Project Name: Chandler Heights - Gilbert Road to Val Vista Drive 
Page 1 
Project No.: ST1804.451; Federal No. CHN-0(244)D; ADOT No. T0203 01C 
 Rev. 1/12/2024 
 
 
 
 
 
PROFESSIONAL SERVICES AGREEMENT 
 Construction Management Services 
Chandler Heights - Gilbert Road to Val Vista Drive 
Project No. ST1804.451 
Federal Project No.: CHN-0(244)D 
ADOT Project No. T0203 01C 
Council Date: October 17, 2024        
 
 
This Agreement (“Agreement”) is made and entered into on the ______ day of_________________, 2024 
(“Effective Date”), by and between City of Chandler, an Arizona municipal corporation, ("City''), 
and Consultant Engineering, Inc., an Arizona corporation , ("Consultant") (City and Consultant 
may individually be referred to as “Party” and collectively referred to as “Parties”). 
 
RECITALS 
 
A. City proposes to engage Consultant to provide Construction Management Services for 
Chandler Heights - Gilbert Road to Val Vista Drive project as more fully described in Exhibit 
"A", which is attached to and made a part of this Agreement by this reference. 
 
B. Consultant is ready, willing, and able to provide the services described in Exhibit “A” for 
the compensation and fees set forth and as described in Exhibit ”B”, which is attached to 
and made a part of this Agreement by this reference. 
 
C. City desires to enter into an Agreement with Consultant to provide these services under 
the terms and conditions set forth in this Agreement. 
 
AGREEMENT 
 
NOW, THEREFORE, in consideration of the premises and the mutual promises contained in this 
Agreement, City and Consultant agree as follows: 
 
SECTION I--CONSULTANT’S SERVICES 
 
Consultant must perform the services described in Exhibit “A” to City’s satisfaction within the 
terms and conditions of this Agreement and within the care and skill that a person who 
provides similar services in Chandler, Arizona exercises under similar conditions. All work or 
services furnished by Consultant under this Agreement must be performed in a skilled and 
workmanlike manner.  All fixtures, furnishings, and equipment furnished by Consultant as

Project Name: Chandler Heights - Gilbert Road to Val Vista Drive 
Page 2 
Project No.: ST1804.451; Federal No. CHN-0(244)D; ADOT No. T0203 01C 
 Rev. 1/12/2024 
 
 
part of the work or services under this Agreement must be new, or the latest model, and of 
the most suitable grade and quality for the intended purpose of the work or service.  
 
SECTION II--PERIOD OF SERVICE 
 
Consultant must perform the services described in Exhibit “A” for the term of this 
Agreement.  Unless amended in writing by the Parties, the Agreement term expires 455 
calendar days after the Notice to Proceed (NTP) Date. 
 
SECTION III--PAYMENT OF COMPENSATION AND FEES 
 
Unless amended in writing by the Parties, Consultant’s compensation and fees as more fully 
described in Exhibit “B” for performance of the services approved and accepted by City 
under this Agreement must not exceed $1,035,646.10 for the full term of the Agreement. 
Consultant may not increase any compensation or fees under this Agreement without the 
City’s prior written consent. Consultant must submit monthly requests for payment of 
services approved and accepted during the previous billing period and must include, as 
applicable, detailed invoices and receipts, a narrative description of the tasks accomplished 
during the billing period, a list of any deliverables submitted, and any subconsultant’s or 
supplier’s actual requests for payment plus similar narrative and listing of their work. 
Consultant must submit an Application and Certification for Payment Sheet with the monthly 
request for payment to: CapitalProjects.Payables@chandleraz.gov. Payment for those 
services negotiated as a lump sum will be made in accordance with the percentage of the 
work completed during the preceding billing period. Services negotiated as a not-to-exceed 
fee will be paid in accordance with the work effort expended on the service during the 
preceding month. All requests for payment must be submitted to City for review and 
approval. City will make payment for approved and accepted services within 30 calendar days 
of City’s receipt of the request for payment. Consultant bears all responsibility and liability for 
any and all tax obligations that result from Consultant’s performance under this Agreement.  
 
SECTION IV--CITY'S OBLIGATIONS 
 
As part of Consultant’s services under this Agreement, City will provide furnished items, 
services, or obligations as detailed in Exhibit “D”. 
 
SECTION V--GENERAL CONDITIONS 
 
5.1 Notices. Unless otherwise provided herein, demands under this Agreement must be in 
writing and will be deemed to have been duly given and received either (a) on the date of 
service if personally served on the party to whom notice is to be given, or (b) on the third day 
after the date of the postmark of deposit by first class United States mail, registered or 
certified, postage prepaid and properly addressed as follows:

Project Name: Chandler Heights - Gilbert Road to Val Vista Drive 
Page 3 
Project No.: ST1804.451; Federal No. CHN-0(244)D; ADOT No. T0203 01C 
 Rev. 1/12/2024 
 
 
 
 
To City: 
City of Chandler - Public Works & Utilities Department 
Attn:  CIP City Engineer: Daniel Haskins, P.E. 
P.O. Box 4008, Mail Stop 407 
Chandler, AZ 85244-4008 
Phone:  480-782-3335         Email:  daniel.haskins@chandleraz.gov 
With a copy to: 
City of Chandler - Public Works & Utilities Department 
Attn: Jason Garcia, Project Manager 
P.O. Box 4008, Mail Stop 407, Chandler, AZ 85244-4008 
Phone: 480-782-3453               Email: jason.garcia@chandleraz.gov 
To Consultant: 
LEGAL COMPANY NAME: Consultant Engineering, Inc. 
Mailing Address:  PO Box 37167, Phoenix, AZ 85069 
Physical Address:   10625 N. 25th Ave., Suite 200, Phoenix, AZ 85029 
Statutory Agent Name: John Patterson 
Statutory Agent Mailing Address: 
PO Box 37167, Phoenix, AZ 85069 
Statutory Agent Physical Address: 
10625 N. 25th Ave., Suite 200 
Phoenix, AZ 85029 
CONSULTANT’S AUTHORIZED PROJECT REPRESENTATIVE  
Name: 
Brian Lizzet 
Title: 
Project Manager/Principal 
Phone:  480-689-6472 
Email: 
blizzet@cei-az.com 
 
5.2 Records/Audit. Records of Consultant’s direct personnel payroll, reimbursable expenses 
pertaining to this Agreement and records of accounts between City and Consultant must be 
kept on the basis of generally accepted accounting principles and must be made available to 
City and its auditors for up to three years following City’s final acceptance of the services 
under this Agreement (this requirement is increased to five years if construction of this 
project is federally funded). City, its authorized representative, or any federal agency, 
reserves the right to audit Consultant’s records to verify the accuracy and appropriateness of 
all cost and pricing data, including data used to negotiate this Agreement and any 
amendments. City reserves the right to decrease the total amount of Agreement price or 
payments made under this Agreement or request reimbursement from Consultant following 
final Agreement payment on this Agreement if, upon audit of Consultant’s records, the audit 
discloses Consultant has provided false, misleading, or inaccurate cost and pricing data. 
Consultant will include a similar provision in all of its Agreements with subconsultants who 
provide services under the Agreement to ensure that City, its authorized representative, or 
the appropriate federal agency, has access to the subconsultants’ records to verify the

Project Name: Chandler Heights - Gilbert Road to Val Vista Drive 
Page 4 
Project No.: ST1804.451; Federal No. CHN-0(244)D; ADOT No. T0203 01C 
 Rev. 1/12/2024 
 
 
accuracy of all cost and pricing data. City reserves the right to decrease Agreement price or 
payments made on this Agreement or request reimbursement from Consultant following 
final payment on this Agreement if the above provision is not included in subconsultant 
agreements, and one or more subconsultants refuse to allow City to audit their records to 
verify the accuracy and appropriateness of all cost and pricing data. If, following an audit of 
this Agreement, the audit discloses Consultant has provided false, misleading, or inaccurate 
cost and pricing data, and the cost discrepancies exceed 1% of the total Agreement billings, 
Consultant will be liable for reimbursement of the reasonable, actual cost of the audit. 
 
5.3 Alteration in Character of Work. Whenever an alteration in the character of work results 
in a substantial change in this Agreement, thereby materially increasing or decreasing the 
scope of services, cost of performance, or Project schedule, the work will be performed as 
directed by City. However, before any modified work is started, a written amendment must 
be approved and executed by City and Consultant. Such amendment must not be effective 
until approved by City. Additions to, modifications, or deletions from this Agreement as 
provided herein may be made, and the compensation to be paid to Consultant may 
accordingly be adjusted by mutual agreement of the Parties. It is distinctly understood and 
agreed that no claim for extra services or materials furnished by Consultant will be allowed 
by City except as provided herein, nor must Consultant do any work or furnish any materials 
not covered by this Agreement unless such work is first authorized in writing. Any such work 
or materials furnished by Consultant without prior written authorization will be at 
Consultant’s own risk, cost, and expense, and Consultant hereby agrees that without written 
authorization Consultant will make no claim for compensation for such work or materials 
furnished. 
 
5.4 Termination. City and Consultant hereby agree to the full performance of the covenants 
contained herein, except that City reserves the right, at its discretion and without cause, to 
terminate or abandon any service provided for in this Agreement, or abandon any portion of 
the Project for which services have been performed by Consultant. In the event City abandons 
or suspends the services, or any part of the services as provided in this Agreement, City will 
notify Consultant in writing and immediately after receiving such notice, Consultant must 
discontinue advancing the work specified under this Agreement. Upon such termination, 
abandonment, or suspension, Consultant must deliver to City all drawings, plans, 
specifications, special provisions, estimates and other work entirely or partially completed, 
together with all unused materials supplied by City. Consultant must appraise the work 
Consultant has completed and submit Consultant’s appraisal to City for evaluation. City may 
inspect Consultant’s work to appraise the work completed. Consultant will receive 
compensation in full for services performed to the date of such termination. The fee will be 
paid in accordance with Section Ill of this Agreement, and as mutually agreed upon by 
Consultant and City. If there is no mutual agreement on payment, the final determination will 
be made in accordance with the "Disputes" provision in this Agreement. However, in no event 
may the fee exceed the fee set forth in Section Ill of this Agreement nor as amended in 
accordance with Section "Alteration in Character of Work." City will make the final payment 
within 60 days after Consultant has delivered the last of the partially completed items and 
the Parties agree on the final fee. If City is found to have improperly terminated the 
Agreement for cause or default, the termination will be converted to a termination for 
convenience in accordance with the provisions of this Agreement.

Project Name: Chandler Heights - Gilbert Road to Val Vista Drive 
Page 5 
Project No.: ST1804.451; Federal No. CHN-0(244)D; ADOT No. T0203 01C 
 Rev. 1/12/2024 
 
 
5.5 Indemnification. To the extent permitted by law, the Consultant ("lndemnitor") must 
indemnify, save and hold harmless City and its officers, officials, agents and employees 
("lndemnitee") from any and all claims, actions, liabilities, damages, losses or expenses 
(including court costs, attorneys' fees and costs of claim processing, investigation and 
litigation) ("Claims") caused or alleged to be caused, in whole or in part, by the wrongful, 
negligent or willful acts, or errors or omissions of Consultant or any of its owners, officers, 
directors, agents, employees, or subconsultants in connection with this Agreement. This 
indemnity includes any claim or amount arising out of or recovered under workers' 
compensation law or on account of the failure of Consultant to conform to any federal, state 
or local law, statute, ordinance, rule, regulation or court decree. Consultant must indemnify 
lndemnitee from and against any and all Claims, except those arising solely from 
lndemnitee's own negligent or willful acts or omissions. Consultant is responsible for primary 
loss investigation, defense and judgment costs where this indemnification applies. In 
consideration of the award of this Agreement, Consultant agrees to waive all rights of 
subrogation against lndemnitee for losses arising from or related to this Agreement. The 
obligations of Consultant under this provision survive the termination or expiration of this 
Agreement. 
 
5.6 Insurance Requirements. Consultant must procure insurance under the terms and 
conditions and for the amounts of coverage set forth in Exhibit “C” against claims that may 
arise from or relate to performance of the work under this Agreement by Consultant and its 
agents, representatives, employees, and subconsultants. Consultant and any subconsultant 
must maintain this insurance until all of their obligations have been discharged, including any 
warranty periods under this Agreement. These insurance requirements are minimum 
requirements for this Agreement and in no way limit the indemnity covenants contained in 
this Agreement. City in no way warrants that the minimum limits stated in Exhibit “C” are 
sufficient to protect Consultant from liabilities that might arise out of the performance of the 
work under this Agreement by Consultant, Consultant’s agents, representatives, employees, 
or subconsultants. Consultant is free to purchase such additional insurance as may be 
determined necessary. 
 
5.7 Cooperation and Further Documentation. Consultant agrees to provide City such other 
duly executed documents as may be reasonably requested by City to implement the intent 
of this Agreement. 
 
5.8 Successors and Assigns. City and Consultant each bind itself, its partners, successors, 
assigns, and legal representatives to the other party to this Agreement and to the partners, 
successors, assigns, and legal representatives of such other party in respect to all covenants 
of this Agreement. Neither City nor Consultant may assign, sublet, or transfer its interest in 
this Agreement without the written consent of the other party. In no event may any 
contractual relation be created between any third party and City. 
 
5.9 Disputes. In any dispute arising out of an interpretation of this Agreement or the duties 
required not disposed of by agreement between Consultant and City, the final determination 
at the administrative level will be made by City Engineer. 
 
5.10 Completeness and Accuracy of Consultant’s Work. Consultant must be responsible for 
the completeness and accuracy of Consultant’s services, data, and other work prepared or

Project Name: Chandler Heights - Gilbert Road to Val Vista Drive 
Page 6 
Project No.: ST1804.451; Federal No. CHN-0(244)D; ADOT No. T0203 01C 
 Rev. 1/12/2024 
 
 
compiled under Consultant’s obligation under this Agreement and must correct, at 
Consultant’s expense, all willful or negligent errors, omissions, or acts that may be discovered.  
Correction of errors disclosed and determined to exist during any construction of the project on 
architectural or engineering drawings and specifications must be accomplished by Consultant.  
The cost of the design necessary to correct those errors attributable to Consultant and any 
damage incurred by City as a result of additional construction costs caused by such engineering 
or architectural errors will be chargeable to Consultant and will not be considered a cost of the 
Work.  The fact that City has accepted or approved Consultant’s work will in no way relieve 
Consultant of any of Consultant’s responsibilities. 
 
5.11 Reporting. Written monthly reports, along with updated work schedules, will be made by 
Consultant in the format prescribed by City.  These reports will be delivered to City per schedule.  
When requested by City, Consultant will attend Council meetings and provide finished documents 
including correspondence for Council action, supporting charts, graphs, drawings and colored 
slides of same. 
 
5.12 Withholding Payment. City reserves the right to withhold funds from Consultant’s 
payments up to the amount equal to the claims City may have against Consultant until such 
time that a settlement on those claims has been reached. 
 
5.13 City's Right of Cancellation. The Parties acknowledge that this Agreement is subject to 
cancellation by City under the provisions of Section 38-511, Arizona Revised Statutes (A.R.S.). 
 
5.14 Independent Consultant. For this Agreement Consultant constitutes an independent 
contractor. Any provisions in this Agreement that may appear to give City the right to direct 
Consultant as to the details of accomplishing the work or to exercise a measure of control 
over the work means that Consultant must follow the wishes of City as to the results of the 
work only. These results must comply with all applicable laws and ordinances. 
 
5.15 Project Staffing. Prior to the start of any work under this Agreement, Consultant must 
submit to City detailed resumes of key personnel that will be involved in performing services 
prescribed in the Agreement. City hereby acknowledges its acceptance of such personnel to 
perform services under this Agreement. At any time hereafter that Consultant desires to 
change key personnel while performing under the Agreement, Consultant must submit the 
qualifications of the new personnel to City for prior approval. Key personnel include, but are 
not limited to, principals-in-charge, project manager, and project Consultant. Consultant will 
maintain an adequate and competent staff of qualified persons, as may be determined by 
City, throughout the performance of this Agreement to ensure acceptable and timely 
completion of the Scope of Services. If City objects, with reasonable cause, to any of 
Consultant’s staff, Consultant must take prompt corrective action acceptable to City and, if 
required, remove such personnel from the Project and replace with new personnel agreed to 
by City. 
 
5.16 Consultants or Subconsultants. Prior to beginning the work, Consultant must furnish City 
for approval the names of consultants or subconsultants to be used under this Agreement. 
Any subsequent changes are subject to City’s written prior approval. 
 
5.17 Force Majeure. If either party is delayed or prevented from the performance of any act

Project Name: Chandler Heights - Gilbert Road to Val Vista Drive 
Page 7 
Project No.: ST1804.451; Federal No. CHN-0(244)D; ADOT No. T0203 01C 
 Rev. 1/12/2024 
 
 
required under this Agreement by reason of acts of God or other cause beyond the control 
and without fault of the Party (financial inability excepted), performance of that act may be 
excused, but only for the period of the delay, if the Party provides written notice to the other 
Party within ten days of such act. The time for performance of the act may be extended for a 
period equivalent to the period of delay from the date written notice is received by the other 
Party. 
 
5.18 Compliance with Federal Laws. Consultant understands and acknowledges the 
applicability of the Americans with Disabilities Act, the Immigration Reform and Control Act 
of 1986 and the Drug Free Workplace Act of 1989 to it. Consultant agrees to comply with these 
laws in performing this Agreement and to permit City to verify such compliance. 
 
5.19 No Israel Boycott. By entering into this Agreement, Consultant certifies that Consultant 
is not currently engaged in, and agrees for the duration of the Agreement, not to engage in a 
boycott of Israel as defined by state statute. 
 
5.20 Legal Worker Requirements. A.R.S. § 41-4401 prohibits City from awarding an Agreement 
to any consultant who fails, or whose subconsultants fail, to comply with A.R.S. § 23-214(A). 
Therefore, Consultant agrees Consultant and each subconsultant it uses warrants their 
compliance with all federal immigration laws and regulations that relate to their employees 
and their compliance with § 23-214, subsection A. A breach of this warranty will be deemed a 
material breach of the Agreement and may be subject to penalties up to and including 
termination of the Agreement. City retains the legal right to inspect the papers of any 
Consultant’s or subconsultant’s employee who provides services under this Agreement to 
ensure that Consultant and subconsultants comply with the warranty under this provision. 
 
5.21 Lawful Presence Requirement. A.R.S. §§ 1-501 and 1-502 prohibit City from awarding an 
Agreement to any natural person who cannot establish that such person is lawfully present 
in the United States. To establish lawful presence, a person must produce qualifying 
identification and sign a City-provided affidavit affirming that the identification provided is 
genuine. This requirement will be imposed at the time of Agreement award. This requirement 
does not apply to business organizations such as corporations, partnerships, or limited 
liability companies. 
 
5.22 Covenant Against Contingent Fees. Consultant warrants that no person has been 
employed or retained to solicit or secure this Agreement upon an agreement or 
understanding for a commission, percentage, brokerage, or contingent fee, and that no 
member of the Chandler City Council, or any City employee has any interest, financially, or 
otherwise, in Consultant’s firm. For breach or violation of this warrant, City may annul this 
Agreement without liability or, at its discretion, to deduct from the Agreement price or 
consideration, the full amount of such commission, percentage, brokerage, or contingent fee. 
 
5.23 Non-Waiver Provision. The failure of either Party to enforce any of the provisions of this 
Agreement or to require performance of the other Party of any of the provisions hereof must 
not be construed to be a waiver of such provisions, nor must it affect the validity of this 
Agreement or any part thereof, or the right of either Party to thereafter enforce each and 
every provision.

Project Name: Chandler Heights - Gilbert Road to Val Vista Drive 
Page 8 
Project No.: ST1804.451; Federal No. CHN-0(244)D; ADOT No. T0203 01C 
 Rev. 1/12/2024 
 
 
5.24 Disclosure of Information Adverse to City’s Interests. To evaluate and avoid potential 
conflicts of interest, Consultant must provide written notice to City, as set forth in this Section, 
of any work or services performed by Consultant for third parties that may involve or be 
associated with any real property or personal property owned or leased by City. Such notice 
must be given 7 business days prior to commencement of the services by Consultant for a 
third party, or 7 business days prior to an adverse action as defined below. Written notice 
and disclosure must be sent in accordance with Section 6.7 above.  An adverse action under 
this Agreement includes, but is not limited to: (a) using data as defined in the Agreement 
acquired in connection with this Agreement to assist a third party in pursuing administrative 
or judicial action against City; or (b) testifying or providing evidence on behalf of any person 
in connection with an administrative or judicial action against City; or (c) using data to produce 
income for Consultant or its employees independently of performing the services under this 
Agreement, without the prior written consent of City. Consultant represents that except for 
those persons, entities, and projects identified to City, the services performed by Consultant 
under this Agreement are not expected to create an interest with any person, entity, or third 
party project that is or may be adverse to City’s interests. Consultant’s failure to provide a 
written notice and disclosure of the information as set forth in this Section constitute a 
material breach of this Agreement. 
 
5.25 Data Confidentiality and Data Security. As used in the Agreement, "data" means all 
information, whether written or verbal, including plans, photographs, studies, investigations, 
audits, analyses, samples, reports, calculations, internal memos, meeting minutes, data field 
notes, work product, proposals, correspondence and any other similar documents or 
information prepared by, obtained by, or transmitted to Consultant or its subconsultants in 
the performance of this Agreement. The Parties agree that all data, regardless of form, 
including originals, images, and reproductions, prepared by, obtained by, or transmitted to 
Consultant or its subconsultants in connection with Consultant’s or its subconsultant’s 
performance of this Agreement is confidential and proprietary information belonging to City. 
Except as specifically provided in this Agreement, Consultant or its subconsultants must not 
divulge data to any third party without City’s prior written consent. Consultant or its 
subconsultants must not use the data for any purposes except to perform the services 
required under this Agreement. These prohibitions do not apply to the following data 
provided to Consultant or its subconsultants have first given the required notice to City: (a) 
data which was known to Consultant or its subconsultants prior to its performance under this 
Consultant or its subconsultants by a third party, who to the best of Consultant’s or its 
subconsultants’ knowledge and belief, had the legal right to make such disclosure and 
Consultant or its subconsultants are not otherwise required to hold such data in confidence; 
or (c) data which is required to be disclosed by virtue of law, regulation, or court order, to 
which Consultant or its subconsultants are subject. In the event Consultant or its 
subconsultants are required or requested to disclose data to a third party, or any other 
information to which Consultant or its subconsultants became privy as a result of any other 
Agreement with City, Consultant must first notify City as set forth in this Section of the request 
or demand for the data. Consultant or its subconsultants must give City sufficient facts so 
that City can be given an opportunity to first give its consent or take such action that City may 
deem appropriate to protect such data or other information from disclosure. All data must 
continue to be subject to the confidentiality agreements of this Agreement. Consultant or its 
subconsultants assume all liability to maintain the confidentiality of the data in its possession 
and agrees to compensate City if any of the provisions of this Section are violated by

Project Name: Chandler Heights - Gilbert Road to Val Vista Drive 
Page 9 
Project No.: ST1804.451; Federal No. CHN-0(244)D; ADOT No. T0203 01C 
 Rev. 1/12/2024 
 
 
Consultant, its employees, agents or subconsultants. Solely for the purposes of seeking 
injunctive relief, it is agreed that a breach of this Section must be deemed to cause irreparable 
harm that justifies injunctive relief in court. Consultant agrees that the requirements of this 
Section must be incorporated into all subagreements entered into by Consultant. A violation 
of this Section may result in immediate termination of this Agreement without notice. 
 
5.26 Personal Identifying Information-Data Security. Personal identifying information, 
financial account information, or restricted City information, whether electronic format or 
hard copy, must be secured and protected at all times by Consultant or its subconsultants. At 
a minimum, Consultant or its subconsultants must encrypt or password-protect electronic 
files. This includes data saved to laptop computers, computerized devices, or removable 
storage devices. When personal identifying information, financial account information, or 
restricted City information, regardless of its format, is no longer necessary, the information 
must be redacted or destroyed through appropriate and secure methods that ensure the 
information cannot be viewed, accessed, or reconstructed. In the event that data collected or 
obtained by Consultant or its subconsultants in connection with this Agreement is believed 
to have been compromised, Consultant or its subconsultants must immediately notify City 
contact. Consultant agrees to reimburse City for any costs incurred by City to investigate 
potential breaches of this data and, where applicable, the cost of notifying individuals who 
may be impacted by the breach. Consultant agrees that the requirements of this Section must 
be incorporated into all subcontracts entered into by Consultant. It is further agreed that a 
violation of this Section must be deemed to cause irreparable harm that justifies injunctive 
relief in court. A violation of this Section may result in immediate termination of this 
Agreement without notice. The obligations of Consultant or its subconsultants under this 
Section must survive the termination of this Agreement. 
 
5.27 Jurisdiction and Venue. This Agreement is made under and must be construed in 
accordance with and governed by the laws of the State of Arizona without regard to the 
conflicts or choice of law provisions thereof. Any action to enforce any provision of this 
Agreement or to obtain any remedy with respect hereto must be brought in the courts 
located in Maricopa County, Arizona, and for this purpose, each Party hereby expressly and 
irrevocably consents to the jurisdiction and venue of such court. 
 
5.28 Survival. All warranties, representations, and indemnifications by Consultant must 
survive the completion or termination of this Agreement. 
 
5.29 Modification. Except as expressly provided herein to the contrary, no supplement, 
modification, or amendment of any term of this Agreement will be deemed binding or 
effective unless in writing and signed by the Parties.  
 
5.30 Severability. If any provision of this Agreement or the application to any person or 
circumstance may be invalid, illegal or unenforceable to any extent, the remainder of this 
Agreement and the application will not be affected and will be enforceable to the fullest 
extent permitted by law. 
 
5.31 Integration. This Agreement contains the full agreement of the Parties. Any prior or 
contemporaneous written or oral agreement between the Parties regarding the subject 
matter is merged and superseded.

Project Name: Chandler Heights - Gilbert Road to Val Vista Drive 
Page 10 
Project No.: ST1804.451; Federal No. CHN-0(244)D; ADOT No. T0203 01C 
 Rev. 1/12/2024 
 
 
 
5.32 Time is of the Essence. Time of each of the terms, covenants, and conditions of this 
Agreement is hereby expressly made of the essence. 
 
