Project Name: APACHE PARK RESTROOM REPLACEMENT 
Page 1 
Project No.: PR2501.401 
Rev. 3/19/2024 
 
 
 
CITY OF CHANDLER 
JOB ORDER PROJECT AGREEMENT  
 
APACHE PARK RESTROOM REPLACEMENT 
 
Project No. PR2501.401 
Council Date: November 7, 2024 
 
This JOB ORDER PROJECT AGREEMENT (”Job Order”) is made this _____ day of _____________ 202____ 
(“Effective Date”), by and between the City of Chandler, an Arizona municipal corporation, (“City”) 
and DNG Construction, LLC, an Arizona Corporation, (“JOC Contractor”) and is entered into 
pursuant to Job Order Master Agreement No. JOC2403.401  (“JOC Master Agreement”). City and 
JOC Contractor may be referred to individually as “Party” or collectively as “Parties”). 
 
City and JOC Contractor, in consideration of the mutual covenants herein set forth, agree as 
follows:   
 
RECITALS 
 
A. On or about February 16, 2024, the Parties entered into the JOC Master Agreement, which 
terms and conditions are made a part of and incorporated into this Job Order Project Agreement 
by this reference. 
 
B. City proposes to engage JOC Contractor for construction services as more fully described in 
Article 1 and Exhibit "A", which is attached to and made a part of this Job Order by this reference. 
 
C. JOC Contractor is ready, willing, and able to provide the services described in Exhibit “A” for 
the compensation and fees set forth and as described in Exhibit ”B”, which is attached to and 
made a part of this Agreement by this reference. 
 
ARTICLE 1.  DESCRIPTION OF WORK 
 
The Parties enter into this Job Order Project Agreement for the APACHE PARK RESTROOM 
REPLACEMENT, Project Number PR2501.401.  The scope of work consists of the design of a 
prefabricated 
restroom 
building 
and 
accompanying 
demo, 
utility, 
and 
hardscape/landscape plans, State permitting, demolition, and construction for the 
prefabricated building and accompanying utility connections, landscape, and hardscape, all 
as more particularly set forth in Exhibit “A” attached hereto and incorporated herein by 
reference.

Project Name: APACHE PARK RESTROOM REPLACEMENT 
Page 2 
Project No.: PR2501.401 
Rev. 3/19/2024 
 
The JOC Contractor will not accept any change of scope, or change in Agreement provisions, unless 
issued in writing, as a Agreement amendment or change order and signed by the authorized 
signatories for each party. 
 
Performance and Payment Bonds, as set forth in Exhibit “C” and Exhibit “D” respectively attached 
hereto and incorporated herein by reference, will be due prior to execution of each Job Order 
Project Agreement in the full amount of each Job Order. 
 
At project completion, JOC Contractor must complete Contractor's Affidavit Regarding Settlement 
of Claims and Certificate of Completion, as set forth in Exhibit “E” and Exhibit “F” respectively 
attached hereto and incorporated herein by reference. 
 
ARTICLE 2.  PROJECT PRICE 
 
City will pay JOC Contractor for completion of the Work in accordance with the JOC Master 
Agreement a fee not to exceed the Guaranteed Maximum Price of $445,248 Dollars determined 
and payable as set forth in JOC Master Agreement and Exhibit “B” attached hereto and made a 
part hereof by reference.  
 
ARTICLE 3.  AGREEMENT TIME & SCHEDULE 
 
JOC Contractor agrees to complete all Construction within 240 calendar days from the Notice to 
Proceed (NTP) Date.  
 
ARTICLE 4.  JOB ORDER CONTACTS 
 
The following parties serve in the capacity below for this Job Order Project. 
 
CITY: 
 
Construction Project Manager:  Jason Garcia 
 
Phone: 480-782-3453 
 
Email: Jason.Garcia@chandleraz.gov     
 
JOC CONTRACTOR: 
DNG Construction, LLC  
 
3933 E. La Salle St. Phoenix, AZ 85040 
 
JOC Contractor Representative:  Dominic DeMark 
 
Phone: 480-361-9137 
 
Email: ddemark@dngllc.com

Project Name: APACHE PARK RESTROOM REPLACEMENT 
Page 3 
Project No.: PR2501.401 
Rev. 3/19/2024 
 
ARTICLE 5. FORCED LABOR OF ETHNIC UYGHURS PROHIBITED   
 
By entering into this Agreement, Contractor certifies and agrees Contractor does not 
currently use and will not use for the term of this Agreement: (i) the forced labor of ethnic 
Uyghurs in the People's Republic of China; or (ii) any goods or services produced by the 
forced labor of ethnic Uyghurs in the People's Republic of China; or (iii) any contractors, 
subcontractors or suppliers that use the forced labor or any goods or services produced 
by the forced labor of ethnic Uyghurs in the People's Republic of China 
 
 
 
 
 
 
SIGNATURE PAGE TO FOLLOW

Project Name: APACHE PARK RESTROOM REPLACEMENT 
Page A-1 
Project No.: PR2501.401 
Rev. 3/19/2024 
 
