Project Name: HANGAR AREA PAVEMENT RECONSTRUCTION
Page 1
Project No.: AI2501.201
Rev. 1/12/2024
PROFESSIONAL SERVICES AGREEMENT
Design Services
HANGAR AREA PAVEMENT RECONSTRUCTION
Project No. AI2501.201
Council Date: October 17, 2024
This Agreement (“Agreement”) is made and entered into on the ______ day of_________________, 2024
(“Effective Date”), by and between City of Chandler, an Arizona municipal corporation, ("City''),
and Dibble & Associates Consulting Engineers, Inc. dba Dibble, an Arizona S Corporation,
("Consultant") (City and Consultant may individually be referred to as “Party” and collectively
referred to as “Parties”).
RECITALS
A. City proposes to engage Consultant to provide Design Services for HANGAR AREA
PAVEMENT RECONSTRUCTION project as more fully described in Exhibit "A", which is attached
to and made a part of this Agreement by this reference.
B. Consultant is ready, willing, and able to provide the services described in Exhibit “A” for
the compensation and fees set forth and as described in Exhibit ”B”, which is attached to
and made a part of this Agreement by this reference.
C. City desires to enter into an Agreement with Consultant to provide these services under
the terms and conditions set forth in this Agreement.
AGREEMENT
NOW, THEREFORE, in consideration of the premises and the mutual promises contained in this
Agreement, City and Consultant agree as follows:
SECTION I--CONSULTANT’S SERVICES
Consultant must perform the services described in Exhibit “A” to City’s satisfaction within the
terms and conditions of this Agreement and within the care and skill that a person who
provides similar services in Chandler, Arizona exercises under similar conditions. All work or
services furnished by Consultant under this Agreement must be performed in a skilled and
workmanlike manner. All fixtures, furnishings, and equipment furnished by Consultant as
part of the work or services under this Agreement must be new, or the latest model, and of
the most suitable grade and quality for the intended purpose of the work or service.
Project Name: HANGAR AREA PAVEMENT RECONSTRUCTION
Page 2
Project No.: AI2501.201
Rev. 1/12/2024
SECTION II--PERIOD OF SERVICE
Consultant must perform the services described in Exhibit “A” for the term of this
Agreement. Unless amended in writing by the Parties, the Agreement term expires 365
calendar days after the Notice to Proceed (NTP) Date.
SECTION III--PAYMENT OF COMPENSATION AND FEES
Unless amended in writing by the Parties, Consultant’s compensation and fees as more fully
described in Exhibit “B” for performance of the services approved and accepted by City
under this Agreement must not exceed $328,578 for the full term of the Agreement.
Consultant may not increase any compensation or fees under this Agreement without the
City’s prior written consent. Consultant must submit monthly requests for payment of
services approved and accepted during the previous billing period and must include, as
applicable, detailed invoices and receipts, a narrative description of the tasks accomplished
during the billing period, a list of any deliverables submitted, and any subconsultant’s or
supplier’s actual requests for payment plus similar narrative and listing of their work.
Consultant must submit an Application and Certification for Payment Sheet with the monthly
request for payment to: CapitalProjects.Payables@chandleraz.gov. Payment for those
services negotiated as a lump sum will be made in accordance with the percentage of the
work completed during the preceding billing period. Services negotiated as a not-to-exceed
fee will be paid in accordance with the work effort expended on the service during the
preceding month. All requests for payment must be submitted to City for review and
approval. City will make payment for approved and accepted services within 30 calendar days
of City’s receipt of the request for payment. Consultant bears all responsibility and liability for
any and all tax obligations that result from Consultant’s performance under this Agreement.
SECTION IV--CITY'S OBLIGATIONS
As part of Consultant’s services under this Agreement, City will provide furnished items,
services, or obligations as detailed in Exhibit “D”.
SECTION V--GENERAL CONDITIONS
5.1 Notices. Unless otherwise provided herein, demands under this Agreement must be in
writing and will be deemed to have been duly given and received either (a) on the date of
service if personally served on the party to whom notice is to be given, or (b) on the third day
after the date of the postmark of deposit by first class United States mail, registered or
certified, postage prepaid and properly addressed as follows:
Project Name: HANGAR AREA PAVEMENT RECONSTRUCTION
Page 3
Project No.: AI2501.201
Rev. 1/12/2024
To City:
City of Chandler - Public Works & Utilities Department
Attn: CIP City Engineer: Daniel Haskins, P.E.
P.O. Box 4008, Mail Stop 407
Chandler, AZ 85244-4008
Phone: 480-782-3335 Email: daniel.haskins@chandleraz.gov
With a copy to:
City of Chandler - Public Works & Utilities Department
Attn: Hafiz Noor, Project Manager
P.O. Box 4008, Mail Stop 407, Chandler, AZ 85244-4008
Phone: 480-782-3324 Email: Hafiz.Noor@chandleraz.gov
To Consultant:
LEGAL COMPANY NAME:
DIBBLE & ASSOCIATES CONSULTING
ENGINEERS, INC.
Mailing Address:
3020 East Camelback Road, Suite 201, Phoenix, AZ
85016
Physical Address: SAME
Statutory Agent Name: Susan Detwiler
Statutory Agent Mailing Address:
3020 East Camelback Road, Suite 201,
Phoenix, AZ 85016
Statutory Agent Physical Address: SAME
CONSULTANT’S AUTHORIZED PROJECT REPRESENTATIVE
Name:
Ryan Toner
Title:
Airport Development Business Unit Leader
Phone: (602) 957-1155
Email:
ryan.toner@dibblecorp.com
5.2 Records/Audit. Records of Consultant’s direct personnel payroll, reimbursable expenses
pertaining to this Agreement and records of accounts between City and Consultant must be
kept on the basis of generally accepted accounting principles and must be made available to
City and its auditors for up to three years following City’s final acceptance of the services
under this Agreement (this requirement is increased to five years if construction of this
project is federally funded). City, its authorized representative, or any federal agency,
reserves the right to audit Consultant’s records to verify the accuracy and appropriateness of
all cost and pricing data, including data used to negotiate this Agreement and any
amendments. City reserves the right to decrease the total amount of Agreement price or
payments made under this Agreement or request reimbursement from Consultant following
final Agreement payment on this Agreement if, upon audit of Consultant’s records, the audit
discloses Consultant has provided false, misleading, or inaccurate cost and pricing data.
Consultant will include a similar provision in all of its Agreements with subconsultants who
provide services under the Agreement to ensure that City, its authorized representative, or
Project Name: HANGAR AREA PAVEMENT RECONSTRUCTION
Page 4
Project No.: AI2501.201
Rev. 1/12/2024
the appropriate federal agency, has access to the subconsultants’ records to verify the
accuracy of all cost and pricing data. City reserves the right to decrease Agreement price or
payments made on this Agreement or request reimbursement from Consultant following
final payment on this Agreement if the above provision is not included in subconsultant
agreements, and one or more subconsultants refuse to allow City to audit their records to
verify the accuracy and appropriateness of all cost and pricing data. If, following an audit of
this Agreement, the audit discloses Consultant has provided false, misleading, or inaccurate
cost and pricing data, and the cost discrepancies exceed 1% of the total Agreement billings,
Consultant will be liable for reimbursement of the reasonable, actual cost of the audit.
5.3 Alteration in Character of Work. Whenever an alteration in the character of work results
in a substantial change in this Agreement, thereby materially increasing or decreasing the
scope of services, cost of performance, or Project schedule, the work will be performed as
directed by City. However, before any modified work is started, a written amendment must
be approved and executed by City and Consultant. Such amendment must not be effective
until approved by City. Additions to, modifications, or deletions from this Agreement as
provided herein may be made, and the compensation to be paid to Consultant may
accordingly be adjusted by mutual agreement of the Parties. It is distinctly understood and
agreed that no claim for extra services or materials furnished by Consultant will be allowed
by City except as provided herein, nor must Consultant do any work or furnish any materials
not covered by this Agreement unless such work is first authorized in writing. Any such work
or materials furnished by Consultant without prior written authorization will be at
Consultant’s own risk, cost, and expense, and Consultant hereby agrees that without written
authorization Consultant will make no claim for compensation for such work or materials
furnished.
5.4 Termination. City and Consultant hereby agree to the full performance of the covenants
contained herein, except that City reserves the right, at its discretion and without cause, to
terminate or abandon any service provided for in this Agreement, or abandon any portion of
the Project for which services have been performed by Consultant. In the event City abandons
or suspends the services, or any part of the services as provided in this Agreement, City will
notify Consultant in writing and immediately after receiving such notice, Consultant must
discontinue advancing the work specified under this Agreement. Upon such termination,
abandonment, or suspension, Consultant must deliver to City all drawings, plans,
specifications, special provisions, estimates and other work entirely or partially completed,
together with all unused materials supplied by City. Consultant must appraise the work
Consultant has completed and submit Consultant’s appraisal to City for evaluation. City may
inspect Consultant’s work to appraise the work completed. Consultant will receive
compensation in full for services performed to the date of such termination. The fee will be
paid in accordance with Section Ill of this Agreement, and as mutually agreed upon by
Consultant and City. If there is no mutual agreement on payment, the final determination will
be made in accordance with the "Disputes" provision in this Agreement. However, in no event
may the fee exceed the fee set forth in Section Ill of this Agreement nor as amended in
accordance with Section "Alteration in Character of Work." City will make the final payment
within 60 days after Consultant has delivered the last of the partially completed items and
the Parties agree on the final fee. If City is found to have improperly terminated the
Agreement for cause or default, the termination will be converted to a termination for
convenience in accordance with the provisions of this Agreement.
