PR2206.401

City of Chandler — Study Session (2024-07-15)

View PDF Meeting page

Extracted text (via pymupdf) 560134 characters
Project Name: Pickleball Courts at Tumbleweed Park GMP I  
Page  i 
Project No.: PR2206.401 
Rev 1-16-2024 
 
 
CITY OF CHANDLER, ARIZONA 
 
 
 
 
PICKLEBALL COURTS AT TUMBLEWEED PARK 
GMP I 
 
CITY PROJECT NO. PR2206.401 
 
 
 
 
CONSTRUCTION SERVICES AGREEMENT 
(CONSTRUCTION MANAGER AT RISK) 
 
 
 
 
 
 
 
 
__________________________________________________ 
Daniel Haskins, P.E. 
CIP City Engineer

Project Name: Pickleball Courts at Tumbleweed Park GMP I  
Page  ii 
Project No.: PR2206.401 
Rev 1-16-2024 
CITY OF CHANDLER, ARIZONA 
 
Pickleball Courts at Tumbleweed Park GMP I 
CITY PROJECT NO.: PR2206.401 
 
 
TABLE OF CONTENTS 
 
 
 PARTICIPANTS AND PROJECT .............................................................................. 1 
 AGREEMENT DOCUMENTS .................................................................................. 3 
 PRE-CONSTRUCTION SERVICES ........................................................................... 3 
 CONSTRUCTION SERVICES ................................................................................... 3 
 CITY RESPONSIBILITIES ........................................................................................ 5 
 AGREEMENT TIME ................................................................................................ 5 
 AGREEMENT PRICE ............................................................................................... 8 
 FORCED LABOR OF ETHNIC UYGHURS PROHIBITED ....................................... 8 
 
 
EXHIBIT A – PROJECT SPECIFIC SPECIAL PROVISIONS .................................................... SP-1 
EXHIBIT B – GENERAL CONDITIONS ................................................................................ GC-1 
EXHIBIT C – TECHNICAL SPECIFICATIONS ........................................................................ TS-1 
EXHIBIT D – ACCEPTED GMP/PRICE PROPOSAL .......................................................... GMP-1 
EXHIBIT E – SUBCONTRACTOR’S LIST FORM ................................................................. SUB-1 
EXHIBIT F – GIS / GPS DATA DELIVERY REQUIREMENTS (IF APPLICABLE) .................... GIS-1 
EXHIBIT G – SUBCONTRACTOR DOCUMENTS WITH CM@RISK ................................. SUBS-1

Project Name: Pickleball Courts at Tumbleweed Park GMP I  
Page 1 
Project No.: PR2206.401 
Rev. 1/16/2024 
CONSTRUCTION MANAGER AT RISK 
CONSTRUCTION SERVICES AGREEMENT 
PROJECT NO.: PR2206.401 
 
This Agreement (the “AGREEMENT”)  is made and entered into on the ______day of _______________, 
2024, (“Effective Date”) by and between City of Chandler, an Arizona municipal corporation, 
hereinafter called “City” and Hunter Contracting Co. the “Construction Manager at Risk” or 
“CM@Risk” designated below (City and CM@Risk may individually be referred to as “Party” 
and collectively referred to as “Parties”). 
 
City and CM@Risk agree as follows: 
 
 PARTICIPANTS AND PROJECT 
 
CITY: 
 
CIP City Engineer: Daniel Haskins, P.E. 
 
Public Works & Utilities Department 
 
P.O. Box 4008, Mail Stop 407   Chandler, AZ  85244-4008 
 
Phone:  480-782-3335     Email:    Daniel.haskins@chandleraz.gov 
 
CITY: 
 
Construction Project Manager: Jason Garcia 
 
Public Works & Utilities Department 
 
P.O. Box 4008, Mail Stop 407  Chandler, AZ  85244-4008 
 
Phone:  480-782-3453     Email:    jason.garcia@chandleraz.gov 
 
 
CM@RISK: 
Legal Company Name:   
Hunter Contracting Co. 
 
Mailing Address:   
701 N. Cooper Road, Gilbert, AZ 85233 
 
Physical Address:   
701 N. Cooper Road, Gilbert, AZ 85233 
 
Arizona Roc No.:   
ROC070961 
 
Federal Tax Id No.:   
 
86-0172434 
 
State Where Organized:    
Arizona 
 
Business Organization:    
S Corporation 
 
Statutory Agent Name:    
WA Service LLC 
 
Statutory Agent Mailing Address: 
 
2555 E. Camelback Road, Suite 800, 
Phoenix, AZ 85016 
 
Statutory Agent Physical Address:    
2555 E. Camelback Road, Suite 800, 
Phoenix, AZ 85016 
 
CM@Risk’s Authorized Project Representative:   
 
 
 
Name: 
Michael Gonzales 
 
 
 
Title: 
Project Manager 
 
 
 
Phone: 
602-541-0671 
 
 
 
Email: 
michaelg@huntercontracting.com

Project Name: Pickleball Courts at Tumbleweed Park GMP I  
Page 2 
Project No.: PR2206.401 
Rev. 1/16/2024 
 
 
 
PROJECT DESCRIPTION: 
 
In response to the increasing popularity of pickleball and the enthusiasm of Chandler 
residents for the sport, City approved the design of a new pickleball complex at Tumbleweed 
Park in October 2023, located at the southeast corner of east Germann Road and south 
Pioneer Parkway. The project includes 18 pickleball courts and accompanying lighting, shade 
ramadas, restrooms, practice areas, lighting, equipment storage, drinking fountains, and 
parking, as well as the design of an additional 3 tennis courts and accompanying lighting 
updates at the adjacent Chandler Tennis Center. 
 
As the design phase of the project is nearing completion, this GMP is for the procurement of 
specified construction materials that have been identified as long-lead procurement and/or 
considered to be at risk significant cost escalation. The intent of this GMP is to provide 
funding authorization for purchase orders of the listed materials to secure current pricing 
and to increase the chances of the project being constructed on time and within budget. 
 
PROJECT LOCATION: 
 
Tumbleweed Park at the southeast corner of east Germann Road and south Pioneer 
Parkway (745 E. Germann Road, Chandler, AZ 85286).

Project Name: Pickleball Courts at Tumbleweed Park GMP I  
Page 3 
Project No.: PR2206.401 
Rev. 1/16/2024 
 AGREEMENT DOCUMENTS 
 
2.1 
AGREEMENT DOCUMENTS 
 
The Agreement between City and CM@Risk will consist of the following Agreement 
Documents: 
 
1. This Construction Services Agreement and all of its Exhibits, including Project 
Plans and Technical Specifications. 
2. General Conditions and General Conditions Appendices, incorporated by 
reference. 
3. Project Specific Special Provisions as set forth in Exhibit A, incorporated by 
reference. 
4. Accepted GMP/Price Proposal as set forth in Exhibit D, incorporated by reference. 
 
2.2 
In the event of any inconsistency, conflict, or ambiguity between or among the 
Agreement Documents, the Agreement Documents will take precedence as described in 
Section 14.1.4 of the General Conditions. 
 
2.3 
DEFINITIONS 
 
The definitions in Sections 2 and 15 of the General Conditions apply to all the 
Agreement Documents, including this Agreement.   
 
 PRE-CONSTRUCTION SERVICES 
 
Although CM@Risk has performed Pre-Construction Services pursuant to a separate 
Agreement between City and CM@Risk, the completion, quality and accuracy of those services 
and the deliverables provided by City thereunder directly impact CM@Risk’s performance of 
its obligations under this Agreement. Therefore, all of CM@Risk’s obligations, duties, and 
warranties in relation to Pre-Construction Services and deliverables survive completion of the 
Pre-Construction Services Agreement and are incorporated herein. Any breach of any of 
CM@Risk’s duties, obligations, or warranties under the Pre-Construction Services Agreement 
will likewise be considered a breach of this Agreement. 
 
 CONSTRUCTION SERVICES 
 
4.1 
GENERAL 
 
4.1.1 
CM@Risk agrees at its own cost and expense, to do all work necessary and required to 
fully, timely and properly complete the construction of the Project in strict accordance 
with the Agreement Documents in a good and workmanlike manner, free and clear of 
all claims, liens, and charges whatsoever, in the manner and under the conditions 
specified, and within the schedule, stated in attached Exhibit A.

Project Name: Pickleball Courts at Tumbleweed Park GMP I  
Page 4 
Project No.: PR2206.401 
Rev. 1/16/2024 
4.1.2 
CM@Risk must provide all of the labor and materials, and perform the Work in 
accordance with Section 4 of the General Conditions. Some, but not all, of the major 
components of the Construction Services and the corresponding subsections of Section 
4 of the General Conditions are set forth below. 
 
4.1.3 
This is an Agreement for complete construction services in accordance with the 
Construction Manager at Risk method of delivery of construction services.  CM@RISK has 
participated in the design process and been an active member of the Project Design 
Team and is fully aware of any issues and constraints involved in this Construction 
Project.   
 
4.1.4 
CM@RISK is the CITY’s fiduciary responsible for undertaking all necessary action 
contemplated under the Agreement documents to construct the Project and ensure 
timely and quality completion of the Project at a cost within the Guaranteed Maximum 
Price (GMP).   
 
4.1.5 
At all times relevant to this Agreement and performance of the Work, the CM@Risk must 
fully comply with all Laws, Regulations, or Legal Requirements applicable to City, the 
Project and the Agreement, 
including, without limitation, those set forth on attached 
Exhibit A. 
 
4.1.6 
CM@Risk must perform the Work under this Agreement using only those firms, team 
members and individuals designated by CM@Risk consistent with the Statement of 
Qualifications dated      , the GMP Proposal, or otherwise approved by City pursuant to 
the General Conditions. No other entities or individuals may be used without prior 
approval of the Project Manager 
 
4.1.7 
CM@Risk will comply with all terms and conditions of the General Conditions. 
 
4.1.8 
In the event of a conflict between this Agreement and the General Conditions or an exhibit 
hereto or appendix thereto, the terms of this Agreement will control. 
 
4.1.9 
Ownership of Work Product.  Notwithstanding anything to the contrary in this 
Agreement, all Work Product prepared or otherwise created in connection with the 
performance of this Agreement, including the Work, are to be and remain the property 
of City. For purposes of this provision, “Work Product” will include all designs, drawings, 
plans, specifications, ideas, renderings and other information or matter, in whatever form 
created (e.g., electronic or printed) and in all media now known or hereinafter created. 
All Work Product will be considered Work Made for Hire as defined in the United States 
Copyright Act 17 U.S.C. § 101 (Copyright Act). If for any reason, any such Work is found 
not to be a Work Made for Hire, CM@Risk hereby transfers and assigns ownership of the 
copyright in such Work to City. The rights in this Section are exclusive to City in perpetuity.

Project Name: Pickleball Courts at Tumbleweed Park GMP I  
Page 5 
Project No.: PR2206.401 
Rev. 1/16/2024 
 
4.2 
CM@RISK’S PRE-AGREEMENT AND PRE-WORK DELIVERABLES 
 
4.2.1 
The CM@Risk must provide the Deliverables in accordance with Section 4.2 of the 
General Conditions.   
 
4.3 
PRE-CONSTRUCTION CONFERENCE 
Refer to Section 4.3 of the General Conditions. 
 
4.4 
PERFORMANCE 
OF 
THE 
WORK 
(INCLUDING 
FIELD 
MEASUREMENTS, 
SUBCONTRACTORS, AND SUPPLIERS) 
Refer to Section 4.4 of the General Conditions. 
 
4.5 
CONTROL OF THE PROJECT SITE 
Refer to Section 4.5 of the General Conditions. 
 
4.6 
PROJECT SAFETY 
Refer to Section 4.6 of the General Conditions. 
 
4.7 
MATERIALS QUALITY, SUBSTITUTIONS AND SHOP DRAWINGS 
Refer to Section 4.7 of the General Conditions. 
 
4.8 
PROJECT RECORD DOCUMENTS 
Refer to Section 4.8 of the General Conditions. 
 
4.9 
WARRANTY AND CORRECTION OF DEFECTIVE WORK 
Refer to Section 4.9 of the General Conditions. 
 
 CITY RESPONSIBILITIES 
 
5.1 
City will have the responsibilities, and provide the information specified in, and subject 
to the conditions set forth in, Section 5 of the General Conditions. 
 
 AGREEMENT TIME 
 
6.1 
GENERAL 
 
6.1.1 
The Agreement Duration is 365 Calendar Days. 
 
6.1.2 
The Agreement Time will start with the Notice to Proceed (NTP) and end with Final 
Acceptance, as set forth in Article 6.4 below. The Notice to Proceed cannot be issued until 
approval and acceptance by City of the GMP or Fixed Price.

Project Name: Pickleball Courts at Tumbleweed Park GMP I  
Page 6 
Project No.: PR2206.401 
Rev. 1/16/2024 
6.1.3 
The Agreement Time will be as set forth in the Project Schedule. CM@Risk agrees that 
it will commence performance of the Work and complete the Project through Final 
Acceptance within the Agreement Time. 
 
6.1.4 
Time is of the essence of this Agreement for the Project, and for each phase and 
designated Milestone thereof. 
 
6.2 
PROJECT SCHEDULE 
 
6.2.1 
The Project Schedule approved as part of the GMP Proposal and incorporated herein as 
part of the attached Exhibit D must be updated and maintained throughout CM@Risk’s 
performance under this Agreement in accordance with Section 6.2 of the General 
Conditions. 
 
6.2.2 
Failure on the part of CM@Risk to adhere to the approved Project Schedule will be 
deemed a material breach and sufficient grounds for termination of this Agreement by 
City. 
 
6.2.3 
Work must be completed to meet the following milestones after the Notice to Proceed: 
 
 
Milestone 
 
Time 
Liquidated damages for delay 
 
1. 
n/a 
within 
n/a 
$n/a 
per calendar day 
6.3 
SUBSTANTIAL COMPLETION 
 
Substantial Completion must be achieved no later than the Substantial Completion Date 
set forth in the Project Schedule.  Substantial Completion will be determined in 
accordance with Section 6.3 of the General Conditions. 
 
6.4 
FINAL ACCEPTANCE 
 
6.4.1 
Final Acceptance will be obtained within the time period set forth in the Project Schedule. 
 
6.4.2 
Final Acceptance will be issued pursuant to Section 6.5 of the General Conditions. 
 
6.5 
LIQUIDATED DAMAGES 
 
6.5.1 
Substantial Completion Liquidated Damages. CM@Risk acknowledges and agrees that 
if CM@Risk fails to obtain Substantial Completion of the Work within the Agreement 
Time, City will sustain extensive damages and serious loss as a result of such failure. The 
exact amount of such damages will be extremely difficult to ascertain. Therefore, City 
and CM@Risk agree that if CM@Risk fails to achieve Substantial Completion of the Work 
within the Agreement Time, City will be entitled to retain or recover from CM@Risk, as

Project Name: Pickleball Courts at Tumbleweed Park GMP I  
Page 7 
Project No.: PR2206.401 
Rev. 1/16/2024 
liquidated damages and not as a penalty, the sum per calendar day as indicated in MAG 
§ 108.9. 
 
6.5.2 
Final Acceptance Liquidated Damages. For the same reasons set forth in Article 6.5.1 
above, City and CM@Risk further agree that if CM@Risk fails to achieve Final Acceptance 
of the Work within the Agreement Time, City will be entitled to retain or recover from 
CM@Risk, as liquidated damages and not as a penalty, the sum per calendar day as 
indicated in MAG § 108.9 commencing from the actual date of Substantial Completion or 
Final Acceptance as required under the Agreement. 
 
6.5.3 
MAG Liquidated Damages. If no liquidated damages are specified in Articles 6.5.1 or 6.5.2 
above, then the liquidated damages provisions in MAG § 108.9 will apply. 
 
6.5.4 
City may deduct liquidated damages described in this Article 6.5 from any unpaid 
amounts then or thereafter due CM@Risk under this Agreement. Any liquidated damages 
not so deducted from any unpaid amounts due CM@Risk will be payable to City at the 
demand of City, together with interest from the date of the demand at the highest lawful 
rate of interest payable by CM@Risk. 
 
6.6 
MUTUAL WAIVER OF CONSEQUENTIAL DAMAGES ONLY 
 
6.6.1 
CM@Risk and City waive claims against each other for consequential damages arising 
out of or relating to this Agreement. This mutual waiver includes: 
 
6.6.1.1 Damages incurred by City for rental expenses, for losses of use, income, profit, financing, 
business and reputation, and for loss of management or employee productivity or of 
the services of such persons; and 
 
6.6.1.2 Damages incurred by CM@Risk for principal office expenses including the compensation 
of personnel stationed there, for losses of financing, business and reputation, and for loss 
of profit except anticipated profit arising directly from the Work. 
 
6.6.2 
This mutual waiver is applicable, without limitation, to all consequential damages due 
to either Party’s termination of this Agreement. Nothing contained in this Article 6.6 
will be deemed to preclude an award of liquidated damages, when applicable, in 
accordance with Article 6.5 above. 
 
6.6.3 
Nothing herein will be deemed to constitute a waiver of any other remedy available to 
City in the event of CM@Risk’s default under this Agreement prior to full performance of 
the Work including, as applicable, specific performance or completion of the Work on 
behalf of CM@Risk, the cost and expense of which will be offset against any monies 
then or thereafter due to CM@Risk (if any) and otherwise immediately reimbursed to 
City by CM@Risk.

Project Name: Pickleball Courts at Tumbleweed Park GMP I  
Page 8 
Project No.: PR2206.401 
Rev. 1/16/2024 
 AGREEMENT PRICE 
 
7.1 
AGREEMENT PRICE 
 
7.1.1 
In exchange for CM@Risk’s full, timely, and acceptable performances and construction of 
the Work under this Agreement, and subject to all of the terms of this Agreement, City 
will pay CM@Risk the “Agreement Price,” which:  
 
The sum of the CM@Risk’s Fee and reimbursable Cost of the Work, as defined in Section 
15 of the General Conditions, which the CM@Risk guarantees will not exceed the GMP 
set forth in Exhibit D in the amount of $1,776,697.99.  Costs which would cause the 
GMP to be exceeded must be paid by CM@Risk without reimbursement from City. 
 
7.1.2 
The Agreement Price is all-inclusive and specifically includes all fees, cost, insurance and 
bond premiums, allowances, construction contingency, owner’s contingency, and taxes 
of any type necessary to fully, properly and timely perform and construct Work. 
 
7.2 
CHANGES TO AGREEMENT PRICE 
Shall be determined under Section 9 of the General Conditions. 
 
 FORCED LABOR OF ETHNIC UYGHURS PROHIBITED 
 
8.1 
FORCED LABOR OF ETHNIC UYGHURS PROHIBITED.  By entering into this 
Agreement, Contractor certifies and agrees Contractor does not currently use and 
will not use for the term of this Agreement: (i) the forced labor of ethnic Uyghurs in 
the People's Republic of China; or (ii) any goods or services produced by the forced 
labor of ethnic Uyghurs in the People's Republic of China; or (iii) any contractors, 
subcontractors or suppliers that use the forced labor or any goods or services 
produced by the forced labor of ethnic Uyghurs in the People's Republic of China. 
 
 
SIGNATURE PAGE TO FOLLOW

EXHIBIT A 
 
Project Name: Pickleball Courts at Tumbleweed Park GMP I  
Page SP-1 
Project No.: PR2206.401 
Rev. 1/16/2024 
 
 
PROJECT SPECIFIC 
SPECIAL PROVISIONS 
 
 
 
4.2.7 Aerial Construction Photography 
General Conditions Section 4 Subsections 4.2.7.1 & 4.2.7.2 are not applicable to this 
project. 
 
4.2.8 Government Approvals and Permits 
General Conditions Section 4 Subsection 4.2.8.1, City permit fees will be paid internally 
by the City and all other fees will be the responsibility of the Contractor. 
 
Subletting of Agreement 
Contractor must perform, with his own organization, work amounting to not less than 50 
percent of the total Agreement cost. 
 
Failure to submit Subcontractor’s List Form, demonstrating self-performance not less than 
50 percent of the total Agreement cost, will cause the bid to be deemed non-responsive.  
 
Contractors should contact the Arizona Registrar of Contractors for information on license 
requirements.

EXHIBIT B 
 
Project Name: Pickleball Courts at Tumbleweed Park GMP I  
Page GC-1 
Project No.: PR2206.401 
Rev. 10/23/23 
GENERAL CONDITIONS

GENERAL CONDITIONS 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Approved date: July 20, 2022

Revised: 7/20/2022 
 
GC-2 of 75 
 
 
 
TABLE OF CONTENTS 
 
 
SECTION 1 - SCOPE OF THESE GENERAL CONDITIONS ............................................................................... 3 
SECTION 2 - GENERAL DEFINITIONS ............................................................................................................ 3 
SECTION 3 - STANDARD SPECIFICATIONS AND DETAILS ........................................................................... 7 
SECTION 4 - CONT R ACT OR’S R ES PONS IBILIT IES FOR CONST RUCT ION SE RVIC ES .................................. 8 
SECTION 5 - CITY RESPONSIBILITIES .......................................................................................................... 27 
SECTION 6 - AGREEMENT TIME ................................................................................................................... 29 
SECTION 7 - AGREEMENT PRICE .................................................................................................................. 35 
SECTION 8 - PAYMENT ................................................................................................................................. 35 
SECTION 9 - CHANGES TO THE AGREEMENT ............................................................................................. 40 
SECTION 10 - SUSPENSION AND TERMINATION ...................................................................................... 43 
SECTION 11 - INSURANCE AND BONDS ..................................................................................................... 44 
SECTION 12 - INDEMNIFICATION ............................................................................................................... 49 
SECTION 13 - DISPUTE RESOLUTION .......................................................................................................... 49 
SECTION 14 - MISCELLANEOUS PROVISIONS ............................................................................................ 50 
SECTION 15 - PROVISIONS APPLICABLE SOLELY TO GMP AND COST-BASED AGREEMENTS, CHANGE 
ORDERS, AND JOB ORDERS ......................................................................................................................... 57 
SECTION 16 - PROVISIONS APPLICABLE SOLELY TO JOB ORDER AGREEMENTS (JOC) ........................ 61 
SECTION 17 - PROVISIONS APPLICABLE SOLELY TO PRE-CONSTRUCTION SERVICES FOR 
CONSTRUCTION MANAGER AT RISK .......................................................................................................... 66 
SECTION 18 - APPENDICES ...................................................................................................... APP-1 of 30 
 
Appendix 1 – Policy Statement for Calculating Delays and Damages 
Appendix 2 – Cost Reduction Incentive Proposals for Design Bid Build Agreements  
Appendix 3 – Contractor’s Affidavit Regarding Settlement of Claims 
Appendix 4 – Forms of Performance Bond 
Appendix 5 – Forms of Payment Bond 
Appendix 6 – Dispute Resolution 
Appendix 7 – Certificate of Completion 
Appendix 8 – Construction Sign Detail 
Appendix 9 – Cost of the Work (Applicable solely to Construction Manager at Risk and 
Job Order Contracting) 
Appendix 10 Landscape Establishment Period

General Conditions 
 
Revised: 7/20/22 
 
GC-3 of 75 
 
SECTION 1 - SCOPE OF THESE GENERAL CONDITIONS 
These General Conditions encompass provisions that apply, and are incorporated into all 
construction Agreements entered into by the City of Chandler, unless otherwise specifically excluded in 
the executed Agreement.  
 
SECTION 2 - GENERAL DEFINITIONS 
 
Allowance :  A specific amount for a specific item of Work, if any, that City agrees has not been sufficiently 
designed, detailed, or selected (including design changes from 90% to 100% as authorized by and at 
the discretion of the City) at the time the Agreement Price is agreed to for Contractor to provide a definitive 
price.  
 
Alternate Systems Evaluations or Alternative Analysis:  Alternatives for design, means and methods or 
other scope considerations that are evaluated using value analysis principles and have the potential to 
reduce construction costs while still delivering a quality and functional Project that meets City 
requirements. 
 
Change Order:  A written instrument issued after execution of the Agreement Documents signed by 
City and Contractor, stating their agreement upon all of the following: the addition, deletion or revision 
in the scope of services or deliverables; the amount of the adjustment to the Agreement Price, the 
extent of the adjustment to the Agreement Time, or modifications of other agreement terms. The 
Agreement Price and the Agreement Time may be changed only by Change Order. 
 
Consultant:  Person or firm that provides professional services. 
 
City (Owner or OWNER):  City of Chandler, a municipal corporation, with whom Contractor has entered 
into the Agreement and for whom the Work or Services are to be provided pursuant to the Agreement(s). 
 
Contingent Bid Items:  This is a minor bid item which is likely, but not certain, to occur during the course 
of work. If the Engineer determines that this work is required, the Contractor will accomplish the work 
and payment will be made based on the contingent unit bid price included in the proposal. Since the 
quantity listed in the proposal is primarily for bid comparison, the amount of work required by the 
Engineer may vary materially from this. 
 
Agreement:  The written agreement executed between City and Contractor, including all of the Agreement 
Documents. 
 
Agreement Documents:  The documents which together form the Agreement between City and 
Contractor, as identified in Article 2 of the Agreement, or are otherwise incorporated into the 
Agreement, including the Agreement, the exhibits thereto, these General Conditions, any Notice to 
Proceed, and any Job Order (if applicable), the Plans and Specifications, Project Schedule, written 
and properly executed Change Orders, MAG Specifications and City’s amendments thereto, and any 
other documents so designated in the Agreement. 
 
Agreement Price:  The agreed-upon price to be paid to Contractor for full, timely, and acceptable 
completion of the Work or Services under the terms of the Agreement. 
 
Agreement Time(s):  The number of calendar days or the dates related to the applicable phase, 
Substantial Completion, or Final Acceptance as stated in Agreement Documents. Agreement Time starts

General Conditions 
 
Revised: 7/20/22 
 
GC-4 of 75 
 
with the Notice to Proceed (NTP) and ends with Final Acceptance. The Agreement Time is set forth in 
the Agreement and is based upon the Project Schedule agreed to by City in writing. 
 
Contractor:  The person or business association with whom City has entered into an agreement for 
construction related Work or Services in relation to the Project at issue.  
 
Contractor Payment Request:  The form that is accepted by City and used by Contractor in requesting 
progress payments or final payment and which must include such supporting documentation as is 
required by the Agreement Documents or City. 
 
Construction Budget:  The City’s budget for construction of the Project. 
 
Construction Documents:  The Plans, Specifications, and Drawings prepared and issued by the Design 
Professional and approved by City for construction, meaning the documents are sealed by the 
Design Professional (as required), acceptable for permitting and incorporated into the Agreement by 
this reference. All amendments and modifications to the Construction Documents must be approved in 
writing by City prior to incorporation into the Agreement. 
 
Cost of the Work:  The term Cost of the Work will mean costs necessarily incurred by Contractor in the 
proper performance of the Work. Such costs will be at rates not higher than the standard paid at the 
place of the Project except with prior consent of City. 
 
Critical Path Method (CPM):  A scheduling technique which identifies the logical sequence of the activities 
occurring in a Construction Project, the anticipated time required to complete each activity in the 
Project, and the activities that must be completed on schedule to finish the Project within the anticipated 
time. Typically, activities are arranged in a network that shows both activities and their dependencies. 
CPM is also used as a management technique which enables contracting parties to predict when 
activities may occur so that resources can be effectively used and limitations can be identified.  
 
Critical Path:  Critical Path is the sequence of project network activities which add up to the longest overall 
duration. Once established in the Project Schedule, the Critical Path for the Project must not be 
changed without prior written approval of City. 
 
Day:  Calendar day(s) unless otherwise specifically stated in the Agreement Documents. 
 
Design Professional:  The qualified, licensed person, firm or corporation who furnishes design and 
construction administration services required under the Agreement Documents. These services may 
include, but are not limited to: development of Construction Drawings and Documents, review of 
Contractor Submittal(s), review of and response 
to 
Requests for Information, approval and 
certification of progress payment 
applications, 
construction administration, and construction 
agreement close out. 
 
Differing Site Conditions:  Concealed or latent physical conditions or subsurface conditions at the Site 
that, (i) materially differ from the conditions indicated in the Agreement Documents, or (ii) are of an 
unusual nature, differing materially from the conditions ordinarily encountered and generally recognized 
as inherent in the Work at the general area of the Site. Caliche, rock, hard-digging or sandy/silty soil 
encountered on a project is not considered a “Differing Site Condition.” 
 
Drawings (Plans):  Documents, which visually represent the scope, extent and character of the Work to 
be furnished and performed by Contractor during the construction phase and which have been prepared

General Conditions 
 
Revised: 7/20/22 
 
GC-5 of 75 
 
or approved by the Design Professional and City.  These documents include Drawings that have reached 
a sufficient state of completion and released by Design Professional solely for the purposes of review 
and use in performing constructability or bid-ability reviews by Contractor and in preparing cost 
estimates (e.g. Master Planning and Programming, Schematic Design, Design Development, and 
Construction Drawings), but “not for construction.” Shop Drawings are not Drawings as so defined. 
 
Final Acceptance:  The City’s acceptance of the facility or project from the Contractor after all Work is 
completed, tested, and inspected in accordance with the Agreement requirements. Final Acceptance 
results in a Letter of Acceptance (LOA). 
 
Fixed Price:  A fixed price or amount for an Agreement Price, Scope of Work, materials, or other item 
under an Agreement, Change Order, or other agreement, which City agrees, in writing, to pay instead 
of the actual cost.  
 
Float:  The number of Days by which an activity can be delayed without lengthening the Critical Path and 
extending the Agreement Time. Unless otherwise expressly agreed in writing, all Float belongs to City. 
 
Laws, Regulations, or Legal Requirements:  Any and all applicable laws, rules, regulations, ordinances, 
codes and orders applicable to the Project of any and all governmental bodies, agencies, authorities 
and courts having jurisdiction and any applicable provisions of the Development Agreement for the 
Project (if any), including, without limitation, those provisions relating to the design and construction 
of the Project. 
 
Line Item:  The individual elements of Work identified on a bid or other schedule and associated with a 
price or a unit price and quantity particular to that individual element of the Work. Also refers to 
individual items of work within the Schedule of Values. 
 
Liquidated Damages:  Designated damages for the City to collect as compensation upon a specific breach 
(example: late delivery). 
 
Long-Lead Item:  Long-lead item refers to the equipment, product, or system that is identified at the 
earliest stage of a project to have a delivery time long enough to affect directly the Critical Path/the overall 
lead time of the project. 
 
MAG:  The Maricopa Association of Governments. 
 
MAG Specifications:  The most current version of the Uniform Standard Specifications for Public Works 
Construction published by MAG. 
 
MAG Standard Details:  The most current version of the Uniform Standard Details as published by MAG. 
 
Minor change:  A change in the Work having no impact on cost or time or the City-approved design intent, 
as determined by City. 
 
Notice to Proceed (NTP):  A written notice given by City to Contractor fixing the date on which 
Contractor will start to perform Contractor’s obligations under the Agreement. 
 
Project:  The Project specified in the Agreement (including a Job Order). 
 
Project Manager:  The Project Manager designated in Article 1 of the Agreement, or any successor thereto

General Conditions 
 
Revised: 7/20/22 
 
GC-6 of 75 
 
designated by City. The Project Manager has the authority to act on behalf of City, as delineated and 
limited by the Agreement Documents and applicable law. And City will communicate with Contractor 
through the Project Manager. However, the Project Manager has no authority to bind City or City 
Council in contravention of any City code, State or Federal statute or regulation, or these General 
Conditions. 
 
Project Schedule:  The schedule for the completion of the Project agreed to and required by City. 
 
Project Specific Conditions:  Additional conditions which apply to the specific Project and Scope of Work 
which are set forth in Exhibit D of the Agreement. 
 
Project Team:  The Project Team consisting of the Design Professional, Contractor, Project Manager, and 
such others as City may designate. 
 
Punch List:  The list initially prepared by Contractor pursuant to the Agreement Documents, reviewed 
and supplemented by the Project Manager (and at the sole option of the Project Manager, the Design 
Professional) and approved by City containing items of incomplete work not impacting Substantial 
Completion, if allowed for under the Agreement, and to be completed or corrected by Contractor after 
Substantial Completion and before Final Acceptance in accordance with the Agreement Documents. 
 
Quality Assurance (QA) Testing:  Testing performed to verify the accuracy and applicability of the QC 
testing results and to ascertain that the materials installed meet the specified levels of quality in 
accordance with the Agreement Documents. 
 
Quality Control (QC) Testing:  Testing performed to assure that the materials installed comply with the 
requirements in the Agreement Documents. 
 
Requests for Information (RFIs):  Formal written request from Contractor to City or Design Professional 
for the Project seeking clarification or additional information needed for Contractor to properly 
complete the Work or Services under the Agreement. City may require RFI’s to be submitted on a specific 
form or in a specified format. 
 
Schedule of Values (SOV):  The specified document prepared by Contractor, and approved and accepted 
by City, which divides the Agreement Price into pay items, such that the sum of all pay items equals 
the Agreement Price for the construction phase Work, or for any portion of the Work having a separate 
specified Agreement Price. 
 
Scope of Work:  The scope of work agreed to or required by City and incorporated into the Agreement as 
Exhibit A. 
 
Shop Drawings:  All drawings, diagrams, schedules and other data specifically prepared for the Work 
by Contractor or a Subcontractor, Sub-subcontractor, manufacturer, supplier or distributor to 
illustrate some portion of the Work. 
 
Site:  The land or premises on which the Project is located. 
 
Specifications:  The part(s) of the Agreement Documents for the construction phase consisting of written 
technical descriptions of materials, equipment, construction systems, standards and workmanship as 
applied to the Work and certain administrative details applicable thereto. Where specified, the Project 
must be constructed using the current Uniform Standard Specifications and Details for Public Works

General Conditions 
 
Revised: 7/20/22 
 
GC-7 of 75 
 
Construction as furnished by the Maricopa Association of Governments, as amended by City. 
 
Subconsultant:  A person, firm or corporation having an Agreement with Consultant/Contractor to 
furnish services required as its independent professional associate or consultant with respect to the 
Project. 
 
Subcontractor:  An individual or firm having a direct Agreement with Contractor or any other individual or 
firm having an Agreement with the aforesaid contractors at any tier, who undertakes to perform a part 
of pre-construction services or construction phase Work at the Site for which Contractor is responsible. 
Subcontractors must be selected 
through the Subcontractor selection process described in the 
Agreement Documents, if any. 
 
Substantial Completion:  The date when the City determines that the Work (or separable units of Phases 
as provided in the Agreement Documents) is essentially and satisfactorily complete in accordance with 
the Agreement Documents such that the Project is ready for use by the City for its intended purpose, 
opening to the general public, full occupancy or use by City (including, without limitation, all separate 
units, or rooms, facilities, access, income-generating areas, and all areas serving the general public, as 
applicable, must be ready for full operation without material inconvenience or discomfort), including, to 
the extent applicable to the Work, the following: all materials, equipment, systems, controls, features, 
facilities, accessories, and similar elements are installed in the proper manner and in operating 
condition, inspected, and approved; surfaces have been painted; masonry and concrete cleaned with 
any sealer or other finish applied; utilities and systems connected and functioning; site work 
complete; permanent heating, ventilation, air conditioning, vertical transportation, and other systems 
properly operating with proper controls; lighting and electrical systems installed, operable and 
controlled; paving completed, signage installed, and other work as applicable, has been performed to 
a similar state of essential and satisfactory completion. 
 
Supplier:  A manufacturer, fabricator, distributor, or vendor having a direct Agreement with Contractor 
or with any Subcontractor to furnish materials or equipment to be incorporated in the construction 
phase Work by Contractor or any Subcontractor. 
 
Total Float:  Number of Days by which pre-construction services or construction phase Work or any part 
of the same may be delayed without necessarily extending a pertinent Agreement Time or schedule 
milestone in the Project Schedule. 
 
Work:  The entire completion of construction or the various separately identifiable parts thereof, 
required to be furnished during the construction phase. Work includes and is the result of performing 
or furnishing labor and furnishing and incorporating materials, resources and equipment into the 
construction, and performing or furnishing services and documents as required by the Agreement 
Documents for the construction phase. 
 
Writing:  Typing, printing, photography and other modes of representing or reproducing words in a 
visible form, including email, and expressions. 
 
SECTION 3 - STANDARD SPECIFICATIONS AND DETAILS 
3.1 
City operates under the latest revision of the MAG Specifications and MAG Standard 
Details as amended by City.  City’s current amendment to the MAG Specifications, part of 
the City’s Unified Development Manual, may be found and downloaded from City’s website 
at http://www.chandleraz.gov.

General Conditions 
 
Revised: 7/20/22 
 
GC-8 of 75 
 
3.2 
Copies of the MAG Specifications and MAG Standard Details are available at the 
Maricopa Association of Governments office, 302 N. 1st Avenue, Suite 300, Phoenix, 
Arizona. 
 
They 
may 
also 
be 
downloaded 
from 
their 
website 
at: 
http://www.azmag.gov/Newsroom/Publications 
3.3 
The MAG Specifications and Standard Details and City’s amendments thereto are 
incorporated into the Agreement by this reference. 
 
SECTION 4 - CONT R ACT OR’S R ES PONS IBILIT IES FOR CONST RUCT ION SE RVIC ES  
4.1 
GENERAL 
4.1.1 
Contractor must construct the Work in accordance with the Agreement Documents and as 
outlined in Exhibit A of the Agreement to the satisfaction of City, exercising the degree of 
professional care, skill, diligence, quality and judgment that a professional construction 
manager engaged, experienced and specializing in the construction management of 
construction and facilities of similar scope, function, size, quality, complexity and detail in 
urban areas throughout the United States comparable to Chandler, Arizona would exercise 
at such time, under similar conditions. Contractor must, at all times, perform the Work in 
conformance with sound and generally accepted engineering principles and construction 
management and construction contracting practices. 
4.1.2 
If Contractor observes errors, discrepancies or omissions in the Agreement Documents, 
Contractor must promptly notify the Design Professional and City and request clarification. 
If Contractor, with the exercise of reasonable care, should have recognized such error, 
inconsistency, omission, or difference and fails to report it to City, and if Contractor 
proceeds with the Work affected by such observed errors, discrepancies or omissions, 
without receiving such clarifications, Contractor does so at its own risk and will be liable to 
City for damages resulting from proceeding without clarification. 
4.1.3 
Project Team and agents of each of them, testing agencies and governmental agencies with 
jurisdictional interests will be provided access to the Work at reasonable times for their 
observation, inspection, and testing.  Contractor must provide proper and safe conditions 
for such access. 
4.1.4 
Contractor must comply with, and require all Subcontractors to comply with, the Arizona 
Contractors’ license laws, including all requirements with respect to being duly registered 
and licensed. 
4.1.5 
Contractor must ensure that all employees performing any Work for which Contractor is 
responsible have a legal right to live and work in the United States. In addition, all 
compensation of any such employee must meet all applicable requirements of the Fair Labor 
Standards Act (FLSA) and Federal Minimum Wage laws. 
4.1.6 
Contractor must comply with the Immigration Reform and Control Act of 1986 (IRCA).  
Contractor understands and acknowledges the applicability of the IRCA activities.  
Contractor agrees to comply with the IRCA while performing their work and to permit City 
inspection of Contractor personnel records to verify such compliance. 
4.1.7 
Pursuant to MAG Specifications §§ 107.4, Contractor must report immediately any discovery 
of archeological ruins or artifacts.  Excavation must stop immediately so that City can decide 
on the pertinent steps to follow such discovery.

General Conditions 
 
Revised: 7/20/22 
 
GC-9 of 75 
 
4.1.8 
All property owners that may be affected by the proposed construction activities must be 
notified of the scope, duration of the construction activities and possible interference with 
their day-to-day activities by Contractor prior to start of construction.  In addition, individual 
residential or commercial interferences, such as driveway restrictions, water outages, and 
all other Work adjacent to residence/business, require 48-hour notification in advance of 
specific adjoining Work.  Notification may be through door hangers or other procedures 
approved by the City. 
4.1.9 
Access must be maintained to adjacent properties at all times during construction. Where 
property has more than one point of access, no more than one access will be restricted or 
closed at any one time. Access to adjacent private driveways will be maintained during all 
non-working hours. 
4.1.10 
Contractor must furnish and erect construction signs in accordance with Project 
Specifications. The signs must be professionally prepared and subject to approval by City, 
must be maintained by Contractor for the duration of the project, and must be removed by 
Contractor during the final project clean up.  
4.1.11 
The number of signs required, the size, shape, installation requirements and information to 
be included for construction signs is established on the detail sheet, provided, however, 
signs must be a minimum of 4 foot by 8 foot and must be installed so that the bottom of 
the sign is at least 4 foot above grade.  No direct payment will be made for furnishing and 
erecting construction signs. The cost thereof must be included in other items for which 
direct payment is made. Sign locations will be determined by City. 
4.1.12 
All required construction signs must be installed by Contractor within 7 Days of Notice to 
Proceed.   
4.1.13 
The Work to be accomplished under these Agreement Documents has been designed for 
City by a Design Professional retained by City for this purpose.  It is understood that normal 
construction Administration for the purpose of interpretation of the Agreement Documents 
is provided by City. Should any services of the Design Professional be required to assist in 
the corrections of errors or omissions by Contractor, or services of the Design Professional 
be required because of changes in structure or equipment where Contractor has requested 
approval of substitute methods or material, or any other items detailed herein below, those 
services will be provided by the Design Professional at the standard hourly rates previously 
negotiated with City and must be paid for by the Contractor. 
4.1.14 
Contractor must reimburse City for costs incurred by the Design Professional for additional 
services to the Project through no fault of City or the Design Professional including, but not 
limited to, the following conditions: 
a. Additional Site visits, investigations, inspections, design work or reports by 
the Design Professional which are required due to damages to existing 
facilities or completed Work caused by the Contractor in his performance, 
Contractor’s negligence, or Contractor’s Work which is rejected as defective 
or as failing to conform to the Agreement Documents; 
b. Design Professional construction phase services rendered on the project 
during the time the project remains incomplete after the Agreement date of 
final completion will be charged to Contractor at a rate previously negotiated 
City; and

General Conditions 
 
Revised: 7/20/22 
 
GC-10 of 75 
 
c. All retesting required due to the failure of Contractor’s Work to meet the 
requirements of the Agreement Documents will be at Contractor’s expense.  
All standby and travel time by the City’s testing lab, the Design Professional 
or City due to Contractor’s inability to be prepared for testing at the agreed 
upon time will be at the Contractor’s expense. 
4.1.15 
City may withhold from any payment otherwise due to Contractor any amounts necessary 
to pay the Design Professional for such additional services as provided herein above.   
4.1.16 
Contractor will not be required to bear additional costs incurred by City due to errors by the 
Design Professional. 
4.2 
 CONTRACTOR’S PRE-AGREEMENT AND PRE-WORK DELIVERABLES 
4.2.1 
Prior to award of the Agreement, Contractor must execute Agreement and deliver to City.  
Failure to do so may delay Agreement award.  Contractor must also provide to City its 
Contractor’s License classification and number and its Federal Tax I.D. number. 
4.2.2 
Before beginning any Work under the Agreement, Agreement must be fully executed by 
City.  
4.2.3 
After Agreement award, City will issue to Contractor an award letter.  At that time Contractor 
must deliver to City such bonds and certificates of insurance with endorsements in such 
amounts (and other evidence of insurance requested by City) required under Section 11 of 
these General Conditions, and as the Agreement requires. 
4.2.4 
As evidence of Workmen’s Compensation Insurance, Contractor must, upon request, 
provide a letter of certification from the Industrial Commission of Arizona that Contractor 
is insured by the State Compensation Fund or is an authorized self-insurer or a certificate 
of insurance issued by an insurance company authorized by the Insurance Department 
of Arizona to write Workmen’s Compensation and Occupational Disease Insurance in the 
State of Arizona. 
4.2.5 
Within 10 Days of the date of the executed Agreement letter issued by City, Contractor must 
submit to City for review and acceptance the following items: 
4.2.5.1 
Comprehensive construction Project Schedule including a Critical Path Method (CPM) 
diagram schedule as described in Section 6.2.  Project Schedule must be in Microsoft Project 
standard file format.  Within 10 Days of receipt of City’s comments, Contractor must make 
all required corrections, adjustments, and additions to complete the Project Schedule and 
resubmit to City for review.   
4.2.5.2 
Preliminary schedule of submittals and Shop Drawings.  Within 10 Days of receipt of City’s 
comments, Contractor must submit the corrected and completed schedule of Shop 
Drawings submissions for approval.  Contractor’s schedule of Shop Drawings and sample 
submittals will be acceptable to City if it provides a workable arrangement for reviewing and 
processing the required submittals.   
4.2.5.3 
Schedule of Values in a form specified by City reflecting the subcontracts and other 
categories that will be used to submit Pay Applications for the Work. The total amount of 
the Schedule of Values must not be greater than the Agreement Price. The Schedule of 
Values will be reviewed at the Pre-Construction Conference and revised by Contractor within 
10 Days after Pre-Construction Conference in response to comments and questions from

General Conditions 
 
Revised: 7/20/22 
 
GC-11 of 75 
 
City. 
Once accepted by City in writing, the Schedule of Values for the Project must not be 
changed without the prior written approval of City. 
4.2.6 
Video Recording Requirement. Prior to performing any Work, Contractor must document 
the existing conditions of the Site, all other areas where Work will occur and all adjacent 
areas that may be impacted by the Work via digital video format.  Contractor must video 
record and index all areas, features, buildings and other public and private improvements 
that could potentially be impacted by the Work.  Video recording must be coordinated with 
City.  When video recording private property, Contractor must also coordinate the video 
recording with the private property owner, if possible.  Contractor must provide City with a 
copy of said digital video format prior to performing any Work. 
4.2.7 
Aerial Drone Construction Photography. 
4.2.7.1 
If Agreement duration is greater than 90 calendar days, Contractor must engage a 
professional unmanned aerial vehicle (UAV) aerial pilot to photograph the Site prior to 
construction mobilization, at three-month intervals during construction, and following final 
inspection.  Drone camera specifications must meet the following minimum requirements:  
a. 1-inch CMOS 
b. Pixels: 20M 
c. FOV 84  8.8 mm/24 mm (35 mm format equivalent) f/2.8-f/11 auto focus at 1 m-   
d. For photographing: 16.9 Aspect Ratio: 5472x3078 
e. For video shooting: MP4/MOV/H.264 
f. 
FHD: 1920x1080 120p @100Mbps 
g. File format: High Definition (HD) JPEG for digital photos and HD MPEG 4 for 
digital video. 
h. All metadata to be recorded including GPS data and preserved with photographs 
provided.   
 
Interval 
JPEG 
3 month intervals 
At an altitude (AGL) between 
70-90 ft. 
3 month intervals 
Images to be taken every 50-
100 ft. to be determined based 
on project scope. 
4.2.7.2 
Drone photos to be taken in sequential geographical order and then organized and provided in 
the same manner unless otherwise specified.   
4.2.7.3 
Photos to be provided digitally via an online file share service and/or by a USB drive to contractor. 
4.2.7.4 
Drone pilots to obey ALL local (city, county, state) UAV regulations as well as FAA UAV 
guidelines including, but not limited to, conducting all flights during daylight hours, not exceeding 
maximum altitude ceilings (depending on area), not flying over people, yielding to other aircraft. 
4.2.7.5 
Drone pilots must fly drone within visual line of sight (VSOL) and have visual spotter when 
needed. Drone pilots only to operate in favorable weather conditions when minimum visibility is 
3 miles or greater. 
4.2.7.6 
Drone pilots to conduct a preflight checklist and visually inspect the entire flight path prior to flying 
to ensure a safe flight.

General Conditions 
 
Revised: 7/20/22 
 
GC-12 of 75 
 
4.2.7.7 
Airspace Authorizations. Operations in Class G airspace are allowed without air traffic control 
(ATC) permission. Operations in Class B, C, D and E airspace need ATC authorization. Drone 
pilots to schedule each flight in advance and based on airspace if required will notify nearby 
airports/control towers, etc. 
4.2.8 
Government Approvals and Permits. 
4.2.8.1 
Contractor must obtain all necessary permits for the Work and pay all applicable fees, 
unless otherwise noted on the Plans and in the Specifications. City permit fees will be paid 
internally by City. For bidding purposes, an allowance for all permit fees is included in the 
bid schedule under the item “allowance for permit fees.” The Contractor will be paid for 
the actual cost of the permit fees upon submitting a receipt showing the fee Contractor 
has paid. Excluded from the above allowance are items such as all costs incurred by the 
Contractor in securing the permit except for the actual permit fee established by the 
agency, cost for all shutdowns or outages, cost for pole bracing, cost of permits for 
construction water, cost of construction water, cost for any additional insurance 
requirements, cost for any licenses, and other similar type costs. Contractor is specifically 
notified of the need to obtain the necessary environmental permits or file the necessary 
environmental and regulatory permit notices. 
4.2.8.2 
Copies of all permits and the associated notices must be provided to City prior to starting 
the permitted activity. 
4.3 
PRE-CONSTRUCTION CONFERENCE 
4.3.1 
Prior to the commencement of any Work, City will schedule a Pre-Construction Conference. 
4.3.2 
The purpose of this Conference is to establish a working relationship between Contractor, 
the utility firms, and various City agencies. The agenda will include critical elements of the 
Work schedule, submittal schedule, cost breakdown of major lump sum items, Payment 
Requests and processing, coordination with the involved utility firms, and emergency 
telephone numbers for all representatives involved in the course of construction. 
4.3.3 
Minimum attendance by Contractor at any mandatory meeting with City must be (1) 
Contractor’s Representative, who is authorized to execute and sign documents on behalf 
of the firm, (2) Contractor’s on-site Superintendent, and (3) Contractor’s Safety Office, 
or other employee responsible for safety. 
4.4 
PERFORMANCE OF THE WORK (INCLUDING FIELD MEASUREMENTS, 
SUBCONTRACTORS, AND SUPPLIERS) 
4.4.1 
Unless otherwise provided in the Agreement Documents to be the responsibility of City or a 
separate Contractor, Contractor must provide through itself or Subcontractors the 
necessary supervision, labor, inspection, testing, start-up, material, equipment, machinery, 
temporary utilities and other temporary facilities to permit Contractor to complete the 
Work consistent with the Agreement Documents. 
4.4.2 
Contractor must perform all construction activities efficiently and with the requisite 
expertise, skill and competence to satisfy the requirements of the Agreement Documents. 
Contractor must at all times exercise complete and exclusive control over the means, 
methods, safety, sequences and techniques of construction. 
4.4.3 
Contractor’s Superintendent must be present at the Site at all times that material Work

General Conditions 
 
Revised: 7/20/22 
 
GC-13 of 75 
 
under this Agreement is taking place. Contractor’s Superintendent or designee must be 
present at the Site at all times any other Work under this Agreement is taking place.  
Superintendent must not be replaced without written notice to City.  Whenever the 
Superintendent is not present at a particular part of the Work where the City or Design 
Professional may desire to inform the Contractor relative to interpretation of the Drawings 
and Specifications or to disapproval or rejection of materials or Work performed, the City 
or Design Professional may provide such information in writing to the foreman or other 
worker in charge of the particular part of the Work in reference to which the information is 
given.  Information so given will be as binding as if given to the Superintendent. 
4.4.4 
All elements of the Work must be under the direct supervision of a foreman or his 
designated representative on the Site who must have the authority to take actions required 
to properly carry out that particular element of the Work. 
4.4.5 
Working Hours.  Except in connection with the safety or protection of persons or the Work 
or property at the Site or adjacent thereto, and except as otherwise indicated, all Work at 
the Site must be performed during regular working hours, and Contractor will not permit 
overtime work or the performance of Work on Saturday, Sunday or any legal holiday without 
City’s written consent given after prior written notice to City.  If it will become absolutely 
necessary to perform Work at night or on Saturdays, Sundays or legal holidays, the City 
must be informed at least 24 hours in advance of the beginning of performance of such 
Work.  Only such Work will be done at night as can be done satisfactorily as determined by 
the City.  Good lighting and all other necessary facilities for carrying out and inspecting the 
Work must be provided and maintained at all points where such Work is being done.  
Further, unless such non-normal work hours are performed at City’s request or required by 
the Agreement Documents, Contractor must pay to City all additional costs incurred by City 
by reason of such non-normal working hours.  Expenses incurred by City for overtime 
compensation must be reimbursed by Contractor as follows: (i) City staff at the rate set forth 
in current City Fee Schedule as published on City website, (ii) Design Professional and staff 
at the standard hourly rates previously negotiated with City, and (iii) all others at actual cost 
plus ten percent administrative overhead.  Such costs may be deducted by City from any 
payments due to Contractor.  Provided, however, if overtime work or work during other 
than normal hours is at the request of City and not due to Contractor delay, City will pay the 
cost of City overtime expenses. 
4.4.6 
Where the Agreement Documents require that a particular product be installed or applied 
by an applicator approved by the manufacturer, it is Contractor’s responsibility to ensure 
the Subcontractor employed for such work is approved by the manufacturer.  All materials 
and equipment must be stored, applied, installed, connected, erected, used, cleaned and 
conditioned in accordance with the instructions of the applicable manufacturer, fabricator, 
supplier or distributor, except as otherwise provided in the Agreement Documents; but no 
provisions of any such instructions will be effective to impose on City of Design Professional 
responsibility for the means, methods, techniques, sequences or procedures of 
construction or for safety precautions incident thereto. 
4.4.7 
Before starting the Work, Contractor must carefully study and compare the various 
Plans, Drawings, other Agreement Documents, and Specifications relative to that portion 
of the Work, as well as the information furnished by City, must take field measurements of 
any existing conditions related to that portion of the Work and must observe any conditions 
at the Site affecting it. The exactness of grades, elevations, dimensions, or locations given 
on any Drawings, or the Work installed by other contractors, is not guaranteed by City.

General Conditions 
 
Revised: 7/20/22 
 
GC-14 of 75 
 
4.4.8 
Before ordering materials or doing Work, Contractor and each Subcontractor must verify 
measurements at the Site and will be responsible for the correctness of such 
measurements. No extra charge or compensation will be allowed because of differences 
between actual dimensions and the dimensions indicated on the Agreement Documents, 
including the Drawings. 
4.4.9 
Ground Level Construction Photography. 
4.4.9.1 
The Contractor must furnish progress photographs of the project.  The photographer 
selected by the Contractor must be approved by the City and must be either a commercial 
photographer or an individual experienced and equipped for such photography.   
4.4.9.2 
The Contractor must deliver to City all photographs taken during that period with each 
application for payment.  If the current photographs do not accompany the application, the 
application will not be reviewed and will be returned to the Contractor as incomplete. 
4.4.9.3 
Photographs must be identified by use of typewritten labels affixed to the back of the 
photograph.  The label must provide a description of the view, the direction from which the 
photograph was taken, the name of the project, City’s project number, the name of 
Contractor and the date of the photography.  The stationing must also be included for all 
pipeline installations.   
4.4.9.4 
Photographs must be taken during the construction period and must be of aesthetic 
composition and depict the progress of the Work from the beginning of construction 
through and including the finished product.  City may vary the specified frequency so that 
significant progress or changes can be recorded on the photographs.  
4.4.10 
Underground Facilities. 
4.4.10.1 
The existence and number of facilities as shown on the Plans are estimated from 
information furnished by the particular utility.  Contractor is responsible for field verification 
and location of all utilities prior to the start of construction.  No field work will be allowed to 
start until Contractor has contacted Arizona 811 and all affected utilities have been located.  
In addition, Contractor must expose and physically locate all potentially conflicting utilities 
prior to construction.  The actual locations of the utilities must be compared to locations 
shown on the Plans and any required changes in alignment and grade must be made at the 
time of construction in consultation with Project Manager.  It is generally recognized and 
Contractor should anticipate that information from Arizona 811 or information from utility 
companies during project design, frequently fails to disclose all underground facilities.  The 
fact that more utility lines or other underground facilities are located in the Project Site than 
shown on the Project Plans does not constitute an “unforeseen Condition” and such 
undisclosed underground facilities do not differ materially from the conditions which 
Contractor should expect. The provisions of Sections 105.4, 105.6, 107.11 and 109.8.1 of the 
MAG Uniform Standard Specifications for Public Works Construction apply and are 
incorporated herein by this reference.   
4.4.10.2 
Contractor is responsible for all coordination with utility companies.  The provisions of 
Sections 105.4, 105.6, 107.11 and 109.8.1 of the MAG Uniform Standard Specifications for 
Public Works Construction strictly apply and no additional compensation will be paid to 
Contractor for delays due to utility work on the project.  
4.4.11 
Relocation of Existing Water Meters.  When a service line has been extended and a line

General Conditions 
 
Revised: 7/20/22 
 
GC-15 of 75 
 
setter installed in a meter box, City forces will re-install meter.  No compression fittings will 
be utilized. 
4.4.12 
Water Turn-On or Turn-Off. 
4.4.12.1 
Contractor must coordinate all water line turn-ons and turn-offs through the City.  
Application must be made to the Municipal Utility Division and Contractor must pay the 
established charges.  The City will close existing valves, but will not guarantee a bone-dry 
Shutdown. 
4.4.12.2 
Contractor must notify all customers affected by the turn-off not less than 48 hours in 
advance.  Notification must be in writing, must give the reason for the turn-off and must 
give the estimated time and duration that water service will be interrupted. Contractor is 
also notified that water turn-off will not be permitted on the Day before and after 
Thanksgiving Day and Christmas Day. 
4.4.12.3 
No direct payment will be made to Contractor for turn-ons or turn-offs. Costs associated 
therewith will be included in other items for which direct payment is made. 
4.4.13 
Tests and Inspections. 
4.4.13.1 
Contractor must give City timely (at a minimum, twenty-four hours) notice of readiness of 
the Work for all required inspections, tests or approvals.  Contractor must give timely notice 
to City in advance of backfilling or otherwise covering any part of the Work so that city 
representative may, if desired, observe such part of the Work before it is concealed.  
Whenever Contractor varies the normal period during which Work or any portion of it is 
carried on each Day, Contractor must give timely notice to City so that city representative 
may, if desired, be present to observe the Work in progress.  If Contractor fails to give such 
timely notice, any Work done in the absence of city representative will be subject to 
rejection.  If Contractor gives such notice to City, but then is not ready for such inspections, 
tests, approvals or observations at the time so noticed, Contractor must reimburse City for 
all costs incurred by the attendance of city representatives.   
4.4.13.2 
If any law, ordinance, rule, regulation, code, or orders of any public body having jurisdiction 
requires any Work (or part thereof) to be inspected, tested or approved, Contractor (unless 
another party is specified in the Agreement Documents) must assume full responsibility 
therefor, pay all costs in connection therewith and furnish City the required certificates of 
inspection, testing, or approval. Contractor must also be responsible for and must pay all 
costs in connection with any inspection or testing required by the Specifications in 
connection with City's acceptance of a manufacturer, fabricator, supplier or distributor of 
materials or equipment proposed to be incorporated in the Work, or of materials or 
equipment submitted for approval prior to Contractor's purchase thereof for incorporation 
in the Work. The cost of all other inspections, tests and approvals required by the 
Agreement Documents will be paid by City (unless otherwise specified). 
4.4.13.3 
All inspections, tests or approvals other than those required by law, ordinance, rule, 
regulation, code or order of any public body having jurisdiction must be performed by 
organizations acceptable to City and by the Design Professional if so specified. 
4.4.13.4 
Neither observations by City, the Design Professional nor inspections, tests or approvals by 
others will relieve Contractor from their obligations to perform the Work in accordance with 
the Agreement Documents.