5.33 Date of Performance. If the date of performance of any obligation or the last day of any 
time period provided for should fall on a Saturday, Sunday, or holiday for City, the obligation 
will be due and owing, and the time period will expire, on the first day after which is not a 
Saturday, Sunday or legal City holiday. Except as may otherwise be set forth in this 
Agreement, any performance provided for herein will be timely made if completed no later 
than 5:00 p.m. (Chandler time) on the day of performance. 
 
5.34 Third Party Beneficiary. Nothing under this Agreement will be construed to give any 
rights or benefits in the Agreement to anyone other than City and Consultant, and all duties 
and responsibilities undertaken pursuant to this Agreement will be for the sole and exclusive 
benefit of City and Consultant and not for the benefit of any other party. 
 
5.35 Conflict in Language. All work performed must conform to all applicable City of Chandler 
codes, ordinances, and requirements as outlined in this Agreement. If there is a conflict in 
interpretation between provisions in this Agreement and those in Exhibit "A", the provisions 
in this Agreement prevail. 
 
5.36 Document/Information Release. Documents and materials released to Consultant, 
which are identified by City as sensitive and confidential, are City’s property. The 
document/material must be issued by and returned to City upon completion of the services 
under this Agreement. Consultant secondary distribution, disclosure, copying, or duplication 
in any manner is prohibited without City’s prior written approval. The document/material 
must be kept secure at all times. This directive applies to all City documents, whether in 
photographic, printed, or electronic data format.  
 
5.37 Exhibits. The following exhibits are made a part of this Agreement and are incorporated 
by reference: 
 
  
 
 
Exhibit A - Scope of Services / Schedule 
Exhibit B - Compensation and Fees 
Exhibit C - Insurance Requirements 
Exhibit D - Special Conditions 
Exhibit E – Subconsultant Documents with Consultant (if applicable) 
Exhibit F - Federal Requirements (if applicable)  
 
5.38 Special Conditions. As part of the services Consultant provides under this Agreement, 
Consultant agrees to comply with and fully perform the special terms and conditions set forth 
in Exhibit “D”, which is attached to and made a part of this Agreement. 
 
5.39 Non-Discrimination and Anti-Harassment Laws. Consultant must comply with all 
applicable City, state, and federal non-discrimination and anti-harassment laws, rules, and 
regulations. 
 
5.40 Licenses and Permits. Beginning with the Effective Date and for the full term of this

Project Name: Chandler Heights - Gilbert Road to Val Vista Drive 
Page 11 
Project No.: ST1804.451; Federal No. CHN-0(244)D; ADOT No. T0203 01C 
 Rev. 1/12/2024 
 
 
Agreement, Consultant must maintain all applicable City, state, and federal licenses and 
permits required to fully perform Consultant’s services under this Agreement. 
 
5.41 Warranties. Consultant must furnish a one-year warranty on all work and services 
performed under this Agreement. Consultant must furnish, or cause to be furnished, a two-
year warranty on all fixtures, furnishings, and equipment furnished by Consultant, 
subconsultants or suppliers under this Agreement. Any defects in design, workmanship, or 
materials that do not comply with this Agreement must be corrected by Consultant (including, 
but not limited to, all parts and labor) at Consultant’s sole cost and expense. All written 
warranties and redlines for as-built conditions must be delivered to City on or before City’s 
final acceptance of Consultant’s services under this Agreement.  
 
5.42 Cooperative Purchasing Agreement (S.A.V.E. – Strategic Alliance for Volume 
Expenditures).  In addition to City of Chandler and with the approval of Consultant, this 
Agreement may be extended for use by other municipalities, school districts, and government 
agencies of the State.  Any such usage by other entities must be in accordance with the 
ordinance, charter, or procurement rules and regulations of the respective political entity.   
 
5.43 Budget Approval into Next Fiscal Year.  This Agreement will commence on the Effective 
Date and continue in full force and effect until it is terminated or expires in accordance with 
the provisions of this Agreement.  The Parties recognize that the continuation of this 
Agreement after the close of the City's fiscal year, which ends on June 30 of each year, is 
subject to the City Council's approval of a budget that includes an appropriation for this item 
as an expenditure.  The City does not represent that this budget item will be actually adopted. 
This determination is solely made by the City Council. 
 
5.44 Forced Labor of Ethnic Uyghurs Prohibited.  By entering into this Agreement, Contractor 
certifies and agrees Contractor does not currently use and will not use for the term of this 
Agreement: (i) the forced labor of ethnic Uyghurs in the People's Republic of China; or (ii) any 
goods or services produced by the forced labor of ethnic Uyghurs in the People's Republic of 
China; or (iii) any contractors, subcontractors or suppliers that use the forced labor or any 
goods or services produced by the forced labor of ethnic Uyghurs in the People's Republic of 
China. 
 
5.45 License to City for Reasonable Use. With this Agreement, Consultant and its 
subconsultants hereby grant a license to City, its agents, employees, and representatives for 
an indefinite period of time to reasonably use, make copies, and distribute as appropriate 
the Documents, works or deliverables developed or created as a result of the Project and this 
Agreement. This license also includes the making of derivative works.

Project Name: Chandler Heights - Gilbert Road to Val Vista Drive 
Page 12 
Project No.: ST1804.451; Federal No. CHN-0(244)D; ADOT No. T0203 01C
 Rev. 1/12/2024 
 
This Agreement will be in full force and effect only when it has been approved and executed 
by the duly authorized City officials. 
IN WITNESS WHEREOF, the Parties have executed this Agreement as of the Effective Date. 
“CITY” CITY OF CHANDLER 
MAYOR 
RECOMMENDED BY: 
Daniel Haskins, P.E. 
CIP City Engineer   
APPROVED AS TO FORM: 
City Attorney 
ATTEST: 
 City Clerk 
 Seal 
“CONSULTANT” 
CONSULTANT ENGINEERING, INC. 
Signature 
 Date 
Print Name 
Title 
Signer Email Address 
September 18, 2024
Brian Lizzet
Project Manager/Principal
blizzet@cei-az.com

Project Name: Chandler Heights - Gilbert Road to Val Vista Drive 
Page A-1  
Project No.: ST1804.451; Federal No. CHN-0(244)D; ADOT No. T0203 01C 
Rev. 1/12/2024 
 
 
EXHIBIT “A” 
SCOPE OF SERVICES/SCHEDULE

September 11, 2024 
 
Mr. Jason Garcia 
 
 
 
 
 
 
Email: 
jason.garcia@chandleraz.gov 
Construction Project Manager 
City of Chandler 
Capital Projects Division 
PO Box 4008, Mail Stop 407 
Chandler, AZ 85244-4008 
 
Re: 
Fee Schedule 
Chandler Heights Road – Gilbert Road to Val Vista Drive 
 
City of Chandler Project No.: ST1804.451 
Federal Project No.: CHN-0(244)D 
ADOT Project No.: T0203 01C 
 
CEI Project No. 0124025.00 
 
Dear Mr. Garcia: 
 
Consultant Engineering, Inc. (CEI) would like to thank the City of Chandler for selecting our firm for the Chandler Heights Road project, from 
Gilbert Road to Val Vista Drive. 
 
Attached, please find our fee proposal, the Construction Management Scope of Services (Exhibit “A”) and Fee Schedules (Exhibit “B”) as well as 
sub consultants’ fee schedules (Exhibits “C”, “D”, “E” and “F”) for your consideration. Our total fee for this project is $1,035,646.10. The proposal 
is based on a total construction duration of 335 calendar days as well as pre-construction assistance and typical close-out services. 
 
As requested, the proposal effort hours for the key staff members during construction includes Brian Lizzet (Project Manager/Senior Resident 
Engineer) with a 3%-time commitment; Pat Mahoney (Resident Engineer) with a 49% time commitment; John Helton (COC Liaison) with a 5%-
time commitment; Daniel Blount (Project Supervisor) with a 50% time commitment; Ryan Warling (Construction Inspector) with a 100%-time 
commitment;  Shanelle Fiske-Bowser (Administrator/Manager) with a 20%-time commitment; Mark Schalliol (Landscape Architect) with a 5%-
time commitment and Dan Ross (Schedule Reviewer) with a 2% time commitment. We have also included allotted time for Saturdays. Our sub-
consultants’ proposals include: Tristar Engineering and Management for inspection support, Quality Testing for QA Materials Testing services, 
MakPro for public reach-out/awareness services and Atek Engineering Consultants for Independent Assurance Testing services.  
 
If you have any questions or require additional information, please feel free to contact me at 480-689-6472 or blizzet@cei-az.com. 
 
CEI looks forward to continuing working with you and the City of Chandler on this contract. 
 
Sincerely, 
 
CONSULTANT ENGINEERING, INC. 
 
 
 
 
Brian Lizzet, PE, CCM 
Project Manager/Principal 
 
Attachment:  
Exhibit A – Scope of Services 
Exhibit B – Fee Schedule 
Exhibit C – Makinen Professional Services (MakPro) Fee Schedule 
 
 
Exhibit D – Quality Testing, LLC (QT) Fee Schedule 
 
 
Exhibit E – Atek Engineering Consultants (Atek) Fee Schedule 
 
 
Exhibit F – Tristar Engineering and Management, Inc. (Tristar) Fee Schedule 
 
 
cc: 
Contract Administration (CEI # 0124025.00)

EXHIBIT “A” 
 
CONSTRUCTION MANAGEMENT 
SCOPE OF SERVICES 
(FHWA FUNDED PROJECTS) 
 
PROJECT TASKS 
 
1. 
PRE-CONSTRUCTION ASSISTANCE 
A. Task 1.1 Preconstruction Assistance  
i. Consultant will have general project coordination with City and contractor 
(2 hours for PM, and City Liaison, 16 hours for RE) 
ii. Consultant must attend the pre-construction meeting.  (2 hours each) 
iii. Consultant will review project plans, documents and take pre-
construction photos (16 hours for Project Supervisor and Construction 
Inspector) 
iv. Consultant must review and evaluate Contractor’s initial CPM schedule 
and provide recommendations for acceptance. (16 hours for Scheduler) 
 
2. 
CONSTRUCTION MANAGEMENT  
A. Task 2.1 Weekly Construction Meetings 
i. Consultant must conduct weekly construction meetings.  Each meeting 
includes agenda and minutes; Request for Information (RFI); Shop 
Drawing; Request for Information (RFI); Field Directive (FD); Material 
Certification; and Allowance Logs. Consultant assumes 45 weekly 
meetings will be held. (1 to 2 hours for PM/RE/Liaison) 
B. Task 2.2 CPM Schedule 
i. Consultant must review Contractor’s monthly CPM schedule updates 
submitted with each payment application, identify CPM tasks behind 
schedule that may affect critical path items, project substantial and final 
completion dates and initiate correspondence to City regarding those 
tasks. Consultant assumes 11 reviews of updated CPM schedule. (4 hours 
total for PM, 2 hours each for RE, 4 hours each for Scheduler) 
C. Task 2.3 Requests for Information (RFI’s) 
i. Consultant must review, evaluate, and respond to Contractor Requests 
for Information (RFI’s); and prepare and maintain a submittal log of all 
RFI’s. Consultant assumes a maximum of 15 RFI responses. (4 hours each 
reply.  Hours includes site visits, administration/coordination prior 
to RFI, for RE)  
D. Task 2.4 Shop Drawing Submittals 
i. Consultant must review, evaluate, and respond to Contractor shop 
drawing submittals; and prepare and maintain a submittal log of all shop 
drawing submittals. Consultant assumes a maximum of 60 reviews. (4 
hours each review for RE, 20 hours for Landscape Architect)

Page 2
E. Task 2.5 Requests for Proposal (RFP) 
i. Consultant must prepare Requests for Proposal (RFP) documents 
detailing requested additional work tasks; review and evaluate Contractor 
RFP responses (cost derivations) with approval recommendations; and 
prepare and maintain a submittal log list of all RFP’s. Consultant assumes 
10 RFPs.  (4 hours each for RE) 
F.  Task 2.6 Field Directives (FD’s) 
i. Consultant must prepare Field Directive (FD) documents detailing 
requested additional work tasks; review and evaluate Contractor FD 
responses with approval recommendations; and prepare and maintain a 
submittal log list of all FD’s. Consultant assumes 15 FD’s.  (4 hours total 
for PM and 2 hours for RE) 
G. Task 2.7 Contractor Payment Applications 
i. Consultant must review and evaluate Contractor monthly payment 
applications and make recommendation for payment; maintain a weekly 
record of constructed pay quantities and compile monthly totals; and 
coordinate payment application with the City quantity report and the 
inspectors’ daily logs. Consultant assumes a maximum of 12 payment 
applications, with 2 reviews each. (4 hours total for PM, City Liaison, 2 
hours for RE each month) 
H.  Task 2.8 Public Outreach 
i. Consultant must provide public outreach services, whether by Consultant 
or subconsultant.  Tasks will include: create and maintain project website; 
maintain a 24-hour trilingual project hotline to respond to inquiries, 
complaints and maintain a call log; public weekly email updates; public 
interactions with property owners as a liaison between property owners 
and the City; coordination meetings; project meetings; public meeting 
coordination; federal funds required partnering process (project team 
partnering meeting, maintaining status). (4 hours total for PM, 1 hour 
each month for RE with PRC). 
 
3. 
CONSTRUCTION ADMINISTRATION 
A. Task 3.1 Federal Compliance Administration  
i. Consultant must provide administrative support to City staff for federal 
reporting requirements. Consultant assumes 1 administrative Support for 
11 months at 33 hours per month.  
B. Task 3.2 Administrative Support   
i. Consultant must provide administrative support to City staff throughout 
project for 11 months. (30 hours/month for RE, 4 hours/month for 
City Liaison) 
 
4. 
CONSTRUCTION INSPECTION 
A. Task 4.1 Inspection Services 
i. Consultant must provide weekly construction inspection to verify 
materials and installations conform to construction documents; prepare

Page 3
daily inspection reports documenting Contractor construction activities 
and progress during field inspection visits; and perform intermittent 
erosion control inspections.  Consultant assumes 2 inspectors; 1 full time 
and 1 half-time for 40 to 20 hours per week for 11 months. Consultant 
assumes 10% overtime for Construction Inspector. (5 hours/month 
for City Liaison as well). 
 
B. Task 4.2 Landscape / Irrigation Inspection Services     
i. Consultant must provide Irrigation system layout and installation 
observations; attend and observe irrigation system pressure tests; and 
attend a nursery visit to tag and inspect plant material. Consultant 
assumes 11 site visits. (8 hours each for Landscape Architect) 
 
C. Task 4.3 Project Closeout    
i. Consultant must compile non-conformance list prior to Substantial 
Completion; schedule and conduct Substantial Completion inspection; 
prepare Substantial Completion punch list generated from Substantial 
Completion inspection; track items on punch list and note completed 
items; and complete and distribute Substantial Completion certificates. 
(12 hours for PM, 20 hours each for City Liaison, Project Supervisor, 
and Federal Support; 24 hours for Landscape Architect) 
ii. Consultant must schedule and conduct Final Completion inspection; and 
complete and distribute Final Completion certificates. (20 hours for RE). 
 
5. 
UTILITY COORDINATION  
A. Task 5.1 Utility Coordination  
i. Consultant must complete Acceptance of Construction (AOC) applications 
and submit to MCESD for reclaimed water booster pump and potable 
water/sewer improvements.  (0 hours – this is completed by EOR) 
ii. Coordination with various utilities including RWCD (10 for PM and 40 
hours for RE) 
 
6. 
MATERIALS TESTING 
A. Task 6.1 Quality Control (QC) Test Program 
i. Consultant must review and verify Contractor’s Quality Control material 
test type and frequencies are consistent with City, MAG, and ADOT 
requirements; review and evaluate Contractor’s QC test schedule and 
provide recommendations on acceptance; and review and evaluate all 
Contractor sampling, test, and inspection results for conformance with 
construction documents. (1 hour total for PM, 2 total for RE) 
B. Task 6.2 Quality Assurance (QA) Test Program 
i. Consultant must prepare and maintain a materials Quality Assurance plan 
per City, MAG, and ADOT requirements. QA plan will be reviewed and 
approved by ADOT prior to initiating construction activities. (1 hour total 
for PM; 1 hour/month for RE, coordination with QA subconsultant)

Page 4
ii. Consultant must coordinate with Contractor’s testing representative to 
obtain required QA tests and sample; complete sampling and compaction 
testing of subgrade (including lime-stabilized subgrade base), aggregate 
base and asphalt concrete materials in new asphalt concrete pavement 
areas; complete sampling and compaction testing of subgrade, aggregate 
base (where required) and concrete for new curbs, gutters, sidewalks and 
concrete pavement and structures; and complete sampling and 
compaction testing of backfill for new irrigation, sewer, water, storm drain 
pipe, and dry utilities. (Included in QA subconsultant fee) 
 
C. Task 6.3 Material Certifications   
i. Consultant must review and verify material certifications are met 
including “Buy America” requirements; and prepare and maintain 
materials certificate and “Buy America” requirement submittal log. (2 
hours/month for RE, remainder included in QA subconsultant fee) 
 
D. Task 6.4 Independent Assurance (IA) Test Program  
i. Consultant must provide 3rd party independent quality assurance 
sampling and testing per the approved QA program produced in task 
6.2.i. (1 hours total for PM, 0.5 hour/month for RE, coordination with 
IA subconsultant). 
7. 
RECORD DRAWINGS  
A. Task 7.1 Record Drawings 
i.  Review and monitor Contractor’s weekly updates on red-line drawing set. 
(4 hours/week for Project Supervisor,40 hours total for City Liaison, 2 
hours total for PM and RE). 
 
ASSUMPTION, CLARIFICATIONS, AND EXCLUSIONS 
1. 
Application fees for City reviews and permits will be paid by CITY. 
2. 
The Owner’s Allowance will only be utilized with prior written approval from the City 
representative (Shown as $50,000). 
3. 
Contract work must be performed in accordance with Exhibit D Title VI Assurances 
Appendix A and Exhibit E Title VI Assurances Appendix E.

Project Name: Chandler Heights - Gilbert Road to Val Vista Drive 
Page B-1 
Project No.: ST1804.451; Federal No. CHN-0(244)D; ADOT No. T0203 01C  
Rev. 1/12/2024 
 
 
EXHIBIT “B” 
COMPENSATION AND FEES

Task
Cost
1
1.1
$12,530.00
12,530.00
$                  
2
2.1
$29,285.00
2.2
$12,600.00
2.3
$11,400.00
2.4
$48,500.00
2.5
$7,600.00
2.6
$6,640.00
2.7
$6,040.00
2.8
$3,030.00
125,095.00
$                
3
3.1
$41,745.00
3.2
$68,640.00
SUBTOTAL TASK 3:
110,385.00
$                
Public Outreach
CONSTRUCTION ADMINISTRATION
Pre-Construction Assistance
EXHIBIT "B-1"
CONSTRUCTION MANAGEMENT
SCOPE OF SERVICES
(FHWA FUNDED PROJECTS)
FEE SCHEDULE
Description
PRE-CONSTRUCTION ASSISTANCE
Requests for Proposal (RFP)
CPM Schedule
Requests for Information (RFI)
CONSTRUCTION MANAGEMENT
SUBTOTAL TASK 1:
SUBTOTAL TASK 2:
Shop Drawing Submittals
Weekly Construction Meetings
Field Directive (FD)
Administrative Support
Contractor Payment Applications
Federal Compliance Administration

Page 2
 
4
4.1
$399,835.00
4.2
$12,760.00
4.3
$21,600.00
434,195.00
$                
5
5.1
$9,950.00
9,950.00
$                    
6
MATERIALS TESTING
6.1
$615.00
6.2
$2,325.00
6.3
$4,560.00
6.4
$1,375.00
8,875.00
$                    
7
7.1
$12,190.00
12,190.00
$                  
34,100.00
$                   
142,815.00
$                 
10,071.10
$                   
85,440.00
$                   
272,426.10
$                
50,000.00
$                   
50,000.00
$                  
1,035,646.10
$    
SUBTOTAL TASK 4:
SUBTOTAL TASK 5:
SUBTOTAL TASK 6:
QC Test Program
Landscape/Irrigation Inspection Services
Project Closeout
UTILITY COORDINATION
Inspection Services
CONSTRUCTION INSPECTION
Record Drawings
Material Certifications
IA Test Program
RECORD DRAWINGS
QA Test Program
Utility Coordination 
Owner's Allowance
SUBTOTAL ALLOWANCES:
PROJECT TOTAL:
SUBTOTAL TASK 7:
SUBTOTAL SUBCONSULTANTS:
Makinen Professional Services
Atek Engineering Consultants
Tristar Engineering and Management, Inc.
SUBCONSULTANTS
ALLOWANCES
Quality Testing, LLC

Classification
Hours
Hourly Rate
Cost
Pre-construction Phase - 1 month
Project Manager (Brian Lizzet) 
4
$235.00
$940.00
Resident Engineer (Pat Mahoney)
18
$190.00
$3,420.00
COC Liaison/Oversight (John Helton)
4
$135.00
$540.00
Project Supervisor (Daniel Blount)
18
$135.00
$2,430.00
Senior Inspector (Ryan Warling)
18
$125.00
$2,250.00
Landscape Architect (Mark Schalliol)
0
$145.00
$0.00
Schedule Reviewer (Dan Ross)
16
$170.00
$2,720.00
Administrator/Manager (Shanelle Fiske-Bowser)
2
$115.00
$230.00
Subtotal Pre-construction
 
$12,530.00
Construction Phase - 11 months
Project Manager (Brian Lizzet) 
55
$235.00
$12,925.00
Resident Engineer (Pat Mahoney)
930
$190.00
$176,700.00
COC Liaison/Oversight (John Helton)
93
$135.00
$12,555.00
Project Supervisor (Daniel Blount)
946
$135.00
$127,710.00
Senior Inspector (Ryan Warling)
1892
$125.00
$236,500.00
Senior Inspector (Ryan Warling) - Overtime
190
$187.50
$35,625.00
Landscape Architect (Mark Schalliol)
108
$145.00
$15,660.00
Schedule Reviewer (Dan Ross)
44
$170.00
$7,480.00
Administrator/Manager (Shanelle Fiske-Bowser)
363
$115.00
$41,745.00
Subtotal Construction
 
$666,900.00
Post-Construction/Close-Out Phase - 3 months
Project Manager (Brian Lizzet) 
14
$235.00
$3,290.00
Resident Engineer (Pat Mahoney)
42
$190.00
$7,980.00
COC Liaison/Oversight (John Helton)
60
$135.00
$8,100.00
Project Supervisor (Daniel Blount)
64
$135.00
$8,640.00
Senior Inspector (Ryan Warling)
0
$125.00
$0.00
Schedule Reviewer (Dan Ross)
0
$170.00
$0.00
Landscape Architect (Mark Schalliol)
24
$145.00
$3,480.00
Administrator/Manager (Shanelle Fiske-Bowser)
20
$115.00
$2,300.00
Subtotal Post-Construction
 
$33,790.00
TOTAL
$713,220.00
Subconsultants 
Makinen Professional Services - Exhibit "C"
$34,100.00
Quality Testing, LLC - Exhibit "D"
$142,815.00
Atek Engineering Consultants - Exhibit "E"
$10,071.10
Tristar Engineering and Management, Inc - "Exhibit F"
$85,440.00
Subconsultants Subtotal
$272,426.10
Owner's Allowance
Owner's Allowance
$50,000.00
Total Cost
$1,035,646.10
Limitations & Conditions and Assumptions:
All rates are loaded rates and include all equipment, trucks, cell phones, laptops,  gas, maintenance, Citrx Sharefile and office supplies.
Pre-construction and post-construction hours are based on anticipated tasks as per the scope of work.
Fee based on Construction duration of 11 months / 335 calendar days + 30 days start up and 90 days close out
Inspectors will be fully equipped with vehicles, computers, cell phones, inspector tools, camera, and equipment required to perform their tasks.
Overtime hours for field staff will be billed at 1.5 times the billing rate
Subconsultants' schedule of efforts and cost break-down is attached.
                       CM Services Fee Proposal (Exhibit B-2)
Chandler Heights: Gilbert Road to Val Vista Drive
City of Chandler Project No. ST1804.451 | Federal Number: CHN-0(244)D | ADOT Project No. T020301C
Cost Proposal - September 2024

Project Name: Chandler Heights - Gilbert Road to Val Vista Drive 
Page C-1 
Project No.: ST1804.451; Federal No. CHN-0(244)D; ADOT No. T0203 01C 
Rev. 1/12/2024 
 
 
EXHIBIT “C” 
INSURANCE REQUIREMENTS 
 
1. 
General. 
 
1.1 At the same time as execution of this Agreement, Consultant must furnish City a certificate 
of insurance on a standard insurance industry ACORD form.  The ACORD form must be 
issued by an insurance company authorized to transact business in the State of Arizona 
possessing a current A.M. Best, Inc. rating of A-7, or better and legally authorized to do 
business in the State of Arizona with policies and forms satisfactory to City.  Provided, 
however, the A.M. Best rating requirement will not be deemed to apply to required Workers’ 
Compensation coverage.  
 
1.2 Consultant and any of its subconsultants must procure and maintain, until all of their 
obligations have been discharged, including any warranty periods under this Agreement are 
satisfied, the insurances set forth below. 
 
1.3 The insurance requirements set forth below are minimum requirements for this Agreement 
and in no way limit the indemnity covenants contained in this Agreement. 
 
1.4 City in no way warrants that the minimum insurance limits contained in this Agreement are 
sufficient to protect Consultant from liabilities that might arise out of the performance of 
the Agreement services under this Agreement by Consultant, its agents, representatives, 
employees, subconsultants, and Consultant is free to purchase any additional insurance as 
may be determined necessary. 
 
1.5 Failure to demand evidence of full compliance with the insurance requirements in this 
Agreement or failure to identify any insurance deficiency will not relieve Consultant from, 
nor will it be considered a waiver of its obligation to maintain the required insurance at all 
times during the performance of this Agreement. 
 
1.6 Use of subconsultants:  If any work is subcontracted in any way, Consultant must execute a 
written Agreement with subconsultant containing the same Indemnification Clause and 
Insurance Requirements as City requires of Consultant in this Agreement. Consultant is 
responsible for executing the Agreement with the subconsultant and obtaining Certificates 
of Insurance and verifying the insurance requirements. 
 