Project Name: HANGAR AREA PAVEMENT RECONSTRUCTION
Page 5
Project No.: AI2501.201
Rev. 1/12/2024
5.5 Indemnification. To the extent permitted by law, the Consultant ("lndemnitor") must
indemnify, save and hold harmless City and its officers, officials, agents and employees
("lndemnitee") from any and all claims, actions, liabilities, damages, losses or expenses
(including court costs, attorneys' fees and costs of claim processing, investigation and
litigation) ("Claims") caused or alleged to be caused, in whole or in part, by the wrongful,
negligent or willful acts, or errors or omissions of Consultant or any of its owners, officers,
directors, agents, employees, or subconsultants in connection with this Agreement. This
indemnity includes any claim or amount arising out of or recovered under workers'
compensation law or on account of the failure of Consultant to conform to any federal, state
or local law, statute, ordinance, rule, regulation or court decree. Consultant must indemnify
lndemnitee from and against any and all Claims, except those arising solely from
lndemnitee's own negligent or willful acts or omissions. Consultant is responsible for primary
loss investigation, defense and judgment costs where this indemnification applies. In
consideration of the award of this Agreement, Consultant agrees to waive all rights of
subrogation against lndemnitee for losses arising from or related to this Agreement. The
obligations of Consultant under this provision survive the termination or expiration of this
Agreement.
5.6 Insurance Requirements. Consultant must procure insurance under the terms and
conditions and for the amounts of coverage set forth in Exhibit “C” against claims that may
arise from or relate to performance of the work under this Agreement by Consultant and its
agents, representatives, employees, and subconsultants. Consultant and any subconsultant
must maintain this insurance until all of their obligations have been discharged, including any
warranty periods under this Agreement. These insurance requirements are minimum
requirements for this Agreement and in no way limit the indemnity covenants contained in
this Agreement. City in no way warrants that the minimum limits stated in Exhibit “C” are
sufficient to protect Consultant from liabilities that might arise out of the performance of the
work under this Agreement by Consultant, Consultant’s agents, representatives, employees,
or subconsultants. Consultant is free to purchase such additional insurance as may be
determined necessary.
5.7 Cooperation and Further Documentation. Consultant agrees to provide City such other
duly executed documents as may be reasonably requested by City to implement the intent
of this Agreement.
5.8 Successors and Assigns. City and Consultant each bind itself, its partners, successors,
assigns, and legal representatives to the other party to this Agreement and to the partners,
successors, assigns, and legal representatives of such other party in respect to all covenants
of this Agreement. Neither City nor Consultant may assign, sublet, or transfer its interest in
this Agreement without the written consent of the other party. In no event may any
contractual relation be created between any third party and City.
5.9 Disputes. In any dispute arising out of an interpretation of this Agreement or the duties
required not disposed of by agreement between Consultant and City, the final determination
at the administrative level will be made by City Engineer.
Project Name: HANGAR AREA PAVEMENT RECONSTRUCTION
Page 6
Project No.: AI2501.201
Rev. 1/12/2024
5.10 Completeness and Accuracy of Consultant’s Work. Consultant must be responsible for
the completeness and accuracy of Consultant’s services, data, and other work prepared or
compiled under Consultant’s obligation under this Agreement and must correct, at
Consultant’s expense, all willful or negligent errors, omissions, or acts that may be discovered.
Correction of errors disclosed and determined to exist during any construction of the project on
architectural or engineering drawings and specifications must be accomplished by Consultant.
The cost of the design necessary to correct those errors attributable to Consultant and any
damage incurred by City as a result of additional construction costs caused by such engineering
or architectural errors will be chargeable to Consultant and will not be considered a cost of the
Work. The fact that City has accepted or approved Consultant’s work will in no way relieve
Consultant of any of Consultant’s responsibilities.
5.11 Reporting. Written monthly reports, along with updated work schedules, will be made by
Consultant in the format prescribed by City. These reports will be delivered to City per schedule.
When requested by City, Consultant will attend Council meetings and provide finished documents
including correspondence for Council action, supporting charts, graphs, drawings and colored
slides of same.
5.12 Withholding Payment. City reserves the right to withhold funds from Consultant’s
payments up to the amount equal to the claims City may have against Consultant until such
time that a settlement on those claims has been reached.
5.13 City's Right of Cancellation. The Parties acknowledge that this Agreement is subject to
cancellation by City under the provisions of Section 38-511, Arizona Revised Statutes (A.R.S.).
5.14 Independent Consultant. For this Agreement Consultant constitutes an independent
contractor. Any provisions in this Agreement that may appear to give City the right to direct
Consultant as to the details of accomplishing the work or to exercise a measure of control
over the work means that Consultant must follow the wishes of City as to the results of the
work only. These results must comply with all applicable laws and ordinances.
5.15 Project Staffing. Prior to the start of any work under this Agreement, Consultant must
submit to City detailed resumes of key personnel that will be involved in performing services
prescribed in the Agreement. City hereby acknowledges its acceptance of such personnel to
perform services under this Agreement. At any time hereafter that Consultant desires to
change key personnel while performing under the Agreement, Consultant must submit the
qualifications of the new personnel to City for prior approval. Key personnel include, but are
not limited to, principals-in-charge, project manager, and project Consultant. Consultant will
maintain an adequate and competent staff of qualified persons, as may be determined by
City, throughout the performance of this Agreement to ensure acceptable and timely
completion of the Scope of Services. If City objects, with reasonable cause, to any of
Consultant’s staff, Consultant must take prompt corrective action acceptable to City and, if
required, remove such personnel from the Project and replace with new personnel agreed to
by City.
5.16 Consultants or Subconsultants. Prior to beginning the work, Consultant must furnish City
for approval the names of consultants or subconsultants to be used under this Agreement.
Any subsequent changes are subject to City’s written prior approval.
Project Name: HANGAR AREA PAVEMENT RECONSTRUCTION
Page 7
Project No.: AI2501.201
Rev. 1/12/2024
5.17 Force Majeure. If either party is delayed or prevented from the performance of any act
required under this Agreement by reason of acts of God or other cause beyond the control
and without fault of the Party (financial inability excepted), performance of that act may be
excused, but only for the period of the delay, if the Party provides written notice to the other
Party within ten days of such act. The time for performance of the act may be extended for a
period equivalent to the period of delay from the date written notice is received by the other
Party.
5.18 Compliance with Federal Laws. Consultant understands and acknowledges the
applicability of the Americans with Disabilities Act, the Immigration Reform and Control Act
of 1986 and the Drug Free Workplace Act of 1989 to it. Consultant agrees to comply with these
laws in performing this Agreement and to permit City to verify such compliance.
5.19 No Israel Boycott. By entering into this Agreement, Consultant certifies that Consultant
is not currently engaged in, and agrees for the duration of the Agreement, not to engage in a
boycott of Israel as defined by state statute.
5.20 Legal Worker Requirements. A.R.S. § 41-4401 prohibits City from awarding an Agreement
to any consultant who fails, or whose subconsultants fail, to comply with A.R.S. § 23-214(A).
Therefore, Consultant agrees Consultant and each subconsultant it uses warrants their
compliance with all federal immigration laws and regulations that relate to their employees
and their compliance with § 23-214, subsection A. A breach of this warranty will be deemed a
material breach of the Agreement and may be subject to penalties up to and including
termination of the Agreement. City retains the legal right to inspect the papers of any
Consultant’s or subconsultant’s employee who provides services under this Agreement to
ensure that Consultant and subconsultants comply with the warranty under this provision.
5.21 Lawful Presence Requirement. A.R.S. §§ 1-501 and 1-502 prohibit City from awarding an
Agreement to any natural person who cannot establish that such person is lawfully present
in the United States. To establish lawful presence, a person must produce qualifying
identification and sign a City-provided affidavit affirming that the identification provided is
genuine. This requirement will be imposed at the time of Agreement award. This requirement
does not apply to business organizations such as corporations, partnerships, or limited
liability companies.
5.22 Covenant Against Contingent Fees. Consultant warrants that no person has been
employed or retained to solicit or secure this Agreement upon an agreement or
understanding for a commission, percentage, brokerage, or contingent fee, and that no
member of the Chandler City Council, or any City employee has any interest, financially, or
otherwise, in Consultant’s firm. For breach or violation of this warrant, City may annul this
Agreement without liability or, at its discretion, to deduct from the Agreement price or
consideration, the full amount of such commission, percentage, brokerage, or contingent fee.
