Public Works Project Meeting #1
Extracted text (via pymupdf)
10276 characters
Public Works Subcommittee
Project Discussion #1
Citizen Bond Exploratory Committee| October 15, 2024
Agenda:
o Large Project Evolution
o Intersection / Roadway Projects
o Miscellaneous Programs
o Next Meeting Preview
o Questions and Discussion
Public Works Project Meeting #1
Large Project Evolution
What Triggers The Need For An Intersection Or
Roadway Project?
Reason for Improvement
How We Identify It________________________________
Safety Concerns
Crash History and Severity and Road Safety Audits (RSA)
Capacity & Congestion
Traffic Counts, Traffic Flow Quality, Geometric Layout Reviews, Field
Observations, Simulation
Operational Efficiency
Signal Timing Analysis, Speed, Traffic Volumes, Turning Movement Counts,
Intersection Performance, Arrival and Departure Counts
Pedestrian & Bicycle Needs
Pedestrian/Bicycle Counts, ADA Compliance Survey/Evaluation, User
Feedback
Land Use Changes
Trip Generation Analysis and Traffic Impact Study_____________
Key Message: Improvements are based on data-driven assessments to enhance safety, efficiency, and
functionality.
What Solutions Can We Build To Fix The Problems?
•
Dual Left-Turn Lanes/Right Turn Lanes: Typically requires road widening, relocation of curbs, sidewalks, and
utilities to accommodate additional lanes, often necessitating relocation of signal poles, mast arms, and
equipment.
•
Bicycle Lanes: Expanding the roadway to add bike lanes often involves widening the street, adjusting lane
markings, and potentially realigning signals and poles.
•
Road Widening for Through Lanes: Adding through lanes increases capacity but necessitates widening the entire
intersection, which impacts not just the roadway, curbs, sidewalks, and utilities but also the signals, requiring
longer mast arms and new poles.
•
Signal Upgrades to Meet MUTCD Standards: Ensuring proper signal indication alignment and visibility, especially
when adding new lanes, often requires longer mast arms, new signal poles/foundations for all directions.
•
Flashing Yellow Arrows (FYA): Improves safety but often necessitates longer mast arms and new signal poles to
ensure proper coverage for the new lanes.
•
ADA Compliance: Installing or relocating audible push buttons and curb ramp upgrades.
•
Improved Crosswalk Visibility: High-visibility markings and enhanced signage improve safety but may also involve
signal pole realignment and upgraded signage infrastructure.
•
Enhanced Lighting: Improving visibility at night or during poor weather conditions involves adding new lighting
poles or upgrading existing ones to illuminate the expanded roadway.
Intersection/Roadway Projects
Page
Program
#
Program Name
Current 10
Year CIP
Bond Auth
Needed
Funding
Source
6ST786
Arizona Ave/Warner Rd Intersection
$1,257,300
15,466,700
Streets General
Obligation Bonds
Arizona Ave/Warner Rd Intersection
The Arizona Avenue and Warner Road intersection was identified by the Maricopa Association of Governments (MAG) as a
top 50 intersection for crash incidences in the MAG region. A Road Safety Assessment, RSA recommended adding dual left
turn lanes for both northbound and southbound traffic on Arizona Ave at Warner, signal phasing changes to better
accommodate traffic flows, installation of dual left-turn lanes on northbound and southbound Arizona Ave to reduce the
severity and number crashes. Arizona Avenue is classified as a high-capacity corridor with multiple road users.
Program
#
Program Name
Current 10
Year CIP
Bond Auth.
Needed
Funding
Source
6ST781
Ray Road / Kyrene Road Intersection
$5,553,000
$5,533,000
Streets General
Obligation Bonds,
Capital Grants
Ray Road / Kyrene Road Intersection
The Ray Road/Kyrene Road program includes intersection includes reconstruction of the intersection to three thru lanes,
dual left turn lanes, right turn lanes, and bike lanes in each direction as well as sidewalks, curb and gutter, street lighting,
traffic signals, storm drainage, landscaping, right-of-way acquisition, and utility relocations. Construction funding for this
project is beyond this 10-year CIP window
Program
#
Program Name
Current 10
Year CIP
Bond Auth
Needed
Funding
Source
6ST737
Kyrene Road (Chandler Boulevard to Santan 202)
$45,403,100
$11,906,000
Streets General
Obligation Bonds,
Capital Grants
Kyrene Road (Chandler Boulevard to Santan 202)
This program includes widening Kyrene Road from Chandler Boulevard to the Santan (Loop 202) Freeway from four to six
thru lanes (widening to outside), traffic signal modifications, street lighting, storm drainage, landscaping, ROW acquisition
and utility relocations. This program also includes intersection improvements at Kyrene Rd and Chandler Blvd consisting of
dual left turn lanes and single right in all directions per study that was completed in 2021.
Program
#
Program Name
Current 10
Year CIP
Bond Auth.