2. 
Minimum Scope and Limits of Insurance.  Consultant must provide coverage with limits of 
liability not less than those stated below. 
 
2.1 Professional Liability.  If the Agreement is the subject of any professional services or work 
performed by Consultant, or if Consultant engages in any professional services or work 
adjunct or residual to performing the work under this Agreement, Consultant must maintain 
Professional Liability insurance covering errors and omissions arising out of the work or 
services performed by Consultant, or anyone employed by Consultant, or anyone whose 
acts, mistakes, errors and omissions Consultant is legally liable, with a liability limit of 
$1,000,000 each claim and $2,000,000 all claims.  In the event the Professional Liability 
insurance policy is written on a “claims made” basis, coverage must extend for 3 years past

Project Name: Chandler Heights - Gilbert Road to Val Vista Drive 
Page C-2 
Project No.: ST1804.451; Federal No. CHN-0(244)D; ADOT No. T0203 01C 
Rev. 1/12/2024 
 
 
completion and acceptance of the work or services, and Consultant, or its selected Design 
Professional will submit Certificates of Insurance as evidence the required coverage is in 
effect.  The Design Professional must annually submit Certificates of Insurance citing that the 
applicable coverage is in force and contains the required provisions for a 3 year period. 
 
2.2 Commercial General Liability-Occurrence Form.  Consultant must maintain “occurrence” form 
Commercial General Liability insurance with a limit of not less than $2,000,000 for each 
occurrence, $4,000,000 aggregate.  Said insurance must also include coverage for products 
and completed operations, independent contractors, personal injury and advertising injury. 
If any Excess insurance is utilized to fulfill the requirements of this paragraph, the Excess 
insurance must be “follow form” equal or broader in coverage scope than underlying 
insurance. 
 
2.3 Automobile Liability-Any Auto or Owned, Hired and Non-Owned Vehicles  
 
Vehicle Liability:  Consultant must maintain Business/Automobile Liability insurance with a 
limit of $1,000,000 each accident on Consultant owned, hired, and non-owned vehicles 
assigned to or used in the performance of Consultant’s work or services under this 
Agreement.  If any Excess or Umbrella insurance is utilized to fulfill the requirements of this 
paragraph, the Excess or Umbrella insurance must be “follow form” equal or broader in 
coverage scope than underlying insurance. 
 
2.4 Workers Compensation and Employers Liability Insurance:  Consultant must maintain Workers 
Compensation insurance to cover obligations imposed by federal and state statutes having 
jurisdiction of Consultant employees engaged in the performance of work or services under 
this Agreement and must also maintain Employers’ Liability insurance of not less than 
$1,000,000 for each accident and $1,000,000 disease for each employee. 
 
3. 
Additional Policy Provisions Required. 
 
3.1 Self-Insured Retentions or Deductibles.  Any self-insured retentions and deductibles must be 
declared and approved by City.  If not approved, City may require that the insurer reduce or 
eliminate any deductible or self-insured retentions with respect to City, its officers, officials, 
agents, employees, and volunteers. 
 
3.1.1. Consultant’s insurance must contain broad form contractual liability coverage. 
 
3.1.2. Consultant’s insurance coverage must be primary insurance with respect to City, its 
officers, officials, agents, and employees.  Any insurance or self-insurance maintained 
by City, its officers, officials, agents, and employees will be in excess of the coverage 
provided by Consultant and must not contribute to it. 
 
3.1.3. Consultant’s insurance must apply separately to each insured against whom claim is 
made or suit is brought, except with respect to the limits of the insurer's liability. 
 
3.1.4. Coverage provided by Consultant must not be limited to the liability assumed under 
the indemnification provisions of this Agreement.

Project Name: Chandler Heights - Gilbert Road to Val Vista Drive 
Page C-3 
Project No.: ST1804.451; Federal No. CHN-0(244)D; ADOT No. T0203 01C 
Rev. 1/12/2024 
 
 
3.1.5. The policies must contain a severability of interest clause and waiver of subrogation 
against City, its officers, officials, agents, and employees, for losses arising from Work 
performed by Consultant for City. (Does not apply to Professional Liability coverage.) 
 
3.1.6. Consultant, its successors and or assigns, are required to maintain Commercial 
General Liability insurance as specified in this Agreement for a minimum period of 3 
years following completion and acceptance of the Work.  Consultant must submit a 
Certificate of Insurance evidencing Commercial General Liability insurance during this 
3-year period containing all the Agreement insurance requirements, including 
naming City of Chandler, its agents, representatives, officers, directors, officials and 
employees as Additional Insured as required. 
 
3.1.7. If a Certificate of Insurance is submitted as verification of coverage, City will 
reasonably rely upon the Certificate of Insurance as evidence of coverage, but this 
acceptance and reliance will not waive or alter in any way the insurance requirements 
or obligations of this Agreement.   
 
3.2.  Insurance Cancellation During Term of Agreement.  
3.2.1. If any of the required policies expire during the life of this Agreement, Consultant 
must forward renewal or replacement Certificates to City within 10 days after the 
renewal date containing all the required insurance provisions. 
 
3.2.2. Each insurance policy required by the insurance provisions of this Agreement must 
provide the required coverage and must not be suspended, voided or canceled 
except after thirty (30) days prior written notice has been given to City, except when 
cancellation is for non-payment of premium, then ten (10) days prior notice may be 
given.  Such notice must be sent directly to Chandler Law-Risk Management 
Department, Post Office Box 4008, Mailstop 628, Chandler, Arizona 85225. If any 
insurance company refuses to provide the required notice, Consultant or its 
insurance broker must notify City of any cancellation, suspension, non-renewal of any 
insurance within seven (7) days of receipt of insurers’ notification to that effect.  
 
3.3 
City as Additional Insured.  The policies are to contain, or be endorsed to contain, the following 
provisions: 
3.3.1. The Commercial General Liability and Automobile Liability policies are to contain, or 
be endorsed to contain, the following provisions:  City, its officers, officials, agents, 
and employees are additional insureds with respect to liability arising out of activities 
performed by, or on behalf of, Consultant; Products and Completed operations of 
Consultant; and automobiles owned, leased, hired, or borrowed by Consultant. 
 
3.3.2. City, its officers, officials, agents, and employees must be additional insureds to the 
full limits of liability purchased by Consultant even if those limits of liability are in 
excess of those required by this Agreement.

Project Name: Chandler Heights - Gilbert Road to Val Vista Drive 
Page D-1 
Project No.: ST1804.451; Federal No. CHN-0(244)D; ADOT No. T0203 01C 
Rev. 1/12/2024 
 
 
EXHIBIT “D” 
SPECIAL CONDITIONS 
 
 
 
Work within City's Right-of-Way. All work performed within City's Right-of-Way by Consultant 
and Consultant’s subconsultants must comply with City of Chandler requirements.

Project Name: Chandler Heights - Gilbert Road to Val Vista Drive 
E-1 
Project No.: ST1804.451; Federal No. CHN-0(244)D; ADOT No. T0203 01C 
Rev. 1/12/2024 
 
 
 
EXHIBIT “E” 
SUBCONSULTANT DOCUMENTS WITH CONSULTANT 
 
 
Any subconsultant assumptions, clarifications, exclusions, terms & conditions, 
signature blocks, etc. included are strictly between the Consultant and their 
subconsultants, and do not apply to the Agreement between the Consultant and 
the City.

MakPro Services, LLC 
2036 N. Gentry • Mesa, AZ 85213 
Office: 480-890-1927 
Email:  teresa@makprosvc.com 
August 27, 2024 
Mr. Brian Lizzet 
Consultant Engineering, Inc. 
135 E Chilton Dr., Suite 101 
Chandler, AZ  85225 
Dear Brian: 
MakPro Services, LLC (MakPro) is pleased to provide the following proposal for public outreach 
services for the City of Chandler for the Chandler Heights Road Improvements (ST1804.451 
CHN0224D T020301C), which will widen Chandler Heights Road, from Gilbert Road to Val Vista 
Drive, to four lanes including raised landscaped median, bike lanes, curb, gutter, and sidewalk, 
including ADA upgrades, traffic signals, LED streetlights, storm drainage, irrigation, and 
associated utility installation or relocation. Public outreach is an important element in projects 
that impact neighboring residents and businesses and provides a link between the project and 
the community it impacts. The City of Chandler has developed a strong relationship with its 
residents and businesses, and during design MakPro was on-team to assist in the interaction 
with nearby stakeholders so it will be important to continue this communication into 
construction. Many times, this link is all that is needed to help a project run more smoothly.     
There are a variety of public outreach tools which can be used to establish appropriate 
communication with the effected stakeholders of a project. The services included in this scope 
and fee are based on my experience with the City of Chandler and CEI on similar current and 
previous projects, and previous experience during design for this project. This estimate is based 
on an estimated 11-month construction schedule. In addition, the public outreach services have 
been categorized into tasks; however, adjusting one task may require adjustment of other tasks 
as there are economies of scale and efficiencies embedded in the cost estimate.     
Please take a moment to review this scope and cost estimate and if I’ve missed or 
misunderstood any of the project characteristics, or if you’d like to customize this proposal in 
some other way, please let me know.   
Task 1:  Pre-Construction Meeting, Partnering Meeting, Project Progress Meetings 
and Ongoing Team Communication 
MakPro will prepare for and attend the pre-construction meeting, coordinate and facilitate the 
partnering meeting and attend progress meetings during construction (11 months ~ 48 
meetings), as well as participate in ongoing team communications throughout the project. This 
task also includes monitoring the partnering process with monthly PEP evaluations and tracking. 
Task 2:  Community Construction Notices & Communications 
Prior to start of construction, MakPro shall develop, print, coordinate and mail one printed pre-
construction notice to project area businesses and residents, and also those property owners 
directly adjacent to the work area. As this is a federal project, collateral will be provided in 
EXHIBIT C

Mr. Brian Lizzet, Consultant Engineering, Inc. 
     
August 27, 2024  
                          
Public Outreach Svcs – Chandler Heights Rd (Gilbert to Val Vista)  (ST1804.401 CHN0224D T020301C)    
 
 
 
English, Spanish and Mandarin languages.  It is expected there may be additional notifications 
for access restrictions or night work, so this estimate includes one additional mailer to 
accommodate that effort.   
 
MakPro will assist the construction management team with resident coordination for properties 
where work will take place related to walls, and compile contact information for HOAs and 
businesses for use by the project team to better schedule construction-related impacts. 
Reimbursable expenses for postage/printing of pre-construction notices are included as part of 
this estimate. Based on our previous experience in this area during design, this would be a 1/4-
mile radius distribution area from Gilbert to Val Vista, with approx. 1,300 pieces. 
 
Task 3:  Project Communications   
• 
Project Webpage: MakPro shall develop and maintain a project webpage for the project on 
ChandlerAz.gov, capable of multi-lingual information, which will include information about 
the project design, construction schedule and how to contact the project team. The site will 
be updated with any new information on a regular basis. 
 
• 
Project E-Updates:  MakPro shall prepare regular email updates with upcoming construction 
schedule information and maintain a distribution list of those interested in the project.   
 
• 
Hotline: MakPro shall maintain a 24-hour bilingual project hotline to respond to inquiries or 
complaints, maintain a call log and coordinate with the project team to respond to calls. 
 
The total cost for public outreach services as identified above and based on an 11-month 
project schedule should not exceed $34,100.00, which includes a $6,500 estimate 
for printing, distribution and translation costs. This cost estimate assumes a labor rate of 
$120/hour for principal and $100/hour for associate hours, and includes meeting preparation, 
materials and equipment, and local transportation. The project hotline is billed at $300/mo for 
availability 24/7, and progress meetings have a one-hour minimum. Excluded from this estimate 
are any unusual out-of-pocket expenses requested by the sponsor. It should be noted that 
reimbursable expenses for this project have been estimated, based on an approximately 1/4-
mile boundary for distribution. This estimate also incorporates efficiencies from one task/activity 
to another, so removal of an activity may require an adjustment of hours in other activities.   
 
Activity 
Principal Hrs 
($120/hr) 
Associate 
Hrs ($100/hr) 
Total 
Public Outreach Services 
 
 
 
Task 1: Pre-construction, Partnering, Progress Meetings 
38 
38 
$8,360 
Task 2: Community Construction Notices & Communications 
42 
28 
$7,840 
Task 3: Project Communications  
                (Hotline: 12 mos @ $300/mo) 
45 
 
24 
$7,800 
$3,600 
Sub Total 
125 
90 
$27,600 
Printing/Distribution Cost (2 mailings at approx. 1,300 pieces each) 
$5,850 
Translator Cost 
$650 
Grand Total 
$34,100 
EXHIBIT C

Mr. Brian Lizzet, Consultant Engineering, Inc. 
     
August 27, 2024  
Public Outreach Svcs – Chandler Heights Rd (Gilbert to Val Vista)  (ST1804.401 CHN0224D T020301C) 
This proposal assumes any displays, exhibits, engineering designs or details, required for public 
meetings or information will be provided by the owner, the design engineer, or the contractor. 
MakPro is not responsible for documenting existing property conditions, project signage, traffic 
signage, or direct door hanger notifications for residential service interruptions, such as water 
outages, or access restrictions as required for the contractor’s work.  Changes of substance to 
this proposal during the project may affect the final cost. 
Thank you for the opportunity to work with CEI and the City of Chandler on this project. 
Should you have questions or need additional information related to this proposal, please feel 
free to contact me at (480) 890-1927. 
Sincerely, 
Teresa Makinen 
EXHIBIT C

Quality Testing, LLC
175 S Hamilton Place, Bldg 6, #114
Gilbert, AZ 85233
(480) 496-2000 ▪ (480) 496-2001
www.qt-corp.com
SUB CONSULTANT :
PROJECT NAME :
PROJECT OWNER:
ESTIMATE NUMBER:
Project Description:
Cost Estimate Summary:
Total Extended QT Direct Billable Labor
(Includes QC Supervisor, QC Reporting Tech, Field Tech, Etc.)
Total Laboratory Testing Fees
(Includes All Laboratory Testing)
Total Other Direct Costs
(Includes Vehicle, Subcontracted Services, etc. if Applicable)
Total Estimate of All Fees
8/16/2024
Date
Estimate Amount Defined Scope: This cost proposal is considered an estimate, subject to the GENERAL 
INFORMATION/ASSUMPTIONS as defined herein. For the estimate amount, QT will perform construction materials sampling and 
testing, both field and lab, that is specifically identified in this cost estimate.
As a subconsultant to CEI, QT will be providing all acceptance testing for the Chandler Heights Road project between Gilbert Road 
and Val Vista Drive within the City of Chandler. QT's scope of services also includes all materials coordination for the project and 
any materials support necessary.
Estimator
Signature
The following pages identify the time frame, resourcing, and other assumptions used in developing this cost estimate. Assumptions 
are based on the information provided by your office, and QT's experience on similar projects, at the time of this proposal. If there 
are changes to the contractor's schedule, re-testing, additional site visits or other items that are not part of the originally assumed 
visits, these visits will be outside this scope of work. Items outside this scope of work will be extra work that will be billed to the 
contractor based on the units and rates established here within.
Jeffery M. Schaper, President
14,950.00
$
 
142,815.00
$
 
91,879.00
$
 
35,986.00
$
 
City of Chandler
240815-01
QT
ST1804.401 Chandler Heights Road; Gilbert Road to Val Vista Drive
EXHIBIT D

PROJECT NAME :
SCOPE OF SERVICES:
LABOR FEES
LABOR 
TYPE
REG
HOURS
REGULAR
RATE
ASS'D
% OT
OVERTIME
HOURS
OVERTIME
RATE(1)
EXTENDED
LABOR COST
Direct
6
250.00
$    
0%
0
250.00
$     
1,500.00
$
 
Direct
41
155.00
$    
0%
0
232.50
$     
6,355.00
$
 
Direct
74
116.00
$    
0%
0
174.00
$     
8,584.00
$
 
Direct
920
82.00
$      
0%
0
123.00
$     
75,440.00
$
 
Indirect
428
-
$          
0%
0
-
$           
-
$
 
SUBTOTAL DIRECT LABOR
91,879.00
$
 
VEHILE AND PER-DIEM CHARGES
NO.
UNITS
UNITS
UNIT
PRICE
EXTENDED VEHICLE
AND PER-DIEM
230
EA
65.00
$       
14,950.00
$
 
0
-
$           
-
$
 
SUBTOTAL VEHICLE AND PER-DIEM CHARGES
14,950.00
$
 
OTHER PROJECT DIRECT CHARGES
NO.
UNITS
UNITS
UNIT
PRICE
EXTENDED OTHER 
PROJECT CHARGES
-
$
 
-
$
 
-
$
 
-
$
 
SUBTOTAL OTHER PROJECT DIRECT CHARGES
-
$
 
LAB TESTING FEES
NO.
UNITS
UNITS
UNIT
PRICE
EXTENDED
LABORATORY FEES
180
EA
16.00
$       
2,880.00
$
 
24
EA
75.00
$       
1,800.00
$
 
24
EA
85.00
$       
2,040.00
$
 
18
EA
120.00
$     
2,160.00
$
 
4
EA
699.00
$     
2,796.00
$
 
30
EA
200.00
$     
6,000.00
$
 
30
EA
190.00
$     
5,700.00
$
 
30
EA
155.00
$     
4,650.00
$
 
30
EA
25.00
$       
750.00
$
 
2
EA
980.00
$     
1,960.00
$
 
2
EA
110.00
$     
220.00
$
 
2
EA
150.00
$     
300.00
$
 
2
EA
150.00
$     
300.00
$
 
2
EA
110.00
$     
220.00
$
 
2
EA
110.00
$     
220.00
$
 
0
EA
20.00
$       
-
$
 
6
EA
120.00
$     
720.00
$
 
1
10%
3,270.00
$  
3,270.00
$
 
TOTAL LABORATORY TESTING FEES
35,986.00
$
 
TOTAL ESTIMATE OF ALL FEES 
142,815.00
$         
Estimator
PROPOSAL SUMMARY 
ST1804.401 Chandler Heights Road; Gilbert Road to Val Vista Drive
Acceptance Testing
Date
Jeffery M. Schaper, President
August 16, 2024
DESCRIPTION
Trip Charge
DESCRIPTION
505 - AC Content w/ Gradation (Ignition Method)
510 - AC Gyratory Bulk Density (Set of 2)
509 - AC Maximum Specific Gravity (Rice) (Set of 3)
501 - AC Core Density/Thickness
DESCRIPTION
416 - Sieve Analysis
301 - Plasticity Index
301 - Standard Proctor
504 - Ignition Furnace Calibration
301 - Concrete Compressive Strength Cylinders
601 - AC Binder PG Verification
658 - Cone Penetration
617 - Kinematic Viscosity
501 - Concrete Core Thickness
820 - Tensile Strength
Unplanned Lab Testing Quantity Factor
623 - Pentration
653 - Resilience
625 - Softening Point
(1) Regular Rate X Overtime Premium of 1.5
CLASSIFICATION
Registered Engineer
Materials Project Manager
Materials Data Coordinator
Materials Field Technician
Lab Trechnician
COST PROPOSAL,  8/16/2024
EXHIBIT D

PROJECT NAME :
DATE:
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
J-25
F-25
M-25
A-25
M-25
J-25
J-25
A-25
S-25
O-25
N-25
D-25
J-26
F-26
M-26
A-26
M-26
J-26
J-26
A-26
S-26
O-26
N-26
D-26
21
19
21
22
21
21
22
21
21
23
18
22
20
19
22
22
20
22
22
21
21
22
19
22
0.01
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.01
0.01
0.01
0%
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0%
0.04
0.04
0.04
0.04
0.04
0.04
0.04
0.04
0.04
0.04
0.04
0.04
0%
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0%
0.20
0.20
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.20
0.20
0%
0.07
0.06
0.06
0.06
0.06
0.06
0.06
0.06
0.07
0.07
0.07
0.06
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0%
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0%
0.20
0.20
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.20
0.20
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0%
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0%
0.77
0.76
0.81
0.81
0.81
0.81
0.81
0.81
0.82
0.77
0.77
0.06
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0%
5
4
4
4
4
4
4
4
5
5
5
2
0
0
0
0
0
0
0
0
0
0
0
0
1
1
1
1
1
1
1
1
1
1
1
0
0
0
0
0
0
0
0
0
0
0
0
0
ESTIMATED FTEs IN THE MONTH
TOTAL VEHICLES
121 m-h
 m-h
428 m-h
TOTAL ACTUAL POSITIONS
50
ABOVE PERIOD - MONTHLY FULL TIME EQUIV. (FTEs)
TOTAL FTEs (SUBCONTRACTED LABOR)
920 m-h
1469 m-h
Materials Project Manager
Materials Data Coordinator
Materials Field Technician
Lab Trechnician
74 m-h
428 m-h
m-h
74 m-h
920 m-h
428 m-h
August 16, 2024
PROJECT PERSONNEL /
 SUB CONSULTANT MAN-HOURS
6 m-h
Registered Engineer
41 m-h
m-h
m-h
6 m-h
41 m-h
JAN 2025 through DEC 2026
CONSULTANT :
SUBTOTAL
REGULAR
HOURS
%
OT
SUBTOTAL
O/T
TOTAL
ST1804.401 Chandler Heights Road; Gilbert Road to Val Vista Drive
QT
SCHEDULED PROJECTED MAN-HOURS 
TOTAL FTEs (DIRECT LABOR & VEHICLE)
TOTAL FTEs (ALL LABOR CLASSES)
TOTAL FTEs (INDIRECT LABOR ONLY)
TOTAL FTEs (DIRECT LABOR ONLY)
1469 m-h
428 m-h
920 m-h
121 m-h
 m-h
 m-h
 m-h
920 m-h
 m-h
 m-h
 m-h
 m-h
 m-h
11
SCHEDULED PROJECT MAN-HOURS,  8/16/2024
EXHIBIT D

111 SOUTH WEBER DRIVE, SUITE 1                   
    WWW.ATEKEC.COM 
 
 
 
P (480) 659-8065  
CHANDLER, AZ 85226 
 
 
 
 
 
 
 
 
F (480) 656-9658 
 
 
 
August 27, 2024 
Proposal No.:  240287 
 
Mr. Brian Lizzet, PE, CCM | Sr. Resident Engineer 
Consultant Engineering, Inc.  
135 E. Chilton, Suite 101 
Chandler, AZ 85225 
 
 
SUBJECT: 
Proposal for Independent Assurance Testing  
 
Chandler Heights Road Improvements Gilbert Road to Val Vista Drive 
 
COC Project No.: ST1804-451 
 
Federal Aid No.: CHN0244D 
 
ADOT No.: T020301C 
 
Chandler, Arizona 
 
Dear Mr. Lizzet: 
 
ATEK Engineering Consultants, LLC (ATEK) is pleased to present this proposal.  This proposal 
was developed after review of Consultant Engineer, Inc., Project Number 24101.00, Materials 
Sample Checklist, dated August 22, 2024 and is a preliminary understanding of the required 
Independent Assurance Testing Services for the subject project. 
 
ATEK is committed to providing a high level of service to its clients, commensurate with their 
wants and needs. If a portion of this proposal does not meet your needs, or if those needs have 
changed, ATEK will consider appropriate modifications, subject to the standards of care to which 
we adhere as professionals.  We look forward to the opportunity to provide professional services 
to this project. 
 
PROJECT UNDERSTANDING 
 
The proposed project consists of roadway improvements for Chandler Heights Road from 
Gilbert Road to Val Vista Drive in Chandler, Arizona 
 
 
We have based our proposal on the following information: 
• 
Review of Consultant Engineer, Inc., Project Number 24101.00, Materials Sample 
Checklist, dated August 22, 2024. 
• 
No project schedule was reviewed for this proposal 
 
Our scope of services for the referenced project includes the following: 
 
Soil and Aggregate Testing 
 
The testing services will include appropriate laboratory evaluation of soils and aggregates used 
on the project site.  
 
Asphalt Concrete Services 
 
ATEK will provide an Engineering Technician to sample asphalt paving for laboratory testing.   
EXHIBIT E

Chandler Heights Road –Gilbert Road to Val Vista Drive  
 
 
        August 27, 2024 
 
Proposal 240287 
 
 
 
 
 
    Page 2 of 6 
 
 
                
Project Management/Coordination Services 
 
ATEK’s Project Manager will conduct periodic site visits for consultation with onsite personnel and 
review ATEK’s project documentation and laboratory testing results during construction.  If 
requested, the Project Manager will prepare a summary presentation of the results of our 
laboratory tests. 
 
ATEK will also provide the following administrative services: 
 
• 
Dispatching and scheduling of field personnel; 
• 
Word processing by administrative staff; and 
• 
Reproduction and distribution of reports. 
 
ESTIMATED PROJECT FEES 
The above-mentioned services will be performed on an hourly and unit rate basis from portal to 
portal.  The attached costs are estimates only and are based on time schedules, our experience 
with similar projects, and other information provided to us regarding this project.  ATEK has no 
control over the project submittal process and schedule, project construction schedule and/or 
materials and methods which can affect the total cost of the services provided.  The actual cost 
will depend on the amount of work requested, the contractor’s schedule, delays due to weather, 
etc.  This estimate is based on a normal 40-hour workweek.  If this information or time schedule 
should change, please contact us immediately so we may adjust our fee accordingly.   
 
A detailed cost estimate is included as an attachment at the end of this proposal. 
 
 
 
 
 
SAFETY 
The safety of our employees is of paramount concern to ATEK.  You will be notified if project 
conditions represent a potential safety concern to our employees.  Unsafe conditions for fieldwork 
will require a modification of our estimated scope of work and associated fees.  If necessary, we 
will advise you of any additional costs required to mitigate these unanticipated conditions.  Job 
site safety will be the sole responsibility of the contractor. 
 
SCHEDULE 
We request that our dispatch office be contacted at least 48 hours in advance of any necessary 
tests and observations.  We will perform this work at the rates presented.  If additional services 
are requested which were not presented, they will be charged at our current fee schedule rate. 
 
ATEK personnel will not direct, lay out, or supervise the construction operations for the project, 
nor will we alter or change the project plans, specifications or reports.  In addition, an onsite pre-
construction meeting with all involved parties is also requested. 
 
AUTHORIZATION 
The work will be conducted in accordance with the attached General Conditions.  Your signature 
on this proposal may indicate your acceptance of these Conditions and authorization for ATEK to 
proceed with the Scope of Work outlined herein.  If this proposal is acceptable, we can begin work 
as soon as we receive an ORIGINAL signature in the “acceptance” field. 
 