5.23 Non-Waiver Provision. The failure of either Party to enforce any of the provisions of this
Agreement or to require performance of the other Party of any of the provisions hereof must
not be construed to be a waiver of such provisions, nor must it affect the validity of this
Project Name: HANGAR AREA PAVEMENT RECONSTRUCTION
Page 8
Project No.: AI2501.201
Rev. 1/12/2024
Agreement or any part thereof, or the right of either Party to thereafter enforce each and
every provision.
5.24 Disclosure of Information Adverse to City’s Interests. To evaluate and avoid potential
conflicts of interest, Consultant must provide written notice to City, as set forth in this Section,
of any work or services performed by Consultant for third parties that may involve or be
associated with any real property or personal property owned or leased by City. Such notice
must be given 7 business days prior to commencement of the services by Consultant for a
third party, or 7 business days prior to an adverse action as defined below. Written notice
and disclosure must be sent in accordance with Section 6.7 above. An adverse action under
this Agreement includes, but is not limited to: (a) using data as defined in the Agreement
acquired in connection with this Agreement to assist a third party in pursuing administrative
or judicial action against City; or (b) testifying or providing evidence on behalf of any person
in connection with an administrative or judicial action against City; or (c) using data to produce
income for Consultant or its employees independently of performing the services under this
Agreement, without the prior written consent of City. Consultant represents that except for
those persons, entities, and projects identified to City, the services performed by Consultant
under this Agreement are not expected to create an interest with any person, entity, or third
party project that is or may be adverse to City’s interests. Consultant’s failure to provide a
written notice and disclosure of the information as set forth in this Section constitute a
material breach of this Agreement.
5.25 Data Confidentiality and Data Security. As used in the Agreement, "data" means all
information, whether written or verbal, including plans, photographs, studies, investigations,
audits, analyses, samples, reports, calculations, internal memos, meeting minutes, data field
notes, work product, proposals, correspondence and any other similar documents or
information prepared by, obtained by, or transmitted to Consultant or its subconsultants in
the performance of this Agreement. The Parties agree that all data, regardless of form,
including originals, images, and reproductions, prepared by, obtained by, or transmitted to
Consultant or its subconsultants in connection with Consultant’s or its subconsultant’s
performance of this Agreement is confidential and proprietary information belonging to City.
Except as specifically provided in this Agreement, Consultant or its subconsultants must not
divulge data to any third party without City’s prior written consent. Consultant or its
subconsultants must not use the data for any purposes except to perform the services
required under this Agreement. These prohibitions do not apply to the following data
provided to Consultant or its subconsultants have first given the required notice to City: (a)
data which was known to Consultant or its subconsultants prior to its performance under this
Consultant or its subconsultants by a third party, who to the best of Consultant’s or its
subconsultants’ knowledge and belief, had the legal right to make such disclosure and
Consultant or its subconsultants are not otherwise required to hold such data in confidence;
or (c) data which is required to be disclosed by virtue of law, regulation, or court order, to
which Consultant or its subconsultants are subject. In the event Consultant or its
subconsultants are required or requested to disclose data to a third party, or any other
information to which Consultant or its subconsultants became privy as a result of any other
Agreement with City, Consultant must first notify City as set forth in this Section of the request
or demand for the data. Consultant or its subconsultants must give City sufficient facts so
that City can be given an opportunity to first give its consent or take such action that City may
deem appropriate to protect such data or other information from disclosure. All data must
Project Name: HANGAR AREA PAVEMENT RECONSTRUCTION
Page 9
Project No.: AI2501.201
Rev. 1/12/2024
continue to be subject to the confidentiality agreements of this Agreement. Consultant or its
subconsultants assume all liability to maintain the confidentiality of the data in its possession
and agrees to compensate City if any of the provisions of this Section are violated by
Consultant, its employees, agents or subconsultants. Solely for the purposes of seeking
injunctive relief, it is agreed that a breach of this Section must be deemed to cause irreparable
harm that justifies injunctive relief in court. Consultant agrees that the requirements of this
Section must be incorporated into all subagreements entered into by Consultant. A violation
of this Section may result in immediate termination of this Agreement without notice.
5.26 Personal Identifying Information-Data Security. Personal identifying information,
financial account information, or restricted City information, whether electronic format or
hard copy, must be secured and protected at all times by Consultant or its subconsultants. At
a minimum, Consultant or its subconsultants must encrypt or password-protect electronic
files. This includes data saved to laptop computers, computerized devices, or removable
storage devices. When personal identifying information, financial account information, or
restricted City information, regardless of its format, is no longer necessary, the information
must be redacted or destroyed through appropriate and secure methods that ensure the
information cannot be viewed, accessed, or reconstructed. In the event that data collected or
obtained by Consultant or its subconsultants in connection with this Agreement is believed
to have been compromised, Consultant or its subconsultants must immediately notify City
contact. Consultant agrees to reimburse City for any costs incurred by City to investigate
potential breaches of this data and, where applicable, the cost of notifying individuals who
may be impacted by the breach. Consultant agrees that the requirements of this Section must
be incorporated into all subcontracts entered into by Consultant. It is further agreed that a
violation of this Section must be deemed to cause irreparable harm that justifies injunctive
relief in court. A violation of this Section may result in immediate termination of this
Agreement without notice. The obligations of Consultant or its subconsultants under this
Section must survive the termination of this Agreement.
5.27 Jurisdiction and Venue. This Agreement is made under and must be construed in
accordance with and governed by the laws of the State of Arizona without regard to the
conflicts or choice of law provisions thereof. Any action to enforce any provision of this
Agreement or to obtain any remedy with respect hereto must be brought in the courts
located in Maricopa County, Arizona, and for this purpose, each Party hereby expressly and
irrevocably consents to the jurisdiction and venue of such court.
5.28 Survival. All warranties, representations, and indemnifications by Consultant must
survive the completion or termination of this Agreement.
5.29 Modification. Except as expressly provided herein to the contrary, no supplement,
modification, or amendment of any term of this Agreement will be deemed binding or
effective unless in writing and signed by the Parties.
5.30 Severability. If any provision of this Agreement or the application to any person or
circumstance may be invalid, illegal or unenforceable to any extent, the remainder of this
Agreement and the application will not be affected and will be enforceable to the fullest
extent permitted by law.
Project Name: HANGAR AREA PAVEMENT RECONSTRUCTION
Page 10
Project No.: AI2501.201
Rev. 1/12/2024
5.31 Integration. This Agreement contains the full agreement of the Parties. Any prior or
contemporaneous written or oral agreement between the Parties regarding the subject
matter is merged and superseded.
5.32 Time is of the Essence. Time of each of the terms, covenants, and conditions of this
Agreement is hereby expressly made of the essence.
5.33 Date of Performance. If the date of performance of any obligation or the last day of any
time period provided for should fall on a Saturday, Sunday, or holiday for City, the obligation
will be due and owing, and the time period will expire, on the first day after which is not a
Saturday, Sunday or legal City holiday. Except as may otherwise be set forth in this
Agreement, any performance provided for herein will be timely made if completed no later
than 5:00 p.m. (Chandler time) on the day of performance.
5.34 Third Party Beneficiary. Nothing under this Agreement will be construed to give any
rights or benefits in the Agreement to anyone other than City and Consultant, and all duties
and responsibilities undertaken pursuant to this Agreement will be for the sole and exclusive
benefit of City and Consultant and not for the benefit of any other party.
5.35 Conflict in Language. All work performed must conform to all applicable City of Chandler
codes, ordinances, and requirements as outlined in this Agreement. If there is a conflict in
interpretation between provisions in this Agreement and those in Exhibit "A", the provisions
in this Agreement prevail.
5.36 Document/Information Release. Documents and materials released to Consultant,
which are identified by City as sensitive and confidential, are City’s property. The
document/material must be issued by and returned to City upon completion of the services
under this Agreement. Consultant secondary distribution, disclosure, copying, or duplication
in any manner is prohibited without City’s prior written approval. The document/material
must be kept secure at all times. This directive applies to all City documents, whether in
photographic, printed, or electronic data format.
5.37 Exhibits. The following exhibits are made a part of this Agreement and are incorporated
by reference:
Exhibit A - Scope of Services / Schedule
Exhibit B - Compensation and Fees
Exhibit C - Insurance Requirements
Exhibit D - Special Conditions
Exhibit E – Subconsultant Documents with Consultant (if applicable)
Exhibit F - Federal Requirements (if applicable)
5.38 Special Conditions. As part of the services Consultant provides under this Agreement,
Consultant agrees to comply with and fully perform the special terms and conditions set forth
in Exhibit “D”, which is attached to and made a part of this Agreement.
