Capital Project Funding Bond Election Discussion Presentation
Extracted text (via pymupdf)
10462 characters
Capital Project Funding
Bond Election Discussion
Mayor and Council Work Session
Thursday, June 27, 2024
Agenda
2025-2034 Capital Improvement Plan (CIP)
Deep Dive on Bond & General Funded Projects
Inflation Impacts to Funding Plan
Secondary Property Tax as CIP Funding Source
Supplementing CIP with Alternate CIP Funding Source
Other Valley Cities
Bond Election History and Timelines
Options and Council Direction
Strategic Framework
Capital Needs in All Areas
Focus Areas
•Economic Vitality
•Sustainability and Technology
•Connectivity
•Neighborhoods
•Quality of Life
•Community Safety
2025-2034 Capital Improvement Plan (CIP)
$2,488,884,031
Total 10-year CIP is funded as follows
7%
Grants
68.4%
Bond
Funded
22%
Current
Revenues/
Fund Balance
1.9%
System
Development
Fees
68.4% of 10-Year CIP is Bond Funded
Total 10-year
CIP is
$2,488,884,031
GO Bond Authorization
Bond Authorization usage higher than anticipated and will be exhausted by FY 2025-26 for Police, 2026-27 for Streets
and Parks, and FY 2028-29 for Fire. Additional Bond Authorization needed to continue capital program in these areas.
Type of Voter
Approved Debt
Available
Authorization
After 2021 &
2023 Bond
Sales
Fall 2025
Bond Sale
Remaining
Authorization
Fall 2027
Bond Sale
Remaining
Authorization
Parks/Recreation/
Museum/Arts
52,130,000
$
(40,930,000)
$
11,200,000
$
(54,825,000)
$
(43,625,000)
$
Streets
98,681,000
(72,725,000)
25,956,000
$
(75,625,000)
(49,669,000)
$
Public Safety- Police
55,340,000
(55,340,000)
-
$
(17,000,000)
(17,000,000)
$
Public Safety- Fire
15,181,000
-
15,181,000
$
(3,300,000)
11,881,000
$
Airport
494,000
-
494,000
$
-
494,000
$
Public Buildings
(Facilities)
31,050,000
(7,100,000)
23,950,000
$
(9,000,000)
14,950,000
$
Stormwater
624,000
-
624,000
$
(300,000)
324,000
$
Library
3,680,000
-
3,680,000
$
-
3,680,000
$
Subtotal
257,180,000
$
(176,095,000)
$
81,085,000
$
(160,050,000)
$
(78,965,000)
$
Landfill
4,935,000
-
4,935,000
$
-
4,935,000
$
Public Buildings
9,960,000
(6,000,000)
3,960,000
$
-
3,960,000
$
Water/Wastewater
-
-
-
$
-
-
$
Total
272,075,000
$
(182,095,000)
$
89,980,000
$
(160,050,000)
$
(70,070,000)
$
GO Bonds
cannot be
issued without
residents
authorizing
this first
Deep Dive on GO Bond & General Fund
10-Year CIP Projects
Refer to Handouts
GO Bond Funded Projects ($626M)
•
Summarized by bond category (blue lines)
•
Projects not highlighted will use existing
bond authorization
•
Projects highlighted need additional bond
authorization to complete ($395M)
•
Supports new and existing infrastructure
General Funded Projects
•
Summarized by department/division
•
Supports areas without bond authorization (i.e.
Technology, Fiber, Airport)
•
Higher revenue used to fund bond eligible
projects to extend current bond authorization
o Applied ARPA to some freeing up General Fd
o Higher General Fund revenue (over $60M) is
result of inflation, Intel and other
developments, and shift to 2.5% flat tax in
State Shared
o Typical one-time revenue is $21M to $30M
GO Bond Projects
Project’s Impacted from 2021 Election
Parks
Existing Neighborhood & Community Parks
AJ Chandler Park Renovation
Mesquite Groves Phase II and III
Existing Community and Neighborhood Park Improvements
Folley Pool/Park Renovation
Lantana Ranch park site
Streets/Transportation
Street Repaving*
Traffic Signal Additions and Repairs
Kyrene Rd (Chandler Blvd. to Santan 202) (portion)
Price Rd Queen Creek Intersection
McQueen Rd (Warner to Pecos)
Washington Street Improvements
Ocotillo Rd shared use path
Public Safety Fire
Fire Station 4 Rebuild (portion)
Public Safety Police
Forensic Services Facility
Police Main Station and Criminal Investigation
Bureau (CIB)/Communications Renovations
Fire Station #4
GO Bond Authorization Project Drivers
Parks
Streets/Transportation
Increases as high as +30% to +50% in Capital Project costs
4 Diamond
Fields
$22.3M +
Ryan Rd
5.9M
Pickleball
$6.6M
(12 to 18 courts)
& 3 Tennis
Cts/Lights
$2M
Cooper/
Insight Loop
$13.5M
Price/Queen
Creek
Intersection
$19.3M (Beg.
FY 2025-26)
Alma School
(Germann to QC)
$10.1M
Cost Changes
since 2021
Arterial +19.2%
Intersect. +19.1%
Collectors +21.4%
Public Safety Police
Public Safety Fire
Forensic
Facility
$64.8M
(incl $9.1 GF)
Station 2
Rebuild
$10.7M
(+$1.4M GF)
Station 4
Rebuild
+$16.8M (beg.
FY 2028-29)
Regional Park Development Auth $18,074,000, now $61.5M
Multi-Gen
Expansion
$14.8M
(gym
delayed)
Forensic Facility Auth $38,325,000
Fire Stations Auth $15,670,000
Streets Auth $10.9M, now $42.9M
Mesquite
Groves Ph 1
$10M
(SDF
shortfall)
Inflation’s New Normal
In last 20 years,
only one year
would have
seen project
costs coming
down 0.4%.
