Capital Projects – Design Phase:

West Airport Facilities Upgrade: City funded at $3.9 million.  Revised scope includes operations
garage, parking lot and aircraft observation area.  At 90% design.

Airport Fuel Tank Relocation: City funded at $610,000.  Cost negotiation with vendors.

Runway End Identifier Light (REIL) Installation Runway 4L-22R (North Runway): FAA funding for
$110,000.  Plans at 100%.  FAA environmental clearance received.

Runway 4R-22L Rehabilitation (South Runway): FAA grant for $350,000 for design approved.  Kick-
off meeting 4/6.  100% plans submitted.  Awaiting FAA notification of construction funding.

Taxiway B Improvements- Phase 1: ADOT grant for $2,035,000 approved.  FAA environmental
clearance received.  30% design meeting with ADOT 5/24.  100% sealed plans submittal on 9/27.
Proceeding to bid phase.

Hangar Area Pavement Rehabilitation:  City funded $7.4 million to redo pavement in and among the
city-owned hangars. Design Kick-off meeting 10/31. Goal for 100% plans by early March.
Capital Projects - Construction Phase:

Taxiway C Electrical:  City funding.  Addresses immediate issues with electrical infrastructure.  Cabling
and lighting system are functional but needs replacement.  7/18 preconstruction meeting.  9/4 meeting
for construction.  Construction underway and substantial completion scheduled for 11/20.

Automated Weather Observation System (AWOS) Replacement:  FAA funding for $200,000.  FAA
environmental clearance received.  Council approval on 6/13.  Precon meeting on 7/15 for long-lead
equipment procurement.  NTP issued 10/28.

Former K&K Site Remediation: City funding for soil remediation near end of Cooper Road north of
Queen Creek.  Mobilization starting on 7/8 with remediation originally scheduled to be completed by mid-
November.  Remediation schedule to be revised due to unforeseen conditions.
Meeting Date:
November 13, 2024
Chandler Municipal Airport
Construction Report