Project Name: Price Road Frontage Road Sewer Rehabilitation – Change Order No. 1
Page 1
Project No.: WW2210.401
Rev. 1/16/2024
Amendment authorized by Owner name: Jermaine Swinton
Date: 5/16/2024
Original Agreement amount:
$14,255,102.98
Previous Change Order total:
n/a
Last Agreement amount approved by Council:
$14,255,102.98
This Change Order:
$1,064,143.72
This Change Order + previous Change Order(s) not approved by
Council total:
$1,064,143.72
Revised Agreement total:
$15,319,246.70
Council Approval Required (yes indicates approval required)
Yes
No
Change Order(s) total over $100,000:
☒
☐
Change Order(s) total causes Agreement to exceed $100,000:
☐
☒
Agreement Time
Agreement time prior to this Change Order (including previous
change order(s):
340
Calendar Days
Net change resulting from this Change Order:
0
Calendar Days
Revised Agreement time (including this Change Order):
340
Calendar Days
Council Approval (if applicable)
Council Approval Date: 6/13/24
CHANGE ORDER NO.
1
DATE
5/16/24
This Change Order No. 1 (“Change Order No. 1”) to the construction services agreement is made by
and between the City of Chandler, an Arizona municipal corporation, (“City”) and B&F Contracting,
Inc., (“Contractor”), on this ______ day of ___________________, 2024 (“Effective Date” by Clerk).
Change Order not valid until signed by both the City and the Contractor. Contractor’s signature indicates
Agreement herewith, including any adjustments in the Agreement Price or Agreement Time.
Project Name:
Price Road Frontage Road Sewer Rehabilitation
Project No.:
WW2210.401
User Dept.:
Public Works & Utilities
NTP Date: 11/27/2023
TO:
B&F Contracting, Inc.
11011 N. 23rd Ave. Phoenix, AZ 85029
(CONTRACTOR)
(Mailing Address)
jonstott@bfcontracting.com
(Email Address)
Contractor must make the following changes to this Agreement: (Detail scope change (Exh. A) / cost
breakdown (Exh. B), if needed)
See the attached Exhibit A and B for the additional scope of work to cured-in-place pipe (CIPP) line the existing
48-inch T-lock lined RCP pipe from Frye Road to the Diversion Structure along northbound Price Frontage Road.
ROC-089744 | BFCONTRACTING.COM | 11011 N. 23rd Avenue| Phoenix, AZ 85029
P: 623.582.1170 | F: 623.582.3761
August 10, 2023
Scott Riter – Construction Project Manager
City of Chandler – Public Works & Utilities
215 E Buffalo Street
Chandler, AZ 85225
RE: Name:
Price Road Frontage Road Sewer Rehab
Project No.:
WW2210.401
SUBJECT: Construction Manager at Risk – Change Order
Dear Mr. Riter,
B&F Contracting, Inc. respectfully submits, for your review, our Proposal for additional CIPP lining of 48-
inch & 27-inch pipe on the Price Road Frontage Road Sewer Rehabilitation. B&F proposes to complete this
work on directly after the contract work is complete utilizing the same equipment to convey flow an
addition 750 LF downstream of the current discharge to complete the 48-inch pipelining from Frye Road
to the Price Diversion Structure. To accommodate this, work the bypass will need to be extended and the
Frye Road Bypass run time will be extended beyond the original duration in the GMP-001. Also included
in this proposal is pricing to complete CIPP lining of the 27-inch line at Frye Road. The line was CCTV
inspected and has buried manhole under ADOT concrete pavement that would need rehabilitated 80 lf
off the price 42” main. This proposal would CIPP line from the new upstream manhole through this buried
manhole to the new polymer downstream manhole and completely cut off corrosive gases to the manhole
on the ADOT property and eliminate the need to abandon or rehabilitate the manhole. The price includes
all labor, equipment, material, and services to complete this additional work. See the attached schedule
of values for reference.
Included in this package are the following documents:
•
COC GMP Work Sheet
•
Schedule of Values
•
Cost Detail
•
Scope of Work
•
Subcontractor Quotes
We are excited about the opportunity to work with the City of Chandler and look forward to discussing
this soon. If you or your team have any questions or comments regarding the above items, please
contact Josh Onstott at (623)238-3792
Sincerely,
Josh Onstott
Josh Onstott – Executive Director
JOnstott@bfcontracting.com
B&F Contracting, Inc.
