Transportation Project Status Update - Sept. 2024

City of Chandler — Cancelled (2024-09-18)

View PDF Meeting page

Extracted text (via pymupdf) 5350 characters
ROADWAY AND TRAFFIC PROJECTS
Designer
Contractor
Status
Comments
PROJECT 
COST 
ESTIMATE
($MILLIONS)
ST1614 Chandler Heights Road Improv. [McQueen Road to Gilbert Road for two 
through lanes each direction]
Kimley-Horn
Granite Construction Co
Construction underway.  Completion scheduled for Fall 2024.
Federal funds
$20.90
ST1804 Chandler Heights Road Improv. [Gilbert Road to Val Vista Drive for two 
through lanes each direction]
Kimley-Horn
tbd
Project is moving forward to construction
Federal funds
$12.50
ST2001 Lindsay Road Improv. [Ocotillo Road to Hunt Highway for two
through lanes in each direction]
Kimley-Horn
tbd
Design in progress.  Bid scheduled for Spring 2025.
Federal funds
$27.20
ST2007 Hamilton Street Improv. [Appleby Road to Carob Drive]
Nfra Consultants
Redpoint
Construction underway.
$5.20
ST2009 Dobson Road Improv. at Intel Driveways #1 and #4 [Price Rd /
Market Pl to Chaparral Way]
Premier
DCS Contracting
Construction complete.  Close out in process.
Funded by 20% from Intel and 80% from State TPT per
ARS 42-5032.02
$0 City Cost (Intel
Funded)
ST2012 Arterial Congestion Monitoring [Install data collection devices at major 
intersections, and use data to map traffic congestion and mobility.]
Y.S. Mantri & Assoc.
CS Construction
Project to be complete end of July 2024.
Grant funds
$1.30
ST2103 Intersection Improv. at Ray Road and Dobson Road
Kimley Horn
tbd
Design underway. Construction anticipated Fall 2026.  
Grant funds & local funds
$11.85
ST2112 Alley Rehab PM10 Dust Emissions Reduction 2 (FMA Areas 16, 25,39, and 40) Premier / Olsson
Cactus Asphalt
Construction underway.
Federal funds
$2.4 (tbc)
ST2110 Chandler Video Detection Cameras 
Y.S. Mantri & Assoc
TCI
Construction complete.  Close out in process.
Federally Funded
$1.7(tbc)
ST2209 Chandler Local Detection and Communication Systems (Replaces 
existing video detecting cameras with new video cameras)
Kimley-Horn and 
Associates
CS Construction
Construction complete.  Close out in process.
Federally Funded
$0.50 
ST2210 Chandler ICM Detection and Communication Systems (Replaces existing 
video detecting cameras near freeways with new video cameras)
Kimley-Horn and 
Associates
CS Construction
Construction complete.  Close out in process.
Federally Funded
$0.60 
ST2301  Armstrong Way and Hamilton Street Improvement (Improves the south 
half of Armstrong Way and the west half of Hamilton Street)
EPS Group, Inc.
tbd
Design underway.  Construction tentatively scheduled 
Summer/Fall 2024.
$2.00 
ST2303 Cooper Road - Insight Loop Extension (Connects Cooper Road to Insight 
Way & Emmett Dr intersection)
Aztec
tbd
Design underway.
$9.30 
ST2309 Alma School Road Germann Rd to Queen Creek Rd (widening Alma School 
Road from Germann Road tro Queen Creek Road)
Olsson Associates
tbd
Design is currently ot 60%
$11.30 
ST2310 Alley Rehab PM10 Dust Emissions Reduction Phase 3 (FMA Areas 6, 24, 26, 
27)
Premier / Olsson
tbd
Design underway.
Federally Funded
$3.50 
ST2403 McQueen Road Improvements - Warner Road to Pecos Road Study 
(Study to widen McQueen Road in three phases from Warner Road to Pecos Road)
Kimley-Horn and 
Associates
tbd
Design Study only
Study is Locally Funded, Project will be Federally Funded and 
Design starts in FY 27-28
$84.00 
PEDESTRIAN, BICYCLE, AND TRANSIT PROJECTS
Designer
Contractor
Status
Comments
PROJECT 
COST 
ESTIMATE
ST2106 Frye Road Protected Bike Lanes [Paseo Trail to San Marcos
Elementary School]
TY Lin
tbd
Study completed by Y2K.  Redesign underway. Construction in 
early 2025.
$13.5 Million grant awarded for construction and $650,000
for design.
$14.00
TP2202  Kyrene Branch and Highline Canal Shared Use Paths
Kimley-Horn
tbd
Study completed by Kimley-Horn.  Design underway.  
Construction in mid-late 2025.
Federal grants have been awarded to fund study, design
and construction.
$4.50
Ashley and Paseo Trails Connection
Y2K Engineering
tbd
Study completed by Y2K.  Design underway.  Construction in 
2025.
Study was federally funded.  Construction and design are 
locally funded.
$1.00
Hunt Highway Bicycle Improvements and Traffic Calming Study
Rick Engineering
tbd
Study complete.
Federally funded study, looking at a potential shared use path 
or separated bike lanes along with recommendations for 
traffic calming between Cooper Rd. and Val Vista Dr. 
$0.10
Arizona Avenue Shared Use Path Study
Y2K Engineering
tbd
Study analyzing feasibility of expanding 4'-6' sidewalks to a 10'-
12' shared use path on Arizona Avenue between Ray Road and 
the Western Canal.
Federally funded study.
$0.10
Pedestrian Connectivity Study
Y2K Engineering
tbd
Study to create a sidewalk inventory and develop a plan to 
address gaps in sidewalks.
Locally funded study.
$0.10
Chandler Flex
NA
Via
Initial study completed in collaboration with Valley Metro - 
operations began July 11, 2022. Completed Airpark Area Flexible 
Transit Study. Began minor implementation of study 
recommendations through a two square-mile expansion 
between Arizona Ave. and McQueen Rd. and Queen Creek Rd. 
and Chandler Height Rd.  and opened the school-only zone 
(north of Chandler Blvd.) to all trip types.
Awarded $2 Million grant for project startup and two years of 
operations.  Awarded $1 Million congressionally-directed 
spending grant to continue operations
$2.10
Transportation Project Status -September 2024