Project Name: HANGAR AREA PAVEMENT RECONSTRUCTION
Page 11
Project No.: AI2501.201
Rev. 1/12/2024
5.39 Non-Discrimination and Anti-Harassment Laws. Consultant must comply with all
applicable City, state, and federal non-discrimination and anti-harassment laws, rules, and
regulations.
5.40 Licenses and Permits. Beginning with the Effective Date and for the full term of this
Agreement, Consultant must maintain all applicable City, state, and federal licenses and
permits required to fully perform Consultant’s services under this Agreement.
5.41 Warranties. Consultant must furnish a one-year warranty on all work and services
performed under this Agreement. Consultant must furnish, or cause to be furnished, a two-
year warranty on all fixtures, furnishings, and equipment furnished by Consultant,
subconsultants or suppliers under this Agreement. Any defects in design, workmanship, or
materials that do not comply with this Agreement must be corrected by Consultant (including,
but not limited to, all parts and labor) at Consultant’s sole cost and expense. All written
warranties and redlines for as-built conditions must be delivered to City on or before City’s
final acceptance of Consultant’s services under this Agreement.
5.42 Cooperative Purchasing Agreement (S.A.V.E. – Strategic Alliance for Volume
Expenditures). In addition to City of Chandler and with the approval of Consultant, this
Agreement may be extended for use by other municipalities, school districts, and government
agencies of the State. Any such usage by other entities must be in accordance with the
ordinance, charter, or procurement rules and regulations of the respective political entity.
5.43 Budget Approval into Next Fiscal Year. This Agreement will commence on the Effective
Date and continue in full force and effect until it is terminated or expires in accordance with
the provisions of this Agreement. The Parties recognize that the continuation of this
Agreement after the close of the City's fiscal year, which ends on June 30 of each year, is
subject to the City Council's approval of a budget that includes an appropriation for this item
as an expenditure. The City does not represent that this budget item will be actually adopted.
This determination is solely made by the City Council.
5.44 Forced Labor of Ethnic Uyghurs Prohibited. By entering into this Agreement, Contractor
certifies and agrees Contractor does not currently use and will not use for the term of this
Agreement: (i) the forced labor of ethnic Uyghurs in the People's Republic of China; or (ii) any
goods or services produced by the forced labor of ethnic Uyghurs in the People's Republic of
China; or (iii) any contractors, subcontractors or suppliers that use the forced labor or any
goods or services produced by the forced labor of ethnic Uyghurs in the People's Republic of
China.
5.45 License to City for Reasonable Use. With this Agreement, Consultant and its
subconsultants hereby grant a license to City, its agents, employees, and representatives for
an indefinite period of time to reasonably use, make copies, and distribute as appropriate
the Documents, works or deliverables developed or created as a result of the Project and this
Agreement. This license also includes the making of derivative works.
Project Name: HANGAR AREA PAVEMENT RECONSTRUCTION
Page 12
Project No.: AI2501.201
Rev. 1/12/2024
This Agreement will be in full force and effect only when it has been approved and executed
by the duly authorized City officials.
IN WITNESS WHEREOF, the Parties have executed this Agreement as of the Effective Date.
“CITY” CITY OF CHANDLER
MAYOR
RECOMMENDED BY:
Daniel Haskins, P.E.
CIP City Engineer
APPROVED AS TO FORM:
City Attorney
ATTEST:
City Clerk
Seal
“CONSULTANT”
DIBBLE & ASSOCIATES CONSULTING
ENGINEERS, INC.
Signature
Date
Print Name
Title
Signer Email Address
09/18/2024
Ryan Toner
Vice President
ryan.toner@dibblecorp.com
Project Name: HANGAR AREA PAVEMENT RECONSTRUCTION
Page A-1
Project No.: AI2501.201
Rev. 1/12/2024
EXHIBIT “A”
SCOPE OF SERVICES/SCHEDULE
p 602.957.1155
3020 East Camelback Road, Suite 201
dibblecorp.com
f 602.957.2838
Phoenix, AZ 85016
August 9, 2024
City of Chandler
Chandler Municipal Airport
2380 S. Stinson Way
Chandler, AZ 85286
Attention:
Mr. Hafiz Noor
Project Manager, Public Works & Utilities Department
City of Chandler
RE:
DESIGN AND BID PHASE SERVICES PROPOSAL
Project No. AI2501.201
Chandler Airport On-Call (2024-2027)
Hangar Area Pavement Reconstruction
We appreciate the opportunity to provide Design and Bid Phase Services to the City of Chandler for the
Hangar Area Pavement Reconstruction project at Chandler Municipal Airport. Dibble will provide the
construction plans, specifications, the Engineer’s Estimate, and Engineer’s Design Report for these
improvements. Dibble as the prime consultant is proposing to complete the Scope of Work as included
in this proposal for the following fees:
Design and Bid Phase Services (Lump Sum UNO):
1. Dibble ............................. Base Fee .......................................... $ 315,558
2. Dibble ............................. Allowance for Expenses .....................
$ 2,500
3. Dibble ............................. Owner’s Allowance (T&M, NTE) ...........
$ 20,000
Project Total .................................................................................... $ 328,578
Transmitted herewith is Exhibit A, containing our proposed Scope of Work; the Project Scope Exhibit;
the Production Schedule; Exhibit B, containing our Fee Schedule and Estimated Manhour matrix for your
review.
We are very much looking forward to working with the City of Chandler and Chandler Municipal Airport
on this project. If you need additional information or have questions, please do not hesitate to call.
Sincerely,
Duane H. Dana, P.E.
Ryan Toner, P.E.
Vice President, Senior Project Manager
Vice President, Business Unit Leader
Dibble
Enclosures
Dibble
Page 1
8/9/2024
CHANDLER MUNICIPAL AIRPORT
HANGAR AREA PAVEMENT RECONSTRUCTION
PROJECT NO. AI2501.201
DESIGN AND BID PHASE SERVICES
EXHIBIT “A”
SCOPE OF SERVICES/SCHEDULE
1. PROJECT DESCRIPTION & SCOPE OF DESIGN:
1.1
Consultant will provide services for the design, development of construction
documents, and specified bidding services for grading and paving improvements
intended to promote drainage away from the hangar structures, located at
Chandler Municipal Airport (CHD), Chandler, Arizona, all as more specifically
described herein below.
1.2
The design includes the full-depth replacement of the existing pavement;
improving drainage flows by regrading the area and constructing valley gutters;
applying pavement markings and any other necessary improvements. This project
will reference the Rehabilitate Hangar Area Pavement Assessment project completed
in 2023 which comprised pre-design services consisting of design concept
recommendations for these grading and paving improvements. The City selected
one option from this project for final design and construction as shown in the
attached Project Scope Exhibit. This project will be constructed in two phases for
funding allocation purposes.
1.3
The project design, construction, furnishing and equipping budget is estimated to
be $ 5,585,000 per the 2023 ACIP. All design, construction and furnishing of the
project are intended be completed within this budget, however, it is not
guaranteed. Consultant will assist the City in evaluating the budget throughout
the design and bidding process.
1.4
Consultant will provide all design and bid phase services for the Project including,
but not limited to civil engineering services. A geotechnical investigation and
topographic survey were conducted in the previous project and will be referenced
in this project.
1.5
All plans are to be prepared in AutoCAD Civil 3D 2023. All work will be prepared in
conformance to FAA and MAG standards (as amended by the City of Chandler).
Dibble
Page 2
8/9/2024
2. ASSIGNMENT:
2.1
The design contract has been awarded to Dibble based on their proposed project
team and specified consultants. Any deviations or substitutions of these team
members must be pre-approved in writing by City. Those team roles listed in
Exhibit B will perform those portions of the work listed therein.
3. PROJECT SCHEDULE:
3.1
Consultant must perform the services within the times set forth in the Production
Schedule included herein and made a part hereof by reference.
3.2
Consultant must adhere to the Production Schedule described herein and such
schedule may not be modified or deviated from without written consent of City.
Consultant must revise and submit for review an updated schedule whenever it is
demonstrated that the time for completion of the Project Design or of any of the
partial completion points listed in the schedule is delayed by two weeks or more.
Such adjusted schedule will include a written explanation stating the reasons for
the change and a plan for getting back on schedule. Consultant must take all
reasonable actions necessary to get the project back on schedule and City will
cooperate to assist Consultant.
3.3
Consultant will deliver monthly “Design and Progress Reports”, including invoicing,
to the City of Chandler in a format acceptable to the City.
3.4
This proposal is based on a twelve (12) month project schedule from the Notice to
Proceed.
Refer to the schedule attached for the anticipated submittal stages and dates. The
following are the anticipated submittal stages:
30% Submittal (City/Airport Review):
•
The documents in Task 9.1 will be uploaded as PDFs to a SharePoint link.
60% Submittal (City/Airport Review):
•
The documents in Task 10.1 will be uploaded as PDFs to a SharePoint link.
95% Submittal (City/Airport Review for bid approval):
•
The documents in Task 11.1 will be uploaded as PDFs to a SharePoint link.