If there is a need for any change in the scope of services or schedule described in the proposal, 
please call us immediately.  Changes may require revision of the proposed fee, which will be 
communicated to you upon assessment of the requested changes effect on the fee. 
EXHIBIT E

Chandler Heights Road –Gilbert Road to Val Vista Drive  
 
 
        August 27, 2024 
 
Proposal 240287 
 
 
 
 
 
    Page 3 of 6 
 
 
                
 
 
LIMITATIONS 
Construction testing and special inspection observation are techniques employed to reduce the 
risk of problems arising during construction.  Provision of these services by ATEK is not insurance, 
nor does it constitute a warranty or guarantee of any type.  Even with diligent construction testing 
and special inspection observation, some latent construction defects may be missed.  In all cases, 
contractors shall retain responsibility for the quality of their work, for adhering to plans and 
specifications, and for repairing defects regardless of when they are found.  In the absence of 
continuous observations by ATEK personnel during site earthwork, we are not able to express an 
opinion regarding the adequacy of site preparation or overall fill composition or compaction. 
 
ATEK will perform its services in a manner consistent with the standards of care and 
skill ordinarily exercised by members of the profession practicing under similar 
conditions in the geographic vicinity and at the time the services will be performed.  
No warranty or guarantee, express or implied, is provided as part of the services offered 
by this proposal.  This proposal neither makes nor intends a warrantee or guarantee, 
express or implied, nor does it create a fiduciary responsibility to Client by Consultant. 
 
TERMS AND CONDITIONS 
All terms and conditions indicated in this proposal and in the attached General 
Conditions will be considered by both parties to be in effect from the effective date of 
the signed proposal through completion of the project.  The proposal will remain in 
effect for 30 days from its date, and thereafter shall be null and void unless it has been 
signed for the work proposed. 
 
We sincerely appreciate the opportunity to be of service and look forward to working 
with you on this project. 
 
Sincerely, 
 
ATEK Engineering Consultants, LLC. 
 
 
 
 
 
 
Armando Ortega, PE 
 
 
Principal 
 
 
 
 
 
 
 
 
 
 
EXHIBIT E

Chandler Heights Road –Gilbert Road to Val Vista Drive  
 
 
        August 27, 2024 
 
Proposal 240287 
 
 
 
 
 
    Page 4 of 6 
 
 
                
Enclosure: General Conditions 2024 
 
Client agrees to the Scope of Work described in this Proposal and Cost Estimate and the 
General Conditions attached and incorporated herein. 
 
 
By: 
__________________________ 
          Consultant Engineering, Inc.  
 
Title: __________________________ 
 
Date: __________________________ 
 
 
 
 
EXHIBIT E

Chandler Heights Road –Gilbert Road to Val Vista Drive  
 
 
 
    August 27, 2024 
 
Proposal 240287 
 
 
 
 
 
    Page 5 of 5 
 
 
 
ATEK GENERAL CONDITIONS 2024 (PROFESSIONAL SERVICES) 
 
This PROFESSIONAL SERVICES AGREEMENT is made by and between Consultant Engineering, Inc. hereinafter referred to as CLIENT, and ATEK Engineering Consultants, LLC, 
hereinafter called ATEK. 
 
The PROFESSIONAL SERVICES AGREEMENT between the parties consists of these terms and conditions, the attached PROPOSAL identified as ATEK Proposal No. 240287, dated  
8/27/2024, and any exhibits or attachments noted in the PROPOSAL. Together, these elements will constitute the entire AGREEMENT superseding any and all prior negotiations, 
correspondence, or agreements either written or oral.  Any changes to this PROFESSIONAL SERVICES AGREEMENT must be mutually agreed to in writing. 
 
SECTION 1 - SCOPE OF WORK 
ATEK shall perform pursuant to the terms and conditions of this PROFESSIONAL SERVICES AGREEMENT the services as set forth in the accompanying PROPOSAL. 
SECTION 2 - PERMITS & UTILITIES 
1. Unless otherwise stated in the PROPOSAL, CLIENT shall apply for and obtain all required permits and licenses.  CLIENT shall make all necessary arrangements for right of entry 
to provide ATEK access to the site for all equipment and personnel at no charge to ATEK.  
2. 
While ATEK will take all reasonable precautions to minimize any damage to the property, CLIENT agrees to hold ATEK harmless for any damages to structures or any damage 
required for right of entry, in the absence of willful and gross misconduct by ATEK. 
SECTION 3 - SAMPLES 
Samples collected during this study will be retained for approximately 30 days after the report is submitted and then disposed. 
SECTION 4 - INVOICES 
ATEK will submit an invoice to CLIENT each month.  Payment is due upon presentation of invoice and is past due thirty (30) days from invoice date. 
SECTION 5 - OWNERSHIP OF DOCUMENTS 
 1. 
All reports, field data, field notes, calculations, estimates and other documents prepared by ATEK, as instruments of service, shall remain the property of ATEK. 
 2. 
CLIENT agrees that all reports and other work furnished to CLIENT or his agents, which are not paid for, will be returned upon demand and will not be used by CLIENT for any 
purpose whatsoever. 
 3. 
ATEK will retain all pertinent records relating to the services performed for a period of five years following submission of the report, during which period the records will be 
made available to CLIENT at reasonable times. 
SECTION 6 - DISPUTES 
In an effort to resolve any conflicts that arise during the design or construction of the Project or following the completion of the Project, the CLIENT and ATEK agree that all disputes 
arising between them out of or relating to this Agreement or the Project shall be submitted to non-bonding mediation unless the parties mutually agree otherwise. 
SECTION 7 - STANDARD OF CARE & NOTIFICATION 
 1. 
Services performed by ATEK under this PROFESSIONAL SERVICES AGREEMENT will be conducted in a manner consistent with that level of care and skill ordinarily 
exercised by members of the profession currently practicing under similar conditions.  No warranty express or implied is made. 
 2. 
ATEK agrees to notify CLIENT when unanticipated hazardous materials or suspected hazardous materials are encountered.  CLIENT agrees to make any disclosures required 
by law to the appropriate governing agencies. 
 3. 
ATEK will be responsible for data, interpretations, and recommendations, but shall not be responsible for the interpretation by others of the information developed. 
SECTION 8 - LIMITATION OF LIABILITY 
1. 
CLIENT agrees to limit ATEK’s liability to CLIENT and all third parties arising from ATEK’s negligent acts, errors or omissions, such that the total aggregate liability of ATEK to all 
those named shall not exceed our fees for the project or $50,000, whichever is greater.  Neither CLIENT nor any third parties assume any liability for damages to others, which 
may arise solely on account of ATEK's negligent acts, errors or omissions. 
2. 
As part of the consideration ATEK requires for provision of the Services indicated herein, CLIENT agrees that any claim for damages filed against ATEK by CLIENT or any 
contractor or subcontractor hired directly or indirectly by CLIENT will be filed solely against ATEK or its successors or assigns and that no individual person shall be made 
personally liable or liable for damages, in whole or in part. 
SECTION 9 - INSURANCE 
ATEK represents and warrants that it and its agents, staff and consultants employed by it are protected by worker's compensation insurance and that ATEK has such coverage under 
public liability and property damage insurance policies which ATEK deems to be adequate.  Certificates for all such policies of insurance will be provided to CLIENT, if requested.  
Within the limits and conditions of such insurance, ATEK agrees to indemnify and hold CLIENT harmless from and against any loss, damage, or liability arising from any negligent acts 
by ATEK, it agents, staff, and consultants employed by it.  ATEK shall not be responsible for any loss, damage or liability arising from any acts by CLIENT, its agents, staff, and other 
consultants employed by it. 
SECTION 10 - TERMINATION 
1. 
This CONSULTING SERVICES AGREEMENT may be terminated by either party upon seven (7) days’ written notice in the event of substantial failure by the other party to 
perform in accordance with the terms hereof, or in the event of the parties' failure to agree upon an adjustment to this PROFESSIONAL SERVICES AGREEMENT in accordance 
with Section 6.  Such termination shall not be effective if that substantial failure has been remedied before expiration of the period specified in the written notice.  In the event of 
termination, ATEK shall be paid for services performed to the termination notice date plus reasonable termination expenses. 
 2. 
In the event of termination or suspension for more than three (3) months prior to completion of all reports contemplated by this PROFESSIONAL SERVICES AGREEMENT, 
ATEK may complete such analyses and records as are necessary to complete ATEK's Project files and may also complete a report on the services performed to the date of 
notice of termination or suspension.  The expenses of termination or suspension shall include all direct costs of ATEK in completing such analyses, records and reports. 
SECTION 11 - ENTIRE AGREEMENT 
 
1. 
This PROFESSIONAL SERVICES AGREEMENT along with the exhibits and/or proposals appended hereto constitute the entire PROFESSIONAL SERVICES AGREEMENT of 
the parties with respect to the subject matter hereof. 
2. 
The Parties have read the foregoing, understand completely the terms and conditions, and willingly enter into this PROFESSIONAL SERVICES AGREEMENT which will become 
effective on the date signed by the CLIENT in the “acceptance” field in the proposal.
EXHIBIT E

ATEK Proposal No.: 240287
Service
Fee
40
hours @
$78.00 /hour
$3,120.00
7
tests @
$104.00 /test
$728.00
2
tests @
$87.00 /test
$174.00
3
tests @
$132.00 /test
$396.00
3
tests @
$125.00 /test
$375.00
210
miles @
$0.67 /mile
$140.70
$4,933.70
20
hours @
$78.00 /hour
$1,560.00
2
tests @
$175.00 /test
$350.00
0
tests @
$170.00 /test
$0.00
2
tests @
$190.00 /test
$380.00
2
tests @
$565.00 /test
$1,130.00
160
miles @
$0.67 /mile
$107.20
$3,527.20
$8,460.90
10
hours @
$95.00 /hour
$950.00
8
hours @
$50.00 /hour
$400.00
2
hours @
$110.00 /hour
$220.00
60
miles @
$0.67 /mile
$40.20
$1,610.20
$10,071.10
Vehicle Mileage
Ignition Oven Calibration Facor
Soil and Aggregate Testing Services
Sieve Analysis
Atterberg Limits (PI) (Dry)
Atterberg Limits (PI) (Wet)
Project Technician
Vehicle Mileage
Subtotal
Project Total Estimate
Project Management/Coordination Services
Project Manager
Project Coordinator
Project Engineer
Project Management & Coordination Services 
Vehicle Mileage
Fee Estimate for Chandler Heights Rd : Gilbert Rd to Val Vista Dr
Max.Theoretical Specific Gravity (Rice)
Asphalt Services
Project Technician
Subtotal
Unit
Rate
Estimated
Units
Professional
Services
Estimate for Site Work Services
Gyratory Bulk Density (Specific Gravity)
Ignition & Gradation of Bituminous 
Subtotal
Fractured Coarse Aggregate Particles
111 SOUTH WEBER DRIVE, SUITE 1
CHANDLER, AZ 85226
WWW.ATEKEC.COM
P (480) 659-8065
F (480) 656-9658
EXHIBIT E

Corporate Office 
Chandler Office  
Tucson Office 
10625 N. 25th Avenue 
135 E. Chilton Drive 
3161 E. 47th Street 
Suite 103 
Suite 201     
Tucson, AZ  85713 
Phoenix, AZ 85029 
Chandler, AZ 85225 
Mailing Address:  PO Box 35278, Phoenix, AZ 85069-5278 
Tel: (602) 288-5594   Fax: (602) 288-5592
September 10, 2024 
Brian Lizzet, P.E., CCM 
Consultant Engineering Inc. 
135 E. Chilton Drive, Suite 101 
Chandler, AZ 85225 
Re:   
Chandler Heights Road (Gilbert Road to Val Vista Drive) 
Project No.: ST1804-451; Federal Project No.: CHN-0(244)D; ADOT No.: T020301C 
Construction Inspection Services Cost Proposal (revised) 
Mr. Lizzet, 
Thank you for comments related to our cost proposal.  Below represents a 37% decrease to our 
original cost proposal, with the assumption that the contractor’s schedule to perform original 
contract work is expected to conclude earlier than expected. 
Tristar’s Inspection Services scope for this project is limited to field electrical inspection during 
the installation of the new roadway lighting system, ITS conduit and component installation, 
minor signal other related dry utility work within the project limits including:  
Task 1.1: Pre-Construction Assistance:  Tristar’s inspector will prepare for, assist and support 
CEI in preparation for the meeting and will attend the pre-construction meeting. 
Task 4.1: Inspection Services:  Assuming the signal and ITS work will be scheduled by the 
contractor in a reasonably sequential and continuous manner over a period of 4 months, 
Tristar’s Electrical Inspector will daily document the contractor’s work and progress on 
Chandler approved forms and provide an accurate accounting of the accepted work, for each 
item for payment and to support CEI in assembling the final Record Drawings.  
Insp. Hrs 
Activity 
($120 /hr) 
Total 
Task 1.1: Pre-Construction Assistance 
8
$960.00 
Task 4.1: Inspection Services 
704
$84,480.00 
Total: 
$85,440.00 
Tristar’s billing rate includes all direct and indirect expenses to perform field inspection on the 
project, which include providing Tristar’s inspector with a company-owned vehicle; field 
computer and mobile internet access to maintain communication and provide support to CEI; 
EXHIBIT F

ST1804-451  CHN-0(244)D  T020301C 
 
Page 2 
 
 
common construction safety personal protective equipment; and non-specialty inspection tools 
to perform measurement of quantities at the project site.  Excluded from this estimate are any 
rental or purchase of specialty electronic measuring devices or other unusual out-of-pocket 
expenses, which will be accounted for by CEI as the Prime Consultant. 
 
Thank you again for including Tristar on your Team.  I look forward to your favorable review 
and hopeful we can work together on this project.  Should you have questions or need 
additional information, feel free to contact me at 602-568-4661. 
 
Sincerely, 
 
 
 
John Akin, PE 
Principal 
EXHIBIT F

Project Name: Chandler Heights - Gilbert Road to Val Vista Drive 
Page F-1 
Project No.: ST1804.451; Federal No. CHN-0(244)D; ADOT No. T0203 01C  
Rev. 1/24/2024 
 
 
 
EXHIBIT “F” 
FEDERAL REQUIREMENTS

FEDERAL REQUIREMENTS 
AND 
DOCUMENTS 
FOR 
PROFESSIONAL SERVICES  
CONTRACT 
With DBE Goal  – DBE Race Conscious 
This is a federal funded contract with Federal Highway Administration (FHWA) 
and must comply with all related federal requirements.

FEDERAL DOCUMENTS  
TABLE OF CONTENTS

TABLE OF CONTENTS 
(for Professional Services Contract with DBE Goal -DBE Race Conscious) 
 
 
1.0  
Requirements of ADOT for the Consultant SOQ Submittal 
2.0 
City SOQ Proposal Certifications Form 
3.0 
Lobby Certification 
4.0 
Federal Requirements Acknowledgement 
5.0 
Verifications Statement 
6.0 
Forced Labor of Ethnic Uyghurs Ban Certification Form 
7.0 
Prompt Pay Provisions 
8.0 
Title VI Assurance, Appendix A and E 
9.0 
Records Retention 
10.0 
Federal Immigration and Nationality Act 
11.0 
Buy America / Build America-Buy America 
12.0 
DBE EPrise 
13.0 
DBE Documents 
 
13.1  
DBE Documents Instructions / Guide 
 
13.2 
ADOT On-Line Bidders-Proposers Lit (see Instructions) 
 
13.3  
DBE Form 3212PS 
 
13.4  
DBE Form 3206PS Consultant/Prime 
 
13.5  
DBE Form 3205PS Subconsultant  
 
13.6  
DBE Form 3203PS Good Faith 
 
13.7  
DBE Form 3210PS Final Payment 
 
13.8  
DBE Form 3108C Substitution or Termination 
14.0 
Payment Requests 
 
14.1 
Pay Application Request Form 
 
14.2 
Subconsultant Summary Form 
15.0 
Subconsultant / Subcontract Requirements

1.0 
REQUIREMENTS OF THE CONSULTANT 
FOR SOQ SUBMITTAL

2024-06-24 
 
Consultant Requirements for SOQ Submittal-Pg 1 of 2 
1.0 
CONSULTANT REQUIREMENTS  
FOR SOQ SUBMITTAL 
                       
 
This contract is a federal funded contract with Federal Highway Administration (FHWA) and must comply 
with all related federal requirements. 
 
1.1 
REQUIRED LICENSURE AND REGISTRATION 
SOQs will be accepted from any prime Consultant prequalified through the Arizona Department of 
Transportation (ADOT) Engineering Consultants Section (ECS) and properly registered with the Arizona 
Board of Technical Registration (BTR) at the time the SOQ is submitted to the City. This contract does 
require a Principal or Officer of the Firm responsible for this contract that is properly registered with the 
BTR at the time of SOQ submittal. It is the prime Consultant’s responsibility to verify that all 
Subconsultants, in the SOQ submittal, have the proper Arizona licenses and registrations, and DBE 
certification if applicable, for the services to be performed under this contract. 
 
1.2  
PRE-QUALIFICATION 
In order to submit an SOQ, the prime Consultant must have on file with ADOT ECS a current 
Prequalification Application/Statement. Subconsultants are not required by ADOT ECS or the City to be 
prequalified, but are encouraged to do so. ADOT ECS currently prequalifies firms on a bi-annual basis. 
Further information regarding the prequalification process can be found at the following ADOT ECS 
website:  
 
https://www.azdot.gov/business/engineering-consultants/consultant-prequalification 
 
Obtaining prequalification does not mean the firm is under contract or entitled to receive a contract. 
Obtaining prequalification means the firm has met minimum requirements to submit qualifications to be 
considered/evaluated for this project. 
 
The City will review prequalification status with ADOT ECS at the time of SOQ due date. If the firm is not 
prequalified on the SOQ submittal date, the SOQ will be rejected. 
 
1.3  
AUDIT & ANALYSIS REQUIREMENTS 
Within two (2) weeks after receiving notice of selection, the selected prime Consultant(s) and its 
Subconsultant(s) must submit financial documentation to ADOT Office of Audit & Analysis (A&A). If the 
selected prime Consultant(s) and its Subconsultant(s) have recently submitted their most current 
financial documents to ADOT A&A, contact ADOT A&A at (602) 712-7042 to inquire if you need to 
resubmit financial documents. Additionally, the selected prime Consultant(s) and its Subconsultant(s) 
are required to comply with ADOT Consultant Audit Guidelines. 
 
https://azdot.gov/about/audit-and-analysis 
 
Prime Consultants and its Subconsultants that propose on an overhead basis must have their Schedule 
of Indirect Costs and Financial Statements available for review by ADOT A&A within six (6) months of 
the completion of the Consultant’s preceding fiscal year-end (FYE). For example, a Consultant 
with December 31, 2013, FYE must have the required information available no later than June 30, 
2014. Noncompliance with this requirement will be considered failed negotiations unless 
waived in writing by the State. 
 
The items outlined above represent the information needed to begin the audit review process. Additional 
information and supporting documentation may be requested. Failure to comply with audit requirements 
within the established timeframes may be considered failed negotiations. Questions regarding ADOT’s 
audit requirements or related information must be directed to ADOT A&A at (602) 712-7042. 
 
The Consultant understands that a compliant accounting system is required in accordance with 
Generally Accepted Accounting Principles (GAAP), Federal Acquisition Regulation (FAR) of Title 48, 
Code of Federal Regulations (CFR)-Part 31, applicable Cost Accounting Standards (CAS), and ADOT 
Advance Agreement Guideline.

2024-06-24 
 
Consultant Requirements for SOQ Submittal-Pg 2 of 2 
 
1.4  
STATE OF ARIZONA LOCAL OFFICE REQUIREMENTS 
All selected prime Consultant(s) must establish a local office in the State of Arizona prior to the contract 
Notice to Proceed (NTP) date if a local office does not already exist. 
 
1.5 
NOT ALLOWED IN SOQ SUBITTAL 
Inclusion of cost, work-hour, and plan-sheet estimates are not allowed in the SOQ. 
 
1.6 
BIDDERS-PROPOSERS LIST EMAIL VERIFICATION   
See the DBE Documents section for instructions. This email verification document must be submitted 
with SOQ and is not included in the limited page count submittal requirements. 
 
  
 
 
 
After contract award, a firm may request a debriefing with the City’s Project Manager.

2.0 
SOQ PROPOSAL CERTIFICATION FORM

3.0 
 
LOBBY CERTIFICATION FORM

4.0 
 
VERIFICATIONS STATEMENT

5.0 
PROMPT PAY PROVISION

Prompt Pay and Payment Reporting Provisions- 1/5 
 
CONSTRUCTION AND PROFESSIONAL SERVICES/DESIGN CONTRACTS 
PROMPT PAY AND PAYMENT REPORTING PROVISIONS 
 
**  FOR USE ON LPA FEDERAL AID PROJECTS  ** 
 
(07/24/2023) 
 
MEASUREMENTS AND PAYMENT: 
 
(A) Partial Payments:  
 
If satisfactory progress is being made, the contractor shall receive a payment based on the 
amount of work completed. Progress payments may be made by the LPA/Subrecipient 
Procurement Office to the contractor on the basis of an approved estimate of the work 
performed during a preceding period of time. The progress payments will be paid on or 
before 14 days after the estimate of the work is approved. The estimate of the work will be 
deemed received by the LPA/Subrecipient Procurement Office on submission to the person 
designated by the LPA/Subrecipient Procurement Office for the submission, review or 
approval of the estimate of the work. The LPA/Subrecipient Procurement Office by mutual 
agreement may make progress payments on contracts of less than 90 days and will make 
monthly progress payments on all other contracts. Payment to the contractor on the basis of 
a duly certified and approved estimate of the work performed during the preceding calendar 
month under the contract may include payment for material and equipment. 
 
An estimate of the work submitted will be deemed approved and certified for payment after 
seven days from the date of submission unless before that time the LPA/Subrecipient 
Procurement Office or Designee prepares and issues a specific written finding setting forth 
those items in detail in the estimate of the work that are not approved for payment under the 
contract. The contractor shall work with the LPA/Subrecipient or the LPA/Subrecipient 
Designee to finalize monthly estimate. The progress payments will be paid on or before 14 
days after the estimate of the work is certified and approved in accordance with Arizona 
Revised Statutes Section 34-221. 
 
The contractor shall pay to the contractor's subcontractors or material suppliers and each 
subcontractor shall pay to the subcontractor's subcontractor or material supplier, within 
seven days of receipt of each progress payment the respective amounts allowed the 
contractor or subcontractor on account of the work performed by the subcontractors, to the 
extent of each subcontractor's interest.  
 
No contract for construction services may materially alter the rights of any contractor, 
subcontractor, or material supplier to receive prompt and timely payment. 
 
A subcontractor may notify the LPA/Subrecipient Procurement Office in writing requesting 
that the subcontractor be notified by the Subrecipient Procurement Office in writing within 
five days from payment of each progress payment made to the contractor.

Prompt Pay and Payment Reporting Provisions- 2/5 
(B) No Retainage on Progress Payments: 
 
(1) This is a federally-funded project. Therefore, notwithstanding A.R.S. § 34-221, 
the LPA/Subrecipient Procurement Office will not withhold retainage from 
progress payments. Neither the contractor, nor the subcontractor of any tier, 
may withhold any retainage on progress payments to subcontractors or 
suppliers of any tier.  
 
(2) This provision does not prevent the LPA/Subrecipient Procurement Office from 
withholding retainage or reducing payments where otherwise provided in the 
contract. These cases may include, but are not limited to:  
 
(a) Delayed work;  
(b) Work that is not satisfactorily performed; or   
(c) 
A failure to submit necessary reports, certifications, or documents to 
the LPA/Subrecipient Procurement Office. 
 
(C) Subcontractor Payments:  
 
 
 
(1) 
No Retainage: 
 
(a) This is a federally-funded project. Therefore, notwithstanding A.R.S. § 
34-221, neither the contractor, nor the subcontractor of any tier, may 
withhold any retainage on progress payments to subcontractors or 
suppliers of any tier.  
 
(b) Pursuant to Subsection (B)(2) of this Specification, the contract does 
not prevent the LPA/Subrecipient Procurement Office from withholding 
retainage or reducing payments where otherwise provided in the 
contract. These cases may include, but are not limited to:  
 
(i) 
Delayed work;  
(ii) 
Work that is not satisfactorily performed; or  
(iii) 
A failure to submit necessary reports, certifications, 
or 
documents 
to 
the 
LPA/Subrecipient 
Procurement Office.  
 
(c) When the LPA/Subrecipient Procurement Office withholds retainage or 
reduces payments under Subsection (B)(2) of this Specification, the 
contractor may withhold retainage on progress payments to 
subcontractors or suppliers of any tier. However, the contractor may 
only withhold a reasonable amount of retainage.  
 
(d) For the purpose of this section, a “reasonable amount” of retainage is 
based on the subcontractor’s involvement or the supplier’s involvement 
in the cause for the LPA/Subrecipient Procurement Office’s reduction 
of payment. The final amount retained from all subcontractors and 
suppliers shall not be higher than the amount retained by the 
LPA/Subrecipient. However, tier subcontracts shall include provisions 
that comply with this section.

Prompt Pay and Payment Reporting Provisions- 3/5 
 
 
 
(2) 
No Set-offs Arising from Other Contracts: 
 
If a subcontractor is performing work on multiple contracts for the same contractor or 
subcontractor of any tier, the contractor or subcontractor of any tier shall not withhold or 
reduce payment from its subcontractors on the contract because of disputes or claims on 
another contract. 
 
 
 
(3) 
Partial Payment: 
 
The contractor and each subcontractor of any tier shall make prompt partial payments to its 
subcontractors within seven days of receipt of payment from the LPA/Subrecipient 
Procurement Office. Notwithstanding any provision of Arizona Revised Statutes Section 34-
221, the parties may not agree otherwise.  
 
 
 
 
(4) 
Final Payment: 
 
The contractor and each subcontractor of any tier shall make prompt final payment to each 
of its subcontractors.  The contractor and each subcontractor of any tier shall pay all 
monies, including retention, due to its subcontractor within seven days of receipt of 
payment. Notwithstanding any provision of Arizona Revised Statutes Section 34-221, the 
parties may not agree otherwise. 
 