Exhibit A
Date: 5/16/2024
Amount
A. Cost of Work
A1 Cost of Work (self perform, no mark-up)
$408,636.98
A2 Cost of Work (subcontractors, suppliers, materialmen)
$937,356.00
TOTAL COST OF WORK:
$1,345,992.98
B. General Conditions
$0.00
$1,345,992.98
C. CM@Risk's Fee
$114,409.40
SUBTOTAL 2 (A + B + C):
$1,460,402.38
D. Bonds and Insurance (on Subtotal 1)
D1 Bonds (Payment and Performance)
$13,459.93
D2 Insurance
$14,805.92
$28,265.85
SUBTOTAL 3 (SUBTOTAL 2 + BONDS & INS):
$1,488,668.24
E. Sales Tax
E1 Sales Tax
$75,475.48
E2 Tax Credits
$0.00
$75,475.48
F. Approved Allowances
$0.00
G. Contingencies
G1
Owner Contingency
$ -
G2
Contractors Contigency
$ -
$0.00
Current GMP Allocation to Proposal
-$500,000.00
$1,064,143.72
Establishment of Values:
a. Cost of Work (A) and Allowances (F) to be submitted with GMP Proposal
b. General Conditions Cost (B) to be established in Baseline Cost Model.
c. CM@Risk Fee as set forth in Section 3.7.3 of this Contract
EXHIBIT D
TOTAL BONDS & INSURANCE:
TOTAL SALES TAX:
TOTAL GMP PROPOSAL:
TOTAL ALLOWANCES:
TOTAL CONTINGENCIES:
CM@RISK GMP SUMMARY (PAGE 2 of 2)
Project Name:
Project Location:
City of Chandler Project No.:
Price Frontage Road Sewer Rehabiliatation 48 & 27 Inch Lining
Price Frontage Road (Ray Road to Frye Road)
WW2210.401
SUBTOTAL 1 (Cost of Work) (A + B):
Exhibit B
Exhibit D3: City of Chandler - Price Road Frontage Road Sewer Rehabiliation - 48-Inch and 27-Inch Lining Proposal
COC Project Number: WW2201.401
B F Project Number: 23-3304-01
A
B
C
WW2210.401
1 Remove And Replace PCCP Between Joints
223.00 SY
384.11 $ 85,656.53
2 Provide Operate And Remove Bypass Pumping & Piping System
1.00 EACH
209,219.59 $ 209,219.59
3 Clean Existing 48-inch Diameter Sanitary Sewer Pipe
1,530.00 LF
22.38 $ 34,241.40
4 42-inch, 36-inch, 12-inch And 8-inch Pre & Post Pipe Rehabilitation CCTV Inspection
1,858.00 LF
7.86 $ 14,603.88
5 Install 27-inch CIPP Liner
328.00 LF
180.13 $ 59,082.64
6 Install 48-inch CIPP Liner
1,538.00 LF
580.13 $ 892,239.94
7 Trench And Install Bypass Crossing Pipes
100.00 LF
509.49 $ 50,949.00
Subtotal of CMAR Direct Work
$ 1,345,992.98
SCHEDULED VALUE
ITEM
No.
DESCRIPTION OF WORK
QTY
Unit of Measure
Unit Price
Exhibit D3: City of Chandler - Price Road Frontage Road Sewer Rehabiliation - 48-Inch and 27-Inch Lining Proposal
COC Project Number: WW2201.401
B F Project Number: 23-3304-01
A
B
C
WW2210.401
SCHEDULED VALUE
ITEM
No.
DESCRIPTION OF WORK
QTY
Unit of Measure
Unit Price
General Conditions
33 General Conditions
0 MO
102,792.23 $ -
Subtotal with General Conditions
$ 1,345,992.98
8.5% Markup
$ 114,409.40
Total with OH&P
$ 1,460,402.38
Insurance and Bond on Subtotal of CMAR Direct Work + Overhead & Profit
Insurance Cost (1.1%)
$ 14,805.92
Bond Cost (1%)
$ 13,459.93
Subtotal Bond and Insurance
$ 28,265.85
Subtotal Bond and Insurance+ CMAR Direct Work + Overhead & Profit
$ 1,488,668.24
Sales Tax (5.07%)
Sales Tax (5.07%) (Includes Cost of Insurance and Bond * .0507)
$ 75,475.48
Combined Total with Insurance, Bonds, & Tax
$ 1,564,143.72
Current GMP Allocation to Proposal
$ (500,000.00)
ORIGINAL CONTRACT TOTALS
$ 1,064,143.72
Cost Detail
Project Name:
Price Road Frontage Road Sewer Rehabilitation Project
Customer:
City of Chandler
Mail Stop 407, P.O. Box 4008
Job Number:
22-3304-01
Bid Number: WW2210.401
Billing Address:
Bid As:
B&F Contracting, Inc.