General Conditions 
 
Revised: 7/20/22 
 
GC-16 of 75 
 
4.4.14 
Uncovering Work.  If any Work that is to be observed, inspected, tested or approved is 
covered without written concurrence of City, it must, if requested by City be uncovered for 
observation. Unless Contractor has given City timely notice of Contractor's intention to 
cover such Work and City has not acted with reasonable promptness in response to such 
notice, Contractor must furnish all necessary labor, material and bear all the expenses of 
such uncovering, exposure, observation, inspection and testing and of satisfactory 
reconstruction, including compensation for additional professional services, and an 
appropriate deductive Change Order will be issued. 
4.4.15 
In all cases of interconnection of its Work with existing or other Work, Contractor must verify 
at the Site all dimensions relating to such existing or other Work.  Any errors due to 
Contractor’s failure to so verify all such grades, elevations, locations or dimensions must 
be promptly rectified by Contractor without any increase in the Agreement Price. Any 
design errors or omissions noted by 
Contractor during this review must be reported 
promptly to City. 
4.4.16 
Contractor must establish and maintain all construction grades, lines, levels, and 
benchmarks, and will be responsible for accuracy and protection of same. This Work 
must be performed or supervised by a licensed civil engineer or surveyor in the State of 
Arizona. 
4.4.17 
Contractor must photograph all buried piping of greater than four (4) inches in diameter 
prior to backfill.   
4.4.18 
Contractor is responsible for the proper performance of the work of Subcontractors and any 
acts and omissions in connection with such performance. Nothing in the Agreement 
Documents is intended or deemed to create any legal or contractual relationship 
between City and any Subcontractor or Sub-Subcontractor, including but not limited to any 
third-party beneficiary rights. 
4.4.19 
Contractor must coordinate the activities of all Subcontractors. Contractor must 
coordinate performance of the Work with City’s Public Works & Utilities Department and 
other departments or agencies within City. The Design Professional and other contractors 
or parties involved in the Project. If City performs other work on the Project or at the Site with 
separate contractors under City’s control, Contractor agrees to cooperate and coordinate 
its activities with those of such separate contractors so that the Project can be completed 
in an orderly and coordinated manner without unreasonable disruption. 
4.4.20 
Contractor will not substitute or change any Subcontractor or Supplier without the prior 
written approval of City. Any substitute or replacement Subcontractor or Supplier must 
be required to meet the same qualifications and selection criteria and process as the 
original Subcontractor or Supplier. If a Subcontract/Supplier selection plan has been 
approved by City, Contractor will follow that plan unless otherwise approved by City in 
writing. 
4.4.21 
Contractor must not change or replace any members of its Project team, including 
Contractor’s Representative, Project Manager, or Superintendent, without an explanation for 
the change being given to City, and receiving prior written approval of the change from City, 
which approval will not be unreasonably withheld. 
4.4.22 
Subcontractors whose scope of work has a value greater than 15% of the total Agreement 
Price are required to furnish performance and payment bonds to Contractor, unless

General Conditions 
 
Revised: 7/20/22 
 
GC-17 of 75 
 
otherwise approved in writing by City. 
4.4.23 
Contractor must comply with MAG Specification § 108.2 (E) unless otherwise specified in 
Agreement Documents. 
4.5 
CONTROL OF THE PROJECT SITE 
4.5.1 
Throughout all phases of construction, including suspension of Work, Contractor must keep 
the Site reasonably free from debris, trash and construction wastes to permit Contractor to 
perform its construction services efficiently, safely and without interfering with the use of 
adjacent land areas. 
Prior to Final Acceptance of the Work, or a portion of the Work, 
Contractor must remove all debris, trash, construction wastes, materials, equipment, 
machinery and tools arising from the Work or applicable portions thereof to permit City 
to occupy the Project or a portion of the Project for its intended use. 
4.5.2 
Contractor must take whatever steps, procedures or means necessary to prevent dust 
nuisance due to construction operations. The dust control measures must be maintained 
at all times to the satisfaction of City and in accordance with the requirements of the 
Maricopa County Bureau of Air Pollution Control Rules and Regulations. 
4.5.3 
Contractor must maintain Americans with Disabilities Act (ADA) and American National 
Standards 
Institute (ANSI) accessibility requirements during construction activities, 
including 
without 
limitation compliance with the 2010 regulations governing 
implementation of the ADA to the extent applicable. 
ADA and ANSI accessibility 
requirements must include, but not be limited to, parking, building access, areas of refuge, 
and emergency exit paths of travel. Contractor i s  responsible for the coordination of all 
Work to minimize disruption to residents and the public. 
4.5.4 
Only materials and equipment used directly in the Work will be brought to and stored on the 
Site by Contractor. When equipment is no longer required for Work, it must be removed 
promptly from the Site. Protection of construction materials and equipment stored at the 
Site from weather, theft, damage and all other adversity is solely the responsibility of the 
Contractor. 
4.5.5 
Contractor agrees all persons working on the Site must act at all times in the best interest 
of the Project and will comply with all applicable rules and regulations reasonably set forth 
by City related to the Site. Notwithstanding the foregoing or anything in this Agreement to 
the contrary, City may remove from the Site any individual who City deems in their 
reasonable discretion to be creating a disturbance or causing any problem on the Site. 
4.5.6 
Contractor will be responsible to City for the acts and omissions of Contractor’s employees, 
Subcontractors and their agents and employees, and any other person performing any of 
the Work under an Agreement with Contractor, or claiming by, through or under Contractor, 
for all damages, losses, costs and expenses resulting from such acts or omissions. 
4.5.7 
City may conduct criminal, drive history, and all other requested background checks of 
Contractor and Subcontractor personnel performing Work or who have access to City’s 
information, data, or facilities in accordance with City’s current background check policies, 
or the provisions of the Project Specific Conditions. Any officer, employee or agent that 
fails to background check must be replaced immediately. 
4.5.8 
City will have a final authority, based upon security reasons: (i) to determine when

General Conditions 
 
Revised: 7/20/22 
 
GC-18 of 75 
 
security clearance of Contractor’s and Subcontractor’s personnel is required; (ii) to determine 
the nature of the security clearance, up to and including fingerprinting personnel; and 
(iii) to determine whether or not any individual or entity may provide Services or perform 
Work under the Agreement. 
4.5.9 
If City objects to any personnel for any reasonable cause, then Contractor must, upon notice 
from City, remove such individual from the Project. 
4.6 
PROJECT SAFETY 
4.6.1 
The Project and all Work performed in relation thereto is governed by applicable provisions 
of the federal laws, including but not limited to, the latest amendments of the following: 
a. Williams-Steiger Occupational Safety & Health Act of 1970, Public Law, 91-596. 
b. Part 1910 and Part 1926 – Occupational Safety and Health Standards, 
Chapter XVII of Title 29, Code of Federal Regulations. 
c. Part 1518 – Safety and Health Regulations for Construction, Chapter XIII of 
Title 29, Code of Federal Regulations. 
4.6.2 
Contractor is responsible for safety of the job Site for employees of Contractor as well 
as for members of the general public and others who may drive or walk through or be at 
the Site.  
4.6.3 
Contractor recognizes the importance of performing the Work in a safe manner so as to 
prevent damage, injury or loss to: (i) all individuals at the Site, whether working or visiting; 
(ii) the Work, including materials and equipment incorporated into the Work and stored On-
Site or Off-Site; and (iii) all other property at the Site or adjacent thereto, including trees, 
shrubs, lawns, walks, pavements, roadways, structures and utilities not designated for 
removal, relocation or replacement in the course of construction; and (iv) the owners or 
tenants of adjacent property and their patrons, employees and invitees. 
4.6.4 
Contractor assumes responsibility for implementing and monitoring all safety precautions 
and programs related to the performance of the Work. 
4.6.5 
Contractor must provide a “competent person’ as required by O.S.H.A regulations. The 
“competent person” must be identified at the Pre-Construction Conference with City 
advised in writing of any changes. 
4.6.6 
The “competent person” must make routine daily inspections of the Site and must hold 
weekly safety meetings with Contractor’s personnel, Subcontractors and others as 
applicable. 
4.6.7 
Contractor and Subcontractors must comply with all legal and regulatory requirements 
relating to safety, as well as any City specific safety requirements set forth in the Agreement 
Documents, provided that such City-specific requirements do not violate any applicable 
legal and regulatory requirements. 
4.6.8 
Contractor will immediately report in writing any safety-related injury, loss, damage or 
accident arising from the Work to Project Manager and, to the extent mandated by Legal 
Requirements, to all government or quasi-government authorities having jurisdiction over 
safety-related matters involving the Project or the Work.

General Conditions 
 
Revised: 7/20/22 
 
GC-19 of 75 
 
4.6.9 
Contractor’s responsibility for safety under this Section is not intended in any way to 
relieve Subcontractors and Sub-Subcontractors of their own contractual and legal 
obligations and responsibility for (i) complying with all Legal Requirements, including those 
related to health and safety matters, and (ii) taking all necessary measures to implement 
and monitor all safety precautions and programs to guard against injury, losses, damages 
or accidents resulting from their performance of the Work. 
4.6.10 
As between City and Contractor, Contractor is responsible to City for any and all the safety 
issues relating to the Work on the Project. Contractor must administer and manage the 
safety program. This will include, but not necessarily be limited to review of the safety 
programs of each Subcontractor. Contractor must monitor the establishment and 
execution of compliance with all applicable regulatory and advisory agency construction 
safety standards. Contractor’s responsibility for review, monitoring, and coordination of the 
Subcontractor’s safety programs will not extend to direct control over execution of the 
Subcontractors’ safety programs. Notwithstanding Contractor’s safety obligations to City, 
it is agreed and understood that each individual Subcontractor will remain controlling 
employer responsible for the safety programs and precautions applicable to its own work 
and the activities of other’s work in areas designated to be controlled by such Subcontractor 
for purposes of workers compensation insurance coverage. 
4.6.11 
Nothing in this agreement will relieve Contractor of his responsibility to maintain traffic, 
structures, etc., as noted on the Plans, Specifications, and Project Specific Conditions. 
Contractor is responsible to provide all necessary shoring, bracing and trench support as 
is necessary to maintain traffic structures, etc., as stipulated in the Plans, Specifications, and 
Special Provisions. If the stability of adjoining building, walls, roadways, etc., is endangered 
by Contractor’s excavation, shoring, bracing, or under pinning must be provided as 
necessary to ensure project safety. Cost for shoring, bracing, underpinnings, and trench 
support will be included in the appropriate items listed in the Agreement Price, and no 
additional payment will be made for this work. 
4.7 
MATERIALS QUALITY, SUBSTITUTIONS, AND SHOP DRAWINGS 
4.7.1 
Quality Control and Quality Assurance Testing. 
4.7.1.1 
All construction materials to be used or incorporated in the Project are subject to 
inspection, Quality Control & Quality Assurance Testing, and approval or rejection by City. 
Any material rejected by City must be removed immediately and replaced in an acceptable 
manner to City at no additional cost to City. When QC/QA tests indicate noncompliance 
with the Agreement Documents, retesting must be performed by the same testing 
laboratory that performed the tests that indicated noncompliance. 
4.7.1.2 
The Contractor must establish, provide, and maintain an effective Quality Control Testing 
Program (QCTP). The Contractor must develop his own program or procure the services of 
a consultant. In either case, the party performing the tests must be currently certified by the 
National Bureau of Standards in the National Voluntary Laboratory Accreditation Program 
(NVLAP) for construction 
services or the AASHTO Accreditation Plan (AAP) for Soils, 
Asphalt and Concrete. The Contractor must provide all support necessary to perform QC 
and QA testing and sampling (i.e. shoring for testing trench backfill, backhoes, motor 
graders, loaders, etc. to facilitate testing and sampling). The City will perform the QA testing. 
4.7.1.3 
The Contractor must submit a written QCTP to the City as a required submittal. The 
Contractor must not begin Work until the Quality Control Program has been reviewed and

General Conditions 
 
Revised: 7/20/22 
 
GC-20 of 75 
 
accepted by the City. Resumes of all personnel that will be associated directly or indirectly 
with the QCTP must be included. 
4.7.1.4 
The QCTP must include, but not be limited to, on-site/field and laboratory testing of all 
material delivered to the Site and any existing materials or conditions pertinent to the 
project. 
4.7.1.5 
All testing must be under the direction of a Professional Engineer registered in the State of 
Arizona, knowledgeable in Materials Testing. All “Test Report” forms must be stamped by 
said Engineer. 
4.7.1.6 
The written QCTP will set forth the responsibilities of the engineer, project manager, 
supervisory personnel and each technician assigned to this project. Substitutions or 
replacement of personnel must require prior written approval by the City. All personnel must 
be proficient within their assigned duties and possess certification(s) commensurate with 
their position and responsibilities. The minimum certification(s) for each technician must 
be NICET Level II, Arizona Technical Testing Institute, American Concrete Institute, or other 
nationally recognized program applicable to the project and approved by the City of 
Chandler. The written QCTP must include a description of the required field and 
construction materials laboratory tests, including required frequencies that meet the 
minimums established herein. 
4.7.1.7 
The Contractor must establish a system to record and report all material test results.  The 
daily test reports must include, but not be limited to: 
a. Test designation; 
b. Date of test; 
c. Name of tester; 
d. Location of test/sample (station and offset); 
e. Product suppliers and product codes (as applicable); 
f. 
Depth/elevation of test/sample; 
g. Test result; 
h. Control requirement(s); 
i. 
Cause of rejection (if applicable); 
j. 
Results of retests (if applicable); and 
k. Remedial action (if applicable). 
4.7.1.8 
The Contractor must submit test results to the designated City representative.   
4.7.1.9 
The Contractor must also submit a weekly report to the City summarizing the testing 
and construction activities completed by emailing the report to the email addresses noted 
above. All weekly reports must be submitted simultaneously to the Contractor and the 
City of Chandler. The report must include individual summary sheets for each utility line, 
structure, and portion of the pavement section. Cores must be numbered sequentially 
throughout the Project. Re-cores must reference the original core by number and must 
contain the averaged values for thickness and density. Total pavement thickness must be 
reported. Vertical location of tests for underground utilities must indicate the depth of the

General Conditions 
 
Revised: 7/20/22 
 
GC-21 of 75 
 
excavation at the location of the test (i.e., cut to flow line [if applicable], depth to bottom 
or top of pipe, etc.). Density tests must be numbered sequentially. If the minimum number 
of tests has not been performed per the written QCTP, this must be stated in the weekly 
summary report with an explanation of the circumstances. 
4.7.1.10 
The City will maintain a copy of the Project test results and weekly reports in the Project 
file. In cases where quality control activities do not comply with the Agreement provisions, 
the City may: 
a. Order the Contractor to replace ineffective or unqualified quality control 
personnel. 
b. Order the Contractor to stop operations until appropriate corrective action is 
taken. 
4.7.1.11 
Although minimum testing requirements are specified herein, the Contractor bears full 
responsibility for the quality of the materials and their installation and may elect to 
perform additional testing beyond the requirements set forth herein to ensure compliance. 
4.7.1.12 
The Quality Control requirements contained in this Section are in addition to and separate 
from Quality Assurance Testing, which will be performed by the City of Chandler or its 
representative. If the Quality Assurance test results are not in agreement with the Quality 
Control test results, the Contractor will have the option to retain a third party consultant for 
referee tests. The third party consultant must meet the same requirements as the 
consultant performing the Quality Control Testing. The results of the third party will be 
binding. All cost incurred by the referee testing will be the Contractor’s expense. If the 
Contractor elects not to retain a third party for referee testing, the City of Chandler test 
results will prevail. 
4.7.1.13 
Except as otherwise noted within this Section, Work or materials required by this Section are 
non- pay items. Per MAG Section 101, a non-pay item is an item of Work for which no 
separate payment will be made, the cost of which is to be included as an incidental cost 
for associated item(s) included on the Bid Schedule or Schedule of Values. 
4.7.2 
Trade Names and Substitutions. 
4.7.2.1 
Substitutions prior to bid will only be considered if in compliance with Arizona Revised 
Statute § 34-104. 
4.7.2.2 
Contractor, if requested by City, must submit Samples or any additional information that 
may be necessary to evaluate the acceptability of the substitution. 
4.7.2.3 
City will make the final decision and will notify Contractor in writing as to whether the 
substitution has been accepted or rejected. 
4.7.2.4 
If City does not respond within 15 working days, Contractor must continue to perform the 
Work in accordance with the Agreement Documents and the substitution will be considered 
rejected. 
4.7.3 
Shop Drawings. 
4.7.3.1 
Contractor must prepare and submit Shop Drawings which show details of all Work to insure 
proper installation of the Work using those materials and equipment specified under the 
approved Plans and Specifications.

General Conditions 
 
Revised: 7/20/22 
 
GC-22 of 75 
 
4.7.3.2 
Contractor must submit a schedule of Shop Drawing submissions, which avoids bulk 
submissions to the extent reasonably possible, with the Project Schedule for City approval.  
The schedule of Shop Drawing submissions must include all of the items for which Shop 
Drawings are required by the Agreement Documents, including the Specifications. Unless 
otherwise noted, Shop Drawings will not be required for items specified or detailed in 
the Uniform Standard Specifications and Details or the Technical Specifications.  
4.7.3.3 
Shop Drawings must be numbered consecutively for each Specification section and must 
accurately and distinctly present the following: 
a. All working and erection dimensions. 
b. Arrangements and sectional views. 
c. Necessary details, including complete information for making connections 
between work under this Agreement and work under other Agreements. 
d. Kinds of materials and finishes. 
e. Parts list and description thereof. 
4.7.3.4 
Each Drawing or page must include: 
a. Project Name, City of Chandler Project Number and descriptions. 
b. Submittal date and space for revision dates. 
c. Identification of equipment, product or material. 
d. Name of Contractor and Subcontractor. 
e. Name of Supplier and Manufacturer. 
f. 
Relation to adjacent structure of material. 
g. Physical dimensions clearly identified. 
h. ASTM and Federal Specifications references. 
i. 
Identification of and justification for deviations from the Agreement 
Documents. 
j. 
Contractor’s stamp, initialed or signed, dated and certifying the review 
of submittal, certification of field measurements and compliance with 
Agreement. 
k. Location at which the equipment or materials are to be installed. 
4.7.3.5 
Location will mean both physical location and location relative to other connected or 
attached material. City will return unchecked any submittal, which does not contain 
complete data on the Work and full information on related matters. 
4.7.3.6 
Stock or standard drawings will not be accepted for review unless full identification and 
supplementary information is shown thereon in ink or typewritten form. 
4.7.3.7 
Contractor must schedule, prepare and submit all Shop Drawings in accordance with a time-
table 
that will allow its suppliers and manufacturers sufficient time to fabricate, 
manufacture, inspect, test and deliver their respective products to the project Site in a 
timely manner so as to not delay the complete performance of the Work.

General Conditions 
 
Revised: 7/20/22 
 
GC-23 of 75 
 
4.7.3.8 
If the Shop Drawings show departures from the Agreement requirements, Contractor 
must make specific mention thereof in the Letter of Transmittal; otherwise review of such 
submittals by City will not constitute review of the departure. Review of the Drawings will 
constitute review of the specific subject matter for which the Drawings were submitted 
and not of any other structure, material, equipment, or apparatus shown on the Drawings. 
4.7.3.9 
The review of Shop Drawings will be general and will not relieve Contractor of responsibility 
for the accuracy of such Drawings, nor for the proper fitting and construction of the Work, 
nor for the furnishing of materials or Work required by the Agreement. No construction 
called for by Shop Drawings will be initiated until such Drawings have been reviewed and 
approved by City. 
4.7.3.10 
The procedure in seeking review of the Shop Drawings will be as follows: 
a. Contractor must submit complete sets of Shop Drawings and other 
descriptive data as specified in this Section. 
b. After Contractor’s submittal or resubmittal of Shop Drawings, if Contractor 
has submitted Shop Drawings in accordance with the City-approved 
submittal schedule, or upon resubmission, City will be provided with three 
(3) calendar weeks for review. Should City require additional review time 
above and beyond the three (3) calendar weeks, Contractor may ask for a 
time extension or monetary compensation, if they can present valid, factual 
evidence that actual damages were incurred by Contractor. City will 
determine 
the amount of the time extension or the monetary 
compensation to be awarded Contractor, if any, in accordance with City’s 
Policy Statement for Calculating Delays and Damages, Appendix 1. 
4.7.3.11 
Contractor will be responsible for all extra costs incurred by City caused by Contractor’s 
failure to comply with the procedure outline above. 
4.7.4 
Long Lead Time Items. Contractor must submit Shop Drawings, as required by the Engineer, 
on all long lead items to be furnished and installed as part of the project within 10 Days 
after the date of the executed Agreement letter issued by City. In addition, 
Contractor must order all long lead items to be furnished and installed as part of this 
Project within 3 Days after receiving approved Shop Drawings. For all long lead times for 
which Shop Drawings are not required, Contractor must order said long lead items within 
15 Days after the date of the executed Agreement letter issued by City. Within 2 Days 
after ordering long lead items, Contractor must supply copies of all purchase orders, 
along with an accurate delivery schedule from the supplier. 
4.7.5 
Construction Water. If Contractor uses water from City’s water system for construction 
water, Contractor must obtain a fire hydrant meter from City of Chandler Utility Services 
(480-782-2280) and all construction water must be obtained through the hydrant meter. 
Contractor must pay all fees related to the hydrant meter and all water bills for construction 
water. All cost for meters and construction water will be included in the Agreement Price. 
4.8 
PROJECT RECORD DOCUMENTS 
4.8.1 
During the construction period, Contractor must maintain at the jobsite a full-size set of 
prints of the Construction Document Drawings and Shop Drawings for Project Record 
Document purposes.

General Conditions 
 
Revised: 7/20/22 
 
GC-24 of 75 
 
4.8.2 
Contractor must mark these Drawings to indicate the actual installation where the installation 
varies from the original Construction Documents. Contractor must give particular attention 
to information on elements that will be concealed, which would be difficult to identify or 
measure and record later. Items required to be marked include but are not limited to: 
a. Dimensional changes to the Drawings. 
b. Revisions to details shown on Drawings. 
c. Locations and depths of underground utilities. 
d. Revisions to routing of piping and conduits. 
e. Actual equipment locations. 
f. 
Changes made by Change Order or Addendum. 
g. Details not on original Agreement Drawings. 
4.8.3 
Contractor must mark completely and accurately Project Record Drawing sets of 
Construction Documents. 
4.8.4 
Contractor must mark Project Record Drawings sets with red erasable colored pencil. 
4.8.5 
Contractor must note Request for Information (RFI) Numbers and Change Order numbers, 
etc., as required to identify the source of the change to the Construction Documents. 
4.8.6 
Contractor must submit Project Record Drawing sets and Shop Drawings to City or its 
representative for review and comment. 
4.8.7 
Upon receipt of the reviewed Project Record Drawings from City, Contractor must correct 
any deficiencies and omissions to the Drawings and submit the final original of the Project 
Record Drawings to City prior to Final Payment. 
4.8.8 
Project Manager will review the Project Record Drawings monthly prior to the date 
established for the Payment Request and will be the sole judge of acceptance of these 
Drawings. 
4.9 
WARRANTY AND CORRECTION OF DEFECTIVE WORK 
4.9.1 
Contractor warrants to City that the construction, including all materials and equipment 
furnished as part of the Work, will be new unless otherwise specified in the Agreement 
Documents, of good quality, and free of defects in materials and workmanship.  Contractor’s 
warranty obligation excludes defects caused by abuse, alterations, or unreasonable failure 
to maintain the construction by persons other than Contractor, subcontractors, or others 
under Contractor’s control.  Nothing in this warranty will limit any manufacturer’s warranty 
which provides City with greater warranty rights than set forth herein or in the Agreement.  
Contractor will provide City with all manufacturers’ warranties and operation and 
maintenance manuals upon substantial completion of the Work.  Contractor’s warranty 
must be for one (1) year, in accordance with MAG Specification § 108.8, and will commence 
for all portions of the Work upon Final Acceptance of the entire Work as determined by City 
under the Agreement.  All statutory or other warranties, express or implied, related to latent 
defects will remain in force and are not limited by this provision. 
4.9.2 
City May Stop the Work.  If the Work is defective, or Contractor fails to supply sufficient 
skilled workmen or suitable materials or equipment, City may order Contractor to stop the

General Conditions 
 
Revised: 7/20/22 
 
GC-25 of 75 
 
Work without cost to City, or any portion thereof, until the cause for such order has been 
eliminated; however, this right of City to stop the Work will not give rise to any duty on the 
part of City to exercise this right for the benefit of Contractor or any other party. 
4.9.3 
Correction or Removal of Defective Work. 
4.9.3.1 
If required by City, Contractor must promptly, without cost to City and as specified by City, 
either correct any defective Work, whether or not fabricated, installed or completed, or, if 
the Work has been rejected by City, remove it from the Site and replace it with non-defective 
Work. Contractor must correct any Work which may be displaced in correcting, removing or 
replacing defective Work. No compensation will be allowed Contractor for such removal, 
replacement or remedial Work.  Contractor must reimburse City for costs incurred by City 
due to such correction or removal including but not limited to additional expenses for 
inspection, testing or observation and for repeated reviews by the City or Design 
Professional.   
4.9.3.2 
Upon failure on the part of the Contractor to comply within a reasonably prompt time with 
any written order of City to correct or remove defective Work, City has authority to cause 
nonconforming materials or rejected Work to be remedied, removed, or replaced at the 
Contractor's expense and to deduct the costs from any moneys due or to become due the 
Contractor. 
4.9.4 
City May Correct Defective Work.  If Contractor fails within a reasonable time after written 
notice of City to proceed to correct defective Work or to remove and replace rejected Work 
as required by City or if Contractor fails to perform the Work in accordance with the 
Agreement Documents (including any requirements of the progress schedule), City may, 
after 7 Days' written notice to Contractor, correct and remedy any such deficiency.  To the 
extent necessary to complete corrective and remedial action, City may exclude Contractor 
from all or part of the Work, and suspend Contractor's services related thereto, take 
possession of Contractor's tools, appliances, construction equipment and machinery at the 
Site and incorporate in the Work all materials and equipment stored at the Site or for which 
City has paid Contractor, but which are stored elsewhere. Contractor must allow City, city 
representatives, agents and employees such access to the Site as may be necessary to 
enable City to exercise City’s rights under this Section.  All direct and indirect costs of City in 
exercising such rights will be charged against Contractor in an amount verified by City 
representative, and a Change Order will be issued incorporating the necessary revisions in 
the Agreement Documents and a reduction in the Agreement Price.  Such direct and indirect 
costs will include, in particular but without limitation, compensation for additional 
professional services required and all costs of repair and replacement of Work or others 
destroyed or damaged by correction, removal or replacement of Contractor's defective 
Work. Contractor will not be allowed an extension of the Agreement Time because of any 
delay in Contractor’s performance of the Work attributable to the exercise by City or City's 
rights hereunder. 
4.9.5 
Correction or Removal of Unauthorized Work. 
4.9.5.1 
Any Work done beyond the lines and grades shown on the Drawings or established by the 
Design Professional or any changes in, additions to, or deductions from the Work done 
without written authority will be considered as unauthorized and will not be paid for. Work 
so done may be ordered remedied, removed, or replaced at the Contractor's expense. 
4.9.5.2 
Upon failure on the part of the Contractor to comply promptly with any order of the City,

General Conditions 
 
Revised: 7/20/22 
 
GC-26 of 75 
 
City will have authority to cause unauthorized Work to be remedied, removed, or replaced 
at the Contractor's expense and to deduct the costs from any moneys due or to become 
due the Contractor. 
4.9.6 
Correction Period - One Year Guarantee. 
4.9.6.1 
If, within one year after the date of Final Acceptance, or such longer period of time as may 
be prescribed by law or by the terms of any applicable special guarantee required by the 
Agreement Documents, or by any specific provision of the Agreement Documents, any Work 
is found to be defective, Contractor must promptly, without cost to City and in accordance 
with City's written instructions, either correct such defective Work, or, if it has been rejected 
by City, remove it from the Site and replace it with non-defective Work. If Contractor does 
not promptly comply with the terms of such instructions, or in an emergency where delay 
would cause serious risk of loss or damage, City may have the defective Work corrected or 
the rejected Work removed and replaced, and all direct and indirect costs of such removal 
and replacement, including compensation for additional professional services, must be paid 
by Contractor. Such action by the City will not relieve the Contractor of the guarantees 
required by this Section or elsewhere in the Agreement Documents.  
4.9.6.2 
If, in the opinion of the City, defective Work creates a dangerous condition or requires 
immediate correction or attention to prevent further loss to the City or to prevent 
interruption of operation of the City, the City will attempt to give the notice required by this 
Section.  If the Contractor cannot be contacted or does not comply with the City's request 
for correction within a reasonable time as determined by the City, the City may, 
notwithstanding the provisions of this Section, proceed to make such correction or provide 
such attention; and the costs of such correction or attention will be charged against the 
Contractor.  Such action by the City will not relieve the Contractor of the guarantees 
required by this Section or elsewhere in the Agreement Documents. 
4.9.6.3 
This Section does not in any way limit the guarantee on any items for which a longer 
guarantee is specified or on any items for which a manufacturer or supplier gives a 
guarantee for a longer period. The Contractor agrees to act as co-guarantor with such 
manufacturer or supplier and must furnish the City all appropriate guarantee or warranty 
certificates upon completion of the Project.  No guarantee period, whether provided for in 
this Section or elsewhere, will in any way limit the liability of Contractor or their sureties or 
insurers under the indemnity or insurance provisions of these General Conditions and the 
Project Specific Special Conditions. 
4.9.7 
Acceptance of Defective Work. 
4.9.7.1 
If, instead of requiring correction or removal and replacement of defective Work, City may 
accept Work when in the best interest of the City to do so with appropriate monetary credit 
from Contractor.  If any such acceptance occurs prior to final payment, a Change Order will 
be issued incorporating the necessary revisions in the Agreement Documents, including 
appropriate reduction in the Agreement Price; or, if the acceptance occurs after final 
payment, an appropriate amount must be paid by Contractor to City. 
4.9.7.2 
Alternatively, City may require Contractor to furnish at Contractor's expense, a special 
performance guarantee or other surety prior to acceptance of defective work. 
4.9.8 
The Warranty period begins on the Final Acceptance date noted in the Certificate of 
Completion, irrespective of early completion by some Subcontractors of their work.

General Conditions 
 
Revised: 7/20/22 
 
GC-27 of 75 
 
4.9.9 
Contractor’s warranty obligation must be in accordance with MAG Specifications. 
4.9.10 
Nothing in the warranties contained in the Agreement Documents are intended to limit any 
manufacturer’s warranty which provides City with greater warranty rights than set forth 
in this Section or the Agreement Documents. Contractor must provide City with all 
manufacturers’ warranties 
prior to Substantial Completion, if applicable, or Final 
Acceptance. 
4.9.11 
Contractor agrees that it will be responsible to manage and administer the correction of any 
Work that is not in conformance with the Agreement Documents during the warranty 
periods set forth in this Section, or during any longer periods to the extent required by the 
Agreement Documents. A progress payment, or partial or entire use or occupancy of the 
Project by City, will not constitute acceptance of Work not in accordance with the Agreement 
Documents. 
4.9.12 
When notified of a warranty issue, Contractor must respond in writing within 48-hours and 
must perform warranty Work as soon as material for said repairs are available (as judged 
solely by City), and in any event Contractor must, take immediate steps to commence and 
complete correction of nonconforming Work no later than the time period set forth in 
City’s written notification in accordance with the Agreement Documents. This includes the 
correction, removal or replacement of the nonconforming Work and any damage caused 
to other parts of the Work affected by the nonconforming Work. If defects develop which 
are determined by City to be an emergency, City will notify Contractor, via the most 
expeditious means regarding the nature and condition of the defects. In turn, Contractor 
must immediately dispatch necessary forces to correct the defect or the emergency 
condition in accordance with Agreement Documents. 
4.9.13 
The time periods referenced in this Section apply only to Contractor’s obligation to 
correct nonconforming Work and is not intended to constitute a period of limitations for any 
other rights or remedies that City may have regarding Contractor’s other obligations under 
the Agreement Documents. 
4.9.14 
Without limiting the foregoing or anything in these General Conditions or the Agreement 
to the contrary, Contractor must obtain and provide to City all warranties for any portion 
of the Project offered by the manufacturer, installer or provider thereof. City and the user 
of the facility will have the right to the full value and benefit of all such warranties. 
Contractor must ensure all such warranties are fully transferrable to facilitate the full value 
of this Section. 
4.9.15 
Contractor’s warranty excludes damages or defects caused by abuse, alterations to the Work 
not executed by or through Contractor, improper or insufficient maintenance, improper 
operation, or normal wear and tear and normal usage. 
4.9.16 
In the event of any noncompliance with this entire Section 4, City may require Contractor to 
stop or suspend the Work in whole or in part. 
 
SECTION 5 - CITY RESPONSIBILITIES 
5.1 
CITY PROJECT MANAGER AND INSPECTORS 
5.1.1 
Project Manager is responsible for providing City-supplied information and approvals in a 
timely manner to assist Contractor to fulfill its obligations under the Agreement Documents.

General Conditions 
 
Revised: 7/20/22 
 
GC-28 of 75 
 
5.1.2 
Project Manager will also provide Contractor with prompt notice when it observes any 
failure on the part of Contractor to fulfill its contractual obligations, including any default 
or defect in the Project or non-conformance with the Drawings and Specifications. 
5.1.3 
City may utilize Field Inspectors to assist Project Manager during construction in 
observing performance of Contractor. City’s use of Inspectors is for the purpose of assisting 
Project Manager. 
5.1.4 
The Inspectors are authorized to inspect all Work and materials furnished. Such inspections 
may extend to all or part of the Work and to preparation, fabrication or manufacture of the 
materials to be used.  The Inspectors have the authority to issue instructions contrary to 
the Construction Documents if approved and coordinated with the directions of Project 
Manager. 
5.1.5 
The Inspectors have the authority to reject work or materials until any questions at issue can 
be decided by Project Manager. 
5.1.6 
The use of Inspectors by City will not make City responsible for or give City control 
over construction means, methods, techniques, sequences or procedures or for safety 
precautions or programs or responsibility for Contractor’s failure to perform the Work in 
accordance with Agreement Documents. The Inspectors are not authorized to direct any of 
Contractor’s activities, employees or Subcontractors. 
5.2 
DESIGN PROFESSIONAL SERVICES 
City may contract separately with one or more Design Professionals to provide 
construction administration of the Project. The Design Professional’s Agreement, as well as 
other firms hired by City may be furnished to Contractor. Contractor does not have the right 
to limit or restrict or reject any Agreement modifications that are mutually acceptable to City 
and Design Professional. 
5.3 
 CIT Y ’S SEP AR AT E CONT R ACT ORS 
City is responsible for all work performed on the Project or at the Site by separate 
contractors retained by City. City will contractually require its separate contractors to 
reasonably cooperate with, and reasonably coordinate their activities so as not to interfere 
with Contractor in order to enable Contractor to timely complete the Work consistent with 
the Agreement Documents. Contractor must immediately notify the Project manager, 
and address the matter in the next monthly status report, if any activities of such separate 
contractors are expected to interfere, or are interfering, with Contractor and such 
interference will or could result in any delay in Contractor’s performance of the Work. 
5.4 
PERMIT REVIEW AND INSPECTIONS 
5.4.1 
If requested by Contractor, Project Manager will provide assistance and guidance in 
obtaining necessary reviews, permits and inspections. 
5.4.2 
The regulating agencies of City, such as Development and Sustainability, Fire and 
Planning Departments, enforce legal requirements. The enforcement activities of City are 
independent and separate from this Agreement. 
5.5 
PLANS AND SPECIFICATIONS TO THE CONTRACTOR.   
Contractor will be provided up to five copies of the Agreement Documents as are 
reasonably necessary for the execution of the Work.  Additional copies will be furnished,

General Conditions 
 
Revised: 7/20/22 
 
GC-29 of 75 
 
upon request, at the cost of reproduction.   
 
SECTION 6 - AGREEMENT TIME 
6.1 
AGREEMENT TIME 
6.1.1 
The Agreement Time will start with the Notice to Proceed (“NTP”) and end with Final 
Acceptance.  
6.1.2 
Beginning on the date of the NTP, Contractor must begin to fulfill Contractor’s obligations 
under the Agreement. Contractor’s obligations include providing City and other 
agencies with any submittals required by the Project Specific Special Provisions, including 
but not limited to, an approved Project Schedule, Traffic Control Plans, and a Stormwater 
Pollution Prevention Plan. Contractor must submit all such required submittals before 
any physical construction work commences on the Site. NTP does not authorize 
construction work until all a greement insurance, bonds, and schedules are submitted to 
and accepted by the City. 
6.1.3 
The Agreement Time will be as set forth in the Project Schedule. Contractor agrees that 
it will commence performance of the Work and complete the Project through both 
Substantial Completion and Final Acceptance within the Agreement Time. 
6.1.4 
Time is of the essence of this Agreement, for the Project, for the Work, and for each phase 
and designated Milestone thereof. 
6.1.5 
Failure of Contractor to perform any covenant or condition contained in the Agreement 
Documents within the time periods specified herein, will constitute a material breach of this 
Agreement entitling City to terminate the Agreement unless Contractor applies for and 
receives an extension of time, in accordance with the procedures set forth in the Agreement 
Documents. 
6.1.6 
Failure of City to insist upon the performance of any covenant or condition within the time 
periods specified herein, will not constitute a waiver of Contractor’s duty to perform every 
other covenant or condition within the designated periods, unless a specific waiver is 
granted in writing for each such covenant or condition. 
6.1.7 
City’s agreement to waive a specific time provision or to extend the time for performance 
will not constitute a waiver of any other time provisions contained in the Agreement 
Documents.  Failure of Contractor to complete performance promptly within the additional 
time authorized in the waiver or extension of time agreement constitutes a material breach 
of this Agreement entitling City to all the remedies set forth herein or provided by law. 
6.2 
PROJECT SCHEDULE 
6.2.1 
The Project Schedule must be in Microsoft Project standard file format, must be updated and 
maintained throughout the Agreement Time, and must contain the following: 
6.2.1.1 
Detailed representation of all activities for the project, both on-site construction and major 
procurement.  All significant activities together with the resource loading requirements for 
each and all items appearing on the schedule of values or bid schedule for progress 
payments must be shown on the Project Schedule or in attached transmittal letter as 
described in Section 6.2.8.

General Conditions 
 
Revised: 7/20/22 
 
GC-30 of 75 
 
6.2.1.2 
Dependencies between activities must be indicated so that it may establish as to the effect 
the progress of any one activity would have on other activities and on the Schedule. 
6.2.1.3 
Activities for submission, review, and approval of all required submittals. 
6.2.1.4 
An amount of time will be established prior to the final completion date for “punch list and 
cleanup”.  No other activities will be scheduled during this period.  Punch list and cleanup 
must be shown on the Project Schedule and must be entirely completed prior to the 
expiration of the Agreement Time. 
6.2.2 
Within 10 Days of receipt of City’s comments, Contractor must make all required 
corrections, adjustments, and additions to complete the Project Schedule and resubmit to 
City for review.  City’s review of and response to the Project Schedule is for the purpose of: 
(1) City planning and staffing for the Project as may be required from time to time; (2) 
ensuring Contractor’s general conformance with the scheduling requirements of the 
Agreement Documents and completion of the Project within the Agreement Time; and (3) 
monitoring and evaluating the construction status for purposes of approving monthly 
progress payments. Acceptance of a submitted schedule by City should in no way be 
construed as an affirmation or admission that the schedule is reasonable or workable by 
Contractor. The responsibility for completing the Work on the Project within the 
Agreement Time remains the obligation of Contractor. City’s review  does not relieve 
Contractor from compliance with the requirements of the Agreement Documents or 
be construed as relieving Contractor of its complete and exclusive control over the 
means, methods, sequences and techniques for executing the work. 
6.2.3 
The Project Schedule must show milestones, including milestones for City-furnished 
information, and must include activities for City-furnished material and construction by 
other contractors when those activities are interrelated with Contractor activities. 
6.2.4 
The Project Schedule must be revised as required by conditions and progress of the Work, 
but such revisions do not relieve Contractor of its obligations to complete the Work 
within the Agreement Time, as adjusted in accordance with the Agreement Documents. 
No modification to the Agreement Documents or the Agreement Time will be effective 
unless approved in advance by City. 
6.2.5 
For all items of materials and equipment that are critical or may require long lead times to 
acquire, the Project Schedule must show dates for submission, review and approval of 
submittals, ordering, and delivery. 
6.2.6 
An updated Project Schedule must be submitted monthly to City as part of the Payment 
Request. The monthly submittal must include one full size plot of the entire schedule and 
one electronic copy containing the schedule in Microsoft Project standard file format. In 
addition, Contractor must, upon request by City, provide a copy of all submitted schedule 
data in electronic 
format which must be clearly labeled with the Project description, 
scheduling program name and version number, and schedule print/data date. 
6.2.7 
Contractor must provide City with a monthly status report with each Project Schedule 
detailing the progress of the Work, including: (i) if the Work is proceeding according to 
schedule, (ii) any discrepancies, conflicts, or ambiguities found to exist in the Agreement 
Documents that require resolution, and (iii) other information detailing items that require 
resolution so as not to jeopardize the ability to complete the Work in the Agreement Time.

General Conditions 
 
Revised: 7/20/22 
 
GC-31 of 75 
 
6.2.8 
With each Project Schedule submittal, Contractor must include a transmittal letter 
including the following: 
a. Description of problem tasks, referenced to field instructions or requests 
for information (RFI’s), as appropriate. 
b. Current and anticipated delays including: 
(i) 
Cause of the delay. 
(ii) 
Corrective action and schedule adjustments to correct the delay. 
(iii) 
Known or potential impacts and their delay on other activities, 
milestones, and their impact on the Substantial Completion and 
Final Acceptance dates. 
(iv) 
Changes in construction sequence. 
c. Pending items and status thereof including but not limited to: 
(i) Time Extension requests; 
(ii) 
Substantial Completion date status; 
(iii) 
Final Acceptance date status. 
d. If ahead of schedule, the number of calendar Days ahead. 
e. If behind schedule, the number of calendar Days behind. 
f. 
Other Project or scheduling concerns. 
6.2.9 
Critical Path Method (CPM). 
6.2.9.1 
Unless otherwise specified in the Agreement, the Project Schedule must include a Critical 
Path 
Method (CPM) diagram schedule showing the sequence of activities, the 
interdependence of each activity and identifies the Critical Path. 
6.2.9.2 
The CPM diagram schedule must be in calendar Days and indicate duration, earliest and 
latest start and finish dates for all activities, and total Float Times for all activities except 
critical activities. The CPM diagram must be presented in a time scaled graphical format for 
the Project as a whole. 
6.2.9.3 
The CPM diagram schedule must indicate all relationships between activities. 
6.2.9.4 
The activities making the Project Schedule must contain sufficient detail to assure that 
adequate planning has been done for proper execution of the Work and such that it provides 
an appropriate basis for monitoring and evaluation the progress of the Work. Individual 
activities must not exceed 30 Days in length, in most cases. 
6.2.9.5 
The CPM diagram schedule must be based upon activities, which coincide with the Schedule 
of Values. 
6.2.9.6 
The CPM diagram schedule must show all submittals associated with each work activity and 
the review time for each submittal. 
6.2.10 
Float Time. 
6.2.10.1 
The total Float Time within the overall schedule is for the exclusive use of City, but City 
may approve Contractor’s use of Float as needed to meet Agreement Milestones and

General Conditions 
 
Revised: 7/20/22 
 
GC-32 of 75 
 
the Project completion date. 
6.2.10.2 
Contractor will not be allowed to sequence, hide, or reallocate Float Time through 
such strategies, as extending activity duration estimates to consume available Float, using 
preferential logic, or using extensive crew/resource sequencing, tec. No time extensions 
will be granted nor delay damages paid until a delay occurs which extends the Work beyond 
the Agreement Time. 
6.2.11 
City-Caused Delays.  City-caused delays on the Project, if any, may be offset by City-caused 
time savings (i.e., Critical Path submittals returned in less time than allowed by the 
Agreement, approval of substitution requests and credit changes which result in savings of 
time to Contractor, etc.) In such an event, Contractor will not be entitled to receive a time 
extension or delay damages until all City-caused time savings are exceeded and the 
Agreement Time is also exceeded. 
6.2.12 
Rain-Related Delays.  Contractor is required, in preparing the Project Schedule to take into 
account all relevant weather conditions, including normal rainfall and distribution. No 
additional compensation will be given for any rain-related delays or impacts on the Work 
or the Project Schedule. No time extension will be granted in the Project Schedule unless 
the rainfall during the construction of Work is unusually severe, was not reasonably 
anticipated, and the total rainfall was significantly in excess of the normal rainfall for the 
Project Site location. Normal rainfall for the Project will be determined from the 10-year 
average rainfall for the Site as measured by the National Oceanic and Atmospheric 
Administration or comparable source of reliable information for rainfall in Chandler, 
Arizona. In addition, the excessive rainfall must have actually impacted Work activities on 
the Critical Path and caused delay beyond any remaining Float at the time of the rain- caused 
delay. The burden of documenting normal rainfall, the excessive rainfall and the impact on 
Critical Path activities is on Contractor. All other provisions in the Agreement Documents 
relating to claims, including without limitation notice requirements, apply to any claim by 
Contractor for a rain delay. 
6.2.13 
City’s “Policy Statement for Calculating Delays and Damages,” Appendix 1 to these 
General Conditions, will apply to all claims of delay and delay damages. 
6.2.14 
Force Majeure.  If Contractor is delayed or prevented from the performance of any Work 
required under this Agreement by reason of acts of God or other causes beyond the control 
and without fault of Contractor (financial inability excepted), performance of that Work will 
be excused, but only for the period of the delay.  The time for performance of the Work will 
be extended for a period equivalent to the period of delay. In addition, the parties agree if 
Contractor’s delayed or suspended performance directly arises out of or directly results 
from the COVID-19 pandemic, Contractor’s delayed or suspended performance may be 
excused as set forth in this clause. Provided, however; Contractor must give the City written 
notice within 30 days of the occurrence of the event giving rise to COVID-19 pandemic 
related delayed or suspended performance. For COVID-19 pandemic related delay or 
suspended performance, the parties must agree in writing to the length of the excused 
delay or suspended performance. Further, Contractor must obtain the City’s written 
approval to use any allowance established as part of the project for delays and costs related 
to the COVID-19 pandemic. 
6.3 
SUBSTANTIAL COMPLETION 
6.3.1 
When Contractor considers that the Work, phase or a portion thereof, which City agrees in

General Conditions 
 
Revised: 7/20/22 
 
GC-33 of 75 
 
writing to accept separately, is substantially complete, City will prepare and submit to 
Contractor a comprehensive Punch List of items to be completed or corrected prior to Final 
Acceptance and Final Payment. Failure to include an item on such Punch List does not alter 
the responsibility of Contractor to complete all Work in accordance with the Agreement 
Documents. 
6.3.2 
Upon receipt of Contractor’s Punch List, Project Manager will make an inspection to 
determine whether the Work or designated portion thereof is substantially complete. 
Project Manager may, at Project Manager’s sole option, be assisted in such inspection by 
the Design Professional for the Project. If the inspection by the Project Manager discloses 
any item, whether or not included on Contractor’s Punch List, which is not sufficiently 
completed in accordance with the Agreement Documents so that City can occupy or utilize 
the Work, phase or designated portion thereof for its intended use, Contractor must, 
before issuance of the Certificate of Substantial Completion, complete or correct such 
item upon notification by Project Manager. In such case, Contractor must then submit a 
request for another inspection by Project Manager to determine Substantial Completion. 
6.3.3 
Certificate of Substantial Completion. 
6.3.3.1 
The Project Manager will not issue a Certificate of Substantial Completion unless and until 
the Work (or separable units or Phases as provided in the Agreement Documents) is 
essentially and satisfactorily complete in accordance with the Agreement Documents, such 
that the Project is ready for use by City for its intended purpose, opening to the general 
public, full occupancy or use by City (including, without limitation, all separate units, or 
rooms, facilities, access, income-generating areas, and all areas serving the general public, 
as applicable, must be ready for full-operation 
without material inconvenience or 
discomfort), including, to the extent applicable to the Work, the following: all materials, 
equipment, systems, controls, features, facilities, accessories and similar elements are 
installed in the proper manner and in operating condition, inspected and approved; 
surfaces have been painted; masonry and concrete cleaned with any sealer or other finish 
applied; utilities and systems connected and functioning; site work complete; permanent 
heating, 
ventilation, air condition, vertical transportation and other systems properly 
operating with proper controls; lighting and electrical systems installed, operable and 
controlled; paving completed, signage installed, and other Work as applicable, has 
been performed to a similar state of essential and satisfactory completion. A minor 
amount of Work, as determined by and at the discretion of the Project Manager, such 
as installation of minor accessories or items, a minor amount of painting, minor 
replacement of defective work, minor adjustment of controls or sound 
systems, or 
completion or correction of minor exterior work that cannot be completed as a result of 
weather conditions, will not delay determination of Substantial Completion. If prior 
written approval is obtained from City for purposes of Substantial Completion, specified 
areas of the entire Work or Project may be individually certified as Substantially 
Complete. In no event will Substantial Completion be deemed to have occurred unless 
and until: (i) a temporary certificate of occupancy has been issued by the appropriate 
Governmental Authorities (as applicable) and (ii) all terms and Work required under this 
Agreement have been fulfilled by Contractor and same will have also been approved and 
accepted by City, subject only to the Punch List items. 
6.3.3.2 
If requested by City, Contractor must complete and turn-over to City the Project on a phased 
basis. Each phase will have a separate inspection by the Project Manager, a Punch List 
generated, and then an inspection by City with final approval and acceptance only after the

General Conditions 
 
Revised: 7/20/22 
 
GC-34 of 75 
 
Project Manager’s Punch List. 
6.4 
PARTIAL UTILIZATION 
6.4.1 
City at City’s option may use and occupy any substantially completed parts of the Work 
which has specifically been identified in the Agreement Documents, or which City, the 
Design Professional and Contractor agree constitutes a separately functioning and usable 
part of the Work that can be used by City for its intended purpose, without significant 
interference with Contractor’s performance of the remainder of the Work, provided, 
however, if the portion of the Work to be used or occupied has not been found to be 
substantially complete, City must do so in accordance with Section 6.3 prior to such 
occupancy.   
6.4.2 
In lieu of the issuance of a Certificate of Substantial Completion as to part of the Work, City 
may take over operation of a facility constituting part of the Work whether or not it is 
substantially complete if such facility is functionally and separately usable; provided that 
prior to any such takeover, City and Contractor agree in writing as to the division of 
responsibilities between City and Contractor for security, operation, safety, maintenance, 
correction period, heat, utilities and insurance with respect to such facility. 
6.4.3 
Substantial Completion of or City's beneficial occupancy of a part of the Project will not alter 
the fact that the one-year warranty for the whole Project starts at the date of Final 
Completion of the whole Project. 
6.5 
FINAL ACCEPTANCE 
6.5.1 
Unless otherwise expressly agreed to in writing by City, Final Acceptance must be obtained 
by no later than 30 Days (60 Days for federally funded agreements) after the date of Substantial 
Completion. Failure to timely obtain Final Acceptance will be a material breach of the 
Agreement. 
6.5.2 
Upon receipt of written notice that the Work is ready for final inspection and acceptance, City 
and Contractor will jointly inspect to verify that the remaining items of Work have been 
completed. There will be no partial acceptance. Final Acceptance will not occur until all 
items of Work, including Punch List Items, have been completed to City’s satisfaction as 
reflected in the written Final Acceptance. 
6.5.3 
Final Payment will not be due, owing, or paid by City until Final Acceptance is issued. 
6.5.4 
Landscape Establishment Period. Unless otherwise expressly agreed to in writing by City, the 
Landscape Establishment Period will begin on the date of Final Acceptance of the Project and 
will run 90 Calendar Days thereafter. Landscape Establishment Period requirements are 
detailed in General Conditions Appendices, attached herein. 
6.6 
CONTINUATION OF WORK 
6.6.1 
Permitting Contractor to continue and finish the Work or any part of it after the time fixed 
for its completion (whether milestone, phase, Substantial Completion or Final Acceptance) 
or after the date to which the time fixed for any completion may have been extended, does 
not operate as a waiver by City of any rights under the Agreement Documents, law or equity. 
6.6.2 
Furthermore, the timely completion of the Work being of the utmost importance under 
this Agreement, notwithstanding the existence of one or more disputes between the parties

General Conditions 
 
Revised: 7/20/22 
 
GC-35 of 75 
 
concerning the scope of the Work, the Project Schedule, Agreement Time, payments or any 
other matter, and further notwithstanding a party’s invocation of the Dispute Resolution 
provisions specified in Appendix 6  of these General Conditions, unless City suspends 
the Agreement or Contractor’s performance pursuant to Section 10 of these General 
Conditions, Contractor will continue to prosecute the Work, including any Change Order 
work or Extra Work Orders, in a diligent and timely manner and not stop, slow down or 
impede by action or inaction the progress of the Work, including commencing performance 
of and thereafter completing any additional work called out in any Change Order or Extra 
Work Order issued by Project Manager with the approval of City, so long as City makes 
payment to Contractor in accordance with Section 8 of these General Conditions. 
 
SECTION 7 - AGREEMENT PRICE 
7.1 
UNIT PRICE AGREEMENTS 
7.1.1 
The Agreement Price for all Unit Price Agreements will be the amount set forth in the 
Agreement or Change Order multiplied by the verified quantity provided. 
7.1.2 
Measurements of quantities to determine the total Agreement Price must be in accordance 
with MAG Specification §§ 109.1 and 109.2. 
7.1.3 
The Unit Price may only be changed as set forth in Section 9 below. 
7.2 
CHANGE ORDERS 
7.2.1 
Unit Price Change Orders.  The Change Order Price for all Unit Price Change Orders will be 
the amount set forth in the Change Order multiplied by the verified quantity provided. 
7.2.2 
Measurements of quantities to determine the total Change Order Price must be in 
accordance with MAG Specifications §§ 109.1 and 109.2. 
7.2.3 
The Unit Price may only be changed as set forth in Section 9 below. 
 
7.2.4 
MAG Specification § 109.4.1 is modified as follows: Before § 109.4.1, the following is added:  
Any deduction or increase in the Agreement Price must be supported by a signed, 
written Change Order fully executed by City, and supported by such backup as the Project 
Manager may require.  
7.3 
SALES TAX 
Contractor is required to pay all applicable sales tax in accordance with the law of the state of 
Arizona and this cost must be included in all Agreement Prices.  When equipment, materials 
or supplies generally taxable to Contractor are eligible for a tax exemption due to the nature 
of the Project, Contractor must assist City in applying for and obtaining such tax credits and 
exemptions which will be paid or credited to City.   
 
SECTION 8 - PAYMENT 
8.1 
PAYMENT FOR CONSTRUCTION SERVICES 
8.1.1 
Payment for the Work will be made in accordance with MAG Standard Specification § 109 
as amended below.  
8.1.2 
Contractor must submit to City for review a completed Contractor Payment Request signed

General Conditions 
 
Revised: 7/20/22 
 
GC-36 of 75 
 
by Contractor, covering the Work completed as of the date of the Request and accompanied 
by such supporting documentation as is required by the Agreement Documents and also 
as City may reasonably require.  A Contractor Payment Request will not be considered 
complete unless it is accompanied by an updated Project Schedule and a certification that 
the on-site, red lined, as built Drawings are up to date.  If payment is requested on the basis 
of materials and equipment not incorporated in the Work but delivered and suitably, 
securely stored at the Site or at another location (such as a bonded warehouse) agreed to 
in writing, the Contractor Payment Request must also be accompanied by such data, 
satisfactory to City, as will establish City's title to the material and equipment and protect 
City's interest therein, including applicable insurance. Each subsequent Contractor Payment 
Request must include an affidavit of Contractor stating that all previous progress payments 
received on account of the Work have been applied to discharge in full all of Contractor's 
obligations reflected in prior Contractor Payment Requests.  
8.1.3 
Except for Work performed under a JOC Agreement, the Contracting Agency will retain 10 
percent of all estimates as a guarantee for complete performance of the Agreement in 
accordance with Arizona Revised Statutes Section 34-221 or 34-607.  The Contractor may 
elect to deposit securities in lieu of retention in accordance with Arizona Revised Statutes 
Section 34-221, Paragraph C.5. or 34-607, Paragraph B.5. 
8.1.4 
The payment process functions as follows: Prior to the payment cycle date, Contractor must 
send a draft Contractor Payment Request to Project Manager.  The Project Team will review 
the Request and agree upon any necessary adjustments.  Contractor must certify the final 
Request by signing and returning to Project Manager. 
8.1.5 
When construction of the Project is fifty percent (50%) completed, Contractor may 
request payment of one-half of the retention pursuant to A.R.S. § 34-609(B)(3), subject to all 
of City’s rights to withhold or offset payments, and other rights of City, under the Agreement. 
8.1.6 
City reserves the right under A.R.S. § 34-609(B)(3) to reinstate the ten percent (10%) retention 
if City determines that satisfactory progress is not being made. 
8.1.7 
Contractor’s Warranty of Title. 
8.1.7.1 
Contractor warrants and guarantees that title to all Work, materials and equipment covered 
by any Contractor Payment Request, whether incorporated in the Project or not, will pass 
to City at the time of payment, free and clear of all liens, claims, security interests, and 
encumbrances, provided that this will not preclude the Contractor from installing metering 
devices or other equipment of utility companies or municipalities, the title of which is 
commonly retained by the utility company or municipality. 
8.1.7.2 
No materials, supplies, or equipment for the Work under this Agreement will be purchased 
subject to any chattel mortgage or under a conditional sale contract or other agreement by 
which an interest therein, or any part thereof, is retained by the seller or supplier. 
8.1.7.3 
Nothing contained in this Section will defeat or impair the right of such persons furnishing 
materials or labor under any bond given by the Contractor for their protection, or any right 
under any law permitting such persons to look to funds due the Contractor in the hands of 
the City. The provisions of this Section must be inserted in all subcontracts and material 
agreements, and notices of its provision must be given to all persons furnishing materials 
for the Work when no formal agreement is entered into for such materials.

General Conditions 
 
Revised: 7/20/22 
 
GC-37 of 75 
 
8.2 
PAYMENT UPON SUBSTANTIAL COMPLETION 
8.2.1 
No payment will be made upon Substantial Completion, except for a regularly-scheduled 
monthly progress payment, as allowed by Section 8.2.2. 
8.2.2 
No further payments will be made to Contractor until Final Acceptance. 
8.3 
FINAL PAYMENT 
8.3.1 
Subject to all of City’s rights to withhold or offset payment, and other rights under the 
Agreement, Final Payment including remaining retainage will be paid only after: 
a. Work has been fully completed (including completion of all incorrect or 
incomplete work items) and the written Final Acceptance has been issued by 
City; 
b. Necessary operating manuals, any excess materials and supplies necessary 
for matching materials and supplies incorporated into the Work, 
acceptable sewer video results (if applicable), and complete “as-built” 
Drawings (including the Building Information Model, if required by the 
Agreement Documents) have been delivered to City, as specified in this 
Section 8.3; 
c. Full and unconditional lien waivers and releases by Contractor and any 
person performing labor or supplying material, machinery, fixtures, or tools 
for the Work have been delivered to Contractor; 
d. All conditions and requirements imposed by City or any financing entity 
for the corresponding disbursement have been met; and 
e. Contractor delivers to City a Contractor Payment Request requesting Final 
Payment. 
8.3.2 
Contractor must also submit a signed copy of Contractor’s Affidavit Regarding Settlement 
of Claims, Appendix 3 to these General Conditions, and Certificate of Completion, Appendix 7 
to these General Conditions, prior to Final Payment. 
8.3.3 
In addition, if required under the Project Specific Special Provisions, Contractor must 
compile a complete equipment list and maintenance manual to be submitted to City 
as a precondition to Final Payment. The list must include the following items for all 
equipment supplied under the Plumbing, Electrical, Air Conditioning, Elevator, and other 
Special Equipment Specifications: 
a. Name, Model and Manufacturer. 
b. Complete parts lists and Drawings. 
c. Local source of supply for replacement parts along with suppliers’ telephone 
numbers. 
d. Local service organizations serving the equipment and their telephone 
numbers. 
e. All tags, inspection slips, instruction packages, etc., removed from 
equipment must be properly identified as to pieces of equipment from 
which they were taken.

General Conditions 
 
Revised: 7/20/22 
 
GC-38 of 75 
 
8.3.4 
Contractor must also deliver to City, prior to Final Payment, one (1) digital (in the format 
specified by City), and if requested by City, one (1) hard copy, of any applicable 
Maintenance manuals. Each manual must include all manufacturer’s operation and 
maintenance instructions and “as-built” Drawings with the list herein specified. It must also 
include all other diagrams and instructions necessary to properly operate and maintain the 
equipment, the name, address and telephone number of Contractor and all Subcontractors 
involved. 
8.4 
 CIT Y ’S RIGHT TO WITHHOLD PAYMENT 
City may withhold payment to such extent as may be necessary in City’s opinion to protect 
City from loss for which Contractor is responsible, including, without limitation, if any of 
the following conditions exist: 
a. Defective Work not remedied; 
b. Third party claims filed or reasonable evidence indicating probable filing of 
such claims unless security acceptable to City is provided by Contractor; 
c. Failure of Contractor to make payments properly to Subcontractors or for 
labor, materials or equipment; 
d. Reasonable evidence that the Work cannot be completed for the unpaid 
balance of the Agreement Price; 
e. Damage to City or another Contractor; 
f. 
Reasonable evidence that the Work will not be completed within the 
Agreement Time, and that the unpaid balance would not be adequate to 
cover actual or liquidated damages for the anticipated delay; 
g. Failure to carry out the Work in accordance with the Agreement Documents; 
or 
h. Contractor is in default of any of its other obligations under the Agreement 
Documents. 
8.5 
JOINT/DIRECT CHECKS 
To promote the timely completion and progress of the Work or when appropriate and 
necessary, payments to Contractor may be made jointly to Contractor and its employees, 
agents, Subcontractors and suppliers, or any of them.  For federally funded agreements, 
see federal provisions for additional requirements for the joint check process. 
8.6 
PAYMENT NOT A WAIVER 
No payment (nor use or occupancy of the Project by City) will be deemed acceptance or 
approval of the Work or as a waiver of any claims, rights, or remedies of City. 
8.7 
LIENS AND BOND CLAIMS 
Contractor must make all payments, in the time required, of all labor and materials 
furnished to Contractor in the course of the Work and must promptly furnish evidence of 
such payments as City may require. Contractor must pay when due all claims arising out of 
performance of the Work covered by this Agreement for which a lien may be filed either 
against the real estate or leasehold interest of City, or against payments due from City to 
Contractor, or for which a claim may be made against any payment or performance bond 
or both. To the fullest extent permitted by law, Contractor agrees that no liens or other 
claims in the nature of a lien against the real estate, leasehold, or other interest of City,

General Conditions 
 
Revised: 7/20/22 
 
GC-39 of 75 
 
against payment due from City to Contractor, or against any payment or performance 
bond, must be filed or made in connection with the Work by any party who has supplied 
professional services, labor, materials, machinery, fixtures, tools, or equipment used in or 
in connection with the performance of this Agreement, and Contractor agrees to remove or 
to cause to be removed any such liens or claims in the nature of a lien or bond claim within 
10 Days upon receiving notice or obtaining actual knowledge of the existence of such liens 
or claim. In addition, Contractor agrees to defend, indemnify, and hold harmless City 
from and against any and all such liens and claims. This paragraph does not apply to claims 
and liens of Contractor due to non-payment for work performed. 
8.8 
 FIN AN CI AL R ECORDKE EPI NG AND C IT Y ’S AUD I T RIGHT  
8.8.1 
Records for all Agreements between City and Contractor must, upon reasonable notice, be 
open to inspection and subject to audit, scanning, and reproduction during normal 
business working hours. Such audits may be performed by any City’s representative or any 
outside representative engaged by City for the purpose of examining such records. City or 
its designee may conduct such audits or inspections throughout the term of this Agreement 
and for a period of five years after Final Payment or longer if required by law. City’s 
representatives may (without limitation) conduct verifications such as counting employees 
at the Site, witnessing the distribution of payroll, verifying information and amounts through 
interviews and written confirmations with Contractor employees, field and agency labor, 
Subcontractors, and vendors. 
8.8.2 
Contractor’s “records” must include any and all information, materials and data of every kind 
and 
character, including without limitation, records, books, papers, documents, 
subscriptions, recordings, agreements, purchase orders, leases, contracts, commitments, 
arrangements, notes daily diaries, superintendent reports, drawings, receipts, vouchers and 
memoranda, and any and all other agreements, sources of information and matters that 
may in City’s judgment have any bearing on or pertain to any matters, rights, duties or 
obligations under or covered by any Agreement Document. Such records must include (hard 
copy, as well as computer readable data if it can be made available), written policies and 
procedures; time sheets; payroll registers; payroll records; cancelled payroll checks; 
subcontract files (including proposals of successful and unsuccessful bidders, bid recaps, 
negotiation notes, etc.); original bid estimates; estimating work sheets; correspondence; 
Change Order files (including documentation covering negotiated settlements); back-
charge logs and supporting documentation; invoices and related payment documentation; 
general ledger, information detailing cash and trade discounts earned, insurance rebates 
and dividends; and any other Contractor records which may have a bearing on matters of 
interest to City or the Project in connection with Contractor’s dealings with City or the 
Project (all foregoing 
hereinafter referred to as “records”) to the extent necessary to 
adequately permit evaluation and verification of any or all of the following: 
a. Compliance with Agreement requirements for deliverables; 
b. Compliance with approved Plans and Specifications; 
c. Compliance with § 14.9 below; 
d. Compliance with Agreement provisions regarding the pricing of Change 
Orders; 
e. Accuracy of Contractor representations regarding the pricing of invoices; or 
f. 
Accuracy of Contractor representations related to claims submitted by

General Conditions 
 
Revised: 7/20/22 
 
GC-40 of 75 
 
Contractor or any of their employees. 
8.8.3 
Contractor must require all payees (examples of payees include Subcontractors, Suppliers, 
Insurance Carriers, etc.) to comply with the provisions of this Section by including the 
requirements hereof in a written agreement between Contractor and payee. Contractor will 
ensure that all payees (including those entering into lump sum agreements) have the same 
right to audit provisions contained in this Agreement included in their agreements with 
Contractor. 
8.8.4 
City’s authorized representative(s) (including, without limitation, Project Manager) must have 
reasonable access to Contractor’s facilities, must be allowed to interview all current or former 
employees to discuss matters pertinent to the performance of this Agreement and must be 
provided adequate and appropriate work space, in order to conduct audits in compliance 
with this Section. 
8.8.5 
If an audit inspection or examination in accordance with this Section, discloses overpricing 
or overcharges to City (of any nature) by Contractor or Contractor’s Subcontractors in excess 
of $100,000 in addition to making adjustments for the overcharges, the reasonable actual 
cost of City’s audit must be reimbursed to City by Contractor. Any adjustments or payments 
which must be made as a result of any such audit or inspection of Contractor’s invoices or 
records must be made within a reasonable amount of time (not to exceed 90 Days) from 
presentation of City’s findings to Contractor. 
8.8.6 
In addition to the normal paperwork documentation Contractor typically furnishes to City, 
Contractor agrees to furnish, upon written request from City, any of the documentation 
necessary for City to exercise its audit rights under this Section 8.8 in computer readable file 
formats (Word, Excel, or .pdf), as City may designate. 
8.8.7 
City, its authorized representative, and the appropriate agency, reserve the right to 
audit Contractor’s records in compliance with local, state or federal policies, statutes 
or at City’s discretion, within three (3) years of Final Acceptance of the Work. 
 