 
 
(5)  Payment Reporting:  
 
For the purposes of this subsection “Reportable Contracts” means any subcontract, of any 
tier, DBE or non-DBE, by which work shall be performed on behalf of the contractor and any 
contract of any tier with a DBE material supplier. 
 
The requirements of this subsection apply to all Reportable Contracts. 
 
Payment Reporting for all Reportable Contracts shall be done through the LPA DBE System 
which can be accessed at AZ UTRACS on the Arizona Transportation Business Portal at 
www.azutracs.com. No later than fifteen calendar days after the preconstruction conference, 
the contractor shall log into the system and enter or verify the name, contact information, 
and subcontract amounts for Reportable Contracts on the project. As Reportable Contracts 
are approved over the course of the contract, the contractor shall enter the subcontractor 
information in the LPA DBE System. Reportable contracts information shall be entered into 
the system no later than five calendar days after approval by the LPA/Subrecipient 
Procurement Office. 
 
The contractor shall report on a monthly basis indicating the amounts actually paid and the 
dates of each payment under any Reportable Contract on the project. The contractor shall 
provide information for payments made on all Reportable Contracts during the previous 
month by the last day of the current month. In the event that no payments were made during 
a given month, the contractor shall identify that by entering a dollar value of zero. If the 
contractor does not pay the full amount of any invoice from a subcontractor, the contractor 
shall note that and provide the reasons in the comment section of the Monthly Payment 
Audit of the LPA DBE System.

Prompt Pay and Payment Reporting Provisions- 4/5 
 
In addition, the contractor shall require that all participants in any Reportable Contract 
electronically verify receipt of payment on the contract within 15 days of receipt of electronic 
payment notification and the contractor shall actively monitor the system to ensure that the 
verifications are input. The contractor shall proactively work to resolve any payment 
discrepancies in the system between payment amounts it reports and payment confirmation 
amounts reported by others. 
 
The contractor shall ensure that all Reportable Contract payment activity is in the LPA DBE 
System. This includes all lower-tier Reportable Contracts. 
 
The contractor shall maintain records for each payment explaining the amount requested by 
the subcontractor, and the amount actually paid pursuant to the request, which may include 
but are not limited to, estimates, invoices, pay requests, copies of checks or wire transfers, 
and lien waivers in support of the monthly payments in the system. 
 
The contractor shall ensure that a copy of this Subsection is included in every Reportable 
Contract of every tier. 
 
 
 
 
(a) Sanctions for Inadequate Reporting:  
 
For each month that the contractor fails to submit timely and complete payment information 
the LPA/Subrecipient Procurement Office will retain $5,000 as sanctions from the monies 
due to the contractor. After 90 consecutive days of non-reporting, the sanctions will increase 
to $10,000 for each subsequent month which the contractor fails to report until the 
information is provided. These sanctions will be in addition to all other retention or liquidated 
damages provided for elsewhere in the contract. 
 
 
 
(6)  
Completion of Work: 
 
A subcontractor's work is satisfactorily completed when all the tasks called for in the 
subcontract have been accomplished, documented, and accepted by the LPA/Subrecipient 
Procurement Office.  
 
 
 
 
(7)  
Disputes:   
 
If there is a discrepancy between what is reported by the contractor in the LPA DBE System 
and what the subcontractor indicates, an alert email will automatically be sent to the 
contractor. The email will be sent to the email address provided by the contractor in the 
LPA DBE System. It is the contractor’s responsibility to ensure that the email address in 
the system is kept current. 
 
The contractor shall provide a verifiable explanation of the discrepancy in the LPA DBE 
System as early as practicable but in no case later than seven days after the date of the 
alert email. 
 
The LPA/Subrecipient will determine whether the contractor has acted in good faith 
concerning any such explanations. The LPA/Subrecipient and ADOT BECO reserves the 
right to request and receive documents from the contractor and all subcontractors of any

Prompt Pay and Payment Reporting Provisions- 5/5 
tier, in order to determine whether prompt payment requirements are met. 
 
The contractor shall implement and use the dispute resolution process outlined in the 
subcontract or by following the LPA/Subcrecipient escalation process, to resolve payment 
disputes. 
 
 
 
(8)  
Non-compliance: 
 
Failure to make prompt partial payment, or prompt final payment including any retention, 
within the time frames established above, will result in remedies, as the LPA/Subrecipient 
Procurement Office deems appropriate, which may include but are not limited to: 
 
(a) Sanctions: These sanctions will be in addition to all other retention or 
liquidated damages provided for elsewhere in the contract. 
 
(i) The LPA/Subrecipient Procurement Office will withhold two times the 
disputed dollar amount not paid to each subcontractor. 
(ii) If full payment is made within 30 days of the LPASubrecipient 
Procurement Office’s payment to the contractor, the amount withheld by 
the LPA/Subrecipient Procurement Office will be released. 
(iii) If full payment is made after 30 days of the LPA/Subrecipient 
Procurement Office’s payment to the contractor, the LPA/Subrecipient 
Procurement Office will release 75 percent of the funds withheld.  The 
LPA/Subrecipient Procurement Office will retain 25 percent of the 
monies withheld as sanctions. 
 
 (b) Additional Remedies.  If the contractor fails to make prompt payment for 
three consecutive months, or any four months over the course of one 
project, or if the contractor fails to make prompt payment on two or more 
projects within 24 months, the LPA/Subrecipient Procurement Office may, 
in addition, invoke the following remedies: 
 
(i) Withhold monthly progress payments until the issue is resolved and full 
payment has been made to all subcontractors, subject to the sanctions 
described in paragraph (a) above, 
(ii) Terminate the contract for default, 
(iii) Disqualify the contractor from future bidding, temporarily or 
(iv) permanently, depending on the number and severity of violations, if 
applicable. 
 
In determining whether sanctions will be assessed, the extent of the sanctions, or additional 
remedies assessed, the LPA/Subrecipient will consider whether there have been other 
violations on this or other contracts, whether the failure to make prompt payment was due to 
circumstances beyond the contractor’s control, and other circumstances.  The contractor 
may, within 15 calendar days of receipt of the decision of the LPA/Subrecipient, escalate the 
decision according to the contract’s escalation process.

6.0 
TITLE VI 
 
TITLE VI ASSURANCE 
TITLE VI APPENDIX A 
TITLE VI APPENDIX E

APPENDIX A 
During the performance of this contract, the contractor, for itself, its assignees, and successors in interest 
(hereinafter referred to as the "contractor") agrees as follows: 
  
1. 
Compliance with Regulations:  The contractor (hereinafter includes consultants) will comply with the 
Acts and the Regulations relative to Non-discrimination in Federally-assisted programs of the U.S. Department of 
Transportation, Federal Highway Administration or the Arizona Department of Transportation,  as they may be 
amended from time to time, which are herein incorporated by reference and made a part of this contract. 
2. 
Non-discrimination:  The contractor, with regard to the work performed by it during the contract, will 
not discriminate on the grounds of race, color, or national origin in the selection and retention of 
subcontractors, including procurements of materials and leases of equipment. The contractor will not 
participate directly or indirectly in the discrimination prohibited by the Acts and the Regulations, including 
employment practices when the contract covers any activity, project, or program set forth in Appendix B of 49 
CFR Part 21.  
3. 
Solicitations for Subcontracts, Including Procurements of Materials and Equipment:  In all solicitations, 
either by competitive bidding, or negotiation made by the contractor for work to be performed under a 
subcontract, including procurements of materials, or leases of equipment, each potential subcontractor or 
supplier will be notified by the contractor of the contractor's obligations under this contract and the Acts and 
the Regulations relative to Non-discrimination on the grounds of race, color, or national origin.  
4. 
Information and Reports:  The contractor will provide all information and reports required by the Acts, 
the Regulations, and directives issued pursuant thereto and will permit access to its books, records, accounts, 
other sources of information, and its facilities as may be determined by the Recipient, the Federal Highway 
Administration or Arizona Department of Transportation to be pertinent to ascertain compliance with such Acts, 
Regulations, and instructions. Where any information required of a contractor is in the exclusive possession of 
another who fails or refuses to furnish the information, the contractor will so certify to the Recipient, the 
Federal Highway Administration, or Arizona Department of Transportation, as appropriate, and will set forth 
what efforts it has made to obtain the information. 
5. 
Sanctions for Noncompliance:  In the event of a contractor's noncompliance with the Non-discrimination 
provisions of this contract, the Recipient will impose such contract sanctions as it or the Federal Highway 
Administration or Arizona Department of Transportation, may determine to be appropriate, including, but not 
limited to: 
a. withholding payments to the contractor under the contract until the contractor complies; and/or 
b. cancelling, terminating, or suspending a contract, in whole or in part.     
 
6. 
Incorporation of Provisions:  The contractor will include the provisions of paragraphs one through six in 
every subcontract, including procurements of materials and leases of equipment, unless exempt by the Acts, the 
Regulations and directives issued pursuant thereto. The contractor will take action with respect to any 
subcontract or procurement as the Recipient, the Federal Highway Administration, or Arizona Department of 
Transportation may direct as a means of enforcing such provisions including sanctions for noncompliance. 
Provided, that if the contractor becomes involved in, or is threatened with litigation by a subcontractor, or 
supplier because of such direction, the contractor may request the Recipient to enter into any litigation to 
protect the interests of the Recipient. In addition, the contractor may request the United States to enter into the 
litigation to protect the interests of the United States. 
  
  
  
A

APPENDIX E 
  
During the performance of this contract, the contractor, for itself, its assignees, and successors in 
interest (hereinafter referred to as the "contractor") agrees to comply with the following non-
discrimination statutes and authorities; including but not limited to: 
  
Pertinent Non-Discrimination Authorities: 
• 
Title VI of the Civil Rights Act of 1964 (42 U.S.C. § 2000d et seq., 78 stat. 252), (prohibits 
discrimination on the basis of race, color, national origin); and 49 CFR Part 21. 
• 
The Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970, (42 
U.S.C. § 4601), (prohibits unfair treatment of persons displaced or whose property has been acquired 
because of Federal or Federal-aid programs and projects); 
• 
Federal-Aid Highway Act of 1973, (23 U.S.C. § 324 et seq.), (prohibits discrimination on the basis 
of sex); 
• 
Section 504 of the Rehabilitation Act of 1973, (29 U.S.C. § 794 et seq.), as amended, (prohibits 
discrimination on the basis of disability); and 49 CFR Part 27; 
• 
The Age Discrimination Act of 1975, as amended, (42 U.S.C. § 6101 et seq.), (prohibits 
discrimination on the basis of age); 
• 
Airport and Airway Improvement Act of 1982, (49 USC  § 471, Section 47123), as amended, 
(prohibits discrimination based on race, creed, color, national origin, or sex); 
• 
The Civil Rights Restoration Act of 1987, (PL 100-209), (Broadened the scope, coverage and 
applicability of Title VI of the Civil Rights Act of 1964, The Age Discrimination Act of 1975 and Section 
504 of the Rehabilitation Act of 1973, by expanding the definition of the terms "programs or activities" 
to include all of the programs or activities of the Federal-aid recipients, sub-recipients and contractors, 
whether such programs or activities are Federally funded or not); 
• 
Titles II and III of the Americans with Disabilities Act, which prohibit discrimination on the basis 
of disability in the operation of public entities, public and private transportation systems, places of 
public accommodation, and certain testing entities (42 U.S.C. §§ 12131-12189) as implemented by 
Department of Transportation regulations at 49 C.F.R. parts 37 and 38; 
• 
The Federal Aviation Administration's Non-discrimination statute (49 U.S.C. §  47123) (prohibits 
discrimination on the basis of race, color, national origin, and sex); 
• 
Executive Order 12898, Federal Actions to Address Environmental Justice in Minority 
Populations and Low-Income Populations, which ensures discrimination against minority populations 
by discouraging programs, policies, and activities with disproportionately high and adverse human 
health or environmental effects on minority and low-income populations; 
• 
Executive Order 13166, Improving Access to Services for Persons with Limited English 
Proficiency, and resulting agency guidance, national origin discrimination includes discrimination 
because of limited English proficiency (LEP). To ensure compliance with Title VI, you must take 
reasonable steps to ensure that LEP persons have meaningful access to your programs (70 Fed. Reg. at 
74087 to 74100); 
• 
Title IX of the Education Amendments of 1972, as amended, which prohibits you from 
discriminating because of sex in education programs or activities (20 U.S.C. 1681 et seq). 
 
 
E

7.0 
 
RECORDS RETENTION

RECORDS RETENTION 
Contractor and Subcontractor Project Records 
(Reference to A.R.S.35-214) 
 
 
The contractor, subcontractors and all suppliers shall keep and maintain all books, papers, records, files, 
accounts, reports, bid documents with backup data, including electronic data, and all other material relating to the 
contract and project for five (5) years following completion and acceptance of the work. 
 
All of the above material shall be made available for auditing, inspection, and copying and shall be produced upon 
request to the Agency.  
The City of Chandler – Capital Projects 
 215 E Buffalo Street, Mail Stop 407 
Chandler, Arizona 85225. 
 
The contractor shall insert the above requirement in each subcontract purchase order and lease agreement and 
shall also include in all subcontracts, a clause requiring subcontractors to include the above requirement in any 
lower-tier subcontract, purchase order, or lease agreement.

8.0 
FEDERAL IMMIGRATION  
AND  
NATIONALITY ACT

Federal Immigration and Nationality Act 
(Reference to Arizona Executive Order 2005-30) 
 
The contractor, including all subcontractors, shall comply with all federal, state and local immigration laws and 
regulations, as set forth in Arizona Executive Order 2005-30, relating to the immigration status of their employees 
who perform services on the contract during the duration of the contract.  The Agency (City of Chandler) shall 
retain the right to perform random audits of contractor and subcontractor records or to inspect papers of any 
employee thereof to ensure compliance. 
 
By submission of a bid, the contractor warrants that the contractor and all prosed subcontractors are and shall 
remain in compliance with all federal, state, and local immigration laws and regulations relating to the immigration 
status of their employees who perform services on the contract.  The Agency may, at its sole discretion, require 
evidence of compliance from the contractor or subcontractor.  Should the Agency request evidence of 
compliance, the contractor or subcontractor shall have ten (10) working days from receipt of the request to supply 
adequate information.  The Department and Agency (City of Chandler) will accept, as evidence of compliance, a 
showing by the contractor or subcontractor, that it has followed the employment verification provisions of the 
Federal Immigration and Nationality Act as set forth in Sections 274A and 274B of that Act, including 
implementation of regulations and agreements between the Department of Homeland Security and the Social 
Security Administration's verification service.  The contractor shall include the requirements of this provision in all 
subcontracts for this project. 
 
Failure to comply with the immigration laws or to submit proof of compliance constitutes a material breach of 
contract.  The Agency will recue the contractor's compensation by $10,000 for the initial instance of non-
compliance by the contractor or a subcontractor.  Should the same contractor or subcontractor commit 
subsequent violations within a two (2) year time period from the initial violation, the contractor's compensation will 
be reduced by $50,000 for each violation.  The third instance by the same contractor or subcontractor within a two 
(2) year period may result, in addition to the $50,000 reduction in compensation, in removal of the offending 
contractor of subcontractor, suspension of work in whole or in part or, in the case of a third violation by the 
contractor, termination of the contract for default  in addition, the Department may debar a contractor or 
subcontractor who has committed three (3) violations within a two (2) year period for up to one (1) year.  For 
purposes of this paragraph, a violation by a subcontractor does not count as a violation by the contractor. 
 
Any delay resulting from a sanction under this subsection is a non-excusable delay.  The contractor is not entitled 
to any compensation or extension of time for any delays or additional costs resulting from a sanction under this 
subsection.

9.0 
BUY AMERICA REQUIREMENTS 
 
 
 
On May 14, 2022 - Build America, Buy America: This new law governs domestic preferences for iron 
and steel, manufactured products and construction materials for infrastructure projects that use federal 
dollars for funding.

Federal Funded Contract Guide for Contractors – Rev 2023-04-10             pg 1 of 5 
                                                        
 
 
 
BUY AMERICA / BUILD AMERICA BUY AMERICA / MATERIAL CERTIFICATION 
REQUIREMENTS 
For City of Chandler Federal Funded Projects Per FHWA 
 
 
The City of Chandler will follow Buy America requirements and the Build America Buy America 
requirements. 
 
 
 
A. REGULATIONS 
1. FHWA - BUY AMERICA  AND THE NEW BUILD AMERICA, BUY AMERICA REGULATION EFFECTIVE 
NOVEMBER 1, 2022.  
https://www.transportation.gov/sites/dot.gov/files/docs/buy_america_provisions_side_by_side.pdf) 
 
Federal Highway Administration (FHWA) - 23 U.S.C. § 313 – Buy America; 23 C.F.R. § 635.410 
 
The Secretary of Transportation shall not obligate any funds unless steel, iron, and manufactured products used 
In such project are produced in the United States. 
 
2. MAG SPECIFICATION SECTION 106.2.1 
 
3. ADOT SPECIFICATION 106, 106.05 AND 106.15 
 
B. PROCEDURE FOR MATERIAL CERTIFICATION REQUIREMENTS – CITY OF CHANDLER 
 
1.  All material for a federal funded project must have a material certification. 
2.  All material delivered to jobsite must be accompanied by a material certification. 
3. Material Certifications must be submitted to the City of Chandler representative for review and approval and is not 
deemed accepted until City of Chandler representative approval. 
4. Buy America Material – All Iron and Steel products.  (See Item A above) 
5. Buy America Material Installation: All Buy America Iron and Steel Products MUST NOT be installed without 
Material Certification received and approval from City of Chandler.   
6. All non-Buy America Material Installation: All non-Buy America material, if installed without material certification 
receipt and approval is at the Prime Contractor's risk and WILL NOT BE PAID until approval of material 
certification for that material. 
 
C. MATERIAL CERTIFICATIONS – Every Material Certification must have the following– Items 1-11 
1. Project Name 
2. City Project Number 
3. Federal Project Number 
4. ADOT Number (previously known as Tracs Number) (if FHWA funded project) 
5. Supplier Information:  Name, Address, Telephone Number 
6. Description of the material supplied 
7. Quantity of material represented by the certificate 
8. Means of material identification, such as label, lot number, or marking 
9. A Statement that the material complies in all respects with the requirements of the cited specifications. 
Certificates shall state compliance with the cited specification, such as AASHTO M 320, ASTM C 494; or specific 
table or subsection of the Arizona Department of Transportation Standard Specifications or Special Provisions. 
Certificates may cite both, if applicable. 
10. Authorization Signature Statement: A statement that the individual signing has the legal authority to bind the 
manufacturer or the supplier of the material. 
11. The name, title, signature, and date of signature of the signing-responsible individual. 
12. Statement that that Federal Requirements for Buy America / BABA have been followed.

Federal Funded Contract Guide for Contractors – Rev 2023-04-10             pg 2 of 5 
                                                        
ADOT SPECIFICATION – BUILD AMERICA BUY AMERICA (106CMATLS, 10-20-22) 
 
SECTION 106 CONTROL OF MATERIALS: of the Standard Specification is modified to add: 
 
106.17 Construction Materials 
 
A construction material, when used on a federal-aid construction project shall comply with the requirements of Build 
America Buy America (BABA) Act specific in Title IX, Subtitle A, Part 1, Sections 70901 and 70911-70918 of the 
Infrastructure Investment and Job Act (ILJA). 
 
A ‘construction material’ that is permanently incorporated on the project shall include an article, material, or supply that is 
or consists primarily of the following: 
 
- 
Non-ferrous metals; 
- 
Plastic and polymer-based products (including polyvinylchloride, composite building materials, and polymers used 
in fiber optic cables); 
- 
Glass (including optic glass); 
- 
Lumber; or 
- 
Drywall  
 
Items manufactured through a combination of either two or more materials listed above, or at least one of the materials list 
above and a material not listed shall be considered as a manufactured product, rather than as a construction material. 
 
Build America Buy America provisions specified for manufactured products in Section 70912(6)(B) of the ILJA, do not 
apply to federal-aid construction projects per FHQWA’s existing statutory requirement applicable to manufactured 
products.  A “manufactured product’ is considered to be an item that undergoes one or more manufacturing processes 
before the item can be used on a federal-aid construction project. 
 
Construction materials shall not include cement and cementitious materials; bituminous materials; aggregates such as 
stone, sand, or gravel; or aggregate binding agents or additives. 
 
All construction materials shall be produced in the United States. This means, all manufacturing processes to produce the 
construction materials shall occur in the United States.  All manufacturing processes for construction materials shall mean 
the final manufacturing process and the immediately preceding manufacturing stage for the construction material. 
 
The contractor shall furnish the Engineer with Certificate of Compliance, conforming to the requirements of Subsection 
106.05 of the ADOT specifications, which shall state that the construction materials incorporated in the project meet the 
requirements specified herein. 
 
Certificates of Compliance shall also certify that all manufacturing processes to produce construction materials occurred in 
the United States. 
 
Convict-produced materials are prohibited in accordance with the requirements of 23 CFR 635.417.

Federal Funded Contract Guide for Contractors – Rev 2023-04-10             pg 3 of 5 
                                                        
 
ADDITIONAL INFORMATION FOR THE BUILD AMERICA, BUY AMERICA ACT

Federal Funded Contract Guide for Contractors – Rev 2023-04-10             pg 4 of 5

10.0 
DBE EPRISE 
FOR CONTRACTS WITH DBE GOAL 
(RACE CONSCIOUS)

Professional Services DBE Special Provisions 06/23/2016 
LPA PS EPRISE GOAL - 1/23 
PROFESSIONAL SERVICES 
DBE PROVISIONS  
 (PROJECT SPECIFIC - CONTRACTS) 
FOR USE ON LPA/SUBRECIPIENT FEDEAL AID PROJECTS WITH DBE GOALS 
(LPA PS EPRISE, 6/23/2016) 
DISADVANTAGED BUSINESS ENTERPRISES: 
1.0 
Policy: 
The Arizona Department of Transportation (hereinafter the Department) has established a 
Disadvantaged Business Enterprise (DBE) program in accordance with the regulations of the 
U.S. Department of Transportation (USDOT), 49 CFR Part 26.  The Department has received 
Federal financial assistance from the U.S. Department of Transportation and as a condition of 
receiving this assistance, the Department has signed an assurance that it will comply with 49 
CFR Part 26. 
It is the policy of the Department to ensure that DBEs, as defined in Part 26, have an equal 
opportunity to receive and participate in USDOT-assisted contracts.  It is also the policy of the 
Department: 
1. To ensure nondiscrimination in the award and administration of USDOT-assisted
contracts;
2. To create a level playing field on which DBEs can compete fairly for
USDOT-assisted contracts;
3. To ensure that the DBE program is narrowly tailored in accordance with applicable
law;
4. To ensure that only firms that fully meet 49 CFR Part 26 eligibility standards are
counted as DBEs;
5. To help remove barriers to the participation of DBEs in USDOT-assisted contracts;
6. To assist in the development of firms that can compete successfully in the market
place outside the DBE program; and
7. To promote the use of DBEs in all types of federally-assisted contracts and
procurement activities.
It is also the policy of the Department to facilitate and encourage participation of Small 
Business Concerns (SBCs), as defined in Subsection 3.0, in USDOT-assisted contracts.  The 
Department encourages consultants to take reasonable steps to eliminate obstacles to SBCs’ 
participation and to utilize SBCs in performing contracts. 
Local Public Agencies (LPA) and or Subrecipients of Federal financial assistance will 
administer and manage the contracts from advertising, consultant selection, negotiation, 
contract execution, processing payment reports and contract modifications, audits, DBE 
compliance (e.g., reporting and monitoring) through contract closeout. 
DBE GOAL FOR ST1804-451: 1.99%

Professional Services DBE Special Provisions 06/23/2016 
LPA PS EPRISE GOAL - 2/23 
2.0 
Assurances of Non-Discrimination: 
The consultant, subrecipient, or subconsultant shall not discriminate on the basis of race, 
color, sex or national origin in the performance of this contract.  The consultant shall carry out 
applicable requirements of 49 CFR Part 26 in the award and administration of DOT-assisted 
contracts.  Failure by the consultant to carry out these requirements is a material breach of this 
contract, which may result in the termination of this contract or such other remedy as the the 
LPA/Subrecipient with the Department’s concurrence deems appropriate, which may include, 
but are not limited to: 
1. Withholding monthly progress payments;
2. Assessing sanctions;
3. Liquidated damages;
4. Disqualifying the consultant from submitting SOQs, or any other forms of proposals, as
non-responsible;
5. Cancellation, termination, or suspension of the Contract, in whole or in part.
The consultant, subrecipient, or subconsultant shall ensure that all subcontract agreements 
contain this non-discrimination assurance. 
3.0 
Definitions: 
(A) Commercially Useful Function (CUF): Commercially Useful Function is defined fully in
49 CFR 26.55, which definition is incorporated herein by reference.
(B) Committed DBE:  A DBE that was identified by the consultant, typically on a DBE
Affidavit, to meet an assigned DBE goal as a condition of contract award and
performance, and includes any substitute DBE that has subsequently been committed
work to meet the assigned contract goal.
(C) Disadvantaged Business Enterprise (DBE):  a for-profit small business concern which
meets both of the following requirements:
(1)
Is at least 51 percent owned by one or more socially and economically
disadvantaged individuals or, in the case of any publicly owned business, at least 51
percent of the stock is owned by one or more such individuals; and,
(2)
Whose management and daily business operations are controlled by one or more of
the socially and economically disadvantaged individuals who own it.
(D) NAICS Code: The North American Industry Classification System (NAICS) is the
standard used by Federal statistical agencies in classifying business establishments for
the purpose of collecting, analyzing, and publishing statistical data related to the U.S.
business economy.