Chandler, AZ 85244 USA
4807823310
Estimator:
Joshua Onstott
Phone:
Project Address:
Price Road From Frye, Chandler, AZ
Contact:
Scott Riter
12/20/2022
Completion Date:
Pay Items
Description
Quantity UM
Direct Cost
Unit
Direct Cost
Total
Unit Price
Total Price
Markup
Percent
1 - Remove And Replace PCCP Between Joints
223.00 SY
$85,657.66
$384.12
$384.11
-0.00%
$85,656.53
Remove And Replace PCCP ADOT Joint To Joint
223.00 SY
$85,657.66
$384.12
Demo PCCP (74.33 SY/DY, 3.00 DY)
223.00 SY
$20,782.56
$93.20
CP-Concrete Replace Crew (37.17 SY/DY, 6.00 DY)
223.00 SY
$18,852.96
$84.54
Misc. Concrete Materials (Forms, Dowels, Stakes, Cure,
Etc.)
1.00 LS
$2,000.00
$2,000.00
Aggregate - ABC MAG Spec (Vulcan Materials
Company)
145.20 TON
$4,472.16
$30.80
Ready Mix Concrete - MAG AA 4000 (Arizona Materials
LLC)
77.70 YARD
$13,908.30
$179.00
Fine Grade (74.33 SY/DY, 3.00 DY)
223.00 SY
$13,850.40
$62.11
Trucking (3.00 DY, 0.66 Trucks, 9.29 SY/HR)
223.00 SY
$2,150.36
$9.64
Dump Fee - Concrete
6.00 LOAD
$750.00
$125.00
Sawcut
223.00 SY
$6,440.93
$28.88
CP-Sawcutting Large Crew (104.00 SY/DY, 2.14 DY)
223.00 SY
$6,440.93
$28.88
Drill And Dowell
1.00 LS
$2,450.00
$2,450.00
5/16/2024 1:32:34 PM
Page 1 of 6
Description
Quantity UM
Direct Cost
Unit
Direct Cost
Total
Unit Price
Total Price
Markup
Percent
2 - Provide Operate And Remove Bypass Pumping &
Piping System
1.00 EACH
$209,220.71
$209,220.71
$209,219.59
-0.00%
$209,219.59
Additional Bypass For 48-inch Pipe CIPP
2.00 EACH
$209,220.71
$104,610.35
Bypass Setup
2.00 EACH
$58,870.94
$29,435.47
Fuse Pipe
1,500.00 LF
$25,972.82
$17.32
Fuse Stringer
1,500.00 LF
$14,617.44
$9.74
RH-Bypass Fusion 18in< Crew (500.00 LF/DY,
3.00 DY)
1,500.00 LF
$14,617.44
$9.74
Misc Fuse Flange Adapters / Fitting
17.00 EACH
$11,355.38
$667.96
RH-Bypass Fusion 12-18in Crew (8.00 EACH/DY,
1.13 DY)
9.00 EACH
$4,858.74
$539.86
RH-Bypass Fusion 18in< Crew (6.00 EACH/DY,
1.33 DY)
8.00 EACH
$6,496.64
$812.08
Plumb Pump Station
4.00 EACH
$19,358.40
$4,839.60
RH-Bypass Sewer Setup Crew (1.00 EACH/DY, 4.00
DY)
4.00 EACH
$18,358.40
$4,589.60
Bolts / Gaskets
1.00 EACH
$1,000.00
$1,000.00
Road X-ing Delays
2.00 EACH
$2,378.44
$1,189.22
RH-Bypass Fusion 12-18in Crew (4.00 EACH/DY,
0.50 DY)
2.00 EACH
$2,378.44
$1,189.22
Test Discharge Piping
1,500.00 LF
$4,164.56
$2.78
GC-Chlorine & Pressure Test Crew (1,500.00 LF/DY,
1.00 DY)
1,500.00 LF
$4,164.56
$2.78
Install And Remove Plugs
2.00 EACH
$6,996.72
$3,498.36
RH-Bypass Sewer Setup Crew (1.00 EACH/DY, 2.00
DY)
2.00 EACH
$6,996.72
$3,498.36
Bypass Removal
2.00 EACH
$25,766.60
$12,883.30
RH-Bypass Sewer Takedown Crew (0.67 EACH/DY,