SECTION 9 - CHANGES TO THE AGREEMENT 
9.1 
FIELD ORDERS 
City may authorize minor changes in the Work not involving an adjustment in the 
Agreement Price or the Agreement Times, which are consistent with the overall intent of 
the Agreement Documents.  These may be accomplished by a written Field Order on the 
standard form approved and executed by City.  Such Field Orders must be binding and 
Contractor must perform the change promptly. If Contractor believes that a Field Order 
justifies an increase in the Agreement Price or Agreement Time, Contractor may make a 
claim therefor as provided in Section 7.2. 
9.2 
EXTRA WORK/CHANGES IN THE WORK 
9.2.1 
City reserves the right to make such changes in the Plans and Specifications for the Work, 
as it may deem appropriate and any such change as set forth in a written Change Order 
must be deemed a part of this Agreement as if originally incorporated herein. 
9.2.2 
In the event City and Contractor cannot agree on the terms of a Change Order, or 
when circumstances otherwise require, the Project Manager has the authority to direct the 
Contractor to perform extra work, if the work in question is an item not provided for in the

General Conditions 
 
Revised: 7/20/22 
 
GC-41 of 75 
 
Agreement as awarded. The Project Manager will have the authority to determine, based 
upon factual evidence presented by the Contractor, whether the work in question is an 
item not provided for in the Agreement as awarded. If the Project Manager directs the 
Contractor to perform extra work, the Project Manager’s instructions will include a price 
that the Contractor cannot exceed in charging the City for the extra work. Upon receipt of 
the Project Manager’s directions to perform extra work, the Contractor must promptly 
proceed with the extra work and document the actual cost thereof. Contractor’s right to 
payment for extra work will be determined under Subsection 9.2.4 below. The Contractor is 
responsible to manage the extra work to ensure that the price limits set by the Project 
Manager are not exceeded. Contractor must perform the extra work and submit 
documentation for the actual cost of the extra work to the City. A Change Order will be 
issued to cover this work. 
9.2.3 
Contractor will not be entitled to payment for extra work unless a written Change Order, in 
form and content prescribed by City, has been executed by City. On all requests for Change 
Orders, Contractor must specify the increased or decreased costs and whether it 
believes any extensions of time will be necessary to complete its Work as modified by the 
Change Order. If extra work is performed under Subsection 9.2.2 above, a corresponding 
Change Order will be prepared, approved and processed by City before payment can be 
made to Contractor. 
9.2.4 
In general, pricing for Change Orders will include the same mark-up percentages that were 
in effect when the Agreement was awarded. The cost or credit to the City resulting from a 
change in the Work is subject to Appendix 1 (Policy Statement for Calculating Delays and 
Damages) and will be determined, based on the type of pricing for the Agreement involved, 
as follows: 
a. By mutual acceptance of a lump sum properly itemized in a form acceptable 
to City; 
b. By unit prices stated in the Agreement Documents; 
c. When the City determines that a Unit Price Book Job Order associated with 
a Job Order Agreement requires a Change Order, by using the same Total 
Cost Data and CCI that are in effect when the Change Order is anticipated to 
be issued; or 
d. By actual cost and a percentage fee covering overhead and profit, as follows: 
(i) 
Contractor will perform the extra work and be compensated for actual 
cost of labor, materials and equipment. 
(ii) 
Contractor will have the right to add the fee percentage applicable 
to the Work under the Agreement, or if no such fee has been agreed 
to by the parties, not more than five percent (5%) to the 
Subcontractor’s prices for authorized extra work performed solely 
by Subcontractors. Such percentage will include all of Contractor’s 
charges for overhead, profit, administration and supervision. 
(iii) 
Contractor or Subcontractor will have the right to add the fee 
percentage applicable to Work under the Agreement for self-
performed extra work, or if no such fee has been agreed to by the 
parties, Contractor’s or Subcontractor’s maximum total allowable 
additions for overhead, profit, administration and supervision will

General Conditions 
 
Revised: 7/20/22 
 
GC-42 of 75 
 
not exceed ten percent (10%) of actual verifiable labor, materials 
and equipment for such self- performed extra work. 
9.2.5 
Any agreement which modifies the terms of the Agreement (including Change Orders) 
will be approved in writing by the Project Manager. Once properly executed by both 
parties, these modifications to the Agreement will have the same effect as if they had been 
included in the original Agreement. 
9.3 
ACCURACY OF CHANGE ORDER PRICING INFORMATION 
9.3.1 
Subject to Sections 9.3.2 through 9.3.4, signature by the contracting parties constitutes full 
accord and satisfaction between City and Contractor for all costs, damages, and expenses 
of whatever kind of nature, including delay, impact or acceleration damages, which may be 
occasioned by a Change Order of other modification of the Agreement agreed to in writing. 
9.3.2 
Accurate Change Order Pricing Information: Contractor agrees that it is responsible for 
submitting accurate cost and pricing data to City to support its Fixed Price, Unit Price, or 
Cost Plus Change Order Proposals or other Agreement Price adjustments under the 
Agreement. Contractor further agrees to submit Change Order proposals with cost and 
pricing data which is accurate, complete, current, and in accordance with the terms of 
the Agreement with respect to pricing of change orders. Contractor agrees that any “buy-
out savings” on Change Orders will accrue 100% to Owner. “Buy-out savings” are defined 
as any savings negotiated by the Contractor with a Subcontractor or a Material Supplier 
after receiving approval of a Change Order amount that was designated to be paid to a 
specific Subcontractor or Supplier for the Approved Change Order work. 
9.3.3 
Right to Verify Change Order Pricing Information: Contractor agrees that City, through 
its designated representative, will have the right to examine, copy, and scan the records 
of the Contractor, Subcontractor or Sub-Subcontractor’s records (during the Agreement 
period and up to three years after final payment is made on the Agreement) to verify 
the accuracy and appropriateness of the pricing data used to price all Change Order 
proposals or claims. Contractor agrees that if City determines the cost and pricing data 
submitted (whether approved or not) was inaccurate, incomplete, not current, or not in 
compliance with the terms of the Agreement regarding pricing of Change Orders, an 
appropriate Agreement Price adjustment will be made. Such post-approval Contact Price 
adjustments will apply to all levels of contractors and Subcontractors and to all types of 
Change Order proposals, specifically including Fixed Price, Unit Price, and Cost Plus Change 
Orders. 
9.3.4 
Requirements for Detailed Change Order Pricing Information: Contractor agrees to 
provide a detailed breakdown of allowable labor and labor burden cost (i.e., base wage 
rate of applicable classifications of workers, payroll taxes, and insurance and benefits 
costs).  This information will be used to evaluate the potential cost of labor and labor burden 
related to Change Order work. It is intended that this information represent an accurate 
estimate of the Contractor’s actual labor and labor burden cost components. Information 
is not intended to establish fixed billing or Change Order pricing labor rates. However, at the 
time Change Orders are priced, the submitted cost data for labor rates may be used to price 
Change Order work. The accuracy of any such agreed upon labor rate cost components 
used to price Change Orders will be subject to later audit. Approved Change Order 
amounts may be adjusted later to correct the impact of inaccurate labor cost 
components if the agreed upon labor cost components are determined to be inaccurate.

General Conditions 
 
Revised: 7/20/22 
 
GC-43 of 75 
 
9.4 
EMERGENCIES 
In any emergency affecting the safety of persons or property, Contractor will act, at its 
discretion, to prevent threatened damage, injury or loss. Any change in the Agreement Price 
or Agreement Time resulting from emergency work will be determined as provided in this 
Section. 
9.5 
DIFFERING SITE CONDITIONS 
9.5.1 
If Differing Site Conditions are encountered at the Project Site, then notice by the observing 
party must be given to the other party promptly before conditions are disturbed (to the extent 
practicable) and in no event later than 14 Days after first observance of the conditions. 
City will promptly investigate such conditions and, if City determines that Differing Site 
Conditions exist and they materially cause an increase in the cost of, or time required for, 
performance of any part of the Work, Contractor will be entitled to equitable adjustment 
in the Agreement Price or Construction Schedule (and other time requirements), or both. 
If it is determined by City that the conditions at the Project Site are not Differing Site 
Conditions and no change is justified, then City will so notify Contractor in writing, stating the 
reasons. Claims in opposition to such determination must be made within 14 Days after 
City has given notice of its decision. If City and Contractor cannot agree on an adjustment 
in the Agreement Price or Construction Schedule (and other time requirements), the 
adjustment may be submitted to dispute resolution as provided these General Conditions. 
9.6 
CHANGES IN LAWS, REGULATIONS, OR LEGAL REQUIREMENTS OR TAXES 
In the event of a material change in applicable Laws, Regulations, or Legal Requirements, or 
taxes subsequent to the date of the Agreement by the parties, Contractor may be entitled 
to a Change Order, in City’s discretion, to the extent Contractor can document to the 
satisfaction of City that such change significantly increases Contractor’s actual cost of 
performance of the Work. 
 
SECTION 10 -SUSPENSION AND TERMINATION 
10.1 
SUSPENSION 
City may suspend the Agreement and Contractor’s performance in accordance with MAG 
Specifications § 105.1 and 108.7. 
10.2 
TERMINATION BY THE CITY FOR CAUSE 
10.2.1 
MAG Specifications § 108.11 applies to the Agreement. 
10.2.2 
City may also terminate the Agreement if City determines, in its sole discretion that 
Contractor has: 
a. After prior written notice, refused or failed to supply enough properly skilled 
workers or proper materials; 
b. After prior written notice, failed to make payment to Subcontractors for 
materials or labor in accordance with the respective agreements between 
Contractor and the Subcontractors; 
c. 
After prior written notice, disregards laws, ordinances, or rules, regulations or 
orders of a public authority having jurisdiction;  
d. After prior written notice, repeatedly failed to comply with written directives 
from City;

General Conditions 
 
Revised: 7/20/22 
 
GC-44 of 75 
 
e. Is adjudged as bankrupt or insolvent; 
f. 
Made a general assignment for the benefit of creditors; 
g. Appointed a trustee or receiver for itself or any of its property; 
h. Filed a petition to take advantage of any debtor's act, or to reorganize under 
the bankruptcy or similar laws; or 
i. 
Otherwise breached a provision of the Agreement Documents or any other 
Agreement between City and Contractor. 
10.2.3 
When any of the above reasons exist, City may terminate the Agreement, without prejudice 
to any other rights or remedies of City, after giving Contractor and Contractors’ surety, if 
any, 7 Days written notice of City’s intent to terminate the Agreement and Contractor’s 
failure to cure any such reasons. Upon such termination, City may: (1) take possession of 
the Site and of all materials thereon owned by Contractor; or (2) finish the Work by whatever 
reasonable method City may deem expedient. When City terminates the Agreement for one 
of the reasons state above, Contractor will not be entitled to receive further payment until 
the Work is finished. If the unpaid balance of the Agreement Price existing at the time of 
such termination exceeds the costs and expenses of finishing the Work and any other 
damages incurred by City, such excess will be paid to Contractor. If such costs, expenses 
and damages exceed such unpaid balance, Contractor must pay the difference to City. This 
obligation for payment will survive termination of the Agreement. 
10.3 
TERMINATION BY CITY FOR CONVENIENCE 
City may also terminate the Agreement at any time for its convenience upon 7 Days written 
notice to Contractor specifying the termination date. In the event of termination which is 
not the fault, in whole or in part, of Contractor, City will pay to Contractor only such 
compensation, including reimbursable expenses, due for Work properly performed on 
the Project prior to the termination date. Upon any termination of the Agreement, no 
further payments will be due from City to Contractor. 
10.4 
A.R.S. § 38-511 
The Agreement is subject to, and may be terminated by City in accordance with, the 
provisions of A.R.S. § 38-511. 
 
SECTION 11 -INSURANCE AND BONDS 
11.1 
INSURANCE REQUIREMENTS 
11.1.1 
After Agreement award, the Contractor must furnish the City a certificate of insurance on a 
standard insurance industry ACORD form.  The ACORD form must be issued by an insurance 
company authorized to transact business in the State of Arizona possessing a current A.M. 
Best, Inc. rating of A-7, or better and legally authorized to do business in the State of Arizona 
with policies and forms satisfactory to City.  Provided, however, the A.M. Best rating 
requirement may not be deemed to apply to required Worker’s Compensation coverage. 
11.1.2 
The Contractor and any of its Subcontractors must procure and maintain, until all of their 
obligations have been discharged, including any warranty periods under this Agreement are 
satisfied, the insurances set forth below. 
11.1.3 
The insurance requirements set forth below are minimum requirements for this Agreement 
and in no way limit the indemnity covenants contained in this Agreement.

General Conditions 
 
Revised: 7/20/22 
 
GC-45 of 75 
 
11.1.4 
The City in no way warrants that the minimum insurance limits contained in this Agreement 
are sufficient to protect Contractor from liabilities that might arise out of the performance 
of the Agreement services under this Agreement by Contractor, its agents, representatives, 
employees, or Subcontractors and the Contractor is free to purchase any additional 
insurance as may be determined necessary. 
11.1.5 
Failure to demand evidence of full compliance with the insurance requirements in this 
Agreement or failure to identify any insurance deficiency will not relieve the Contractor 
from, nor will it be considered a waiver of its obligation to maintain the required insurance 
at all times during the performance of this Agreement. 
11.1.6 
Use of Subcontractors:  If any Work is subcontracted in any way, the Contractor must 
execute a written agreement with Subcontractor containing the same Indemnification 
Clause and Insurance Requirements as the City requires of the Contractor in this 
Agreement.  The Contractor is responsible for executing the Agreement with the 
Subcontractor and obtaining Certificates of Insurance and verifying the insurance 
requirements. 
11.2 
MINIMUM SCOPE AND LIMITS OF INSURANCE 
11.2.1 
The Contractor must provide coverage with limits of liability not less than those stated 
below. 
11.2.1.1 
Commercial General Liability-Occurrence Form.  Contractor must maintain “occurrence” 
form Commercial General Liability insurance with a limit of not less than $2,000,000 for each 
occurrence, $4,000,000 aggregate.  Said insurance must also include coverage for products 
and completed operations, independent contractors, personal injury and advertising injury. 
If any Excess insurance is utilized to fulfill the requirements of this paragraph, the Excess 
insurance must be “follow form” equal or broader in coverage scope than underlying 
insurance. 
11.2.1.2 
Automobile Liability-Any Automobile or Owned, Hired and Non-Owned Vehicles.  Contractor 
must maintain Business/Automobile Liability insurance with a limit of $1,000,000 each 
accident on Contractor owned, hired, and non-owned vehicles assigned to or used in the 
performance under this Agreement.  If any Excess or Umbrella insurance is utilized to fulfill 
the requirements of this paragraph, the Excess  or Umbrella insurance must be “follow 
form” equal or broader in coverage scope than underlying insurance. 
11.2.1.3 
Workers Compensation and Employers Liability Insurance.  Contractor must maintain 
Workers Compensation insurance to cover obligations imposed by federal and state 
statutes having jurisdiction of Contractor employees engaged in the performance of Work 
under this Agreement and must also maintain Employers’ Liability insurance of not less than 
$1,000,000 for each accident and $1,000,000 disease for each employee.  
11.2.1.4 
Builders’ Risk/Installation Floater Insurance.  The Contractor bears all responsibility for loss 
to all equipment or Work under construction.  Unless waived in writing by the City the 
Contractor will purchase and maintain in force Builders’ Risk/Installation Floater insurance 
on the entire Work until completed and accepted by the City.  This insurance will be Special 
Causes of Loss policy form, (minimally including perils of fire, flood, lightning, explosion, 
windstorm and hail, smoke, aircraft and vehicles, riot and civil commotion, theft, vandalism, 
malicious mischief, and collapse), completed value, replacement cost policy form equal to 
the Agreement Price and all subsequent modifications.  The Contractor’s Builders’

General Conditions 
 
Revised: 7/20/22 
 
GC-46 of 75 
 
Risk/Installation Floater insurance must be primary and not contributory. 
a. Builders’ Risk/Installation Floater insurance must cover the entire Work 
including reasonable compensation for architects and engineers’ services 
and expenses and other “soft costs” made necessary by an insured loss.  
Builders’ Risk/Installation Floater insurance must provide coverage from the 
time any covered property comes under the Contractor’s control and or 
responsibility, and continue without interruption during course of 
construction, renovation and or installation, including any time during which 
any Project property or equipment is in transit, off Site, or while on Site for 
future use or installation.  Insured property must include, but not be limited 
to, scaffolding, false work, and temporary buildings at the Site.  This 
insurance must also cover the cost of removing debris, including demolition 
as may be legally required by operation of any law, ordinance, regulation or 
code. 
b. The Contractor must also purchase and maintain Boiler and Machinery 
insurance with the same requirements as Builders’ Risk/Installation Floater 
insurance cited above if the Work to be performed involves any exposures 
or insurable property normally covered under a Boiler and Machinery 
insurance policy or made necessary as required by law or testing 
requirements in the performance of this Agreement.  The Contractor will be 
responsible for any and all deductibles under these policies and the 
Contractor waives all rights of recovery and subrogation against the City 
under the Contractor- Builders’ Risk/Installation Floater insurance described 
herein. 
c. Builders’ Risk/Installation Floater Insurance must be maintained until 
whichever of the following first occurs: (i) final payment has been made; or, 
(ii) until no person or entity, other than the City, has an insurable interest in 
the property required to be covered. 
d. The Builders’ Risk/Installation Floater insurance must be endorsed so that 
the insurance will not be canceled or lapse because of any partial use or 
occupancy by the City. 
e. The Builders Risk/Installation Floater insurance must include as named 
insureds, the City, the Contractor, and all tiers of Subcontractors and others 
with an insurable interest in the Work who will be named as additional 
insureds unless they are able to provide the same level of coverage with the 
City and Contractor named as additional insureds. Certificates must contain 
a provision that the insurance will not be canceled or materially altered 
without at least 30 Days advance notice to the City.  The City must also be 
named as a Loss Payee under the Builders’ Risk/Installation Floater coverage. 
f. 
The Builders Risk/Installation Floater insurance must be written using the 
Special Causes of Loss policy form, replacement cost basis. 
g. All rights of subrogation under the Builders Risk/Installation Floater 
insurance are, by this Agreement, waived against the City, its officers, 
officials, agents and employees. 
h. The Contractor is responsible for payment of all deductibles under the 
Builders’ Risk/Installation Floater insurance policy.

General Conditions 
 
Revised: 7/20/22 
 
GC-47 of 75 
 
11.2.1.5 
Pollution Liability Insurance (Including Errors and Omissions).  For Job Orders, Pollution 
Liability Insurance is only required if applicable and determined on a project specific basis.  
Contractor must maintain Pollution Liability Insurance with a limit of not less than 
$5,000,000 per loss, $5,000,000 aggregate for losses caused by pollution conditions 
including coverage for bodily injury, property damage, defense costs, clean-up costs, and 
completed operations that arise from the operations of Contractor as described in this 
Agreement.  
a. The policy must provide for complete professional service coverage, 
including coverage for pollution liability that is a result of a breach of 
professional duties. 
b. The policy must provide for protection again claims for third-party bodily 
injury, property damage, or environmental damage caused for pollution 
conditions resulting from general contracting activities for which Contractor 
is legally liable. 
c. The policy must provide for cleanup costs when mandated by governmental 
entities, when required by law, or as a result of third-party claims. 
d. Completed Operations Coverage must be kept in place for up to the statute 
of repose. 
e. The policy must be endorsed to include the following additional insured 
language: “City, its elected officials, trustees, employees, agents, and 
volunteers must be named as additional insureds with respect to liability 
arising out of the activities performed by, or on behalf of Contractor”.   
f. 
If Work under this Agreement requires the transportation of any hazardous 
material or regulated substances, Contractor must carry Auto Liability with a 
CA 9948 endorsement or equivalent.   
g. If Work under this Agreement requires the disposal of any hazardous 
materials from the job site, Contractor must obtain a certificate of insurance 
for Pollution Legal Liability from the disposal site operator with a limit of not 
less than $5,000,000 per loss, $5,000,000 aggregate. 
11.3 
ADDITIONAL POLICY PROVISIONS REQUIRED 
11.3.1 
Self-Insured Retentions or Deductibles.  Any self-insured retentions and deductibles must 
be declared and approved by the City.  If not approved, the City may require that the insurer 
reduce or eliminate any deductible or self-insured retentions with respect to the City, its 
officers, officials, agents, employees, and volunteers. 
11.3.2 
The Contractor’s insurance must contain broad form contractual liability coverage. 
11.3.3 
The Contractor's insurance coverage must be primary insurance with respect to the City, its 
officers, officials, agents, and employees.  Any insurance or self-insurance maintained by 
the City, its officers, officials, agents, and employees will be in excess of the coverage 
provided by the Contractor and must not contribute to it. 
11.3.4 
The Contractor's insurance must apply separately to each insured against whom claim is 
made or suit is brought, except with respect to the limits of the insurer's liability. 
11.3.5 
Coverage provided by the Contractor must not be limited to the liability assumed under the

General Conditions 
 
Revised: 7/20/22 
 
GC-48 of 75 
 
indemnification provisions of this Agreement. 
11.3.6 
The policies must contain a severability of interest clause and waiver of subrogation against 
the City, its officers, officials, agents, and employees, for losses arising from Work 
performed by the Contractor for the City. 
11.3.7 
The Contractor, its successors and or assigns, are required to maintain Commercial General 
Liability insurance as specified in this Agreement for a minimum period of 3 years following 
completion and acceptance of the Work.  The Contractor must submit a Certificate of 
Insurance evidencing Commercial General Liability insurance during this 3 year period 
containing all the Agreement insurance requirements, including naming the required 
Additional Insureds set forth herein. 
11.3.8 
If a Certificate of Insurance is submitted as verification of coverage, the City will reasonably 
rely upon the Certificate of Insurance as evidence of coverage but this acceptance and 
reliance will not waive or alter in any way the insurance requirements or obligations of this 
Agreement.   
11.3.9 
Insurance Cancellation During Agreement Term.   
11.3.9.1 
If any of the required policies expire during the life of this Agreement, the Contractor must 
forward renewal or replacement Certificates to the City within 10 Days after the renewal 
date containing all the required insurance provisions. 
11.3.9.2 
Each insurance policy required by the insurance provisions of this Agreement must provide 
the required coverage and must not be suspended, voided or canceled except after 30 Days 
prior written notice has been given to the City, except when cancellation is for non-payment 
of premium, then 10 Days prior notice may be given.  Such notice must be sent directly to 
Chandler Law-Risk Management Department, Post Office Box 4008, Mailstop 628, Chandler, 
Arizona  85225. If any insurance company refuses to provide the require notice, the 
Contractor or its insurance broker must notify the City of any cancellation, suspension, non-
renewal of any insurance within 7 Days of receipt of insurers’ notification to that effect. 
11.3.10 
City as Additional Insured.  The above-referenced policies are to contain, or be endorsed to 
contain, the following provisions: 
11.3.10.1 
The Commercial General Liability and Automobile Liability policies are to contain, or be 
endorsed to contain, the following provisions:  The City, its officers, officials, agents, and 
employees are additional insureds with respect to liability arising out of activities performed 
by, or on behalf of, the Contractor including the City's general supervision of the Contractor; 
Products and Completed Operations of the Contractor; and automobiles owned, leased, 
hired, or borrowed by the Contractor. 
11.3.10.2 
The City, its officers, officials, agents, and employees must be additional insureds to the full 
limits of liability purchased by the Contractor even if those limits of liability are in excess of 
those required by this Agreement. 
11.4 
BONDS AND OTHER PERFORMANCE SECURITY 
11.4.1 
After Agreement award, Contractor must provide a Performance Bond and a Payment 
Bond, each in an amount equal to the full amount of the Agreement Price. 
11.4.2 
Each such bond must be executed by a surety company or companies holding a Certificate

General Conditions 
 
Revised: 7/20/22 
 
GC-49 of 75 
 
of Authority to transact surety business in the State of Arizona, issued by the Director of the 
Arizona Department of Insurance and must be named in the current list of "Companies 
Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and as Acceptable 
Reinsuring Companies" as published in Circular 570 (amended) by the Audit Staff Bureau of 
Accounts, U.S. Treasury Department. A copy of the Certificate of Authority must accompany 
the bonds. The Certificate must have been issued or updated within two (2) years prior to 
the execution of this Agreement. The bonds must be written or countersigned by an 
authorized representative of the surety who is either a resident of the state of Arizona or 
whose principal office is maintained in this state, as by law required. 
11.4.3 
The bonds must be made payable and be acceptable to City. The bond forms for the 
performance and payment bonds must be in the forms required under A.R.S. § 34-221, et. 
Seq., as in Appendices 4  and 5 of these General Conditions. 
11.4.4 
Upon the request of any person or entity appearing to be a potential beneficiary of bonds 
covering payment of obligations arising under the Agreement Documents, Contractor must 
promptly furnish a copy of the bonds or must permit a copy to be made. 
11.4.5 
All bonds submitted for this Project must be provided by a company which has been rated AM 
Best rating of A- or better for the prior four quarters by the latest edition of the ‘Results 
Best’s Key Rating Guide (Property/Casualty)” published by the A.M. Best Company. 
11.4.6 
Personal or individual bonds are not acceptable. 
11.4.7 
If the surety on any Bond furnished by Contractor is declared a bankrupt or becomes 
insolvent, or Contractor’s right to do business is terminated in any state where any part of 
the Project is located, or it ceases to meet the requirements of this Section 11.4, Contractor 
must within 5 Days thereafter substitute another Bond and surety, both of which must be 
acceptable to City. 
 
SECTION 12 - INDEMNIFICATION 
12.1 
To the extent permitted by law, the Contractor and its owners, officers, directors, agents, 
employees, and subconsultants (collectively "lndemnitor") must indemnify, save, and hold 
harmless the City and its officers, officials, agents, and employees (collectively "lndemnitee") 
from any and all claims, actions, liabilities, damages, losses, or expenses (including court 
costs, attorneys' fees, and costs of claim processing, investigation, and litigation) (collectively 
"Claims") caused or alleged to be caused, in whole or in part, by the negligent, reckless, 
wrongful, or willful acts, errors, or omissions of Indemnitor in connection with this 
Agreement. This indemnity includes any Claim or amount arising out of or recovered under 
workers' compensation laws or on account of Indemnitor's failure to conform to any federal, 
state, or local law, statute, ordinance, rule, regulation, or court decree. Indemnitor must 
indemnify lndemnitee from and against any and all Claims, except those arising solely from 
lndemnitee's own negligent, reckless, wrongful, or willful acts, errors, or omissions. 
Indemnitor is responsible for primary loss investigation, defense, and judgment costs where 
this indemnification applies. In consideration of the award of this Agreement, Indemnitor 
agrees to waive all rights of subrogation against lndemnitee for losses arising from or 
related to this Agreement. Indemnitor's obligations under this provision survive the 
termination or expiration of this Agreement. 
 
SECTION 13 -DISPUTE RESOLUTION

General Conditions 
 
Revised: 7/20/22 
 
GC-50 of 75 
 
13.1 
All disputes arising out of or relating to the Agreement, the Work or the Project, other than 
termination under Section 10, will be resolved pursuant to the Dispute Resolution 
process set forth in Appendix 6 of these General Conditions, and not pursuant to MAG 
Specifications § 110. 
13.2 
Contractor agrees that during any dispute between the parties, Contractor will continue to 
perform its obligations under the Agreement until such dispute is resolved. 
13.3 
Notwithstanding any other provision in this Agreement, City has the right to immediately file 
in court and pursue an action for a temporary restraining order and injunctive relief against 
Contractor if City determines that such action is necessary to protect its interests under the 
Agreement, to obtain specific performance of any provision of the Agreement, to advance 
the completion of the Project, or to protect health, welfare and safety. 
 
 
SECTION 14 - MISCELLANEOUS PROVISIONS 
14.1 
AGREEMENT DOCUMENTS 
14.1.1 
The Agreement Documents are intended to permit the parties to complete the Work 
and all obligations required by the Agreement Documents within the Agreement Times for 
the Agreement Price. The Agreement Documents are intended to be complementary and 
interpreted in harmony so as to avoid conflict, with words and phrases interpreted in a 
manner consistent with construction and design industry standards. 
14.1.2 
It is the intent of the Agreement Documents to describe a functionally complete Project (or 
part thereof) to be constructed in accordance with the Agreement Documents.  Any labor, 
documentation, services, materials, or equipment that may reasonably be inferred from the 
Agreement Documents or from prevailing custom or trade usage as being required to 
produce the intended result must be provided by Contractor whether or not specifically 
called for at no additional cost to City.   
14.1.3 
The Agreement Documents establish the rights and obligations of the parties and include 
the Agreement, Addenda (which pertain to the Agreement Documents), Contractor's Bid or 
Proposal (including documentation accompanying the Bid and any post-Bid documentation 
submitted prior to Agreement award) when attached as an exhibit to the Agreement, the 
accepted Project Schedule, the Notice to Proceed, the Performance Bond, the Payment 
Bond, Project Design, Engineering and Specifications, these General Conditions, the Project 
Specific Special Provisions, Technical Specifications, Agreement Drawings, as the same may 
be more specifically identified in the Agreement, Change Orders, Work Change Directives, 
Field Orders and the written interpretations and clarifications of the Design Professional or 
City representative and Modifications issued after execution of the Agreement.  Approved 
Shop Drawings and the reports and drawings of subsurface and physical conditions are not 
Agreement Documents.   
14.1.4 
In the event of any inconsistency, conflict, or ambiguity between or among the Agreement 
Documents, the Agreement Documents will take precedence as follows from highest to 
lowest: Change Orders, Addenda, Agreement, Project Specific Special Provisions, General 
Conditions, Technical Specifications, Drawings/Plans, Chandler Amendments to MAG 
Standard Specifications and Chandler Standard Details, and MAG Uniform Standard 
Specifications and Details for Public Works Construction.  If applicable to this Agreement, 
Federal Provisions prevail.

General Conditions 
 
Revised: 7/20/22 
 
GC-51 of 75 
 
14.1.5 
On the Drawings, given dimensions will take precedence over scaled measurements and 
large scale drawings over small-scale drawings.  
14.1.6 
Clarifications and interpretations of the Agreement Documents will be issued by the Design 
Professional through the City. 
14.1.7 
The headings used in this Agreement or any other Agreement Documents, are for ease of 
reference only and must not in any way be construed to limit or alter the meaning of any 
provision. 
14.1.8 
The Agreement Documents form the entire agreement between City and Contractor. 
No oral representations or other agreements have been made by the parties except as 
specifically stated in the Agreement Documents. 
14.1.9 
The Agreement Documents may not be changed, altered, or amended in any way except in 
writing signed by a duly authorized representative of each party in the form of a Change 
Order. 
14.1.10 
Re-Use of Documents.  Neither Contractor nor any Subcontractor, manufacturer, fabricator, 
supplier or distributor will have or acquire any title to or ownership rights in any of the 
Drawings, Specifications or other documents (or copies of any thereof) prepared by or 
bearing the seal of the Design Professional; and they must not re-use any of them on 
extensions of the Project or any other project without written consent of City and the Design 
Professional and specific written verification or adaptation by the Design Professional. 
14.2 
REFERENCE STANDARDS 
14.2.1 
Reference to standards, specifications, manuals, or codes of any technical society, 
organization, or association, or to Laws or Regulations, whether such reference be specific 
or by implication, will mean the standard, specification, manual, code, or Laws or 
Regulations in effect at the time of opening of Bids (or on the Effective Date of the 
Agreement if there were no Bids), except as may be otherwise specifically stated in the 
Agreement Documents. 
14.2.2 
The provisions of any such standard, specification, manual or code, or any instruction of a 
Supplier will not change the duties or responsibilities of City, Contractor, Design 
Professional or Project Manager, or any of their Subcontractors, consultants, agents, or 
employees from those set forth in the Agreement Documents, nor will any such provision 
or instruction assign to City, Contractor, Design Professional, or any of their agents, or 
employees any duty or authority to supervise or direct the performance of the Work or any 
duty or authority to undertake responsibility inconsistent with the provisions of the 
Agreement Documents. 
14.3 
COMPLIANCE WITH ARIZONA LAW AND FEDERAL LAW 
14.3.1 
Compliance with A.R.S. § 41-4401.  Pursuant to the provisions of A.R.S. § 41-4401, the 
Contractor hereby warrants to the City that the Contractor and each of its subcontractors 
(“Subcontractors”) must comply with all Federal Immigration laws and regulations that 
relate to the immigration status of their employees and the requirement to use E-Verify set 
forth in A.R.S. §23-214(A).   
14.3.2 
A breach of the Contractor Immigration Warranty constitutes a material breach of this 
Agreement and subject to penalties up to and including termination of this Agreement.

General Conditions 
 
Revised: 7/20/22 
 
GC-52 of 75 
 
14.3.3 
The City retains the legal right to inspect the papers of any Contractor or Subcontractor 
employee who works on this Agreement to ensure that the Contractor or Subcontractor is 
complying with the Contractor Immigration Warranty.  The Contractor agrees to assist the 
City in the conduct of any such inspections.  
14.3.4 
The City may, at its sole discretion, conduct random verifications of the employment records 
of the Contractor and any Subcontractors to ensure compliance with Contractors 
Immigration Warranty.  The Contractor agrees to assist the City in performing any such 
random verifications.  
14.3.5 
The provisions of this Article must be included in any agreement the Contractor enters into 
with any and all of its subcontractors who provide services under this Agreement or any 
subcontract.  “Services” are defined as furnishing labor, time or effort in the State of Arizona 
by a contractor or subcontractor.  Services include construction or maintenance of any 
structure, building or transportation facility or improvement to real property.  
14.4 
HAZARDOUS ENVIRONMENTAL CONDITIONS 
14.4.1 
Contractor will not be responsible for any Hazardous Environmental Condition uncovered 
or revealed at the Site which was not shown or indicated in Drawings or Specifications or 
identified in the Agreement Document to be within the scope of the Work.  Contractor will 
be responsible for a Hazardous Environmental Condition created with any materials 
brought to the Site by Contractor, Subcontractors, Suppliers, or anyone else for whom 
Contractor is responsible. 
14.4.2 
If Contractor encounters a Hazardous Environmental Condition or if Contractor or anyone 
for whom Contractor is responsible creates a Hazardous Environmental Condition. 
Contractor must immediately:  
a. Secure or otherwise isolate such condition; 
b. Stop all Work in connection with such condition and in any area affected 
thereby; and 
c. Notify City and promptly thereafter confirm such notice in writing. 
14.4.3 
City will promptly retain a qualified expert to evaluate such condition or take corrective 
action, if any. 
14.4.4 
Contractor will be responsible for any and all civil or criminal penalties, fines, damages, or 
other charges imposed by any regulatory agency or court for sewage discharges that are in 
violation of applicable statutes and laws and that are a result, direct or indirect, of work 
performed under this Agreement.  Contractor will also be responsible for reimbursement 
to City for administration, reporting, and tracking expenses required as a result of any spill 
event.  In the event the regulatory agency or court imposes a probationary period, 
Contractor must post bond for the probationary period to ensure that all such costs are 
reimbursed to City.  This responsibility will apply whether penalties are imposed directly on 
Contractor or any of its Subcontractors, or the City of Chandler.  Contractor must defend 
and indemnify City against such penalties.  Regulatory agencies may include, but are not 
limited to, the Arizona Department of Environmental Quality (ADEQ) and the United States 
Environmental Protection Agency (USEPA). 
14.5 
COOPERATION AND FURTHER DOCUMENTATION

General Conditions 
 
Revised: 7/20/22 
 
GC-53 of 75 
 
Contractor agrees to provide City such other duly executed documents as may be 
reasonably requested by City to implement the intent of the Agreement Documents. 
14.6 
ASSIGNMENT 
Neither Contractor nor City will, without the written consent of the other assign, transfer or 
sublet any portion of this Agreement or part of the Work or the obligations required by 
the Agreement Documents, any such assignment will be void, will transfer no rights to the 
purported assignee, and would be a material breach of the Agreement. 
14.7 
SUCCESSORS 
Contractor and City intend that the provisions of the Agreement Documents are binding 
upon the parties, their employees, agents, heirs, successors and assigns. 
14.8 
LAWFUL PRESENCE 
Pursuant to A.R.S. §§ 1-501 and 1-502, City is prohibited from awarding an agreement to any 
natural person who cannot establish that such person is lawfully present in the United 
States.  To establish lawful presence, a person must produce qualifying identification and 
sign a City-provided affidavit affirming the identification provided is genuine.  This 
requirement will be imposed at the time of agreement award.  This requirement does not 
apply to business organizations such as corporations, partnerships, or limited liability 
companies. 
14.9 
NO BOYCOTT OF ISRAEL CERTIFICATION 
By Contractor's signature on this Agreement, Contractor certifies under A.R.S. § 35-393.01 
that Contractor is not currently engaged in and for the duration of this Agreement will not 
engage in a boycott of Israel. 
14.10 
NO THIRD PARTY BENEFICIARY 
Nothing under the Agreement Documents will be construed to give any rights or benefits 
in the Agreement Documents to anyone other than City and Contractor, and all duties and 
responsibilities undertaken pursuant to the Agreement Documents will be for the sole and 
exclusive benefit of City and Contractor and not for the benefit of any other party, unless 
otherwise expressly set forth in the Agreement Documents. 
14.11 
GOVERNING LAW AND VENUE 
The Agreement and all Agreement Documents will be deemed to be made under, and will 
be construed in accordance with and governed by the laws of the State of Arizona without 
regard to the conflicts or choice of law provisions thereof.  Any court action to enforce any 
provision of the Agreement or to obtain any remedy with respect hereto must be brought 
in the Superior Court, Maricopa County, Arizona, and for this purpose, each party hereby 
expressly and irrevocably consents to the jurisdiction and venue of such Court. 
14.12 
SEVERABILITY 
If any provision of the Agreement Documents or the application thereof to any person or 
circumstance will be invalid, illegal or unenforceable to any extent, the remainder of the 
affected provision, the remainder of the Agreement Documents, and the application 
thereof will not be affected and will be enforceable to the fullest extent permitted by law. 
14.13 
LEGAL REQUIREMENTS 
At all times relevant to its entry into this Agreement and performance of the Services and 
the Work, Contractor must fully comply with all Laws, Regulations, or Legal Requirements 
applicable to City, the Project, and the Agreement, including, without limitation, those set

General Conditions 
 
Revised: 7/20/22 
 
GC-54 of 75 
 
forth on Exhibit C of the Agreement. 
14.14 
PARTIAL INVALIDITY 
If any provision of the Agreement is held by a court of competent jurisdiction to be invalid, 
void or unenforceable, the remaining provisions will nevertheless continue in full force 
without being impaired or invalidated in any way. 
14.15 
ATTORNEYS' FEES 
Should either party to the Agreement bring an action to enforce any provision of the 
Agreement, the prevailing party will be entitled to recover reasonable attorneys' fees and 
costs in connection therewith. 
14.16 
CONFLICT OF INTEREST 
14.16.1 
Contractor agrees to disclose any financial or economic interest with the Project property, 
or any property affected by the Project, existing prior to the execution of the Agreement. 
Further, Contractor agrees to disclose any financial or economic interest with the Project 
property, or any property affected by the Project, if Contractor gains such interest during 
the course of this Agreement. If Contractor gains financial or economic interest in the 
Project during the course of this Agreement, 
this may be grounds for terminating this 
Agreement. Any decision to terminate the Agreement must be at the sole discretion of City. 
14.16.2 
Contractor will not engage the services on this Agreement of any present City employee who 
was involved as a decision maker in the selection or approval processes, or who negotiated 
or approved billings or Agreement Modifications for this Agreement. 
14.16.3 
Contractor agrees that it will not perform services on this Project for a contractor, 
subcontractor, or any supplier, not covered under this Agreement. 
14.17 
INDEPENDENT CONTRACTOR 
Contractor is and must be an independent contractor. Any provisions in the Agreement 
Documents that may appear to give City the right to direct Contractor as to the details of 
accomplishing the Work or to exercise a measure of control over the Work means that 
Contractor must follow the wishes of City as the results of the Work only. These results 
must comply with all applicable laws and ordinances. 
14.18 
NOTICE OF INJURY 
Should City or Contractor suffer injury or damage to their person or property because of 
any error, omission or act of the other party or of any of the other party's employees or 
agents or others for whose acts the other party is legally liable, claim must be made in 
writing to the other party within 7 Days of the first observance of such injury or damage. 
14.19 
CONFIDENTIALITY 
Contractor, for the benefit of City, hereby agrees it will not release or cause or permit 
to be released to the public any press notices, publicity (oral or written) or advertising 
promotion relating to, any statement regarding, or any other public announcement or 
disclosure or cause or permit to be publicly announced or disclosed, in any manner 
whatsoever, the specific terms and conditions of this Agreement or any comment relating 
to the Project or the Site. Notwithstanding the foregoing, Contractor will be entitled to 
disclose the terms of the Agreement to the extent required by law or in the course of 
enforcing or defending a claim or action hereunder. Contractor must give City reasonably 
prompt notice of any disclosure or statement made pursuant to this provision.

General Conditions 
 
Revised: 7/20/22 
 
GC-55 of 75 
 
14.20 
DATA CONFIDENTIALITY 
14.20.1 
As used in the Agreement, “data” means all information, whether written or verbal, including 
plans, specifications, renderings, photographs, studies, investigations, audits, analyses, 
samples, reports, calculations, internal memos, meeting minutes, data field notes, work 
product, proposals, correspondence and any other similar documents or information 
prepared by, obtained by, or transmitted to the City in the performance of this Agreement. 
14.20.2 
Contractor agrees that all data, regardless of form, including originals, images, and 
reproductions, prepared by, obtained by, or transmitted to City in connection with the 
Contractor’s performance of this Agreement is confidential and proprietary information 
belonging to City. 
14.20.3 
Except as specifically provided in this Agreement, Contractor or its Subcontractors must not 
divulge data to any third party without prior written consent of City.  Contractor or its 
Subcontractors must not use data for any purposes except to perform Work required under 
this Agreement.  These prohibitions will not apply to the following data provided Contractor 
has first given the required notice to City: 
a. Data which was known to Contractor or its Subcontractors prior to its 
performance under this Agreement unless such data was acquired in 
connection with Work performed for City; 
b. Data which was acquired by Contractor or its Subcontractors in its 
performance under this Agreement and which was disclosed to Contractor 
or its Subcontractors by a third party, who to the best of Contractor’s or its 
Subcontractor’s knowledge and belief, had the legal right to make such 
disclosure and Contractor or its Subcontractors are not otherwise required 
to hold such data in confidence; or  
c. Data which is required to be disclosed by virtue of law, regulation, or court 
order, to which the Contractor or its Subcontractors are subject. 
14.20.4 
In the event the Contractor or its Subcontractors are required or requested to disclose data 
to a third party, or any other information to which the Contractor or its Subcontractors 
became privy as a result of any other agreement with City, the Contractor must first notify 
City as set forth in this Section of the request or demand for the data.  The Contractor or its 
Subcontractors must give City sufficient facts so that City can be given an opportunity to 
first give its consent or take such action that City may deem appropriate to protect such 
data or other information from disclosure. 
14.20.5 
Unless prohibited by law, within 10 Days after completion of services for a third party on 
real or personal property owned or leased by City, the Contractor must promptly deliver, as 
set forth in this Section, a copy of all data to City.  All data will continue to be subject to the 
confidentiality agreements of this Agreement.  
14.20.6 
Contractor or its Subcontractors assume all liability for maintaining the confidentiality of 
the data in its possession and agree to compensate City if any of the provisions of this 
Section are violated by Contractor, its employees, agents, or Subcontractors.  Solely for the 
purposes of seeking injunctive relief, it is agreed that a breach of this Section will be deemed 
to cause irreparable harm that justified injunctive relief in court.  Contractor agrees that the 
requirements of this Section will be incorporated into all subcontracts entered into by 
Contractor.  A violation of this Section may result in immediate termination of this

General Conditions 
 
Revised: 7/20/22 
 
GC-56 of 75 
 
Agreement without notice.   
14.21 
SURVIVAL 
All warranties, representations and indemnifications by Contractor must survive the 
completion or termination of this Agreement. 
14.22 
COVENANTS AGAINST CONTINGENT FEES 
Contractor warrants that no person has been employed or retained to solicit or secure 
this Agreement upon an agreement or understanding for a commission, percentage, 
brokerage, or contingent fee, and that no member of City Council, or any employee of 
City has any interest, financially, or otherwise, in the firm. For breach or violation of this 
warrant, City will have the right to annul the Agreement without liability or at its discretion 
to deduct from the Agreement Price or consideration, the full amount of such commission, 
percentage, brokerage, or contingent fee. 
14.23 
NO WAIVER 
The failure of either party to enforce any of the provisions of the Agreement Documents or 
to require performance of the other party of any of the provisions hereof must not be 
construed to be a waiver of such provisions, nor will it affect the validity of the Agreement 
Documents or any part thereof, or the right of either party to thereafter enforce each and 
every provision. 
14.24 
NONEXCLUSIVE REMEDIES 
The remedies set forth in this Agreement are cumulative and not exclusive, and failure to 
exercise any remedy (including, without limitation, any right to terminate) will not preclude 
any party from exercising any other right in seeking any other remedy available to it at law 
or in equity. 
14.25 
PROJECT COMMUNICATIONS 
14.25.1 
All communications concerning the performance of the Work or the Project will be provided 
to the designated Project Manager and Contractor’s Representative set forth in Article 1 
of the Agreement. City may change the designated Project Manager and, subject to 
Section 4.4.20 of 
these General Conditions, Contractor may change Contractor 
Representative, by written notice to the other. 
14.25.2 
Project communications may be exchanged by e-mail, but email communications cannot 
change the terms of the Agreement or the Scope of Work, or effectuate any change that 
requires a written Change Order. 
14.25.3 
When any provisions of the Agreement Documents requires Contractor or the Design 
Professional to give written notice to City, it will be deemed to have been validly given if 
delivered in person or if delivered at or sent by registered or certified mail, postage prepaid, 
to the Parties indicated in Agreement Article 1, incorporated by reference.   
14.25.4 
When any provisions of the Agreement Documents requires City, Project Manager, or the 
Design Professional to give written notice to Contractor, it will be deemed to have been 
validly given if delivered in person to the person designated in the Agreement Documents 
as Contractor’s Resident Superintendent, or if delivered at or sent by registered or certified 
mail, postage prepaid, to Contractor at the last address in the Agreement Documents or 
such substitute address which Contractor designates in writing, or to the business address 
known to the giver of notice.

General Conditions 
 
Revised: 7/20/22 
 
GC-57 of 75 
 
14.26 
DRUG FREE WORKPLACE PROGRAM 
14.26.1 
City has adopted a policy establishing a drug free workplace for itself and as a requirement 
for Contractors doing business with City, to ensure the safety and health of employees 
working on City projects. 
14.26.2 
Contractor must require a drug free workplace for all employees working under the 
Agreement. Specifically, all employees of Contractor who are working under an 
agreement with City must be notified, in writing, by Contractor that they are prohibited 
from the manufacture, distribution, 
dispensation, possession or unlawful use of a 
controlled substance in the workplace. 
14.27 
Failure to require a drug free workplace in accordance with the City’s policy may result 
in termination of the Agreement and possible debarment form bidding on future City 
projects. 
SECTION 15 - PROVISIONS APPLICABLE SOLELY TO GMP AND COST-BASED AGREEMENTS, 
CHANGE ORDERS, AND JOB ORDERS 
15.1 
ADDITIONAL DEFINITIONS 
The definitions set forth in Section 2 apply to GMP and Cost-Based Agreements, Change 
Orders, and Job Orders, together with the additional definitions set forth below. 
 
Baseline Cost Model – 
A breakdown and estimate of the scope of the Project developed by CM@Risk pursuant to Section 17.5 
of these General Conditions. 
 
CM@Risk or Construction Manager at Risk – 
The person or firm selected by City to provide pre-construction and/or construction services as 
detailed in a Construction Manager at Risk Agreement with City. In these General Conditions, the 
term “Contractor” includes CM@Risk under both Pre-Construction and Construction Services 
Agreements. 
CM@Risk Fee or Contractor’s Fee – 
An agreed to percentage in an accepted GMP that represents the Contractor’s fee for performance of 
the Work. 
 
Agreement Documents – 
Where compensation under the Agreement is based upon a GMP accepted by City, the term 
“Agreement Documents” also includes the accepted GMP Proposal. 
 
Agreement Price – 
Where compensation under the Agreement based upon a GMP accepted by City, the term 
“Agreement Price” refers to the GMP. 
 
Cost-Based Agreement, Change Order, or Job Order – 
A Agreement, Change Order, or Job Order where the Agreement Price is based upon the actual 
cost of performing the Work, subject to the terms of the Agreement Documents, including this 
Section 15. These would include those generally referred to as “Cost of the Work plus a Fee with 
a GMP,” “Time and Materials,” or “Cost Plus a Fee.” 
 
Cost of the Work – 
The direct costs necessarily incurred by Contractor in the proper, timely, and complete performance 
on the Work. The Cost of the Work will include only those costs set forth in Section 15.2 of these

General Conditions 
 
Revised: 7/20/22 
 
GC-58 of 75 
 
General Conditions. 
 
Deliverables – 
The work products prepared by Contractor in performing the scope of work described in the 
Agreement. Some of the major deliverables to be prepared and provided by Contractor during pre-
construction may include but are not limited to: the Baseline Cost Model and Schedule that validate 
City’s plan and budget, Construction Management Plan, Detailed Project Schedule, Schedule of Values, 
alternative system evaluations, procurement strategies and plans, Detailed Cost Estimates, 
construction market surveys, cash flow projections, GMP Proposals, Subcontractor procurement plan, 
Subcontractor agreements, Subcontractor bid packages, Supplier agreements, Constructability 
Review, Cost Control Log, Traffic control and phasing plans and others as indicated in this Agreement 
or required by the Project Team. 
 
Pre-Construction Services Agreement – 
The Agreement entered into between City and the CM@Risk for Pre-Construction Services to be 
provided by the CM@Risk, including, without limitation, the generation of a GMP Proposal. If the GMP 
Proposal is accepted by City and a Construction Agreement is entered into between City and CM@Risk, 
the duties, obligations and warranties of the CM@Risk under the Pre-Construction Services 
Agreement survive and are incorporated into the resulting Construction Agreement. 
 
Pre-Construction Services – 
The services to be provided under the Pre-Construction Services Agreement, including Section 17 of 
these General Conditions. 
 
Detailed Project Schedule – 
The Detailed Project Schedule developed by the CM@Risk for the review and approval of the Project 
Manager in accordance with Section 17.3 of these General Conditions, if applicable. 
 
General Conditions Costs – 
Those costs set forth in Section 4 of Appendix 9 to these General Conditions. 
 
GMP Plans and Specifications – 
The plan and specifications upon which the Guaranteed Maximum price Proposal is based. 
 
GMP Proposal – 
The proposal of Contractor submitted pursuant to Section 17.7 of these General Conditions for the 
entire Work and/or portion (phases) of the Work. 
 
Guaranteed Maximum Price or GMP – 
The Guaranteed Maximum Price set forth in the Agreement, Change Order, or Job Order if applicable. 
15.2 
AGREEMENT PRICE 
15.2.1 
The Agreement Price for all Agreements, Change Orders, and Job Orders based upon 
payment of the Cost of the Work plus a Fee with a GMP, time and materials, or cost-plus a 
fee will be the Cost of the Work incurred plus the Fee agreed to in writing by City, limited to 
the amount of the GMP, if agreed to. Unless otherwise expressly provided in the Agreement, 
Change Order, or Job Order, all Cost Based pricing will be subject to and limited to GMP. 
15.2.2 
The Agreement Price may only be changed as set forth in Section 9 above.

General Conditions 
 
Revised: 7/20/22 
 
GC-59 of 75 
 
15.2.3 
Only costs specifically designated as reimbursable costs are eligible for payment by City or 
may be charged against the Agreement Price. All other costs will not be paid by City and will 
not be chargeable against the Agreement Price. 
15.2.4 
Cost-Based Agreements. For Agreements, Change Orders, or Job Orders, reimbursable 
costs must be determined pursuant to Appendix 9 to these General Conditions, Cost of the 
Work, and not by MAG Specifications §109.5. 
15.3 
ALLOWANCES 
15.3.1 
Contractor must include in the Agreement Price all Allowances stated in the Agreement 
Documents and agreed to in writing by City. Items covered by these Allowances must be 
supplied for such amounts and by such persons as City may direct, provided Contractor will 
not be required to employ persons against whom Contractor makes a reasonable objection. 
Materials, labor, and equipment under an Allowance will be selected by City in accordance 
with a schedule to be mutually agreed upon by City, Design Professional and Contractor or 
otherwise in reasonably sufficient time to avoid delay in the Work. 
15.3.2 
Unless otherwise provided in the Agreement Documents: 
15.3.2.1 
These Allowances must cover the cost to Contractor, less any applicable trade discount, of 
the materials, labor, and equipment required by the Allowances, delivered at the Site, and 
all applicable taxes; 
15.3.2.2 
Contractor’s costs for unloading and handling on the Site, labor, installation costs, overhead, 
profit and other expenses relating to materials, labor, and equipment required by the 
Allowance must be included in the Agreement Sum and not in the Allowance; and 
15.3.2.3 
Whenever the cost is more or less than the Allowance, the Agreement Sum must be 
adjusted accordingly by Change Order, the amount of which will recognize the difference 
between actual costs for an Allowance item and the amount of the Allowance item and 
changes, if any, in handling costs on the Site, labor, installation costs, overhead, profit and 
other expenses. 
15.4 
CONTINGENCY 
An agreed to amount in the GMP that may only be used in accordance with the terms set 
forth in these General Conditions and with prior written approval by the City. 
15.4.1 
Construction Contingency.  This GMP includes a dollar amount listed as a Construction 
Contingency which will be readily available for increased costs for subcontractors, material, 
and equipment subject to prior approval of City, which approval will not be withheld 
unreasonably.  The Construction Contingency may also be used, at the discretion of City, to 
reimburse CM@Risk for unexpected costs due to (a) scope gaps between trade 
subcontractors; (b) agreement default by trade subcontractors; (c) unforeseen field 
conditions, but only as defined in Section 9.5 above; (d) work completed to meet the intent 
of the design, but which was not indicated on the plans; (e) costs overruns not covered by 
allowances; (f) costs of corrective work not provided for elsewhere; and (g) implementation 
of any Recovery Plan.  Cost for which CM@Risk desires to be paid from the Construction 
Contingency must be documented by CM@Risk on a time and materials basis and are 
subject to verification by City.  If agreed to by City, a “Use of Contingency” form will be 
executed by both parties authorizing the actual cost of the work to be paid and included in 
the Work Item Direct Costs.  The Construction Contingency is not allocated to any particular

General Conditions 
 
Revised: 7/20/22 
 
GC-60 of 75 
 
item of the Project but may be used for any portion of the work as determined above.  Any 
amount not used in the Construction Contingency will belong to City and will reduce the 
GMP.  
15.4.2 
Owner’s Contingency.  This GMP also includes a dollar amount listed as an Owner’s 
Contingency which may be used only by the City (owner department) for upgrades and 
changes in scope or other changes not already included within the intent of the Project 
Program.  City will provide CM@Risk with a Work Change Directive authorizing CM@Risk to 
perform the additional work and to transfer funds from the Owner’s Contingency to the 
Work Item Direct Costs category to be paid with such direct costs.  These additional costs 
will be in an amount mutually agreed upon by CM@Risk and City or will be documented by 
CM@Risk on a time and materials basis and are subject to verification by City.  Any amount 
not used in the Owner’s Contingency will belong to the City and will reduce the GMP. 
15.5 
REDUCTION IN RETENTION 
If the Agreement Price is based upon a GMP, in order to receive payment of one-half of the 
retention as set forth in Section 8.1.5 above, Contractor must also submit to the Project 
Manager a complete accounting of the Actual Reimbursable Cost of the Work to date, 
including all such documentation (including, without limitation, invoices, subcontract, 
subcontractor change orders, purchase orders, records of payment, etc.) as City may require, 
to establish whether the payments made to Contractor equal, exceed, or are less than the 
actual reimbursable Cost of the Work to date. Any excess payments by City, as determined 
by the Project Manager, will be deducted from the one-half retention payment to be made 
to Contractor, and any additional excess amounts paid to Contractor will be refunded by 
Contractor to City. The Project Manager’s determinations as to Actual Reimbursable Cost 
of the Work will be the basis of payment until final Project Closeout and Final Payment 
under the Agreement. 
15.6 
FINAL PAYMENT 
If the Agreement Price is based upon a GMP, as a further condition precedent to Final 
Payment by City, Contractor must submit to the Project Manager a complete final 
accounting of the Actual Reimbursable Cost of the Work, including all such documentation 
(including, without limitation, 
invoices, subcontracts, subcontractor change orders, 
purchase orders, records of payment, etc.) as City may require, to establish whether the 
payments made to Contractor equal, exceed, or are less than the Actual Reimbursable Cost 
of the Work to date. Any excess payments by City, as determined by the Project Manager, 
will be deducted from the one-half retention payment to be made to Contractor, and any 
additional excess amounts paid to Contractor will be refunded by Contractor to City. 
Disputes relating to the Final Cost of the Work will be subject to City’s audit rights under 
Sections 8.8 above and 15.7 below, and the dispute resolution process under Section 13 
above. 
15.7 
OPEN BOOK 
On any GMP-based or Cost-Based Agreement, Job Order, or Change Order, City may attend 
any and all meetings or discussions pertaining to the Project, including bid openings, and 
must have access to all books, invoices, accounts, memoranda, correspondence, and 
written communications or records of any kind pertaining to the Project, including without 
limitation, those stored in electronic format. 
15.8 
DIFFERING SITE CONDITIONS AND/OR CHANGE IN LAWS 
A Change Order for increased costs under Section 9.5 or 9.6 above will only be considered

General Conditions 
 
Revised: 7/20/22 
 
GC-61 of 75 
 
or granted by City to the extent such actual, documented costs are justified. 
 
SECTION 16 - PROVISIONS APPLICABLE SOLELY TO JOB ORDER AGREEMENTS (JOC) 
16.1 
ADDITIONAL DEFINITIONS 
The definitions set forth in Sections 2 and below will apply to all Job Order Agreements and 
Job Orders. In addition, the definitions set forth in Section 15.1 above will apply to all Cost-
Based Job Orders. 
 
Agreement – 
Includes the Job Order Master Agreement and Job Order Project Agreements issued and agreed to by City 
and JOC Contractor. 
 
JOC Contractor’s Coefficient – 
A numerical factor that represents JOC Contractor total costs (indirect and direct costs, sales tax, 
profit, etc.) and other adjustments for market conditions. 
 
Job Order Request for Proposal (RFP) – 
The Request for Proposals issued by City for each Job Order Project Agreement relating to a specific 
Project. 
 
Job Order Cost Proposal – 
The Proposal submitted by JOC Contractor in response to a Job Order Request for Proposal (RFP) issued 
by City to develop a Job Order Project Agreement for a specific Project. 
 
Guaranteed Maximum Price (GMP) Job Order – 
Job Order under which JOC Contractor is compensated for actual costs incurred. 
 
Job Order Project Agreement (Job Order) – 
The agreement for a specific project, as it may be modified by all Change Orders, executed by the 
Parties, which incorporates the terms and conditions of the Job Order Master Agreement.  
16.2 
ORDERING AND PROCESSING PROCEDURES FOR JOB ORDERS 
16.2.1 
The process for developing and issuing a Job Order for a particular Project consists of three 
(3) procedures: (1) issuance of a RFP by City; (2) JOC Contractor’s response to the RFP in the 
form of JOC Contractor’s Job Order Cost Proposal; and (3) Issuance of a Job Order by City, as 
set for below. 
16.2.2 
RFP’s For Job Orders 
16.2.2.1 
City will provide to JOC Contractor RFP with a Scope of Work (SOW) describing the Work to 
be performed, which may include special instructions and conditions, material submittal 
requirements, and, if applicable, a complete set of sketches, construction drawings and 
specifications for the Job Order. 
16.2.2.2 
Some Job Order RFP’s will be issued by City without detailed sketches, drawing and 
specifications and will rely on JOC Contractor to produce them for City review and approval 
and is considered to be Pre-Construction and incidental design services included in JOC 
Contractor’s overhead for GMP Job Orders. In addition JOC Contractor will not be 
reimbursed for any Pre-Job Order costs, including proposal preparation, attendance during 
negotiations, or site visits.