Professional Services DBE Special Provisions 06/23/2016 
LPA PS EPRISE GOAL - 3/23 
(E) Non-DBE:  any firm that is not a DBE.
(F) Race-Conscious (RC): a measure or program focused specifically on assisting only
DBEs, including women-owned DBEs.
(G) Race-Neutral (RN): a measure or program used to assist all small businesses. For the
purposes of this part, race-neutral includes gender-neutrality.
(H) Small Business Concern (SBC): a business that meets all of the following conditions:
(1)
Operates as a for-profit business registered to do business in Arizona;
(2)
Operates a place of business primarily within the U.S., or makes a significant
contribution to the U.S. economy through payment of taxes or use of American
products, materials, or labor;
(3)
Is independently owned and operated;
(4)
Is not dominant in its field on a national basis; and
(5)
Does not have annual gross receipts that exceed the Small Business
Administration size standards average annual income criteria for its primary North
American Industry Classification System (NAICS) code.
(I) Socially and Economically Disadvantaged Individuals:  any individual who is a
citizen (or lawfully admitted permanent resident) of the United States and who is:
(1)
Any individual who is found to be a socially and economically disadvantaged
individual on a case-by-case basis.
(2)
Any individual in the following groups, members of which are rebuttably presumed
to be socially and economically disadvantaged:
(i)
"Black Americans," which includes persons having origins in any of the Black
racial groups of Africa;
(ii)
"Hispanic Americans," which includes persons of Mexican, Puerto Rican,
Cuban, Dominican, Central or South American, or other Spanish or
Portuguese culture or origin, regardless of race;
(iii)
"Native Americans," which includes persons who are enrolled members of
federally or State recognized Indian tribe, Alaskan Natives or Native
Hawaiians;
(iv)
“Asian-Pacific Americans,” which includes persons whose origins are from
Japan, China, Taiwan, Korea, Burma (Myanmar), Vietnam, Laos, Cambodia

Professional Services DBE Special Provisions 06/23/2016 
LPA PS EPRISE GOAL - 4/23 
(Kampuchea), Thailand, Malaysia, Indonesia, the Philippines, Brunei, 
Samoa, Guam, the U.S. Trust Territories of the Pacific Islands (Republic of 
Palau), the Republic of the Northern Marianas Islands, Macao, Fiji, Tonga, 
Kiribati, Tuvalu, Nauru, Federated States of Micronesia, or Hong Kong; 
(v)
“Subcontinent Asian Americans,” which includes persons whose origins are
from India, Pakistan, Bangladesh, Bhutan, the Maldives Islands, Nepal or Sri
Lanka;
(vi)
"Women;"
(vii)
Any additional groups whose members are designated as socially and
economically disadvantaged by the Small Business Administration (SBA), at
such time as the SBA designation becomes effective.
4.0 
Working with DBEs: 
The Department works with DBEs and assists them in their efforts to participate in the highway 
construction program.  All proposers should contact the Department’s Business Engagement 
and Compliance Office (BECO) by phone, through email, or at the address shown below, for 
assistance in their efforts to use DBEs in the highway construction industry.  BECO contact 
information is as follows: 
Arizona Department of Transportation 
Business Engagement and Compliance Office 
1801 W. Jefferson St, Suite 101, Mail Drop 154A 
Phoenix, AZ  85007 
Phone (602) 712-7761 
FAX    (602) 712-8429 
Email: ContractorCompliance@azdot.gov 
Website :  www.azdot.gov/bec 
4.01 
Mentor-Protège Program 
The Department has established a Mentor-Protégé program as an initiative to encourage and 
develop disadvantaged businesses in the highway construction industry.  The program 
encourages prime consultants to provide certain types of assistance to certified DBE 
subconsultants.  ADOT encourages consultants and certified DBE subconsultants to engage in a 
Mentor-Protégé agreement under certain conditions.  Such an agreement must be mutually 
beneficial to both parties and to ADOT in fulfilling requirements of 49 CFR Part 23.  For guidance 
regarding this program refer to the Mentor-Protégé Program Guidelines available on the BECO 
website.   
The Mentor-Protégé program is intended to increase legitimate DBE activities and is not 
intended to diminish nor circumvent existing DBE rules or regulations.

Professional Services DBE Special Provisions 06/23/2016 
LPA PS EPRISE GOAL - 5/23 
5.0 
Applicability: 
The Department has established an overall annual goal for DBE participation on Federal-aid 
contracts.  The Department intends for the goal to be met with a combination of race conscious 
efforts and race neutral efforts.  Race conscious participation occurs when the consultant uses 
a percentage of DBEs, as defined herein, to meet the contract-specified goal.  Race neutral 
efforts are those that are, or can be, used to assist all small businesses or increase 
opportunities for all small businesses.  The regulation, 49 CFR 26, defines race neutral as 
when a DBE wins a prime contract through customary competitive procurement procedures or 
is awarded a subcontract on a prime contract that does not carry a DBE contract goal. 
The consultant shall meet the goal specified herein with DBEs, or establish that it was unable 
to meet the goal despite making good faith efforts to do so.  Prime consultants are encouraged 
to obtain DBE participation above and beyond any goals that may be set for this project. 
The DBE provisions are applicable to all consultants including DBE consultants. 
6.0 
Certification and Registration: 
6.01 
DBE Certification: 
Certification as a DBE shall be predicated on: 
(1) The completion and execution of an application for certification as a "Disadvantaged
Business Enterprise."
(2) The submission of documents pertaining to the firm(s) as stated in the application(s),
including but not limited to a statement of social disadvantage and a personal financial
statement.
(3) The submission of any additional information which the Department or the applicable
Arizona Unified Certification (UCP) agency may require to determine the firm's eligibility to
participate in the DBE program.
(4) The information obtained during the on-site visits to the offices of the firm and to active
job-sites.
Applications for certification may be filed online with the Department or the applicable UCP 
agency at any time through the Arizona Unified Transportation Registration and Certification 
System (AZ UTRACS) website at http://www.azutracs.com. 
DBE firms and firms seeking DBE certification shall cooperate fully with requests for 
information relevant to the certification process.  Failure or refusal to provide such information 
is a ground for denial or removal of certification.

Professional Services DBE Special Provisions 06/23/2016 
LPA PS EPRISE GOAL - 6/23 
ADOT is a member of the AZ Unified Certification Program (AZUCP).  Only DBE firms that are 
certified by the AZUCP are eligible for credit on ADOT projects.  A list of DBE firms certified by 
AZUCP is available on the internet at http://www.azutracs.com.  The list will indicate contact 
information and specialty for each DBE firm, and may be sorted in a variety of ways.  However, 
ADOT does not guarantee the accuracy and/or completeness of this information, nor does 
ADOT represent that any licenses or registrations are appropriate for the work to be done. 
The Department’s certification of a DBE is not a representation of qualifications and/or abilities 
nor does it mean that a DBE firm is guaranteed or entitled to receive or be awarded a contract.  
Being certified simply means that a firm has met the criteria for DBE certification as outlined in 
49 CFR Part 26.  The consultant bears all risks of ensuring that DBE firms selected by the 
consultant are able to perform the work. 
6.02 
SBC Registration: 
To comply with 49 CFR Part 26.39, ADOT’s DBE Program incorporates contracting 
requirements to facilitate participation by Small Business Concerns (SBCs) in federally 
assisted contracts. SBCs are for-profit businesses authorized to do businesses in Arizona that 
meet the Small Business Administration (SBA) size standards for average annual revenue 
criteria for its primary North American Industry Classification System (NAICS) code 
While the SBC component of the DBE program does not require utilization of goals on 
projects, ADOT and the LPA/Subrecipient strongly encourages consultants to utilize small 
businesses that are registered in AZ UTRACS on their contracts, in addition to DBEs meeting 
the certification requirement. The consultant may use the AZ UTRACS website to search for 
certified DBEs and registered SBCs that can be used on the contract.  However, SBCs that are 
not DBEs will not be counted toward the DBE contract goal. 
SBCs can register online at the AZ UTRACS website. 
The Department’s registration of SBCs is not a representation of qualifications and/or abilities 
nor does it mean that an SBC firm is guaranteed or entitled to receive or be awarded a contract.  
Being SBC registered simply means that a firm has met the criteria for SBC registration as 
outlined in 49 CFR Part 26.  The consultant bears all risks of ensuring that SBC firms selected 
by the consultant are able to perform the work. 
7.0 
DBE Financial Institutions: 
The Department thoroughly investigates the full extent of services offered by financial institutions 
owned and controlled by socially and economically disadvantaged individuals in its service area 
and makes reasonable efforts to use these institutions. The Department encourages prime 
consultants to use such institutions on USDOT assisted contracts.  However, use of DBE 
financial institutions will not be counted toward the DBE contract goal.

Professional Services DBE Special Provisions 06/23/2016 
LPA PS EPRISE GOAL - 7/23 
The Department and the LPA/Subrecipient encourages prime consultants to research the 
Federal Reserve Board website at www.federalreserve.gov to identify minority-owned banks in 
Arizona derived from the Consolidated Reports of Condition and Income filed quarterly by banks 
(FFIEC 031 and 041) and from other information on the Board’s National Information Center 
database.  
8.0 
 
Time is of the Essence: 
TIME IS OF THE ESSENCE IN RESPECT TO THE DBE PROVISIONS 
9.0  
 
Computation of Time: 
In computing any period of time described in this DBE special provision, such as calendar 
days, the day from which the period begins to run is not counted, and when the last day of the 
period is a Saturday, Sunday, Federal or State holiday, the period extends to the next day that 
is not a Saturday, Sunday, Federal or State holiday. In circumstances where the 
LPA/Subrecipient Procurement Office is closed for all or part of the last day, the period extends 
to the next day on which the LPA / Subrecipient Procurement Office is open. 
10.0 
Consultant and Subconsultant Requirements: 
10.01 
General: 
The consultant shall establish a DBE program that will ensure nondiscrimination in the award 
and administration of contracts and subcontracts. 
Agreements between the proposer and a DBE in which the DBE promises not to provide 
subcontracting quotations to other proposers are prohibited. 
10.02 
DBE Liaison: 
The consultant shall designate a DBE Liaison responsible for the administration of the 
consultant’s DBE program.  The name of the designated DBE Liaison shall be included on the 
DBE Intended Participation Affidavit Summary.  
11.0  
DBE Goal: 
The minimum goal for participation by DBEs on this project is as follows: 
_____% Percent 
The percentage of DBE participation shall be based on the total dollar value of the contract. 
Proposers are strongly encouraged to secure and include sufficient DBE firms on their team for 
multiple disciplines and work categories to ensure they can meet the DBE goal on the contract 
and for any Contract Modifications that are executed post-award. The DBE goal requirements 
1.99

Professional Services DBE Special Provisions 06/23/2016 
LPA PS EPRISE GOAL - 8/23 
extend to additional dollars added by Contract Modification to help ensure that the overall DBE 
goal is met on the contract. Indicating there is no DBE firm on a prime proposer’s team to meet 
the DBE goal on Contract Modifications does not meet the criteria for Good Faith Efforts in 49 
CFR 26.53, and will not be accepted by the Department as Good Faith Efforts when Contract 
Modifications are issued. Since proposers have been notified of the DBE goal prior to the 
submittal of their Statement of Qualifications (SOQ) they are required to do their due diligence to 
secure enough DBE participation to meet the goal or make good faith efforts on the contract and 
each subsequent Contract Modification. Firms will be required to locate DBEs to meet the goal 
on each Contract Modification even if these DBEs were not originally included as part of their 
team, if the LPA/Subrecipient , with BECO concurrence, determines there are qualified DBEs 
available to complete portions of the work of the Contract Modification.  
12.0 
Submission with SOQ Proposals: 
12.01 
DBE Assurance/Goal Declaration  
In order to be awarded this contract, in addition to all other pre-award requirements, all 
proposers are required to certify on the DBE Assurance Project Specific form provided by the 
LPA/Subrecipient that: 
The proposer will meet the established DBE goal or will make good faith efforts to meet 
the goal and that arrangements with certified DBEs have been made prior to the SOQ 
and/or cost proposal submission. 
Failure to affirmatively make this declaration/certification in the manner outlined in the Request 
for Qualifications (RFQ) furnished by the LPA/Subrecipient will cause a Proposer’s SOQ to be 
considered non-responsive. 
12.02    
Bidders/Proposers List and AZ UTRACS Registration Requirement: 
Under Title 49 CFR of the Code of Federal Regulations, Part 26.11, DOTs are required to collect 
certain information from all consultants and subconsultants who seek to work on federally-
assisted contracts in order to set overall and contract DBE goals. ADOT collects this information 
when firms register their companies on the Arizona Unified Transportation Registration and 
Certification System (AZ UTRACS) web portal at http://www.azutracs.com/ a centralized 
database for companies that seek to do business with ADOT. This information will be maintained 
as confidential to the extent allowed by federal and state law. 
Prime consultants and all subconsultants, including DBEs listed in the SOQ must be registered 
in AZ UTRACS.  Proposers may verify that their firm and each subconsultant is registered using 
the AZ UTRACS website.  
Proposers may obtain additional information at the AZ UTRACS website or by contacting the 
LPA/Subrecipient.

Professional Services DBE Special Provisions 06/23/2016 
LPA PS EPRISE GOAL - 9/23 
All proposers shall create a Bidders/Proposers list in the AZ UTRACS by selecting all firms, 
service providers, and vendors that expressed interest or submitted proposals or quotes for this 
contract. The Bidders/Proposers List form must be complete and must include the names for all 
subconsultants, service providers, and vendors that submitted proposals or quotes on this 
project regardless of the proposer’s intentions to use the those firms on the project.  
All proposers must complete and submit the Bidders/Proposers List online at AZ UTRACS prior 
to Cost Proposal submittal. A confirmation email will be generated by the system. This email 
confirmation shall be submitted with the Cost Proposal.   
FAILURE TO SUBMIT THE REQUIRED BIDDERS/PROPOSERS LIST CONFIRMATION 
EMAIL WITH THE COST PROPOSAL BY THE STATED TIME AND IN THE MANNER HEREIN 
SPECIFIED AND AS OUTLINED IN THE RFQ SHALL BE CAUSE FOR THE PROPOSER’S 
COST PROPOSAL TO BE REJECTED. 
13. 0   DBE Cost Proposal Submissions:
13.01   DBE Intended Participation Affidavits: 
If the proposer indicates in the Cost Proposal submittal that it has met or exceeded the DBE 
goal, a DBE Intended Participation Affidavit form for each DBE firm, and the DBE Intended 
Participation Affidavit Summary form shall be submitted to the LPA/Subrecipient Procurement 
Office with each Cost Proposal as follows: 
(1) The DBE Intended Participation Affidavit Form must be submitted for each individual
DBE firm at all tiers, including direct expense vendors, that is being proposed to be
used to meet the DBE goal on the project.  A copy of this form is available from the
LPA/Subrecipient.
(2) The DBE Intended Participation Affidavit Summary Form must be completed by the
consultant summarizing information about all DBEs being proposed to meet the DBE
goal that are listed on each DBE Intended Participation Affidavit Form. The DBE
Intended Participation Affidavit Summary Form, along with the DBE Intended
Participation Affidavit form for each individual DBE firm, must be submitted together with
the Cost Proposal to the LPA/Subrecipient Procurement Office All forms must be
accurate and complete in every detail and must be signed by an officer of the
consultant(s). Percentages and dollar amounts must be accurate. Percentages shall be
listed to two decimal places. The DBE Intended Participation Affidavit Summary must be
submitted listing all the DBEs intended to be used and the creditable amounts. Copies
of these forms are available from the LPA/Subrecipient.
(3) The DBE Intended Participation Affidavits Forms and the DBE Intended Participation
Affidavit Summary Form must be submitted with the original cost proposal documents.
The same documents must be submitted as part of the contract modification
documentation submittals reflecting any change in the contract amount associated with
the contract modification.

Professional Services DBE Special Provisions 06/23/2016 
LPA PS EPRISE GOAL - 10/23 
(4) A proposer must determine DBE credit for the contract in accordance with DBE Special
Provision Subsection 17.0 Crediting DBE Participation Toward Meeting Goals.  The
affidavits will be reviewed by the LPA/Subrecipient.
(5)
Only those DBE firms certified by the Arizona Unified Certification Program (AZUCP) at
the time of the Cost Proposal submittal will be considered for DBE credit. It shall be the
proposer’s responsibility to ascertain the certification status of designated DBEs.
(6) All DBE commitment amounts must be finalized between the DBE subconsultant and
the proposer prior to affidavit submittal.  Proposers shall not inflate DBE awards in order
to meet contract goals.  Reduction of DBE commitments after affidavit submittal and
prior to execution of the contract without good cause may be grounds for the proposer
to be considered nonresponsive.  Scheduling conflicts are not necessarily evidence of
good cause as this should have been considered prior to affidavit submittal.  Proposers
are required to use DBEs identified in both the SOQ and Cost Proposal to meet the
contract goal, so the consultant is responsible for ensuring the DBEs listed in the SOQ
and submitted with the Cost Proposal are available to meet those requirements at the
time of contract execution.
(7) Cost proposals without affidavits shall be considered incomplete and contract
negotiations shall not be finalized nor will the contract be executed until affidavits are
submitted and approved.
14.0 
Documented Good Faith Effort: 
14.01 
General: 
If the selected proposer has indicated in its cost proposal submittal that it will be unable to 
meet the DBE goal, that proposer must demonstrate, through detailed and comprehensive 
documentation, that good faith efforts have been made to solicit, assist, and use DBE firms to 
meet the DBE goal prior to submission of the SOQ and cost proposal. 
Failure to demonstrate good faith efforts to the satisfaction of LPA/Subrecipient with concurrence 
of BECO will result in denying the award and moving to the next second highest ranked 
proposer. 
The selected proposer who cannot meet the DBE goal at the time the cost proposal is due must 
submit its documentation of good faith efforts to the LPA/Subrecipient with the cost proposal.  
Contract negotiations will not be finalized nor will the contract be executed until the required 
Good Faith Effort forms and required documentation are received and approved. 
The documentation of good faith efforts must include copies of each DBE and non-DBE 
subconsultant quotes submitted to the proposer when a non-DBE subconsultant was selected 
over a DBE for work on the contract. A generalized assertion that the consultant received 
multiple quotes is not sufficient unless copies of those quotes are provided.

Professional Services DBE Special Provisions 06/23/2016 
LPA PS EPRISE GOAL - 11/23 
Proposers are encouraged to review Appendix A of 49 CFR Part 26.  
Useful information related to encouraging DBE participation and documented good faith efforts 
can be found in the “Good Faith Effort Guide” and other documents made available on the 
BECO website.  The information provided in the “Good Faith Effort Guide” does not replace 
this specification; proposers must comply with the requirements of this specification. 
In order to be awarded a contract on the basis of good faith efforts, a proposer must show that 
it took all necessary and reasonable steps to achieve the DBE goal, which, by their scope, 
intensity, and appropriateness to the objective, could reasonably be expected to obtain 
sufficient DBE participation, even if they were not fully successful.  The quality, quantity, and 
intensity of the different kinds of efforts the proposer has made will be evaluated.  The efforts 
employed by the proposer should be those that one could reasonably expect a proposer to 
make if the proposer were actively and aggressively trying to obtain DBE participation 
sufficient to meet the DBE goal.  Mere pro forma efforts are not sufficient good faith efforts to 
meet the DBE contract requirements. 
The proposer shall, as a minimum, seek DBEs in the same geographic area in which it generally 
seeks subconsultants for a given project.  If the proposer cannot meet the goals using DBEs 
from this geographic area, the proposer, as part of its effort to meet the goals, shall expand its 
search to a reasonably wider geographic area. 
The following is a list of types of efforts a proposer must address when submitting good faith 
effort documentation. 
(1) Contacting the LPA/Subrecipient and BECO prior to the submission of proposals, either
by e-mail, or by telephone, to inform of the firm’s difficulty in meeting the DBE goals on
a given project, and requesting assistance.  The proposer must document its contact
with the LPA/Subrecipient and BECO, and indicate the type of contact, the date and
time of the contact, the name of the person(s) contacted, and any details related to the
communication.  The contact must be made in sufficient time before proposal
submission to allow the LPA/Subrecipient and BECO to provide effective assistance.
The proposer will not be considered to have made good faith efforts if the proposer
failed to contact the LPA/Subrecipient and BECO.
(2) Conducting market research to identify small business consultants and suppliers, and
soliciting, through all reasonable and available means, the interest of all certified DBEs
who have the capability to perform the work of the contract.  This may include
attendance at pre-proposal meetings and business matchmaking meetings and events,
advertising and/or providing written notices, posting of “Notices of Sources Sought”
and/or “Requests for Proposals” at reasonable locations, including the consultant’s
website, written notices or emails to all DBEs listed in the Department’s directory of
transportation firms that specialize in areas of work desired (as noted in the DBE
directory) and which are located in the area or surrounding areas of the project.  The
proposer should solicit this interest as early in the acquisition process as practicable to

Professional Services DBE Special Provisions 06/23/2016 
LPA PS EPRISE GOAL - 12/23 
allow DBEs to respond to the solicitation and submit a timely offer for the subcontract. 
The proposer should determine with certainty if DBEs are interested by taking 
appropriate steps to follow-up initial solicitations. 
(3) Selecting portions of the work to be performed by DBEs in order to increase the
likelihood that the DBE goal will be achieved.  This includes, where appropriate,
breaking out contract work items into economically feasible units (for example smaller
tasks or quantities) to facilitate DBE participation, even when the prime consultant might
otherwise prefer to perform these work items with its own forces.  This may include,
where possible, establishing flexible time frames for performance and delivery
schedules in a manner that encourages and facilitates DBE participation.
(4) Providing interested DBEs with adequate information about the plans, specifications,
and requirements of the contract in a timely manner to assist them in responding to a
solicitation with their offer for a subcontract.
(5) Negotiating in good faith with interested DBEs.  It is the proposer’s responsibility to
make a portion of the work available to the DBE subconsultants and suppliers, and to
select those portions of work or material needs consistent with the available DBE
subconsultants and suppliers, so as to facilitate DBE participation.  Evidence of such
negotiation includes the names, addresses, and telephone numbers of DBEs that were
considered; a description of the information provided from the plans and specifications
for the work selected for subcontracting; and evidence as to why additional agreements
could not be reached for DBEs to perform work.
Pro forma mailings to DBEs requesting proposals are not alone sufficient to constitute
good faith negotiation.
A proposer using good business judgment would consider a number of factors in
negotiating with subconsultants, including DBE subconsultants, and would take a firm’s
price and capabilities as well as contract goals into consideration.  However, the fact
that there may be some additional costs involved in finding and using DBEs is not in
itself sufficient reason for a proposer’s failure to meet the DBE goal, as long as such
costs are reasonable.  Also, the ability or desire of a prime consultant to perform the
work of a contract with its own organization does not relieve the proposer of the
responsibility to make good faith efforts.  However, prime consultants are not required to
accept higher quotes from DBEs if the price difference is excessive or unreasonable.
Documentation, such as copies of all other proposals or quotes, must be submitted.
Another practice considered an insufficient good faith effort is the rejection of the DBE
because its quotation for the work was not the lowest received.  The consultant must
submit copies of each DBE and non-DBE subconsultant quote submitted to the
proposer when a non-DBE subconsultant was selected over a DBE for work on the
contract.  The Department may contact rejected DBEs as part of its investigation.
However, nothing in this paragraph shall be construed to require the proposer or prime
consultant to accept unreasonable quotes in order to satisfy contract goals.

Professional Services DBE Special Provisions 06/23/2016 
LPA PS EPRISE GOAL - 13/23 
(6) Not rejecting DBEs as being unqualified without sound reasons based on a thorough
investigation of their capabilities.  The consultant’s standing within its industry,
membership in specific groups, organizations or associations and political or social
affiliations (for example, union vs. non-union employee status) are not legitimate causes
for the rejection or non-solicitation of proposals in the consultant’s efforts to meet the
project goal.  Consultant must submit documentation of past performance and with input
from the PM, consultant’s qualifications are then reviewed for acceptance and approval.
(7) Making efforts to assist interested DBEs in obtaining bonding, lines of credit, or
insurance as required by the recipient or consultant.
(8) Making efforts to assist interested DBEs in obtaining necessary equipment, supplies,
materials, or related assistance or services.
(9) Effectively using the services of available minority/women community organizations;
minority/women consultants’ groups; local, state, and Federal minority/women business
assistance offices; and other organizations as allowed on a case-by-case basis to
provide assistance in the recruitment and placement of DBEs.
In determining whether a proposer has made good faith efforts, the LPA/Subrecipient will 
review the documented efforts of the consultant and will review the performance of other 
proposers in meeting the contract goal. 
A promise to use DBEs after contract award is not considered to be responsive to the contract 
solicitation or to constitute good faith efforts. 
The LPA/Subrecipient will evaluate the submittal and  make a determination, with BECO 
concurrence, whether in fact good faith efforts have been demonstrated consistent with the 
specifications and the Federal regulations, 49 CFR 26, Appendix A. 
14.02 
Protest for Denied Good Faith Efforts: 
If the LPA/Subrecipient, with BECO concurrence, determines that the proposer failed to make 
adequate good faith efforts, the proposer may protest the determination by submitting an appeal 
in writing to the ADOT State Engineer.  The decision of the ADOT State Engineer is 
administratively final.      
The proposer whose proposal was rejected for failure to meet the goal or make GFE will be 
given the opportunity to meet in person with the State Engineer, at the proposer’s written request 
included in the protest, to discuss the issue of whether it met the goal or made adequate good 
faith efforts to do so. The State Engineer shall promptly consider any appeals and notify the 
LPA/Subrecipient and all proposers in writing on its findings and decision.  
In accordance with 49 CFR 26.53(d)(5), the result of the protest decision is not subject to 
administrative appeal to the USDOT.

Professional Services DBE Special Provisions 06/23/2016 
LPA PS EPRISE GOAL - 14/23 
15.0 
Rejection of Proposal: 
If, for any reason, the proposer’s GFE is rejected or contract negotiations fail, the 
LPA/Subrecipient will proceed with negotiating with the second highest ranked firm.  The 
LPA/Subrecipient, will notify the second highest ranked firm, and this firm shall submit its 
subsequent detailed submission as set forth in the DBE Subsections 13 or 14. 
16.0 
Payment Reporting: 
The consultant shall report on a monthly basis indicating the amounts paid to all subconsultants, 
of all tiers, working on the project.  Reporting shall be in accordance with Prompt Pay 
and Payment Reporting requirements. 
17.0 
Crediting DBE Participation Toward Meeting Goals: 
17.01 
General Requirements: 
To count toward meeting the goal, the DBE firms must be certified at the time of Cost Proposal 
submission in each NAICS code applicable to the kind of work the firm will perform on the 
contract. NAICS for each DBE can be found on the AZ UTRACS website. General descriptions 
of all NAICS codes can be found at http://www.naics.com/search/.  
Credit towards the consultant’s DBE goal is given only after the DBE has been paid for the work 
performed. 
The entire amount of a contract that is performed by the DBE’s own forces, including the cost of 
supplies and materials purchased by the DBE for the work on the contract and equipment leased 
by the DBE will be credited toward DBE participation. Supplies and equipment the DBE 
subconsultant purchases or leases from the prime consultant or its affiliate will not be credited 
toward DBE participation. 
The consultant bears the responsibility to determine whether the DBE possesses the proper 
consultant’s license(s) to perform the work and, if DBE credit is requested, that the DBE 
subconsultant is certified for the requested type of work. 
If a DBE cannot complete its work due to failure to obtain or maintain its licensing, the consultant 
bears the responsibility to notify the LPA/Subrecipient, immediately after the consultant becomes 
aware of the situation, and request approval to replace the DBE with another DBE. The 
consultant shall follow the DBE termination/substitution requirements described in Subsection 
22.0 of these DBE provisions. 
The Department’s certification is not a representation of a DBE’s qualifications and/or abilities.  
The consultant bears all risks that the DBE may not be able to perform its work for any reason.

