Capital Projects – Design Phase:

West Airport Facilities Upgrade (fmr Airport Operations Garage): City funded at $3.9 million.
Revised scope includes parking lot and aircraft observation area.  Design kick-off meeting 5/28.

Airport Fuel Tank Relocation: City funded at $610,000.  Awaiting construction permits.

Runway End Identifier Light (REIL) Installation Runway 4L-22R (North Runway): FAA funding for
$110,000.  Plans at 100%.  FAA environmental clearance received.

Runway 4R-22L Rehabilitation (South Runway): FAA grant for $350,000 for design approved.  Kick-
off meeting 4/6.  100% sealed plans to be submitted on 8/16.

Taxiway B Improvements- Phase 1: ADOT grant for $2,035,000 approved.  FAA environmental
clearance received.  30% design meeting with ADOT 5/24.  60% plans submitted and under review.
Capital Projects - Construction Phase:

Taxiway C Electrical:  City funding.  Addresses immediate issues with electrical infrastructure.  Cabling
and lighting system are functional but needs replacement.  5/20 Council approval of $495,479 contract
with DNG.  Approximately 7-week lead time for material.  7/18 preconstruction meeting.  9/4 meeting for
construction.

Automated Weather Observation System (AWOS) Replacement:  FAA funding for $200,000.  FAA
environmental clearance received.  Council approval on 6/13.  Precon meeting on 7/15 for long-lead
equipment procurement.

Former K&K Site Remediation: City funding for soil remediation near end of Cooper Road north of
Queen Creek.  Mobilization starting on 7/8 with remediation completed by mid-November.