General Conditions 
 
Revised: 7/20/22 
 
GC-62 of 75 
 
16.2.3 
JOC Contractor’s Job Order Cost Proposal 
16.2.3.1 
JOC Contractor must respond within ten (10) calendar days of the RFP date or site visit, 
whichever is later or as otherwise indicated on a case-by-case basis, by submitting JOC 
Contractor’s Job Order Cost Proposal to the City representative. 
16.2.3.2 
Unless otherwise required under the terms of the RFP, JOC Contractor’s Job Order Cost 
Proposal must include the following. 
a. JOC Contractor’s Job Order Cost Proposal in PDF and electronic format; 
b. A Project Schedule and schedule of values that reflects the costs of each work 
element on the schedule. The schedule must show all milestones (e.g., 
permits, submittals, ordering materials, demolition, work phases, closeout 
and completion date); and 
c. Necessary documentation will be required to indicate that adequate scoping, 
layout, setup and planning to accomplish the Work has been done. 
Examples of documentation that might reasonably be expected include 
sketches, drawings, calculations, catalog cuts and specifications produced 
to a level of detail and skill that could be expected of experienced, 
competent Project Managers with five or more periods experience in their 
respective trade. 
16.2.3.3 
JOC Contractor must select Subcontractors based on qualifications alone or on a 
combination of qualifications and price and must not select Subcontractors based on 
price alone. A qualifications and price selection may be a one-step selection based on 
a combination of qualifications and price or two-step selection. In a two-step selection, 
the first step must be based on qualifications alone and the second step may be based or 
a combination of qualifications and price or on price alone. 
16.2.3.4 
Upon request, JOC Contractor must provide City with copies of Subcontractor quotes and 
the basis for selection of each Subcontractor. 
16.2.3.5 
If City objects to a selected Subcontractor, City will make the objection and the reasons for 
the objection known to the JOC Contractor. JOC Contractor must then present an 
acceptable Subcontractor for the applicable discipline. City will not unreasonably object 
to or withhold approval of a Subcontractor. 
16.2.3.6 
For self-performed work, the City retains the right to have the JOC Contractor establish JOC 
Contractor’s costs by bidding their costs against at least three (3) other interested trade 
Contractors. No self- performed work will be allowed to be performed on a lump sum basis. 
16.2.4 
Issuance of Job Order 
16.2.4.1 
City Representative will compare the JOC Contractor’s Job Order Cost Proposal with the City’s 
estimate, 
schedules and other requirements, and then, if the City Representative 
determines it is in the best interest of City, arrange a meeting with JOC Contractor, at which 
time the JOC Contractor’s Job Order Cost Proposal will be discussed and negotiated. 
16.2.4.2 
If the City Representative determines that it is in the best interest of the City, City will then 
issue a Job Order to JOC Contractor for execution. 
16.2.4.3 
Specific Job Orders may vary, but unless agreed to by City in writing otherwise, the content

General Conditions 
 
Revised: 7/20/22 
 
GC-63 of 75 
 
of Job Orders under the Agreement will generally be as follow, all of which will be signed 
and/or initialed by JOC Contractor’s designated representative: 
a. The description of the Scope of the Work and Project Schedule (attached as 
Exhibit A to the Job Order); 
b. The address or location of the Work; 
c. The Agreement Price for Work (Construction) included in the Project 
(attached as Exhibit B to the Job Order); 
d. The name of the JOC Contractor representative for the Project; 
e. The Drawings and Specifications for the Project; 
f. 
If any shop drawings, project date and/or samples are required for the Job 
Order, the date for delivery of each required item (included in the Project 
Schedule, Exhibit A to the Job order); and 
g. Project Specific Provisions, if any, in Exhibit A  to the Job Order, 
including, without limitation, whether any of the following are required: 
Pre-Construction Conference, weekly progress meetings, field office, 
storage enclosure, materials and equipment handling facility, submittals, 
shop drawings, product data, equipment list, samples, project manual, 
schedule of values, Construction progress schedule, narrative reports, 
progress report, progress charts, progress photographs, materials status 
report, Construction diagram, Construction status report, operation and 
maintenance data, operating maintenance instructions and parts list, and 
as-build drawings. 
16.2.5 
Job Order Intent. Each Job Order will be interpreted to include all items reasonably 
necessary to complete the Project under that Job Order as described in the scope of the 
Work in that Job Order. All Work must be performed in a professional manner and all 
materials used must be new and of the highest quality and of the type best adapted to 
their purpose, unless otherwise specified. The Notice to Proceed date, and the award date 
established therein, will be deemed an integral part of the Job Order the same as if set forth 
therein. 
16.3 
INCIDENTAL DESIGN SERVICES 
16.3.1 
This effort includes all “extensions of design” for systems that are typically specified in 
a performance oriented manner by consultants and designers. Examples include: fire 
sprinkler systems, fire alarm and sprinkler systems, DDC controls, control systems, 
prefabricated metal building and similar situations. These designs are normally provided 
under submittals as a shop drawing with engineering backup and as appropriate, seals of 
registered engineers specializing in the particular system. 
16.3.2 
Incidental design includes all documents, sketches, schematic diagrams, floor plan 
layouts, equipment schedules and other documents produced by the JOC Contractor to 
define the work required for projects that the City does not develop formal or abbreviated 
designs requiring a seal by a registered engineer. Incidental design does not include 
preparation of designs requiring an architect or engineer seal. 
16.3.3 
JOC Contractor represents, covenants, and agrees, and contractually assumes the 
obligation to furnish, all of the required Design Services through properly licensed and

General Conditions 
 
Revised: 7/20/22 
 
GC-64 of 75 
 
experienced Design Professionals in complete accordance with all of the duties imposed 
on a Design Professional under the Agreement Documents, Laws, Regulations, or Legal 
Requirements, and the common law. 
16.3.4 
All Design Documents (and all other Project-related documents, models, computer 
drawings and other electronic expression, photographs and other expressions CADD, and 
BIM files and images included) that JOC Contractor and/or JOC Contractor’s Design 
Professional(s) prepare in connection with a Job Order and the copyrights therein 
(collectively, the “Instruments of Service”) will be the property of City. JOC Contractor 
covenants and agrees to execute any additional document reasonably requested by City 
to confirm such assignment without any additional compensation. 
16.4 
CONSTRUCTION SERVICES 
16.4.1 
The following subsections of this Section 16.4 set forth requirements beyond those set forth 
in Section 4 above which apply to Construction Services performed under a Job Order. 
16.4.2 
JOC Contractor must perform the Work using only those firms, team members and 
individuals designated by JOC Contractor consistent with each Job Order or otherwise 
approved by City pursuant to the General Conditions. No other entities or individuals may 
be used without the prior written approval of the Project Manager. 
16.4.3 
Construction Phasing 
16.4.3.1 
City use of the facilities is anticipated while the Work is being performed. The Work must 
be planned and accomplished so that there will be a minimum of interference and 
inconvenience to occupants in the building and agencies in the vicinity and to other 
craftsmen who may have to do work in the affected facilities. Any blockage of building 
exits or driveways must be coordinated in advance. 
16.4.3.2 
If applicable, furniture, portable office equipment and wall appurtenances not rigidly 
fastened to the walls must be moved by JOC Contractor, protected from damage and 
replaced to the original position upon completion of the work. If the work required by 
the Job Order will not allow furniture and portable office equipment to be replaced to its 
original position, new locations will be designated by City. Incidental costs associated with 
moving one-piece furnishings up to approximately 150 pounds to perform such tasks as 
painting, carpet or tile replacement, etc., are considered a general cost of building 
renovation and must be included in the JOC Contractor’s Coefficient. Costs for large scale 
or wholesale removal and replacement of large quantities of 
desks or modular 
workstations, copiers, multiple full file cabinets, etc. to another location or storage outside 
the work space, or disassembly and reassembly of modular furniture is not considered 
part of the JOC Contractor’s Coefficient and will be priced separately. 
16.4.3.3 
The work must, so far as practicable, be done in definite sections or divisions and confined 
to limited areas which must be completed before work in other sections or divisions are 
begun. 
16.4.4 
Work Site Conflicts. In the event of a conflict between JOC Contractor and others in an 
occupied facility or where other Contractors are performing work on the same facility 
under other Agreements, City will decide to dispute and that decision will be final. 
16.4.5 
Ownership of Work Product. Work Product prepared or otherwise created in connection

General Conditions 
 
Revised: 7/20/22 
 
GC-65 of 75 
 
with the performance of this Agreement, including the Work, are to be and remain the 
property of City. For purposes of this provision, “Work Product” will include all designs, 
drawings, plans, specifications, ideas, renderings and other information or matter, in 
whatever form created (e.g., electronic or printed) and in all media now known or 
hereinafter created. All Work Product will be considered Work Made for Hire as defined 
in the United States Copyright Act 17 U.S.C. §101 (Copyright Act). If for any reason any such 
Work is found not to be a work for hire, JOC Contractor hereby transfers and assigns 
ownership of the copyright in such Work to City. The rights in this Section are exclusive to 
City in perpetuity. 
16.5 
OPTIONAL LIQUIDATED DAMAGES 
16.5.1 
Specific Job Orders. City will have the right to assess liquidated damages in relation to 
any specific JOC Project Agreement as set forth below. 
16.5.2 
Substantial Completion Liquidated Damages. JOC Contractor acknowledges and agrees 
that if JOC Contractor fails to obtain Substantial Completion of the Work within the 
Agreement Time, City will sustain extensive damages and serious loss as a result of such 
failure. The exact amount of such damages will be extremely difficult to ascertain. 
Therefore, City and JOC Contractor agree that if JOC Contractor fails to achieve Substantial 
Completion of the Work within the Agreement Time, City will be entitled to retain or 
recover from JOC Contractor, as liquidated damages and not as a penalty, the sum per 
calendar day as indicated in MAG § 108.9. 
16.5.3 
Final Acceptance Liquidated Damages. For the same reasons set forth in Section 16.5.2 
above, City and JOC Contractor further agree that if JOC Contractor fails to achieve Final 
Acceptance of the Work within the Agreement Time, City will be entitled to retain or recover 
from JOC Contractor, as liquidated damages and not as a penalty, the sum per calendar 
day as indicated in MAG § 108.9 commencing from the actual date of Substantial 
Completion or Final Acceptance as required under any specific JOC Project Agreement. 
16.5.4 
MAG Liquidated Damages. Liquidated damages provisions in MAG § 108.9 may apply to any 
specific JOC Project Agreement.   
16.5.5 
City may deduct liquidated damages assessed pursuant to this Section 16.5 from any 
unpaid amounts then or thereafter due JOC Contractor under the Agreement or any 
specific JOC Project Agreement between JOC Contractor and City. Any liquidated damages 
not so deducted from any unpaid amounts due JOC Contractor must be payable to City 
at the demand of City, together with interest from the date of the demand at the highest 
lawful rate of interest payable to JOC Contractor. 
16.6 
PERFORMANCE MEASUREMENT 
16.6.1 
Performance Assessment. After the Final Acceptance of Work under each Job Order, City 
will complete a written evaluation of the performance of JOC Contractor on the Job Order. 
16.6.2 
Consideration in Assignment of Work. JOC Contractor’s record of cost, schedule and 
quality performance and comparative assessments will be significant considerations in 
City’s determination whether to award future Job Orders. JOC Contractor agrees that any 
determination by City not to not award future Job Orders or Option periods based on 
performance will be at the sole discretion of City.

General Conditions 
 
Revised: 7/20/22 
 
GC-66 of 75 
 
SECTION 17 - PROVISIONS APPLICABLE SOLELY TO PRE-CONSTRUCTION SERVICES FOR 
CONSTRUCTION MANAGER AT RISK 
17.1 
ADDITIONAL DEFINITIONS 
The definitions set forth in Section 2 and 15.1 above will apply to all Pre-Construction 
Services Agreements. 
17.2 
GENERAL 
17.2.1 
CM@Risk must perform the  Services required by, and in accordance with the Agreement 
Documents and as outlined in Exhibit A of the Agreement to the satisfaction of the 
Project Manager, exercising the degree of care, skill, diligence and judgment a professional 
construction manager experienced in the performance of such services for construction 
and/or facilities of similar scope, function, size, quality, complexity and detail to the 
Project in urban areas throughout the United States, would exercise at such time, under 
similar conditions. CM@Risk must, at all times, perform the required services consistent 
with sound and generally accepted engineering principles and construction management 
and construction contracting practices. 
17.2.2 
As a participating member of the Project Team, CM@Risk must provide to City and Design 
Professional a written evaluation of City’s Project Program and budget, each in terms of 
the other, with recommendations as to the appropriateness of each. CM@Risk must 
prepare a Baseline Cost Model that validates City’s budget. The Baseline Cost Model must 
include all assumptions and basis of estimates in enough detail so that the Project Team 
can compare future detail estimates to the Baseline Cost model for variances. City and 
Design Professional will provide all the reasonably required data that is available in 
order to reach agreement between the team members that the Baseline Cost Model is an 
accurate projection of the costs of the Project. 
17.2.3 
CM@Risk must attend Project Team meetings, which may include, but are not limited to, 
bi- weekly Project management meetings, Project workshops, special Project meetings, 
construction document rolling reviews, public meetings and partnering sessions. CM@Risk 
attendance at design or other meetings in which CM@Risk is provided the opportunity but 
does not actively participate and/or is not properly prepared is not acceptable. Repeated 
instances of non-participation and/or lack of preparedness will be grounds for termination 
of CM@Risk Agreement for default. 
17.2.4 
CM@Risk must provide Pre-Construction Services, described herein, in a timely manner 
and consistent with the intent of the most current Drawings and Specifications. CM@Risk 
must promptly notify City in writing whenever CM@Risk determines any Drawings or 
Specifications are inappropriate for the Project and/or cause changes in the scope of Work 
that deviates more than the allowed contingencies within the Baseline Cost Model or 
requires an adjustment in the Baseline Cost Model, Detailed Cost Estimate, Detailed 
Project Schedule, GMP Proposals and/or in the Agreement Time for the Work, to the extent 
such as established. 
17.2.5 
CM@Risk when requested by City, must attend, make presentations and participate as may 
be appropriate in public agency and or community meetings, relevant to the Project. 
CM@Risk must provide drawings, schedule diagrams, budget charges and other materials 
describing the Project when their use is required or appropriate in any such public agency 
meetings.

General Conditions 
 
Revised: 7/20/22 
 
GC-67 of 75 
 
17.2.6 
Ownership of Work Product. All Work Product prepared or otherwise created in connection 
with the performance of this Agreement, including the Work, are to be and remain the 
property of City. For purposes of this provision, “Work Product” will include all designs, 
drawings, plans, specifications, ideas, renderings and other information or material, in 
whatever form created (e.g., electronic or printed) and in all media now know or hereinafter 
created. All Work Product will be considered Work Made for Hire as defined in the United 
States Copyright Act 17 U.S.C. 
§101 (Copyright Act). If for any reason any such Work is found not to be a work for 
hire, Contractor hereby transfers and assigns ownership of the copyright in such Work to 
City. The rights in this Section are exclusive to City in perpetuity. 
17.2.7 
CM@Risk represents to City in completing Pre-Construction Services and providing the 
reports 
and analysis required thereunder, that Work can be properly and timely 
constructed within the GMP Proposal, if accepted. CM@Risk does not assume any design 
responsibilities unless specifically called for in the scope of work, but CM@Risk will be 
responsible for their errors, omissions or inconsistencies included in the Work. 
17.3 
DETAILED PROJECT SCHEDULE 
17.3.1 
The fundamental purpose of the Detailed Project Schedule is to identify, coordinate and 
record the tasks and activities to be performed by all of the Project Team members and 
then for the Project Team to utilize that Deliverable as a basis for managing and 
monitoring all member’s compliance with the schedule requirements of the Project. 
Each Project Team member is responsible for its compliance with the Detailed Project 
Schedule requirements. CM@Risk must, however, develop and maintain the Detailed 
Project Schedule on behalf of and to be used by the Project Team based on input from the 
other Project Team members. The Baseline Project Schedule must be developed as part 
of the Baseline Cost Model. The Detailed Project Schedule must use the Critical Path 
method (“CPM”) technique, unless required otherwise, in writing by City. CM@Risk must 
use scheduling software acceptable to City to develop the Detailed Project Schedule. 
The Detailed Project Schedule must be presented in graphical and tabular reports as 
agreed upon by the Project Team. If Project phasing as described below is required, the 
Detailed Project Schedule must indicate milestone dates for the phases once 
determined. As part of construction phase, City may require CM@Risk to prepare a 
“resource loaded” schedule for all work, including work performed by Subcontractors, 
detailing each of the project tasks and the required/anticipated number of personnel per 
day for each task. CM@Risk must also indicate on the schedule its ability to meet said 
required/anticipated personnel requirements. 
17.3.2 
CM@Risk must include and integrate in the Detailed Project Schedule the services and 
activities required of City, Design Professional and CM@Risk including all construction 
phase activities based on the input received from City and the Design Professional. 
The Detailed Project Schedule must define activities as determined by City to the extent 
required to show: (a) the coordination between preliminary design and various pre-
construction documents, (b) any separate long-lead procurements, (c) any permitting 
issues, (d) any land, right-of-way, or easement acquisition, (e) bid packaging strategy and 
awards to Subcontractors and Suppliers, (f) major stages of construction, (g) start-up and 
commissioning, and (h) occupancy of the completed Work by City. The Detailed Project 
Schedule must include by example and not limitation, proposed activity sequences and 
durations for design, procurement, construction and testing activities, milestone dates for 
actions and decisions by the Project Team, preparation and processing of shop drawings

General Conditions 
 
Revised: 7/20/22 
 
GC-68 of 75 
 
and samples, delivery of materials or equipment requiring long-lead time procurement (if 
any), milestone dates for various construction phases, Total Float for all activities to the 
extent authorized by City, relationships between the activities, 
City’s occupancy 
requirements showing portions of the Project having occupancy priority, and proposed 
dates for Final Acceptance. 
17.3.3 
A Baseline Project Schedule must be initiated with the project Baseline Cost Model and 
agreed to by the project team at the same time. CM@Risk must update and maintain a 
detailed Project Schedule throughout pre-construction such that it will not require major 
changes at the start of the construction phase to incorporate CM@Risk’s plan for the 
performance of the construction phase Work. CM@Risk must provide updates and/or 
revisions to the Detailed Project Schedule for use by the Project Team, whenever required, 
but no less often than at the Project Team meetings. CM@Risk must include with such 
submittals a narrative describing its analysis of the progress achieved to-date vs. the 
Baseline Project Schedule, including any concerns regarding delays or potential delays, and 
any recommendations regarding mitigating actions. 
17.3.4 
If phased construction is deemed appropriate at the time of developing the Baseline Cost 
Model or during the development of the Detailed Project Schedule, and City approves, 
CM@Risk must review the design and make recommendations regarding the phased 
issuance of Construction Documents to facilitate phased construction of the Work, with 
the objective of reducing the Project Schedule and/or Cost of the Work. CM@Risk must take 
into consideration such factors as natural and practical lines of work severability, 
sequencing effectiveness, access and availability constraints, total time for completion, 
construction market conditions, labor and materials availability, and any other factors 
pertinent to saving time and cost. 
17.3.5 
Long Lead Time Items. As part of developing the Detailed Project Schedule, CM@Risk must 
identify all long lead time materials, fabrications, equipment, or other items which may 
impact the Project Schedule and may require early action on the part of the Project Team. 
Dates for selecting and ordering long lead time items will be included and highlighted 
in the Detailed Project Schedule 
17.3.6 
Equipment Plan. Contractor must develop an Equipment Plan that addresses all rental 
and owned equipment, regardless of whether such equipment will be provided by 
CM@Risk or subcontractor(s), that will be necessary to construct the Project and the cost 
of which will be included as a Cost of the Work in the GMP Proposal. The Equipment Plan 
will seek to minimize the cost of the equipment to City and maximize the efficient and 
coordinated use of the equipment for completion of the Project. The Equipment Plan will 
not only include the costs and allowable lease rates for the equipment, but will also include 
an equipment schedule that will be incorporated into the Detailed Project Schedule and the 
Schedule of Values submitted with the GMP Proposal. 
17.4 
DESIGN DOCUMENT REVIEWS 
17.4.1 
CM@Risk must evaluate periodically the availability of labor, materials/equipment, cost- 
sensitive aspects of the design; and other factors that may create an unacceptable variance 
to the Baseline Cost Model and/or Baseline Project Schedule. 
17.4.2 
CM@Risk must recommend, in conjunction with the Project Team, those additional surface 
and subsurface investigations that, in its professional opinion, are required to provide the 
necessary 
information for CM@Risk to construct the Project. 
These additional

General Conditions 
 
Revised: 7/20/22 
 
GC-69 of 75 
 
investigations, if agreed to 
be necessary by the Project Manager and the Design 
Professional, will be acquired by City and copies of the reports will be provided to CM@Risk. 
17.4.3 
CM@Risk must meet with the Project Team as required to review designs during their 
development. CM@Risk must familiarize itself with the evolving documents through 
pre- 
construction. CM@Risk must proactively advise the Project Team and make 
recommendations on factors related to construction costs, and concerns pertaining to the 
feasibility and practicality 
of any proposed means and methods, selected materials, 
equipment and building systems, and, labor and material availability. CM@Risk must 
furthermore advise the Project Team on proposed site improvements, excavation and 
foundation considerations, as well as, concerns that exist with respect to coordination of 
the Drawings and Specifications. CM@Risk must use established value analysis principles 
in recommending cost effective alternatives. 
17.4.4 
CM@Risk must routinely conduct constructability and bid-ability reviews of the Drawings 
and Specifications as necessary to satisfy the needs of the Project Team. The reviews must 
attempt to identify all discrepancies and inconsistencies in the Construction Documents 
especially those related to clarity, consistency, completeness and coordination of Work of 
Subcontractors and Suppliers. 
17.4.4.1 
CM@Risk must evaluate whether: (a) the Drawings and Specifications are configured to 
enable efficient construction; (b) design elements are standardized; (c) construction 
efficiency 
is 
properly 
considered 
in 
the 
Drawings 
and 
Specifications; 
(d) 
module/preassembly design is prepared to facilitate fabrication, transport and installation; 
(e) sequences of Work required by or inferable from the Drawings and Specifications are 
practicable; (f) the design has taken into consideration efficiency issues concerning access 
and entrance to the site, laydown and storage 
of materials, staging of site facilities, 
construction parking, and other similar pertinent issues; and (g) the design maintains 
continued operation of the existing City systems and maintains traffic on adjacent 
roadways. CM@Risk must also review the Drawings and Specifications to ensure that what 
is depicted therein can be constructed as designed and must promptly inform the Project 
Team of any issues. 
17.4.4.2 
CM@Risk must check cross-reference and complementary Drawings and sections within 
the Specifications and in general evaluate whether: (a) the Drawings and Specifications 
are sufficiently clear and detailed to minimize ambiguity and to reduce scope interpretation 
discrepancies; (b) named materials and equipment are commercially available and are 
performing well, or otherwise, in similar installations; (c) Specifications include alternatives 
in the event a requirement cannot be met in the field; and (d) in its professional opinion, the 
Project is likely to be subject to Differing Site Conditions. 
17.4.4.3 
The results of the reviews must be provided to Project Team in formal, written reports 
clearly 
identifying all reviewed documents and the discovered discrepancies and 
inconsistencies in the Drawings and Specifications with notations and recommendations 
made on the Drawings, Specifications and other documents. CM@Risk must meet with 
Project Team to discuss any findings and review reports. 
17.4.4.4 
CM@Risk’s reviews must be from a Contractor’s perspective, and though it will serve to 
eliminate/reduce the number of RFIs) and changes during the construction phase, 
responsibility for the Drawings and Specifications will remain with the Design Professional 
and not CM@Risk.

General Conditions 
 
Revised: 7/20/22 
 
GC-70 of 75 
 
17.4.5 
It is CM@Risk’s responsibility to assist the Design Professional in ascertaining that, in 
CM@Risk’s professional opinion, the Construction Documents are in accordance with 
applicable Laws, Regulations, or Legal Requirements, building codes, sound engineering 
principle’s rules and regulations. If CM@Risk recognizes that portions of the Construction 
Documents are at variance with applicable laws, statutes, ordinances, building codes, 
sound engineering principle’s rules and regulations, it must promptly notify the Project Team 
in writing, describing the apparent variance of deficiency. However, the Design Professional 
is ultimately responsible for the compliance of the Drawings and Specifications with those 
laws, statutes, ordinances, building codes, rules and regulations. 
17.4.6 
The Project Team will routinely identify and evaluate using value analysis principles and 
alternate systems, approaches, design changes that have the potential to reduce Project 
costs while still delivering a high quality and fully functional Project consistent with 
the Project Program. If the Project Team agrees, CM@Risk in cooperation with the Design 
Professional, will perform a cost/benefit analysis of the alternatives and submit such in 
writing to the Project Team. City, through the Project Manager, will direct which alternatives 
will be incorporated into the Project. The Design Professional will have full design 
responsibility for the review and incorporation of CM@Risk suggested alternatives into 
the Drawings and Specifications. CM@Risk must analyze the costs and schedule impacts of 
the alternatives against the Baseline 
Cost Model and Schedule and provide a 
recommendation for the Project Team’s consideration and City’s approval prior to the 
establishment of the GMP. 
17.5 
BASELINE COSTS MODEL, DETAILED COST ESTIMATES, AND SCHEDULE OF VALUES 
17.5.1 
At the conclusion of the Master Planning and Programming, if required, CM@Risk will 
review all available information regarding the design and scope of the Project using 
CM@Risk’s experience in performing similar work, knowledge of similar projects and 
current and projected construction costs and, based upon that review, must develop a 
Baseline Cost Model for review by the Project Team and approval by City.  Once approved 
by City, the Baseline Cost Model will be continually referenced as detailed estimates are 
created as the design progresses throughout Pre-Construction until the final GMP for the 
entire Project is established.  A final GMP for the entire Project must be established and 
approved by City prior to the start of construction. It is the responsibility of CM@Risk 
to ensure City has sufficient information to evaluate  and  approve  a  final  GMP  prior  to  
the  time  necessary to  start  construction  so construction can be completed within the 
Agreement Time.  The Project Detailed Cost Estimate will be the best representation from 
CM@Risk of what the complete functional Project’s construction costs will be as indicated 
by the most current available documents and will be constantly checked against the 
Baseline Cost Model. CM@Risk must communicate to the Project Team and assumptions 
made in preparing the Baseline Cost Model. The Baseline Cost 
Model must support 
CM@Risk’s Detailed Cost Estimates and may be broken down initially as dictated by the 
available information, as required by City. 
17.5.2 
After receipt of the Design Professional’s most current documents from certain specified 
pre- construction milestones, CM@Risk must provide a draft Detailed Cost Estimate 
including a detailed written report detailing any variances to the Baseline Cost Model and 
Baseline Project Schedule. The Design Professional and CM@Risk will reconcile any 
disagreements on the estimate to arrive at an agreed upon Detailed Cost Estimate for the 
construction costs based on the scope of the Project through that specified pre-
construction milestone. Pre-Construction milestones applicable to this paragraph are:

General Conditions 
 
Revised: 7/20/22 
 
GC-71 of 75 
 
Master Planning and Programming, Schematic Design, 50% Design Development, 100% 
Design Development, and 50% Construction Drawings, If no consensus is reached, City will 
make the final determination. If the Project Team requires additional updates of the 
Detailed Cost Estimate beyond that specified in this paragraph, CM@Risk must provide the 
requested information in a timely manner. 
17.5.3 
If at any point the Detailed Cost Estimate submitted to City exceeds the previously 
accepted Baseline Cost Model or previously approved Detailed Cost Estimate agreed to as 
set forth in Section 17.5.2 above, CM@Risk must make appropriate recommendations to 
project Team on means/methods, materials, and or other design elements that it 
believes will reduce the estimated construction costs, such that it is equal to or less than 
the established Project Team’s Baseline Cost Model. 
17.5.4 
Unless other levels of completion are agreed to in writing in the Construction Documents, 
at 50% Construction Drawings and included with the associated report, CM@Risk must 
also submit to the Project Team for review and approval a Schedule of Values that complies 
with the following requirements. The Schedule of Values must be based on City standard 
bid schedule and highlight significant variances from any previously submitted Schedule 
of Values. The Schedule of Values must be directly related to the breakdowns reflected in 
the Detailed Project Schedule and CM@Risk’s Detailed Cost Estimate.  In addition, the 
Schedule of Values must:  (a) detail unit prices and quantity take-offs, (b) detail all other 
contingencies and unit price Work shown and specified in the detailed design documents. 
17.5.5 
CM@Risk is to track, estimate/price and address the Project Team’s overall project cost issues 
that arise outside of the Baseline Cost Model and the latest approved Detailed Cost 
Estimate such as: City generated changes, Project Team proposed changes, alternate 
system analysis, constructability items and value engineering analysis. The system used 
to implement this process will be referred to as the Design Evolution Log. This is to be 
addressed between the Baseline Cost Model and the Master Planning and Programming 
Detailed Cost Estimate, and then (unless other levels of completion are agreed to in writing 
in the Construction Documents) between the Detailed Cost Estimates for each of the pre-
construction milestones thereafter, Schematic Design, 50% Design Development, 100% 
Design Development, and 50% Construction Documents, and the bid packages for all 
Phases. 
17.5.6 
Upon request by City, CM@Risk must submit to City a cash flow projection for the Project 
based on the current updated/revised Detailed Project Schedule and the anticipated level of 
payments for CM@Risk during the design and construction phases. In addition, if requested 
by City and based on information provided by City, CM@Risk must prepare a cash flow 
projection for the entire Project based on historical records for similar types of projects 
to assist City in the financing process. 
17.5.7 
Construction Water. CM@Risk must estimate the quantity of water to be used and include 
the cost thereof in each Detailed Cost Estimate and GMP Proposal provided by City. 
17.6 
SUBCONTRACTOR AND MAJOR SUPPLIER SELECTIONS 
17.6.1 
There are two ways to select Subcontractors and major Suppliers prior to submission of a 
GMP Proposal: (1) qualifications-based selection; or (2) a combination of qualifications 
and price. Except as noted below, the selection of Subcontractors/Suppliers is the sole 
responsibility of CM@Risk. In any case, CM@Risk is solely responsible for the performance 
of the selected Subcontractors/Suppliers, and for compliance with the requirements of

General Conditions 
 
Revised: 7/20/22 
 
GC-72 of 75 
 
Title 34 of the Arizona Revised Statutes in the selection of a Subcontractors/Suppliers, 
to the extent applicable. CM@Risk must comply with its Subcontractor Selection Plan 
submitted with its Statement of Qualifications. 
17.6.2 
City may approve the selection of a Subcontractor(s) or Suppliers(s) based only on their 
qualifications when CM@Risk can demonstrate it is in the best interest of the Project. All 
Work that is performed, after such a qualifications-based selection, for a price that is 
negotiated by CM@Risk will be billed in accordance with the GMP for actual costs and may 
be subject to audit by City. 
17.6.2.1 
Qualifications based selection of a Subcontractor(s)/Supplier(s) should only occur prior to 
the submittal of the GMP Proposal. 
17.6.2.2 
If a Subcontractor/Supplier selection plan was submitted and agreed to by City, CM@Risk 
must apply the plan in the evaluation of the qualifications of a Subcontractor(s) or 
Supplier(s) and provide City with its review and recommendations. 
17.6.2.3 
CM@Risk must receive written City approval for each selected Subcontractor(s) and 
Supplier(s). 
17.6.2.4 
CM@Risk must negotiate costs for services/supplies from each Subcontractor/Supplier 
selected under this method. 
17.6.3 
All Work must be competitively bid unless a Subcontractor or Supplier was selected pursuant 
to Section 17.6.2 above. 
17.6.3.1 
CM@Risk must develop Subcontractor and Supplier interest, submit the names of a 
minimum of three qualified Subcontractors or Suppliers for each trade in the Project for 
approval by City and solicit bids for the various Work categories. If there are not three 
qualified Subcontractors/Suppliers available for a specific trade or there are extenuating 
circumstances warranting such, CM@Risk may request approval by City to submit less 
than three names. Without prior written notice to City, no change in the recommended 
Subcontractors/Supplies will be allowed. 
17.6.3.2 
If City objects to any nominated Subcontractor/Supplier or to any self-performed Work for 
good 
reason, CM@Risk must nominate a substitute Subcontractor/Supplier that is 
acceptable to City. 
17.6.3.3 
CM@Risk must distribute Drawings and Specifications, and when appropriate, conduct a 
Pre- Bid Conference with prospective Subcontractors and Suppliers. 
17.6.3.4 
If CM@Risk desires to self-perform certain portions of the Work, it must request to be one of 
the approved Subcontractor bidders for those specific bid packages. CM@Risk’s bid will 
be evaluated in accordance with the process identified below. If events warrant and City 
concurs that it is necessary in order to ensure compliance with the Project Schedule 
and/or the most recent Detailed Cost Estimate, CM@Risk may be authorized to self-
perform Work without bidding or rebidding the Work. When CM@Risk self-performs work 
without bidding, only the actual costs associated with performing the Work in accordance 
with the approved GMP will be billed and may be subject to audit by City. 
17.6.3.5 
CM@Risk must receive, open, record and evaluate the bids; provided, however, that if 
CM@Risk or one of its affiliates is bidding to self-perform the Work that is the subject of the 
bid, then the bids must be received, opened, recorded and evaluated by Project Manager

General Conditions 
 
Revised: 7/20/22 
 
GC-73 of 75 
 
instead of CM@Risk. Bids for each category of Work must be opened and recorded at a 
pre-determined time. The apparent low bidders must be interviewed to determine the 
responsiveness of their proposals. In evaluating the responsiveness of bid proposals 
CM@Risk, in addition to bid price, may consider the following factors: past performance 
on similar projects, qualifications and 
experience of personnel assigned, quality 
management plan, approach or understanding of the 
Work to be performed, and 
performance 
schedule 
to 
complete 
the 
Work. 
The 
final 
evaluation 
of 
Subcontractor/Supplier bids must be done with Project Manager in attendance to observe 
and witness the process. CM@Risk must resolve any Subcontractor/Supplier bid withdrawal, 
protest or disqualification in connection with the award at no increase in the Cost of Work. 
17.6.4 
CM@Risk will be required to prepare two different reports on the subcontracting process. 
17.6.4.1 
Within fifteen days after each major Subcontractor/Supplier bid opening process; 
CM@Risk must prepare a report for City’s review and approval identifying the 
recommended Subcontractors/Supplier for each category of Work. The report must detail: 
(a) the name of the recommended Subcontractor/Supplier and the amount of the 
Subcontractor/Supplier bid for each sub-agreement; (b) the sum of all recommended 
Subcontractor/Supplier bids received; (c) and trade work and its cost that CM@Risk intends 
to self-perform, if any. 
17.6.4.2 
Upon completion of the Subcontractor/Supplier bidding process, CM@Risk must submit 
a summary report to City of the entire Subcontractor/Supplier selection process. The report 
must indicate, by bid process, all Subcontractors/Suppliers contacted to determine 
interest, the Subcontractors/Suppliers solicited, the bids received and costs negotiated, 
and the recommended Subcontractors/Suppliers for each category of Work. 
17.6.5 
The approved Subcontractors/Suppliers will provide a Schedule of Values with their bid 
proposals, which will be used to create the overall Project Schedule of Values. 
17.6.6 
If after receipt of sub-bids or after award to Subcontractors and Suppliers, City objects to 
any nominated Subcontractor/Supplier or to any self-performed Work without any 
reasonable basis, CM@Risk must nominate a substitute Subcontractor or Supplier, 
preferably if such option is still available, from those who submitted Subcontractor bids 
for the Work affected.  Once such substitute Subcontractors and Suppliers are consented 
to by City, CM@Risk’s proposed GMP for the Work or portion thereof must be 
correspondingly adjusted to reflect any higher or lower costs form any such substitution. 
17.7 
GMP PROPOSAL 
17.7.1 
When a GMP Proposal is submitted for a phase of the Work, the GMP will have a Detailed Cost 
Estimate of the Costs of the Work (as set forth in Section 15.2) in each phase of the Work 
that is being proposed plus the current estimate for all other Work. City will not approve 
the GMP for the phase of work without a total estimate for the complete Project. City may 
request a GMP Proposal for all or any portion of the Project and at any time during pre-
construction. Any GMP Proposals submitted by CM@Risk must be based on and consistent 
with Baseline Cost Model and the current update/revised Detailed Cost Estimate at the 
time of the request and include any clarifications or assumptions upon which the GMP 
Proposal(s) are based. 
17.7.2 
A GMP Proposal for the entire Project will be the sum of the Cost of the Work, CM@Risk Fee, 
and General Conditions Cost. CM@Risk guarantees to complete the Project at or less than

General Conditions 
 
Revised: 7/20/22 
 
GC-74 of 75 
 
the final GMP Proposal amount plus approved Change Orders. CM@Risk will be responsible 
for any costs for expenses that would cause the Cost of the Work actually incurred, 
including the Construction Fee and General Conditions Costs, to exceed the GMP. 
17.7.3 
CM@Risk must prepare its GMP Proposal in accordance with City’s request for GMP Proposal 
requirements based on the most current completed Drawings and Specifications at that 
time, which unless otherwise directed by City in writing, will be at 100% Construction 
Drawings. CM@Risk must mark the face of each document of each set upon which its GMP 
Proposal is based. 
These documents must be identified as the GMP Plans and 
Specifications. CM@Risk must send one set of those documents to the Project Manager, 
keep one set and return the third set to the Design Professional. 
17.7.4 
An updated/revised Detailed Project Schedule, Equipment Plan, and Schedule of Values 
must be included in any GMP Proposal(s), all of which must reflect the GMP Plans and 
Specifications the Detailed Project Schedule must be shown in relationship to the Project 
Schedule and identify any variance to the Baseline Project Schedule. Any such Detailed 
Project Schedule updates/revisions must continue to comply with the requirements of 
Section 17.3.1 through 17.3.5. 
17.7.5 
GMP Proposals(s) Review and Approval 
17.7.5.1 
CM@Risk must meet with the Project Team to review the GMP Proposal(s) and the written 
statement of its basis. In the event the Project Team discovers inconsistencies or 
inaccuracies 
in the information presented, CM@Risk must make adjustments as 
necessary to the GMP Proposal. 
17.7.5.2 
If during the review and negotiation of GMP Proposals design changes are required, City 
may authorize and cause the Design Professional to revise the GMP Plans and Specifications 
to the extent necessary to reflect the agreed-upon assumptions and clarifications contained 
in the final approved GMP Proposal. Such revised GMP Plans and Specification will be 
furnished to CM@Risk. CM@Risk must promptly notify the Project Team in writing if any 
such revised 
GMP Plans and Specifications are inconsistent with the agreed upon 
assumptions and clarifications. 
17.7.6 
All portions of or items comprising the GMP Proposal are subject to audit by City, as 
deemed appropriate by City, including, without limitation, any based upon unit prices or 
Work to be self- performed by CM@Risk, or its affiliates. 
17.8 
PAYMENT PROCEDURE FOR PRE-CONSTRUCTION SERVICES 
17.8.1 
Requests for monthly payments by CM@Risk for Pre-Construction Services must be 
submitted monthly and must be accompanied by a progress report, detailed invoices 
and receipts, if applicable. Any requests for payment must include, as a minimum, a 
narrative description of the tasks accomplished during the billing period, a listing of any 
Deliverables submitted, and copies of any Subconsultants’ requests for payment, plus 
similar narrative and listings of Deliverables associated with their Work. Payment for 
services negotiated as a lump sum will be made in accordance with the percentage of work 
completed during the preceding month. 
17.8.2 
In no event will City pay more than seventy-five (75%) of the Agreement Price until 
acceptance of ALL Pre-Construction Services and award of the final approved Construction 
Services Agreement for the entire Project by City Council. If CM@Risk does not prepare a

General Conditions 
 
Revised: 7/20/22 
 
GC-75 of 75 
 
GMP Proposal that is acceptable to City, or the GMP Proposal exceeds the City’s 
Construction Budget, then CM@Risk understands and acknowledges that it will forfeit any 
right to receive the 25% of the Agreement Price being retained by City. 
17.8.3 
CM@Risk agrees that no charges or claims for costs or damages of any type will be made by 
it for any delays or hindrances beyond the reasonable control of City during the progress of 
any portion of Pre-Construction Services specified in this Agreement. Such delays or 
hindrances, if 
any, will be solely compensated for by an extension of time for such 
reasonable period and may be mutually agreed between the parties. It is understood 
and agreed, however, that permitting CM@Risk to proceed to complete any such Services, 
in whole or in part after the date to which the time of completion may have been extended, 
will in no way act as a waiver on the part of City of any of their respective legal rights herein. 
17.8.4 
No compensation to CM@Risk will be allowed contrary to Article I, Chapter I, Title 34 of the 
Arizona Revised Statutes. 
17.8.5 
If any service(s) executed by CM@Risk is abandoned or suspended in whole or in part, for 
a period of more than 180 days through no fault of CM@Risk, CM@Risk is to be paid for 
the services performed prior to the abandonment or suspension. 
17.9 
SURVIVAL OF THE DESIGN SERVICES AGREEMENT, DUTIES, OBLIGATIONS AND 
WARRANTIES 
If the GMP Proposal is accepted by City and a Construction Agreement is entered into 
between City and CM@Risk, the duties, obligations and warranties of CM@Risk under the 
Pre- Construction Services Agreement survive and are incorporated into the resulting 
Construction Agreement.

App’d 7/20/2022 
APP-1 of 33 
 
General Conditions Appendices 
 
 
 
SECTION 15 – APPENDICES 
 
The following Appendices attached hereto are referenced in the General Conditions and 
are incorporated herein. 
 
 
Appendix 1 – Policy Statement for Calculating Delays and Damages 
Appendix 2 – Cost Reduction Incentive Proposals for Design Bid Build Agreements 
Appendix 3 – Contractor’s Affidavit Regarding Settlement of Claims 
Appendix 4 – Forms of Performance Bond 
Appendix 5 – Forms of Payment Bond 
Appendix 6 – Dispute Resolution 
Appendix 7 – Certificate of Completion 
Appendix 8 – Construction Sign Detail 
Appendix 9 – Cost of the Work (Applicable solely to Construction Manager at Risk and 
Job Order Contracting) 
Appendix 10 Landscape Establishment Period

App’d 7/20/2022 
APP-2 of 33 
General Conditions  
Appendix 1 
 
 
 
CALCULATING DELAYS AND DAMAGES 
 
 
The purpose of this policy statement is to establish guidelines and procedures for negotiation 
between the Contractor and City of Chandler relating to compensation for delays pursuant to 
Arizona Revised Statutes (A.R.S.) 34-221(F). This policy statement contains notice requirements in 
addition to those set forth in the Agreement Documents, and will be the Agreement Provision 
contemplated by that statute. 
 
NOTE: As used herein, the term “Engineer” will refer to the City of Chandler City Engineer or 
his/her designated representative. Nothing in this Policy Statement will be construed to void any 
provision in the Agreement which requires timely notice of delays or provides for arbitration or 
any other procedure for settlement or provides for liquidated damages. 
 
I. 
TYPES OF DELAYS: 
 
For the purposes of this document, there are essentially four types of delays encountered by 
City of Chandler Construction Contractors; excusable/compensable, excusable/non-
compensable, non- excusable, and concurrent. Only delays that extend Agreement 
Completion Time set forth in the Agreement Document will be considered for issues 
relating to Agreement extensions or additional compensation. All other delays are 
considered to be activity delays and do not entitle the Contractor to either time 
extensions or additional compensation. Agreement Completion Time will be defined as the 
date set forth in Maricopa Association of Governments (MAG) Uniform Standard Specification 
Section 101 and as may be modified by the Agreement Documents. 
 
A. 
Excusable/Compensable: 
 
These are delays caused solely by the City’s actions or inactions, are unreasonable 
under the circumstances, and which were not within the contemplation of the 
parties to the Agreement at or prior to the time of execution of the 
Agreement. Since the Contractor presumably has no control over the events 
causing the delay, he may be entitled to both Agreement time extensions and 
additional compensation for delay damages. Further, he/she may be entitled to 
additional compensation from the impact of that delay on other work. Examples of 
excusable/compensable (E/C) delays include: 
failure to properly locate 
an 
underground City-owned utility within 2 feet of the actual location; failure to 
relocate City-owned utilities far enough in advance of construction in an area 
where the Contractor is scheduled to work that it delays start or completion of 
the Contractor’s regularly scheduled work; failure to provide City-furnished 
equipment or materials in a timely manner if required by the Agreement; failure 
to acquire necessary Right-of-Way or Public Utility Easements prior to the Contractor 
beginning Work in the area; failure to timely return Shop Drawings or other 
Agreement Submittals in accordance with the Agreement; unreasonable delay by 
the City in making decisions which affect critical activities; surveying errors when the 
City is contractually responsible for providing Project Surveying. This list is not meant 
to be all inclusive, but is intended merely as examples of the type of City action or 
inaction which can result in a Contractor’s claim for additional time and

App’d 7/20/2022 
APP-3 of 33 
General Conditions  
Appendix 1 
 
 
compensation. 
 
 
B. 
Excusable/Non-compensable: 
 
These are delays over which neither the City nor the Contractor had control. Since 
both parties to the Agreement have been potentially damaged by the delay, but 
neither have caused it, only Time Extensions are warranted. Examples of excusable, 
non-compensable (E/N) delays include: unusually severe weather; fire; acts of God; 
failure of non-City owned utilities (SRP, CenturyLink, Cable TV, Southern Pacific 
Railroad, and Southwest Gas, etc.) to properly or timely locate accurately; failure of 
non-City owned utilities to relocate in advance of construction; the voluntary or 
involuntary filing for Bankruptcy protection by a Supplier or Subcontractor which 
causes the Supplier/Subcontractor to fail to meet a contractual deadline provided 
the Contractor can provide documentation that he/she executed the required 
Purchase Orders/Subcontract Agreements and received delivery schedules which, 
if met, would have eliminated the delay; delays as a result of an incomplete 
shutdown of a City or non-City owned utility main (the City does not guarantee a 
complete shutdown). This list also is not necessarily all inclusive but merely 
indicative of type and class of E/N delays. 
 
C. 
Non-excusable/Non-compensable: 
 
These are delays caused by the actions or inactions of Contractor or an officer, 
employee, agent, Subcontractor, Supplier or any other party for whom the 
Contractor is responsible. Since the Contractor has assumed responsibility for the 
risks associated with the events that caused the delay, he/she are not entitled to 
either time extensions or monetary delay damages. All non-excusable delays are 
also non-compensable. Examples of non- excusable, non-compensable (N/N) 
delays include: failure to perform by the Contractor, its Subcontractors and/or 
Suppliers (except as noted in section I.B above); failure to provide adequate 
labor, 
materials, 
and/or 
equipment 
on 
the 
Project; 
failure 
to 
perform 
contractually-required coordination with utilities, agencies and other Contractors; 
failure to notify the Engineer, in writing, of delay impacts within two working days, 
as required by MAG 104.2.3, or the next work day, as required by MAG 109.8.2; 
failure to timely submit Shop Drawings; failure to pothole or otherwise visually locate 
utilities sufficiently ahead of the Work to allow the Engineer to direct corrective 
action when necessary; delays due to retesting of previously failed work, re-
inspection, and/or restaking resulting from faulty workmanship, poor quality 
control, or lack of compliance with Agreement Specifications. Again, this list is not 
necessarily all inclusive. 
 
D. 
Concurrent: 
 
When two or more delays occur simultaneously or overlap, each delay is 
analyzed separately to determine its impact on the overall project completion date 
based on when that delay started. Once again, only those delays which actually 
extend the Agreement completion 
time 
are 
considered 
as 
delays. 
The 
concurrent delay is considered an additional delay only to the extent it prolongs

App’d 7/20/2022 
APP-4 of 33 
General Conditions  
Appendix 1 
 
 
the delay to the Agreement Completion Time beyond the date that the one it is 
concurrent with had already delayed that date. For example, if two delays are 
concurrent, and one is five days long and the second is seven days long, the second 
concurrent delay will only extend the Agreement Completion Time by two days. The 
same method of analysis is used when there are multiple concurrent delays. Only 
those extending the Project Completion Date are considered to be delays for the 
purposes of this policy. The portion of each concurrent delay that delays the 
completion of the work is classified in the same manner as described previously for 
individual delays and being either E/C, E/N or N/N. 
 
An example of a concurrent delay is where the City delays furnishing material, 
but the Contractor could not have installed it anyway due to unusually severe 
weather. The effect of the first delaying activity will extend for the full duration 
and will be considered controlling on the Contractor’s schedule. A subsequent, 
concurrent delay will thereafter only be considered to effect the project completion 
(if at all) once the first delaying activity has ceased to impact the project completion. 
In this case, if the unusually severe weather continued and delayed the work after 
the material was delivered, the first portion of the delay would be classified E/C 
(delay for material) and the second as E/N (delay due to unusually severe weather). 
Using the procedure set forth above, the entire concurrent portion would be 
considered E/C as shown in the chart which follows. 
 
Example of a Concurrent Delay: 
 
 
 
 
E/C Delay 
E/N Delay 
 
 
 
City Related Material Delay 
 
 
 
Rain Delay 
 
 
 
 
 
II. 
ANALYZING THE DELAY: 
 
The Contractor must provide all documents required or requested by the Engineer to analyze the 
delay(s). It is important to understand that, prior to the delay analysis, delays and their impacts are 
alleged issues. The information the Contractor provides will be compared with the Inspector’s Daily 
Log, Schedules and other available Project information and together they will support or refute that 
delays occurred and, if so, how they impact other work and the overall project completion. The 
Contractor’s delay in providing these documents will be considered prima facie evidence that either 
the delay did not occur or it did not impact the Project Completion Date and any claim for time 
extension or damages will be denied.

App’d 7/20/2022 
APP-5 of 33 
General Conditions  
Appendix 1 
 
 
The Engineer will accept delay analyses in CPM format, as these may demonstrate to his/her 
satisfaction whether or not Project Completion has been impacted by a specific event. If the 
Contractor chooses not to use CPM scheduling procedures, then the burden will be on the 
Contractor to prove to the Engineer’s satisfaction that the Project Completion has been 
impacted. The procedures below assume that the Contractor is using CPM scheduling methods. 
As a minimum the Contractor must provide the following materials to the Engineer: 
 
A. 
As-Planned Schedule. The initial construction schedule, required by the Agreement 
Documents, will be considered the baseline schedule. It is to the Contractor’s 
advantage that the As-Planned (baseline) Schedule be as detailed as possible in 
order for delays, as they occur, to be incorporated into the schedule in 
representative locations. It is also to the Contractor’s advantage to use a computer 
software program to generate the schedule since updated schedules are required 
monthly by the Agreement Documents and since updated schedules are 
required to support delays and requests for additional compensation for delays. 
The As-Planned (baseline) Schedule must be presented in network format which 
clearly shows the interrelationships of the activities. The Contractor must also 
provide a printout of the activities showing early start, early finish, late start, late 
finish, duration and float. The activity list printout must also indicate predecessor 
and successor activities. 
 
B. 
As-Built Schedules. The as planned (baseline) schedule must be updated with 
complete progress-to-date information (actualized) up to the date of the start of the 
alleged delay. Each updated schedule will serve as the as-built schedule for analyzing 
the alleged delay and provide a new baseline as-planned schedule for the next delay. 
This process must be repeated for each alleged delay as it occurs. In updating the 
baseline schedule, the alleged delay must be treated as an activity and inserted into 
the schedule as a predecessor to the impacted activity (ies). When an activity that 
has already started is impacted, it is preferable to divide this activity into two 
parts and show the impact affecting the second part. For schedules which 
incorporate a time line (or data date), the delay activity must be inserted at the time 
it actually occurred. Some software scheduling programs have a PAUSE-RESUME 
feature that can be used to facilitate the requirements. The updated schedule must 
also be accompanied by a listing of activities as with the baseline schedule. This 
activities list must contain the alleged delay as an activity showing the duration and 
the activities which are predecessors and successors to it. When computer 
generated schedules are used, the Contractor must provide, in electronic media 
format, the complete data files for the updated schedule that included the delay 
activity, preferably either in Suretrak or in Microsoft Project. Each electronic media 
must contain a label identifying the Project name, Contractor’s name, program 
name and version number, data date and project finish date. 
 
C. 
Other Documents: In order to determine the amount of the alleged delay and if 
it is compensable, the Contractor must provide all backup documentation relevant to 
the issue and as required by the Engineer. This documentation must include copies 
of such items as: purchase orders; delivery schedules; correspondence; memoranda 
of telephone calls; force account daily worksheets (initialed by the Inspector); 
payroll data; estimating (bid) worksheets; and any other materials which may be

App’d 7/20/2022 
APP-6 of 33 
General Conditions  
Appendix 1 
 
 
requested by the Engineer. 
 
D. 
Procedure: Only after receipt of sufficient documentation will the Engineer analyze 
each alleged delay and determine if it is supported or refuted. If supported, the 
Engineer will determine if it is excusable or non-excusable, compensable or non-
compensable. If the Engineer determines that the delay did not affect the Project 
Completion, the as-planned schedule, which has been updated to the date of the 
alleged delay, must be revised to indicate this. If the Engineer determines the delay 
did occur but was N/N, then no time extension will be granted. It is imperative that 
an actualized schedule be submitted as soon as the occurrence of the alleged delay 
is known. In no event will the Contractor submit an actualized updated schedule 
later than 60 days after the occurrence of the alleged delay becomes known. 
 
If the Engineer determines the delay did occur and was excusable but, due to a 
reason listed in section I.B. is non-compensable, he/she will determine the length 
of the E/N delay and prepare a Change Order to add that time to the Agreement. 
The Engineer’s decision will be final. 
 
If the Engineer determines the delay was excusable and compensable, he/she will 
determine the length of the E/C delay and proceed to review the Contractor’s 
damage calculations in accordance with Section III. The Engineer will check the 
Contractor’s calculations, review the backup documentation provided, and prepare a 
Change Order to cover both the additional compensation and the time extension. 
The Engineer’s decision on both the time extension and additional compensation for 
the delay will be final. 
 
If the issue involves a concurrent delay, the Engineer will analyze available data 
to determine the portions which are E/C, E/N, and/or N/N as described above. The 
Engineer will proceed to determine the length of E/C delay and verify the Contractor’s 
delay damage calculations, if any are provided. Upon completion of this review, the 
Engineer will prepare a Change Order for the Contractor’s review and signature. 
The Engineer’s decision regarding excusable delay and additional compensation for 
the delay is final. 
 
The amount of time the Engineer will require to analyze the alleged delay(s) will 
depend upon the Engineer’s workload, the complexity of the delay analysis, 
availability of supporting data, extent of cooperation by the Contractor, and other 
factors beyond the Engineer’s control. It is entirely possible other delay(s) may 
occur while the Engineer is analyzing particular claim for delay(s). The Engineer’s 
failure to respond to the Contractor in a set period of time will not be used as the 
basis for a further delay claim or as justification for extending and existing delay 
claim. The time required for delay analysis by the Engineer will not be counted 
against the time allotted for processing Final Payment as required by (MAG Section 
109.7(B)) or the release of retention and Final Payment as prescribed by A.R.S. 
Arizona Revised Statutes §34-221. 
 
III. 
CALCULATING MONETARY DELAY DAMAGES: 
 
Additional compensation for delay, when authorized by the Engineer, will be calculated in accordance

App’d 7/20/2022 
APP-7 of 33 
General Conditions  
Appendix 1 
 
 
with MAG Section 109.5 ACTUAL COST WORK with the following exceptions: 
 
A. 
No additional compensation or other monetary damages will be awarded or paid for 
any loss of anticipated profits by the Contractor, Subcontractors or Suppliers. 
 
B. 
No additional compensation or other monetary damages will be awarded for home 
office overhead or non-project general conditions of the Contractor, Subcontractors 
or Suppliers. 
 
C. 
Equipment: 
 
1. 
Contractor-owned equipment rate calculations must be computed in 
accordance with Section 109.04(D)(3), Arizona Department of Transportation 
“Standard Specifications for Road and Bridge Construction,” 2008 or latest 
edition and as modified herein. Year and regional adjustment factors must 
be based on the most recent publications of the Rental Rate Blue Book for 
Construction 
Equipment, published 
by 
the 
Equipment 
Guide-Book 
Company, San Jose, CA, same as provided by ADOT and in print as of the 
date of alleged delay. In no event will the compensation for Contractor-
owned equipment exceed the purchase price, including tax, paid by the 
Contractor for the equipment. Compensation will not be allowed for small 
tools or equipment that show a daily equipment rental rate of less than $5.00 
per day or for unlisted equipment that has a value of less than for 
hundred dollars ($400.00). 
2. 
For leased and rented equipment or equipment not otherwise listed in the 
Blue Book, rental contracts, or other supporting data will be used to establish 
the hourly rate. No hourly operating expense will be allowed for delay on 
standby equipment. In no case will equipment be considered for rental which 
exceeds the hourly rate for the first eight hours and the daily rate 
divided by eight for all additional hours as compared with similar 
equipment listed in the Blue Book. The hourly standby rate must be 
computed as the lesser of: 
 
a. 
Dividing the monthly invoice or rental value by 176 hours 
per month when the equipment is utilized by the Contractor 
for more than three weeks; 
 
b. 
Dividing the monthly invoice or rental value by 40 hours per 
week when the equipment is utilized by the Contractor for 
more than three days. 
 
In no event will compensation be paid for delay at more than 
8 hours per day or 40 hours per week. 
 
3. 
Except for vehicles used by supervisory personnel, all equipment will be paid 
at the “standby” rate during the delay period. 
 
4. 
Equipment brought solely to mitigate the delay (such as pumps, light plants, 
etc.) may be paid in accordance with ADOT section 109.04(D) (3).

App’d 7/20/2022 
APP-8 of 33 
General Conditions  
Appendix 1 
 
 
 
5. 
The Blue Book regional adjustment will apply in determining rental rates. 
 
D. 
Material: 
 
Allowable material charges may include, in addition to material incorporated in the 
work material used to mitigate the delay such as barricades, plates, shoring, cold 
mix, etc. Except in emergencies the Contractor will not employ such material 
without the prior written approval of the Engineer. 
 
E. 
Labor: 
 
1. 
Except for Supervisory Personnel (Superintendent, Project Engineer, and 
Foremen), labor wages will not be paid after the first one-half day of 
claimed delay or impact. It is expected the Contractor will reassign or 
layoff unneeded employees. 
 
2. 
For Foreman wages to be included, that Foreman must have been 
actively employed on the project prior to the commencement of the delay 
and be directly responsible for the activity being delayed. 
 
3. 
Labor burden must be actual amounts incurred but must not exceed the 
ADOT approved rate. 
 
F. 
All costs (equipment, material, and labor) must be substantiated by the City of 
Chandler’s Daily Work Reports. 
 
IV. 
DOCUMENT REQUIRED FOR CLAIM ANALYSIS: 
 
For purposes of reviewing the Contractor’s request for additional compensation, it will be required 
that the Contractor submit the following listed information. Information requested must be prepared 
on forms which are substantially similar to the City of Chandler’s Daily Work Report form, a copy of 
which is attached as an exhibit. 
 
A. 
Labor: 
 
For each employee, laborer, and foreman, for which compensation is requested: 
Name, classification, dates of work performed, daily hours worked, total hours worked, 
labor rates, labor burden rates, overtime or premium time charges. Further, the 
Contractor must make available for inspection and copying to the Engineer the 
following listed documentation. 
 
1. 
Certified payroll reports for the period of work claimed. 
2. 
Accounting of Fringe Benefits – certified by a CPA. 
3. 
Contractor’s and Subcontractor’s daily field reports and daily diaries. 
 
B. 
Materials: 
 
For all materials for which compensation is requested, if any, total quantities of 
materials, prices, extensions and transportation costs must be provided on a daily

App’d 7/20/2022 
APP-9 of 33 
General Conditions  
Appendix 1 
 
 
basis. Further, the Contractor must make available for inspection and copying to the 
Engineer the following listed documentation. 
 
1. 
Invoices for all materials incorporated. 
2. 
Weigh tickets. 
3. 
Purchase orders. 
4. 
Delivery schedules. 
5. 
Quotes or proposals from manufacturers or supplier. 
6. 
Freight bills, Bills of Lading, or other documentation to show transportation 
costs. 
7. 
Restocking charges-invoices from vendor. 
 
C. 
Equipment: 
 
For all equipment, the Contractor must provide the Engineer with the designation, 
dates and hours of usage, dates and hours of standby, if any, daily hours, total hours, 
rental rates and extension for each unit of equipment and machinery. Rental 
rates will be as established in Section III. Further, the Contractor must make 
available for inspection and copying to the Engineer the following listed 
documentation. 
 
1. 
Owned: 
a. 
Purchase contracts(s). 
b. 
Depreciation schedule(s). 
c. 
Invoices for fuel, lube, repairs and other operating costs. 
 
2. 
Leased: 
a. 
Lease agreement with hourly rate, overtime rate, double shift rate, etc. 
b. 
Invoices or other documentation showing hours worked on a daily 
basis. 
 
D. 
Subcontractors/Owner-Operators: 
 
In the event the Contractor submits a claim which includes requests for 
compensation for Subcontractors of Owner-Operators, the same information 
requested of the Contractor must be provided by the Subcontractor/Owner-
Operator. Further, the Contractor must make available for inspection and copying 
to the Engineer the following listed documentation. 
 
1. 
Bid/Estimate work sheets and/or spreadsheets. 
2. 
Subcontract Agreements or Agreements with Owner-Operator. 
3. 
All invoices and billing statements received from the Subcontractor/Owner- 
Operator which relates to the amount requested. 
 
E. 
Miscellaneous: 
 
Further, the Contractor must make available for inspection and copying to the 
Engineer the following listed documentation. 
 
1. 
Evidence of payment for bonds and insurance premiums (MAG 109.5.6).

App’d 7/20/2022 
APP-10 of 33 
General Conditions  
Appendix 1 
 
 
2. 
Taxes – unless the Contractor can show otherwise, taxes are reimbursable at 
65% of the total cost (less bonds and insurance). 
 
V. 
TIME LIMIT ON SUBMISSIONS OF CLAIM FOR DELAY OR IMPACT DAMAGES: 
 
No claims for delay or impact damages will be considered or allowed more than 45 days after the 
event or occurrence which the Contractor claims gives rise to the delay or impact. In no event will 
a claim for delay or impact damages be considered after submission by the Contractor of the Final 
Payment Request.

App’d 7/20/2022 
APP-11 of 33 
General Conditions  
Appendix 2 
 
 
 
 
COST REDUCTION INCENTIVE PROPOSALS 
FOR DESIGN BID BUILD AGREEMENTS 
 
 
The Contractor may submit to the Engineer proposals for modifying the Plans, Specifications, or 
other requirements of the Agreement for the sole purpose of reducing the total cost of Project 
construction. The proposals must not impair in any manner the essential functions or characteristics 
of the project; including but not limited to service life, economy of operations, ease of maintenance, 
desired appearance, compatibility with existing or planned equipment, standardization of 
systems, or  design and safety standards. 
 
It must not be inferred from this Policy that the Engineer is required to consider any proposal 
submitted. 
 
Submissions that propose changes in the basic design of a bridge, propose changes in pipe line 
size, materials, bedding conditions, pipe specifications; or that propose any change in pavement 
design will not be considered. 
 
Proposals submitted pursuant to this Policy will be identified as Cost Reduction Incentive Proposals. 
They must be submitted in writing and, at a minimum, contain the following. 
 
1. 
Complete the attached or similar cost reduction incentive proposal form. 
 
2. 
A description of both the existing Agreement Requirements for performing the work 
and the proposed changes. 
 
3. 
All Engineering Drawings and computations necessary for the thorough and 
expeditious evaluation. 
 
4. 
An itemization of the existing Agreement Requirements that must be changed if the 
Proposal is adopted and a recommendation as to the manner in which the change 
should be made. 
 