3.00 DY)
2.00 EACH
$14,299.68
$7,149.84
RH-Pipe Pigging Crew (4.00 EACH/DY, 0.50 DY)
2.00 EACH
$2,016.56
$1,008.28
Chlorine And Dechlorine
2.00 EACH
$850.00
$425.00
Plug Removal
1.00 EACH
$3,600.36
$3,600.36
RH-Bypass Sewer Setup Crew (1.00 EACH/DY, 1.00
DY)
1.00 EACH
$3,600.36
$3,600.36
Repair Fence
1.00 EACH
$5,000.00
$5,000.00
Price Road Frontage Road Sewer Rehabilitation Project
5/16/2024 1:32:34 PM
Page 2 of 6
Description
Quantity UM
Direct Cost
Unit
Direct Cost
Total
Unit Price
Total Price
Markup
Percent
Pump Watch
24.00 DY
$47,372.16
$1,973.84
RH-Bypass Sewer Pump Watch Crew (1.00 DY/DY,
24.00 DY)
24.00 DY
$46,652.16
$1,943.84
Consumables
24.00 LS
$720.00
$30.00
Bypass Equipment
30.00 DY
$11,986.05
$399.53
Mobilization
1.00 EACH
$6,188.48
$6,188.48
GC-Mobilization Crew (2.00 EACH/DY, 2.00 DY)
4.00 EACH
$2,676.00
$669.00
GC-Unload & String Pipe Crew (2.00 EACH/DY, 2.00
DY)
4.00 EACH
$3,512.48
$878.12
Demobilization
1.00 EACH
$6,188.48
$6,188.48
GC-Mobilization Crew (2.00 EACH/DY, 2.00 DY)
4.00 EACH
$2,676.00
$669.00
GC-Unload & String Pipe Crew (2.00 EACH/DY, 2.00
DY)
4.00 EACH
$3,512.48
$878.12
Frye Existing Bypass
24.00 DY
$52,848.00
$2,202.00
3 - Clean Existing 48-inch Diameter Sanitary Sewer
Pipe
1,530.00 LF
$34,237.64
$22.38
$22.38
0.01%
$34,241.40
48" Heavy Cleaning
1,530.00 LF
$14,382.24
$9.40
Heavy Cleaning (510.00 LF/DY, 3.00 DY)
1,530.00 LF
$7,746.24
$5.06
GC-CCTV Crew (510.00 LF/DY, 3.00 DY)
1,530.00 LF
$5,286.00
$3.45
Dump Fees
3.00 EACH
$1,350.00
$450.00
27" Cleaning
328.00 LF
$2,617.60
$7.98
3 Pass Cleaning (328.00 LF/DY, 1.00 DY)
328.00 LF
$2,617.60
$7.98
Remove T-Lock (No Grout Placement)
1,530.00 LF
$9,385.00
$6.13
RH-CIPP Lining Support Crew (510.00 LF/DY, 3.00 DY)
1,530.00 LF
$8,385.00
$5.48
Consumables (Tyvek, Gloves, Blades, Sanitation)
1.00 EACH
$500.00
$500.00
Dump Fee - Concrete
1.00 LOAD
$500.00
$500.00
Dewatering Downstream Pipe
3.00 DY
$7,852.80
$2,617.60
GC-Combo Hydro Truck Crew (1.00 DY/DY, 3.00 DY)
3.00 DY
$7,852.80
$2,617.60
4 - 42-inch, 36-inch, 12-inch And 8-inch Pre & Post
Pipe Rehabilitation CCTV Inspection
1,858.00 LF
$14,613.22
$7.87
$7.86
-0.06%
$14,603.88
Pre Pipe CCTV Inspection
1,858.00 LF
$7,181.22
$3.87
GC-CCTV Crew (895.13 LF/DY, 4.15 DY)
3,716.00 LF
$7,181.22
$1.93
Post Pano
1,858.00 LF
$7,432.00
$4.00
Price Road Frontage Road Sewer Rehabilitation Project
5/16/2024 1:32:34 PM
Page 3 of 6
Description
Quantity UM
Direct Cost
Unit
Direct Cost
Total
Unit Price
Total Price
Markup
Percent
5 - Install 27-inch CIPP Liner
328.00 LF
$59,082.96
$180.13
$180.13
-0.00%
$59,082.64
CIPP Lining 27" DIP (Insituform Technologies, Inc.)