Data source: U.S. Bureau of Labor Statistics: All Items in U.S. city average, all urban consumers, not seasonally adjusted.
Construction Price Index New Normal
Construction
Costs continue
to go up, just
not as fast
Data source: The Mortenson Construction Cost Index is calculated quarterly by pricing a representative non-residential
construction project in geographies throughout the country.
CIP Inflation Impact Example
Forensic Facility
$ 30.3M
$ 31.3M
$ 37.8M
$ 32.4M
$ 32.4M
$ 39.1M
$ 33.6M
$ 33.6M
$ 40.4M
$ 34.7M
$ 34.7M
$ 41.8M
$ 35.9M
Should future
partnerships
happen,
authorization
would last longer
for other projects
•Anticipate cost of build to continue to increase
•Project at $55.340M using current bond authorization and $9.1M of
General Fund included in FY 2024-25 and FY 2025-26
•Study anticipates new build since growth of Police Department has
exceeded current Police Admin building
•Options retrofitting existing or building new are both large capital costs
•Partnership options may be available, but size of facility would be larger
with larger savings being on ongoing operations
CIP Inflation Impact Example
Mesquite Groves
Current
Year 1 Shift
Year 2 Shift
Year 3 Shift
Year 4 Shift
Year 5 Shift
Mesquite Groves Park Site Phase I
Mesquite Groves Park Site Phase II
Mesquite Groves Park Site Phase III
$ 35.2M
$ 30.3M
$ 30.3M
$ 36.5M
$ 31.3M
$ 31.3M
$ 37.8M
$ 32.4M
$ 32.4M
$ 39.1M
$ 33.6M
$ 33.6M
$ 40.4M
$ 34.7M
$ 34.7M
$ 41.8M
$ 35.9M
$ 35.9M
$ 95.8M
$ 99.1M
$ 102.6M
$ 106.2M
$ 109.9M
$ 113.7M
Costs
anticipated to
increase each
year under this
new normal
($12M/phase
est. pre-COVID)
Funding the 10-year CIP
Secondary Property Tax Supports GO Bonds
(AAA bond rated = low-cost debt)
Property Tax Rate supporting
current 10-year CIP in Orange
Property Tax Rate supporting
current bond auth only in Blue
Benefits of utilizing Secondary
Property Tax:
•
Tax Rate approved by voters
and collected annually
•
Deductible on personal taxes
•
Considered a more stable
revenue source
•
Equitable – pay over time
•
Levy funds debt service of
entire 10-year plan without
rate increase based on current
projects
Funding the 10-year CIP
Supplementing Secondary Property Tax when
Existing Bond Authorization is Fully Utilized
Current TPT Rate in Orange
Tax Rate supplementing
secondary tax when existing
bond authorization is fully
utilized in Blue
Considerations:
•
Changes impact businesses
•
Rate change every three years
would be needed or increase
from 1.5 to 1.85 to meet debt
service need
•
Would constrain use of ETROs
for Utility projects and
ongoing operations
•
Tax increase must remain for
life of bonds
Who is in
“The Same
Boat” with
Chandler?
Chandler
Glendale
2025
Buckeye
2024
Mesa
2024
Gilbert
2025-26?
Phoenix
2023
Tempe
2024
Scottsdale
TPT- Nov
Surprise
2023
Bond Election History
The City of Chandler has had
great success with residents
voting to approve bond
authorization to support the
capital plan. Since 2000 the
City has held 4 bond
elections. All with significant
education/outreach.
The table shows the bond
authorization amounts
approved in each category
since 2000.
Previous 2021 Bond Election Results
73.14% Yes
65.69% Yes
69.33% Yes
73.22% Yes
68.24% Yes
Council
direction was to
not increase
secondary
property tax
rate
Previous 49 Member
Bond Exploratory Election Committee
Purpose of Committee
Newly formed
committee
focus can be
reimagined
Bond Exploratory Sample Committee
Timeline
Committee selected
July-Aug 2024
Kick-off begins
Aug. – Sep. 2024
Committee meetings
take place
Sep.–Nov. 2024
Final Review with Finance
Sub-committee in
December 2024
Dec. 2024
Recommendation
approved by Committee
Jan. 2025
Draft report prepared
Jan. - Feb. 2025
Committee chair reports
to Mayor and Council on
recommendation and
presents executive
report
Feb. - Mar. 2025
Call for Bond Election by
May 8, 2025, for
November 4, 2025,
election
May 8, 2025
Bond Election Sample Process
Date
Description
Aug-Dec 2024
Bond Steering Committee process
Feb-Apr 2025
City Council discussion of recommendation
May 8, 2025
City Council calls for an election/approves ballot language by Resolution
June 7, 2025
Ballot language submitted to Maricopa County by deadline
July 7- Aug 6, 2025
Accepts Pro/Con Arguments
September 23, 2025
Sample ballot and informational pamphlet mailed to voters before election
October 6, 2025
Last day for voters to register for election
October 8, 2025
First day to mail out ballot
November 4, 2025
Election Day
November 24, 2025
Deadline for City Council to canvas the election
Options and Council
Direction
•Begin formulation of Bond Exploratory Committee to
evaluate project merits, financing options, and timelines
•Evaluate other sources of CIP financing to maintain as
much of 10-year plan as possible (e.g. TPT, impact fees)
•Significantly pare back 10-year CIP to avoid bond
authorization shortfalls post-2026 with no additional
revenue stream
Questions