100% Sealed Submittal (Bid-Ready Package):
•
The documents in Task 12.1 will be uploaded as PDFs to a SharePoint link.
Dibble
Page 3
8/9/2024
4. QUALITY CONTROL:
4.1
Consultant must institute and comply with the Design Quality Control Plan.
4.2
In addition to the continual quality assurance reviews performed by senior
practice staff, Consultant will perform additional quality control reviews prior to
each submittal utilizing a standardized checking processes by Consultant’s Quality
Director. Each subconsultant will be responsible for their own Quality
Assurance/Quality Control program; however, the Quality Director will review all
combined project documents for consistency amongst the design elements
before each submittal.
5. PRELIMINARY RESEARCH:
5.1
Consultant will reference the preliminary research conducted in the Rehabilitate
Hangar Area Pavement Assessment project completed in 2023 which comprised the
pre-design phase portion of this project. This includes geotechnical investigation
and topographic survey.
6. UTILITY/AGENCY COORDINATION:
6.1
Coordination with utility companies and agencies must be in accordance with the
latest version of the Public Improvement Project Guide (PIPG).
6.2
Consultant must submit preliminary plans to utilities/agencies for review and
comment to confirm the presence of nearby facilities to be protected in place or
conflicts and if so what design there may be required for service improvements
or any necessary relocations.
6.3
Consultant will, if necessary, incorporate the utility/agency private developer
construction requirements into the bid documents.
7. GEOTECHNICAL INVESTIGATION:
7.1
Consultant has performed all soil and pavement borings necessary to complete
their work. The geotechnical investigation was performed by a subconsultant
(Speedie & Associates) as part of the Rehabilitate Hangar Area Pavement Assessment
project completed in 2023 and will be referenced in this project.
Dibble
Page 4
8/9/2024
8. PROGRAMMING:
8.1
Consultant must meet with City staff to ascertain the requirements of the Project
and will arrive at a mutual understanding of such requirements.
a. Project Kick-Off Meeting: This meeting will be held with the City and Airport
staff at the beginning of the project. Discussion items will include the design
team, control of correspondence, design standards, design schedule,
submittals, and coordination of impacts to airport operations/tenants.
8.2
Consultant will provide project management and coordination of the design team
and will provide coordination between design team members, the City, Airport, and
other interested stakeholders.
a. Project Coordination Meetings: These meetings will be held as needed with the
Design team throughout the project. Discussion items will include design
review, comparison of options, and design schedule.
9. SCHEMATIC DESIGN (30% Document Review):
9.1
When the design is approximately thirty percent complete, Consultant must
prepare and submit the following:
a. Drainage Memorandum: Consultant shall prepare a memorandum to present
the design methodology of the Rehabilitate Hangar Area Pavement Assessment
project as discussed in Section 1.2 and confirm that the proposed grading and
drainage improvements are still effective and appropriate. A modification to
the hydrology model will be required to ensure that the interim state of the
construction project after the completion of Phase 1 will meet grading and
drainage requirements.
b. 30% Design Plans: Consultant shall prepare plan sheets which may include the
following: general construction notes, design legend and abbreviations;
airport access location, contractor’s haul route, staging and storage yard;
construction phasing and barricading plans; demolition and construction
plans; and other informational sheets as necessary.
Dibble
Page 5
8/9/2024
c. 30% Engineer’s Opinion of Probable Construction Cost (EOPCC): Based on the
30% design plans and anticipated technical specifications, Consultant shall
develop an EOPCC on a unit price basis. Unit pricing will be based on recent
bid tabulations from comparative projects, locations, materials, and quantities
available at that time.
d. Draft Engineer’s Design Report (EDR): The Draft EDR shall provide the design
criteria and standards used in developing the construction documents (i.e.,
plans and anticipated technical specifications) and document the work and
results of any investigative efforts. The report shall cover the following: airport
and project descriptions; critical environmental and archeological aspects or
documents including the approved Categorical Exclusion; relevant design
standards; topographic survey and control; civil and electrical design
considerations and recommendations; and a list of anticipated technical
specifications. The Draft EDR shall also include airport and project location
exhibits and appendices such as the Project Photos, Geotechnical Report,
Drainage Memorandum, and EOPCC, and any other design elements as
needed to document design intent.
e. Internal QA/QC Project Review: (See Task 4)
f. 30% City/Airport Review Meeting: This meeting will be held shortly after the
30% Submittal with representatives from the City and Airport to review the
30% submittal package and discuss any comments from these agencies.
g. Plans-in-Hand Site Visit: Shortly after the 30% Submittal and before proceeding
with the remainder of the project, Consultant will perform a plans-in-hand site
visit to visually compare the plans to existing field conditions. Design elements
will be reviewed and/or confirmed in the field, such as utilities infrastructure
and structures (visible in the field), grades, project limits, etc.
Dibble
Page 6
8/9/2024
10. DESIGN DEVELOPMENT (60% Document Review):
10.1
Based on the approved Schematic Design Documents and any adjustments in the
scope or quality of the project or in the construction budget authorized by City,
Consultant must prepare for approval by City the 60% Design Development
Documents. Consultant must prepare and submit the following:
a. Construction Phasing Workshop: Consultant will meet with representatives
from the City and Airport in a workshop setting to review considerations for
construction duration(s), construction cost impacts, impacts to airport
operations, safety, and accessibility with the ultimate outcome of developing
a preferred construction phasing methodology.
b. 60% Design Plans: The 60% plans submission shall include the plan sheets
noted in the 30% design plans and shall also include detailed construction
phasing and aircraft detouring plans, and construction details.
c. Draft Technical Specifications: Technical specifications and special provisions,
and FAA general provisions as needed will be compiled and developed for
review by the City and Airport.
d. 60% Quantities and EOPCC: Based on the 60% design plans and technical
specifications, Consultant shall develop an EOPCC on a unit price basis. Unit
pricing will be based on recent bid tabulations from comparative projects,
locations, materials, and quantities available at that time.
e. Draft CSPP: A CSPP will be developed to be included in the contract documents
as guidance to the contractor on important safety standards and regulations
that are typically required on airport construction projects. The CSPP will be
prepared in accordance with the most recent edition of FAA Advisory Circular
(AC) 150/5370-2G.
f. Internal QA/QC Project Review: (See Task 4)
g. 60% City/Airport Review Meeting: This meeting will be held shortly after the
60% Submittal with representatives from the City and Airport to review the
60% submittal package. The team will discuss any comments from the City and
Airport.
Dibble
Page 7
8/9/2024
11. CONSTRUCTION DOCUMENTS (95% Document Review):
11.1
Based on the approved Design Development Documents and any further
adjustments in the scope or quality of the project or in the construction budget
authorized by City, Consultant must prepare, for approval by City, the 95%
Construction Documents. Consultant must prepare and submit the following:
a. 95% Design Plans: The 95% plans submission shall include the plan sheets
noted in the 60% design plans.
b. Pre-Final Technical Specifications: Technical specifications and special
provisions, and FAA general provisions as needed will be compiled and
developed for final review/approval by the City and Airport.
c. 95% Quantities and EOPCC: Based on the 95% design plans and technical
specifications, Consultant shall develop an EOPCC on a unit price basis. Unit
pricing will be based on recent bid tabulations from comparative projects,
locations, materials, and quantities available at that time.
d. Pre-Final EDR: The EDR shall provide all the design criteria and standards used
in developing the construction documents (i.e., plans and technical
specifications) and document the work and results of investigative efforts.
e. Pre-Final CSPP: A CSPP will be developed to be included in the contract
documents as guidance to the contractor on important safety standards and
regulations that are typically required on airport construction projects. The
CSPP will be prepared in accordance with the most recent edition of FAA
Advisory Circular (AC) 150/5370-2G.
f. Internal QA/QC Project Review: (See Task 4)
g. 95% City/Airport Review Meeting: This meeting will be held shortly after the
95% Submittal with representatives from the City and Airport to review the
95% submittal package. The team will discuss any comments from these
agencies.
h. Plans-in-Hand Site Visit: Shortly after the 95% Submittal and before the 100%
Submittal, Consultant will perform a plans-in-hand site visit to visually
compare the plans to existing field conditions. Design elements will be
reviewed and/or confirmed in the field such as utility infrastructure and
structures, pavement markings, general slopes, project limits, etc.
Dibble
Page 8
8/9/2024
12. BID DOCUMENTS (100% Sealed Documents):
12.1
Based on the approved Construction Documents and any further adjustments in
the scope or quality of the project or in the construction budget authorized by
City, Consultant must prepare for approval by City the 100% Final Construction
Documents. Consultant must prepare and submit the following:
a. Final Design Plans: The sealed final design plans shall include the plan sheets
noted in the 60% design plans.
b. Final Design Alignments and Grading Model: The design CAD files used to
prepare the final design plans shall be packaged and provided for use in
construction.
c. Final Technical Specifications: The sealed final technical specifications, special
provisions, and FAA general provisions as needed will be compiled and
developed for bidding.
d. Final Quantities and EOPCC: Based on the 100% design plans and technical
specifications, Consultant shall develop a 100% EOPCC on a unit price basis.
