6.2024 Construction Report

City of Chandler — Regular Meeting (2024-06-12)

View PDF Meeting page

Extracted text (via pymupdf) 1798 characters
Capital Projects – Design Phase: 
 
Airport Operations Garage: City funded at $1 million.  Programming and conceptual layout 
completed.  Scope includes parking lot and aircraft observation area.  Design Kick-off meeting 5/28.  
 
Airport Fuel Tank Relocation: City funded at $610,000.  Design for new above ground tank at 
100%.  Evaluating project delivery options.  Final edits to plans underway. 
 
Runway End Identifier Light (REIL) Installation Runway 4L-22R– (North Runway): FAA funding 
for $110,000.  Kick-off meeting 2/21. Plans at 100%.  FAA environmental clearance received. 
 
Runway 4R-22L Rehabilitation (South Runway): FAA grant for $350,000 for design approved.  
Kick-off meeting 4/6.  100% plans to be submitted in June. 
 
Taxiway B Improvements- Phase 1: ADOT grant for $2,035,000 approved.  FAA environmental 
clearance received.  30% design meeting with ADOT 5/24. 
 
Old Heliport Redevelopment: Proceeding with design contract for $30,805 in local funds for new 
fencing and pavement maintenance/tie-down design.  Kick-off meeting January 4th.  Design 
underway with initial layout for internal comment. 
 
Capital Projects - Construction Phase: 
 
Taxiway C Electrical:  Local funding.  Addresses immediate issues with electrical infrastructure.  
Cabling and lighting system are functional but needs replacement.  5/20 Council approval of 
$495,479 contract with DNG.  Approximately 7-week lead time for material.  Construction start in 
late July/early August. 
 
Automated Weather Observation System (AWOS) Replacement:  FAA funding for $200,000.  FAA 
environmental clearance received.  100% plans finalized.  Bid closing April 9th.  Targeting Council 
approval on June 24th. 
 
 
 
Meeting Date:  
June 12, 2024 
Chandler Municipal Airport 
Construction Report