Professional Services DBE Special Provisions 06/23/2016 
LPA PS EPRISE GOAL - 15/23 
A DBE may participate as a prime consultant, subconsultant, or as a vendor of materials or 
supplies.  The dollar amount of work to be accomplished by DBEs, including partial amount of a 
lump sum or other similar item, shall be on the basis of subcontract, purchase order, hourly rate, 
rate per ton, etc., as agreed to between parties. 
 
DBE credit may be obtained only for specific work done for the project, supply of equipment 
specifically for physical work on the project, or supply of materials to be incorporated in the work.  
DBE credit will not be allowed for costs such as overhead items, capital expenditures (for 
example, purchase of equipment), and office items. 
 
The consultant may credit second-tier subcontracts issued to DBEs by non-DBE subconsultants.  
Any second-tier subcontract to a DBE used to meet the goal must meet the requirements of a 
first-tier DBE subcontract. 
 
A prime consultant may credit the entire amount of that portion of a contract that is performed 
by the DBE’s own forces.  The cost of supplies and materials obtained by the DBE for the work 
of the contract can be included so long as that cost is reasonable.  Leased equipment may 
also be included.  No credit is permitted for supplies purchased or equipment leased from the 
prime consultant or its affiliate(s). 
 
When a DBE subcontracts a part of the work of its contract to another firm, the value of the 
subcontract may be credited towards the DBE goal only if the DBE’s subconsultant is itself a 
DBE and performs the work with its own forces.  Work that a DBE subcontracts to a non-DBE 
firm does not count toward a DBE goal. 
 
A prime consultant may credit the entire amount of fees or commissions charged by a DBE 
firm for providing a bona fide service, such as professional, technical, consulting, or 
managerial services, or for providing bonds or insurance specifically required for the 
performance of a USDOT-assisted contract, provided the fees are reasonable and not 
excessive as compared with fees customarily allowed for similar services. 
 
17.02  
DBE Prime Consultant: 
 
When a certified DBE firm proposes on a contract that contains a DBE goal, the DBE firm is 
responsible for meeting the DBE goal on the contract or making good faith efforts to meet the 
goal, just like any other proposer. In most cases, a DBE proposer on a contract will meet the 
DBE goal by virtue of the work it performs on the contract with its own forces. However, all the 
work that is performed by the DBE proposer or any other DBE subconsultants and DBE 
suppliers will count toward the DBE goal. The DBE proposer shall list itself along with any DBE 
subconsultants and suppliers, on the DBE Intended Participation Affidavit Individual and 
Summary in order to receive credit toward the DBE goal.  
 
17.03  
Effect of Loss of DBE Eligibility: 
 
If a DBE is deemed ineligible (decertified) or suspended in accordance with 49 CFR 26.87 and 
26.88, the DBE may not be considered to meet a contract goal on a new contract, but may be

Professional Services DBE Special Provisions 06/23/2016 
LPA PS EPRISE GOAL - 16/23 
considered to meet the contract goal under a subcontract that was executed before the DBE 
suspension or decertification is effective. 
 
When the consultant makes a commitment to use an ineligible DBE firm or the 
LPA/Subrecipient, made a commitment to use an ineligible DBE prime consultant, but a 
subcontract or contract has not been executed before a decertification notice is issued to the 
DBE firm by its certifying agency, the ineligible firm does not count toward the contract goal. The 
consultant must meet the contract goal with an eligible DBE firm or demonstrate good faith effort. 
When a subcontract is executed with the DBE firm before the Department notified the firm of its 
ineligibility, the consultant may continue to use the firm on the contract and may continue to 
receive credit toward the DBE goal for the firm’s work. 
 
17.04   
Notifying the Consultant of DBE Certification Status: 
 
Each DBE contract at any tier shall require any DBE subconsultant or supplier that is either 
decertified or certified during the term of the contract to immediately notify the consultant and 
all parties to the DBE contract in writing, with the date of decertification or certification. The 
consultant shall require that this provision be incorporated in any contract of any tier in which a 
DBE is a participant. 
 
17.05  
Police Officers: 
 
DBE credit will not be permitted for procuring DPS officers.  For projects on which officers from 
other agencies are supplied, DBE credit will be given only for the broker fees charged, and will 
not include amounts paid to the officers.  The broker fees must be reasonable. 
 
17.06  
Commercially Useful Function: 
 
A prime consultant can credit expenditures to a DBE subconsultant toward DBE goals only if 
the DBE performs a Commercially Useful Function (CUF). 
 
A DBE performs a CUF when it is responsible for execution of the work of a contract and 
carries out its responsibilities by actually performing, managing, and supervising the work 
involved.  To perform a commercially useful function, the DBE must also be responsible, with 
respect to materials and supplies on the contract, for negotiating price, determining quality and 
quantity, ordering the material, and installing (where applicable) and paying for the material 
itself that it uses on the project.  To determine whether a DBE is performing a commercially 
useful function, the LPA/Subrecipient will evaluate the amount of work subcontracted, industry 
practices, whether the amount the firm is to be paid under the contract is commensurate with 
the work it is actually performing and the DBE credit claimed for its performance of the work, 
and other relevant factors. 
 
A DBE will not be considered to perform a commercially useful function if its role is limited to 
that of an extra participant in a transaction, contract, or project through which funds are passed 
in order to obtain the appearance of DBE participation.  In determining whether a DBE is such

Professional Services DBE Special Provisions 06/23/2016 
LPA PS EPRISE GOAL - 17/23 
an extra participant, the LPA/Subrecipient will examine similar transactions, particularly those 
in which DBEs do not participate. 
 
If a DBE does not perform or exercise responsibility for at least 30 percent of the total cost of 
its contract with its own work force, or if the DBE subcontracts a greater portion of the work of 
a contract than would be expected on the basis of normal industry practice for the type of work 
involved, LPA/Subrecipient will presume that the DBE is not performing a commercially useful 
function. 
 
When a DBE is presumed not to be performing a commercially useful function as provided 
above, the DBE may present evidence to rebut this presumption.  The Department will 
determine if the firm is performing a CUF given the type of work involved and normal industry 
practices. 
 
The LPA/Subrecipient will notify the consultant, in writing, if it determines that the consultant’s 
DBE subconsultant is not performing a CUF.  The consultant will be notified within seven 
calendar days of the LPA/Subrecipient’s decision. 
 
Decisions on CUF may be appealed to the ADOT BECO.  The appeal must be in writing and 
personally delivered or sent by certified mail, return receipt requested, to the ADOT BECO.  
The appeal must be received by ADOT BECO no later than seven calendar days after the 
LPA/Subrecipient’s decision.  LPA/Subrecipient’s decision remains in place unless and until 
the ADOT BECO reverses or modifies LPA/Subrecipient’s decision. ADOT BECO will promptly 
consider any appeals under this subsection and notify the consultant of the ADOT BECO 
findings and decisions.  Decisions on CUF matters are not administratively appealable to 
USDOT. 
 
The LPA/Subrecipient may conduct project site visits on the contract to confirm that DBEs are 
performing a CUF. The consultant shall cooperate during the site visits and the 
LPA/Subrecipient staff will make every effort not to disrupt work on the project. 
 
18.0   
Effect of Contract Changes: 
 
The consultant acknowledges that uncertainties can occur during the performance of the work 
and if for any reason it becomes apparent that the DBE goal will not be met then the consultant 
shall:  (1) immediately notify the LPA/Subrecipient of the potential or actual decrease in DBE 
compensation, and (2) make good faith efforts to obtain DBE participation to meet or exceed 
the project DBE goal. Good faith efforts required under the provisions of this section may vary, 
depending on the time available, the nature of the change, and other factors as determined 
by LPA/Subrecipient. 
 
LPA/Subrecipient will approve or deny the consultant’s good faith efforts with BECO 
concurrence.  
 
The consultant is not required to take work committed to another subconsultant and assign it to 
a DBE subconsultant in order to meet the committed DBE percentage.

Professional Services DBE Special Provisions 06/23/2016 
LPA PS EPRISE GOAL - 18/23 
 
If the resulting change increases the scope or quantity of work being done by a DBE 
subconsultant, the DBE shall be given the opportunity to complete the additional work and 
receive additional compensation beyond their original subcontract amount. 
 
19.0   
DBE Participation Above the Goal (Race-Neutral Participation): 
 
Additional DBE participation above the DBE participation required to meet the contract DBE goal 
is an important aspect of the Department’s DBE program. The consultant is strongly encouraged 
to use additional DBEs above the DBE goal requirement in the contract to assist the Department 
in meeting its overall DBE goal and help the Department to meet the maximum feasible portion 
of its DBE goals through race neutral participation as outlined in 49 CFR Part 26. 
 
There are fewer administrative requirements on the part of the consultant when using race 
neutral DBEs (DBEs not listed on the DBE Intended Participation Affidavit Summary). For 
example, if a DBE is not listed on the DBE Intended Participation Affidavit Summary, the DBE 
does not have to submit an Affidavit, and the subcontract approval process follows the same 
process of any other subcontract. The consultant does not have to replace the DBE with another 
DBE subconsultant if the DBE fails to perform. Therefore these DBEs are treated as any other 
subconsultant on the project. 
 
20.0  
Required Provisions for DBE Subcontracts: 
 
All subcontracts of any tier, all supply contracts, and any other contracts in which a DBE is a 
participant shall include as a physical attachment, DBE Subconsultant Compliance Assurances 
available from the LPA/Subrecipient and all of the Uniform Terms and Conditions set forth in 
other sections of this contract. 
 
Consultants executing agreements with subconsultants, DBE or non-DBE, that materially 
modify federal regulation and state statutes such as, prompt payment and retention 
requirements, through subcontract terms and conditions will be found in breach of contract 
which may result in termination of the contract, or any other such remedy as the 
LPA/Subrecipient and ADOT deem appropriate as outlined in DBE Subsection 2.0. 
 
The LPA/Subrecipient reserves the right to conduct random reviews of DBE and non-DBE 
subcontract documentation to ensure compliance with federal requirements. 
 
The consultant shall ensure that all subcontracts or agreements with DBEs to supply labor or 
materials require that the subcontract and all lower tier subcontracts be performed in accordance 
with 49 CFR Part 26 provisions. 
 
The Consultant shall provide electronic copies of signed subcontract agreements for all DBE 
Subconsultants listed on the DBE Intended Participation Affidavit Summary by uploading them 
within 15 calendar days of an approved contract to the LPA DBE System.

Professional Services DBE Special Provisions 06/23/2016 
LPA PS EPRISE GOAL - 19/23 
 
21.0  
Contract Performance: 
 
Contract items of work designated by the consultant to be awarded to DBEs shall be 
performed by the designated DBE or a LPA/Subrecipient, with BECO concurrence, approved 
DBE substitute.  The Consultant or a non-DBE Subconsultant shall not perform DBE contract 
work items without prior approval by LPA/Subrecipient, with BECO concurrence. The DBE 
must perform a commercially useful function; that is, the DBE must manage, perform, and 
supervise a distinct element of work. 
 
The consultant is required to use DBEs identified in the SOQ to meet the contract goal, so the 
prime consultant is responsible for ensuring that the DBEs are available to meet scheduling, 
work and other requirements on the contract.  
 
The LPA/Subrecipient will visit the consultant’s office to conduct reviews to ensure compliance 
with CUF and other DBE requirements.  The reviews may include, among other activities, 
interview of DBEs and their employees and the consultant and its employees.  The consultant 
shall cooperate in the review and make its employees available.  The consultant shall inform 
the LPA/Subrecipient in advance when each DBE will be working on the project to help 
facilitate reviews. 
 
The LPA/Subrecipient reserves the right to request and inspect all records of the consultant 
and all records of the DBEs and non-DBE subconsultants concerning this contract.  The 
consultant must make available a copy of all documents related to all contracts the 
LPA/Subrecipient upon request. 
 
Use of every DBE listed on the DBE Intended Participation Affidavit Summary is a condition of 
this contract. The consultant shall utilize the specific DBEs listed to perform the work and 
supply the materials for which each is listed on the DBE Intended Participation Affidavit 
Summary unless the consultant obtains written consent from the LPA/Subrecipient with BECO 
concurrence. The consultant shall not be entitled to any payment for work or material that is 
not performed or supplied by the listed DBE unless the consultant obtains written consent from 
the LPA/Subrecipient with BECO concurrence. 
 
22.0  
DBE Termination/Substitution: 
 
22.01  
General Requirements: 
 
The consultant shall make all reasonable efforts to avoid terminating or substituting a DBE 
listed on the DBE Intended Participation Affidavit Summary. At a minimum, the consultant shall 
negotiate in good faith, give timely notices and/or extend deadlines to the extent that it will not 
jeopardize the contract with the LPA/Subrecipient. Reasonable methods to resolve 
performance disputes must be applied and documentation provided to the LPA/Subrecipient 
before attempting to substitute or terminate a DBE.

Professional Services DBE Special Provisions 06/23/2016 
LPA PS EPRISE GOAL - 20/23 
 
22.02  
Consultant Notice of Termination/Substitution: 
 
All terminations, substitutions, and reductions in scope of work to be performed by DBEs listed 
on the DBE Intended Participation Affidavit Summary must be approved in writing by the 
LPA/Subrecipient, with BECO concurrence and by means of the executed contract 
modification. The consultant shall contact the LPA/Subrecipient within 24 hours from the first 
sign of any reason for potential DBE termination/substitution. 
 
The consultant shall not terminate a DBE subconsultant listed on the DBE Intended 
Participation Affidavit Summary or complete the work contracted to the DBE with its own forces 
or with a non-DBE firm without the LPA/Subrecipient written consent and BECO concurrence. 
Before submitting a formal request to the LPA/Subrecipient for DBE termination/substitution, 
the consultant shall give written notice to the DBE subconsultant with a copy to the 
LPA/Subrecipient of its intent to terminate or substitute the DBE identifying the reason for the 
action.  The DBE shall be allowed a minimum of five calendar days to respond to the 
consultant’s notice advising the consultant, the LPA/Subrecipient of its position. Before making 
a determination for approval regarding the consultant’s termination and substitution request, 
the LPA/Subrecipient, with BECO concurrence, will consider both the consultant’s request and 
the DBE firm’s response. 
 
22.03  
Consultant Request of Termination/Substitution:  
 
The consultant shall formally request the termination or substitution of a DBE listed on the DBE 
Intended Participation Affidavit Summary by submitting the DBE Termination/Substitution 
Request Form and supporting documentation to the LPA/Subrecipient; form is available from 
the LPA/Subrecipient. The submission shall include the following information: 
 
1) The date the consultant determined the DBE to be unwilling, unable or ineligible to 
perform. 
2) A brief statement of facts describing the situation and citing specific actions or 
inaction by the DBE firm giving rise to consultant’s assertion that the DBE firm is 
unwilling, unable, or ineligible to perform. 
3) A brief statement of the good faith efforts undertaken by the consultant to enable the 
DBE firm to perform. 
4) The total dollar amount currently paid for work performed by the DBE firm. 
5) The total dollar amount remaining to be paid to the DBE firm for work completed, but 
for which the DBE firm has not received payment, and over which the consultant and 
the DBE firm have no dispute.  
6) The remaining work that has not been completed by the DBE and the corresponding 
dollar amount 
7) The projected date that the consultant requires a substitution or replacement DBE to 
commence work, if consent is granted to the request. 
 
Written consent for terminating the performance of any DBE listed on the DBE Intended 
Participation Affidavit Summary will be granted only where the consultant can demonstrate

Professional Services DBE Special Provisions 06/23/2016 
LPA PS EPRISE GOAL - 21/23 
good cause showing that the DBE is unable, unwilling, or ineligible to perform. Such written 
consent to terminate any DBE shall concurrently constitute written consent to substitute or 
replace the terminated DBE. Termination or substitution of a DBE listed on the DBE Intended 
Participation Summary will not be allowed based solely on a consultant's ability to negotiate a 
more advantageous contract with another subconsultant.  Prior to making a determination for 
approval regarding the consultant’s termination and substitution request, the LPA/Subrecipient, 
with BECO concurrence, will consider both the consultant’s request and the DBE firm’s 
response. 
 
Any requests for substitutions or terminations of DBEs shall be made on the forms provided 
by LPA/Subrecipient. 
 
22.04  
Good Cause:  
 
The LPA/Subrecipient, with BECO concurrence, will make the determination of good cause by 
providing written consent to the consultant after evaluating the consultant’s good cause to 
terminate or substitute a DBE firm. Good cause for this purpose includes the following in 
relation to the listed DBE subconsultant: 
 
1. Fails or refuses to execute a written contract. 
2. Fails or refuses to perform the work of its subcontract in a way consistent with normal 
industry practice standards. However, good cause does not exist if the failure or refusal 
of the DBE subconsultant to perform its work on the subcontract results from the bad 
faith or discriminatory action of the prime consultant. 
3. Fails or refuses to meet the prime consultant’s reasonable, nondiscriminatory 
insurance/bond requirements. 
4. Becomes bankrupt, insolvent, or exhibits credit unworthiness. 
5. Is ineligible to work on public works projects because of suspension and debarment 
proceedings pursuant to federal or state law. 
6. Is not a responsible consultant. 
7. Voluntarily withdraws from the project and provides written notice of its withdrawal to the 
LPA/Subrecipient. 
8. Is ineligible to receive DBE credit for the type of work required 
9. A DBE owner dies or becomes disabled with the result that the firm is unable to 
complete its work on the contract. 
10. Other documented good cause that the LPA/Subrecipient determines compels the 
termination or substitution of the DBE subconsultant. 
 
If good cause is determined, the LPA/Subrecipient and will notify the Consultant of the decision 
and necessary modifications to the contract can be made. 
 
22.05  
DBE Replacement Good Faith Effort:  
 
If the LPA/Subrecipient, with BECO concurrence, approves the termination of a DBE, the 
consultant shall make good faith efforts to find another DBE subconsultant to substitute for the 
original DBE. The good faith efforts as identified in DBE Subsection 17.0 shall be directed at

Professional Services DBE Special Provisions 06/23/2016 
LPA PS EPRISE GOAL - 22/23 
finding another DBE to perform at least the same amount of work under the contract as the 
DBE that was terminated, to the extent needed to meet the contract goal. The good faith 
efforts shall be documented and provided, upon request, to the LPA/Subrecipient within seven 
calendar days from the date of the request.  
 
A prime consultant’s inability to find a replacement DBE at the original price is not alone 
sufficient to support a finding that good faith efforts have been made to replace the original 
DBE. The fact that the consultant has the ability and/or desire to perform the contract work with 
its own forces does not relieve the consultant of the obligation to make good faith efforts to find 
the replacement DBE, and it is not a sound basis for rejecting a perspective replacement 
DBE’s reasonable quote. 
 
The termination of a DBE firm shall not relieve the consultant of its obligations under this 
Special Provision, and the unpaid portion of the terminated DBE firm’s subcontract will not be 
counted toward the DBE goal. If the LPA/Subrecipient has eliminated items of work 
subcontracted to a committed DBE, the prime consultant shall still make good faith efforts to 
replace the DBE with another DBE to the extent necessary to meet the goal. The 
LPA/Subrecipient will review the quality, thoroughness, and intensity of those efforts. 
 
When a DBE substitution has been approved by the LPA/Subrecipient and concurred by 
BECO, the consultant shall submit an amended DBE Intended Participation Affidavit Individual 
and Intended Participation Affidavit Summary to the LPA/Subrecipient for approval with the 
substitute DBE's name, description of work, NAICS code, AZ UTRACS registration number, 
and dollar value of work. Approval from LPA/Subrecipient with BECO concurrence must be 
obtained prior to the execution of a contract modification and before substituted DBE can begin 
work. 
 
22.06  
Sanctions: 
 
 
Failure by the consultant to carry out the requirements of these DBE Termination/Substitution 
specifications is a material breach of contract and will result in such remedies as 
LPA/Subrecipient deems appropriate, with ADOT concurrence, which will include, but are not 
limited to the assessment of liquidated damages. The LPA/Subrecipient will deduct from 
monies due or becoming due the consultant, the dollar amount of the wrongfully 
substituted/replaced DBE subcontract plus 25% of the amount remaining to be paid to the DBE 
as liquidated damages. These liquidated damages shall be in addition to all other retention or 
liquidated damages provided for elsewhere in the contract. 
 
23.0    
Certification of Final DBE Payments: 
 
The consultant’s achievement of the goal is measured by actual payments made to the DBEs.  
The consultant shall submit the “Certification of Final DBE Payments” form for each DBE firm 
working on the contract. This form shall be signed by the consultant and the relevant DBE, and 
submitted to the LPA/Subrecipient no later than 30 days after the DBE completes its work.  
 
The LPA/Subrecipient and ADOT will use this certification and other information available to 
determine applicable DBE credit allowed to date by the Prime Consultant and the extent to

Professional Services DBE Special Provisions 06/23/2016 
LPA PS EPRISE GOAL - 23/23 
which the DBE firms were fully paid for that work. By the act of filing the forms, the consultant 
acknowledges that the information is supplied in order to justify the payment of state and 
federal funds to the consultant. 
 
The consultant will not be released from the obligations of the contract until the “Certification of 
Final DBE Payments” forms are received and deemed acceptable by the LPA/Subrecipient.  
 
24.0  
Sanctions for Not Meeting Contract DBE Goal: 
 
If the LPA/Subrecipient determines, with BECO concurrence, that the consultant has not met 
the DBE goal at the end of the contract, the LPA/Subrecipient will, at its discretion, may assess 
liquidated damages up to two times the amount of the unattained portion of the original DBE 
goal, based on the circumstances of the noncompliance. Not meeting the DBE goal will also be 
reflected in the consultant evaluation. 
 
The LPA/Subrecipient, with BECO concurrence, will determine whether liquidated damages 
will be assessed and the amount of the liquidate damages, the LPA/Subrecipient will consider 
whether there have been other violations on this or other contracts, whether the failure was 
due to circumstances beyond the control of the consultant, whether the consultant has made 
good faith efforts to meet the goal, and other appropriate circumstances. 
 
In addition to any other sanctions, willful failure of the consultant, DBE or other subconsultant 
to comply with this contract or with the Federal DBE regulations may result in disqualification 
from further contracting, subcontracting, or other participation in the Department’s and 
LPA/Subrecipient projects. 
 
25.0   
False, Fraudulent, or Dishonest Conduct: 
 
In addition to any other remedies or actions, the Department will bring to the attention of the 
US Department of Transportation any appearance of false, fraudulent, or dishonest conduct in 
connection with the DBE program, so that USDOT can take steps such as referral to the 
Department of Justice for criminal prosecution, referral to the USDOT Inspector General for 
possible initiation of suspension and debarment proceedings against the offending parties or 
application of “Program Fraud and Civil Penalties” rules provided in 49 CFR Part 31.

11.0 
DBE  
FORMS/DOCUMENTS 
-
INSTRUCTIONS / GUIDE
-
BIDDERS PROPOSER LIST INSTRUCTIONS
-
DBE FORM 3212PS
-
DBE FORM 3206PS
-
DBE FORM 3205PS
-
DBE FORM 3210PS
-
DBE FORM 3108C
-
DBE FORM 3203PS

Rev 2023-11-16 
DBE Documents Instructions/Guide 
Race Conscious DBE Goal % Assessed For This Contract 
 
*Important Note: City of Chandler DBE Forms and ADOT DBE Forms are not always the same.  The forms provided with the 
RFQ/Contract must be used. Do not go to ADOT Website to obtain DBE Forms (Forms 3212PS, 3206PS, 3205PS, 3203PS, 
3210PS, 3208PS). Also, forms are updated at unspecified dates.  Do not use previously saved City of Chandler forms. 
 
SUBMIT WITH SOQ: 
Bidders –Proposers List 
This is an ADOT On Line Submittal Process.   
 
 
 
An Email Verification / Confirmation will be 
 
 
 
provided to you by the system after you submit. 
 
 
 
A copy of this Email Verification is the document 
 
 
 
that must be submitted with SOQ.  
 
 
 
 
DBE Form 3212PS DBE Assurance 
Fill out, sign, and submit with SOQ. 
 
----------------------------------------------------------------------------------------------------------------------------- -------- 
SUBMIT AT SCOPE & FEE FINALIZATION: 
DBE Form 3206PS 
At Scope & Fee Finalization. 
Consultant Participation Affidavit 
To be filled out and submitted to 
 
 
 
City of Chandler Federal Compliance 
 
 
 
for approval packet that will be submittal 
 
 
 
to ADOT BECO. 
 
DBE Form 3205PS 
At Scope & Fee Finalization. 
Subconsultant Participation Affidavit 
To be filled out and submitted to 
 
 
 
City of Chandler Federal Compliance 
 
 
 
for approval packet that will be submittal 
 
 
 
to ADOT BECO.   
 
*note: A packet of all DBE documentation is prepared and submitted to ADOT BECO by City of Chandler.  This  
DBE Packet must be approved by ADOT BECO prior to City of Chandler Council Date for approval of the contract. 
----------------------------------------------------------------------------------------------------------------------------- --------- 
SUBMIT AS APPLICABLE: 
DBE Form 3203PS Good Faith 
To be submitted at any time Consultant  
 
  
 
determines that the DBE Goal will be 
 
  
 
unobtainable.  This can be submitted with SOQ, 
 
  
 
or submitted at Scope and Fee. 
 