328.00 LF
$54,120.00
$165.00
RH-CIPP Lining Support Crew (164.00 LF/DY, 2.00 DY)
328.00 LF
$4,962.96
$15.13
6 - Install 48-inch CIPP Liner
1,538.00 LF
$892,246.42
$580.13
$580.13
-0.00%
$892,239.94
CIPP Lining 48" DIP (Insituform Technologies, Inc.)
1,538.00 LF
$868,970.00
$565.00
RH-CIPP Lining Support Crew (310.00 LF/DY, 4.96 DY)
1,538.00 LF
$8,276.42
$5.38
CIPP Mobe
1.00 EACH
$15,000.00
$15,000.00
7 - Trench And Install Bypass Crossing Pipes
100.00 LF
$50,949.15
$509.49
$509.49
-0.00%
$50,949.00
Dig Temp Trench
100.00 LF
$19,792.43
$197.92
SL-PVC SDR 17 18in Res Extra Large Diameter Crew
(100.00 LF/DY, 1.00 DY)
100.00 LF
$7,284.32
$72.84
CP-Sawcutting Small Crew (100.00 LF/DY, 2.00 DY)
200.00 LF
$4,372.96
$21.86
Plate
10.00 UNIT
$3,600.00
$360.00
Backfill Materials
68.00 TON
$1,564.00
$23.00
ABC
68.00 TON
$1,564.00
$23.00
Trucking (1.00 DY, 2.40 Trucks, 12.50 LF/HR)
100.00 LF
$2,596.15
$25.96
Dump Fee - Dirt
5.00 LOAD
$375.00
$75.00
Backfill Trench
100.00 LF
$18,039.75
$180.40
SL-PVC SDR 17 18in Res Extra Large Diameter Crew
(100.00 LF/DY, 1.00 DY)
100.00 LF
$7,800.64
$78.01
Backfill Materials
120.00 TON
$3,270.00
$27.25
ABC
120.00 TON
$2,820.00
$23.50
Dump Fee - Dirt
6.00 LOAD
$450.00
$75.00
Trucking (1.00 DY, 2.40 Trucks, 12.50 LF/HR)
100.00 LF
$2,596.15
$25.96
CP-Sawcutting Small Crew (100.00 LF/DY, 2.00 DY)
200.00 LF
$4,372.96
$21.86
Concrete Repairs
2.00 EACH
$9,641.52
$4,820.76
CP-Concrete Curb & Gutter Crew (1.00 EACH/DY, 2.00
DY)
2.00 EACH
$7,731.36
$3,865.68
Ready Mix Concrete - MAG AA 4000 (Arizona Materials
LLC)
8.40 YARD
$1,503.60
$179.00
Aggregate - ABC MAG Spec (Vulcan Materials
Company)
13.20 TON
$406.56
$30.80
GC-Pothole
4.00 EACH
$3,475.44
$868.86
Price Road Frontage Road Sewer Rehabilitation Project
5/16/2024 1:32:34 PM
Page 4 of 6
Description
Quantity UM
Direct Cost
Unit
Direct Cost
Total
Unit Price
Total Price
Markup
Percent
GC-Utility Potholing Crew (4.00 EACH/DY, 1.00 DY)
4.00 EACH
$3,475.44
$868.86
Price Road Frontage Road Sewer Rehabilitation Project
5/16/2024 1:32:34 PM
Page 5 of 6
Direct Cost Totals
Amount
Equipment Rented:
Direct Cost
Percent of
Equipment Owned:
Materials Owned:
Materials Purchased:
Labor:
Subcontracted:
Trucking Owned:
Trucking Hired:
Miscellaneous:
Plug:
Direct Cost:
$151,663.18
$139,401.69
$8,610.60
$20,290.62
$937,356.00
$0.00
$7,342.66
$6,145.00
$75,198.00
$0.00
$1,346,007.76
11.27%
0.64%
0.00%
69.64%
0.00%
0.55%
0.46%
5.59%
10.36%
1.51%
Bid Price
$1,345,992.98
($14.78)
Pay Item Summary
Amount
Total Bond:
Total Indirect Cost:
Total Overhead:
Total Profit:
Total Direct Cost:
Total Bid Price:
$1,346,007.76
$0.00
$0.00
$0.00
Total DC Adds/Cuts:
$0.00
100.00%
0.00%
0.00%
0.00%
0.00%
-0.00%
$1,346,007.76
Total Overall Cost:
($14.78)
Total Margin:
100.00%
-0.00%
Percent of
Price Road Frontage Road Sewer Rehabilitation Project
5/16/2024 1:32:34 PM
Page 6 of 6
EXHIBIT F
Project Name: [TITLE]
F-1
City Project No.: [####]
Rev. 10/23/23
SUBCONTRACTOR DOCUMENTS WITH CM@RISK
Any subcontractor assumptions, clarifications, exclusions, terms & conditions, signature
blocks, etc. included are strictly between the CM@Risk and their subcontractors, and do
not apply to the Agreement between the CM@Risk and the City.