Unit pricing will be based on recent bid tabulations from comparative projects,
locations, materials, and quantities available at that time.
e. Final EDR: The sealed final EDR shall provide all the design criteria and
standards used in developing the construction documents (i.e., plans and
technical specifications) and document the work and results of investigative
efforts.
f. Final CSPP: The final CSPP will be developed to be included in the contract
documents as guidance to the contractor on important safety standards and
regulations that are typically required on airport construction projects. The
final CSPP will be prepared in accordance with the most recent edition of FAA
Advisory Circular (AC) 150/5370-2G.
g. OE/AAA Submittal: A 7460-1 Site Exhibit will be prepared and Consultant will
upload this with the final CSPP submission to the FAA Airspace Review website,
Obstruction Evaluation and Airport Airspace Analysis (OE/AAA).
h. Internal Final QA/QC Project Review: (See Task 4)
Dibble
Page 9
8/9/2024
13. BID & AWARD:
13.1
Attend and participate at the pre-bid conference for the purpose of answering
technical questions from potential bidders.
a. Pre-Bid Meeting: Consultant will attend the pre-bid meeting and assist the
City/Airport in conducting as needed. Consultant, upon the request of the City,
will provide a brief overview of the project and contract components,
identifying important elements within the documents that the Contractors
should be particularly familiar with prior to submitting a bid. Consultant shall
also assist the City in developing and submitting the pre-bid meeting minutes.
13.2
Assist City in the evaluation of “substitutions and or-equals” and make a
recommendation to accept or decline.
a. Contractor Questions: Consultant will coordinate, address, and appropriately
respond to contractor communications and questions during the bidding
process. Responses will be submitted through addenda as needed.
13.3
Prepare addenda for review and approval by City. City will distribute.
a. Bid Addenda: Pending contractors’ reviews, comments, and questions,
Consultant will assist the City in developing and issuing up to two (2)
addendums, including revisions to contract documents (i.e. plans and
technical specifications). It should be noted that the hours provided in the
Estimated Manhour matrix contained herein is estimated for a maximum of
two (2) addenda.
13.4
If bids are 10% over or under the “engineers estimate”, Consultant will be required
to provide a detailed evaluation explaining differences.
a. Bid Opening Meeting: Consultant will attend the bid opening meeting at the
City of Chandler City Hall.
b. Bid Tabulation and Recommendation: Consultant will evaluate each bid
submitted for mathematical/calculative errors and for comparative purposes
against the EOPCC and other bids submitted. Consultant will provide a bid
summary letter noting inconsistencies, results and a recommendation for the
lowest responsible, responsive bidder.
Dibble
Page 10
8/9/2024
14. PERIOD OF SERVICE (MILESTONES):
14.1
Following receipt of a “Notice to Proceed” with the design work, Consultant must
complete the design and have all documents submitted within 365 calendar days
of the date indicated on the Notice to Proceed.
14.2
Consultant must complete all services specified herein in accordance with the
Production Schedule attached. In the event delays are experienced beyond the
control of Consultant, the completion date may be extended as mutually agreed
upon by City and Consultant.
XXX
XXX
XXX
XXX
XXX
XXX
XXX
XXX
XXX
1021015.06
CHD HANGAR
TAXILANES -
EXHIBIT.DWG
CITY OF CHANDLER, ARIZONA
CHANDLER MUNICIPAL AIRPORT
Call 811 or click Arizona811.com
Contact Arizona 811 at least two full
working days before you begin excavation
HANGAR AREA PAVEMENT
REHABILITATION ASSESSMENT
ALTERNATIVE NO. 5
PHASE 1
PHASE 2
Project Name: HANGAR AREA PAVEMENT RECONSTRUCTION
Page B-1
Project No.: AI2501.201
Rev. 1/12/2024
EXHIBIT “B”
COMPENSATION AND FEES
6,726.00
$
3.1 Production Schedule
1,206.00
$
3.3 Monthly Design and Progress Reports
5,520.00
$
31,276.00
$
4.1 Prepare Quality Control Plan
1,836.00
$
4.2 30%, 60%, 95% & 100% Submittals QA/QC
29,440.00
$
-
$
2,368.00
$
6.3 Coordination with Utilities (PIPG)
2,368.00
$
-
$
14,832.00
$
8.1a Project Kick-Off Meeting
1,824.00
$
8.2a Project Coordination Meetings
13,008.00
$
86,196.00
$
9.1a Drainage Memorandum
15,952.00
$
9.1b 30% Design Plans
47,600.00
$
9.1c 30% Quantities and EOPCC
7,192.00
$
9.1d Draft EDR
12,380.00
$
9.1e 30% City/Airport Review Meeting
1,824.00
$
9.1f Plans-in-Hand Site Visit
1,248.00
$
81,976.00
$
10.1a Construction Phasing Workshop
2,564.00
$
10.1b 60% Design Plans
48,760.00
$
10.1c Draft Technical Specifications
12,080.00
$
10.1d 60% Quantities and EOPCC
3,468.00
$
10.1e Draft CSPP
13,280.00
$
10.1f 60% City/Airport Review Meeting
1,824.00
$
Lump Sum Cost Per Task
Task 5.0 Preliminary Research (Complete)
Task 4.0 Quality Control
Task 3.0 Project Schedule
Task 2.0 Assignment
Task 1.0 Project Description & Scope of Construction
EXHIBIT "B-1"
TASK DESCRIPTION
SUBTOTAL
Task 8.0 Programming
Task 6.0 Utility/Agency Coordination
Task 7.0 Geotechnical Investigation (Complete)
Task 10.0 Design Development (60% Document Review)
Task 9.0 Schematic Design (30% Document Review)
Dibble
Page 1
8/9/2024
Lump Sum Cost Per Task
EXHIBIT "B-1"
TASK DESCRIPTION
SUBTOTAL
39,476.00
$
11.1a 95% Design Plans
20,568.00
$
11.1b Pre-Final Technical Specifications
2,396.00
$
11.1c 95% Quantities and EOPCC
3,468.00
$
11.1d Pre-Final EDR
4,836.00
$
11.1e Pre-Final CSPP
5,136.00
$
11.1f 95% City/Airport Review Meeting
1,824.00
$
11.1g Plans-in-Hand Site Visit
1,248.00
$
27,636.00
$
12.1a Final Design Plans
13,032.00
$
12.1b Final Design Alignments and Grading Model
1,544.00
$
12.1c Final Technical Specifications
2,268.00
$
12.1d Final Quantities and EOPCC
3,238.00
$
12.1e Final EDR
2,568.00
$
12.1e Final CSPP
2,868.00
$
12.1f OE/AAA Submittal
2,118.00
$
15,592.00
$
13.1a Pre-Bid Meeting
1,824.00
$
13.2a Contractor Questions
3,976.00
$
13.3a Bid Addendums (up to 2)
5,916.00
$
13.4a Bid Opening Meeting
1,480.00
$
13.4b Bid Tabulation & Recommendation
2,396.00
$
22,500.00
$
14.1 Allowance for Printing Expenses at Direct Cost
2,000.00
$
14.2 Allowance for Mileage to Meetings and Site Visits
500.00
$
14.3 Owner's Allowance (T&M, NTE)
20,000.00
$
TOTAL COST:
328,578.00
$
Task 11.0 Construction Documents (95% Document Review)
ALLOWANCES & SUB-CONSULTANT COSTS
Task 13.0 Contractor Coordination / Bidding
Task 12.0 Bid Documents (100% Sealed Documents)
Dibble
Page 2
8/9/2024
Principal
Sr. Project
Manager
Sr. Eng /
QAQC
Manager
Project
Engineer
Assistant
Engineer
Senior
Designer
Ryan
Toner
Duane
Dana
Vince
Gibbons
Mark
Hall
Eryn
Guevara
Darin
Oakley
$ 250.00 $ 230.00 $ 210.00 $ 172.00 $ 140.00 $ 150.00
0
27
0
3
0
0
30
3.1 Production Schedule