5. 
A detailed estimate of the cost of performing the Work under the existing 
Agreement and under the proposed changes, including the cost of developing 
and implementing the changes. 
 
6. 
The Agreement items affected by the proposed changes and any variations in 
quantities resulting from the changes. 
 
7. 
An objective estimate of any effects the proposal will have on collateral cost to the 
City, costs of related items, and cost of maintenance and operation. 
 
8. 
A statement as to the effect that the Proposal will have on the time for the 
completion of the Project. 
 
9. 
A statement as to the time by which a Change Order adopting the Proposal must 
be executed or when the Engineer must have given verbal approval.

App’d 7/20/2022 
APP-12 of 33 
General Conditions  
Appendix 2 
 
 
 
Proposals will be processed expeditiously; however, the City will not be liable for any delay in acting 
upon any Proposal nor for any failure to accept any Proposal pursuant to this Special Provision. 
 
The Engineer will be the sole judge of the acceptability of a Proposal and of the estimated net 
savings in construction costs from the adoption of all or any part of the Proposal. The Contractor 
will be notified in writing by the Engineer as to whether his/her Proposal has been accepted. The 
decision by the Engineer is final. 
 
When the City deems such action to be appropriate, it reserves the right to require the Contractor to 
share equally in the cost to the City of investigating, evaluating, and processing the proposal as a 
condition for the consideration of such Proposal. Such cost must be shared whether the Proposal is 
accepted or rejected. When such a condition is imposed, the City will estimate these costs and the 
Contractor must indicate his acceptance thereof in writing. Such acceptance will authorize the City 
to deduct the Contractor’s share of the costs from any monies due or that may become due to the 
Contractor under the Agreement. 
 
If the Contractor’s Proposal is accepted in whole or in part, the necessary Agreement 
Modifications and Agreement Price Adjustments will be affected by the execution of a Change Order 
which will specifically state that it is executed pursuant to this Special Provision. 
 
The Contractor must continue to perform the work in accordance with the requirements of the 
Agreement until a Change Order incorporating the Proposal has been executed or until he/she 
has been given verbal approval by the Engineer that his/her Proposal has been accepted. If the 
Change Order has not been executed or he/she has not been given verbal approval on or before the 
date specified on the attached cost reduction incentive proposal form or on or before such other date 
as the Contractor may have subsequently specified in writing, the Proposal may be deemed to be 
rejected. 
 
The executed Change Order will incorporate the changes in the Plans, Specifications, or other 
requirements of the Agreement which are necessary to permit the Proposal, or such part of it which 
has been accepted, to be put into effect, and will include any condition – upon which the City’s 
approval thereof is based, if such approval is conditional. The executed Change Order may also 
extend the time for the completion of the Agreement if such an extension has been deemed to be 
warranted by the Engineer as a result of his evaluation of the Proposal. 
 
The executed Change Order will also establish the estimated net savings in the cost of performing 
the Work attributable to the Proposal effectuated by the Change Order. In determining the net 
savings, the right is reserved to the Engineer to disregard the Agreement bid prices if, in his/her 
judgment, such prices do not represent a fair measure of the value of the Work to be performed or 
to be deleted. The net savings will be established by determining the Contractor’s cost of performing 
the Work, taking into account his/her cost of developing the Proposal and implementing the 
change, and reducing  this amount by any ascertainable collateral costs to the City. The executed 
Change Order may provide that the Contractor be paid 50 percent of the estimated net savings 
amount. 
 
The executed Change Order may also provide for the adjustment in Agreement prices. Agreement 
prices may be adjusted by subtracting the City’s share of the accrued net savings.

App’d 7/20/2022 
APP-13 of 33 
General Conditions  
Appendix 2 
 
 
 
The amount specified to be paid to the Contractor in the executed Change Order which effectuates a 
Cost Reduction Proposal will constitute full compensation to the Contractor for the Cost Reduction 
Proposal and the performance of the work thereof pursuant to the said Change Order. 
 
Upon acceptance of a Cost Reduction Incentive Proposal, any restrictions imposed by the 
Contractor on its use or on disclosure of the information will become void, and the City thereafter 
will have the right to use all or any part of the Proposal without obligation or compensation of any 
kind to the Contractor.

App’d 7/20/2022 
APP-14 of 33 
General Conditions  
Appendix 2 
 
 
 
 
 
COST REDUCTION INCENTIVE PROPOSAL FORM 
 
 
 
TO: 
CIP City Engineer 
 
 
FROM: 
 
 
 
PROJECT NAME: 
[TITLE] 
 
 CITY PROJECT NUMBER: 
[####] 
 
 
DATE: 
 
 
Summary of Change (Brief description of proposed change including advantages and disadvantages): 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
ESTIMATED COST SUMMARY (Attached detailed estimate): 
 
A. 
Original Cost: 
$   
 
B. 
Proposed Cost: 
$   
 
C. 
Construction Savings (A-B): 
$   
 
D. 
Gross Savings (Included OH 
%, Bond 
%) 
$   
 
E. 
Contractor Implementing 
$_  
 
F. 
City Implementing Cost: 
$_  
 
Reduction in Agreement Price (C+D-E-F) x 50%: 
$   
 
 
 
 
 
Date by which a Change Order must be issued so as to obtain maximum cost reduction:

App’d 7/20/2022 
APP-15 of 33 
General Conditions  
Appendix 3 
 
 
 
 
 
CITY OF CHANDLER, ARIZONA 
PUBLIC WORKS & UTILITIES DEPARTMENT 
 
CONTRACTOR'S AFFIDAVIT REGARDING SETTLEMENT OF CLAIMS 
 
 
________________________, Arizona 
Date ____________________________ 
 
Project Name:  [TITLE] 
City Project No.:  [####] 
To the City of Chandler, Arizona 
Gentlemen: 
This is to certify that all lawful claims for materials, rental of equipment and labor used in connection 
with the construction of the above project, whether by subcontractor or claimant in person, have been 
duly discharged. 
 
The undersigned, for the total compensation of $________________________, as set out in the final pay 
application, as full and complete payment under the terms of the Agreement, hereby waives and 
relinquishes any and all further claims or right of lien under, in connection with, or as a result of the 
above described project.  The undersigned further agrees to indemnify and save harmless the City of 
Chandler against any and all liens, claims or liens, suits, actions, damages, charges and expenses 
whatsoever, which said City may suffer arising out of the failure of the undersigned to pay for all labor 
performances and materials furnished for the performance of said installation. 
 
Signed and dated at ________________, this _________ day of _______________ 20_____. 
 
 
__________________________________ 
CONTRACTOR 
 
By _______________________________ 
STATE OF ARIZONA 
 
) 
) SS 
COUNTY OF MARICOPA 
) 
 
The foregoing instrument was subscribed and sworn to before me this __________ day of 
__________________ 20 _________. 
 
___________________________________ 
 
 
 
 
 
Notary Public 
 
___________________________________ 
 
 
 
 
 
My Commission Expires

App’d 7/20/2022 
APP-16 of 33 
General Conditions  
Appendix 4 
 
 
 
 
PERFORMANCE BOND 
 
ARIZONA STATUTORY PERFORMANCE BOND 
PURSUANT TO TITLES 28, 34, AND 41, ARIZONA REVISED STATUTES 
(Penalty of this bond must be 100% of the Agreement amount) 
 
KNOW ALL MEN BY THESE PRESENTS THAT:___________________________________________________ 
 
(hereinafter "Principal"), and __________________________________________________________ (hereinafter "Surety"), a 
corporation organized and existing under the laws of the State of ______________ with its principal office in the City 
of _____________________________, holding a certificate of authority to transact surety business in Arizona issued by 
the Director of Insurance pursuant to Title 20, Chapter 2, Article 1, as Surety, are held and firmly bound unto 
__________________________(hereinafter "Obligee") in the amount of __________________________________________ 
(Dollars) ($___________), for the payment whereof, Principal and Surety bind themselves, and their heirs, 
administrators, executors, successors and assigns, jointly and severally, firmly by these presents. 
 
WHEREAS, the Principal has entered into a certain written Agreement with the Obligee, dated  
 
the ____________ day of _______________________, 20___ for construction of [TITLE], [####] which Agreement is hereby 
referred to and made a part hereof as fully and to the same extent as if copies at length herein. 
 
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION IS SUCH, that if the Principal faithfully performs 
and fulfills all the undertakings, covenants, terms, and conditions of the Agreement during the original term of the 
Agreement and any extension of the Agreement, with or without notice of the Surety, and during the life of any 
guaranty required under the Agreement, and also performs and fulfills all the undertakings, covenants, terms, 
conditions, and agreements of all duly authorized modifications of the Agreement that may hereafter be made, 
notice of which modifications to the Surety being hereby waived, the above obligation is void.  Otherwise it 
remains in full force and effect. 
 
PROVIDED, HOWEVER that this bond is executed pursuant to the provisions of Title 34, Chapter 2, Article 2, 
Arizona Revised Statutes, and all liabilities on this bond will be determined in accordance with the provisions of 
Title 34, Chapter 2, Article 2, Arizona Revised Statutes, to the same extent as if it were copied at length in this 
Agreement. 
 
The prevailing party in a suit on this bond may recover as part of the judgment reasonable attorney fees 
that may be fixed by a judge of the court. 
 
Witness our hands this ________________ day of ____________________, 20__. 
____________________________________ 
PRINCIPAL          
SEAL 
___________________________________ 
             AGENT OF RECORD 
By _________________________________ 
____________________________________ 
SURETY  
 
SEAL 
___________________________________ 
               AGENT ADDRESS

App’d 7/20/2022 
APP-17 of 33 
General Conditions  
Appendix 5 
 
 
 
PAYMENT BOND 
 
 
ARIZONA STATUTORY PAYMENT BOND 
PURSUANT TO TITLES 28, 34, AND 41, OF THE ARIZONA REVISED STATUTES 
(Penalty of this Bond must be 100% of the Agreement amount) 
 
KNOW ALL MEN BY THESE PRESENTS THAT:________________________________________________  
 
(hereinafter "Principal"), as Principal, and _________________________________________(hereinafter "Surety"), a 
corporation organized and existing under the laws of the State of __________________   with its principal office in the 
City of __________________, holding a certificate of authority to transact surety business in Arizona issued by the 
Director of the Department of Insurance pursuant to Title 20, Chapter 2, Article 1, as Surety, are held and firmly 
bound 
unto 
________________________ 
 
(hereinafter 
"Obligee") 
in 
the 
amount 
of 
______________________________________________ (Dollars) ($___________), for the payment whereof, the Principal and 
Surety bind themselves, and their heirs, administrators, executors, successors and assigns, jointly and severally, 
firmly by these presents. 
 
WHEREAS, the Principal has entered into a certain written Agreement with the Obligee, dated the _________ day of 
_______________________, 20___ for construction of [TITLE], [####] which Agreement is hereby referred to and made 
a part hereof as fully and to the same extent as if copied at length herein. 
 
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION IS SUCH, that if the Principal promptly pays all 
moneys due to all persons supplying labor or materials to the Principal or the Principal's subcontractors in the 
prosecution of the work provided for in said Agreement, this obligation is void. Otherwise it remains in full force 
and effect. 
 
PROVIDED, HOWEVER that this bond is executed pursuant to the provisions of Title 34, Chapter 2, Article 2 
Arizona Revised Statutes, and all liabilities on this bond will be determined in accordance with the provisions, 
conditions and limitations of Title 34, Chapter 2, Article 2, Arizona Revised Statutes, to the same extent as if it were 
copied at length in this Agreement. 
 
The prevailing party in a suit on this bond may recover as part of the judgment reasonable attorney fees 
that may be fixed by a judge of the court. 
 
Witness our hands this ________________ day of ____________________, 20__. 
____________________________________ 
PRINCIPAL          
SEAL 
___________________________________ 
                 AGENT OF RECORD 
By _________________________________ 
____________________________________ 
SURETY  
 
SEAL 
___________________________________ 
                  AGENT ADDRESS

App’d 7/20/2022 
APP-18 of 33 
General Conditions  
Appendix 6 
 
 
 
 
DISPUTE RESOLUTION 
 
A. 
INFORMAL DISPUTE RESOLUTION 
 
The parties to the Agreement agree that time is of the essence in relation to 
performance of the Agreement and completion of the Project, therefore any and all 
disputes in relation to the Agreement will initially be referred to the Project 
Manager, 
the 
Design 
Professional Representative 
and/or 
the 
Contractor 
Representative as applicable to the dispute, for immediate resolution. If, after 
good faith efforts to reach a resolution, none is reached, any party to the dispute 
may submit the dispute to the Dispute Resolution Representative (“DRR”) process 
set forth below, which is intended to be an expedited process. 
 
B. 
DISPUTE RESOLUTION REPRESENTATIVE (“DRR”) PROCESS 
 
1. 
The Parties under the Agreement agree that all claims and disputes in relation 
to the Project which are not resolved in the ordinary course of the Project 
(“Claim” or “Claims”) will, as a prerequisite to any mediation, or litigation of 
the Claim, first be submitted for resolution between the designated 
Dispute Resolution Representatives of the Parties as set forth herein (the 
“DRR Process”). 
 
2. 
The DRR Process will be initiated through service of a DRR Notice as set 
forth below: 
 
a. 
For claims by the Contractor or the Design Professional, the DRR 
Process will be initiated by the party asserting the claim serving 
written notice on the City setting forth in detail: (i) the basis for the 
claim; (ii) the effect of the Claim upon the construction of, and/or 
Project Schedule for, the Project; 
(iii) the specific relief requested, the amount thereof, and how such 
was calculated; (iv) the parties involved in the Claim, and how 
they are involved; (v) the specific Agreement provisions in the 
Agreement Documents (including, if applicable, drawings and 
specifications) which apply; and (vi) efforts made to date to resolve 
the Claim. 
 
b. 
For claims by the City, the DRR process will be initiated by the 
City providing written notice to the other parties of the basis and 
amount of its claim, the parties involved in the Claim, and how they 
are involved, the provisions in the Agreement Documents that apply, 
and the relief requested. 
 
c. 
The DRR Notice will be hand-delivered and e-mailed to the other 
parties’ designated Dispute Resolution Representatives. 
 
3. 
The other parties will respond in writing to the DRR Notice (“DRR 
Response”) within ten (10) calendar days of receipt of the DRR Notice, setting 
forth those items set forth in the DRR Notice that they agree with, dispute, 
and/or have questions concerning. The DRR Response will be hand-delivered 
and e-mailed to the other parties’ Dispute Resolution Representatives.

App’d 7/20/2022 
APP-19 of 33 
General Conditions  
Appendix 6 
 
 
 
4. 
The designated Dispute Resolution Representatives for the Parties to the 
claim will then meet as soon as possible and in any event within twenty (20) 
calendar days of submission of the DRR Notice (regardless of whether a 
DRR Response has been submitted by all parties involved in the dispute), at 
a mutually agreed upon time and place, to attempt to resolve the Claim 
based upon the DRR Notice and DRR Response. 
 
5. 
At any time after the first meeting required above, either party may 
terminate the DRR Process by written notice to the other party. 
 
6. 
The parties may agree, in writing, to extend or modify the time limits or 
other provisions of the DRR process in relation to a specific pending Claim. 
 
7. 
Unless otherwise designated in a written notice to the other parties, the City 
and the representatives of the Contractor and of the Design Professional will 
act as the parties’ designated Dispute Resolution Representatives. 
 
8. 
If a resolution of the Claim is reached, that resolution must be set forth in 
writing and must be signed by the Parties’ designated Dispute Resolution 
Representative. If the resolution involves a change in any Agreement 
Documents, the Agreement Price, the Project Schedule, or any other change 
requiring a written Change Order or Amendment, the parties must execute 
an appropriate written Change Order or Amendment pursuant to the terms 
of the Agreement Documents. 
 
C. 
MEDIATION 
 
1. 
Unless extended by written agreement of the parties involved in the dispute, 
any Claim not resolved through the DRR process set forth above within 
five (5) calendar days after the meeting required under B (4) above, or after 
the DRR is terminated pursuant to B (5) above, whichever is earlier, will be 
submitted to mediation as a condition precedent to litigation by either party. 
 
2. 
The mediation will be commenced by written demand upon the other party 
for mediation. If the parties cannot agree upon a mediator within ten (10) 
calendar days of the written demand, either party may make a request to the 
Civil Presiding Judge of the Maricopa County Superior  Court to appoint a 
mediator. The mediation will occur within forth (40) calendar days of the 
written demand for mediation, unless the parties agree, in writing, to a 
longer period of time. 
 
3. 
The qualifications for the mediator will be that he/she be: (a) an 
experienced mediator, arbitrator or litigator of construction disputes; and (b) 
having engaged a significant portion of his/her time involving and/or 
resolving construction disputes for at least the past five (5) years. 
 
4. 
Each party will provide to the other party and the mediator all of the 
information and documentation required under B(1) and (2) above, together 
with any additional information and documentation which the party believes 
relevant. In addition, the parties will exchange, and provide to the mediator

App’d 7/20/2022 
APP-20 of 33 
General Conditions  
Appendix 6 
 
 
such additional memoranda, information and/or documentation, as the 
mediator may request, and in the form and at such times, as the mediator 
may direct. 
 
5. 
The parties will share the mediator’s fee and any filing fees equally. The 
mediation will be held in Chandler, Arizona, unless another location is 
mutually agreed upon.  Agreements reached in mediation will be specifically 
enforceable in any court having jurisdiction thereof. 
 
D. 
LITIGATION 
 
Any claim arising out of or related to the Agreement, except Claims relating to 
aesthetic effect and except those claims waived as provided for in the Agreement 
Documents, must be resolved through litigation in the Maricopa County, Arizona 
Superior Court.

App’d 7/20/2022 
APP-21 of 33 
General Conditions  
Appendix 7 
 
 
 
 
CITY OF CHANDLER, ARIZONA 
PUBLIC WORKS & UTILITIES DEPARTMENT 
 
CERTIFICATE OF COMPLETION 
 
 
PROJECT NAME: 
[TITLE] 
CITY PROJECT NO.: 
[####] 
If Federally Funded: 
 
FEDERAL NO.: 
 
ADOT NO: 
 
 
 
(This section to be completed by Prime) 
I HEREBY CERTIFY THAT ALL GOODS AND/OR SERVICES REQUIRED BY CITY OF CHANDLER FOR THIS 
PROJECT HAVE BEEN DELIVERED IN ACCORDANCE WITH THE AGREEMENT DOCUMENTS AND BID 
SPECIFICATIONS AND ALL ACTIVITIES REQUIRED BY THE AGREEMENTOR UNDER THE AGREEMENT 
HAVE BEEN COMPLETED AS OF THE COMPLETION DATE LISTED HERE: 
 
FINAL ACCEPTANCE DATE: 
 
 
PRIME CONTRACTOR: 
FIRM NAME: 
 
PRINCIPAL: 
 
TITLE: 
 
SIGNATURE: 
 
DATE: 
 
 
 
 
CERTIFIED BY [INSERT NAME AND TITLE OF PARTY THAT OVERSEES CONSTRUCTION]: 
FIRM NAME: 
 
SIGNATURE: 
 
DATE: 
 
 
 
 
 
PROJECT ACCEPTED BY CITY OF CHANDLER: 
NAME: 
 
SIGNATURE: 
 
DATE:

App’d 7/20/2022 
APP-22 of 33 
General Conditions  
Appendix 8 
 
 
 
CONSTRUCTION SIGN DETAIL 
 
 
8' 
 
 
 
  3"   
 
 
CITY OF CHANDLER 
  5"   
 
 
 
  3"   
 
 
PUTTING YOUR FUNDS TO WORK 
  5"   
 
 
 
  3"   
 
 
PROJECT TITLE: 
  5"   
 
4' 
 
 
  3"   
 
 
PROJECT NUMBER: 
  3"   
 
 
 
  2"   
 
 
PROJECT COST: 
  3"   
 
 
 
  2"   
 
 
CONTRACTOR: 
  3"   
 
 
 
  2"   
 
 
MANAGED BY: 
PUBLIC WORKS & UTILITIES DEPARTMENT 
  3"   
 
 
 
CAPITAL PROJECTS DIVISION 
  3"   
 
 
 
 
 
 
 
 
 
 
 
                              <--- 4" X 4" POSTS ---> 
 
 
 
 
NOTES: 
 
SIGN(S) MUST BE FURNISHED AND ERECTED PRIOR TO COMMENCEMENT OF CONSTRUCTION.  POSTS 
MUST BE ANCHORED A MINIMUM OF TWO FEET INTO THE GROUND. BOTTOM OF SIGN MUST BE A 
MINIMUM OF FOUR FEET ABOVE THE GROUND. 
 
TYPICAL PROJECT IDENTIFICATION SIGN FOR GENERAL PROJECTS MUST BE NON-REFLECTORIZED 
GREEN BACKGROUND, AND NON-REFLECTORIZED WHITE LETTERS AND NUMERALS. 
 
ONE SIGN MUST BE ERECTED FOR BUILDINGS AND OTHER LIMITED AREA SINGLE SITES.  FOR MULTIPLE 
SITES, ONE SIGN MUST BE ERECTED AT EACH SITE. 
 
FOR LINEAR PROJECTS ONE HALF MILE OR LONGER, PLACE ONE SIGN AT EACH END OF THE PROJECT.

App’d 7/20/2022 
APP-23 of 33 
General Conditions  
Appendix 9 – CM@Risk & JOC 
 
 
 
COST OF THE WORK 
(APPLICABLE SOLELY TO CONSTRUCTION MANAGER AT RISK AND JOB ORDER CONTRACTING) 
SECTION 1 – COSTS TO BE REIMBURSED 
1.1 Cost of the Work 
The term Cost of the Work will mean costs necessarily incurred by Contractor in the proper 
performance of the Work. Such costs must be at rates not higher than the standard paid at the place 
of the Project except with prior consent of City. The Cost of the Work will include only the items set 
forth in this Section 1. 
 
1.2 Labor Costs 
1.2.1 
Wages of construction workers directly employed by the Contractor to perform the 
construction of the Work at the site or, with City’s approval, at off-site workshops. Cost to 
be reimbursed will be the actual wages paid to the individuals performing the work. 
 
1.2.2 
Wages or salaries of the Contractor’s supervisory and administrative personnel when 
stationed at the site with City’s approval. No Contractor personnel stationed at the 
Contractor’s home or branch offices will be charged to the Cost of the Work. Non-field 
office based Contractor management and support personnel are expected to provide 
service and advice from time to time throughout the job and his/her time devoted to 
Project matters is considered to be covered by the Contractor’s Fee. 
 
1.2.3 
Wages and salaries of Contractor’s supervisory or administrative personnel who would 
normally be stationed at the field office in accordance with Section 1.2.2 but who become 
engaged, at factories, 
workshops or on the road, in expediting the production or 
transportation of materials or equipment required for the Work, but only for that portion 
of his/her time required for the Work. Employee bonuses and/or costs associated with 
Employee Stock Ownership Plans (“ESOP”) will not be considered reimbursable labor or 
labor burden costs and will be considered non-reimbursable costs considered to be covered 
by the Contractor’s Fee. 
 
1.2.4 
Costs paid or incurred by Contractor for taxes, insurance, contributions, assessments and 
benefits required by law or collective bargaining agreements and, for personnel not 
covered by such agreements, customary benefits such as sick leave, medical and health 
benefits, holiday, vacations and pensions, provided such costs are based on wages and 
salaries included in the Cost of the Work under Subparagraphs 1.2.1 through 1.2.3. 
 
1.2.4.1 Cost of the Work will include the actual net cost to Contractor for worker’s 
compensation insurance attributable to the wages chargeable to the Cost of Work per this 
Agreement. The actual net cost of worker’s compensation must take into consideration 
all cost adjustments due to experience modifiers, premium discounts, policy dividends, 
retrospective rating plan premium 
adjustments, assigned risk pool rebates, any 
applicable weekly maximums, etc. Contractor may charge an estimated amount for 
worker’s compensation insurance costs, but will make appropriate cost adjustments to 
actual costs within 45 days of receipt of actual cost adjustments from the insurance 
carrier.

App’d 7/20/2022 
APP-24 of 33 
General Conditions  
Appendix 9 – CM@Risk & JOC 
 
 
 
1.2.4.3 Overtime wages paid to salaried personnel (if approved in advance in writing by City) 
will be reimbursed at the actual rate of overtime pay paid to the individual. No time 
charges for overtime hours worked on the Project will be allowed if the individual is not paid 
for the overtime worked. 
 
1.2.4.4 Any overtime premium or shift differential expense to be incurred by Contractor for hourly 
workers will require City’s advance written approval before the incremental cost of the 
overtime premium or shift differential will be considered a reimbursable cost. If the 
Contractor is required to work overtime as a result of an inexcusable delay or other 
coordination problems caused by the Contractor or anyone he/she is responsible for, 
the overtime premium and/or shift differential expense portion of the payroll expense 
and related labor burden costs will be considered as cost not to be reimbursed. 
 
1.2.4.5 Reimbursable labor burden costs will be limited to payroll taxes, worker’s compensation 
insurance, the employer’s portion of union benefit costs for union employees working on the 
Project, and the actual verifiable fringe benefit costs incurred by Contractor for non-union 
individuals working on the Project subject to the following maximum percentages for the 
following reimbursable non-union fringe benefit costs. The following maximums (as a 
percentage of reimbursable actual wages by individual) will apply for each of the following 
types of fringe benefit costs specifically attributable to each of the non-union personnel 
working on the Project: 
 
• 
Medical Insurance, Dental, Life & AD&D Insurance: 
12.00% 
• 
Holiday, vacation and other paid time not worked: 
10.00% 
• 
Pension Plan Contributions to Vested Employee Account, 
Simplified Employee Pension Plans, or 401K matching plans 
(Note: ESOP related costs are covered by the Contractor Fee) 
10.00% 
For non-union personnel, no other fringe benefit costs (other than the three specific 
categories listed immediately above, will be considered reimbursable Cost of Work. Any 
labor burden costs that are in excess of the amounts considered reimbursable or are 
otherwise not considered reimbursable under the terms of this agreement are intended to 
be covered by the Contractor Fee. 
 
1.3 
Subcontract Costs 
1.3.1 
Payments made by Contractor to Subcontractors in accordance with the requirements of 
the subcontracts. 
 
1.3.2 
For Scope of Work Bid Packages typically performed by Subcontractors, Contractor may 
“self- perform” such work on an actual cost basis subject to an agreed upon Guaranteed 
Maximum Price for the “self-performed work”. The Contractor must, unless agreed to by City 
in writing, bid his/her proposed guaranteed Maximum Price for the work to be “self-
performed” against at least three other interested trade Contractors. All savings under 
any such Subcontract for “self-performed work” must be applied to reduce the Cost of Work 
under the Agreement and the Guaranteed Maximum Price. For purposes of defining “self-
performed work” subject to this provision, any division of Contractor, or any separate 
Contractor or Subcontractor that is partially owned or wholly owned by the Contractor or 
any of his/her employees or employee’s relatives will be considered a related party entity

App’d 7/20/2022 
APP-25 of 33 
General Conditions  
Appendix 9 – CM@Risk & JOC 
 
 
and will be subject to this provision regarding “self-performed work”. No self-performed work 
will be allowed to be performed on a Fixed Price basis. 
 
1.3.3 
Contractor (with respect to its Suppliers, Subcontractors and all lower tier Subcontractors) 
must provide City advance written notice and must obtain City’s approval for any proposed 
Subcontract Change Order, Material Purchase Order, or other financial commitment in an 
amount in excess of $5,000 prior to placing such order or entering into such agreement 
(regardless of whether or not any such commitment will affect the prime Agreement 
Guaranteed Maximum Cost). It is agreed that sums applicable to any Subcontract Change 
Order, Purchase Order or other financial commitment entered into in violation of the above 
notice and approval requirement will not be included in the amounts owning to Contractor, 
Subcontractors or Suppliers whether as Costs of the Work or as reasonable termination 
costs in the event of termination. 
 
1.4 
Costs of Material and Equipment Incorporated in the Completed Construction 
1.4.1 
Costs, including transportation and storage, of materials and equipment incorporated or 
to be incorporated in the completed construction. 
 
1.4.2 
Costs of materials described in the preceding Subparagraph 1.4.1 in excess of those 
actually installed to allow for reasonable waste and spoilage. Unused excess materials, in 
any, will become City’s property at the completion of the Work or, at City’s option, may be 
sold by the Contractor. Any amounts realized from such sales must be credited to City as a 
deduction from the Cost of Work. 
 
1.4.3 
Proceeds from the sale of recyclable materials, scrap, waste, etc. will be credited to job cost. 
 
1.5 
Costs of Other materials and Equipment, Temporary Facilities and Related Items 
1.5.1 
Costs, including transportation and storage, installation, maintenance, dismantling and 
removal of materials, supplies, temporary facilities, machinery, equipment and hand tools 
not customarily owned by construction workers, that are provided by the Contractor at the 
site and fully consumed in the performance of the Work; and cost (less salvage value) of such 
items if not fully consumed, whether sold to others or retained by Contractor. Cost for 
items previously used by Contractor will mean fair market value. 
 
1.5.2 
Rental charges for temporary facilities, machinery, equipment, and hand tools not 
customarily owned by construction workers that are provided by Contractor at the site, 
whether rented from Contractor or others, and costs of transportation, installation, minor 
repairs and replacements, 
dismantling and removal thereof. Rates and quantities of 
equipment rented will be subject to City’s prior written approval. 
 
1.5.2.1 The Projected usage for each piece of equipment to be rented for use on the Project and 
the estimated total rentals must be considered by Contractor before the piece of 
equipment is rented so that an appropriate rent versus buy decision can be made. 
Purchased equipment must be considered “job owned”. At the completion of the Project, 
Contractor must transfer title and possession of all remaining job-owned equipment to 
City, or Contractor may keep any such equipment for an appropriate fair market value 
credit to job cost, which will be mutually agreed to by City and Contractor.

App’d 7/20/2022 
APP-26 of 33 
General Conditions  
Appendix 9 – CM@Risk & JOC 
 
 
1.5.2.2 Each piece of equipment to be rented must have hourly, daily, weekly and monthly rates 
and the most economical rate available will be reimbursed based on the circumstances of 
actual need and usage of the piece of equipment while it is stationed at the jobsite. 
When the piece of equipment is no longer needed for the work, no rental charges will be 
reimbursed if the piece of equipment remains at the jobsite for the convenience of 
Contractor. 
 
1.5.2.3 Equipment Rental Rates 
1.5.2.3.1 Compensation for equipment used on the Project will be paid in accordance with the 
Equipment Plan submitted by Contractor in the accepted GMP Proposal and no payments 
will be made in excess of the rates set forth in the Equipment Plan, or actual 
documented costs, whichever is less. 
 
1.5.2.3.2 All equipment rental rates and costs are subject to City’s right to audit when submitted as 
part of Equipment Plan and/or at any time during the Project. 
 
1.5.2.4 The aggregate rentals chargeable for each piece of Contractor owned tools or equipment 
must not exceed 50% of the fair market value of such equipment at the time of its 
commitment to the Work. The original purchase price and date of purchase of the equipment 
will be documented with a copy of the purchase invoice for the piece of equipment. Such 
aggregate limitations will apply and no further rentals will be charged even if a piece of 
equipment is taken off the job and is later replaced by a similar piece of equipment. For 
purposes of computing the aggregate rentals applicable to aggregate rental limitations, 
rental charges for similar pieces of equipment will be combined if the pieces of equipment 
were not used at the same time. 
 
1.5.2.5 Fair market value for used material and equipment as referred to in the Agreement 
Documents will mean the estimated price a reasonable purchaser would pay to purchase 
the used material or equipment at the time it was initially needed for the job. Note: This is 
usually lower than the price a reasonable purchaser would pay for similar new construction 
material or construction equipment. 
 
1.5.2.6 All losses resulting from lost, damaged or stolen tools and equipment will be the sole 
responsibility of Contractor, and not City, and the cost of such losses will not be 
reimbursable under the Agreement. 
 
1.5.2.7 Contractor will be required to maintain a detailed equipment inventory of all job-owned 
equipment (either purchased and charged to job cost or job-owned through aggregate 
rentals) and such inventory must be submitted to City each month. For each piece of 
equipment, such inventory should contain at a minimum (1) original purchase price or 
acquisition cost (2) acquisition date (3) approved Fair Market Value at the time the piece of 
equipment was first used on the job and (4) final disposition. 
 
1.5.2.8 All costs incurred for minor maintenance and repairs will be reimbursed at actual cost. Such 
costs include routine and preventative maintenance, minor repairs and other incidental 
costs. Repairs and/or replacement of a capital nature are considered to be covered by the 
rental rates. Major repairs and overhauls are not considered routine and ordinary; 
consequently such costs are not reimbursable and are intended to be covered by the rental

App’d 7/20/2022 
APP-27 of 33 
General Conditions  
Appendix 9 – CM@Risk & JOC 
 
 
rates. 
 
1.5.3 
Costs of removal of debris from the Site. 
 
1.5.4 
Costs of document reproductions, facsimile transmissions and long-distance telephone 
calls, postage and parcel delivery charges, telephone service at the site and reasonable 
petty cash expenses of the site office. 
 
1.5.5 
That portion of the reasonable expenses of Contractor’s personnel incurred while 
traveling in discharge of duties connected with the Work. 
 
1.5.5.1 No travel expenses will be reimbursed to Contractor’s representatives unless Project related 
travel required them to travel to a destination more than 100 miles from the Project 
location. Any travel involving airfare will require advance written approval by an authorized 
City’s representative. 
 
1.5.6 
Costs of materials and equipment suitably stored off the site at a mutually acceptable 
location, if approved in advance by the City. 
 
1.5.7 
Reproduction costs will be the actual costs of reproduction subject to a maximum of five 
cents ($.05) per square foot for prints and a maximum of five cents ($.05) per 8 ½ by 11-
inch page for offset print or photo copied agreement documents, specifications, etc. 
Telephone costs will be the actual costs paid to the third party telephone company for the 
field office telephone. 
 
1.6 
Miscellaneous Costs 
1.6.1 
That portion of insurance and bond premiums that can be directly attributed to the 
Agreement. The City will reimburse Contractor for contractually required bond at time of first 
pay application for GMP and Cost-Based Agreements upon receipt of proof of payment 
from the Contractor. If the Contractor completes Work for less than the Agreement Price, 
Contractor must credit the City a pro- rated amount for the unused portion of the bond 
payment 
 
1.6.1.1 Contractor’s actual cost for insurance will be considered to be included within the Maximum 
limit for General Conditions Costs. All premiums for any insurance and bonds required for 
the Project must reflect the net actual costs to Contractor after taking into consideration cost 
adjustments due 
to experience modifiers, premium 
discounts, policy dividends, 
retrospective rating plan premium adjustments, assigned risk pool rebates, refunds, etc. 
 
1.6.1.2 The amount to be reimbursed to Contractor for all contractually required insurance will be 
actual costs not to exceed a total of 2% of the Agreement Value, unless Contractor 
establishes to City’s satisfaction that the actual cost is higher and City agrees to such actual 
higher cost in writing. If Contractor’s cost of contractually required insurance is greater 
than the amount agreed to be reimbursed per this Agreement Provision, the difference 
will be considered to be covered by the Contractor’s Fee.  The City will reimburse 
Contractor for contractually required insurance on a monthly basis for GMP and Cost-
Based Agreements. If Contractor can demonstrate substantial savings by paying for all 
insurance in advance, the City may agree to reimburse all insurance costs at time of first pay

App’d 7/20/2022 
APP-28 of 33 
General Conditions  
Appendix 9 – CM@Risk & JOC 
 
 
application for GMP and Cost-Based Agreements with proof of payment from Contractor. 
 
1.6.2 
Sales, use or similar taxes imposed by a governmental authority that are related to the Work. 
 
1.6.3 
Fees and assessments for the building permit and for other permits, licenses and 
inspections for which Contractor is required by the Agreement Documents to pay. 
 
1.6.4 
Fees of laboratories for tests required by the Agreement Documents, except those related to 
defective or nonconforming Work and which do not fall within the scope of ¶ 1.7.3 below. 
 
1.6.5 
Royalties and license fees paid for the use of a particular design, process or product 
required by the Agreement Documents; the cost of defending suites or claims for 
infringement of patent rights arising from such requirement of the Agreement Documents; 
and payments made in accordance with legal judgments against Contractor resulting from 
such suites or claims and payments of settlements made with City’s consent. However, 
such costs of legal defenses, judgments and settlements must not be included in the 
calculation of the Contractor’s Fee or subject to the Guaranteed Maximum Price. 
 
1.6.6 
Data processing costs related to the Work. However, any such data processing costs will be 
limited to the cost of personal computer hardware used at the field office in the 
normal day to day administration, management and control of the Project. The 
aggregate charges for any such hardware must not exceed the Fair Market Value of the 
hardware at the time it was brought to the field office. If the total charges for any particular 
piece of hardware reach an amount equal to the Fair Market Value, that particular piece of 
hardware must be turned over to City whenever it is no longer needed for the Project. If 
Contractor elects to keep the particular piece of hardware, the job costs must be credited 
with a mutually agreeable amount which will represent the Fair Market Value of the 
particular piece of hardware at the time it was no longer needed for the job. Software or 
other costs associated with the use of computer programs will not be considered to be a 
reimbursable cost and will be considered to be covered by the Contractor’s Fee. 
 
1.6.7 
Deposits lost for causes other than Contractor’s negligence or failure to fulfill a specific 
responsibility to City as set forth in the Agreement Documents. 
 
1.6.8 
Legal, mediation and arbitration costs, including attorneys’ fees, other than those arising 
from disputes between City and Contractor, reasonably incurred by Contractor in the 
performance of the Work and with City’s prior written approval; which approval will not be 
unreasonably withheld. 
 
1.6.9 
Expenses incurred in accordance with Contractor’s standard personnel policy for relocation 
and temporary living allowances of personnel required for the Work, if pre-approved by City 
in writing. If City authorizes the reimbursement of relocation costs, the reimbursable 
relocation expenses will be limited to a maximum of $50,000 per person. Any relocation 
cost incurred by Contractor in excess of the amount reimbursed by City will be considered to 
be covered by the Contractor’s Fee. 
 
1.7 
Other Costs and Emergencies 
1.7.1 
Other costs incurred in the performance of the Work if and to the extent approved in

App’d 7/20/2022 
APP-29 of 33 
General Conditions  
Appendix 9 – CM@Risk & JOC 
 
 
advance in writing by City. 
 
1.7.2 
Costs due to emergencies incurred in taking action to prevent threatened damage, injury or 
loss in case of an emergency affecting the safety of persons and property. 
 
1.7.3 
Costs of repairing or correcting damaged or nonconforming Work executed by Contractor, 
Subcontractors or Suppliers, provided that such damaged or nonconforming Work was not 
caused by negligence or failure to fulfill a specific responsibility of Contractor and only to the 
extent that the cost of repair or correction is not recoverable by Contractor from 
insurance, sureties, Subcontractors or Suppliers. 
 
1.8 
Related Party Transactions 
1.8.1 
The term “related party” will mean a parent, subsidiary, affiliate or other entity having 
common ownership or management with Contractor; any entity in which any stockholder in, 
or management employee of, Contractor owns any interest in excess of ten percent in the 
aggregate; or any person or entity which has the right to control the business or affairs of 
Contractor. The term “related party” includes any member of the immediate family of any 
person identified above. 
 
1.8.2 
If any of the costs to be reimbursed arise from a transaction between Contractor and a 
related party, Contractor must notify City in writing of the specific nature of the 
contemplated transaction, including the identity of the related party and the anticipated 
cost to be incurred, before any such transaction is consummated or cost incurred. If City, 
after such notification, authorizes in writing 
the proposed transaction, then the cost 
incurred will be included as a cost to be reimbursed, and Contractor must procure the Work, 
equipment, goods or service from the related party, as a Subcontractor. If City fails to 
authorize the transaction, Contractor must procure the Work, equipment, goods or 
service from some person or entity other than a related party. 
 
SECTION 2 – COSTS NOT TO BE REIMBURSED 
 
2.1 
The Cost of Work must not include: 
 
2.1.1 
Salaries and other compensation of Contractor’s personnel stationed at Contractor’s principal 
office or offices other than the site office, except as specifically provided in Subparagraphs 
1.2.2 and 1.2.3. 
 
2.1.2 
Expenses of Contractors’ principal office and offices other than the site office. 
 
2.1.3 
Overhead and general expenses, except as may be expressly included in Section 1. 
 
2.1.3.1 Costs of Contractor’s home office computer services or other outside computer processing 
services will be considered overhead and general expense. Accordingly, Contractor should 
not plan to perform any such computer related services or alternatives at the field office 
when such services or functions can be performed at Contractor’s home or branch offices, 
or other outside service locations. 
 
2.1.4 
Contractor’s capital expenses, including interest on Contractor’s capital employed for the Work.

App’d 7/20/2022 
APP-30 of 33 
General Conditions  
Appendix 9 – CM@Risk & JOC 
 
 
 
2.1.5 
Rental costs of machinery and equipment, except as specifically provided in subparagraph 
1.5.2. 
 
2.1.6 
Except as provided in Subparagraph 1.7.3 of the Agreement, costs due to the negligence or 
failure to fulfill a specific responsibility of Contractor, Subcontractors and Suppliers or 
anyone directly or indirectly employed by any of them or for whose acts of them may be 
liable. 
 
2.1.7 
Any cost not specifically and expressly described in Section 1. 
 
2.1.8 
Costs, other than costs included in Change Orders approved by City that would cause the 
GMP to be exceeded. 
 
SECTION 3 – DISCOUNTS, REBATES, REFUNDS AND SAVINGS 
 
3.1 
Cash discounts obtained on payments made by Contractor will accrue to City if (1) before 
making the payment, Contractor included them in an Application for Payment and 
received payment therefore from City, or (2) City has deposited funds with Contractor with 
which to make payments; otherwise, cash discounts will accrue to Contractor. Trade 
discounts, rebates, refunds and amounts received from sales or surplus materials and 
equipment will accrue to City, and Contractor must make provisions so that they can be 
secured. 
 
3.1.1 
Cost of the Work will be credited with all insurance policy discounts, performance and 
payment bond rebates or refunds, refunds or return premiums from any Subcontractor 
default insurance, refunds or rebates from any Contractor controlled insurance programs 
applicable to the Project, merchandise rebates of any nature, refunds of any nature, 
insurance dividends; and a portion of any volume rebates or free material credits earned 
with purchase of material or other goods and services charged to the job. 
 
3.1.2 
“Cash” discounts which may accrue to Contractor will be limited to a maximum of 1.5% of 
invoice cost. Any portion of “Cash” discounts greater than 1.5% will automatically accrue 
to City if Contractor is eligible to take advantage of the discounts. 
 
3.2 
Amounts that accrue to City in accordance with the provisions of Paragraph 3.1 will be 
credited to City as a deduction from the Cost of the Work. 
 
3.3 
Any and all savings on the GMP, or any separately guaranteed items comprising the GMP, 
will belong to City, subject to any express right in the Agreement for Contractor to share 
in savings. Savings are subject to City’s right to audit, and may be audited separately. 
 
SECTION 4 – GENERAL CONDITIONS COSTS 
 
4.1 
General Conditions Costs may include, but are not limited to, the following types of costs 
incurred by Contractor during construction of the Work to the extent they are reimbursable 
Costs of the Work as delineated above: payroll costs for Work conducted at the site, payroll 
costs for the superintendent and full-time general foremen, payroll costs for management

App’d 7/20/2022 
APP-31 of 33 
General Conditions  
Appendix 9 – CM@Risk & JOC 
 
 
personnel resident and working on the site workers not included as direct labor costs 
engaged in support (e.g. loading/unloading, clean-up, etc.), administrative office personnel, 
costs of offices and temporary facilities including office materials, office supplies, office 
equipment, minor expenses, utilities, fuel, sanitary facilities and telephone services at the 
site, costs of liability insurance premiums not included in labor burdens for direct labor 
costs, costs of bond premiums, costs of consultants not in the direct employ of Contractor 
or Subcontractors, fees for permits and licenses. 
 
4.2 
General Conditions Costs may be paid on a percentage of the Agreement Price or on a 
lump/stipulate sum basis as set forth in the Agreement. All costs included in the General 
Conditions Costs will not be separately invoiced to or paid by City. 
 
4.3 
The total amount of General Conditions Costs for the Work may be divided by the number of 
days allowed for performance of the Work, to determine a fixed daily rate for General 
Conditions Costs that may be used in computing the General Conditions Costs allocated to 
any period of time, or for any adjustments in the General Conditions Costs agreed to in  
 
writing by City.

App’d 7/20/2022 
APP-32 of 33 
General Conditions  
Appendix 10 
 
 
LANDSCAPE ESTABLISHMENT PERIOD 
 
Section 1 – Description and General 
Contractor is in direct control of work performed under the Landscape Establishment Period. If work 
is subcontracted, a representative of the Contractor will be present at the site of the work for all 
hours that the subcontractor works. Subcontracting of Landscape Establishment work will be 
permitted for weed eradication with herbicides, because of special licensing. A licensed temporary 
service may be used to supply labor to Contractor if Contractor has received approval from City 
Representatives.  Contractor will submit the required subcontract documentation. 
 
Contractor must provide adequate personnel to accomplish the required maintenance of the plant 
materials at intervals acceptable to City Representatives. 
 
If not healthy at the end of the maintenance period, the maintenance must be continued until the 
plant material is approved by City. 
 
1.1 Time and Schedule 
Unless otherwise expressly agreed to in writing by City, the Landscape Establishment Period will be 
per General Conditions Section 6.5.4.   
 
1.2 Planted Stock and Seeding Establishment 
1.2.1 
Tree planting and staking must be per City of Chandler Standard Detail C-801.  
1.2.2 
All trees will stand erect on their own without stakes when brought to this site. If the tree 
cannot stand on its own when nursery stakes are removed, the tree will be removed and 
replaced. 
 
1.3 Pre-Emergent Herbicide and Weed Control 
1.3.1 
Contractor will provide three applications of an approved pre-emergent herbicide on all 
unpaved areas of the project, as directed by City Representatives, to control weed growth in 
all areas of the project. The number of applications may be increased as directed by the City 
Representative, and at no additional cost to City, if the City Representative deems additional 
applications are required to control weed growth. 
1.3.2 
Application sequence will be approved in advance by City. The first application of pre-
emergent will be completed prior to the application of Decomposed Granite and will be 
included with the cost of the Decomposed Granite as specified and part of the Construction 
Phase portion of work. The second application of pre-emergent will be completed after 
installation of the Decomposed Granit and no later than half-way through the Landscape 
Establishment Period. The third and final application of pre-emergent will be applied 15 
days prior to completion of the Landscape Establishment portion of the project. The second 
and third pre-emergent applications will be included with the cost of Landscape 
Establishment. Watering will be completed in accordance with the manufacturer’s 
recommendations, as included and as related to each application. 
1.3.3 
The pre-emergent herbicide will be applied in accordance with the Technical Specifications 
and the recommendations of the pre-emergent herbicide manufacturer, as approved by 
City Representatives.

App’d 7/20/2022 
APP-33 of 33 
General Conditions  
Appendix 10 
 
 
1.3.4 
The control of weeds will be accomplished by the use of herbicides. Manual removal of 
weeds will be required, after herbicides have taken affect. 
1.3.5 
Contractor is responsible for the removal and disposal of all trash and debris that during 
the Landscape Establishment Period. Contractor will keep the project in a neat and orderly 
manner during the duration of the Landscape Establishment Period. 
 
1.4 Water 
The water used during Landscape Establishment to properly maintain the plant material will be 
furnished by City, at designated sources from within the project limits, at no charge to Contractor. 
Contractor will be responsible for all equipment, materials and labor necessary to load, transport and 
unload water for watering purposes. 
 
1.5 Plant Material Replacements 
The plant material replacement will be considered as included in the work for Landscape 
Establishment, and will be made at no charge to the City. 
1.5.1 
Shrub and Plant Replacement - During the second half of the Landscaping Establishment 
period, Contractor will provide, where required, plant replacements as follows: 
 
Original Size 
Replacement Size 
1 gallon 
5 gallon 
5 gallon 
15 gallon 
15 gallon 
24-inch box 
36-inch box 
48-inch box 
 
1.5.2 
Tree Replacement – During the second half of the Landscape Establishment Period, 
Contractor will provide plant material replacements for existing plants that die as follows: 
 
Existing Plant Material Sizes 
Replacement Size 
Trees: 
 
2-inch Caliper 
24-inch box 
4-inch Caliper 
36-inch box 
6-inch Caliper and greater 
54-inch box 
Shrubs: 
 
All Existing Shrubs 
15 gallon 
 
1.6 Measurement and Payment 
See Technical Specifications for Measurement Payment provisions.

EXHIBIT C 
 
Project Name: Pickleball Courts at Tumbleweed Park GMP I  
Page TS-1 
Project No.: PR2206.401 
Rev. 1/16/2024 
TECHNICAL SPECIFICATIONS

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
1 
 
 
 
 
DOCUMENT 000101 - PROJECT TITLE PAGE 
1.1 
PROJECT MANUAL VOLUME 1  
A. 
City of Chandler, Arizona 
B. 
Tumbleweed Pickleball 
C. 
City Project No. PR2206.201 
D. 
Dig Studio Landscape Architecture 
E. 
 
F. 
3003 N.Central Ave. Suite 800 
G. 
Phoenix, Arizona 85012 
H. 
602.595.4101 
I. 
https://www.digstudio.com/  
J. 
Issued: 12/21/23 
K. 
Copyright 2023 Dig Studio. All rights reserved. 
END OF DOCUMENT 000101

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
1 
 
 
 
 
 
 
DOCUMENT 000107 - SEALS PAGE 
1.1 
DESIGN PROFESSIONALS OF RECORD 
A. 
Landscape Architect: 
1. 
Jay Hicks, Dig Studio 
2. 
27181 
3. 
Responsible for  00-32 
 
B. 
Civil Engineer: 
1. 
John Barker, Huitt Zollars 
2. 
<Insert license #>. 
3. 
Responsible for <Insert list of Sections>. 
4. 
Insert dated and signed stamp 
C. 
Electrical Engineer: 
1. 
Cliff Tolman, Wright Engineering 
2. 
<Insert license #>. 
3. 
Responsible for <Insert list of Sections>. 
4. 
Insert dated and signed stamp 
END OF DOCUMENT 000107

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
1 
 
 
 
 
SECTION 015639 - TEMPORARY TREE AND PLANT PROTECTION 
PART 1 - GENERAL 
1.1 
RELATED DOCUMENTS 
A. 
Drawings and general provisions of the Contract, including General and Supplementary 
Conditions and other Division 01 Specification Sections, apply to this Section. 
1.2 
SUMMARY 
A. 
Section includes general protection and pruning of existing trees and plants that are affected by 
execution of the Work, whether temporary or permanent construction. 
B. 
Related Sections: 
1. 
Section 015000 "Temporary Facilities and Controls" for temporary site fencing. 
2. 
Section 311000 "Site Clearing" for removing existing trees and shrubs. 
1.3 
DEFINITIONS 
A. 
Caliper:  Diameter of a trunk measured by a diameter tape or the average of the smallest and 
largest diameters at 6 inches (150 mm) above the ground for trees up to, and including, 4-inch 
(100-mm) size; and 12 inches (300 mm) above the ground for trees larger than 4-inch (100-mm) 
size. 
B. 
Plant-Protection Zone:  Area surrounding individual trees, groups of trees, shrubs, or other 
vegetation to be protected during construction, to match edge of canopy. 
C. 
Tree-Protection Zone:  Area surrounding individual trees or groups of trees to be protected 
during construction, and defined by a circle concentric with each tree with a radius 1.5 times the 
diameter of the drip line unless otherwise indicated. 
D. 
Vegetation:  Trees, shrubs, groundcovers, grass, and other plants. 
1.4 
ACTION SUBMITTALS 
A. 
Product Data:  For each type of product indicated. 
B. 
Samples for Verification:  For each type of the following: 
1. 
Organic Mulch: 1-quart (1-L) volume of organic mulch; in sealed plastic bags labeled 
with composition of materials by percentage of weight and source of mulch. 
2. 
Protection-Zone Fencing:  Assembled Samples of manufacturer's standard size made 
from full-size components

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
2 
 
 
 
 
3. 
Protection-Zone Signage:  Full-size Samples of each size and text, ready for installation. 
C. 
Tree Pruning Schedule:  Written schedule detailing scope and extent of pruning of trees to 
remain that interfere with or are affected by construction. 
1. 
Species and size of tree. 
2. 
Location on site plan.  Include unique identifier for each. 
3. 
Reason for pruning. 
4. 
Description of pruning to be performed. 
5. 
Description of maintenance following pruning. 
1.5 
INFORMATIONAL SUBMITTALS 
A. 
Qualification Data:  For qualified arborist and tree service firm. 
B. 
Certification:  From arborist, certifying that trees indicated to remain have been protected 
during construction according to recognized standards and that trees were promptly and 
properly treated and repaired when damaged. 
C. 
Maintenance Recommendations:  From arborist, for care and protection of trees affected by 
construction during and after completing the Work. 
D. 
Existing Conditions:  Documentation of existing trees and plantings indicated to remain, which 
establishes preconstruction conditions that might be misconstrued as damage caused by 
construction activities. 
1. 
Use sufficiently detailed photographs or videotape. 
2. 
Include plans and notations to indicate specific wounds and damage conditions of each 
tree or other plants designated to remain. 
1.6 
QUALITY ASSURANCE 
A. 
Arborist Qualifications: Certified Arborist as certified by ISA 
B. 
Tree Service Firm Qualifications:  An experienced tree service firm that has successfully 
completed temporary tree and plant protection work similar to that required for this Project and 
that will assign an experienced, qualified arborist to Project site during execution of the Work. 
C. 
Preinstallation Conference:  Conduct conference at Project site 
1. 
Review methods and procedures related to temporary tree and plant protection including, 
but not limited to, the following: 
a. 
Construction schedule.  Verify availability of materials, personnel, and equipment 
needed to make progress and avoid delays. 
b. 
Enforcing requirements for protection zones. 
c. 
Arborist's responsibilities. 
d. 
Field quality control.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
3 
 
 
 
 
1.7 
PROJECT CONDITIONS 
A. 
The following practices are prohibited within protection zones: 
1. 
Storage of construction materials, debris, or excavated material. 
2. 
Parking vehicles or equipment. 
3. 
Foot traffic. 
4. 
Erection of sheds or structures. 
5. 
Impoundment of water. 
6. 
Excavation or other digging unless otherwise indicated. 
7. 
Attachment of signs to or wrapping materials around trees or plants unless otherwise 
indicated. 
B. 
Do not direct vehicle or equipment exhaust toward protection zones. 
C. 
Prohibit heat sources, flames, ignition sources, and smoking within or near protection zones and 
organic mulch. 
PART 2 - PRODUCTS 
2.1 
MATERIALS 
A. 
Topsoil:  Natural or cultivated top layer of the soil profile or manufactured topsoil; containing 
organic matter and sand, silt, and clay particles; friable, pervious, and black or a darker shade of 
brown, gray, or red than underlying subsoil; reasonably free of subsoil, clay lumps, gravel, and 
other objects more than 1 inch (25 mm) in diameter; and free of weeds, roots, and toxic and 
other nonsoil materials. 
1. 
Obtain topsoil only from well-drained sites where topsoil is 4 inches (100 mm) deep or 
more; do not obtain from bogs or marshes. 
B. 
Topsoil:  Stockpiled topsoil from location shown on Drawings 
C. 
Organic Mulch:  Free from deleterious materials and suitable as a top dressing for trees and 
shrubs, consisting of one of the following: 
1. 
Type: Partially composted Shredded hardwood, Ground or shredded bark, or Wood and 
bark chips  
2. 
Size Range:  3 inches (76 mm) maximum, 1/2 inch (13 mm) minimum 
3. 
Color:  Natural. 
D. 
Protection-Zone Fencing:  Fencing fixed in position and meeting the following requirements. 
1. 
Chain-Link Protection-Zone Fencing: Galvanized-steel fencing fabricated from minimum 
2-inch (50-mm) opening, 0.148-inch- (3.76-mm-) diameter wire chain-link fabric; with 
pipe posts, minimum 2-3/8-inch- (60-mm-) OD line posts, and 2-7/8-inch- (73-mm-) OD 
corner and pull posts and 0.177-inch- (4.5-mm-) diameter bottom tension wire; with tie 
wires, hog ring ties, and other accessories for a complete fence system.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
4 
 
 
 
 
a. 
Height: 6 feet (1.8 m) 
2. 
Wood Protection-Zone Fencing:  Constructed of two 2-by-4-inch (50-by-100-mm) 
horizontal rails, with 4-by-4-inch (100-by-100-mm) preservative-treated wood posts 
spaced not more than 8 feet (2.4 m) apart, and lower rail set halfway between top rail and 
ground. 
a. 
Height:  4 feet (1.2 m) 
3. 
Plastic Protection-Zone Fencing:  Plastic construction fencing constructed of high-density 
extruded and stretched polyethylene fabric with 2-inch (50-mm) maximum opening in 
pattern and weighing a minimum of 0.4 lb/ft. (0.6 kg/m); remaining flexible from minus 
60 to plus 200 deg F (minus 16 to plus 93 deg C); inert to most chemicals and acids; 
minimum tensile yield strength of 2000 psi (13.8 MPa) and ultimate tensile strength of 
2680 psi (18.5 MPa); secured with plastic bands or galvanized-steel or stainless-steel 
wire ties; and supported by tubular or T-shape galvanized-steel posts spaced not more 
than 8 feet (2.4 m) apart. 
a. 
Height:  4 feet (1.2 m) 
b. 
Color:  High-visibility orange, nonfading. 
E. 
Protection-Zone Signage:  Shop-fabricated, rigid plastic or metal sheet with attachment holes 
prepunched and reinforced; legibly printed with nonfading lettering. 
PART 3 - EXECUTION 
3.1 
EXAMINATION 
A. 
Erosion and Sedimentation Control:  Examine the site to verify that temporary erosion- and 
sedimentation-control measures are in place.  Verify that flows of water redirected from 
construction areas or generated by construction activity do not enter or cross protection zones. 
B. 
For the record, prepare written report, endorsed by arborist, listing conditions detrimental to tree 
and plant protection. 
3.2 
PREPARATION 
A. 
Locate and clearly identify trees, shrubs, and other vegetation to remain or to be relocated.  
B. 
Protect tree root systems from damage caused by runoff or spillage of noxious materials while 
mixing, placing, or storing construction materials.  Protect root systems from ponding, eroding, 
or excessive wetting caused by dewatering operations. 
C. 
Tree-Protection Zones:  Mulch areas inside tree-protection zones and other areas indicated. 
1. 
Apply 4-inch (100-mm) average thickness of organic mulch.  Do not place mulch within 
6 inches (150 mm) of tree trunks.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
5 
 
 
 
 
3.3 
TREE- AND PLANT-PROTECTION ZONES 
A. 
Protection-Zone Fencing:  Install protection-zone fencing along edges of protection zones 
before materials or equipment are brought on the site and construction operations begin in a 
manner that will prevent people[ and animals] from easily entering protected area except by 
entrance gates.  Construct fencing so as not to obstruct safe passage or visibility at vehicle 
intersections where fencing is located adjacent to pedestrian walkways or in close proximity to 
street intersections, drives, or other vehicular circulation. 
1. 
Chain-Link Fencing:  Install to comply with ASTM F 567 and with manufacturer's 
written instructions. 
2. 
Posts:  Set or drive posts into ground one-third the total height of the fence without 
concrete footings.  Where a post is located on existing paving or concrete to remain, 
provide appropriate means of post support acceptable to Architect. 
B. 
Protection-Zone Signage:  Install protection-zone signage in visibly prominent locations in a 
manner approved by Architect.  Install one sign spaced approximately every 20 feet (6 m) on 
protection-zone fencing, but no fewer than four signs with each facing a different direction. 
C. 
Maintain protection zones free of weeds and trash. 
D. 
Repair or replace trees, shrubs, and other vegetation indicated to remain or be relocated that are 
damaged by construction operations, in a manner approved by Architect. 
E. 
Maintain protection-zone fencing and signage in good condition as acceptable to Architect and 
remove when construction operations are complete and equipment has been removed from the 
site. 
1. 
Do not remove protection-zone fencing, even temporarily, to allow deliveries or 
equipment access through the protection zone. 
2. 
Temporary access is permitted subject to preapproval in writing by arborist if a root 
buffer effective against soil compaction is constructed as directed by arborist.  Maintain 
root buffer so long as access is permitted. 
3.4 
EXCAVATION 
A. 
General:  Excavate at edge of protection zones and for trenches indicated within protection 
zones according to requirements in Section 312000 "Earth Moving." 
B. 
Trenching near Trees:  Where utility trenches are required within protection zones, hand 
excavate under or around tree roots or tunnel under the roots by drilling, auger boring, or pipe 
jacking.  Do not cut main lateral tree roots or taproots; cut only smaller roots that interfere with 
installation of utilities.  Cut roots as required for root pruning. 
C. 
Redirect roots in backfill areas where possible.  If encountering large, main lateral roots, expose 
roots beyond excavation limits as required to bend and redirect them without breaking.  If 
encountered immediately adjacent to location of new construction and redirection is not 
practical, cut roots approximately 3 inches (75 mm) back from new construction and as required 
for root pruning.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
6 
 
 
 
 
D. 
Do not allow exposed roots to dry out before placing permanent backfill.  Provide temporary 
earth cover or pack with peat moss and wrap with burlap.  Water and maintain in a moist 
condition.  Temporarily support and protect roots from damage until they are permanently 
relocated and covered with soil. 
3.5 
ROOT PRUNING 
A. 
Prune roots that are affected by temporary and permanent construction.  Prune roots as follows: 
1. 
Cut roots manually by digging a trench and cutting exposed roots with sharp pruning 
instruments; do not break, tear, chop, or slant the cuts.  Do not use a backhoe or other 
equipment that rips, tears, or pulls roots. 
2. 
Cut Ends: Per Arborist Direction 
3. 
Temporarily support and protect roots from damage until they are permanently redirected 
and covered with soil. 
4. 
Cover exposed roots with burlap and water regularly. 
5. 
Backfill as soon as possible according to requirements in Section 312000 "Earth 
Moving." 
B. 
Root Pruning at Edge of Protection Zone: Per Arborist Direction 
C. 
Root Pruning within Protection Zone:  Per Arborist Direction. Clear and excavate by hand to the 
depth of the required excavation to minimize damage to root systems.  Use narrow-tine spading 
forks, comb soil to expose roots, and cleanly cut roots as close to excavation as possible. 
3.6 
CROWN PRUNING 
A. 
Prune branches that are affected by temporary and permanent construction.  Prune branches per 
Arborist Direction. 
1. 
Prune trees to remain to compensate for root loss caused by damaging or cutting root 
system.  Provide subsequent maintenance during Contract period as recommended by 
arborist. 
2. 
Pruning Standards:  Prune trees according to ANSI A300 (Part 1) 
3. 
Cut branches with sharp pruning instruments; do not break or chop. 
4. 
Do not apply pruning paint to wounds. 
B. 
Chip removed branches and spread over areas identified by Landscape Architect and Arborist. 
3.7 
REGRADING 
A. 
Lowering Grade:  Where new finish grade is indicated below existing grade around trees, slope 
grade beyond the protection zone.  Maintain existing grades within the protection zone. 
B. 
Lowering Grade within Protection Zone:  Where new finish grade is indicated below existing 
grade around trees, slope grade away from trees as recommended by arborist unless otherwise 
indicated.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
7 
 