Needed
Funding
Source
6ST774
Warner Rd. (Price to Arizona Ave)
$13,911,000
$13,911,000
Streets General
Obligation Bonds,
Capital Grants
Warner Rd. (Price to Arizona Ave)
Warner Road will be widened from 4 to 6 lanes between Price Rd and Arizona Ave, including intersection
improvements at Dobson Rd, Alma School Rd, and Arizona Ave. Improvements will consist of thru lanes, turn
lanes, bike lanes, sidewalks, curbs and gutters, street lighting, Intelligent Transportation System (ITS), traffic
signals as warranted, storm drainage, landscaping, right-of-way acquisition, and utility relocation. Construction
funding for this project is beyond this 10-year CIP window
2040 Level of Service Without Improvements
o Capacity constraints
primarily north of
Loop 202
o Programmed projects
accounted for in
analysis
Roadway Recommendations (2020-2040)
o Network of primarily 4
-lane and 6-lane
roads
o Several 4-lane roads
with 6 lanes at
intersections north of
Loop 202 and east of
Loop 101
Program
#
Program Name
Current 10
Year CIP
Bond Auth.
Needed
Funding
Source
6ST793
McQueen Road Improvements (Warner to Pecos)
$84,885,000
$26,631,000
Streets General
Obligation Bonds,
Capital Grants
McQueen Road Improvements (Warner to Pecos)
McQueen Road improvements will consist of thru lanes, turn lanes, bike lanes, sidewalks, curbs and gutters, street lighting,
ITS, traffic signals, storm drainage, landscaping, right-of-way acquisition, and utility relocation. A study began in FY 2023-24
to provide recommended intersection improvements, roadway alignment modifications, and inner/outer widening
requirements.
Miscellaneous Programs
Program
#
Program Name
Current 10
Year CIP
Bond Auth
Needed
Funding
Source
6ST303
Street Construction - Various Improvements
$12,000,000
$4,800,000
Streets General
Obligation Bonds,
Capital Grants
Street Construction - Various Improvements
Photo
Photo
This program provides funding for small safety related projects and developer agreements that arise outside of the normal
budget cycle. The program also provides budget appropriation for “year-end closeout” federal grants for various projects
and for other federal, state, or county grants. The notification of these grants is often received after the budget has been
finalized. The program includes $4 million in grant appropriation for these unforeseen grant awards.
Program
#
Program Name
Current 10
Year CIP
Bond Auth
Needed
Funding
Source
6ST322
Traffic Signals Improvements and Repairs
$16,019,500
$10,038,500
Streets General
Obligation Bonds
Traffic Signals Improvements and Repairs
This program will provide traffic signal equipment for ongoing operations, maintenance, and rehabilitation of existing traffic
signals, rewiring of intersections, replacement of illuminated street name sign faces, and pole painting. Equipment ranges
from signal poles and heads, cameras, controllers, pedestrian signal audibles, speed reader boards, timers, and cabinets.
Funding includes upgraded cabinets with the capacity to fit all required equipment necessary including cameras and allows
for access to parts of the cabinet making it easier and more efficient for staff.
Traffic Signal and Street Light Maintenance
Managing the Wiring and Electronic Systems
Repair of Damaged Poles and Wiring
Sharing the Beauty of Chandler From a Streets Guy!!
Program
#
Program Name
Current 10
Year CIP
Bond Auth
Needed
Funding
Source
6ST719
Collector Street Improvements
$7,270,000
$1,425,000
Streets General
Obligation Bonds
Collector Street Improvements
This request is to improve collector streets to city standards. Improvements will occur on the following collector streets:
South half of Armstrong Way (from Hamilton Street to approximately 1,250 feet east) and the west half of Hamilton St (from
Armstrong St to approximately 420 feet north) to collector roadway. This collector is included in the transportation plan.
Willis Road (Vine Street to 1,700 feet east) El Monte Place (from Cheri Lynn Drive to 1,000 feet east)
Armstrong Way and Hamilton Street
Willis Road (Vine Street to 1,700 feet east)
El Monte Place (from Cheri Lynn Drive to 1,000 feet east)
Preview of
Project Meeting #2
October 29, 2024
Program
#
Program Name
Current 10
Year CIP
Bond Auth
Needed
Funding
Source
6ST248
Street Repaving
$185,940,000
$88,008,000
HURF, General
Government Capital
Projects, Streets
General Obligation
Bonds
2025-2034 CIP - Streets
Chandler maintains about 2,090 lane miles of streets. The Streets Division inventories all streets on a four-year cycle to
evaluate pavement condition. Pavement Quality Index (PQI) is tracked to determine maintenance priority. Streets with a
PQI of 40 or less (scale of 1 to 100) are scheduled for repaving. Asphalt seals and ADA related concrete sidewalk
replacement are also part of this program.
Page
Program
#
Program Name
Current 10
Year CIP
Bond Auth
Needed
Funding
Source
6ST702
Washington Street Improvements
$12,841,000
$9,833,000
Streets General
Obligation Bonds
2025-2034 CIP - Streets
Photo
Photo
Photo
Photo
Photo
Photo
Waiting On Kim
Program
#
Program Name
Current 10
Year CIP
Bond Auth.
Needed
Funding
Source
6ST753
Ocotillo Rd. Shared Use Path
$21,911,000
$21,911,000
Streets General
Obligation Bonds,
Capital Grants
2025-2034 CIP - Streets
This program will add a ten to twelve-foot-wide shared use path on one side of Ocotillo Road between Dobson Road and