3
3
6
3.3 Monthly Design and Progress Reports
24
24
64
2
64
8
0
0
138
4.1 Prepare Quality Control Plan
2
8
10
4.2 30%, 60%, 95% & 100% Submittals QA/QC
64
64
128
0
0
0
0
0
0
0
0
0
0
4
12
0
16
6.3 Coordination with Utilities (PIPG)
4
12
16
0
0
0
0
0
0
0
0
28
0
26
28
0
82
8.1a Project Kick-Off Meeting
4
2
4
10
8.2a Project Coordination Meetings
24
24
24
72
0
48
16
118
160
194
536
9.1a Drainage Memorandum
8
16
16
40
16
96
9.1b 30% Design Plans
24
40
80
160
304
9.1c 30% Quantities and EOPCC
4
16
8
16
44
9.1d Draft EDR
8
40
24
2
74
9.1e 30% City/Airport Review Meeting
4
2
4
10
9.1f Plans-in-Hand Site Visit
4
4
8
Task 6.0 Utility/Agency Coordination
Task 7.0 Geotechnical Investigation (Complete)
Task 9.0 Schematic Design (30% Document Review)
Task 8.0 Programming
Task 1.0 Project Description & Scope of Construction
EXHIBIT "B-2"
Task 2.0 Assignment
Task 5.0 Preliminary Research (Complete)
< PROJECT ROLE
< HOURLY RATES
TOTAL HOURS
PER TASK
Hours and Rates
TASK DESCRIPTION
Task 3.0 Project Schedule
Task 4.0 Quality Control
Dibble
Page 3
8/9/2024
Principal
Sr. Project
Manager
Sr. Eng /
QAQC
Manager
Project
Engineer
Assistant
Engineer
Senior
Designer
Ryan
Toner
Duane
Dana
Vince
Gibbons
Mark
Hall
Eryn
Guevara
Darin
Oakley
$ 250.00 $ 230.00 $ 210.00 $ 172.00 $ 140.00 $ 150.00
EXHIBIT "B-2"
< PROJECT ROLE
< HOURLY RATES
TOTAL HOURS
PER TASK
Hours and Rates
TASK DESCRIPTION
0
44
0
128
146
196
514
10.1a Construction Phasing Workshop
6
2
6
14
10.1b 60% Design Plans
16
40
80
180
316
10.1c Draft Technical Specifications
8
40
24
72
10.1d 60% Quantities and EOPCC
2
4
8
8
22
10.1e Draft CSPP
8
40
24
8
80
10.1f 60% City/Airport Review Meeting
4
2
4
10
0
24
0
58
92
74
248
11.1a 95% Design Plans
8
24
40
60
132
11.1b Pre-Final Technical Specifications
2
8
4
14
11.1c 95% Quantities and EOPCC
2
4
8
8
22
11.1d Pre-Final EDR
4
8
16
2
30
11.1e Pre-Final CSPP
4
8
16
4
32
11.1f 95% City/Airport Review Meeting
4
2
4
10
11.1g Plans-in-Hand Site Visit
4
4
8
0
12
0
38
56
70
176
12.1a Final Design Plans
4
16
24
40
84
12.1b Final Design Alignments and Grading Model
2
8
10
12.1c Final Technical Specifications
2
4
8
14
12.1d Final Quantities and EOPCC
1
4
8
8
21
12.1e Final EDR
2
4
8
2
16
12.1e Final CSPP
2
4
8
4
18
12.1f OE/AAA Submittal
1
4
8
13
Task 11.0 Construction Documents (95% Document Review)
Task 10.0 Design Development (60% Document Review)
Task 12.0 Bid Documents (100% Sealed Documents)
Dibble
Page 4
8/9/2024
Principal
Sr. Project
Manager
Sr. Eng /
QAQC
Manager
Project
Engineer
Assistant
Engineer
Senior
Designer
Ryan
Toner
Duane
Dana
Vince
Gibbons
Mark
Hall
Eryn
Guevara
Darin
Oakley
$ 250.00 $ 230.00 $ 210.00 $ 172.00 $ 140.00 $ 150.00
EXHIBIT "B-2"
< PROJECT ROLE
< HOURLY RATES
TOTAL HOURS
PER TASK
Hours and Rates
TASK DESCRIPTION
0
16
0
26
36
16
94
13.1a Pre-Bid Meeting
4
2
4
10
13.2a Contractor Questions
4
8
12
24
13.3a Bid Addendums (up to 2)
2
8
12
16
38
13.4a Bid Opening Meeting
4
4
8
13.4b Bid Tabulation & Recommendation
2
8
4
14
Task 13.0 Contractor Coordination / Bidding
Dibble
Page 5
8/9/2024
ID
Task Name
Work
Days
Calendar
Days
Start
Finish
Predecessors
1
Hangar Area Pavement Reconstruction -
Design Schedule
248 days
355 days
Mon 10/7/24
Fri 9/26/25
2
PRE-DESIGN PHASE
1 day
1 day
Mon 10/7/24
Mon 10/7/24
3
Project Kick-Off Meeting
1 day
1 day
Mon 10/7/24
Mon 10/7/24
4
30% SCHEMATIC DESIGN
73 days
112 days
Tue 10/8/24
Mon 1/27/25
5
30% Design Documents
51 days
73 days
Tue 10/8/24
Thu 12/19/24 3
6
30% Submittal to City/Airport
1 day
1 day
Fri 12/20/24
Fri 12/20/24 5
7
30% City/Airport Review
20 days
33 days
Mon 12/23/24
Fri 1/24/25 6
8
30% City/Airport Review Meeting
1 day
1 day
Mon 1/27/25
Mon 1/27/25 7
9
Plans-in-Hand Site Visit
1 day
1 day
Mon 1/27/25
Mon 1/27/25 7
10
60% DESIGN DEVELOPMENT
65 days
91 days
Tue 1/28/25
Mon 4/28/25
11
60% Design Documents
43 days
59 days
Tue 1/28/25
Thu 3/27/25 9
12
60% Submittal to City
1 day
1 day
Fri 3/28/25
Fri 3/28/25 11
13
60% City/Airport Review
20 days
26 days
Mon 3/31/25
Fri 4/25/25 12
14
60% City/Airport Review Meeting
1 day
1 day
Mon 4/28/25
Mon 4/28/25 13
15
95% CONSTRUCTION DOCUMENTS
45 days
63 days
Tue 4/29/25
Mon 6/30/25
16
95% Design Documents
23 days
31 days
Tue 4/29/25
Thu 5/29/25 14
17
95% Submittal to City
1 day
1 day
Fri 5/30/25
Fri 5/30/25 16
18
95% City/Airport Review
20 days
26 days
Mon 6/2/25
Fri 6/27/25 17
19
95% City/Airport Review Meeting
1 day
1 day
Mon 6/30/25
Mon 6/30/25 18
20
Plans-in-Hand Site Visit
1 day
1 day
Mon 6/30/25
Mon 6/30/25 18
21
FINAL 100% BID-READY DOCUMENTS
19 days
25 days
Tue 7/1/25
Fri 7/25/25
22
100% Bid Documents
14 days
18 days
Tue 7/1/25
Fri 7/18/25 20
23
Compile Design Files/Package Submittal
4 days
4 days
Mon 7/21/25
Thu 7/24/25 22
24
100% Submittal to City
1 day
1 day
Fri 7/25/25
Fri 7/25/25 23
25
BID PHASE
45 days
61 days
Mon 7/28/25
Fri 9/26/25
26
Bid Period
45 days
61 days
Mon 7/28/25
Fri 9/26/25 24
Project Kick-Off Meeting
10/7
30% Design Documents
30% Submittal to City/Airport
12/20
30% City/Airport Review
30% City/Airport Review Meeting
1/27
Plans-in-Hand Site Visit
60% Design Documents
60% Submittal to City
3/28
60% City/Airport Review
60% City/Airport Review Meeting
4/28
95% Design Documents
95% Submittal to City
5/30
95% City/Airport Review
95% City/Airport Review Meeting
6/30
Plans-in-Hand Site Visit
100% Bid Documents
Compile Design Files/Package Submittal
100% Submittal to City
7/25
Bid Period
28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 2 9 16 23 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 5
Aug '24
Sep '24
Oct '24
Nov '24
Dec '24
Jan '25
Feb '25
Mar '25
Apr '25
May '25
Jun '25
Jul '25
Aug '25
Sep '25
Oc
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Progress
Deadline
Design Production Schedule
CHD Hangar Area Pavement Reconstructi
Dibble - 8/2/2024
Project Name: HANGAR AREA PAVEMENT RECONSTRUCTION
Page C-1
Project No.: AI2501.201
Rev. 1/12/2024
EXHIBIT “C”
INSURANCE REQUIREMENTS
1.
General.
1.1 At the same time as execution of this Agreement, Consultant must furnish City a certificate
of insurance on a standard insurance industry ACORD form. The ACORD form must be
issued by an insurance company authorized to transact business in the State of Arizona
possessing a current A.M. Best, Inc. rating of A-7, or better and legally authorized to do
business in the State of Arizona with policies and forms satisfactory to City. Provided,
however, the A.M. Best rating requirement will not be deemed to apply to required Workers’
Compensation coverage.
1.2 Consultant and any of its subconsultants must procure and maintain, until all of their
obligations have been discharged, including any warranty periods under this Agreement are
satisfied, the insurances set forth below.
1.3 The insurance requirements set forth below are minimum requirements for this Agreement
and in no way limit the indemnity covenants contained in this Agreement.