 
 
 
1. 
Root Pruning:  Prune tree roots exposed by lowering the grade.  Do not cut main lateral 
roots or taproots; cut only smaller roots.  Cut roots as required for root pruning. 
C. 
Raising Grade:  Where new finish grade is indicated above existing grade around trees, slope 
grade beyond the protection zone.  Maintain existing grades within the protection zone. 
D. 
Minor Fill within Protection Zone:  Where existing grade is 2 inches (50 mm) or less below 
elevation of finish grade, fill with topsoil.  Place topsoil in a single uncompacted layer and hand 
grade to required finish elevations. 
3.8 
FIELD QUALITY CONTROL 
A. 
Inspections:  Engage a qualified arborist to direct plant-protection measures in the vicinity of 
trees, shrubs, and other vegetation indicated to remain and to prepare inspection reports. 
3.9 
REPAIR AND REPLACEMENT 
A. 
General:  Repair or replace trees, shrubs, and other vegetation indicated to remain or be 
relocated that are damaged by construction operations, in a manner approved by Architect. 
1. 
Submit details of proposed root cutting and tree and shrub repairs. 
2. 
Have arborist perform the root cutting, branch pruning, and damage repair of trees and 
shrubs. 
3. 
Treat damaged trunks, limbs, and roots according to arborist's written instructions. 
4. 
Perform repairs within 24 hours. 
5. 
Replace vegetation that cannot be repaired and restored to full-growth status, as 
determined by Architect. 
B. 
Trees:  Remove and replace trees indicated to remain that are more than 50 percent dead or in 
an unhealthy condition before the end of the corrections period or are damaged during 
construction operations that Architect determines are incapable of restoring to normal growth 
pattern. 
1. 
Provide new trees of same size and species as those being replaced for each tree that 
measures 4 inches (100 mm) or smaller in caliper size. 
2. 
Provide one new tree(s) of  4-inch (100-mm) caliper size for each tree being replaced that 
measures more than 4 inches (100 mm) in caliper size. 
a. 
Species:  Species selected by Landscape Architect 
3. 
Plant and maintain new trees as specified in Section 329300 "Plants." 
3.10 
DISPOSAL OF SURPLUS AND WASTE MATERIALS 
A. 
Disposal:  Remove excess excavated material, displaced trees, trash and debris, and legally 
dispose of them off Owner's property.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
8 
 
 
 
 
END OF SECTION 015639

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
1 
 
 
 
 
SECTION 033000.02 - CAST-IN-PLACE CONCRETE 
PART 1 - GENERAL 
1.1 
RELATED DOCUMENTS 
A. 
Drawings and general provisions of the Contract, including General and Supplementary 
Conditions and Division 01 Specification Sections, apply to this Section.  
1.2 
SUMMARY 
A. 
Section includes cast-in-place concrete, including formwork, reinforcement, concrete materials, 
mixture design, placement procedures, and finishes, for the following: 
1. 
Site walls. 
2. 
Slab on Grade. 
3. 
Footings 
B. 
Related Sections: 
1. 
Section 321316 "Decorative Concrete Paving" for decorative concrete pavement and 
walks. 
2. 
Section 321373 " Concrete Paving Joint Sealants" for concrete pavement and walks. 
1.3 
DEFINITIONS 
A. 
Cementitious Materials:  Portland cement alone or in combination with one or more of the 
following:  blended hydraulic cement, fly ash and other pozzolans, ground granulated blast-
furnace slag, and silica fume; subject to compliance with requirements. 
1.4 
ACTION SUBMITTALS 
A. 
Product Data:  For each type of product indicated. 
B. 
Design Mixtures:  City of Chandler standard for each concrete mixture.  Submit alternate design 
mixtures when characteristics of materials, Project conditions, weather, test results, or other 
circumstances warrant adjustments. 
1. 
Indicate amounts of mixing water to be withheld for later addition at Project site. 
C. 
Steel Reinforcement Shop Drawings:  Placing drawings that detail fabrication, bending, and 
placement.  Include bar sizes, lengths, material, grade, bar schedules, stirrup spacing, bent bar 
diagrams, bar arrangement, splices and laps, mechanical connections, tie spacing, hoop spacing, 
and supports for concrete reinforcement. 
D. 
Formwork Shop Drawings:  Prepared by or under the supervision of a qualified professional 
engineer detailing fabrication, assembly, and support of formwork.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
2 
 
 
 
 
1. 
Shoring and Reshoring:  Indicate proposed schedule and sequence of stripping formwork, 
shoring removal, and reshoring installation and removal. 
E. 
Construction Joint Layout:  Indicate proposed construction joints required to construct the 
structure. 
1. 
Location of construction joints is subject to approval of the Landscape Architect. 
F. 
Samples:  For vapor retarder. 
1.5 
INFORMATIONAL SUBMITTALS 
A. 
Qualification Data:  For Installer manufacturer and testing agency. 
B. 
Welding certificates. 
C. 
Material Certificates:  For each of the following, signed by manufacturers: 
1. 
Cementitious materials. 
2. 
Admixtures. 
3. 
Form materials and form-release agents. 
4. 
Steel reinforcement and accessories. 
5. 
Fiber reinforcement. 
6. 
Waterstops. 
7. 
Curing compounds. 
8. 
Floor and slab treatments. 
9. 
Bonding agents. 
10. 
Adhesives. 
11. 
Vapor retarders. 
12. 
Semirigid joint filler. 
13. 
Joint-filler strips. 
14. 
Repair materials. 
D. 
Material Test Reports:  For the following, from a qualified testing agency, indicating 
compliance with requirements: 
1. 
Aggregates: Include service record data indicating absence of deleterious expansion of 
concrete due to alkali aggregate reactivity. 
E. 
Floor surface flatness and levelness measurements indicating compliance with specified 
tolerances. 
F. 
Field quality-control reports. 
G. 
Minutes of preinstallation conference.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
3 
 
 
 
 
1.6 
QUALITY ASSURANCE 
A. 
Installer Qualifications:  A qualified installer who employs on Project personnel qualified as 
ACI-certified Flatwork Technician and Finisher and a supervisor who is an ACI-certified 
Concrete Flatwork Technician. 
B. 
Manufacturer Qualifications:  A firm experienced in manufacturing ready-mixed concrete 
products and that complies with ASTM C 94/C 94M requirements for production facilities and 
equipment. 
1. 
Manufacturer certified according to NRMCA's "Certification of Ready Mixed Concrete 
Production Facilities." 
C. 
Testing Agency Qualifications:  An independent agency, acceptable to authorities having 
jurisdiction, qualified according to ASTM C 1077 and ASTM E 329 for testing indicated. 
1. 
Personnel conducting field tests shall be qualified as ACI Concrete Field Testing 
Technician, Grade 1, according to ACI CP-1 or an equivalent certification program. 
2. 
Personnel performing laboratory tests shall be ACI-certified Concrete Strength Testing 
Technician and Concrete Laboratory Testing Technician - Grade I.  Testing Agency 
laboratory supervisor shall be an ACI-certified Concrete Laboratory Testing Technician - 
Grade II. 
D. 
Source Limitations:  Obtain each type or class of cementitious material of the same brand from 
the same manufacturer's plant, obtain aggregate from single source, and obtain admixtures from 
single source from single manufacturer. 
E. 
Welding Qualifications:  Qualify procedures and personnel according to AWS D1.4/D 1.4M, 
"Structural Welding Code - Reinforcing Steel." 
F. 
ACI Publications:  Comply with the following unless modified by requirements in the Contract 
Documents: 
1. 
ACI 117, "Specifications for Tolerances for Concrete Construction and Materials." 
G. 
Concrete Testing Service:  Engage a qualified independent testing agency to perform material 
evaluation tests and to design concrete mixtures. 
H. 
Mockups:  Cast concrete slab-on-grade and formed-surface panels to demonstrate typical joints, 
surface finish, texture, tolerances, floor treatments, and standard of workmanship. 
1. 
Build panel approximately 100 sq. ft. for slab-on-grade and 60 sq. ft. for formed surface 
in the location indicated or, if not indicated, as directed by Landscape Architect. 
2. 
Approved mockups may become part of the completed Work if undisturbed at time of 
Substantial Completion. 
I. 
Preinstallation Conference:  Conduct conference at Project site. 
1. 
Before submitting design mixtures, review concrete design mixture and examine 
procedures for ensuring quality of concrete materials.  Require representatives of each 
entity directly concerned with cast-in-place concrete to attend, including the following:

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
4 
 
 
 
 
a. 
Contractor's superintendent. 
b. 
Independent testing agency responsible for concrete design mixtures. 
c. 
Ready-mix concrete manufacturer. 
d. 
Concrete subcontractor. 
e. 
Special concrete finish subcontractor. 
2. 
Review special inspection and testing and inspecting agency procedures for field quality 
control, concrete finishes and finishing, cold- and hot-weather concreting procedures, 
curing procedures, construction contraction and isolation joints, and joint-filler strips, 
semirigid joint fillers, forms and form removal limitations, shoring and reshoring 
procedures, vapor-retarder installation, anchor rod and anchorage device installation 
tolerances, steel reinforcement installation, floor and slab flatness and levelness 
measurement, concrete repair procedures, and concrete protection. 
1.7 
DELIVERY, STORAGE, AND HANDLING 
A. 
Steel Reinforcement:  Deliver, store, and handle steel reinforcement to prevent bending and 
damage. Avoid damaging coatings on steel reinforcement. 
B. 
Waterstops:  Store waterstops under cover to protect from moisture, sunlight, dirt, oil, and other 
contaminants. 
PART 2 - PRODUCTS 
2.1 
FORM-FACING MATERIALS 
A. 
Smooth-Formed Finished Concrete:  Form-facing panels that will provide continuous, true, and 
smooth concrete surfaces.  Furnish in largest practicable sizes to minimize number of joints. 
1. 
Plywood, metal, or other approved panel materials. 
2. 
Exterior-grade plywood panels, suitable for concrete forms, complying with DOC PS 1, 
and as follows: 
a. 
Medium-density overlay, Class 1 or better; mill-release agent treated and edge 
sealed. 
3. 
Reckli formliner 2/208 Volta, or equal. 
B. 
Forms for Cylindrical Columns, Pedestals, and Supports:  Metal, glass-fiber-reinforced plastic, 
paper, or fiber tubes that will produce surfaces with gradual or abrupt irregularities not 
exceeding specified formwork surface class.  Provide units with sufficient wall thickness to 
resist plastic concrete loads without detrimental deformation. 
C. 
Pan-Type Forms:  Glass-fiber-reinforced plastic or formed steel, stiffened to resist plastic 
concrete loads without detrimental deformation. 
D. 
Void Forms:  Biodegradable paper surface, treated for moisture resistance, structurally 
sufficient to support weight of plastic concrete and other superimposed loads.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
5 
 
 
 
 
E. 
Chamfer Strips:  Wood, metal, PVC, or rubber strips, 3/4 by 3/4 inch (19 by 19 mm), minimum. 
F. 
Rustication Strips:  Wood, metal, PVC, or rubber strips, kerfed for ease of form removal. 
G. 
Form-Release Agent:  Commercially formulated form-release agent that will not bond with, 
stain, or adversely affect concrete surfaces and will not impair subsequent treatments of 
concrete surfaces. 
1. 
Formulate form-release agent with rust inhibitor for steel form-facing materials. 
H. 
Form Ties:  Factory-fabricated, removable or snap-off metal or glass-fiber-reinforced plastic 
form ties designed to resist lateral pressure of fresh concrete on forms and to prevent spalling of 
concrete on removal. 
1. 
Furnish units that will leave no corrodible metal closer than 1 inch (25 mm) to the plane 
of exposed concrete surface. 
2. 
Furnish ties that, when removed, will leave holes no larger than 1 inch (25 mm) in 
diameter in concrete surface. 
3. 
Furnish ties with integral water-barrier plates to walls indicated to receive dampproofing 
or waterproofing. 
2.2 
STEEL REINFORCEMENT 
A. 
Reinforcing Bars:  ASTM A 615/A 615M, Grade 60, deformed. 
B. 
Plain-Steel Welded Wire Reinforcement:  ASTM A 185/A 185M, plain, fabricated from as-
drawn steel wire into flat sheets. 
2.3 
REINFORCEMENT ACCESSORIES 
A. 
Joint Dowel Bars:  ASTM A 615/A 615M, Grade 60, plain-steel smooth bars, cut true to length 
with ends square and free of burrs. 
B. 
Epoxy Repair Coating:  Liquid, two-part, epoxy repair coating; compatible with epoxy coating 
on reinforcement and complying with ASTM A 775/A 775M. 
C. 
Zinc Repair Material:  ASTM A 780, zinc-based solder, paint containing zinc dust, or sprayed 
zinc. 
D. 
Bar Supports:  Bolsters, chairs, spacers, and other devices for spacing, supporting, and fastening 
reinforcing bars and welded wire reinforcement in place.  Manufacture bar supports from steel 
wire, plastic, or precast concrete according to CRSI's "Manual of Standard Practice," of greater 
compressive strength than concrete and as follows: 
1. 
For concrete surfaces exposed to view where legs of wire bar supports contact forms, use 
CRSI Class 1 plastic-protected steel wire or CRSI Class 2 stainless-steel bar supports. 
2. 
For epoxy-coated reinforcement, use epoxy-coated or other dielectric-polymer-coated 
wire bar supports.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
6 
 
 
 
 
2.4 
CONCRETE MATERIALS 
A. 
Cementitious Material:  Use the following cementitious materials, of the same type, brand, and 
source, throughout Project: 
1. 
Portland Cement:  ASTM C 150, Type II Supplement with the following: 
a. 
Fly Ash:  ASTM C 618, 
b. 
Ground Granulated Blast-Furnace Slag:  ASTM C 989, Grade 100 or 120. 
B. 
Silica Fume:  ASTM C 1240, amorphous silica. 
C. 
Normal-Weight Aggregates:  ASTM C 33, coarse aggregate or better, graded.  Provide 
aggregates from a single source[ with documented service record data of at least 10 years' 
satisfactory service in similar applications and service conditions using similar aggregates and 
cementitious materials]. 
1. 
Maximum Coarse-Aggregate Size: 3/4 inch (19 mm) nominal. 
D. 
Water:  ASTM C 94/C 94M and potable. 
2.5 
ADMIXTURES 
A. 
Air-Entraining Admixture:  ASTM C 260. 
B. 
Chemical Admixtures:  Provide admixtures certified by manufacturer to be compatible with 
other admixtures and that will not contribute water-soluble chloride ions exceeding those 
permitted in hardened concrete.  Do not use calcium chloride or admixtures containing calcium 
chloride. 
1. 
Water-Reducing Admixture:  ASTM C 494/C 494M, Type A. 
2. 
Retarding Admixture:  ASTM C 494/C 494M, Type B. 
3. 
Water-Reducing and Retarding Admixture:  ASTM C 494/C 494M, Type D. 
4. 
High-Range, Water-Reducing Admixture:  ASTM C 494/C 494M, Type F. 
5. 
High-Range, Water-Reducing and Retarding Admixture:  ASTM C 494/C 494M, 
Type G. 
6. 
Plasticizing and Retarding Admixture:  ASTM C 1017/C 1017M, Type II. 
2.6 
VAPOR RETARDERS 
A. 
Sheet Vapor Retarder:  ASTM E 1745, Class A, Include manufacturer's recommended adhesive 
or pressure-sensitive tape. 
1. 
Products:  Subject to compliance with requirements, available products that may be 
incorporated into the Work include, but are not limited to, the following: 
a. 
Carlisle Coatings & Waterproofing, Inc.; Blackline 400. 
b. 
Fortifiber Building Systems Group; Moistop Ultra 15. 
c. 
Grace Construction Products, W. R. Grace & Co.; Florprufe 120.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
7 
 
 
 
 
d. 
Insulation Solutions, Inc.; Viper VaporCheck 16 
e. 
Meadows, W. R., Inc.; Perminator  10 mil 
f. 
Raven Industries Inc.; Vapor Block 10. 
g. 
Reef Industries, Inc.; Griffolyn 10 mil Green. 
h. 
Stego Industries, LLC; Stego Wrap 10 mil Class A. 
2.7 
CURING MATERIALS 
A. 
Evaporation Retarder: ASTM C309 Type 2 Waterborne, monomolecular film forming, 
manufactured for application to fresh concrete. 
1. 
Products:  Subject to compliance with requirements, available products that may be 
incorporated into the Work include, but are not limited to, the following: 
a. 
Axim Italcementi Group, Inc.; CATEXOL CimFilm. 
b. 
BASF Construction Chemicals - Building Systems; Confilm. 
c. 
ChemMasters; SprayFilm. 
d. 
Conspec by Dayton Superior; Aquafilm. 
e. 
Dayton Superior Corporation; Sure Film (J-74). 
f. 
Edoco by Dayton Superior; BurkeFilm. 
g. 
Euclid Chemical Company (The), an RPM company; Eucobar. 
h. 
Kaufman Products, Inc.; Vapor-Aid. 
i. 
Lambert Corporation; LAMBCO Skin. 
j. 
L&M Construction Chemicals, Inc.; E-CON. 
k. 
Meadows, W. R., Inc.; EVAPRE. 
l. 
Metalcrete Industries; Waterhold. 
m. 
Nox-Crete Products Group; MONOFILM. 
n. 
Sika Corporation; SikaFilm. 
o. 
SpecChem, LLC; Spec Film. 
p. 
Symons by Dayton Superior; Finishing Aid. 
q. 
TK Products, Division of Sierra Corporation; TK-2120 TRI-FILM. 
r. 
Unitex; PRO-FILM. 
s. 
Vexcon Chemicals, Inc.; Certi-Vex Envio Set. 
B. 
Absorptive Cover:  AASHTO M 182, Class 2, burlap cloth made from jute or kenaf, weighing 
approximately 9 oz./sq. yd. (305 g/sq. m) when dry. 
C. 
Moisture-Retaining Cover:  ASTM C 171, polyethylene film or white burlap-polyethylene 
sheet. 
D. 
Water:  Potable. 
2.8 
RELATED MATERIALS 
A. 
Expansion- and Isolation-Joint-Filler Strips: ASTM D 1751, asphalt-saturated cellulosic fiber 
B. 
Semirigid Joint Filler:  Two-component, semirigid, 100 percent solids, epoxy resin with a 
Type A shore durometer hardness of 80 per ASTM D 2240.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
8 
 
 
 
 
C. 
Bonding Agent:  ASTM C 1059/C 1059M, Type II, non-redispersible, acrylic emulsion or 
styrene butadiene. 
D. 
Epoxy Bonding Adhesive:  ASTM C 881, two-component epoxy resin, capable of humid curing 
and bonding to damp surfaces, of class suitable for application temperature and of grade to suit 
requirements, and as follows: 
1. 
Types I and II, non-load bearing Types IV and V, load bearing, for bonding hardened or 
freshly mixed concrete to hardened concrete. 
E. 
Reglets:  Fabricate reglets of not less than 0.022-inch- (0.55-mm-) thick, galvanized-steel sheet.  
Temporarily fill or cover face opening of reglet to prevent intrusion of concrete or debris. 
F. 
Dovetail Anchor Slots:  Hot-dip galvanized-steel sheet, not less than 0.034 inch (0.85 mm) 
thick, with bent tab anchors.  Temporarily fill or cover face opening of slots to prevent intrusion 
of concrete or debris. 
2.9 
CONCRETE MIXTURES, GENERAL 
A. 
Prepare design mixtures for each type and strength of concrete, proportioned on the basis of 
laboratory trial mixture or field test data, or both, according to ACI 301. 
1. 
Use a qualified independent testing agency for preparing and reporting proposed mixture 
designs based on laboratory trial mixtures. 
B. 
Cementitious Materials: Limit percentage, by weight, of cementitious materials other than 
portland cement in concrete as follows: 
1. 
Fly Ash:  25 percent. 
2. 
Combined Fly Ash and Pozzolan:  25 percent. 
3. 
Ground Granulated Blast-Furnace Slag:  50 percent. 
4. 
Combined Fly Ash or Pozzolan and Ground Granulated Blast-Furnace Slag:  50 percent 
portland cement minimum, with fly ash or pozzolan not exceeding 25 percent. 
5. 
Silica Fume:  10 percent. 
6. 
Combined Fly Ash, Pozzolans, and Silica Fume:  35 percent with fly ash or pozzolans not 
exceeding 25 percent and silica fume not exceeding 10 percent. 
7. 
Combined Fly Ash or Pozzolans, Ground Granulated Blast-Furnace Slag, and Silica 
Fume:  50 percent with fly ash or pozzolans not exceeding 25 percent and silica fume not 
exceeding 10 percent. 
C. 
Limit water-soluble, chloride-ion content in hardened concrete to [0.06] [0.15] [0.30] [1.00] 
percent by weight of cement. 
D. 
Admixtures:  Use admixtures according to manufacturer's written instructions. 
1. 
Use water-reducing admixture in concrete, as required, for placement and workability. 
2. 
Use water-reducing and retarding admixture when required by high temperatures, low 
humidity, or other adverse placement conditions.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
9 
 
 
 
 
3. 
Use water-reducing admixture in pumped concrete, concrete for heavy-use industrial 
slabs and parking structure slabs, concrete required to be watertight, and concrete with a 
water-cementitious materials ratio below 0.50. 
4. 
Use corrosion-inhibiting admixture in concrete mixtures where indicated. 
2.10 
CONCRETE MIXTURES FOR BUILDING ELEMENTS 
A. 
Footings:  Proportion normal-weight concrete mixture as follows: 
1. 
Minimum Compressive Strength: 3500 psi (24.1 MPa) at 28 days. 
2. 
Maximum Water-Cementitious Materials Ratio:  0.40 
3. 
Slump Limit:  4 inches (100 mm) for concrete with verified slump of 2 to 4 inches (50 to 
100 mm) before adding high-range water-reducing admixture or plasticizing admixture 
plus or minus 1 inch (25 mm). 
4. 
Air Content:  5.5 percent, plus or minus 1.5 percent at point of delivery for 1-1/2-inch 
(38-mm) nominal maximum aggregate size. 
5. 
Air Content:  6 percent, plus or minus 1.5 percent at point of delivery for 3/4-inch (19-
mm) nominal maximum aggregate size. 
B. 
Slabs-on-Grade:  Proportion normal-weight concrete mixture as follows: 
1. 
Minimum Compressive Strength: 3500 psi (24.1 MPa) at 28 days. 
2. 
Minimum Cementitious Materials Content:  470 lb/cu. yd. (279 kg/cu. m 
3. 
Slump Limit:  4 inches (100 mm) plus or minus 1 inch (25 mm). 
4. 
Air Content:  5.5percent, plus or minus 1.5 percent at point of delivery for 1-1/2-inch (38-
mm) nominal maximum aggregate size. 
5. 
Air Content:  6 percent, plus or minus 1.5 percent at point of delivery for 3/4-inch (19-
mm)] nominal maximum aggregate size. 
6. 
Air Content:  Do not allow air content of trowel-finished floors to exceed 3 percent. 
7. 
a rate of [50 lb/cu. yd. (29.7 kg/cu. m)] <Insert weight>. 
8. 
Synthetic Micro-Fiber:  Uniformly disperse in concrete mixture at manufacturer's 
recommended rate, but not less than 1.0 lb/cu. yd. (0.60 kg/cu. m) 
2.11 
FABRICATING REINFORCEMENT 
A. 
Fabricate steel reinforcement according to CRSI's "Manual of Standard Practice." 
2.12 
CONCRETE MIXING 
A. 
Ready-Mixed Concrete:  Measure, batch, mix, and deliver concrete according to 
ASTM C 94/C 94M[ and ASTM C 1116/C 1116M], and furnish batch ticket information. 
1. 
When air temperature is between 85 and 90 deg F (30 and 32 deg C), reduce mixing and 
delivery time from 1-1/2 hours to 75 minutes; when air temperature is above 90 deg F (32 
deg C), reduce mixing and delivery time to 60 minutes.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
10 
 
 
 
 
B. 
Project-Site Mixing:  Measure, batch, and mix concrete materials and concrete according to 
ASTM C 94/C 94M.  Mix concrete materials in appropriate drum-type batch machine mixer. 
1. 
For mixer capacity of 1 cu. yd. (0.76 cu. m) or smaller, continue mixing at least 1-1/2 
minutes, but not more than 5 minutes after ingredients are in mixer, before any part of 
batch is released. 
2. 
For mixer capacity larger than 1 cu. yd. (0.76 cu. m), increase mixing time by 15 seconds 
for each additional 1 cu. yd. (0.76 cu. m). 
3. 
Provide batch ticket for each batch discharged and used in the Work, indicating Project 
identification name and number, date, mixture type, mixture time, quantity, and amount 
of water added.  Record approximate location of final deposit in structure. 
PART 3 - EXECUTION 
3.1 
FORMWORK 
A. 
Design, erect, shore, brace, and maintain formwork, according to ACI 301, to support vertical, 
lateral, static, and dynamic loads, and construction loads that might be applied, until structure 
can support such loads. 
B. 
Construct formwork so concrete members and structures are of size, shape, alignment, 
elevation, and position indicated, within tolerance limits of ACI 117. 
C. 
Limit concrete surface irregularities, designated by ACI 347 as abrupt or gradual, as follows: 
1. 
Class A, 1/8 inch (3.2 mm) for smooth-formed finished surfaces. 
2. 
Class B, 1/4 inch (6 mm) for rough-formed finished surfaces. 
D. 
Construct forms tight enough to prevent loss of concrete mortar. 
E. 
Fabricate forms for easy removal without hammering or prying against concrete surfaces.  
Provide crush or wrecking plates where stripping may damage cast concrete surfaces.  Provide 
top forms for inclined surfaces steeper than 1.5 horizontal to 1 vertical. 
1. 
Install keyways, reglets, recesses, and the like, for easy removal. 
2. 
Do not use rust-stained steel form-facing material. 
F. 
Set edge forms, bulkheads, and intermediate screed strips for slabs to achieve required 
elevations and slopes in finished concrete surfaces.  Provide and secure units to support screed 
strips; use strike-off templates or compacting-type screeds. 
G. 
Provide temporary openings for cleanouts and inspection ports where interior area of formwork 
is inaccessible.  Close openings with panels tightly fitted to forms and securely braced to 
prevent loss of concrete mortar.  Locate temporary openings in forms at inconspicuous 
locations. 
H. 
 Chamfer, refer to details for finish of exterior corners and edges of permanently exposed 
concrete.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
11 
 
 
 
 
I. 
Form openings, chases, offsets, sinkages, keyways, reglets, blocking, screeds, and bulkheads 
required in the Work.  Determine sizes and locations from trades providing such items. 
J. 
Clean forms and adjacent surfaces to receive concrete.  Remove chips, wood, sawdust, dirt, and 
other debris just before placing concrete. 
K. 
Retighten forms and bracing before placing concrete, as required, to prevent mortar leaks and 
maintain proper alignment. 
L. 
Coat contact surfaces of forms with form-release agent, according to manufacturer's written 
instructions, before placing reinforcement. 
3.2 
EMBEDDED ITEMS 
A. 
Place and secure anchorage devices and other embedded items required for adjoining work that 
is attached to or supported by cast-in-place concrete.  Use setting drawings, templates, 
diagrams, instructions, and directions furnished with items to be embedded. 
1. 
Install anchor rods, accurately located, to elevations required and complying with 
tolerances in Section 7.5 of AISC's "Code of Standard Practice for Steel Buildings and 
Bridges." 
2. 
Install reglets to receive waterproofing and to receive through-wall flashings in outer face 
of concrete frame at exterior walls, where flashing is shown at lintels, shelf angles, and 
other conditions. 
3. 
Install dovetail anchor slots in concrete structures as indicated. 
3.3 
REMOVING AND REUSING FORMS 
A. 
General:  Formwork for sides of beams, walls, columns, and similar parts of the Work that does 
not support weight of concrete may be removed after cumulatively curing at not less than 50 
deg F (10 deg C) for 24 hours after placing concrete.  Concrete has to be hard enough to not be 
damaged by form-removal operations and curing and protection operations need to be 
maintained. 
1. 
Leave formwork for beam soffits, joists, slabs, and other structural elements that supports 
weight of concrete in place until concrete has achieved[ at least 70 percent of] its 28-day 
design compressive strength. 
2. 
Remove forms only if shores have been arranged to permit removal of forms without 
loosening or disturbing shores. 
B. 
Clean and repair surfaces of forms to be reused in the Work.  Split, frayed, delaminated, or 
otherwise damaged form-facing material will not be acceptable for exposed surfaces.  Apply 
new form-release agent. 
C. 
When forms are reused, clean surfaces, remove fins and laitance, and tighten to close joints.  
Align and secure joints to avoid offsets.  Do not use patched forms for exposed concrete 
surfaces unless approved by Architect.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
12 
 
 
 
 
3.4 
SHORES AND RESHORES 
A. 
Comply with ACI 318 (ACI 318M) and ACI 301 for design, installation, and removal of 
shoring and reshoring. 
1. 
Do not remove shoring or reshoring until measurement of slab tolerances is complete. 
B. 
Plan sequence of removal of shores and reshore to avoid damage to concrete.  Locate and 
provide adequate reshoring to support construction without excessive stress or deflection. 
3.5 
VAPOR RETARDERS 
A. 
Sheet Vapor Retarders:  Place, protect, and repair sheet vapor retarder according to 
ASTM E 1643 and manufacturer's written instructions. 
1. 
Lap joints 6 inches (150 mm) and seal with manufacturer's recommended tape. 
B. 
Bituminous Vapor Retarders:  Place, protect, and repair bituminous vapor retarder according to 
manufacturer's written instructions. 
C. 
Granular Course:  Cover vapor retarder with fine-graded granular material, moisten, and 
compact with mechanical equipment to elevation tolerances of plus 0 inch (0 mm) or minus 3/4 
inch (19 mm). 
1. 
Place and compact a 1/2-inch- (13-mm-) thick layer of fine-graded granular material over 
granular fill. 
3.6 
STEEL REINFORCEMENT 
A. 
General:  Comply with CRSI's "Manual of Standard Practice" for placing reinforcement. 
1. 
Do not cut or puncture vapor retarder.  Repair damage and reseal vapor retarder before 
placing concrete. 
B. 
Clean reinforcement of loose rust and mill scale, earth, ice, and other foreign materials that 
would reduce bond to concrete. 
C. 
Accurately position, support, and secure reinforcement against displacement.  Locate and 
support reinforcement with bar supports to maintain minimum concrete cover.  Do not tack 
weld crossing reinforcing bars. 
1. 
Weld reinforcing bars according to AWS D1.4/D 1.4M, where indicated. 
D. 
Set wire ties with ends directed into concrete, not toward exposed concrete surfaces. 
E. 
Install welded wire reinforcement in longest practicable lengths on bar supports spaced to 
minimize sagging.  Lap edges and ends of adjoining sheets at least one mesh spacing.  Offset 
laps of adjoining sheet widths to prevent continuous laps in either direction.  Lace overlaps with 
wire.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
13 
 
 
 
 
F. 
Epoxy-Coated Reinforcement:  Repair cut and damaged epoxy coatings with epoxy repair 
coating according to ASTM D 3963/D 3963M.  Use epoxy-coated steel wire ties to fasten 
epoxy-coated steel reinforcement. 
G. 
Zinc-Coated Reinforcement:  Repair cut and damaged zinc coatings with zinc repair material 
according to ASTM A 780.  Use galvanized steel wire ties to fasten zinc-coated steel 
reinforcement. 
3.7 
JOINTS 
A. 
General:  Construct joints true to line with faces perpendicular to surface plane of concrete. 
B. 
Construction Joints:  Install so strength and appearance of concrete are not impaired, at 
locations indicated or as approved by Architect. 
1. 
Place joints perpendicular to main reinforcement.  Continue reinforcement across 
construction joints unless otherwise indicated.  Do not continue reinforcement through 
sides of strip placements of floors and slabs. 
2. 
Form keyed joints as indicated.  Embed keys at least 1-1/2 inches (38 mm) into concrete. 
3. 
Locate joints for beams, slabs, joists, and girders in the middle third of spans.  Offset 
joints in girders a minimum distance of twice the beam width from a beam-girder 
intersection. 
4. 
Locate horizontal joints in walls and columns at underside of floors, slabs, beams, and 
girders and at the top of footings or floor slabs. 
5. 
Space vertical joints in walls as indicated. Locate joints beside piers integral with walls, 
near corners, and in concealed locations where possible. 
6. 
Use a bonding agent at locations where fresh concrete is placed against hardened or 
partially hardened concrete surfaces. 
7. 
Use epoxy-bonding adhesive at locations where fresh concrete is placed against hardened 
or partially hardened concrete surfaces. 
C. 
Contraction Joints in Slabs-on-Grade:  Form weakened-plane contraction joints, sectioning 
concrete into areas as indicated.  Construct contraction joints for a depth equal to at least one-
fourth of concrete thickness as follows: 
1. 
Grooved Joints:  Form contraction joints after initial floating by grooving and finishing 
each edge of joint to a radius of 1/8 inch (3.2 mm).  Repeat grooving of contraction joints 
after applying surface finishes.  Eliminate groover tool marks on concrete surfaces. 
2. 
Sawed Joints:  Form contraction joints with power saws equipped with shatterproof 
abrasive or diamond-rimmed blades.  Cut 1/8-inch- (3.2-mm-) wide joints into concrete 
when cutting action will not tear, abrade, or otherwise damage surface and before 
concrete develops random contraction cracks. 
D. 
Isolation Joints in Slabs-on-Grade:  After removing formwork, install joint-filler strips at slab 
junctions with vertical surfaces, such as column pedestals, foundation walls, grade beams, and 
other locations, as indicated. 
1. 
Extend joint-filler strips full width and depth of joint, terminating flush with finished 
concrete surface unless otherwise indicated.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
14 
 
 
 
 
2. 
Terminate full-width joint-filler strips not less than 1/2 inch (13 mm) or more than 1 inch 
(25 mm) below finished concrete surface where joint sealants, specified in 
Section 079200 "Joint Sealants," are indicated. 
3. 
Install joint-filler strips in lengths as long as practicable.  Where more than one length is 
required, lace or clip sections together. 
E. 
Doweled Joints:  Install dowel bars and support assemblies at joints where indicated.  Lubricate 
or asphalt coat one-half of dowel length to prevent concrete bonding to one side of joint. 
3.8 
WATERSTOPS 
A. 
Flexible Waterstops:  Install in construction joints and at other joints indicated to form a 
continuous diaphragm.  Install in longest lengths practicable.  Support and protect exposed 
waterstops during progress of the Work.  Field fabricate joints in waterstops according to 
manufacturer's written instructions. 
B. 
Self-Expanding Strip Waterstops:  Install in construction joints and at other locations indicated, 
according to manufacturer's written instructions, adhesive bonding, mechanically fastening, and 
firmly pressing into place.  Install in longest lengths practicable. 
3.9 
CONCRETE PLACEMENT 
A. 
Before placing concrete, verify that installation of formwork, reinforcement, and embedded 
items is complete and that required inspections have been performed. 
B. 
Do not add water to concrete during delivery, at Project site, or during placement unless 
approved by Architect. 
C. 
Before test sampling and placing concrete, water may be added at Project site, subject to 
limitations of ACI 301. 
1. 
Do not add water to concrete after adding high-range water-reducing admixtures to 
mixture. 
D. 
Deposit concrete continuously in one layer or in horizontal layers of such thickness that no new 
concrete will be placed on concrete that has hardened enough to cause seams or planes of 
weakness.  If a section cannot be placed continuously, provide construction joints as indicated.  
Deposit concrete to avoid segregation. 
1. 
Deposit concrete in horizontal layers of depth to not exceed formwork design pressures 
and in a manner to avoid inclined construction joints. 
2. 
Consolidate placed concrete with mechanical vibrating equipment according to ACI 301. 
3. 
Do not use vibrators to transport concrete inside forms.  Insert and withdraw vibrators 
vertically at uniformly spaced locations to rapidly penetrate placed layer and at least 6 
inches (150 mm) into preceding layer.  Do not insert vibrators into lower layers of 
concrete that have begun to lose plasticity.  At each insertion, limit duration of vibration 
to time necessary to consolidate concrete and complete embedment of reinforcement and 
other embedded items without causing mixture constituents to segregate.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
15 
 
 
 
 
E. 
Deposit and consolidate concrete for floors and slabs in a continuous operation, within limits of 
construction joints, until placement of a panel or section is complete. 
1. 
Consolidate concrete during placement operations so concrete is thoroughly worked 
around reinforcement and other embedded items and into corners. 
2. 
Maintain reinforcement in position on chairs during concrete placement. 
3. 
Screed slab surfaces with a straightedge and strike off to correct elevations. 
4. 
Slope surfaces uniformly to drains where required. 
5. 
Begin initial floating using bull floats or darbies to form a uniform and open-textured 
surface plane, before excess bleedwater appears on the surface.  Do not further disturb 
slab surfaces before starting finishing operations. 
F. 
Cold-Weather Placement:  Comply with ACI 306.1 and as follows.  Protect concrete work from 
physical damage or reduced strength that could be caused by frost, freezing actions, or low 
temperatures. 
1. 
When average high and low temperature is expected to fall below 40 deg F (4.4 deg C) 
for three successive days, maintain delivered concrete mixture temperature within the 
temperature range required by ACI 301. 
2. 
Do not use frozen materials or materials containing ice or snow.  Do not place concrete 
on frozen subgrade or on subgrade containing frozen materials. 
3. 
Do not use calcium chloride, salt, or other materials containing antifreeze agents or 
chemical accelerators unless otherwise specified and approved in mixture designs. 
G. 
Hot-Weather Placement:  Comply with ACI 301 and as follows: 
1. 
Maintain concrete temperature below 90 deg F (32 deg C) at time of placement.  Chilled 
mixing water or chopped ice may be used to control temperature, provided water 
equivalent of ice is calculated to total amount of mixing water.  Using liquid nitrogen to 
cool concrete is Contractor's option. 
2. 
Fog-spray forms, steel reinforcement, and subgrade just before placing concrete.  Keep 
subgrade uniformly moist without standing water, soft spots, or dry areas. 
3.10 
FINISHING FORMED SURFACES 
A. 
Rough-Formed Finish:  As-cast concrete texture imparted by form-facing material with tie holes 
and defects repaired and patched.  Remove fins and other projections that exceed specified 
limits on formed-surface irregularities. 
1. 
Apply to concrete surfaces not exposed to public view 
B. 
Smooth-Formed Finish:  As-cast concrete texture imparted by form-facing material, arranged in 
an orderly and symmetrical manner with a minimum of seams.  Repair and patch tie holes and 
defects.  Remove fins and other projections that exceed specified limits on formed-surface 
irregularities. 
1. 
Apply to concrete surfaces to receive a rubbed finish

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
16 
 
 
 
 
C. 
Rubbed Finish:  Apply the following to smooth-formed finished as-cast concrete where 
indicated: 
1. 
Smooth-Rubbed Finish:  Not later than one day after form removal, moisten concrete 
surfaces and rub with carborundum brick or another abrasive until producing a uniform 
color and texture.  Do not apply cement grout other than that created by the rubbing 
process. 
D. 
“Sand” or Acid Etch Finish: Dayton Superior Products Topcast 05 surface retarder finish. Refer 
to Manufacturer’s installation recommendations for vertical applications. 
E. 
Related Unformed Surfaces:  At tops of walls, horizontal offsets, and similar unformed surfaces 
adjacent to formed surfaces, strike off smooth and finish with a texture matching adjacent 
formed surfaces.  Continue final surface treatment of formed surfaces uniformly across adjacent 
unformed surfaces unless otherwise indicated. 
3.11 
FINISHING FLOORS AND SLABS 
A. 
General:  Comply with ACI 302.1R recommendations for screeding, restraightening, and 
finishing operations for concrete surfaces.  Do not wet concrete surfaces. 
B. 
Broom Finish:  Apply a broom finish to exterior concrete platforms, steps, ramps, and 
elsewhere as indicated. 
1. 
Immediately after float finishing, slightly roughen trafficked surface by brooming with 
fiber-bristle broom perpendicular to main traffic route.  Coordinate required final finish 
with Landscape Architect before application. 
3.12 
MISCELLANEOUS CONCRETE ITEMS 
A. 
Filling In:  Fill in holes and openings left in concrete structures after work of other trades is in 
place unless otherwise indicated.  Mix, place, and cure concrete, as specified, to blend with in-
place construction.  Provide other miscellaneous concrete filling indicated or required to 
complete the Work. 
B. 
Curbs:  Provide monolithic finish to interior curbs by stripping forms while concrete is still 
green and by steel-troweling surfaces to a hard, dense finish with corners, intersections, and 
terminations slightly rounded. 
C. 
Equipment Bases and Foundations: 
1. 
Coordinate sizes and locations of concrete bases with actual equipment provided. 
2. 
Construct concrete bases 6 inches (150 mm) high unless otherwise indicated; and extend 
base not less than 6 inches (150 mm) in each direction beyond the maximum dimensions 
of supported equipment unless otherwise indicated or unless required for seismic anchor 
support. 
3. 
Minimum Compressive Strength: 3500 psi (24.1 MPa) at 28 days.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
17 
 
 
 
 
4. 
Install dowel rods to connect concrete base to concrete floor.  Unless otherwise indicated, 
install dowel rods on 18-inch (450-mm) centers around the full perimeter of concrete 
base. 
5. 
For supported equipment, install epoxy-coated anchor bolts that extend through concrete 
base, and anchor into structural concrete substrate. 
6. 
Prior to pouring concrete, place and secure anchorage devices.  Use setting drawings, 
templates, diagrams, instructions, and directions furnished with items to be embedded. 
7. 
Cast anchor-bolt insert into bases.  Install anchor bolts to elevations required for proper 
attachment to supported equipment. 
3.13 
CONCRETE PROTECTING AND CURING 
A. 
General:  Protect freshly placed concrete from premature drying and excessive cold or hot 
temperatures.  Comply with ACI 306.1 for cold-weather protection and ACI 301 for hot-
weather protection during curing. 
B. 
Evaporation Retarder:  Apply evaporation retarder to unformed concrete surfaces if hot, dry, or 
windy conditions cause moisture loss approaching 0.2 lb/sq. ft. x h (1 kg/sq. m x h) before and 
during finishing operations.  Apply according to manufacturer's written instructions after 
placing, screeding, and bull floating or darbying concrete, but before float finishing. 
C. 
Formed Surfaces:  Cure formed concrete surfaces, including underside of beams, supported 
slabs, and other similar surfaces.  If forms remain during curing period, moist cure after 
loosening forms.  If removing forms before end of curing period, continue curing for the 
remainder of the curing period. 
D. 
Unformed Surfaces:  Begin curing immediately after finishing concrete.  Cure unformed 
surfaces, including floors and slabs, concrete floor toppings, and other surfaces. 
E. 
Cure concrete according to ACI 308.1, by one or a combination of the following methods: 
1. 
Moisture Curing:  Keep surfaces continuously moist for not less than seven days with the 
following materials: 
a. 
Water. 
b. 
Continuous water-fog spray. 
c. 
Absorptive cover, water saturated, and kept continuously wet.  Cover concrete 
surfaces and edges with 12-inch (300-mm) lap over adjacent absorptive covers. 
2. 
Moisture-Retaining-Cover Curing:  Cover concrete surfaces with moisture-retaining 
cover for curing concrete, placed in widest practicable width, with sides and ends lapped 
at least 12 inches (300 mm), and sealed by waterproof tape or adhesive.  Cure for not less 
than seven days.  Immediately repair any holes or tears during curing period using cover 
material and waterproof tape. 
a. 
Moisture cure or use moisture-retaining covers to cure concrete surfaces to receive 
floor coverings. 
b. 
Moisture cure or use moisture-retaining covers to cure concrete surfaces to receive 
penetrating liquid floor treatments.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
18 
 
 
 
 
c. 
Cure concrete surfaces to receive floor coverings with either a moisture-retaining 
cover or a curing compound that the manufacturer certifies will not interfere with 
bonding of floor covering used on Project. 
3. 
Curing Compound:  Apply uniformly in continuous operation by power spray or roller 
according to manufacturer's written instructions.  Recoat areas subjected to heavy rainfall 
within three hours after initial application.  Maintain continuity of coating and repair 
damage during curing period. 
a. 
Removal:  After curing period has elapsed, remove curing compound without 
damaging concrete surfaces by method recommended by curing compound 
manufacturer. 
3.14 
JOINT FILLING 
A. 
Prepare, clean, and install joint filler according to manufacturer's written instructions. 
B. 
Remove dirt, debris, saw cuttings, curing compounds, and sealers from joints; leave contact 
faces of joint clean and dry. 
C. 
Install semirigid joint filler full depth in saw-cut joints and at least 2 inches (50 mm) deep in 
formed joints.  Overfill joint and trim joint filler flush with top of joint after hardening. 
3.15 
CONCRETE SURFACE REPAIRS 
A. 
Defective Concrete:  Repair and patch defective areas when approved by Landscape Architect.  
Remove and replace concrete that cannot be repaired and patched to Landscape Architect's 
approval. 
B. 
Patching Mortar:  Mix dry-pack patching mortar, consisting of one part portland cement to two 
and one-half parts fine aggregate passing a No. 16 (1.18-mm) sieve, using only enough water 
for handling and placing. 
C. 
Repairing Formed Surfaces:  Surface defects include color and texture irregularities, cracks, 
spalls, air bubbles, honeycombs, rock pockets, fins and other projections on the surface, and 
stains and other discolorations that cannot be removed by cleaning. 
1. 
Immediately after form removal, cut out honeycombs, rock pockets, and voids more than 
1/2 inch (13 mm) in any dimension to solid concrete.  Limit cut depth to 3/4 inch (19 
mm).  Make edges of cuts perpendicular to concrete surface.  Clean, dampen with water, 
and brush-coat holes and voids with bonding agent.  Fill and compact with patching 
mortar before bonding agent has dried.  Fill form-tie voids with patching mortar or cone 
plugs secured in place with bonding agent. 
2. 
Repair defects on surfaces exposed to view by blending white portland cement and 
standard portland cement so that, when dry, patching mortar will match surrounding 
color.  Patch a test area at inconspicuous locations to verify mixture and color match 
before proceeding with patching.  Compact mortar in place and strike off slightly higher 
than surrounding surface.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
19 
 
 
 
 
3. 
Repair defects on concealed formed surfaces that affect concrete's durability and 
structural performance as determined by Architect. 
D. 
Repairing Unformed Surfaces:  Test unformed surfaces, such as floors and slabs, for finish and 
verify surface tolerances specified for each surface.  Correct low and high areas.  Test surfaces 
sloped to drain for trueness of slope and smoothness; use a sloped template. 
1. 
Repair finished surfaces containing defects.  Surface defects include spalls, popouts, 
honeycombs, rock pockets, crazing and cracks in excess of 0.01 inch (0.25 mm) wide or 
that penetrate to reinforcement or completely through unreinforced sections regardless of 
width, and other objectionable conditions. 
2. 
After concrete has cured at least 14 days, correct high areas by grinding. 
3. 
Correct localized low areas during or immediately after completing surface finishing 
operations by cutting out low areas and replacing with patching mortar.  Finish repaired 
areas to blend into adjacent concrete. 
4. 
Repair defective areas, except random cracks and single holes 1 inch (25 mm) or less in 
diameter, by cutting out and replacing with fresh concrete.  Remove defective areas with 
clean, square cuts and expose steel reinforcement with at least a 3/4-inch (19-mm) 
clearance all around.  Dampen concrete surfaces in contact with patching concrete and 
apply bonding agent.  Mix patching concrete of same materials and mixture as original 
concrete except without coarse aggregate.  Place, compact, and finish to blend with 
adjacent finished concrete.  Cure in same manner as adjacent concrete. 
5. 
Repair random cracks and single holes 1 inch (25 mm) or less in diameter with patching 
mortar.  Groove top of cracks and cut out holes to sound concrete and clean off dust, dirt, 
and loose particles.  Dampen cleaned concrete surfaces and apply bonding agent.  Place 
patching mortar before bonding agent has dried.  Compact patching mortar and finish to 
match adjacent concrete.  Keep patched area continuously moist for at least 72 hours. 
E. 
Perform structural repairs of concrete, subject to Landscape Architect's approval, using epoxy 
adhesive and patching mortar. 
F. 
Repair materials and installation not specified above may be used, subject to Architect's 
approval. 
3.16 
FIELD QUALITY CONTROL 
A. 
Testing and Inspecting:  Engage a qualified testing and inspecting agency to perform tests and 
inspections and to submit reports. 
B. 
Inspections: 
1. 
Steel reinforcement placement. 
2. 
Steel reinforcement welding. 
3. 
Headed bolts and studs. 
4. 
Verification of use of required design mixture. 
5. 
Concrete placement, including conveying and depositing. 
6. 
Curing procedures and maintenance of curing temperature. 
7. 
Verification of concrete strength before removal of shores and forms from beams and 
slabs.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
20 
 
 
 
 
C. 
Concrete Tests:  Testing of composite samples of fresh concrete obtained according to 
ASTM C 172 shall be performed according to the following requirements: 
1. 
Testing Frequency:  Obtain one composite sample for each day's pour of each concrete 
mixture exceeding 5 cu. yd. (4 cu. m), but less than 25 cu. yd. (19 cu. m), plus one set for 
each additional 50 cu. yd. (38 cu. m) or fraction thereof. 
a. 
When frequency of testing will provide fewer than five compressive-strength tests 
for each concrete mixture, testing shall be conducted from at least five randomly 
selected batches or from each batch if fewer than five are used. 
2. 
Slump:  ASTM C 143/C 143M; one test at point of placement for each composite sample, 
but not less than one test for each day's pour of each concrete mixture.  Perform 
additional tests when concrete consistency appears to change. 
3. 
Air Content:  ASTM C 231, pressure method, for normal-weight concrete; 
ASTM C 173/C 173M, volumetric method, for structural lightweight concrete; one test 
for each composite sample, but not less than one test for each day's pour of each concrete 
mixture. 
4. 
Concrete Temperature:  ASTM C 1064/C 1064M; one test hourly when air temperature is 
40 deg F (4.4 deg C) and below and when 80 deg F (27 deg C) and above, and one test 
for each composite sample. 
5. 
Compression Test Specimens:  ASTM C 31/C 31M. 
a. 
Cast and laboratory cure two sets of two standard cylinder specimens for each 
composite sample. 
b. 
Cast and field cure [two] sets of two standard cylinder specimens for each 
composite sample. 
6. 
Compressive-Strength Tests:  ASTM C 39/C 39M; test one set of two laboratory-cured 
specimens at 7 days and one set of two specimens at 28 days. 
a. 
Test one set of two field-cured specimens at 7 days and one set of two specimens 
at 28 days. 
b. 
A compressive-strength test shall be the average compressive strength from a set of 
two specimens obtained from same composite sample and tested at age indicated. 
7. 
When strength of field-cured cylinders is less than 85 percent of companion laboratory-
cured cylinders, Contractor shall evaluate operations and provide corrective procedures 
for protecting and curing in-place concrete. 
8. 
Strength of each concrete mixture will be satisfactory if every average of any three 
consecutive compressive-strength tests equals or exceeds specified compressive strength 
and no compressive-strength test value falls below specified compressive strength by 
more than 500 psi (3.4 MPa). 
9. 
Test results shall be reported in writing to Architect, concrete manufacturer, and 
Contractor within 48 hours of testing.  Reports of compressive-strength tests shall contain 
Project identification name and number, date of concrete placement, name of concrete 
testing and inspecting agency, location of concrete batch in Work, design compressive 
strength at 28 days, concrete mixture proportions and materials, compressive breaking 
strength, and type of break for both 7- and 28-day tests.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
21 
 
 
 
 
10. 
Nondestructive Testing:  Impact hammer, sonoscope, or other nondestructive device may 
be permitted by Architect but will not be used as sole basis for approval or rejection of 
concrete. 
11. 
Additional Tests:  Testing and inspecting agency shall make additional tests of concrete 
when test results indicate that slump, air entrainment, compressive strengths, or other 
requirements have not been met, as directed by Architect.  Testing and inspecting agency 
may conduct tests to determine adequacy of concrete by cored cylinders complying with 
ASTM C 42/C 42M or by other methods as directed by Architect. 
12. 
Additional testing and inspecting, at Contractor's expense, will be performed to determine 
compliance of replaced or additional work with specified requirements. 
13. 
Correct deficiencies in the Work that test reports and inspections indicate do not comply 
with the Contract Documents. 
END OF SECTION 033000

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
1 
 
 
 
 
SECTION 129300 - SITE FURNISHINGS 
PART 1 - GENERAL 
1.1 
RELATED DOCUMENTS 
A. 
Drawings and general provisions of the Contract, including General and Supplementary 
Conditions and Division 01 Specification Sections, apply to this Section. 
1.2 
SUMMARY 
A. 
Section Includes: 
1. 
Trash Receptacles 
2. 
Bike Rack 
3. 
Drinking Fountain with chiller 
4. 
Fitness Station 
5. 
Bench 
6. 
Picnic Table 
7. 
Picnic Table (ADA Accessible)  
B. 
Related Requirements: 
1. 
Section 033000 "Cast-in-Place Concrete" for installing pipe sleeves cast, installing 
anchor bolts cast, and formed voids in concrete footings. 
2. 
Section 312000 "Earth Moving" for excavation for installing concrete footings. 
1.3 
ACTION SUBMITTALS 
A. 
Product Data:  For each type of product. 
B. 
Samples:  For each exposed product and for each color and texture specified. 
C. 
Samples for Initial Selection:  For units with factory-applied finishes. 
D. 
Samples for Verification:  For each type of exposed finish, not less than 6-inch- (152-mm-) long 
linear components and 4-inch- (102-mm-) square sheet components. 
1. 
Include full-size Samples of bench, table (all types), movable chairs, concrete chairs, 
bicycle rack, trash receptacle, recycling receptacle. 
E. 
Product Schedule:  For site furnishings.  Use same designations indicated on Drawings. 
1.4 
CLOSEOUT SUBMITTALS 
A. 
Maintenance Data:  For site furnishings to include in maintenance manuals.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
2 
 
 
 
 
1.5 
MAINTENANCE MATERIAL SUBMITTALS 
A. 
Furnish extra materials that match products installed and that are packaged with protective 
covering for storage and identified with labels describing contents. 
1. 
Trash Receptacle Inner Containers:  Five full-size units for each size indicated 
2. 
Anchors. 
PART 2 - PRODUCTS 
A. 
See Materials Schedule L001 for all product information. This includes Benches, Trash and 
Recycling Receptacles, Bollards, Bike Racks, and other site furnishings as depicted on 
drawings.  
 
