding with design contract for $30,805 in local funds for new 
fencing and pavement maintenance/tie-down design.  Kick-off meeting January 4th.  Design 
underway. 
 
Capital Projects - Construction Phase: 
 
Taxiway C Electrical:  Local funding. Addresses immediate issues with electrical infrastructure.  
Cabling repaired and lighting system is functional but needs replacement. Reviewing cost proposal 
from job order contractor. 