Transportation Project Status Update - Sept. 2024
Extracted text (via pymupdf)
5350 characters
ROADWAY AND TRAFFIC PROJECTS Designer Contractor Status Comments PROJECT COST ESTIMATE ($MILLIONS) ST1614 Chandler Heights Road Improv. [McQueen Road to Gilbert Road for two through lanes each direction] Kimley-Horn Granite Construction Co Construction underway. Completion scheduled for Fall 2024. Federal funds $20.90 ST1804 Chandler Heights Road Improv. [Gilbert Road to Val Vista Drive for two through lanes each direction] Kimley-Horn tbd Project is moving forward to construction Federal funds $12.50 ST2001 Lindsay Road Improv. [Ocotillo Road to Hunt Highway for two through lanes in each direction] Kimley-Horn tbd Design in progress. Bid scheduled for Spring 2025. Federal funds $27.20 ST2007 Hamilton Street Improv. [Appleby Road to Carob Drive] Nfra Consultants Redpoint Construction underway. $5.20 ST2009 Dobson Road Improv. at Intel Driveways #1 and #4 [Price Rd / Market Pl to Chaparral Way] Premier DCS Contracting Construction complete. Close out in process. Funded by 20% from Intel and 80% from State TPT per ARS 42-5032.02 $0 City Cost (Intel Funded) ST2012 Arterial Congestion Monitoring [Install data collection devices at major intersections, and use data to map traffic congestion and mobility.] Y.S. Mantri & Assoc. CS Construction Project to be complete end of July 2024. Grant funds $1.30 ST2103 Intersection Improv. at Ray Road and Dobson Road Kimley Horn tbd Design underway. Construction anticipated Fall 2026. Grant funds & local funds $11.85 ST2112 Alley Rehab PM10 Dust Emissions Reduction 2 (FMA Areas 16, 25,39, and 40) Premier / Olsson Cactus Asphalt Construction underway. Federal funds $2.4 (tbc) ST2110 Chandler Video Detection Cameras Y.S. Mantri & Assoc TCI Construction complete. Close out in process. Federally Funded $1.7(tbc) ST2209 Chandler Local Detection and Communication Systems (Replaces existing video detecting cameras with new video cameras) Kimley-Horn and Associates CS Construction Construction complete. Close out in process. Federally Funded $0.50 ST2210 Chandler ICM Detection and Communication Systems (Replaces existing video detecting cameras near freeways with new video cameras) Kimley-Horn and Associates CS Construction Construction complete. Close out in process. Federally Funded $0.60 ST2301 Armstrong Way and Hamilton Street Improvement (Improves the south half of Armstrong Way and the west half of Hamilton Street) EPS Group, Inc. tbd Design underway. Construction tentatively scheduled Summer/Fall 2024. $2.00 ST2303 Cooper Road - Insight Loop Extension (Connects Cooper Road to Insight Way & Emmett Dr intersection) Aztec tbd Design underway. $9.30 ST2309 Alma School Road Germann Rd to Queen Creek Rd (widening Alma School Road from Germann Road tro Queen Creek Road) Olsson Associates tbd Design is currently ot 60% $11.30 ST2310 Alley Rehab PM10 Dust Emissions Reduction Phase 3 (FMA Areas 6, 24, 26, 27) Premier / Olsson tbd Design underway. Federally Funded $3.50 ST2403 McQueen Road Improvements - Warner Road to Pecos Road Study (Study to widen McQueen Road in three phases from Warner Road to Pecos Road) Kimley-Horn and Associates tbd Design Study only Study is Locally Funded, Project will be Federally Funded and Design starts in FY 27-28 $84.00 PEDESTRIAN, BICYCLE, AND TRANSIT PROJECTS Designer Contractor Status Comments PROJECT COST ESTIMATE ST2106 Frye Road Protected Bike Lanes [Paseo Trail to San Marcos Elementary School] TY Lin tbd Study completed by Y2K. Redesign underway. Construction in early 2025. $13.5 Million grant awarded for construction and $650,000 for design. $14.00 TP2202 Kyrene Branch and Highline Canal Shared Use Paths Kimley-Horn tbd Study completed by Kimley-Horn. Design underway. Construction in mid-late 2025. Federal grants have been awarded to fund study, design and construction. $4.50 Ashley and Paseo Trails Connection Y2K Engineering tbd Study completed by Y2K. Design underway. Construction in 2025. Study was federally funded. Construction and design are locally funded. $1.00 Hunt Highway Bicycle Improvements and Traffic Calming Study Rick Engineering tbd Study complete. Federally funded study, looking at a potential shared use path or separated bike lanes along with recommendations for traffic calming between Cooper Rd. and Val Vista Dr. $0.10 Arizona Avenue Shared Use Path Study Y2K Engineering tbd Study analyzing feasibility of expanding 4'-6' sidewalks to a 10'- 12' shared use path on Arizona Avenue between Ray Road and the Western Canal. Federally funded study. $0.10 Pedestrian Connectivity Study Y2K Engineering tbd Study to create a sidewalk inventory and develop a plan to address gaps in sidewalks. Locally funded study. $0.10 Chandler Flex NA Via Initial study completed in collaboration with Valley Metro - operations began July 11, 2022. Completed Airpark Area Flexible Transit Study. Began minor implementation of study recommendations through a two square-mile expansion between Arizona Ave. and McQueen Rd. and Queen Creek Rd. and Chandler Height Rd. and opened the school-only zone (north of Chandler Blvd.) to all trip types. Awarded $2 Million grant for project startup and two years of operations. Awarded $1 Million congressionally-directed spending grant to continue operations $2.10 Transportation Project Status -September 2024