2.2 
MATERIALS 
A. 
Aluminum:  Alloy and temper recommended by aluminum producer and finisher for type of use 
and finish indicated; free of surface blemishes and complying with the following: 
1. 
Rolled or Cold-Finished Bars, Rods, and Wire:  ASTM B 211 (ASTM B 211M). 
2. 
Extruded Bars, Rods, Wire, Profiles, and Tubes:  ASTM B 221 (ASTM B 221M). 
3. 
Structural Pipe and Tube:  ASTM B 429/B 429M. 
4. 
Sheet and Plate:  ASTM B 209 (ASTM B 209M). 
5. 
Castings:  ASTM B 26/B 26M. 
B. 
Steel and Iron:  Free of surface blemishes and complying with the following: 
1. 
Plates, Shapes, and Bars:  ASTM A 36/A 36M. 
2. 
Steel Pipe:  Standard-weight steel pipe complying with ASTM A 53/A 53M, or electric-
resistance-welded pipe complying with ASTM A 135/A 135M. 
3. 
Tubing:  Cold-formed steel tubing complying with ASTM A 500/A 500M. 
4. 
Mechanical Tubing:  Cold-rolled, electric-resistance-welded carbon or alloy steel tubing 
complying with ASTM A 513, or steel tubing fabricated from steel complying with 
ASTM A 1011/A 1011M 
and 
complying 
with 
dimensional 
tolerances 
in 
ASTM A 500/A 500M; zinc coated internally and externally. 
5. 
Sheet:  Commercial steel sheet complying with ASTM A 1011/A 1011M. 
6. 
Perforated Metal:  From steel sheet not less than [0.075-inch (1.9-mm)] [0.090-inch (2.3-
mm)] [0.120-inch (3.0-mm)] nominal thickness; manufacturer's standard perforation 
pattern. 
7. 
Expanded Metal:  Carbon-steel sheets, deburred after expansion, and complying with 
ASTM F 1267. 
8. 
Malleable-Iron Castings:  ASTM A 47/A 47M, grade as recommended by fabricator for 
type of use intended. 
9. 
Gray-Iron Castings:  ASTM A 48/A 48M, Class 200.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
3 
 
 
 
 
C. 
Fiberglass:  Multiple laminations of glass-fiber-reinforced polyester resin with UV-light stable, 
colorfast, nonfading, weather- and stain-resistant, colored polyester gel coat, and with 
manufacturer's standard finish. 
D. 
Plastic:  Color impregnated, color and UV-light stabilized, and mold resistant. 
1. 
Polyethylene:  Fabricated from virgin plastic HDPE resin. 
2. 
Recycled Content of Polyethylene:  Postconsumer recycled content plus one-half of pre-
consumer recycled content not less than 50 percent. 
E. 
Anchors, Fasteners, Fittings, and Hardware: Manufacturer's standard, corrosion-resistant-coated 
or 
noncorrodible 
materials; 
commercial 
quality, tamperproof, 
vandal 
and 
theft 
resistant, concealed, recessed, and capped or plugged. 
1. 
Angle Anchors:  For inconspicuously bolting legs of site furnishings to on-grade 
substrate; extent as indicated 
F. 
Nonshrink, Nonmetallic Grout:  Premixed, factory-packaged, nonstaining, noncorrosive, 
nongaseous grout complying with ASTM C 1107/C 1107M; recommended in writing by 
manufacturer, for exterior applications. 
G. 
Erosion-Resistant Anchoring Cement:  Factory-packaged, nonshrink, nonstaining, hydraulic-
controlled expansion cement formulation for mixing with potable water at Project site to create 
pourable anchoring, patching, and grouting compound; resistant to erosion from water exposure 
without needing protection by a sealer or waterproof coating; recommended in writing by 
manufacturer, for exterior applications. 
H. 
Galvanizing:  Where indicated for steel and iron components, provide the following protective 
zinc coating applied to components after fabrication: 
1. 
Zinc-Coated Tubing:  External, zinc with organic overcoat, consisting of a minimum of 
0.9 oz./sq. ft. (0.27 kg/sq. m) of zinc after welding, a chromate conversion coating, and a 
clear, polymer film.  Internal, same as external or consisting of 81 percent zinc pigmented 
coating, not less than 0.3 mil (0.0076 mm) thick. 
2. 
Hot-Dip Galvanizing:  According to ASTM A 123/A 123M, ASTM A 153/A 153M, or 
ASTM A 924/A 924M. 
2.3 
FABRICATION 
A. 
Metal Components:  Form to required shapes and sizes with true, consistent curves, lines, and 
angles.  Separate metals from dissimilar materials to prevent electrolytic action. 
B. 
Welded Connections:  Weld connections continuously.  Weld solid members with full-length, 
full-penetration welds and hollow members with full-circumference welds.  At exposed 
connections, finish surfaces smooth and blended so no roughness or unevenness shows after 
finishing and welded surface matches contours of adjoining surfaces. 
C. 
Pipes and Tubes:  Form simple and compound curves by bending members in jigs to produce 
uniform curvature for each repetitive configuration required; maintain cylindrical cross section

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
4 
 
 
 
 
of member throughout entire bend without buckling, twisting, cracking, or otherwise deforming 
exposed surfaces of handrail and railing components. 
D. 
Preservative-Treated Wood Components:  Complete fabrication of treated items before 
treatment if possible.  If cut after treatment, apply field treatment complying with AWPA M4 to 
cut surfaces. 
E. 
Exposed Surfaces:  Polished, sanded, or otherwise finished; all surfaces smooth, free of burrs, 
barbs, splinters, and sharpness; all edges and ends rolled, rounded, or capped. 
F. 
Factory Assembly:  Assemble components in the factory to greatest extent possible to minimize 
field assembly.  Clearly mark units for assembly in the field. 
2.4 
GENERAL FINISH REQUIREMENTS 
A. 
Appearance of Finished Work:  Noticeable variations in same piece are not acceptable.  
Variations in appearance of adjoining components are acceptable if they are within the range of 
approved Samples and are assembled or installed to minimize contrast. 
2.5 
ALUMINUM FINISHES 
A. 
Baked-Enamel, Powder-Coat Finish:  Manufacturer's standard, baked, polyester, powder-coat 
finish complying with finish manufacturer's written instructions for surface preparation, 
including pretreatment, application, baking, and minimum dry film thickness. 
2.6 
STEEL AND GALVANIZED-STEEL FINISHES 
A. 
Baked-Enamel, Powder-Coat Finish:  Manufacturer's standard, baked, polyester, powder-coat 
finish complying with finish manufacturer's written instructions for surface preparation, 
including pretreatment, application, baking, and minimum dry film thickness. 
B. 
PVC Finish:  Manufacturer's standard, UV-light stabilized, mold-resistant, slip-resistant, matte-
textured, dipped or sprayed-on, PVC-plastisol finish, with flame retardant added; complying 
with coating manufacturer's written instructions for pretreatment, application, and minimum dry 
film thickness. 
2.7 
IRON FINISHES 
A. 
Baked-Enamel, Powder-Coat Finish:  Manufacturer's standard, baked, polyester, powder-coat 
finish complying with finish manufacturer's written instructions for surface preparation, 
including pretreatment, application, baking, and minimum dry film thickness.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
5 
 
 
 
 
PART 3 - EXECUTION 
3.1 
EXAMINATION 
A. 
Examine areas and conditions, with Installer present, for compliance with requirements for 
correct and level finished grade, mounting surfaces, installation tolerances, and other conditions 
affecting performance of the Work. 
B. 
Proceed with installation only after unsatisfactory conditions have been corrected. 
3.2 
INSTALLATION, GENERAL 
A. 
Comply with manufacturer's written installation instructions unless more stringent requirements 
are indicated.  Complete field assembly of site furnishings where required. 
B. 
Unless otherwise indicated, install site furnishings after landscaping and paving have been 
completed. 
C. 
Install site furnishings level, plumb, true, and securely anchored or positioned at locations 
indicated on Drawings. 
D. 
Post Setting:  Set cast-in support posts in concrete footing with smooth top, shaped to shed 
water.  Protect portion of posts above footing from concrete splatter.  Verify that posts are set 
plumb or at correct angle and are aligned and at correct height and spacing.  Hold posts in 
position during placement and finishing operations until concrete is sufficiently cured. 
E. 
Posts Set into Voids in Concrete:  Form or core-drill holes for installing posts in concrete to 
depth recommended in writing by manufacturer of site furnishings and 3/4 inch (19 mm) larger 
than OD of post.  Clean holes of loose material, insert posts, and fill annular space between post 
and concrete with nonshrink, nonmetallic grout or anchoring cement, mixed and placed to 
comply with anchoring material manufacturer's written instructions, with top smoothed and 
shaped to shed water. 
F. 
Pipe Sleeves:  Use steel pipe sleeves preset and anchored into concrete for installing posts.  
After posts have been inserted into sleeves, fill annular space between post and sleeve with 
nonshrink, nonmetallic grout or anchoring cement, mixed and placed to comply with 
anchoring material manufacturer's written instructions, with top smoothed and shaped to shed 
water. 
END OF SECTION 129300

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
1 
 
SECTION 311000 - SITE CLEARING 
PART 1 - GENERAL 
1.1 
RELATED DOCUMENTS 
A. 
Drawings and general provisions of the Contract, including General and Supplementary 
Conditions and Division 01 Specification Sections, apply to this Section. 
1.2 
SUMMARY 
A. 
Section Includes: 
1. 
Protecting existing vegetation to remain. 
2. 
Removing existing vegetation. 
3. 
Clearing and grubbing. 
4. 
Stripping and stockpiling topsoil. 
5. 
Removing above- and below-grade site improvements. 
6. 
Disconnecting, capping or sealing, and removing site utilities, abandoning site utilities in 
place. 
7. 
Temporary erosion- and sedimentation-control measures. 
1.3 
DEFINITIONS 
A. 
Subsoil:  All soil beneath the topsoil layer of the soil profile, and typified by the lack of organic 
matter and soil organisms. 
B. 
Surface Soil:  Soil that is present at the top layer of the existing soil profile at the Project site.  
In undisturbed areas, the surface soil is typically topsoil; but in disturbed areas such as urban 
environments, the surface soil can be subsoil. 
C. 
Topsoil:  Top layer of the soil profile consisting of existing native surface topsoil or existing in-
place surface soil and is the zone where plant roots grow. 
D. 
Vegetation:  Trees, shrubs, groundcovers, grass, and other plants. 
1.4 
MATERIAL OWNERSHIP 
A. 
Except for stripped topsoil and other materials indicated to be stockpiled or otherwise remain 
Owner's property, cleared materials shall become Contractor's property and shall be removed 
from Project site.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
2 
 
1.5 
INFORMATIONAL SUBMITTALS 
A. 
Existing Conditions:  Documentation of existing trees and plantings, adjoining construction, and 
site improvements that establishes preconstruction conditions that might be misconstrued as 
damage caused by site clearing. 
1. 
Use sufficiently detailed photographs or videotape. 
B. 
Record Drawings:  Identifying and accurately showing locations of capped utilities and other 
subsurface structural, electrical, and mechanical conditions. 
1.6 
PROJECT CONDITIONS 
A. 
Traffic:  Minimize interference with adjoining roads, streets, walks, and other adjacent occupied 
or used facilities during site-clearing operations. 
1. 
Do not close or obstruct streets, walks, or other adjacent occupied or used facilities 
without permission from Owner and authorities having jurisdiction. 
2. 
Provide alternate routes around closed or obstructed traffic ways if required by Owner or 
authorities having jurisdiction. 
B. 
Utility Locator Service:  Notify utility locator service for area where Project is located before 
site clearing. 
C. 
Do not commence site clearing operations until temporary erosion- and sedimentation-control 
measures are in place. 
D. 
Soil Stripping, Handling, and Stockpiling:  Perform only when the topsoil is dry or slightly 
moist. 
PART 2 - PRODUCTS 
2.1 
MATERIALS 
A. 
Satisfactory Soil Material:  Requirements for satisfactory soil material are specified in 
Section 312000 "Earth Moving." 
1. 
Obtain approved borrow soil material off-site when satisfactory soil material is not 
available on-site.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
3 
 
PART 3 - EXECUTION 
3.1 
PREPARATION 
A. 
Protect and maintain benchmarks and survey control points from disturbance during 
construction. 
B. 
Protect existing site improvements to remain from damage during construction. 
1. 
Restore damaged improvements to their original condition, as acceptable to Owner. 
3.2 
TEMPORARY EROSION AND SEDIMENTATION CONTROL 
A. 
Provide temporary erosion- and sedimentation-control measures to prevent soil erosion and 
discharge of soil-bearing water runoff or airborne dust to adjacent properties and walkways, 
according to erosion- and sedimentation-control Drawings and requirements of authorities 
having jurisdiction. 
B. 
Verify that flows of water redirected from construction areas or generated by construction 
activity do not enter or cross protection zones. 
C. 
Inspect, maintain, and repair erosion- and sedimentation-control measures during construction 
until permanent vegetation has been established. 
D. 
Remove erosion and sedimentation controls and restore and stabilize areas disturbed during 
removal. 
3.3 
EXISTING UTILITIES 
A. 
Owner will arrange for disconnecting and sealing indicated utilities that serve existing structures 
before site clearing, when requested by Contractor. 
1. 
Verify that utilities have been disconnected and capped before proceeding with site 
clearing. 
B. 
Locate, identify, disconnect, and seal or cap utilities indicated to be removed  or abandoned in 
place. 
1. 
Arrange with utility companies to shut off indicated utilities. 
2. 
Owner will arrange to shut off indicated utilities when requested by Contractor. 
C. 
Locate, identify, and disconnect utilities indicated to be abandoned in place.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
4 
 
D. 
Interrupting Existing Utilities:  Do not interrupt utilities serving facilities occupied by Owner or 
others unless permitted under the following conditions and then only after arranging to provide 
temporary utility services according to requirements indicated: 
1. 
Notify Architect not less than two days in advance of proposed utility interruptions. 
2. 
Do not proceed with utility interruptions without Architect's written permission. 
E. 
Excavate for and remove underground utilities indicated to be removed. 
3.4 
CLEARING AND GRUBBING 
A. 
Remove obstructions, trees, shrubs, and other vegetation to permit installation of new 
construction. 
1. 
Grind down stumps and remove roots, obstructions, and debris to a depth of 18 inches 
(450 mm) below exposed subgrade. 
2. 
Use only hand methods for grubbing within protection zones. 
3. 
Chip removed tree branches and dispose of off-site 
B. 
Fill depressions caused by clearing and grubbing operations with satisfactory soil material 
unless further excavation or earthwork is indicated. 
1. 
Place fill material in horizontal layers not exceeding a loose depth of 8 inches (200 mm), 
and compact each layer to a density equal to adjacent original ground. 
3.5 
TOPSOIL STRIPPING 
A. 
Remove sod and grass before stripping topsoil. 
B. 
Strip topsoil in a manner to prevent intermingling with underlying subsoil or other waste 
materials. 
1. 
Remove subsoil and nonsoil materials from topsoil, including clay lumps, gravel, and 
other objects more than 2 inches (50 mm) in diameter; trash, debris, weeds, roots, and 
other waste materials. 
C. 
Stockpile topsoil away from edge of excavations without intermixing with subsoil.  Grade and 
shape stockpiles to drain surface water.  Cover to prevent windblown dust and erosion by water. 
1. 
Limit height of topsoil stockpiles to 72 inches (1800 mm). 
2. 
Do not stockpile topsoil within protection zones. 
3. 
Dispose of surplus topsoil.  Surplus topsoil is that which exceeds quantity indicated to be 
stockpiled or reused. 
4. 
Stockpile surplus topsoil to allow for respreading deeper topsoil.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
5 
 
3.6 
SITE IMPROVEMENTS 
A. 
Remove existing above- and below-grade improvements as indicated and necessary to facilitate 
new construction. 
B. 
Remove slabs, paving, curbs, gutters, and aggregate base as indicated. 
1. 
Unless existing full-depth joints coincide with line of demolition, neatly saw-cut along 
line of existing pavement to remain before removing adjacent existing pavement.  Saw-
cut faces vertically. 
2. 
Paint cut ends of steel reinforcement in concrete to remain with two coats of antirust 
coating, following coating manufacturer's written instructions.  Keep paint off surfaces 
that will remain exposed. 
3.7 
DISPOSAL OF SURPLUS AND WASTE MATERIALS 
A. 
Remove surplus soil material, unsuitable topsoil, obstructions, demolished materials, and waste 
materials including trash and debris, and legally dispose of them off Owner's property. 
B. 
Separate recyclable materials produced during site clearing from other nonrecyclable materials.  
Store or stockpile without intermixing with other materials and transport them to recycling 
facilities.  Do not interfere with other Project work. 
END OF SECTION 311000

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
1 
 
SECTION 312000 - EARTH MOVING 
PART 1 - GENERAL 
1.1 
RELATED DOCUMENTS 
A. 
Drawings and general provisions of the Contract, including General and Supplementary 
Conditions and Division 01 Specification Sections, apply to this Section. 
1.2 
SUMMARY 
A. 
Section Includes: 
1. 
Preparing subgrades for slabs-on-grade, walks, turf and grasses and plants. 
2. 
Drainage course for concrete slabs-on-grade. 
3. 
Subbase course for concrete walks. 
4. 
Subsurface drainage backfill for walls and trenches. 
B. 
Related Sections: 
1. 
Section 033000 "Cast-in-Place Concrete" for granular course if placed over vapor 
retarder and beneath the slab-on-grade. 
2. 
Section 311000 "Site Clearing" for site stripping, grubbing, stripping and stockpiling 
topsoil, and removal of above- and below-grade improvements and utilities. 
3. 
Section 329200 "Turf and Grasses" for finish grading in turf and grass areas, including 
preparing and placing planting soil for turf areas. 
4. 
Section 329300 "Plants" for finish grading in planting areas and tree and shrub pit 
excavation and planting. 
1.3 
DEFINITIONS 
A. 
Backfill:  Soil material or controlled low-strength material used to fill an excavation. 
1. 
Initial Backfill:  Backfill placed beside and over pipe in a trench, including haunches to 
support sides of pipe. 
2. 
Final Backfill:  Backfill placed over initial backfill to fill a trench. 
B. 
Base Course:  Aggregate layer placed between the subbase course and hot-mix asphalt paving. 
C. 
Bedding Course:  Aggregate layer placed over the excavated subgrade in a trench before laying 
pipe. 
D. 
Borrow Soil:  Satisfactory soil imported from off-site for use as fill or backfill.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
2 
 
E. 
Drainage Course:  Aggregate layer supporting the slab-on-grade that also minimizes upward 
capillary flow of pore water. 
F. 
Excavation:  Removal of material encountered above subgrade elevations and to lines and 
dimensions indicated. 
1. 
Authorized Additional Excavation:  Excavation below subgrade elevations or beyond 
indicated lines and dimensions as directed by Architect.  Authorized additional 
excavation and replacement material will be paid for according to Contract provisions for 
changes in the Work. 
2. 
Bulk Excavation:  Excavation more than 10 feet (3 m) in width and more than 30 feet 
(9 m) in length. 
3. 
Unauthorized Excavation:  Excavation below subgrade elevations or beyond indicated 
lines and dimensions without direction by Architect.  Unauthorized excavation, as well as 
remedial work directed by Architect, shall be without additional compensation. 
G. 
Fill:  Soil materials used to raise existing grades. 
H. 
Rock:  Rock material in beds, ledges, unstratified masses, conglomerate deposits, and boulders 
of rock material 3/4 cu. yd. (0.57 cu. m) or more in volume that exceed a standard penetration 
resistance of 100 blows/2 inches (97 blows/50 mm) when tested by a geotechnical testing 
agency, according to ASTM D 1586. 
I. 
Structures:  Buildings, footings, foundations, retaining walls, slabs, tanks, curbs, mechanical 
and electrical appurtenances, or other man-made stationary features constructed above or below 
the ground surface. 
J. 
Subbase Course:  Aggregate layer placed between the subgrade and base course for hot-mix 
asphalt pavement, or aggregate layer placed between the subgrade and a cement concrete 
pavement or a cement concrete or hot-mix asphalt walk. 
K. 
Subgrade:  Uppermost surface of an excavation or the top surface of a fill or backfill 
immediately below subbase, drainage fill, drainage course, or topsoil materials. 
L. 
Utilities:  On-site underground pipes, conduits, ducts, and cables, as well as underground 
services within buildings. 
1.4 
ACTION SUBMITTALS 
A. 
Product Data:  For each type of the following manufactured products required: 
1. 
Geotextiles. 
2. 
Warning tapes. 
B. 
Samples for Verification:  For the following products, in sizes indicated below: 
1. 
Geotextile:  12 by 12 inches (300 by 300 mm).

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
3 
 
2. 
Warning Tape:  12 inches (300 mm) long; of each color. 
1.5 
INFORMATIONAL SUBMITTALS 
A. 
Qualification Data:  For qualified testing agency. 
B. 
Material Test Reports:  For each on-site and borrow soil material proposed for fill and backfill 
as follows: 
1. 
Classification according to ASTM D 2487. 
2. 
Laboratory compaction curve according to ASTM D 698 or ASTM D 1557. 
C. 
Preexcavation Photographs or Videotape:  Show existing conditions of adjoining construction 
and site improvements, including finish surfaces, that might be misconstrued as damage caused 
by earth moving operations.  Submit before earth moving begins. 
1.6 
QUALITY ASSURANCE 
A. 
Geotechnical Testing Agency Qualifications:  Qualified according to ASTM E 329 and 
ASTM D 3740 for testing indicated. 
B. 
Preexcavation Conference:  Conduct conference at Project site. 
1.7 
PROJECT CONDITIONS 
A. 
Traffic:  Minimize interference with adjoining roads, streets, walks, and other adjacent occupied 
or used facilities during earth moving operations. 
1. 
Do not close or obstruct streets, walks, or other adjacent occupied or used facilities 
without permission from Owner and authorities having jurisdiction. 
2. 
Provide alternate routes around closed or obstructed traffic ways if required by Owner or 
authorities having jurisdiction. 
B. 
Do not commence earth moving operations until temporary erosion- and sedimentation-control 
measures, specified in  Section 311000 "Site Clearing," are in place. 
PART 2 - PRODUCTS 
2.1 
SOIL MATERIALS 
A. 
General:  Provide borrow soil materials when sufficient satisfactory soil materials are not 
available from excavations.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
4 
 
B. 
Satisfactory Soils:  Soil Classification Groups GW, GP, GM, SW, SP, and SM according to 
ASTM D 2487, Groups A-1, A-2-4, A-2-5, and A-3 according to AASHTO M 145, or a 
combination of these groups; free of rock or gravel larger than 3 inches (75 mm) in any 
dimension, debris, waste, frozen materials, vegetation, and other deleterious matter. 
C. 
Unsatisfactory Soils:  Soil Classification Groups GC, SC, CL, ML, OL, CH, MH, OH, and PT 
according to ASTM D 2487, Groups A-2-6, A-2-7, A-4, A-5, A-6, and A-7 according to 
AASHTO M 145, or a combination of these groups. 
1. 
Unsatisfactory soils also include satisfactory soils not maintained within 2 percent of 
optimum moisture content at time of compaction. 
D. 
Subbase Material:  Naturally or artificially graded mixture of natural or crushed gravel, crushed 
stone, and natural or crushed sand; ASTM D 2940; with at least 90 percent passing a 1-1/2-inch 
(37.5-mm) sieve and not more than 12 percent passing a No. 200 (0.075-mm) sieve. 
E. 
Base Course:  Naturally or artificially graded mixture of natural or crushed gravel, crushed 
stone, and natural or crushed sand; ASTM D 2940; with at least 95 percent passing a 1-1/2-inch 
(37.5-mm) sieve and not more than 8 percent passing a No. 200 (0.075-mm) sieve. 
F. 
Engineered Fill:  Naturally or artificially graded mixture of natural or crushed gravel, crushed 
stone, and natural or crushed sand; ASTM D 2940; with at least 90 percent passing a 1-1/2-inch 
(37.5-mm) sieve and not more than 12 percent passing a No. 200 (0.075-mm) sieve. 
G. 
Bedding Course:  Naturally or artificially graded mixture of natural or crushed gravel, crushed 
stone, and natural or crushed sand; ASTM D 2940; except with 100 percent passing a 1-inch 
(25-mm) sieve and not more than 8 percent passing a No. 200 (0.075-mm) sieve. 
H. 
Drainage Course:  Narrowly graded mixture of washed crushed stone, or crushed or uncrushed 
gravel; ASTM D 448; coarse-aggregate grading Size 57; with 100 percent passing a 1-1/2-inch 
(37.5-mm) sieve and 0 to 5 percent passing a No. 8 (2.36-mm) sieve. 
I. 
Filter Material:  Narrowly graded mixture of natural or crushed gravel, or crushed stone and 
natural sand; ASTM D 448; coarse-aggregate grading Size 67; with 100 percent passing a 1-
inch (25-mm) sieve and 0 to 5 percent passing a No. 4 (4.75-mm) sieve. 
J. 
Sand:  ASTM C 33; fine aggregate. 
K. 
Impervious Fill:  Clayey gravel and sand mixture capable of compacting to a dense state. 
2.2 
GEOTEXTILES 
A. 
Subsurface Drainage Geotextile:  Nonwoven needle-punched geotextile, manufactured for 
subsurface drainage applications, made from polyolefins or polyesters; with elongation greater 
than 50 percent; complying with AASHTO M 288 and the following, measured per test 
methods referenced: 
1. 
Grab Tensile Strength:  157 lbf (700 N); ASTM D 4632.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
5 
 
2. 
Sewn Seam Strength:  142 lbf (630 N); ASTM D 4632. 
3. 
Tear Strength:  56 lbf (250 N); ASTM D 4533. 
4. 
Puncture Strength:  56 lbf (250 N); ASTM D 4833. 
5. 
Apparent Opening Size:  No. 40 (0.425-mm) sieve, maximum; ASTM D 4751. 
6. 
Permittivity:  0.5 per second, minimum; ASTM D 4491. 
7. 
UV Stability:  50 percent after 500 hours' exposure; ASTM D 4355. 
B. 
Separation Geotextile:  Woven geotextile fabric, manufactured for separation applications, 
made from polyolefins or polyesters; with elongation less than 50 percent; complying with 
AASHTO M 288 and the following, measured per test methods referenced: 
1. 
Grab Tensile Strength:  247 lbf (1100 N); ASTM D 4632. 
2. 
Sewn Seam Strength:  222 lbf (990 N); ASTM D 4632. 
3. 
Tear Strength:  90 lbf (400 N); ASTM D 4533. 
4. 
Puncture Strength:  90 lbf (400 N); ASTM D 4833. 
5. 
Apparent Opening Size:  No. 60 (0.250-mm) sieve, maximum; ASTM D 4751. 
6. 
Permittivity:  0.02 per second, minimum; ASTM D 4491. 
7. 
UV Stability:  50 percent after 500 hours' exposure; ASTM D 4355. 
C. 
Produce conventional-weight, controlled low-strength material with [80-psi (550-kPa)] 
compressive strength when tested according to ASTM C 495. 
2.3 
ACCESSORIES 
A. 
Warning Tape:  Acid- and alkali-resistant, polyethylene film warning tape manufactured for 
marking and identifying underground utilities, 6 inches (150 mm) wide and 4 mils (0.1 mm) 
thick, continuously inscribed with a description of the utility; colored as follows: 
1. 
Red:  Electric. 
2. 
Yellow:  Gas, oil, steam, and dangerous materials. 
3. 
Orange:  Telephone and other communications. 
4. 
Blue:  Water systems. 
5. 
Green:  Sewer systems. 
6. 
Purple: Reclaimed Water 
PART 3 - EXECUTION 
3.1 
PREPARATION 
A. 
Protect structures, utilities, sidewalks, pavements, and other facilities from damage caused by 
settlement, lateral movement, undermining, washout, and other hazards created by earth moving 
operations. 
B. 
Protect and maintain erosion and sedimentation controls during earth moving operations.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
6 
 
C. 
Protect subgrades and foundation soils from freezing temperatures and frost.  Remove 
temporary protection before placing subsequent materials. 
3.2 
DEWATERING 
A. 
Prevent surface water and ground water from entering excavations, from ponding on prepared 
subgrades, and from flooding Project site and surrounding area. 
B. 
Protect subgrades from softening, undermining, washout, and damage by rain or water 
accumulation. 
1. 
Reroute surface water runoff away from excavated areas.  Do not allow water to 
accumulate in excavations.  Do not use excavated trenches as temporary drainage ditches. 
3.3 
EXPLOSIVES 
A. 
Explosives:  Do not use explosives. 
3.4 
EXCAVATION, GENERAL 
A. 
Classified Excavation:  Excavate to subgrade elevations.  Material to be excavated will be 
classified as earth and rock.  Do not excavate rock until it has been classified and cross 
sectioned by Architect.  The Contract Sum will be adjusted for rock excavation according to 
unit prices included in the Contract Documents.  Changes in the Contract Time may be 
authorized for rock excavation. 
1. 
Earth excavation includes excavating pavements and obstructions visible on surface; 
underground structures, utilities, and other items indicated to be removed; together with 
soil, boulders, and other materials not classified as rock or unauthorized excavation. 
a. 
Intermittent drilling; blasting, if permitted; ram hammering; or ripping of material 
not classified as rock excavation is earth excavation. 
2. 
Rock excavation includes removal and disposal of rock.  Remove rock to lines and 
subgrade elevations indicated to permit installation of permanent construction without 
exceeding the following dimensions: 
a. 
24 inches (600 mm) outside of concrete forms other than at footings. 
b. 
12 inches (300 mm) outside of concrete forms at footings. 
c. 
6 inches (150 mm) outside of minimum required dimensions of concrete cast 
against grade. 
d. 
Outside dimensions of concrete walls indicated to be cast against rock without 
forms or exterior waterproofing treatments. 
e. 
6 inches (150 mm) beneath bottom of concrete slabs-on-grade.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
7 
 
f. 
6 inches (150 mm) beneath pipe in trenches, and the greater of [24 inches (600 
mm) wider than pipe or 42 inches (1065 mm) wide. 
3.5 
EXCAVATION FOR STRUCTURES 
A. 
Excavate to indicated elevations and dimensions within a tolerance of plus or minus 1 inch (25 
mm).  If applicable, extend excavations a sufficient distance from structures for placing and 
removing concrete formwork, for installing services and other construction, and for inspections. 
1. 
Excavations for Footings and Foundations:  Do not disturb bottom of excavation.  
Excavate by hand to final grade just before placing concrete reinforcement.  Trim 
bottoms to required lines and grades to leave solid base to receive other work. 
2. 
Excavation for Underground Tanks, Basins, and Mechanical or Electrical Utility 
Structures:  Excavate to elevations and dimensions indicated within a tolerance of plus or 
minus 1 inch (25 mm).  Do not disturb bottom of excavations intended as bearing 
surfaces. 
3.6 
EXCAVATION FOR WALKS AND PAVEMENTS 
A. 
Excavate surfaces under walks and pavements to indicated lines, cross sections, elevations, and 
subgrades. 
3.7 
EXCAVATION FOR UTILITY TRENCHES 
A. 
Excavate trenches to indicated gradients, lines, depths, and elevations. 
1. 
Beyond building perimeter, excavate trenches to allow installation of top of pipe below 
frost line. 
B. 
Excavate trenches to uniform widths to provide the following clearance on each side of pipe or 
conduit.  Excavate trench walls vertically from trench bottom to 12 inches (300 mm) higher 
than top of pipe or conduit unless otherwise indicated. 
1. 
Clearance:  12 inches (300 mm) each side of pipe or conduit. 
C. 
Trench Bottoms:  Excavate and shape trench bottoms to provide uniform bearing and support of 
pipes and conduit.  Shape subgrade to provide continuous support for bells, joints, and barrels of 
pipes and for joints, fittings, and bodies of conduits.  Remove projecting stones and sharp 
objects along trench subgrade. 
1. 
For pipes and conduit less than 6 inches (150 mm) in nominal diameter, hand-excavate 
trench bottoms and support pipe and conduit on an undisturbed subgrade.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
8 
 
2. 
For pipes and conduit 6 inches (150 mm) or larger in nominal diameter, shape bottom of 
trench to support bottom 90 degrees of pipe or conduit circumference.  Fill depressions 
with tamped sand backfill. 
3. 
For flat-bottomed, multiple-duct conduit units, hand-excavate trench bottoms and support 
conduit on an undisturbed subgrade. 
4. 
Excavate trenches 6 inches (150 mm) deeper than elevation required in rock or other 
unyielding bearing material to allow for bedding course. 
D. 
Trench Bottoms:  Excavate trenches 4 inches (100 mm) deeper than bottom of pipe and conduit 
elevations to allow for bedding course.  Hand-excavate deeper for bells of pipe. 
1. 
Excavate trenches 6 inches (150 mm) deeper than elevation required in rock or other 
unyielding bearing material to allow for bedding course. 
3.8 
SUBGRADE INSPECTION 
A. 
Notify Architect when excavations have reached required subgrade. 
B. 
If Architect determines that unsatisfactory soil is present, continue excavation and replace with 
compacted backfill or fill material as directed. 
C. 
Proof-roll subgrade below the building slabs and pavements with a pneumatic-tired and loaded 
10-wheel, tandem-axle dump truck weighing not less than 15 tons (13.6 tonnes) to identify soft 
pockets and areas of excess yielding.  Do not proof-roll wet or saturated subgrades. 
1. 
Completely proof-roll subgrade in one direction repeating proof-rolling in direction 
perpendicular to first direction.  Limit vehicle speed to 3 mph (5 km/h). 
2. 
Excavate soft spots, unsatisfactory soils, and areas of excessive pumping or rutting, as 
determined by Architect, and replace with compacted backfill or fill as directed. 
D. 
Authorized additional excavation and replacement material will be paid for according to 
Contract provisions for changes in the Work. 
E. 
Reconstruct subgrades damaged by freezing temperatures, frost, rain, accumulated water, or 
construction activities, as directed by Architect, without additional compensation. 
3.9 
UNAUTHORIZED EXCAVATION 
A. 
Fill unauthorized excavation under foundations or wall footings by extending bottom elevation 
of concrete foundation or footing to excavation bottom, without altering top elevation.  Lean 
concrete fill, with 28-day compressive strength of 2500 psi (17.2 MPa), may be used when 
approved by Architect.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
9 
 
1. 
Fill unauthorized excavations under other construction, pipe, or conduit as directed by 
Architect. 
3.10 
STORAGE OF SOIL MATERIALS 
A. 
Stockpile borrow soil materials and excavated satisfactory soil materials without intermixing.  
Place, grade, and shape stockpiles to drain surface water.  Cover to prevent windblown dust. 
1. 
Stockpile soil materials away from edge of excavations.  Do not store within drip line of 
remaining trees. 
3.11 
BACKFILL 
A. 
Place and compact backfill in excavations promptly, but not before completing the following: 
1. 
Construction below finish grade including, where applicable, subdrainage, dampproofing, 
waterproofing, and perimeter insulation. 
2. 
Surveying locations of underground utilities for Record Documents. 
3. 
Testing and inspecting underground utilities. 
4. 
Removing concrete formwork. 
5. 
Removing trash and debris. 
6. 
Removing temporary shoring and bracing, and sheeting. 
7. 
Installing permanent or temporary horizontal bracing on horizontally supported walls. 
B. 
Place backfill on subgrades free of mud, frost, snow, or ice. 
3.12 
UTILITY TRENCH BACKFILL 
A. 
Place backfill on subgrades free of mud, frost, snow, or ice. 
B. 
Place and compact bedding course on trench bottoms and where indicated.  Shape bedding 
course to provide continuous support for bells, joints, and barrels of pipes and for joints, 
fittings, and bodies of conduits. 
C. 
Trenches under Footings:  Backfill trenches excavated under footings and within 18 inches (450 
mm) of bottom of footings with satisfactory soil; fill with concrete to elevation of bottom of 
footings.  Concrete is specified in Section 033000 "Cast-in-Place Concrete" 
D. 
Trenches under Roadways:  Provide 4-inch thick, concrete-base slab support for piping or 
conduit less than 30 inches below surface of roadways.  After installing and testing, completely 
encase piping or conduit in a minimum of 4 inches of concrete before backfilling or placing 
roadway subbase course.  Concrete is specified in Section 033000 "Cast-in-Place Concrete" 
E. 
Backfill voids with satisfactory soil while removing shoring and bracing.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
10 
 
F. 
Place and compact initial backfill of subbase material , free of particles larger than 1 inch in any 
dimension, to a height of 12 inches (300 mm) over the pipe or conduit. 
1. 
Carefully compact initial backfill under pipe haunches and compact evenly up on both 
sides and along the full length of piping or conduit to avoid damage or displacement of 
piping or conduit.  Coordinate backfilling with utilities testing. 
G. 
Controlled Low-Strength Material:  Place initial backfill of controlled low-strength material to a 
height of 12 inches (300 mm) over the pipe or conduit.  Coordinate backfilling with utilities 
testing. 
H. 
Place and compact final backfill of satisfactory soil to final subgrade elevation. 
I. 
Install warning tape directly above utilities, 12 inches (300 mm) below finished grade, except 6 
inches (150 mm) below subgrade under pavements and slabs. 
3.13 
SOIL FILL 
A. 
Plow, scarify, bench, or break up sloped surfaces steeper than 1 vertical to 4 horizontal so fill 
material will bond with existing material. 
B. 
Place and compact fill material in layers to required elevations as follows: 
1. 
Under grass and planted areas, use satisfactory soil material. 
2. 
Under walks and pavements, use satisfactory soil material. 
3. 
Under steps and ramps, use engineered fill. 
4. 
Under building slabs, use engineered fill. 
5. 
Under footings and foundations, use engineered fill. 
C. 
Place soil fill on subgrades free of mud, frost, snow, or ice. 
3.14 
SOIL MOISTURE CONTROL 
A. 
Uniformly moisten or aerate subgrade and each subsequent fill or backfill soil layer before 
compaction to within 2 percent of optimum moisture content. 
1. 
Do not place backfill or fill soil material on surfaces that are muddy, frozen, or contain 
frost or ice. 
2. 
Remove and replace, or scarify and air dry, otherwise satisfactory soil material that 
exceeds optimum moisture content by 2 percent and is too wet to compact to specified 
dry unit weight.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
11 
 
3.15 
COMPACTION OF SOIL BACKFILLS AND FILLS 
A. 
Place backfill and fill soil materials in layers not more than 8 inches in loose depth for material 
compacted by heavy compaction equipment, and not more than 4 inches in loose depth for 
material compacted by hand-operated tampers. 
B. 
Place backfill and fill soil materials evenly on all sides of structures to required elevations, and 
uniformly along the full length of each structure. 
C. 
Compact soil materials to not less than the following percentages of maximum dry unit weight 
according to [ASTM D 698] [ASTM D 1557]: 
1. 
Under structures, building slabs, steps, and pavements, scarify and recompact top 12 
inches (300 mm) of existing subgrade and each layer of backfill or fill soil material at 
[95] percent. 
2. 
Under walkways, scarify and recompact top 6 inches below subgrade and compact each 
layer of backfill or fill soil material at [92] percent. 
3. 
Under turf or unpaved areas, scarify and recompact top 6 inches below subgrade and 
compact each layer of backfill or fill soil material at [85] percent. 
4. 
For utility trenches, compact each layer of initial and final backfill soil material at [85] 
percent. 
3.16 
GRADING 
A. 
General:  Uniformly grade areas to a smooth surface, free of irregular surface changes.  Comply 
with compaction requirements and grade to cross sections, lines, and elevations indicated. 
1. 
Provide a smooth transition between adjacent existing grades and new grades. 
2. 
Cut out soft spots, fill low spots, and trim high spots to comply with required surface 
tolerances. 
B. 
Site Rough Grading:  Slope grades to direct water away from buildings and to prevent ponding.  
Finish subgrades to required elevations within the following tolerances: 
1. 
Turf or Unpaved Areas:  Plus or minus 1 inch  
2. 
Walks:  Plus or minus 1 inch  
3. 
Pavements:  Plus or minus 1/2 inch  
C. 
Grading inside Building Lines:  Finish subgrade to a tolerance of 1/2 inch (when tested with a 
10-foot (3-m) straightedge. 
3.17 
SUBSURFACE DRAINAGE 
A. 
Subdrainage Pipe:  Specified in Section 334600 "Subdrainage." 
B. 
Subsurface Drain:  Place subsurface drainage geotextile around perimeter of subdrainage trench.  
Place a 6-inch (150-mm) course of filter material on subsurface drainage geotextile to support

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
12 
 
subdrainage pipe.  Encase subdrainage pipe in a minimum of 12 inches (300 mm) of filter 
material, placed in compacted layers 6 inches (150 mm) thick, and wrap in subsurface drainage 
geotextile, overlapping sides and ends at least 6 inches (150 mm). 
1. 
Compact each filter material layer to 85 percent of maximum dry unit weight according 
to ASTM D 698 with a minimum of two passes of a plate-type vibratory compactor. 
C. 
Drainage Backfill:  Place and compact filter material over subsurface drain, in width indicated, 
to within 12 inches (300 mm) of final subgrade, in compacted layers 6 inches (150 mm) thick.  
Overlay drainage backfill with one layer of subsurface drainage geotextile, overlapping sides 
and ends at least 6 inches (150 mm). 
1. 
Compact each filter material layer to 85 percent of maximum dry unit weight according 
to ASTM D 698 with a minimum of two passes of a plate-type vibratory compactor. 
2. 
Place and compact impervious fill over drainage backfill in 6-inch thick compacted layers 
to final subgrade. 
3.18 
SUBBASE AND BASE COURSES UNDER PAVEMENTS AND WALKS 
A. 
Place subbase course and base course on subgrades free of mud, frost, snow, or ice. 
B. 
On prepared subgrade, place subbase course and base course under pavements and walks as 
follows: 
1. 
Install separation geotextile on prepared subgrade according to manufacturer's written 
instructions, overlapping sides and ends. 
2. 
Place base course material over subbase course under hot-mix asphalt pavement. 
3. 
Shape subbase course and base course to required crown elevations and cross-slope 
grades. 
4. 
Place subbase course and base course 6 inches or less in compacted thickness in a single 
layer. 
5. 
Place subbase course and base course that exceeds 6 inches in compacted thickness in 
layers of equal thickness, with no compacted layer more than 6 inches thick or less than 3 
inches thick. 
6. 
Compact subbase course and base course at optimum moisture content to required grades, 
lines, cross sections, and thickness to not less than [95] percent of maximum dry unit 
weight according to [ASTM D 698] [ASTM D 1557]. 
C. 
Pavement Shoulders:  Place shoulders along edges of subbase course and base course to prevent 
lateral movement.  Construct shoulders, at least 12 inches wide, of satisfactory soil materials 
and compact simultaneously with each subbase and base layer to not less than 95 percent of 
maximum dry unit weight according to [ASTM D 698] [ASTM D 1557]. 
3.19 
DRAINAGE COURSE UNDER CONCRETE SLABS-ON-GRADE 
A. 
Place drainage course on subgrades free of mud, frost, snow, or ice.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
13 
 
B. 
On prepared subgrade, place and compact drainage course under cast-in-place concrete slabs-
on-grade as follows: 
1. 
Install subdrainage geotextile on prepared subgrade according to manufacturer's written 
instructions, overlapping sides and ends. 
2. 
Place drainage course 6 inches (150 mm) or less in compacted thickness in a single layer. 
3. 
Place drainage course that exceeds 6 inches (150 mm) in compacted thickness in layers of 
equal thickness, with no compacted layer more than 6 inches (150 mm) thick or less than 
3 inches (75 mm) thick. 
4. 
Compact each layer of drainage course to required cross sections and thicknesses to not 
less than 95  percent of maximum dry unit weight according to ASTM D 698. 
3.20 
FIELD QUALITY CONTROL 
A. 
Special Inspections:  Owner will engage a qualified special inspector to perform the following 
special inspections: 
1. 
Determine prior to placement of fill that site has been prepared in compliance with 
requirements. 
2. 
Determine that fill material and maximum lift thickness comply with requirements. 
3. 
Determine, at the required frequency, that in-place density of compacted fill complies 
with requirements. 
B. 
Testing Agency:  Owner will engage a qualified geotechnical engineering testing agency to 
perform tests and inspections. 
C. 
Allow testing agency to inspect and test subgrades and each fill or backfill layer.  Proceed with 
subsequent earth moving only after test results for previously completed work comply with 
requirements. 
D. 
Footing Subgrade:  At footing subgrades, at least one test of each soil stratum will be performed 
to verify design bearing capacities.  Subsequent verification and approval of other footing 
subgrades may be based on a visual comparison of subgrade with tested subgrade when 
approved by Architect. 
E. 
Testing agency will test compaction of soils in place according to ASTM D 1556, 
ASTM D 2167, ASTM D 2922, and ASTM D 2937, as applicable.  Tests will be performed at 
the following locations and frequencies: 
1. 
Paved and Building Slab Areas:  At subgrade and at each compacted fill and backfill 
layer, at least one test for every 2000 sq. ft. or less of paved area or building slab, but in 
no case fewer than three tests. 
2. 
Foundation Wall Backfill:  At each compacted backfill layer, at least one test for every 
100 feet or less of wall length, but no fewer than two tests. 
3. 
Trench Backfill:  At each compacted initial and final backfill layer, at least one test for 
every 150 feet or less of trench length, but no fewer than two tests.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
14 
 
F. 
When testing agency reports that subgrades, fills, or backfills have not achieved degree of 
compaction specified, scarify and moisten or aerate, or remove and replace soil materials to 
depth required; recompact and retest until specified compaction is obtained. 
3.21 
PROTECTION 
A. 
Protecting Graded Areas:  Protect newly graded areas from traffic, freezing, and erosion.  Keep 
free of trash and debris. 
B. 
Repair and reestablish grades to specified tolerances where completed or partially completed 
surfaces become eroded, rutted, settled, or where they lose compaction due to subsequent 
construction operations or weather conditions. 
1. 
Scarify or remove and replace soil material to depth as directed by Architect; reshape and 
recompact. 
C. 
Where settling occurs before Project correction period elapses, remove finished surfacing, 
backfill with additional soil material, compact, and reconstruct surfacing. 
1. 
Restore appearance, quality, and condition of finished surfacing to match adjacent work, 
and eliminate evidence of restoration to greatest extent possible. 
3.22 
DISPOSAL OF SURPLUS AND WASTE MATERIALS 
A. 
Remove surplus satisfactory soil and waste materials, including unsatisfactory soil, trash, and 
debris, and legally dispose of them off Owner's property. 
B. 
Transport surplus satisfactory soil to designated storage areas on Owner's property.  Stockpile or 
spread soil as directed by Architect. 
1. 
Remove waste materials, including unsatisfactory soil, trash, and debris, and legally 
dispose of them off Owner's property. 
END OF SECTION 312000

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
1 
 
 
 
 
SECTION 321313 - CONCRETE PAVING 
PART 1 - GENERAL 
1.1 
RELATED DOCUMENTS 
A. 
Drawings and general provisions of the Contract, including General and Supplementary 
Conditions and Division 01 Specification Sections, apply to this Section. 
1.2 
SUMMARY 
A. 
Section Includes: 
1. 
Walks. 
B. 
Related Sections: 
1. 
Section 033000 "Cast-in-Place Concrete" for general building applications of concrete. 
2. 
Section 321316 "Decorative Concrete Paving" for color and finished concrete other than 
detectable warnings. 
3. 
Section 321373 "Concrete Paving Joint Sealants" for joint sealants in expansion and 
contraction joints within concrete paving and in joints between concrete paving and 
asphalt paving or adjacent construction. 
1.3 
DEFINITIONS 
A. 
Cementitious Materials:  Portland cement alone or in combination with one or more of blended 
hydraulic cement, fly ash and other pozzolans, and ground granulated blast-furnace slag. 
1.4 
ACTION SUBMITTALS 
A. 
Product Data:  For each type of product indicated. 
B. 
Samples for Verification:  For each type of product or exposed finish, prepared as Samples of 
size indicated below: 
1. 
Medium Sandblast Finish: 5’ x 5’ in size of each type of sand blast finish, indicating 
materials and methods used to produce the sand blast finishes. 
C. 
Other Action Submittals: 
1. 
Design Mixtures:  For each concrete paving mixture.  Include alternate design mixtures 
when characteristics of materials, Project conditions, weather, test results, or other 
circumstances warrant adjustments.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
2 
 
 
 
 
1.5 
INFORMATIONAL SUBMITTALS 
A. 
Qualification Data:  For qualified ready-mix concrete manufacturer and testing agency. 
B. 
Material Certificates:  For the following, from manufacturer: 
1. 
Cementitious materials. 
2. 
Steel reinforcement and reinforcement accessories. 
3. 
Fiber reinforcement. 
4. 
Admixtures. 
5. 
Curing compounds. 
6. 
Applied finish materials. 
7. 
Bonding agent or epoxy adhesive. 
8. 
Joint fillers. 
C. 
Material Test Reports:  For each of the following: 
1. 
Aggregates.  Include service-record data indicating absence of deleterious expansion of 
concrete due to alkali-aggregate reactivity. 
D. 
Field quality-control reports. 
1.6 
QUALITY ASSURANCE 
A. 
Detectable Warning Installer Qualifications:  An employer of workers trained and approved by 
manufacturer of stamped concrete paving systems. 
B. 
Ready-Mix-Concrete Manufacturer Qualifications:  A firm experienced in manufacturing ready-
mixed concrete products and that complies with ASTM C 94/C 94M requirements for 
production facilities and equipment. 
1. 
Manufacturer certified according to NRMCA's "Certification of Ready Mixed Concrete 
Production Facilities" (Quality Control Manual - Section 3, "Plant Certification 
Checklist"). 
C. 
Testing Agency Qualifications:  Qualified according to ASTM C 1077 and ASTM E 329 for 
testing indicated. 
1. 
Personnel conducting field tests shall be qualified as ACI Concrete Field Testing 
Technician, Grade 1, according to ACI CP-1 or an equivalent certification program. 
D. 
Concrete Testing Service:  Engage a qualified testing agency to perform material evaluation 
tests and to design concrete mixtures. 
E. 
ACI Publications:  Comply with ACI 301 (ACI 301M) unless otherwise indicated. 
F. 
Mockups:  Build mockups to verify selections made under sample submittals and to 
demonstrate aesthetic effects and set quality standards for materials and execution.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
3 
 
 
 
 
1. 
Build mockups of full-thickness sections of concrete paving to demonstrate typical joints; 
surface finish, texture, and color; curing; and standard of workmanship. 
2. 
Build mockups of concrete paving in the location and of the size indicated or, if not 
indicated, build mockups where directed by Architect and not less than 96 inches (2400 
mm) by 96 inches (2400 mm). 
3. 
Approval of mockups does not constitute approval of deviations from the Contract 
Documents contained in mockups unless Architect specifically approves such deviations 
in writing. 
4. 
Approved mockups may become part of the completed Work if undisturbed at time of 
Substantial Completion. 
G. 
Preinstallation Conference:  Conduct conference at Project Site. 
1. 
Review methods and procedures related to concrete paving, including but not limited to, 
the following: 
a. 
Concrete mixture design. 
b. 
Quality control of concrete materials and concrete paving construction practices. 
2. 
Require representatives of each entity directly concerned with concrete paving to attend, 
including the following: 
a. 
Contractor's superintendent. 
b. 
Independent testing agency responsible for concrete design mixtures. 
c. 
Ready-mix concrete manufacturer. 
d. 
Concrete paving subcontractor. 
1.7 
PROJECT CONDITIONS 
A. 
Traffic Control:  Maintain access for vehicular and pedestrian traffic as required for other 
construction activities. 
PART 2 - PRODUCTS 
2.1 
FORMS 
A. 
Form Materials:  Plywood, metal, metal-framed plywood, or other approved panel-type 
materials to provide full-depth, continuous, straight, and smooth exposed surfaces. 
1. 
Use flexible or uniformly curved forms for curves with a radius of 100 feet (30.5 m) or 
less.  Do not use notched and bent forms. 
B. 
Form-Release Agent:  Commercially formulated form-release agent that will not bond with, 
stain, or adversely affect concrete surfaces and that will not impair subsequent treatments of 
concrete surfaces.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
4 
 
 
 
 
2.2 
STEEL REINFORCEMENT 
A. 
Plain-Steel Welded Wire Reinforcement:  ASTM A 185/A 185M, fabricated from galvanized-
steel wire into flat sheets. 
B. 
Epoxy-Coated Welded Wire Reinforcement:  ASTM A 884/A 884M, Class A, plain steel. 
C. 
Reinforcing Bars:  ASTM A 615/A 615M, Grade 60 (Grade 420); deformed. 
D. 
Galvanized Reinforcing Bars:  ASTM A 767/A 767M, Class II zinc coated, hot-dip galvanized 
after fabrication and bending; with ASTM A 615/A 615M, Grade 60 (Grade 420) deformed 
bars. 
E. 
Epoxy-Coated Reinforcing Bars:  ASTM A 775/A 775M or ASTM A 934/A 934M; with 
ASTM A 615/A 615M, Grade 60 (Grade 420) deformed bars. 
F. 
Plain-Steel Wire:  ASTM A 82/A 82M, galvanized. 
G. 
Epoxy-Coated-Steel Wire:  ASTM A 884/A 884M, Class A coated, plain. 
H. 
Joint Dowel Bars:  ASTM A 615/A 615M, Grade 60 (Grade 420) plain-steel bars[; zinc coated 
(galvanized) after fabrication according to ASTM A 767/A 767M, Class I coating].  Cut bars 
true to length with ends square and free of burrs. 
I. 
Epoxy-Coated, Joint Dowel Bars:  ASTM A 775/A 775M; with ASTM A 615/A 615M, 
Grade 60 (Grade 420), plain-steel bars. 
J. 
Tie Bars:  ASTM A 615/A 615M, Grade 60 (Grade 420), deformed. 
K. 
Bar Supports:  Bolsters, chairs, spacers, and other devices for spacing, supporting, and fastening 
reinforcing bars, welded wire reinforcement, and dowels in place.  Manufacture bar supports 
according to CRSI's "Manual of Standard Practice" from steel wire, plastic, or precast concrete 
of greater compressive strength than concrete specified, and as follows: 
1. 
Equip wire bar supports with sand plates or horizontal runners where base material will 
not support chair legs. 
2. 
For epoxy-coated reinforcement, use epoxy-coated or other dielectric-polymer-coated 
wire bar supports. 
L. 
Epoxy Repair Coating:  Liquid, two-part, epoxy repair coating, compatible with epoxy coating 
on reinforcement. 
M. 
Zinc Repair Material:  ASTM A 780. 
2.3 
CONCRETE MATERIALS 
A. 
Cementitious Material:  Use the following cementitious materials, of same type, brand, and 
source throughout Project: 
1. 
Portland Cement:  ASTM C 150, Type II Supplement with the following:

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
5 
 
 
 
 
a. 
Fly Ash:  ASTM C 618, 
b. 
Ground Granulated Blast-Furnace Slag:  ASTM C 989, Grade 100 or 120. 
B. 
Silica Fume:  ASTM C 1240, amorphous silica. 
C. 
Normal-Weight Aggregates:  ASTM C 33, coarse aggregate or better, graded.  Provide 
aggregates from a single source[ with documented service record data of at least 10 years' 
satisfactory service in similar applications and service conditions using similar aggregates and 
cementitious materials]. 
1. 
Maximum Coarse-Aggregate Size: 3/4 inch (19 mm) nominal. 
D. 
Lightweight Aggregate:  ASTM C 330, 3/8-inch (10-mm) nominal maximum aggregate size. 
E. 
Water:  ASTM C 94/C 94M and potable. 
F. 
Color Pigment:  See Decorative Concrete Spec Section 
2.4 
FIBER REINFORCEMENT 
A. 
Synthetic Fiber: Monofilament polypropylene fibers engineered and designed for use in 
concrete paving, complying with ASTM C 1116/C 1116M, Type III, 1/2 to 1-1/2 inches (13 to 
38 mm) long. 
1. 
Products:  Subject to compliance with requirements, available products that may be 
incorporated into the Work include, but are not limited to, the following: 
a. 
Monofilament Fibers: 
1) 
Axim Italcementi Group, Inc.; FIBRASOL II P. 
2) 
Euclid Chemical Company (The), an RPM company; Fiberstrand 100, 
Fiberstrand 150. 
3) 
Grace, W. R. & Co. - Conn.; Grace MicroFiber. 
4) 
Metalcrete Industries; Polystrand 1000. 
5) 
QC Construction Products; QC FIBERS. 
2.5 
CURING MATERIALS 
A. 
Evaporation Retarder: ASTM C309 Type 2 Waterborne, monomolecular film forming, 
manufactured for application to fresh concrete. 
1. 
Products:  Subject to compliance with requirements, available products that may be 
incorporated into the Work include, but are not limited to, the following: 
a. 
Axim Italcementi Group, Inc.; CATEXOL CimFilm. 
b. 
BASF Construction Chemicals - Building Systems; Confilm. 
c. 
ChemMasters; SprayFilm. 
d. 
Conspec by Dayton Superior; Aquafilm. 
e. 
Dayton Superior Corporation; Sure Film (J-74).

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
6 
 
 
 
 
f. 
Edoco by Dayton Superior; BurkeFilm. 
g. 
Euclid Chemical Company (The), an RPM company; Eucobar. 
h. 
Kaufman Products, Inc.; Vapor-Aid. 
i. 
Lambert Corporation; LAMBCO Skin. 
j. 
L&M Construction Chemicals, Inc.; E-CON. 
k. 
Meadows, W. R., Inc.; EVAPRE. 
l. 
Metalcrete Industries; Waterhold. 
m. 
Nox-Crete Products Group; MONOFILM. 
n. 
Sika Corporation; SikaFilm. 
o. 
SpecChem, LLC; Spec Film. 
p. 
Symons by Dayton Superior; Finishing Aid. 
q. 
TK Products, Division of Sierra Corporation; TK-2120 TRI-FILM. 
r. 
Unitex; PRO-FILM. 
s. 
Vexcon Chemicals, Inc.; Certi-Vex Envio Set. 
B. 
Absorptive Cover:  AASHTO M 182, Class 2, burlap cloth made from jute or kenaf, weighing 
approximately 9 oz./sq. yd. (305 g/sq. m) when dry. 
C. 
Moisture-Retaining Cover:  ASTM C 171, polyethylene film or white burlap-polyethylene 
sheet. 
D. 
Water:  Potable. 
2.6 
RELATED MATERIALS 
A. 
Expansion- and Isolation-Joint-Filler Strips: ASTM D 1751, asphalt-saturated cellulosic fiber 
B. 
Slip-Resistive Aggregate Finish:  Factory-graded, packaged, rustproof, nonglazing, abrasive 
aggregate of fused aluminum-oxide granules or crushed emery aggregate containing not less 
than 50 percent aluminum oxide and not less than 20 percent ferric oxide; unaffected by 
freezing, moisture, and cleaning materials. 
C. 
Bonding Agent:  ASTM C 1059, Type II, non-redispersible, acrylic emulsion or styrene 
butadiene. 
D. 
Epoxy Bonding Adhesive:  ASTM C 881/C 881M, two-component epoxy resin capable of 
humid curing and bonding to damp surfaces; of class suitable for application temperature, of 
grade complying with requirements, and of the following types: 
1. 
Types I and II, non-load bearing Types IV and V, load bearing, for bonding hardened or 
freshly mixed concrete to hardened concrete. 
2.7 
CONCRETE MIXTURES 
A. 
Prepare design mixtures for each type and strength of concrete, proportioned on the basis of 
laboratory trial mixture or field test data, or both, according to ACI 301.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
7 
 
 
 
 
1. 
Use a qualified independent testing agency for preparing and reporting proposed mixture 
designs based on laboratory trial mixtures. 
B. 
Cementitious Materials: Limit percentage, by weight, of cementitious materials other than 
portland cement in concrete as follows: 
1. 
Fly Ash:  25 percent. 
2. 
Combined Fly Ash and Pozzolan:  25 percent. 
3. 
Ground Granulated Blast-Furnace Slag:  50 percent. 
4. 
Combined Fly Ash or Pozzolan and Ground Granulated Blast-Furnace Slag:  50 percent 
portland cement minimum, with fly ash or pozzolan not exceeding 25 percent. 
5. 
Silica Fume:  10 percent. 
6. 
Combined Fly Ash, Pozzolans, and Silica Fume:  35 percent with fly ash or pozzolans not 
exceeding 25 percent and silica fume not exceeding 10 percent. 
7. 
Combined Fly Ash or Pozzolans, Ground Granulated Blast-Furnace Slag, and Silica 
Fume:  50 percent with fly ash or pozzolans not exceeding 25 percent and silica fume not 
exceeding 10 percent. 
C. 
Limit water-soluble, chloride-ion content in hardened concrete to [0.06] [0.15] [0.30] [1.00] 
percent by weight of cement. 
D. 
Admixtures:  Use admixtures according to manufacturer's written instructions. 
1. 
Use water-reducing admixture in concrete, as required, for placement and workability. 
2. 
Use water-reducing and retarding admixture when required by high temperatures, low 
humidity, or other adverse placement conditions. 
3. 
Use water-reducing admixture in pumped concrete, concrete for heavy-use industrial 
slabs and parking structure slabs, concrete required to be watertight, and concrete with a 
water-cementitious materials ratio below 0.50. 
4. 
Use corrosion-inhibiting admixture in concrete mixtures where indicated. 
2.8 
CONCRETE MIXING 
A. 
Ready-Mixed Concrete:  Measure, batch, and mix concrete materials and concrete according to 
ASTM C 94/C 94M[ and ASTM C 1116/C 1116M].  Furnish batch certificates for each batch 
discharged and used in the Work. 
1. 
When air temperature is between 85 and 90 deg F (30 and 32 deg C), reduce mixing and 
delivery time from 1-1/2 hours to 75 minutes; when air temperature is above 90 deg F (32 
deg C), reduce mixing and delivery time to 60 minutes. 
B. 
Project-Site Mixing:  Measure, batch, and mix concrete materials and concrete according to 
ASTM C 94/C 94M.  Mix concrete materials in appropriate drum-type batch machine mixer. 
1. 
For concrete batches of 1 cu. yd. (0.76 cu. m) or smaller, continue mixing at least 1-1/2 
minutes, but not more than 5 minutes after ingredients are in mixer, before any part of 
batch is released. 
2. 
For concrete batches larger than 1 cu. yd. (0.76 cu. m), increase mixing time by 15 
seconds for each additional 1 cu. yd. (0.76 cu. m).