1.4 City in no way warrants that the minimum insurance limits contained in this Agreement are
sufficient to protect Consultant from liabilities that might arise out of the performance of
the Agreement services under this Agreement by Consultant, its agents, representatives,
employees, subconsultants, and Consultant is free to purchase any additional insurance as
may be determined necessary.
1.5 Failure to demand evidence of full compliance with the insurance requirements in this
Agreement or failure to identify any insurance deficiency will not relieve Consultant from,
nor will it be considered a waiver of its obligation to maintain the required insurance at all
times during the performance of this Agreement.
1.6 Use of subconsultants: If any work is subcontracted in any way, Consultant must execute a
written Agreement with subconsultant containing the same Indemnification Clause and
Insurance Requirements as City requires of Consultant in this Agreement. Consultant is
responsible for executing the Agreement with the subconsultant and obtaining Certificates
of Insurance and verifying the insurance requirements.
2.
Minimum Scope and Limits of Insurance. Consultant must provide coverage with limits of
liability not less than those stated below.
2.1 Professional Liability. If the Agreement is the subject of any professional services or work
performed by Consultant, or if Consultant engages in any professional services or work
adjunct or residual to performing the work under this Agreement, Consultant must maintain
Professional Liability insurance covering errors and omissions arising out of the work or
services performed by Consultant, or anyone employed by Consultant, or anyone whose
acts, mistakes, errors and omissions Consultant is legally liable, with a liability limit of
$1,000,000 each claim and $2,000,000 all claims. In the event the Professional Liability
insurance policy is written on a “claims made” basis, coverage must extend for 3 years past
Project Name: HANGAR AREA PAVEMENT RECONSTRUCTION
Page C-2
Project No.: AI2501.201
Rev. 1/12/2024
completion and acceptance of the work or services, and Consultant, or its selected Design
Professional will submit Certificates of Insurance as evidence the required coverage is in
effect. The Design Professional must annually submit Certificates of Insurance citing that the
applicable coverage is in force and contains the required provisions for a 3 year period.
2.2 Commercial General Liability-Occurrence Form. Consultant must maintain “occurrence” form
Commercial General Liability insurance with a limit of not less than $2,000,000 for each
occurrence, $4,000,000 aggregate. Said insurance must also include coverage for products
and completed operations, independent contractors, personal injury and advertising injury.
If any Excess insurance is utilized to fulfill the requirements of this paragraph, the Excess
insurance must be “follow form” equal or broader in coverage scope than underlying
insurance.
2.3 Automobile Liability-Any Auto or Owned, Hired and Non-Owned Vehicles
Vehicle Liability: Consultant must maintain Business/Automobile Liability insurance with a
limit of $1,000,000 each accident on Consultant owned, hired, and non-owned vehicles
assigned to or used in the performance of Consultant’s work or services under this
Agreement. If any Excess or Umbrella insurance is utilized to fulfill the requirements of this
paragraph, the Excess or Umbrella insurance must be “follow form” equal or broader in
coverage scope than underlying insurance.
2.4 Workers Compensation and Employers Liability Insurance: Consultant must maintain Workers
Compensation insurance to cover obligations imposed by federal and state statutes having
jurisdiction of Consultant employees engaged in the performance of work or services under
this Agreement and must also maintain Employers’ Liability insurance of not less than
$1,000,000 for each accident and $1,000,000 disease for each employee.
3.
Additional Policy Provisions Required.
3.1 Self-Insured Retentions or Deductibles. Any self-insured retentions and deductibles must be
declared and approved by City. If not approved, City may require that the insurer reduce or
eliminate any deductible or self-insured retentions with respect to City, its officers, officials,
agents, employees, and volunteers.
3.1.1. Consultant’s insurance must contain broad form contractual liability coverage.
3.1.2. Consultant’s insurance coverage must be primary insurance with respect to City, its
officers, officials, agents, and employees. Any insurance or self-insurance maintained
by City, its officers, officials, agents, and employees will be in excess of the coverage
provided by Consultant and must not contribute to it.
3.1.3. Consultant’s insurance must apply separately to each insured against whom claim is
made or suit is brought, except with respect to the limits of the insurer's liability.
3.1.4. Coverage provided by Consultant must not be limited to the liability assumed under
the indemnification provisions of this Agreement.
Project Name: HANGAR AREA PAVEMENT RECONSTRUCTION
Page C-3
Project No.: AI2501.201
Rev. 1/12/2024
3.1.5. The policies must contain a severability of interest clause and waiver of subrogation
against City, its officers, officials, agents, and employees, for losses arising from Work
performed by Consultant for City. (Does not apply to Professional Liability coverage.)
3.1.6. Consultant, its successors and or assigns, are required to maintain Commercial
General Liability insurance as specified in this Agreement for a minimum period of 3
years following completion and acceptance of the Work. Consultant must submit a
Certificate of Insurance evidencing Commercial General Liability insurance during this
3-year period containing all the Agreement insurance requirements, including
naming City of Chandler, its agents, representatives, officers, directors, officials and
employees as Additional Insured as required.
3.1.7. If a Certificate of Insurance is submitted as verification of coverage, City will
reasonably rely upon the Certificate of Insurance as evidence of coverage, but this
acceptance and reliance will not waive or alter in any way the insurance requirements
or obligations of this Agreement.
3.2. Insurance Cancellation During Term of Agreement.
3.2.1. If any of the required policies expire during the life of this Agreement, Consultant
must forward renewal or replacement Certificates to City within 10 days after the
renewal date containing all the required insurance provisions.
3.2.2. Each insurance policy required by the insurance provisions of this Agreement must
provide the required coverage and must not be suspended, voided or canceled
except after thirty (30) days prior written notice has been given to City, except when
cancellation is for non-payment of premium, then ten (10) days prior notice may be
given. Such notice must be sent directly to Chandler Law-Risk Management
Department, Post Office Box 4008, Mailstop 628, Chandler, Arizona 85225. If any
insurance company refuses to provide the required notice, Consultant or its
insurance broker must notify City of any cancellation, suspension, non-renewal of any
insurance within seven (7) days of receipt of insurers’ notification to that effect.
3.3
City as Additional Insured. The policies are to contain, or be endorsed to contain, the following
provisions:
3.3.1. The Commercial General Liability and Automobile Liability policies are to contain, or
be endorsed to contain, the following provisions: City, its officers, officials, agents,
and employees are additional insureds with respect to liability arising out of activities
performed by, or on behalf of, Consultant; Products and Completed operations of
Consultant; and automobiles owned, leased, hired, or borrowed by Consultant.
3.3.2. City, its officers, officials, agents, and employees must be additional insureds to the
full limits of liability purchased by Consultant even if those limits of liability are in
excess of those required by this Agreement.
Project Name: HANGAR AREA PAVEMENT RECONSTRUCTION
Page D-1
Project No.: AI2501.201
Rev. 1/12/2024
EXHIBIT “D”
SPECIAL CONDITIONS
Standard Details and Specifications. Consultant must be familiar with City’s latest revision of
the MAG Specifications and MAG Standard Details as amended by City. City’s current
amendment to the MAG Specifications, part of City’s Unified Development Manual, may be found
and downloaded from City’s website at http://www.chandleraz.gov/udm.
City Ownership of Project Documents. All work products (electronically or manually
generated) including, but not limited to: plans, specifications, cost estimates, field notes,
tracings, studies, investigations, design analyses, original drawings, original mylars, Computer
Aided Drafting and Design (CADD) file diskettes which reflect all final drawings, and other
related documents which are prepared in the performance of this Agreement (collectively
referred to as "Documents") are to be and remain the property of City and are to be delivered
to the Project Manager before the final payment is made to Consultant. In the event these
Documents are altered, modified or adapted without the written consent of Consultant,
which consent Consultant must not unreasonably withhold, City agrees to hold Consultant
harmless to the extent permitted by law from the legal liability arising out of City's alteration,
modification or adaptation of the Documents.
Re-use of Documents. The parties agree the documents, drawings, specifications and designs,
although the property of City, are prepared for this specific project and are not intended nor
represented by Consultant to be suitable for re-use for any other project. Any re-use without
written verification or adaptation by Consultant for the specific purpose intended will be at
City’s sole risk and without liability or legal exposure to Consultant.
Documents to Bear Seal. Consultant and its subconsultants must endorse by professional
seal all plans, works, and deliverables prepared by each for this Agreement as required by
state law.
Project Name: HANGAR AREA PAVEMENT RECONSTRUCTION
E-1
Project No.: AI2501.201
Rev. 1/12/2024
EXHIBIT “E”
SUBCONSULTANT DOCUMENTS WITH CONSULTANT
Any subconsultant assumptions, clarifications, exclusions, terms & conditions,
signature blocks, etc. included are strictly between the Consultant and their
subconsultants, and do not apply to the Agreement between the Consultant and
the City.
N/A
Project Name: HANGAR AREA PAVEMENT RECONSTRUCTION
Page F-1
Project No.: AI2501.201
Rev. 1/24/2024
EXHIBIT “F”
FEDERAL REQUIREMENTS
N/A