DBE Form 3210PS – Final Payment 
This DBE Form is required for every DBE 
 
 
 
Subconsultant, whether or not listed as 
 
 
 
the dedicated DBE of 3206PS and/or whether 
 
 
 
or not there is a DBE Goal Assessment for 
 
 
 
this contract. 
 
 
 
 
 
DBE Form 3108C  
At any time throughout the life of the contract, 
 
DBE Substitution/Termination 
a designated contract goal DBE subconsultant 
 
 
 
(from Forms 3206PS) needs to be substituted 
 
 
 
or terminated, immediately notify the City of 
 
 
 
Chandler Federal Compliance to start the  
 
 
 
Federal required process - Form 3108C 
 
 
 
and other backup documents will be required.  
----------------------------------------------------------------------------------------------------------------------------- ------------ 
 
Important Note: 
The “Joint Check” process – where the Prime pays a subconsultant’s lower tier or vendor – is not 
allowed by ADOT BECO on FHWA Federal Funded Professional Services contracts.

BIDDERS/PROPOSERS LIST 
 
FEDERAL DOCUMENT REQUIRED:  Email Verification Print Out 
 
Email Verification Print Out Received from Utracs/AzDOT.gov confirms your electronic submittal Of 
Bidders/Proposers List.  The email confirmation should be a submitted document.  Do not forward the 
email. 
Caution: This email originated outside the organization. Do not click links or open attachments unless you recognize
the sender and know the content is safe.
From:
ADOT Business Engagement and Compliance Office
To:
Carla Silvernale
Cc:
ContractorCompliance@azdot.gov
Subject:
Bidders List for Consultant Engineering, Inc.
Date:
Monday, July 22, 2024 10:53:56 AM
Consultant Engineering, Inc., AZUTRACS Number: 10192 has submitted a Bidder/Proposer list for T020301C-CM on
07/22/2024 at 10:53 AM MST (UTC - 07:00). 
Bidders/Proposers for this firm include:
Firm
Name
AZUTRACS
#
Expiration
Date
Email
Address
Phone
Number
ATEK Engineering Consultants, LLC.
11395
08/31/2025
aortega@atekec.com
480-659-
8065
Mak Pro Services LLC
10670
10/05/2025
teresa@makprosvc.com
602-421-
3069
Quality Testing, LLC
10910
02/20/2027
bizdev@qt-az.com
480-496-
2000
Tristar Engineering and Management, Inc.
11222
11/15/2025
jakin@tristar-az.com
602-568-
4661

_______________________
PROFESSIONAL SERVICES  
PROJECT SPECIFIC CONTRACT 
BECO Form 3212PS (Rev. 9-1-16) 
Disadvantaged Business Enterprise (DBE) 
Goal Assurance 
ADOT TRACS No.: 
Agency Project/Contract No.: 
Project Name:  
Prime:  
AZ UTRACS Vendor #: 
The undersigned, fully cognizant of the requirements and of the goal established, hereby certifies that in 
the preparation of the proposal for the above stated federal aid project, 
THIS CERTIFICATE MAY NOT BE REVISED OR CORRECTED AFTER SUBMISSION OF THE PROPOSAL. 
FAILURE TO AFFIRMATIVELY MAKE THIS DECLARATION/CERTIFICATION IN THE MANNER OUTLINED IN THE 
REQUEST FOR QUALIFICATIONS (RFQ) FURNISHED BY THE LPA/SUBRECIPIENT WILL CAUSE A PROPOSER’S SOQ 
TO BE CONSIDERED NON-RESPONSIVE. 
(Name of Authorized Officer) 
(Title) 
(Authorized Officer Signature) 
(Date) 
☐ the Proposer will meet the established DBE goal or will make good faith efforts to meet the goal 
for the contract and that arrangements with certified DBEs have been made prior to the SOQ 
   and/or cost proposal submission.
CITY OF CHANDLER
T020301C
ST1804.451
Construction Management Services, Chandler Heights - Gilbert Road to Val Vista Drive
Consultant Engineering, Inc.
10192
Brian C. Lizzet, PE
Sr. Vice President
7/24/2024

N/A
N/A
$10,071.10
9/11/2024
The DBE firm will be performing the scope as described above for a DBE credit of

Date contacted:  
Prime Contact Name:  
Brief summary of discussion and resolution: 
PROFESSIONAL SERVICES/DESIGN  
CERTIFICATION OF GOOD FAITH EFFORTS 
Submit completed GFE Form (pages 1 – 6 only) with backup documentation, if any) 
1 
BECO  Form 3203PS (Rev. 1-4-2017) 
General 
Complete all sections of the form and include all back-up documentation. Incomplete forms will be returned unprocessed.  For the 
purpose of this form, project specific contracts shall be evaluated on a contract basis and on-call contracts will be evaluated on a task 
order by task order basis.  For on-call contracts, consultants must complete this form by detailing efforts made to find additional 
DBEs if their current DBEs are unable to perform the work needed for this task order.  If the information does not relate to the task
order in review, this GFE will be denied.  The Agency reserves the right to request further documentation from the Consultant/
Subconsultant(s) to support and validate actions undertaken to secure DBE participation to meet the DBE goal for this contract/task 
order.   
Attestation 
I, (Name) 
, do hereby acknowledge that I am the (Title) 
of (Name of Firm) 
and the Consultant selected for the Agency project listed below:
Contract No. 
Mod 
No. 
Task 
Order 
No. 
TRACS No. 
Project Name 
Total 
Contract/Task 
Amount * 
DBE Percentage 
Contract 
Goal 
Committed 
Goal 
* Total Contract/Task Amount must include any previous amounts of the Contract or Task Order.
Provide a brief summary on why you believe your firm is unable to meet the DBE participation goals on this contract/task order.  
Attach additional pages if necessary. 
I hereby certify I demonstrated comprehensive good faith efforts to solicit and utilize DBE firms to meet the DBE participation 
requirements of this contract/task order in accordance with Section 14.0 of the LPA DBE Contract Specifications by my responses to
the following: 
GFE Activities 
1.
Contacting Agency and BECO For Assistance
Agency Staff contacted:
  Phone Number: 
Was a DBE Supportive Services Solicitation Request submitted?  
 Yes 
 No      Submission Date 
BECO Staff contacted:
  Phone Number: 
  City of Chandler

PROFESSIONAL SERVICES/DESIGN  
CERTIFICATION OF GOOD FAITH EFFORTS 
Submit completed GFE Form (pages 1 – 6 only) with backup documentation, if any) 
2 
BECO  Form 3203PS (Rev. 1-4-2017) 
2.
Market Research and Soliciting Through All Reasonable Means
List all DBE solicitations made for this contract/task order.
Solicitation Activity 
Date 
Name of Interested DBEs 
Follow-Up Date 
3.
Selecting Portions of Work to be Performed by DBEs
List work items needed to be performed and include how work items were broken down into economically feasible units to
facilitate DBE participation.
4.
Provide Interested DBEs With Project Information
Explain how interested DBEs were provided with access to project information.

PROFESSIONAL SERVICES/DESIGN  
CERTIFICATION OF GOOD FAITH EFFORTS 
Submit completed GFE Form (pages 1 – 6 only) with backup documentation, if any) 
3 
BECO  Form 3203PS (Rev. 1-4-2017)
5.
Negotiate In Good Faith With Interested DBEs – When a non-DBE is selected over a DBE, attach copies of the DBE and non-DBE
firms’ quotes.
A.
Identify DBE firms in which negotiations were considered but were unsuccessful.
DBE Firm Name & Contact Person 
Address 
Phone Number 
B.
Explain why negotiations above were unsuccessful.
DBE Firm Name 
Explanation 
6.
Having Sound Reason For Rejecting DBEs
Explain why any DBE(s) was rejected for being unqualified.
DBE Firm Name 
Explanation

PROFESSIONAL SERVICES/DESIGN  
CERTIFICATION OF GOOD FAITH EFFORTS 
Submit completed GFE Form (pages 1 – 6 only) with backup documentation, if any) 
4 
BECO  Form 3203PS (Rev. 1-4-2017) 
7.
Assisting Interested DBEs – Bonding, Credit, Insurance
Identify interested DBE firms in which assistance was provided in obtaining bonding, credit or insurance.
DBE Firm Name 
Assistance Offered 
8.
Assisting Interested DBEs – Equipment, Supplies, Materials, Related Services
Identify interested DBE firms in which assistance was provided in obtaining necessary equipment, supplies, materials, or related
assistance or services.
DBE Firm Name 
Assistance Offered 
9.
Minority/Women Community Organizations
Identify minority/women community organizations used for providing assistance in the recruitment and placement of DBEs.
Organization Name 
Contact Person 
Assistance Requested

PROFESSIONAL SERVICES/DESIGN  
CERTIFICATION OF GOOD FAITH EFFORTS 
Submit completed GFE Form (pages 1 – 6 only) with backup documentation, if any) 
5 
BECO  Form 3203PS (Rev. 1-4-2017) 
This is not intended to be a mandatory checklist nor is it intended to be an exclusive or exhaustive list of good faith efforts. Other 
factors or types of efforts may be relevant on a case-by-case basis as determined by ADOT BECO. 
10. Other comments or information you want the Agency and ADOT BECO to consider as part of your good faith effort.
Affidavit 
The undersigned, (Name) ______________________________________, attest and declare under penalty of perjury in the second 
degree, and any other applicable state or federal laws, that the information provided on this certificate is true and correct to the 
best of my knowledge and belief. 
Signature: 
_____________________________________ 
Date: 
________________________________ 
Consultant Representative/DBE Liaison 
Note: 
The GFE form must be signed by an authorized signatory for the Consultant/Subconsultant. 
AGENCY/BECO INTERNAL USE ONLY
Date Received: 
_________________  
Date Approved / Denied: _________________  (Circle one) 
Received by: _________________________________________ 
Signature: 
__________________________________________ 
Comments: 
Date Received: 
_________________  
Date Approved / Denied: _________________  (Circle one) 
Received by: _________________________________________ 
Signature: 
__________________________________________ 
SIGN
SIGN

PROFESSIONAL SERVICES/DESIGN  
CERTIFICATION OF GOOD FAITH EFFORTS 
Submit completed GFE Form (pages 1 – 6 only) with backup documentation, if any) 
6 
BECO  Form 3203PS (Rev. 1-4-2017) 
APPENDIX A TO PART 26 — GUIDANCE CONCERNING GOOD FAITH EFFORTS 
Note: 
“YOU” means the Agency (ADOT) in the following sections of this requirement.
I.
When, as a recipient, you establish a contract goal on a DOT-assisted contract for procuring construction, equipment,
services, or any other purpose, a bidder must, in order to be responsible and/or responsive, make sufficient good faith efforts
to meet the goal. The bidder can meet this requirement in either of two ways. First, the bidder can meet the goal,
documenting commitments for participation by DBE firms sufficient for this purpose. Second, even if it doesn't meet the goal,
the bidder can document adequate good faith efforts. This means that the bidder must show that it took all necessary and
reasonable steps to achieve a DBE goal or other requirement of this part which, by their scope, intensity, and appropriateness
to the objective, could reasonably be expected to obtain sufficient DBE participation, even if they were not fully successful.
II.
In any situation in which you have established a contract goal, Part 26 requires you to use the good faith efforts mechanism of
this part. As a recipient, you have the responsibility to make a fair and reasonable judgment whether a bidder that did not
meet the goal made adequate good faith efforts. It is important for you to consider the quality, quantity, and intensity of the
different kinds of efforts that the bidder has made, based on the regulations and the guidance in this Appendix.
The efforts employed by the bidder should be those that one could reasonably expect a bidder to take if the bidder were
actively and aggressively trying to obtain DBE participation sufficient to meet the DBE contract goal. Mere pro forma efforts
are not good faith efforts to meet the DBE contract requirements. We emphasize, however, that your determination
concerning the sufficiency of the firm's good faith efforts is a judgment call. Determinations should not be made using
quantitative formulas.
III.
The Department also strongly cautions you against requiring that a bidder meet a contract goal (i.e., obtain a specified
amount of DBE participation) in order to be awarded a contract, even though the bidder makes an adequate good faith efforts
showing. This rule specifically prohibits you from ignoring bona fide good faith efforts.
IV.
The following is a list of types of actions which you should consider as part of the bidder's good faith efforts to obtain DBE
participation. It is not intended to be a mandatory checklist, nor is it intended to be exclusive or exhaustive. Other factors or
types of efforts may be relevant in appropriate cases.
A.
(1)  Conducing market research to identify small business contractors and suppliers and soliciting through all reasonable
and available means the interest of all certified DBEs that have the capability to perform the work of the contract. 
This may include attendance at pre-bid and business matchmaking meetings and events, advertising and/or written 
notices, posting of Notices of Sources Sought and/or Requests for Proposals, written notices or emails to all DBEs 
listed in the State's directory of transportation firms that specialize in the areas of work desired (as noted in the DBE 
directory) and which are located in the area or surrounding areas of the project. 
(2)
The bidder should solicit this interest as early in the acquisition process as practicable to allow the DBEs to respond
to the solicitation and submit a timely offer for the subcontract. The bidder should determine with certainty if the
DBEs are interested by taking appropriate steps to follow up initial solicitations.
B.
Selecting portions of the work to be performed by DBEs in order to increase the likelihood that the DBE goals will be
achieved. This includes, where appropriate, breaking out contract work items into economically feasible units (for
example, smaller tasks or quantities) to facilitate DBE participation, even when the prime contractor might otherwise
prefer to perform these work items with its own forces. This may include, where possible, establishing flexible
timeframes for performance and delivery schedules in a manner that encourages and facilitates DBE participation.

PROFESSIONAL SERVICES/DESIGN 
CERTIFICATION OF GOOD FAITH EFFORTS 
Submit completed GFE Form (pages 1 – 6 only) with backup documentation, if any) 
7 
BECO  Form 3203PS (Rev. 1-4-2017) 
C.
Providing interested DBEs with adequate information about the plans, specifications, and requirements of the contract in
a timely manner to assist them in responding to a solicitation with their offer for the subcontract.
D.
(1)  Negotiating in good faith with interested DBEs. It is the bidder's responsibility to make a portion of the work
available to DBE subcontractors and suppliers and to select those portions of the work or material needs consistent 
with the available DBE subcontractors and suppliers, so as to facilitate DBE participation. Evidence of such 
negotiation includes the names, addresses, and telephone numbers of DBEs that were considered; a description of 
the information provided regarding the plans and specifications for the work selected for subcontracting; and 
evidence as to why additional Agreements could not be reached for DBEs to perform the work. 
(2)
A bidder using good business judgment would consider a number of factors in negotiating with subcontractors,
including DBE subcontractors, and would take a firm's price and capabilities as well as contract goals into
consideration. However, the fact that there may be some additional costs involved in finding and using DBEs is not
in itself sufficient reason for a bidder's failure to meet the contract DBE goal, as long as such costs are reasonable.
Also, the ability or desire of a prime contractor to perform the work of a contract with its own organization does not
relieve the bidder of the responsibility to make good faith efforts. Prime contractors are not, however, required to
accept higher quotes from DBEs if the price difference is excessive or unreasonable.
E.
(1) 
Not rejecting DBEs as being unqualified without sound reasons based on a thorough investigation of their
capabilities. The contractor's standing within its industry, membership in specific groups, organizations, or 
associations and political or social affiliations (for example union vs. non-union status) are not legitimate causes for 
the rejection or non-solicitation of bids in the contractor's efforts to meet the project goal. Another practice 
considered an insufficient good faith effort is the rejection of the DBE because its quotation for the work was not 
the lowest received. However, nothing in this paragraph shall be construed to require the bidder or prime 
contractor to accept unreasonable quotes in order to satisfy contract goals. 
(2)
A prime contractor's inability to find a replacement DBE at the original price is not alone sufficient to support a
finding that good faith efforts have been made to replace the original DBE. The fact that the contractor has the
ability and/or desire to perform the contract work with its own forces does not relieve the contractor of the
obligation to make good faith efforts to find a replacement DBE, and it is not a sound basis for rejecting a
prospective replacement DBE's reasonable quote.
F.
Making efforts to assist interested DBEs in obtaining bonding, lines of credit, or insurance as required by the recipient or
contractor.
G.
Making efforts to assist interested DBEs in obtaining necessary equipment, supplies, materials, or related assistance or
services.
H.
Effectively using the services of available minority/women community organizations; minority/women contractors'
groups; local, State, and Federal minority/women business assistance offices; and other organizations as allowed on a
case-by-case basis to provide assistance in the recruitment and placement of DBEs.
V.
In determining whether a bidder has made good faith efforts, it is essential to scrutinize its documented efforts. At a
minimum, you must review the performance of other bidders in meeting the contract goal. For example, when the
apparent successful bidder fails to meet the contract goal, but others meet it, you may reasonably raise the question of
whether, with additional efforts, the apparent successful bidder could have met the goal. If the apparent successful
bidder fails to meet the goal, but meets or exceeds the average DBE participation obtained by other bidders, you may
view this, in conjunction with other factors, as evidence of the apparent successful bidder having made good faith efforts.
As provided in §26.53(b)(2)((vi), you must also require the contractor to submit copies of each DBE and non-DBE
subcontractor quote submitted to the bidder when a non-DBE subcontractor was selected over a DBE for work on the
contract to review whether DBE prices were substantially higher; and contact the DBEs listed on a contractor's solicitation

PROFESSIONAL SERVICES/DESIGN 
CERTIFICATION OF GOOD FAITH EFFORTS 
Submit completed GFE Form (pages 1 – 6 only) with backup documentation, if any)  
8 
BECO  Form 3203PS (Rev. 1-4-2017) 
to inquire as to whether they were contacted by the prime. Pro forma mailings to DBEs requesting bids are not alone 
sufficient to satisfy good faith efforts under the rule. 
VI. A promise to use DBEs after contract award is not considered to be responsive to the contract solicitation or to constitute
good faith efforts.
[79 FR 59600, Oct. 2, 2014] 
Note: 
Contacting ADOT BECO (602 712-7761) for assistance in identifying certified DBEs that can perform work on a contract or 
task order is also considered a strong factor in making good faith efforts.

PROFESSIONAL SERVICES/DESIGN  
CERTIFICATION OF GOOD FAITH EFFORTS 
Submit completed GFE Form (pages 1 – 6 only) with backup documentation, if any) 
9 
BECO  Form 3203PS (Rev. 1-4-2017) 
Good Faith Efforts Tips 
The intent of the Good Faith Effort Form is to document the good faith efforts undertaken by the Consultant in soliciting and utilizing 
DBE firms to meet the DBE participation requirements for the contract/project. The completed form will assist the Agency and ADOT
in determining if the Consultant performed its due diligence, took all necessary and reasonable steps to secure DBE participation for 
the referenced contract/project and resulted in obtaining comprehensive good faith efforts.  The Agecny and ADOT Business
Engagement & Compliance Office (BECO) will determine if the Consultant made satisfactory good faith efforts to secure sufficient 
DBE participation to meet the DBE goal.  The burden of proof rests with the Consultant. Failure to provide good faith efforts to 
ADOT BECO’s satisfaction will result in the rejection of the proposal/modification.  However, ADOT BECO will reconsider 
Consultant’s GFE resubmittal if Consultant has adequately and sufficiently documented its good faith efforts in obtaining DBE 
participation.  
Tips for Documenting Good Faith Efforts 
1.
Review Scope of Work (SOW) for subcontracting opportunities.
2.
Make reasonable efforts to designate economically feasible and meaningful units of work for a DBE(s) that meets or
exceeds the DBE goal.
3.
Keep in mind that selected DBEs must perform commercially useful function (CUF) as required by 49 CFR §26.55.
4.
Determine if there are DBE firms on the contract team that can do the work.  If not, the Consultant must solicit other DBEs
through the DBE Directory to perform work to meet or exceed the goal.
5.
Some projects may be too small or do not provide meaningful units of work for subcontracting opportunities. Any reason
for this must be thoroughly explained.
6.
When providing good faith documentation, it is not good enough to say that project is too small to include DBEs.
Consultants must explain the project SOW and why no subcontracting opportunities are possible.
7.
Consultants must keep in mind that DBEs must be utilized when developing their SOWs and cost proposal.  Arranging and
planning work items to circumvent the utilization of Subconsultants and DBEs violates the federal regulations.
8.
For on-call contracts, consultants must complete this form by detailing efforts made to find additional DBEs if their current
DBEs are unable to perform the work needed for this task order.
9.
When providing good faith documentation, Consultants must include:
a.
Date, contact name of staff they contacted at BECO for assistance
b.
List of DBE firms contacted to do the work
c.
Any evidence of negotiations with the DBE firms
d.
Evidence of efforts to reach out to DBE firms
10. Assistance provided to DBEs should include efforts to assist the DBE firms in obtaining bonding, lines of credit, insurance,
equipment, materials, supplies or other project-related assistance.

12.0 
 
PAY REQUESTS 
 
 
 
- 
PAYMENT APPLICATION 
- 
SUBCONSULTANT SUMMARY FORM

Approved By:
Project Manager
Date
CIP Supervisor
Date
Revised: 4/14/23
Official City of Chandler Use Only
Authorized Signature
Date
Email PDF Signed Payment Application to: CapitalProjects.Payables@chandleraz.gov 
Or Submit to: City of Chandler, Capital Projects MS 407, PO Box 4008, Chandler, AZ 85244
PROFESSIONAL SERVICES AGREEMENT  
APPLICATION AND CERTIFICATION FOR
Budget Account #'s:
PO #:
 PAYMENT # _____  
Application is made for payment as shown below and on the 
attached Payment Schedule Summary Sheet in accordance with the 
Contract Documents.
Official City of Chandler
Use Only
Date Rec'd: _____________________
Record ID: ______________________
Date Recorded:_________________
Check if FINAL payment:
Consultant Information:
Name: _______________________________________________________   Invoice #:__________________________________ 
Remit to Address: _______________________________________________________________________________________________________________________ 
Contact Name: ___________________________________ Phone: __________________ Email Address: ___________________________________________
Project Name: ___________________________________________________________________________________________________________ 
Project No.: ____________________________ Federal/ADOT No. (if applicable): __________________________________________________ 
Pay Period Beginning: _______________  Ending: _______________  City Contact Name: ______________________________________ 
Total Time Elapsed: ___________%      
Contract Amendment Summary
No.  Date 
 Amount 
RED FIELDS AUTO CALCULATE 
Do not enter amount manually
Consultant's/Engineer's Certification
The undersigned certifies that the work covered by this Application for Payment has been completed in accordance with the Contract 
Documents; that all amounts have been paid for work which previous Certificates of Payment were issued and payments received from the Owner; 
and that the current payment requested as shown is current, accurate, and complete.  
1. Original Contract Price:
$__________________________________ 
2. Contract Amendments to Date:
$__________________________________
3. Adjusted Contract Price (Line 1 + 2):
$__________________________________
4. Total Amount Due to Date:
$__________________________________
(per attached Payment Schedule)
Work Completed to Date:__________%
5. Total Previous Certificates for Payment: $__________________________________
6. Federal Penalties if Applicable (per City):  $_________________________________
Deduct Penalties (-) or Credit Reimb (+)
7. Current Payment Due (Line 4 - 5 - or +6): $__________________________________
$
$
$
Calendar
Days
$
Notice to Proceed (NTP) Date:
Original Contract Duration:
Revised Contract Duration:
Contract Amendments:
Contract Expiration Date:
Contract Time Summary
(applicable milestones per contract)
Calendar Days
Calendar Days
Calendar Days
0.00
0.00
0.00
0.00
0
0

name
name
name
name
name
name
name
-
$            
-
$            
-
$            
-
$            
-
$                   
-
$           
-
$                  
Pay App 
#
Work Mo
Pay Mo
DBE Rpt 
Mo
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
-
$            
-
$            
-
$            
-
$            
-
$                   
-
$           
-
$            
-
$            
-
$            
-
$            
-
$                   
-
$           
Project Numbers
SUBCONSULTANT INVOICES/PAYMENT SUMMARY DETAIL
Consultant
Project Name
PROFESSIONAL SERVICES PAY APP BACKUP - (REQUIRED)
Total To Date
Bal Remaining
Month
Subconsultants
DBE->  YES / NO
Contract Amt
Change Order(s):
Total Contract:
Lower Tier --> (x)
Lower Tier to:

13.0 
SUBCONSULTANT SUBCONTRACTS REQUIREMENTS

Rev: 2023-04-10 
 
SUBCONSULTANTS – PROFESSIONAL SERVICES 
REQUIREMENTS AND SUBCONTRACTS 
 
 
1. Subconsultants will be required to be approved by the City.  Required forms will be provided. 
2. Subconsultants must have a current AZUTracs registration 5-digit number and current profile. 
https://utracs.azdot.gov/ 
3. Subconsultants must be registered/have a current/up to date profile in the DOORS reporting 
system for Payment Reporting, DBE Reporting, and Prompt Pay Reporting. (link is on the 
AZUTracs web page). 
4. Subconsultants (including lower tiers) will be required to report into the DOORs system on a 
monthly basis during the life of their subcontract. 
5. No Consultant/Subconsultant can work on a federal funded contract if they have been debarred 
and/or have unresolved federal tax liens.  
6. The “Joint Check” process – where a Prime pays a subconsultant’s lower tier or vendor is not 
allowed on FHWA Federal Funded Professional Services Contracts. 
7. DBE Subconsultants subcontract tasks must be applicable to their registered NAICS code(s). 
8. Subconsultants for QA/QC/IA Testing – must be on the ADOT Accredited Laboratories / ADOT 
Accredited Material Testing Laboratories List. 
https://azdot.gov/business/engineering-and-construction/materials/materials-quality-assurance/adot-accredited 
9. Subconsultants will be required to submit timely/monthly invoices to the Prime on a calendar 
monthly basis. The Prime Consultant’s monthly pay application to the City must include all work 
performed during the work period the pay application is being submitted for.   
10. No work can be started prior to the Prime’s Contract Notice to Proceed date. 
 
SUBCONTRACTS 
All Subcontracts: 
1. There are specific federal documents that must be included in all subcontracts.   
2. A set of these federal documents will be provided by the City.  There will be a required set of 
federal documents for a DBE Subconsultant Subcontract and a Non-DBE Subconsultant 
Subcontract. 
3. Subcontract tasks must be applicable to/related to the Prime’s Contract Task Detail with the City. 
4. DBE Subcontract Task Detail must show breakdown pricing for each task item. 
5. Subcontract must show both parties name and address.

END OF FEDERAL DOCUMENTS SECTION