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
8 
 
 
 
 
3. 
Provide batch ticket for each batch discharged and used in the Work, indicating Project 
identification name and number, date, mixture type, mixing time, quantity, and amount of 
water added. 
PART 3 - EXECUTION 
3.1 
EXAMINATION 
A. 
Examine exposed subgrades and subbase surfaces for compliance with requirements for 
dimensional, grading, and elevation tolerances. 
B. 
Proof-roll prepared subbase surface below concrete paving to identify soft pockets and areas of 
excess yielding. 
1. 
Completely proof-roll subbase in one direction and repeat in perpendicular direction.  
Limit vehicle speed to 3 mph (5 km/h). 
2. 
Proof-roll with a pneumatic-tired and loaded, 10-wheel, tandem-axle dump truck 
weighing not less than 15 tons (13.6 tonnes). 
3. 
Correct subbase with soft spots and areas of pumping or rutting exceeding depth of 1/2 
inch (13 mm) according to requirements in Section 312000 "Earth Moving." 
C. 
Proceed with installation only after unsatisfactory conditions have been corrected. 
3.2 
PREPARATION 
A. 
Remove loose material from compacted subbase surface immediately before placing concrete. 
3.3 
EDGE FORMS AND SCREED CONSTRUCTION 
A. 
Set, brace, and secure edge forms, bulkheads, and intermediate screed guides to required lines, 
grades, and elevations.  Install forms to allow continuous progress of work and so forms can 
remain in place at least 24 hours after concrete placement. 
B. 
Clean forms after each use and coat with form-release agent to ensure separation from concrete 
without damage. 
3.4 
STEEL REINFORCEMENT 
A. 
General:  Comply with CRSI's "Manual of Standard Practice" for fabricating, placing, and 
supporting reinforcement. 
B. 
Clean reinforcement of loose rust and mill scale, earth, ice, or other bond-reducing materials. 
C. 
Arrange, space, and securely tie bars and bar supports to hold reinforcement in position during 
concrete placement.  Maintain minimum cover to reinforcement.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
9 
 
 
 
 
D. 
Install welded wire reinforcement in lengths as long as practicable.  Lap adjoining pieces at 
least one full mesh, and lace splices with wire.  Offset laps of adjoining widths to prevent 
continuous laps in either direction. 
E. 
Zinc-Coated Reinforcement:  Use galvanized-steel wire ties to fasten zinc-coated reinforcement.  
Repair cut and damaged zinc coatings with zinc repair material. 
F. 
Epoxy-Coated Reinforcement:  Use epoxy-coated steel wire ties to fasten epoxy-coated 
reinforcement.  Repair cut and damaged epoxy coatings with epoxy repair coating according to 
ASTM D 3963/D 3963M. 
G. 
Install fabricated bar mats in lengths as long as practicable.  Handle units to keep them flat and 
free of distortions.  Straighten bends, kinks, and other irregularities, or replace units as required 
before placement.  Set mats for a minimum 2-inch (50-mm) overlap of adjacent mats. 
3.5 
JOINTS 
A. 
General:  Construct joints true to line with faces perpendicular to surface plane of concrete. 
B. 
Construction Joints:  Install so strength and appearance of concrete are not impaired, at 
locations indicated or as approved by Architect. 
1. 
Place joints perpendicular to main reinforcement.  Continue reinforcement across 
construction joints unless otherwise indicated.  Do not continue reinforcement through 
sides of strip placements of floors and slabs. 
2. 
Form keyed joints as indicated.  Embed keys at least 1-1/2 inches (38 mm) into concrete. 
3. 
Locate joints for beams, slabs, joists, and girders in the middle third of spans.  Offset 
joints in girders a minimum distance of twice the beam width from a beam-girder 
intersection. 
4. 
Locate horizontal joints in walls and columns at underside of floors, slabs, beams, and 
girders and at the top of footings or floor slabs. 
5. 
Space vertical joints in walls as indicated. Locate joints beside piers integral with walls, 
near corners, and in concealed locations where possible. 
6. 
Use a bonding agent at locations where fresh concrete is placed against hardened or 
partially hardened concrete surfaces. 
7. 
Use epoxy-bonding adhesive at locations where fresh concrete is placed against hardened 
or partially hardened concrete surfaces. 
C. 
Contraction Joints in Slabs-on-Grade:  Form weakened-plane contraction joints, sectioning 
concrete into areas as indicated.  Construct contraction joints for a depth equal to at least one-
fourth of concrete thickness as follows: 
1. 
Sawed Joints:  Form contraction joints with power saws equipped with shatterproof 
abrasive or diamond-rimmed blades.  Cut 1/8-inch- (3.2-mm-) wide joints into concrete 
when cutting action will not tear, abrade, or otherwise damage surface and before 
concrete develops random contraction cracks. 
D. 
Isolation Joints in Slabs-on-Grade:  After removing formwork, install joint-filler strips at slab 
junctions with vertical surfaces, such as column pedestals, foundation walls, grade beams, and 
other locations, as indicated.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
10 
 
 
 
 
1. 
Extend joint-filler strips full width and depth of joint, terminating flush with finished 
concrete surface unless otherwise indicated. 
2. 
Terminate full-width joint-filler strips not less than 1/2 inch (13 mm) or more than 1 inch 
(25 mm) below finished concrete surface where joint sealants, specified in 
Section 079200 "Joint Sealants," are indicated. 
3. 
Install joint-filler strips in lengths as long as practicable.  Where more than one length is 
required, lace or clip sections together. 
E. 
Doweled Joints:  Install dowel bars and support assemblies at joints where indicated.  Lubricate 
or asphalt coat one-half of dowel length to prevent concrete bonding to one side of joint. 
F. 
Edging:  After initial floating, tool edges of paving, gutters, curbs, and joints in concrete with an 
edging tool to a 1/4-inch (6-mm) radius.  Repeat tooling of edges after applying surface 
finishes. Eliminate edging-tool marks on concrete surfaces. 
3.6 
CONCRETE PLACEMENT 
A. 
Before placing concrete, verify that installation of formwork, reinforcement, and embedded 
items is complete and that required inspections have been performed. 
B. 
Do not add water to concrete during delivery, at Project site, or during placement unless 
approved by Architect. 
C. 
Before test sampling and placing concrete, water may be added at Project site, subject to 
limitations of ACI 301. 
1. 
Do not add water to concrete after adding high-range water-reducing admixtures to 
mixture. 
D. 
Deposit concrete continuously in one layer or in horizontal layers of such thickness that no new 
concrete will be placed on concrete that has hardened enough to cause seams or planes of 
weakness.  If a section cannot be placed continuously, provide construction joints as indicated.  
Deposit concrete to avoid segregation. 
1. 
Deposit concrete in horizontal layers of depth to not exceed formwork design pressures 
and in a manner to avoid inclined construction joints. 
2. 
Consolidate placed concrete with mechanical vibrating equipment according to ACI 301. 
3. 
Do not use vibrators to transport concrete inside forms.  Insert and withdraw vibrators 
vertically at uniformly spaced locations to rapidly penetrate placed layer and at least 6 
inches (150 mm) into preceding layer.  Do not insert vibrators into lower layers of 
concrete that have begun to lose plasticity.  At each insertion, limit duration of vibration 
to time necessary to consolidate concrete and complete embedment of reinforcement and 
other embedded items without causing mixture constituents to segregate. 
E. 
Deposit and consolidate concrete for floors and slabs in a continuous operation, within limits of 
construction joints, until placement of a panel or section is complete. 
1. 
Consolidate concrete during placement operations so concrete is thoroughly worked 
around reinforcement and other embedded items and into corners.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
11 
 
 
 
 
2. 
Maintain reinforcement in position on chairs during concrete placement. 
3. 
Screed slab surfaces with a straightedge and strike off to correct elevations. 
4. 
Slope surfaces uniformly to drains where required. 
5. 
Begin initial floating using bull floats or darbies to form a uniform and open-textured 
surface plane, before excess bleedwater appears on the surface.  Do not further disturb 
slab surfaces before starting finishing operations. 
F. 
Cold-Weather Placement:  Comply with ACI 306.1 and as follows.  Protect concrete work from 
physical damage or reduced strength that could be caused by frost, freezing actions, or low 
temperatures. 
1. 
When average high and low temperature is expected to fall below 40 deg F (4.4 deg C) 
for three successive days, maintain delivered concrete mixture temperature within the 
temperature range required by ACI 301. 
2. 
Do not use frozen materials or materials containing ice or snow.  Do not place concrete 
on frozen subgrade or on subgrade containing frozen materials. 
3. 
Do not use calcium chloride, salt, or other materials containing antifreeze agents or 
chemical accelerators unless otherwise specified and approved in mixture designs. 
G. 
Hot-Weather Placement:  Comply with ACI 301 and as follows: 
1. 
Maintain concrete temperature below 90 deg F (32 deg C) at time of placement.  Chilled 
mixing water or chopped ice may be used to control temperature, provided water 
equivalent of ice is calculated to total amount of mixing water.  Using liquid nitrogen to 
cool concrete is Contractor's option. 
2. 
Fog-spray forms, steel reinforcement, and subgrade just before placing concrete.  Keep 
subgrade uniformly moist without standing water, soft spots, or dry areas. 
3.7 
FLOAT FINISHING 
A. 
General:  Do not add water to concrete surfaces during finishing operations. 
B. 
Float Finish:  Begin the second floating operation when bleed-water sheen has disappeared and 
concrete surface has stiffened sufficiently to permit operations.  Float surface with power-driven 
floats or by hand floating if area is small or inaccessible to power units.  Finish surfaces to true 
planes.  Cut down high spots and fill low spots.  Refloat surface immediately to uniform 
granular texture. 
1. 
Medium-to-Fine-Textured Broom Finish:  Draw a soft-bristle broom across float-finished 
concrete surface perpendicular to line of traffic to provide a uniform, fine-line texture. 
3.8 
SPECIAL FINISHES 
A. 
Sand Blast Finish: 
1. 
Apply sandblast finish to exposed concrete surfaces as indicated by Architect. 
2. 
Perform sand blasting at least 72 hours after placement of concrete. Coordinate with 
formwork construction, concrete placement schedule, and formwork removal to ensure 
that surfaces to be blast finished are blasted at the same age for uniform results.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
12 
 
 
 
 
3. 
Determine type of nozzle, nozzle pressure, and blasting techniques required to match the 
Engineer's control samples. 
4. 
Abrasive blast corners and edge of patterns carefully, using back-up boards, to maintain 
uniform corner or edge line. 
3.9 
CONCRETE PROTECTION AND CURING 
A. 
General:  Protect freshly placed concrete from premature drying and excessive cold or hot 
temperatures.  Comply with ACI 306.1 for cold-weather protection and ACI 301 for hot-
weather protection during curing. 
B. 
Evaporation Retarder:  Apply evaporation retarder to unformed concrete surfaces if hot, dry, or 
windy conditions cause moisture loss approaching 0.2 lb/sq. ft. x h (1 kg/sq. m x h) before and 
during finishing operations.  Apply according to manufacturer's written instructions after 
placing, screeding, and bull floating or darbying concrete, but before float finishing. 
C. 
Formed Surfaces:  Cure formed concrete surfaces, including underside of beams, supported 
slabs, and other similar surfaces.  If forms remain during curing period, moist cure after 
loosening forms.  If removing forms before end of curing period, continue curing for the 
remainder of the curing period. 
D. 
Unformed Surfaces:  Begin curing immediately after finishing concrete.  Cure unformed 
surfaces, including floors and slabs, concrete floor toppings, and other surfaces. 
E. 
Cure concrete according to ACI 308.1, by one or a combination of the following methods: 
1. 
Moisture Curing:  Keep surfaces continuously moist for not less than seven days with the 
following materials: 
a. 
Water. 
b. 
Continuous water-fog spray. 
c. 
Absorptive cover, water saturated, and kept continuously wet.  Cover concrete 
surfaces and edges with 12-inch (300-mm) lap over adjacent absorptive covers. 
2. 
Moisture-Retaining-Cover Curing:  Cover concrete surfaces with moisture-retaining 
cover for curing concrete, placed in widest practicable width, with sides and ends lapped 
at least 12 inches (300 mm), and sealed by waterproof tape or adhesive.  Cure for not less 
than seven days.  Immediately repair any holes or tears during curing period using cover 
material and waterproof tape. 
a. 
Moisture cure or use moisture-retaining covers to cure concrete surfaces to receive 
floor coverings. 
b. 
Moisture cure or use moisture-retaining covers to cure concrete surfaces to receive 
penetrating liquid floor treatments. 
c. 
Cure concrete surfaces to receive floor coverings with either a moisture-retaining 
cover or a curing compound that the manufacturer certifies will not interfere with 
bonding of floor covering used on Project.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
13 
 
 
 
 
3. 
Curing Compound:  Apply uniformly in continuous operation by power spray or roller 
according to manufacturer's written instructions.  Recoat areas subjected to heavy rainfall 
within three hours after initial application.  Maintain continuity of coating and repair 
damage during curing period. 
a. 
Removal:  After curing period has elapsed, remove curing compound without 
damaging concrete surfaces by method recommended by curing compound 
manufacturer. 
3.10 
PAVING TOLERANCES 
A. 
Comply with tolerances in ACI 117 and as follows: 
1. 
Elevation:  3/4 inch (19 mm). 
2. 
Thickness:  Plus 3/8 inch (10 mm), minus 1/4 inch (6 mm). 
3. 
Surface:  Gap below 10-foot- (3-m-) long, unleveled straightedge not to exceed 1/2 inch 
(13 mm). 
4. 
Alignment of Tie-Bar End Relative to Line Perpendicular to Paving Edge:  1/2 inch per 
12 inches (13 mm per 300 mm) of tie bar. 
5. 
Lateral Alignment and Spacing of Dowels:  1 inch (25 mm). 
6. 
Vertical Alignment of Dowels:  1/4 inch (6 mm). 
7. 
Alignment of Dowel-Bar End Relative to Line Perpendicular to Paving Edge:  1/4 inch 
per 12 inches (6 mm per 300 mm) of dowel. 
8. 
Joint Spacing:  3 inches (75 mm). 
9. 
Contraction Joint Depth:  Plus 1/4 inch (6 mm), no minus. 
10. 
Joint Width:  Plus 1/8 inch (3 mm), no minus. 
3.11 
FIELD QUALITY CONTROL 
A. 
Testing and Inspecting:  Engage a qualified testing and inspecting agency to perform tests and 
inspections and to submit reports. 
B. 
Inspections: 
1. 
Steel reinforcement placement. 
2. 
Steel reinforcement welding. 
3. 
Headed bolts and studs. 
4. 
Verification of use of required design mixture. 
5. 
Concrete placement, including conveying and depositing. 
6. 
Curing procedures and maintenance of curing temperature. 
7. 
Verification of concrete strength before removal of shores and forms from beams and 
slabs. 
C. 
Concrete Tests:  Testing of composite samples of fresh concrete obtained according to 
ASTM C 172 shall be performed according to the following requirements:

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
14 
 
 
 
 
1. 
Testing Frequency:  Obtain one composite sample for each day's pour of each concrete 
mixture exceeding 5 cu. yd. (4 cu. m), but less than 25 cu. yd. (19 cu. m), plus one set for 
each additional 50 cu. yd. (38 cu. m) or fraction thereof. 
a. 
When frequency of testing will provide fewer than five compressive-strength tests 
for each concrete mixture, testing shall be conducted from at least five randomly 
selected batches or from each batch if fewer than five are used. 
2. 
Slump:  ASTM C 143/C 143M; one test at point of placement for each composite sample, 
but not less than one test for each day's pour of each concrete mixture.  Perform 
additional tests when concrete consistency appears to change. 
3. 
Air Content:  ASTM C 231, pressure method, for normal-weight concrete; 
ASTM C 173/C 173M, volumetric method, for structural lightweight concrete; one test 
for each composite sample, but not less than one test for each day's pour of each concrete 
mixture. 
4. 
Concrete Temperature:  ASTM C 1064/C 1064M; one test hourly when air temperature is 
40 deg F (4.4 deg C) and below and when 80 deg F (27 deg C) and above, and one test 
for each composite sample. 
5. 
Compression Test Specimens:  ASTM C 31/C 31M. 
a. 
Cast and laboratory cure two sets of two standard cylinder specimens for each 
composite sample. 
b. 
Cast and field cure [two] sets of two standard cylinder specimens for each 
composite sample. 
6. 
Compressive-Strength Tests:  ASTM C 39/C 39M; test one set of two laboratory-cured 
specimens at 7 days and one set of two specimens at 28 days. 
a. 
Test one set of two field-cured specimens at 7 days and one set of two specimens 
at 28 days. 
b. 
A compressive-strength test shall be the average compressive strength from a set of 
two specimens obtained from same composite sample and tested at age indicated. 
7. 
When strength of field-cured cylinders is less than 85 percent of companion laboratory-
cured cylinders, Contractor shall evaluate operations and provide corrective procedures 
for protecting and curing in-place concrete. 
8. 
Strength of each concrete mixture will be satisfactory if every average of any three 
consecutive compressive-strength tests equals or exceeds specified compressive strength 
and no compressive-strength test value falls below specified compressive strength by 
more than 500 psi (3.4 MPa). 
9. 
Test results shall be reported in writing to Architect, concrete manufacturer, and 
Contractor within 48 hours of testing.  Reports of compressive-strength tests shall contain 
Project identification name and number, date of concrete placement, name of concrete 
testing and inspecting agency, location of concrete batch in Work, design compressive 
strength at 28 days, concrete mixture proportions and materials, compressive breaking 
strength, and type of break for both 7- and 28-day tests. 
10. 
Nondestructive Testing:  Impact hammer, sonoscope, or other nondestructive device may 
be permitted by Architect but will not be used as sole basis for approval or rejection of 
concrete.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
15 
 
 
 
 
11. 
Additional Tests:  Testing and inspecting agency shall make additional tests of concrete 
when test results indicate that slump, air entrainment, compressive strengths, or other 
requirements have not been met, as directed by Architect.  Testing and inspecting agency 
may conduct tests to determine adequacy of concrete by cored cylinders complying with 
ASTM C 42/C 42M or by other methods as directed by Architect. 
12. 
Additional testing and inspecting, at Contractor's expense, will be performed to determine 
compliance of replaced or additional work with specified requirements. 
13. 
Correct deficiencies in the Work that test reports and inspections indicate do not comply 
with the Contract Documents. 
3.12 
REPAIRS AND PROTECTION 
A. 
Remove and replace concrete paving that is broken, damaged, or defective or that does not 
comply with requirements in this Section.  Remove work in complete sections from joint to 
joint unless otherwise approved by Architect. 
B. 
Drill test cores, where directed by Architect, when necessary to determine magnitude of cracks 
or defective areas.  Fill drilled core holes in satisfactory paving areas with portland cement 
concrete bonded to paving with epoxy adhesive. 
C. 
Protect concrete paving from damage.  Exclude traffic from paving for at least 14 days after 
placement.  When construction traffic is permitted, maintain paving as clean as possible by 
removing surface stains and spillage of materials as they occur. 
D. 
Maintain concrete paving free of stains, discoloration, dirt, and other foreign material.  Sweep 
paving not more than two days before date scheduled for Substantial Completion inspections. 
END OF SECTION 321313

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
1 
 
 
 
 
SECTION 321316 - DECORATIVE CONCRETE PAVING 
PART 1 - GENERAL 
1.1 
RELATED DOCUMENTS 
A. 
Drawings and general provisions of the Contract, including General and Supplementary 
Conditions and Division 01 Specification Sections, apply to this Section. 
1.2 
SUMMARY 
A. 
Section includes colored and specialty finish concrete paving. 
B. 
Related Sections: 
1. 
Section 033000 "Cast-in-Place Concrete" for general building applications of concrete. 
2. 
Section 321373 "Concrete Paving Joint Sealants" for joint sealants in expansion and 
contraction joints within decorative concrete paving and in joints between decorative 
concrete paving and asphalt paving or adjacent construction. 
1.3 
DEFINITIONS 
A. 
Cementitious Materials:  Portland cement alone or in combination with one or more of blended 
hydraulic cement, fly ash and other pozzolans, and ground granulated blast-furnace slag. 
1.4 
ACTION SUBMITTALS 
A. 
Samples for Verification:  For each type of exposed color, pattern, or texture indicated. 
B. 
Other Action Submittals: 
1. 
Design Mixtures:  For each decorative concrete paving mixture.  Include alternate design 
mixtures when characteristics of materials, Project conditions, weather, test results, or 
other circumstances warrant adjustments. 
2. 
Medium Sandblast Finish: 5’ x 5’ in size of each type of sand blast finish, indicating 
materials and methods used to produce the sand blast finishes. 
1.5 
INFORMATIONAL SUBMITTALS 
A. 
Qualification Data:  For qualified Installer, ready-mix concrete manufacturer and testing 
agency. 
B. 
Material Certificates:  For the following, from manufacturer: 
1. 
Color Pigment Admixtures.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
2 
 
 
 
 
2. 
Applied finish materials. 
1.6 
QUALITY ASSURANCE 
A. 
Installer Qualifications:  An employer of workers trained and approved by manufacturer of 
decorative concrete paving systems. 
B. 
Ready-Mix-Concrete Manufacturer Qualifications:  A firm experienced in manufacturing ready-
mixed concrete products and that complies with ASTM C 94/C 94M requirements for 
production facilities and equipment. 
1. 
Manufacturer certified according to NRMCA's "Certification of Ready Mixed Concrete 
Production Facilities" (Quality Control Manual - Section 3, "Plant Certification 
Checklist"). 
C. 
Testing Agency Qualifications:  Qualified according to ASTM C 1077 and ASTM E 329 for 
testing indicated. 
1. 
Personnel conducting field tests shall be qualified as ACI Concrete Field Testing 
Technician, Grade 1, according to ACI CP-1 or an equivalent certification program. 
D. 
Source Limitations:  Obtain decorative concrete paving products and each type or class of 
cementitious material of the same brand from same manufacturer's plant, and obtain each 
aggregate from single source. 
E. 
Concrete Testing Service:  Engage a qualified testing agency to perform material evaluation 
tests and to design concrete mixtures. 
F. 
ACI Publications:  Comply with ACI 301 (ACI 301M)unless otherwise indicated. 
G. 
Mockups:  Build mockups to verify selections made under sample submittals and to 
demonstrate aesthetic effects and set quality standards for materials and execution. 
1. 
Build mockups of full-thickness sections of decorative concrete paving to demonstrate 
typical joints; surface color, pattern, and texture; curing; and standard of workmanship. 
2. 
Build mockups of decorative concrete paving in the location and of the size indicated or, 
if not indicated, build mockups where directed by Landscape Architect and not less than 
96 inches (2400 mm) by 96 inches (2400 mm). 
3. 
Approval of mockups does not constitute approval of deviations from the Contract 
Documents contained in mockups unless Landscape Architect specifically approves such 
deviations in writing. 
4. 
Approved mockups may become part of the completed Work if undisturbed at time of 
Substantial Completion. 
H. 
Preinstallation Conference:  Conduct conference at Project site. 
1. 
Review methods and procedures related to decorative concrete paving, including but not 
limited to, the following:

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
3 
 
 
 
 
a. 
Concrete mixture design. 
b. 
Quality control of concrete materials and decorative concrete paving construction 
practices. 
2. 
Require representatives of each entity directly concerned with decorative concrete paving 
to attend, including the following: 
a. 
Contractor's superintendent. 
b. 
Independent testing agency responsible for concrete design mixtures. 
c. 
Ready-mix concrete manufacturer. 
d. 
Decorative concrete paving Installer. 
e. 
Manufacturer's representative of decorative concrete paving system. 
1.7 
PROJECT CONDITIONS 
A. 
Traffic Control:  Maintain access for vehicular and pedestrian traffic as required for other 
construction activities. 
PART 2 - PRODUCTS 
2.1 
CONCRETE MATERIALS 
A. 
Color Pigment:  ASTM C 979, synthetic mineral-oxide pigments or colored water-reducing 
admixtures; color stable, nonfading, and resistant to lime and other alkalis. 
1. 
Manufacturers:  Subject to compliance with requirements, provide products by one of the 
following: 
a. 
Davis Colors. Omaha Tan #5084 
2.2 
CURING AND SEALING MATERIALS 
A. 
Curing Paper:  Nonstaining, waterproof paper, consisting of two layers of kraft paper cemented 
together and reinforced with fiber, and complying with ASTM C 171. 
B. 
Evaporation Retarder:  Waterborne, monomolecular, film forming, manufactured for application 
to fresh concrete. 
C. 
Waterborne, Membrane-Forming Curing Compound:  ASTM C 309, Type I, Class B, 
manufactured for colored concrete. 
1. 
For integrally colored concrete, curing compound shall be pigmented type approved by 
coloring admixture manufacturer.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
4 
 
 
 
 
2.3 
CONCRETE MIXTURES 
A. 
Color Pigment: Add color pigment to concrete mixture according to manufacturer's written 
instructions and to result in hardened concrete color consistent with approved mockup. 
PART 3 - EXECUTION 
3.1 
FLOAT FINISHING 
A. 
General:  Do not add water to concrete surfaces during finishing operations. 
B. 
Float Finish:  Begin the second floating operation when bleed-water sheen has disappeared and 
concrete surface has stiffened sufficiently to permit operations.  Float surface with power-driven 
floats or by hand floating if area is small or inaccessible to power units.  Finish surfaces to true 
planes.  Cut down high spots and fill low spots.  Refloat surface immediately to uniform 
granular texture. 
1. 
Medium-to-Fine-Textured Broom Finish:  Draw a soft-bristle broom across float-finished 
concrete surface perpendicular to line of traffic to provide a uniform, fine-line texture. 
3.2 
SPECIALTY CONCRETE FINISHES 
A. 
Sand Blast 
1. 
Apply sandblast finish to exposed concrete surfaces as indicated by Architect. 
2. 
Perform sand blasting at least 72 hours after placement of concrete. Coordinate with 
formwork construction, concrete placement schedule, and formwork removal to ensure 
that surfaces to be blast finished are blasted at the same age for uniform results.  
3. 
Determine type of nozzle, nozzle pressure, and blasting techniques required to match the 
Engineer's control samples. 
4. 
Abrasive blast corners and edge of patterns carefully, using back-up boards, to maintain 
uniform corner or edge line. 
3.3 
CONCRETE PROTECTION AND CURING 
A. 
General:  Protect freshly placed concrete from premature drying and excessive cold or hot 
temperatures. 
B. 
Comply with ACI 306.1 for cold-weather protection. 
C. 
Evaporation Retarder:  Apply evaporation retarder to concrete surfaces if hot, dry, or windy 
conditions cause moisture loss approaching 0.2 lb/sq. ft. x h (1 kg/sq. m x h) before and during 
finishing operations.  Apply according to manufacturer's written instructions after placing, 
screeding, and bull floating or darbying concrete but before float finishing. 
D. 
Begin curing after finishing concrete but not before free water has disappeared from concrete 
surface.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
5 
 
 
 
 
E. 
Curing Compound:  Apply curing compound immediately after final finishing.  Apply 
uniformly in continuous operation by power spray or roller according to manufacturer's written 
instructions.  Recoat areas that have been subjected to heavy rainfall within three hours after 
application.  Maintain continuity of coating, and repair damage during curing period. 
1. 
Cure integrally colored concrete with a pigmented curing compound. 
F. 
Curing and Sealing Compound:  Apply uniformly in continuous operation by power spray or 
roller according to manufacturer's written instructions.  Recoat areas subjected to heavy rainfall 
within three hours after initial application.  Repeat process 24 hours later and apply a second 
coat.  Maintain continuity of coating and repair damage during curing period. 
3.4 
PAVING TOLERANCES 
A. 
Comply with tolerances in ACI 117 and as follows: 
1. 
Elevation:  3/4 inch (19 mm). 
2. 
Thickness:  Plus 3/8 inch (10 mm), minus 1/4 inch (6 mm). 
3. 
Surface:  Gap below 10-foot- (3-m-) long, unleveled straightedge not to exceed 1/2 inch 
(13 mm). 
4. 
Lateral Alignment and Spacing of Dowels:  1 inch (25 mm). 
5. 
Vertical Alignment of Dowels:  1/4 inch (6 mm). 
6. 
Alignment of Dowel-Bar End Relative to Line Perpendicular to Paving Edge:  1/4 inch 
per 12 inches (6 mm per 300 mm) of dowel. 
7. 
Joint Spacing:  3 inches (75 mm). 
8. 
Contraction Joint Depth:  Plus 1/4 inch (6 mm), no minus. 
9. 
Joint Width:  Plus 1/8 inch (3 mm), no minus. 
3.5 
FIELD QUALITY CONTROL 
A. 
Testing Agency:  Engage a qualified testing agency to perform tests and inspections. 
B. 
Testing Services:  Testing of composite samples of fresh concrete obtained according to 
ASTM C 172 shall be performed according to the following requirements: 
1. 
Testing Frequency:  Obtain at least one composite sample for each 1,000 sq. ft. or 
fraction thereof of each concrete mixture placed each day. 
a. 
When frequency of testing will provide fewer than five compressive-strength tests 
for each concrete mixture, testing shall be conducted from at least five randomly 
selected batches or from each batch if fewer than five are used. 
2. 
Slump:  ASTM C 143/C 143M; one test at point of placement for each composite sample, 
but not less than one test for each day's pour of each concrete mixture.  Perform 
additional tests when concrete consistency appears to change. 
3. 
Air Content:  ASTM C 231, pressure method; one test for each composite sample, but not 
less than one test for each day's pour of each concrete mixture.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
6 
 
 
 
 
4. 
Concrete Temperature:  ASTM C 1064/C 1064M; one test hourly when air temperature is 
40 deg F (4.4 deg C) and below and when it is 80 deg F (27 deg C) and above, and one 
test for each composite sample. 
5. 
Compression Test Specimens:  ASTM C 31/C 31M; cast and laboratory cure one set of 
three standard cylinder specimens for each composite sample. 
6. 
Compressive-Strength Tests:  ASTM C 39/C 39M; test one specimen at seven days and 
two specimens at 28 days. 
a. 
A compressive-strength test shall be the average compressive strength from two 
specimens obtained from same composite sample and tested at 28 days. 
C. 
Strength of each concrete mixture will be satisfactory if average of any three consecutive 
compressive-strength tests equals or exceeds specified compressive strength and no 
compressive-strength test value falls below specified compressive strength by more than 500 psi 
(3.4 MPa). 
D. 
Test results shall be reported in writing to Architect, concrete manufacturer, and Contractor 
within 48 hours of testing.  Reports of compressive-strength tests shall contain Project 
identification name and number, date of concrete placement, name of concrete testing and 
inspecting agency, location of concrete batch in Work, design compressive strength at 28 days, 
concrete mixture proportions and materials, compressive breaking strength, and type of break 
for both 7- and 28-day tests. 
E. 
Nondestructive Testing:  Impact hammer, sonoscope, or other nondestructive device may be 
permitted by Architect but will not be used as sole basis for approval or rejection of concrete. 
F. 
Additional Tests:  Testing and inspecting agency shall make additional tests of concrete when 
test results indicate that slump, air entrainment, compressive strengths, or other requirements 
have not been met, as directed by Architect. 
G. 
Decorative concrete paving will be considered defective if it does not pass tests and inspections. 
H. 
Additional testing and inspecting, at Contractor's expense, will be performed to determine 
compliance of replaced or additional work with specified requirements. 
I. 
Prepare test and inspection reports. 
3.6 
REPAIRS AND PROTECTION 
A. 
Remove and replace decorative concrete paving that is broken or damaged or does not comply 
with requirements in this Section.  Remove work in complete sections from joint to joint unless 
otherwise approved by Architect. 
B. 
Detailing:  Grind concrete "squeeze" left from tool placement.  Color ground areas with slurry 
of color hardener mixed with water and bonding agent.  Remove excess release agent with high-
velocity blower.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
7 
 
 
 
 
C. 
Protect decorative concrete paving from damage.  Exclude traffic from paving for at least 14 
days after placement.  When construction traffic is permitted, maintain paving as clean as 
possible by removing surface stains and spillage of materials as they occur. 
D. 
Maintain decorative concrete paving free of stains, discoloration, dirt, and other foreign 
material.  Sweep paving not more than two days before date scheduled for Substantial 
Completion inspections. 
 
END OF SECTION 321316

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
1 
 
 
 
 
SECTION 321373 - CONCRETE PAVING JOINT SEALANTS 
PART 1 - GENERAL 
1.1 
RELATED DOCUMENTS 
A. 
Drawings and general provisions of the Contract, including General and Supplementary 
Conditions and Division 01 Specification Sections, apply to this Section. 
1.2 
SUMMARY 
A. 
Section Includes: 
1. 
Cold-applied joint sealants. 
2. 
Hot-applied joint sealants. 
B. 
Related Sections: 
1. 
Section 033000 "Cast-in-Place Concrete" for constructing joints in concrete pavement. 
1.3 
PRECONSTRUCTION TESTING 
A. 
Preconstruction Compatibility and Adhesion Testing:  Submit to joint-sealant manufacturers, 
for testing indicated below, Samples of materials that will contact or affect joint sealants. 
1. 
Use manufacturer's standard test method to determine whether priming and other specific 
joint-preparation techniques are required to obtain rapid, optimum adhesion of joint 
sealants to joint substrates. 
2. 
Submit no fewer than eight pieces of each type of material, including joint substrates, 
shims, joint-sealant backings, secondary seals, and miscellaneous materials. 
3. 
Schedule sufficient time for testing and analyzing results to prevent delaying the Work. 
4. 
For materials failing tests, obtain joint-sealant manufacturer's written instructions for 
corrective measures including use of specially formulated primers. 
5. 
Testing will not be required if joint-sealant manufacturers submit joint-preparation data 
that are based on previous testing, not older than 24 months, of sealant products for 
compatibility with and adhesion to joint substrates and other materials matching those 
submitted. 
1.4 
ACTION SUBMITTALS 
A. 
Product Data:  For each joint-sealant product indicated. 
B. 
Pavement-Joint-Sealant Schedule:  Include the following information: 
1. 
Joint-sealant application, joint location, and designation. 
2. 
Joint-sealant manufacturer and product name.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
2 
 
 
 
 
3. 
Joint-sealant formulation. 
4. 
Joint-sealant color. 
1.5 
INFORMATIONAL SUBMITTALS 
A. 
Qualification Data:  For qualified Installer and testing agency. 
B. 
Product Certificates:  For each type of joint sealant and accessory, from manufacturer. 
C. 
Product Test Reports:  Based on evaluation of comprehensive tests performed by a qualified 
testing agency, for joint sealants. 
D. 
Preconstruction Compatibility and Adhesion Test Reports:  From joint-sealant manufacturer, 
indicating the following: 
1. 
Materials forming joint substrates and joint-sealant backings have been tested for 
compatibility with and adhesion to joint sealants. 
2. 
Interpretation of test results and written recommendations for primers and substrate 
preparation needed for adhesion. 
1.6 
QUALITY ASSURANCE 
A. 
Installer Qualifications:  Manufacturer's authorized representative who is trained and approved 
for installation of units required for this Project. 
B. 
Source Limitations:  Obtain each type of joint sealant from single source from single 
manufacturer. 
C. 
Product Testing:  Test joint sealants using a qualified testing agency. 
1. 
Testing Agency Qualifications:  An independent testing agency qualified according to 
ASTM C 1021 to conduct the testing indicated. 
1.7 
PROJECT CONDITIONS 
A. 
Do not proceed with installation of joint sealants under the following conditions: 
1. 
When ambient and substrate temperature conditions are outside limits permitted by joint-
sealant manufacturer 
2. 
When joint substrates are wet. 
3. 
Where joint widths are less than those allowed by joint-sealant manufacturer for 
applications indicated. 
4. 
Where contaminants capable of interfering with adhesion have not yet been removed 
from joint substrates.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
3 
 
 
 
 
PART 2 - PRODUCTS 
2.1 
MATERIALS 
A. 
Compatibility:  Provide joint sealants, backing materials, and other related materials that are 
compatible with one another and with joint substrates under conditions of service and 
application, as demonstrated by joint-sealant manufacturer based on testing and field 
experience. 
2.2 
COLD-APPLIED JOINT SEALANTS 
A. 
Single-Component, Nonsag, Silicone Joint Sealant for Concrete:  ASTM D 5893, Type NS. 
1. 
Products:  Subject to compliance with requirements, available products that may be 
incorporated into the Work include, but are not limited to, the following: 
a. 
Crafco Inc., an ERGON company; RoadSaver Silicone. 
b. 
Dow Corning Corporation; 888. 
c. 
Pecora Corporation; 301 NS. 
B. 
Single-Component, Self-Leveling, Silicone Joint Sealant for Concrete:  ASTM D 5893, 
Type SL. 
1. 
Products:  Subject to compliance with requirements, available products that may be 
incorporated into the Work include, but are not limited to, the following: 
a. 
Crafco Inc., an ERGON company; RoadSaver Silicone SL. 
b. 
Dow Corning Corporation; 890-SL. 
c. 
Pecora Corporation; 300 SL. 
C. 
Multicomponent, Pourable, Traffic-Grade, Urethane Joint Sealant for Concrete:  ASTM C 920, 
Type M, Grade P, Class 25, for Use T. 
1. 
Products:  Subject to compliance with requirements, products that may be incorporated 
into the Work include, but are not limited to, the following: 
a. 
Pecora Corporation; Urexpan NR-200. 
2.3 
HOT-APPLIED JOINT SEALANTS 
A. 
Hot-Applied, Single-Component Joint Sealant for Concrete:  ASTM D 3406. 
1. 
Products:  Subject to compliance with requirements, available products that may be 
incorporated into the Work include, but are not limited to, the following: 
a. 
Crafco Inc., an ERGON company; Superseal 444/777.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
4 
 
 
 
 
B. 
Hot-Applied, Single-Component Joint Sealant for Concrete and Asphalt:  ASTM D 6690, 
Types I, II, and III. 
1. 
Products:  Subject to compliance with requirements, available products that may be 
incorporated into the Work include, but are not limited to, the following: 
a. 
Meadows, W. R., Inc.; [Sealtight Hi-Spec] [Sealtight 3405]. 
b. 
Right Pointe; D-3405 Hot Applied Sealant. 
2.4 
JOINT-SEALANT BACKER MATERIALS 
A. 
General:  Provide joint-sealant backer materials that are nonstaining; are compatible with joint 
substrates, sealants, primers, and other joint fillers; and are approved for applications indicated 
by joint-sealant manufacturer based on field experience and laboratory testing. 
B. 
Backer Strips for Cold- and Hot-Applied Joint Sealants:  ASTM D 5249; Type 2; of thickness 
and width required to control joint-sealant depth, prevent bottom-side adhesion of sealant, and 
fill remainder of joint opening under sealant. 
2.5 
PRIMERS 
A. 
Primers:  Product recommended by joint-sealant manufacturer where required for adhesion of 
sealant to joint substrates indicated, as determined from preconstruction joint-sealant-substrate 
tests and field tests. 
PART 3 - EXECUTION 
3.1 
EXAMINATION 
A. 
Examine joints indicated to receive joint sealants, with Installer present, for compliance with 
requirements for joint configuration, installation tolerances, and other conditions affecting joint-
sealant performance. 
B. 
Proceed with installation only after unsatisfactory conditions have been corrected. 
3.2 
PREPARATION 
A. 
Surface Cleaning of Joints:  Clean out joints immediately before installing joint sealants to 
comply with joint-sealant manufacturer's written instructions. 
B. 
Joint Priming:  Prime joint substrates where indicated or where recommended in writing by 
joint-sealant manufacturer, based on preconstruction joint-sealant-substrate tests or prior 
experience.  Apply primer to comply with joint-sealant manufacturer's written instructions.  
Confine primers to areas of joint-sealant bond; do not allow spillage or migration onto adjoining 
surfaces.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
5 
 
 
 
 
3.3 
INSTALLATION OF JOINT SEALANTS 
A. 
General:  Comply with joint-sealant manufacturer's written installation instructions for products 
and applications indicated unless more stringent requirements apply. 
B. 
Joint-Sealant Installation Standard:  Comply with recommendations in ASTM C 1193 for use of 
joint sealants as applicable to materials, applications, and conditions indicated. 
C. 
Install joint-sealant backings of kind indicated to support joint sealants during application and at 
position required to produce cross-sectional shapes and depths of installed sealants relative to 
joint widths that allow optimum sealant movement capability. 
1. 
Do not leave gaps between ends of joint-sealant backings. 
2. 
Do not stretch, twist, puncture, or tear joint-sealant backings. 
3. 
Remove absorbent joint-sealant backings that have become wet before sealant application 
and replace them with dry materials. 
D. 
Install joint sealants using proven techniques that comply with the following and at the same 
time backings are installed: 
1. 
Place joint sealants so they directly contact and fully wet joint substrates. 
2. 
Completely fill recesses in each joint configuration. 
3. 
Produce uniform, cross-sectional shapes and depths relative to joint widths that allow 
optimum sealant movement capability. 
E. 
Tooling of Nonsag Joint Sealants:  Immediately after joint-sealant application and before 
skinning or curing begins, tool sealants according to the following requirements to form 
smooth, uniform beads of configuration indicated; to eliminate air pockets; and to ensure 
contact and adhesion of sealant with sides of joint: 
1. 
Remove excess joint sealant from surfaces adjacent to joints. 
2. 
Use tooling agents that are approved in writing by joint-sealant manufacturer and that do 
not discolor sealants or adjacent surfaces. 
F. 
Provide joint configuration to comply with joint-sealant manufacturer's written instructions 
unless otherwise indicated. 
3.4 
CLEANING 
A. 
Clean off excess joint sealant or sealant smears adjacent to joints as the Work progresses, by 
methods and with cleaning materials approved in writing by manufacturers of joint sealants and 
of products in which joints occur. 
3.5 
PROTECTION 
A. 
Protect joint sealants, during and after curing period, from contact with contaminating 
substances and from damage resulting from construction operations or other causes so sealants 
are without deterioration or damage at time of Substantial Completion.  If, despite such

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
6 
 
 
 
 
protection, damage or deterioration occurs, cut out and remove damaged or deteriorated joint 
sealants immediately and replace with joint sealant so installations in repaired areas are 
indistinguishable from the original work. 
3.6 
PAVEMENT-JOINT-SEALANT SCHEDULE 
A. 
Joint-Sealant Application:  Joints within cement concrete pavement 
1. 
Joint Location: 
a. 
Expansion and isolation joints in cast-in-place concrete pavement. 
b. 
Contraction joints in cast-in-place concrete slabs. 
c. 
Other joints as indicated. 
2. 
Silicone Joint Sealant for Concrete:  Single component, nonsag Single component, self-
leveling 
3. 
Urethane Joint Sealant for Concrete:  Multicomponent, pourable, traffic-grade 
4. 
Hot-Applied Joint Sealant for Concrete:  Single component 
B. 
Joint-Sealant Application:  Joints between cement concrete and asphalt pavement. 
1. 
Joint Location: 
a. 
Joints between concrete and asphalt pavement. 
b. 
Joints between concrete curbs and asphalt pavement. 
c. 
Other joints as indicated. 
2. 
Hot-Applied Joint Sealant for Concrete and Asphalt:  Single component 
C. 
Joint-Sealant Application:  Joints within cement concrete pavement at Splash Pad. 
1. 
Joint Location: 
a. 
Expansion and isolation joints in cast-in-place concrete pavement at splash pad. 
b. 
Contraction joints in cast-in-place concrete slabs pavement at splash pad. 
2. 
Silicone Joint Sealant for Concrete:  Single component, nonsag Single component, self-
leveling 
END OF SECTION 321373

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
1 
 
 
 
 
SECTION 32 15 40 - CRUSHED STONE PAVING 
PART 1 - GENERAL 
1.1 
RELATED DOCUMENTS 
A. 
Contract Drawings and general provisions of the Contract, including General and 
Supplementary Conditions and Division 01 Specification Sections, apply to this Section. 
1.2 
SUMMARY 
A. 
This Section includes requirements for demolition, earthwork, grading, furnishing, and 
placement of crushed stone paving. 
1. 
Furnish and place crushed stone paving, bonded with fine aggregate, constructed on a 
prepared underlying base course in accordance with these specifications and in 
conformity with the dimensions, typical cross section, and the lines and grades shown on 
the Contract Drawings.  The locations where crushed stone paving will be used are 
shown on the Contract Drawings. 
1.3 
REFERENCES 
A. 
ASTM C117 – Test Method for Materials Finer than No. 200 (75-um) Sieve in Mineral 
Aggregates by Washing. 
B. 
ASTM C136 – Method for Sieve Analysis of Fine and Coarse Aggregates. 
C. 
ASTM D4318 – Test Method for Liquid Limit, Plastic Limit and Plasticity Index of Soils. 
1.4 
SUBMITTALS 
A. 
Material Analysis:  Contractor shall provide copies of the following test data required by 
ASTM: 
1. 
ASTM C136 - Sieve Analysis. 
2. 
ASTM C127 - Specific Gravity and Absorption. 
3. 
ASTM C131 - L.A. Abrasion. 
B. 
Samples:  Provide a one (1) gallon sample of material for approval. 
1.5 
DELIVERY, STORAGE, AND HANDLING 
A. 
Packaged Materials:  Deliver packaged materials in original, unopened containers showing 
weight, certified analysis, name and address of manufacturer, and indication of conformance 
with state and federal laws if applicable. 
B. 
Bulk Materials: 
1. 
Do not dump or store bulk materials near structures, utilities, walkways and pavements, 
or on existing turf areas, plant materials or within critical root zones. 
2. 
Provide erosion-control measures to prevent erosion or displacement of bulk materials, 
discharge of soil-bearing water runoff, and airborne dust reaching adjacent properties, 
water conveyance systems, or walkways.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
2 
 
 
 
 
3. 
Accompany each delivery of bulk materials with appropriate certificates. 
C. 
Rejection of material. 
1. 
Evidence of inadequate protection or improper handling or storage shall be cause for 
rejection. 
2. 
Any product or material exhibiting signs of damage due to nonconformity to 
specifications or due to delivery, storage or handling shall be rejected by the Project 
Manager.  Contractor shall be responsible for hauling off-site and disposing of according 
to general conditions and codes of the governing jurisdiction. 
1.6 
PROJECT CONDITIONS 
A. 
Environmental requirements: Work shall occur only when weather and soil conditions permit in 
accordance with locally accepted practice. 
B. 
Field Measurements:  Verify actual grade elevations, service and utility locations, irrigation 
system components, and dimensions of plantings and construction contiguous with proposed 
crushed stone paving areas by field measurements before proceeding with work. 
C. 
Interruption of Existing Services or Utilities:  Do not interrupt services or utilities to facilities 
occupied by Owner or others. 
D. 
Existing Conditions:   
1. 
Utilities:  Determine location of existing and proposed underground utilities.  Perform 
work in a manner to avoid damage.  Hand excavate, as required. 
2. 
Excavation:  Maintain grade stakes set by others until removal is mutually agreed upon 
by parties concerned. 
E. 
Weather Limitations:  Proceed with installation only when existing and forecasted weather 
conditions permit planting to be performed when beneficial and optimum results may be 
obtained.   
1.7 
MAINTENANCE SERVICE 
A. 
General:  Maintain Work in accordance with Division 01. 
1. 
Maintenance Period:  Begin maintenance immediately after Work is completed.  
Maintain areas until the end of the Warranty period. 
1.8 
WARRANTY 
A. 
See Division 01 Section “Warranty”. 
PART 2 - PRODUCTS 
2.1 
CRUSHED STONE PAVING 
A. 
Type:  Crushed granite stone or gravel. Shall be unused material free of shale, lay, friable 
materials, organics and debris.  
1. 
Size Range:  1/4 inch Minus

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
3 
 
 
 
 
2. 
Color: See Materials Schedule L001 
3. 
Acceptable Supplier: Rock Pros 
B. 
Type: Crushed granite stone or gravel. Shall be unused material free of shale, lay, friable 
materials, organics and debris.  
1. 
Size Range:  1/2 inch Minus 
2. 
Color: See Materials Schedule L001 
3. 
Acceptable Supplier: Rock Pros 
C. 
Type: Crushed granite stone or gravel. Shall be unused material free of shale, lay, friable 
materials, organics and debris.  
1. 
Size Range:  1/2 inch Screened 
2. 
Color: See Materials Schedule L001 
3. 
Acceptable Supplier: Rock Pros 
D. 
Type: Crushed granite stone or gravel rip rap. Shall be unused material free of shale, lay, friable 
materials, organics and debris.  
1. 
Size Range:  4”-6” Screened 
2. 
Color: See Materials Schedule L001 
3. 
Acceptable Supplier: Rock Pros 
 
E. 
Type: Crushed granite stone or gravel rip rap. Shall be unused material free of shale, lay, friable 
materials, organics and debris.  
1. 
Size Range:  1”-3” Screened 
2. 
Color: See Materials Schedule L001 
3. 
Acceptable Supplier: Rock Pros 
F. 
 
2.2 
EXAMINATION 
A. 
Examine areas where the Work of this Section will be performed for compliance with 
requirements and conditions affecting installation and performance. 
1. 
Verify that no foreign or deleterious material or liquid such as paint, paint washout, 
concrete slurry, concrete layers or chunks, cement, plaster, oils, gasoline, diesel fuel, 
paint thinner, turpentine, tar, roofing compound, or acid has been deposited in soil within 
the work area. 
2. 
Verify that final grades are completed in accordance with the drawings. 
B. 
Proceed with installation only after unsatisfactory conditions have been corrected and approved 
by Project Manager. 
2.3 
QUALITY CONTROL 
A. 
Mock-up:  Provide field constructed sample installation of crushed stone paving,  and prepared  
subgrade.   
1. 
Mock-up to be ten foot (10’) x ten foot (10’) and located where directed by Construction 
Manager.  Mock-up shall include proposed edge and banding, and surface stabilization if 
specified.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
4 
 
 
 
 
2. 
Project Manager shall review mock up within forty eight (48) hours of notification by the 
contractor. 
3. 
Make necessary adjustments as directed by Project Manager. 
4. 
Obtain approval from Project Manager before proceeding with the Work. 
5. 
Retain and protect mock-up during construction as a standard for judging completed 
crushed stone paving work.  Do not remove or destroy mock-up until work is completed. 
6. 
Accepted and properly maintained sample installations may remain in completed work if 
approved in writing by Project Manager. 
7. 
All work shall match accepted field mock-up. 
2.4 
PREPARATION 
A. 
Protect structures, utilities, sidewalks, pavements, and other facilities, turf areas, existing 
landscape areas, and trees from damage. 
B. 
Install erosion-control measures to prevent erosion or displacement of soils and discharge of  
C. 
Install edging of type and in locations shown on drawings.  Obtain acceptance of layout by 
Project Manager before excavating or installing.  Make minor adjustments as required. 
2.5 
PLACEMENT OF CRUSHED STONE PAVING 
A. 
Cut earthwork to width of trail/area to receive crusher fines paving to approximate depth section 
as specified on the Contract Drawings.  Remove, haul and dispose of excess material off site, or 
use on-site with approval of Project Manager. 
B. 
Complete excavation required in sub-grade before fine grading and final compaction of sub-
grade is performed. Extend sub-grade compaction one foot (1’) beyond proposed edge of 
crushed stone paving or as indicated on drawings. 
1. 
Where earth moving is required    the sub-grade shall be compacted to ninety five percent 
(95%) standard proctor within two percent (2%) of the optimum moisture.   
2. 
Keep areas being graded or compacted shaped and drained during construction.  Ruts 
greater than or equal to 1 inch deep in sub-grade shall be graded out and reshaped as 
required, and re-compacted before crushed stone paving placement. 
C. 
Prior to placement of Crushed Stone Paving material, the sub-grade shall be proof rolled.  
Where soft spots are detected, scarify subgrade beneath Crushed Stone Paving trail to a 
minimum of six inch (6”) depth.  Moisture treat and compact to a minimum ninety five percent 
(95%) proctor density as determined by ASTM D698 or AASHTO T-99.  Take moisture density 
tests every two hundred fifty (250) lineal feet of trail or proof roll.  Treat and compact sub-
grade, leaving it 5-inches below final grade for placement of Crushed Stone Paving.  Compact 
material and retest by proof rolling to achieve approval of Project Manager. 
D. 
Install crushed stone paving only after excavation and construction work which might injure it 
have been completed, and after edging has been completely installed on the compacted sub-
grade.  Install crushed stone paving, over compacted base course in areas indicated on plan. 
E. 
Spread crushed stone evenly to fifty percent (50%) of specified depth.  Avoid segregation of 
aggregate and contamination with lower courses or sub-grade.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
5 
 
 
 
 
F. 
Compact to ninety five percent (95%) of maximum density as determined by ASTM D1557.  
1. 
Maintain surface course moisture content within plus/minus three percent (± 3%) of 
optimum.  Add water to quarry fines paving as required to achieve optimum moisture 
content and a uniform, compacted surface conforming to the finish grades indicated. 
2. 
Compact areas inaccessible to rolling by mechanical tamping. 
G. 
Protect crushed stone paving from soil or other contaminates during and following installation. 
H. 
Spread and compact additional crushed stone paving to achieve the required minimum 
compacted thickness.  Compact per 3.3.F above. 
2.6 
PLACEMENT OF STABILIZED CRUSHED STONE PAVING 
A. 
Do not allow traffic on stabilized crushed stone paving for two days.  
2.7 
MAINTENANCE AND REPAIRS: 
A. 
Crusher Fines Paving: 
1. 
Areas that do not compact, become eroded or are degraded in visual quality and/or 
performance as determined by the Project Manager are to be removed and/or repaired.  
Obtain approval of repair methods from Project Manager prior to affecting repairs.   
2.8 
CLEANUP AND PROTECTION 
A. 
All areas shall be clean at the end of each workday. 
B. 
The contractor shall maintain protection during installation, curing, and maintenance periods.   
1. 
Erect temporary fencing or barricades and warning signs as required protecting newly 
installed Crushed Stone Paving areas from traffic, other trades, and trespassers.  Maintain 
fencing and barricades throughout initial maintenance period and remove with approval 
of Project Manager. 
C. 
Project completion: All debris, soil, trash, and excavated and/or stripped material resulting from 
Crushed Stone Paving operations and unsuitable for or in excess of requirements for completing 
work of this Section shall be disposed of off-site.   
D. 
Maintain protection during installation and maintenance periods. See Division 1.  Treat, repair 
or replace damaged work as required. 
2.9 
QUALITY ASSURANCE 
A. 
Refer to Division 1 Section “Quality Assurance”.   
END OF SECTION 32 15 40

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
 
1 
 
 
 
 
SECTION 325200 – LANDSCAPE SYNTHETIC TURF 
PART 1 - GENERAL 
1.1 
SUMMARY 
A. 
Section Includes: 
1. 
Synthetic Turf 
1.2 
ACTION SUBMITTALS 
A. 
Product Data:  For each type of product. 
B. 
Samples:  For each exposed product and for each color and texture specified. 
C. 
Samples for Verification:  For each type of synthetic turf, supply 12”x12” sample for approval. 
1.3 
CLOSEOUT SUBMITTALS 
A. 
Maintenance Data:  Include in maintenance manuals. 
PART 2 - PRODUCTS 
2.1 
SYNTHETIC TURF, (1-19) 
A. 
Basis of Design Manufacturer: THE SYNTHETIC GRASS STORE 
B. 
Acceptable Product: Kool K-9 
2.2 
GENERAL FINISH REQUIREMENTS 
A. 
Appearance of Finished Work:  Noticeable variations in same piece are not acceptable.  
Variations in appearance of adjoining turf rolls are not acceptable. 
PART 3 - EXECUTION 
3.1 
EXAMINATION 
A. 
Examine areas and conditions, with Installer present, for compliance with requirements for 
correct and level finished grade, installation tolerances, and other conditions affecting 
performance of the Work.

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
 
2 
 
 
 
 
B. 
Proceed with installation only after unsatisfactory conditions have been corrected. 
3.2 
INSTALLATION, GENERAL 
A. 
Comply with manufacturer's written installation instructions unless more stringent requirements 
are indicated.   
END OF SECTION 325200

Tumbleweed Pickleball 
 
 
TECHNICAL SPECIFICATIONS 
Dig Studio 
 
90% SUBMITTAL 
  
1 
 
 
 
 
SECTION 329200 - 329400 
PART 1 - GENERAL 
1.1 
RELATED DOCUMENTS 
A. 
Refer to City of Chandler specifications for planting, irrigation and turf specifications.

EXHIBIT D 
 
Project Name: Pickleball Courts at Tumbleweed Park GMP I  
Page GMP-1 
Project No.: PR2206.401 
Rev. 1/16/2024 
ACCEPTED GMP/PRICE PROPOSAL

701 N. Cooper Rd. 
Gilbert, AZ 85233 
Phone: 480-892-0521 
Fax: 480-892-4932 
 
 
 
 
Pickleball Courts at Tumbleweed Park  
GMP 1 – Long-lead Procurement @ 90% Plans 
Project No: PR2206.401 
Submitted: 
June 5, 2024
Page 1 of 8

TABLE OF CONTENTS 
 
COVER PAGE  
 
 
 
 
 
 
 
 
 
1 
TABLE OF CONTENTS  
 
 
 
 
 
 
 
2 
PROJECT DESCRIPTION 
 
 
 
 
 
 
 
3 
SUMMARY 
 
 
 
 
 
 
 
 
 
 
4 
SCHEDULE OF VALUES 
 
 
 
 
 
 
      5 
ASSUMPTIONS & CLARIFICATIONS  
 
 
 
     6 – 7 
LIST OF GMP PLANS AND SPECIFICATIONS 
 
 
 
8 
 
 
 
 
 
 
 
 
 
 
 
 
 
Page 2 of 8

PROJECT DESCRIPTION 
 
This project includes construction services for 18 standard post-tensioned concrete pickleball courts 
and accompanying amenities including but not limited to: parking lot with approximately 130 spaces, 
sidewalk, landscape, irrigation, restroom, equipment storage, lighting, benches, practice areas, and 
shade canopies. Construction efforts may also include 3 standard post-tensioned concrete tennis 
courts at the Chandler Tennis Center. 
 
GMP 1 DESCRIPTION 
 
This GMP is for the procurement of specified materials necessary for the construction of the project 
that have been identified as long-lead procurement and/or considered to be at risk significant cost 
escalation. The intent of this GMP is to provide funding authorization for purchase orders of the listed 
materials so as to secure pricing and to increase the chances of the project being constructed on 
time.  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Page 3 of 8

EXHIBIT D
CM @ RISK GMP SUMMARY
Date:
6/5/2024
Cost Model
GMP 1
Amount
A. Cost of Work
    A1 Cost of Work (self perform, no mark-up)
$0.00
    A2 Cost of Work (subcontractors, suppliers, material)
$1,431,848.20
TOTAL COST OF WORK:
$1,424,149.80
B. General Conditions
$7,698.40
$1,431,848.20
C. CM@Risk's Fee 
8.50%
$121,707.10
SUBTOTAL 2 (A + B + C):
$1,553,555.30
D. Bonds and Insurance (on Subtotal 1) 
    D1 Bonds (Payment and Performance)
0.77%
$11,962.38
    D2 Insurance
1.00%
$15,535.55
$27,497.93
SUBTOTAL 3 (SUBTOTAL 2 + BONDS & INS):
$1,581,053.23
E. Sales Tax 
    E1 Sales Tax
5.07%
$80,159.40
    E2 Tax Credits
$0.00
$80,159.40
F. Approved Allowances
    F1 Owner's Allowance
$0.00
    F2 Owner's Allowance for Water and Wastewater
$0.00
$0.00
G. Contingencies
   G1 Owner Contingency
$44,417.45
   G2 Project Contingency (Design Development & Contractor)
$71,067.92
$115,485.37
$1,776,697.99
Establishment of Values:
a. Cost of Work (A) and Allowances (F) to be submitted with GMP Proposal.
b. General Conditions Cost (B) to be established in Baseline Cost Model.
c. CM@Risk Fee as set forth in Section 3.7.3 of this Contract
Project Name: Pickleball Courts at Tumbleweed Park 
Project Location: Pioneer Pkwy / Germann Rd
TOTAL CONTINGENCIES:
TOTAL GMP PROPOSAL:
City of Chandler Project No.: PR2206.401
SUBTOTAL 1 (Cost of Work) (A + B):
TOTAL BONDS & INSURANCE:
TOTAL SALES TAX:
TOTAL ALLOWANCES:
 
 
Page 4 of 8

Pickleball Courts at Tumbleweed Park 
Date:
6/4/24
Project No. PR2206.401
Schedule of Values
Cost Model - 90% 
Long 
Lead
Bid Item Description
 Bid Qty 
UM
Unit Cost
Total Cost
Weeks
2
SEWER
1
              
EA
5,500.00
$          
5,500.00
$               
2.7
Sewer Pipe Materials
1
              
LS
5,500.00
$           
5,500.00
$               
Weeks
3
WATER
1
              
EA
6,500.00
$          
6,500.00
$               
3.7
Water Pipe Materials
1
              
LS
6,500.00
$           
6,500.00
$               
Weeks
4
STORM DRAIN
1
              
EA
55,000.00
$        
55,000.00
$             
4.1
Storm Drain Materials
1
              
LS
55,000.00
$         
55,000.00
$             
Weeks
5
ELECTRICAL
1
              
EA
660,000.00
$      
660,000.00
$           
49+
5.1
800 amp SES
1
              
EA
45,000.00
$         
45,000.00
$             
18
5.14
Light Poles and Fixtures (Area and Site Lights)
1
              
LS
615,000.00
$      
615,000.00
$           
Weeks
9
FENCES & GATES
1
              
EA
74,553.60
$        
74,553.60
$             
9.2
6' Wind Screen
2,118
      
LF
9.85
$                  
20,862.30
$             
8
9.2a
10' Vinyl Wind Screen (blue) (this is an add, not a replacement)
2,118
      
LF
25.35
$                
53,691.30
$             
Weeks
10
SPORTS COURTS
1
              
EA
125,000.00
$      
125,000.00
$           
14
10.5
Practice Wall Materials (3Form)
40
            
LF
3,125.00
$           
125,000.00
$           
Weeks
11
MONUMENT & WAYFINDING
1
              
EA
20,000.00
$        
20,000.00
$             
11.3
Monument Materials 
1
              
LS
20,000.00
$         
20,000.00
$             
Weeks
12
AMENITIES
1
              
EA
40,420.80
$        
40,420.80
$             
12.6
Bike Rack
6
              
EA
1,437.00
$           
8,622.00
$               
12.7
Pickleball Bollards
8
              
EA
2,303.60
$           
18,428.80
$             
12.9
Situp Bench
1
              
EA
4,435.00
$           
4,435.00
$               
12.10
Lower Back Bench
1
              
EA
4,435.00
$           
4,435.00
$               
12.11
Stretch Station
1
              
EA
4,500.00
$           
4,500.00
$               
Weeks
14
RAMADAS
1
              
EA
126,985.00
$      
126,985.00
$           
30
14.1
20' x 20' Ramada
1
              
EA
47,061.00
$         
47,061.00
$             
30
14.2
20' x 38' Ramada
1
              
EA
79,924.00
$         
79,924.00
$             
Weeks
15
BATHROOM BUILDING
1
              
EA
225,000.00
$      
225,000.00
$           
16
15.2
Masonry Walls
1
              
LS
100,000.00
$      
100,000.00
$           
15.5
Roof & Structural Steel
1,759
      
SF
71.06
$                
125,000.00
$           
SUBTOTAL - COST
17
GENERAL CONDITIONS
1
              
EA
7,698.40
$          
7,698.40
$               
109-01
17.1
Project Manager
20
            
HR
110.45
$              
2,209.00
$               
109-01
17.2
Project Engineer
40
            
HR
77.23
$                
3,089.20
$               
109-01
17.6
Project Sponsor
10
            
HR
121.02
$              
1,210.20
$               
109-01
17.8
Truck, Pickup
70
            
HR
17.00
$                
1,190.00
$               
SUBTOTAL - GENERAL CONDITIONS
18
TENNIS COURTS 
1
              
EA
85,190.40
$        
85,190.40
$             
Weeks
Fence
1
              
EA
21,190.40
$        
21,190.40
$             
18.8
6' Vinyl Wind Screen
602
          
LF
9.85
$                  
5,929.70
$               
8
18.8a
10' Vinyl Wind Screen (blue) (this is an add, not a replacement)
602
          
LF
25.35
$                
15,260.70
$             
Weeks
Electrical
1
              
EA
64,000.00
$        
64,000.00
$             
18
18.16
Light Poles and Luminaires
1
              
EA
64,000.00
$         
64,000.00
$             
SUBTOTAL - TENNIS COURTS 
              1 
EA
GRAND TOTAL - COST
Contingency
6.50%
115,485.37
$           
Design Development Contingency
3.0%
53,300.94
$             
Cost Inflation Contingency
1.0%
17,766.98
$             
Contractor Contingency
0.0%
-
$                         
Owner Contingency
2.5%
44,417.45
$             
SUBTOTAL - CONTINGENCIES
$                                          115,485.37 
$                                      1,338,959.40 
$                                              7,698.40 
$                                      1,431,848.20 
$                                            85,190.40 
5
 
 
Page 5 of 8

ASSUMPTIONS & CLARIFICATIONS 
1) Section 2.7, 3.7, 4.1 – Pipe Materials:  
a. Costs are based on a pipe quote received from one of several pipe suppliers. We 
anticipate receiving several pipe quotes and will choose the most cost effective and 
responsible supplier.  
b. Storm Drain Materials included are for the Pickleball and Tennis Court areas of the 
project.  
2) Section 5.1, 5.14, 18.16 – Electrical: 
a. The furnish and install price for the 800 amp SES is included with a lead time of 49+ 
weeks.  
b. The furnish and install price for the Light poles and fixture package is included with a 
lead time of 18+ weeks.  
c. We received two proposals to date, one includes labor and the other is for materials 
only. We will receive the installed price from the second subcontractor and a third 
proposal prior to the submission of GMP 2 which will determine which subcontractor 
will be awarded the procurement and installation of the electrical work on the project.  
3) Section 9.2, 9.2a, 18.8, 18.8a – Fence:  
a. The furnish and install price of the designed 6’ tall wind screen is included.  
b. Alternate pricing to change the wind screen to 10’ tall in the color blue is included as 
an added cost to the 6’ tall wind screen cost. The alternate price does not replace 
the 6’ pricing, but is an added cost.  
c. We received one proposal to date. We will receive additional proposals prior to the 
submission of GMP 2 which will determine which subcontractor will be awarded the 
procurement and installation of the fence work on the project.  
4) Section 10.5 – Practice Walls:  
a. The practice walls materials is primarily the specified acrylic product from 3Form. 
We have included the cost received and included in a previous cost model. Updated 
pricing prior to the submission of GMP 2 will determine which if 3Form or an 
alternate product will be awarded the materials. A third party installer will be 
identified at that time as well.  
5) Section 11.3 – Monument Materials:  
a. We are still identifying material suppliers and contractors for the monument sign. 
The plans indicate a 3From product which is still being evaluated by 3From for 
constructability.  
 
Page 6 of 8

6) Section 12 – Amenities: 
a. Custom bike racks, bollards and fitness equipment suppliers is being evaluated at 
this time. Options will be presented as a part of the GMP 2 package. 
7) Section 14 – Ramadas: 
a. The plans specify Classic Recreation Systems. These ramadas are furnished 
through authorized sales representative Exerplay. The cost listed is a proposal 
received through Exerplay.  
b. We will evaluate alternative-like ramadas for evaluation. 
8) Section 14 – Bathroom Building: 
a. Masonry is a furnish and install cost quoted from one subcontractor, additional 
subcontractors will be evaluated with GMP 2.  
b. Roof and Structural Steel cost are established from the costs from the Tumbleweed 
Softball Diamond project currently being constructed, which includes a similar 
structure.  
 
 
 
 
 
 
 
 
 
 
 
 
 
Page 7 of 8

LIST OF GMP PLANS AND SPECIFICATIONS 
 
The following documents were referenced to establish pricing for this GMP: 
 
• Plans: “Tumbleweed Park Pickleball”; Project No. PR2206.201; 90% Design Submittal dated 
April 16, 2024 by Dig Studio 
 
• Specifications: Not available  
 
 
• Geotechnical: Not available 
 
Page 8 of 8

EXHIBIT E 
Project Name: Pickleball Courts at Tumbleweed Park GMP I  
Page SUB-1 
Project No.: PR2206.401 
Rev. 1/16/2024 
SUBCONTRACTOR DOCUMENTS WITH CM@RISK 
 
Any subcontractor assumptions, clarifications, exclusions, terms & conditions, signature blocks, etc. included are strictly between the CM@RISK 
and their subcontractors, and do not apply to the Agreement between the CM@RISK and the City. 
 
SUBCONTRACTOR’S LIST FORM 
If CM@Risk intends to subcontract any portion of this Agreement, the CM@Risk must submit the name, address, and contractor’s license number (if 
applicable) of each subcontractor, including the work component of such subcontracting.  Include the form with the bid submittal documents.  CM@Risk 
may make multiple copies of this form as needed.
Company Name: 
 
Contact Name: 
 
Contact Email: 
 
Contact Phone: 
 
Work Component: 
 
Percentage of Total 
Work Performed: 
 
 
 
Company Name: 
 
Contact Name: 
 
Contact Email: 
 
Contact Phone: 
 
Work Component: 
 
Percentage of Total 
Work Performed: 
 
 
 
Company Name: 
 
Contact Name: 
 
Contact Email: 
 
Contact Phone: 
 
Work Component: 
 
Percentage of Total 
Work Performed: 
 
Company Name: 
 
Contact Name: 
 
Contact Email: 
 
Contact Phone: 
 
Work Component: 
 
Percentage of Total 
Work Performed: 
 
 
 
Company Name: 
 
Contact Name: 
 
Contact Email: 
 
Contact Phone: 
 
Work Component: 
 
Percentage of Total 
Work Performed: 
 
 
 
Company Name: 
 
Contact Name: 
 
Contact Email: 
 
Contact Phone: 
 
Work Component: 
 
Percentage of Total 
Work Performed:

EXHIBIT F 
 
 
Project Name: Pickleball Courts at Tumbleweed Park GMP I  
Page GIS-1 
Project No.: PR2206.401 
Rev 1/16/2024 
                                                    GIS / GPS DATA DELIVERY REQUIREMENTS 
                                                                           (IF APPLICABLE) 
 
 
                                                                                     N/A

EXHIBIT G 
 
 
Project Name: Pickleball Courts at Tumbleweed Park GMP I  
Page SUBS-1 
Project No.: PR2206.401 
Rev 1/16/2024 
 
 
SUBCONTRACTOR DOCUMENTS WITH CM@RISK 
 
Any subcontractor assumptions, clarifications, exclusions, terms & conditions, 
signature blocks, etc. included are strictly between the CM@Risk and their 
subcontractors, and do not apply to the Agreement between the CM@Risk and the City. 
 
 
 
                                                                                    N/A