Exhibit C
Project Name: Price Road Frontage Road Sewer Rehabilitation – Change Order No. 1
Project No.: WW2210.401
Rev. 1/16/2024
Technologies, LLC.
Worldwide Pipeline Rehabilitation
645 W 24th St
Tempe, AZ, 85282
Tel: (480) 446-0620
Fax: (480) 446-0349
www.insituform.com
May 8, 2024
Mr. Josh Onstott
Executive Director
B&F Contracting
Re:
Change Order Proposal # 3 for Project WW2210.401 – City of Chandler Price Rd Rehab
Dear Mr. Onstott:
COP # 3 below includes two options for CIPP lining 27”.
-
Option 1 is 82 LF of 27” assuming lining from MH 756006977 to buried MH 756005854 (Manhole needs
exposed).
-
Option 2 is 328 LF of 27” assuming lining from MH 756006977 to New MH 01.
CHANGE ORDER PROPOSAL 3 – Option 1
Item Description
Unit Price
Qty
TOTAL
1
Price and Frye Rd 27” CIPP – Option 1
$360
82 LF
$29,520.00
TOTAL CO3 – Option 1
$29,520.00
CHANGE ORDER PROPOSAL 3 – Option 2
Item Description
Unit Price
Qty
TOTAL
1
Price and Frye Rd 27” CIPP – Option 2
$165
328 LF
$54,120.00
TOTAL CO3 – Option 2
$54,120.00
All assumptions, inclusions and exclusions remain same per the original contract. Please do not hesitate to
contact me with any further questions.
Very truly yours,
Insituform Technologies, Inc.
Seth Ganesan
Technologies, LLC.
Worldwide Pipeline Rehabilitation
645 W 24th St
Tempe, AZ, 85282
Tel: (480) 408-9203
Fax: (480) 446-0349
www.insituform.com
May 14, 2024
Mr. Josh Onstott
Executive Director
B&F Contracting
Re:
Change Order Proposal # 4 for Project WW2210.401 – City of Chandler Price Rd Rehab
Dear Mr. Onstott:
The proposal below includes CIPP lining of approximately 1,530 LF of 48” segments at Price and Frye Road.
CHANGE ORDER PROPOSAL 4
Item
#
Description
Unit Price
Qty
TOTAL
1
Mobilization
$15,000
1
$15,000.00
2
Price and Frye Rd 48” OTH CIPP
$565
1,530 LF
$864,450.00
TOTAL CO4
$879,450.00
Assumptions specific to this project:
-
Insituform will continue these installations with minimum gap (approximately a month) from finishing the
current Chandler Over the Hole installations, so we can keep most of the OTH equipment in Tempe
-
Designs are based on following MH depths measured: 21 feet at Frye Rd, 15 feet at Fairview Rd and 10 feet
at MH with bend
-
We will install two OTH shots from Fairview St manhole, one to Frye Rd and other to the Structure
All other assumptions, inclusions and exclusions remain same per the original contract. Please do not hesitate to
contact me with any further questions.
Very truly yours,
Insituform Technologies, Inc.
Seth Ganesan
Project Director
Insituform Technologies