July 2024 Project Status Update

City of Chandler — Regular Meeting (2024-07-17)

View PDF Meeting page

Extracted text (via pymupdf) 4341 characters
ROADWAY AND TRAFFIC PROJECTS
Designer
Contractor
Status
Comments
PROJECT COST 
ESTIMATE
($MILLIONS)
ST1614, Chandler Heights Road Improv. [McQueen Road to Gilbert Road for two 
through lanes each direction]
Kimley-Horn
Granite Construction 
Company
Construction underway.  Completion scheduled for 
Fall 2024.
Federal funds
$20.90
ST1804, Chandler Heights Road Improv. [Gilbert Road to Val Vista Drive for
two through lanes each direction]
Kimley-Horn
tbd
Proejct is currently out to Bid
Federal funds
$20.90
ST2001, Lindsay Road Improv. [Ocotillo Road to Hunt Highway for two
through lanes in each direction]
Kimley-Horn
tbd
Design in progress.  Bid scheduled for Spring 2025.
Federal funds
$27.20
ST2007, Hamilton Street Improv. [Appleby Road to Carob Drive]
Nfra Consultants
Redpoint
Construction underway.
$5.20
ST2009, Dobson Road Improv. at Intel Driveways #1 and #4 [Price Rd /
Market Pl to Chaparral Way]
Premier
DCS Contracting
Construction in progress.  Completion date 
extended to coordinate with other projects.  
Completion scheduledfor Winter 2024.
Funded by 20% from Intel and 80% from State TPT per
ARS 42-5032.02
$0 City Cost (Intel
Funded)
ST2012, Arterial Congestion Monitoring [Install data collection devices at major 
intersections, and use data to map traffic congestion and mobility.]
Y.S. Mantri & Assoc.
CS Construction
Project to be complete end of July 2024.
Grant funds
$1.30
ST2103, Intersection Improv. at Ray Road and Dobson Road
Kimley Horn
tbd
Design underway. Construction anticipated Fall 
2026.  
Grant funds & local funds
$11.85
ST2112, Alley Rehab PM10 Dust Emissions Reduction 2 (FMA Areas 16, 25,
39, and 40)
Premier / Olsson
Cactus Asphalt
Construction underway.
Federal funds
$2.4 (tbc)
ST2110, Chandler Video Detection Cameras 
Y.S. Mantri & Assoc.
TCI
Construction complete.  Close out in process.
Federally Funded
$1.7(tbc)
ST2209,  Chandler Local Detection and Communication Systems (Replaces 
existing video detecting cameras with new video cameras)
Kimley-Horn and 
Associates
CS Construction
Construction complete.  Close out in process.
Federally Funded
$0.50 
ST2210, Chandler ICM Detection and Communication Systems (Replaces existing 
video detecting cameras near freeways with new video cameras)
Kimley-Horn and 
Associates
CS Construction
Construction complete.  Close out in process.
Federally Funded
$0.60 
ST2301  Armstrong Way and Hamilton Street Improvement (Improves the south 
half of Armstrong Way and the west half of Hamilton Street)
EPS Group, Inc.
tbd
Design underway.  Construction tentatively 
scheduled Summer/Fall 2024.
$2.00 
ST2303 Cooper Road - Insight Loop Extension (Connects Cooper Road to Insight 
Way & Emmett Dr intersection)
Aztec
tbd
Design underway.
$9.30 
PEDESTRIAN, BICYCLE, AND TRANSIT PROJECTS
Designer
Contractor
Status
Comments
PROJECT COST 
ESTIMATE
($MILLIONS)
ST2106, Frye Road Protected Bike Lanes [Paseo Trail to San Marcos
Elementary School]
TY Lin
tbd
Study completed by Y2K.  Redesign underway. 
Construction in early 2025.
Federal grants have been awarded to fund study, design
and construction.
$14.00
TP2202, Kyrene Branch and Highline Canal Shared Use Paths
Kimley-Horn
tbd
Study completed by Kimley-Horn.  Design 
underway.  Construction in mid-late 2025.
Federal grants have been awarded to fund study, design
and construction.
$4.50
Ashley and Paseo Trails Connection
Y2K Engineering
tbd
Study completed by Y2K.  Design underway.  
Construction in 2025.
Study was federally funded.  Construction and design are locally 
funded.
$1.00
Arizona Avenue Shared Use Path Study
Y2K Engineering
tbd
Study analyzing feasibility of expanding 4'-6' 
sidewalks to a 10'-12' shared use path on Arizona 
Avenue between Ray Road and the Western Canal.
Federally funded study.
$0.10
Pedestrian Connectivity Study
Y2K Engineering
tbd
Study to create a sidewalk inventory and develop a 
plan to address gaps in sidewalks.
Locally funded study.
$0.10
Chandler Flex
NA
Via
Operations began July 11, 2022.  Study recently 
completed to consider expansion options in 
Southeast Chandler.  Minor expansions may be 
pursued in 2024 or 2025.
Awarded $2 Million grant for project startup and two years of 
operations.  Awarded $1 Million congressionally-directed 
spending grant to continue operations.
$1.2 (Annually)
Transportation Project Status - July 2024