EXHIBIT A 
SCOPE OF WORK

ID
Task Name
Days
Start
Finish
Predecessors
1
APACHE PARK RESTROOM RENOVATION
170 d
Tue 11/12/24
Mon 7/7/25
2
NOTICE TO PROCEED
0 d
Tue 11/12/24
Tue 11/12/24
3
PERMITS
102 d
Tue 11/12/24
Wed 4/2/25
2
4
BUILDING FABRICATION & DELIVERY
145 d
Tue 11/12/24
Mon 6/2/25
2
5
TEMPORARY FENCE INSTALLATIOIN
0 d
Tue 4/22/25
Tue 4/22/25
4FS-30 d
6
EXISTING UTILITIES EXPLORATION
5 d
Tue 4/22/25
Mon 4/28/25
5
7
DEMOLITION
5 d
Tue 4/29/25
Mon 5/5/25
6
8
PAD UNDEREXCAVATION
5 d
Tue 5/6/25
Mon 5/12/25
7
9
SUB-BASE GRADING
5 d
Tue 5/13/25
Mon 5/19/25
8
10
AGREGATE BASE COURSE PAD
10 d
Tue 5/20/25
Mon 6/2/25
9
11
BUILDING INSTALLATION
10 d
Tue 6/3/25
Mon 6/16/25
4
12
UTILITIES TIE-IN
10 d
Tue 6/17/25
Mon 6/30/25
11
13
HARDSCAPE
5 d
Tue 6/17/25
Mon 6/23/25
11
14
LANDSCAPE
5 d
Tue 6/24/25
Mon 6/30/25
13
15
SUBSTANTIAL COMPLETION
0 d
Mon 6/30/25
Mon 6/30/25
12
16
PUNCH LIST
5 d
Tue 7/1/25
Mon 7/7/25
15
17
FINAL COMPLETION
0 d
Mon 7/7/25
Mon 7/7/25
16
11/12
NOTICE TO PROCEED
11/12
4/2
PERMITS
11/12
6/2
BUILDING FABRICATION & DELIVERY
11/12
6/2
BUILDING FABRICATION & DELIVERY
4/22
TEMPORARY FENCE INSTALLATIOIN
4/22
4/28
EXISTING UTILITIES EXPLORATION
4/29
5/5
DEMOLITION
5/6
5/12
PAD UNDEREXCAVATION
5/13
5/19
SUB-BASE GRADING
5/20
6/2
AGREGATE BASE COURSE PAD
6/3
6/16
BUILDING INSTALLATION
6/3
6/16
BUILDING INSTALLATION
6/17
6/30
UTILITIES TIE-IN
6/17
6/30
UTILITIES TIE-IN
6/17
6/23
HARDSCAPE
6/24
6/30
LANDSCAPE
6/30
SUBSTANTIAL COMPLETION
7/1
7/7
PUNCH LIST
7/1
7/7
PUNCH LIST
7/7
FINAL COMPLETION
October
November
December
January
February
March
April
May
June
July
August
Task
Critical
Milestone
Summary
Progress
      
APACHE PARK RESTROOM RENOVATION
Project: APACHE PARK                SEPT 20, 2024
Project Manager: JOSE TORRES
Site Superintendent:  DOUGLAS MACY
.

EXHIBIT B 
FEE SCHEDULE 
 
Project Name: APACHE PARK RESTROOM REPLACEMENT  
Page B-1 
Project No.: PR2501.401 
 
Rev. 3/19/2024

3933 E. La Salle St.
Phoenix, AZ 85040
Phone- 480-361-9137
AZ ROC- 282951, 288968
dngcontruction.com
Negotiated Prices
283,271
$                
16,291
$                  
41,175
$                  
-
$                        
-
$                        
SUBTOTAL (NEGOTIATED PRICES):
340,737
$               
9%
30,666
$                  
TOTAL (NEGOTIATED PRICES + OVERHEAD & PROFIT):
371,403
$                
Sales Tax, Material Only (Current Tax Rate)
5.07%
19,502
$                   
General Liability Insurance Percentage (Actual Cost per Job Order)
4,547
$                     
Builder's Risk Insurance Percentage (Actual Cost per Job Order)
2,021
$                    
Payment/Payment Bond (Actual Cost per Job Order)
6,679
$                    
SUBTOTAL (INSURANCE, BONDS, & TAXES):
32,748
$                 
COMBINED TOTAL (TOTAL + INSURANCE, BONDS, & TAXES):
404,151
$                
City's Allowance
10.00%
40,415
$                  
TOTAL JOB ORDER:
445,248
$         
Per the Job Order Master Agreement - This Fee Table includes all fees, costs, insurance and bond premiums, allowances, construction 
contingency, and taxes of any type necessary to fully, propertly and timely perform and construct the Work.  Also per the Job Order Master 
Agreement - For any portion of the Work which, either through this Contract, Change Order or otherwise, is performed and paid for on a cost, 
or time and materials basis, the costs may be reimbursed to JOC Contractor and chargeable against the Contract Price will be determined as 
set forth in MAG 109.5.
Construction Labor (if applicable)
Insurance, Bonds, & Taxes
Price of Subcontractor(s)
Price of Subconsultant(s)
General Conditions
Preconstruction Labor (if applicable)
ENTER TAX % HERE:
EXHIBIT "B"
JOB ORDER COST PROPOSAL
SUMMARY SHEET
Overhead and Profit (Coefficient per Job Order Master Agreement)
APACHE PARK RESTROOM

DATE:
04/05/24
PROJECT:
PREP. BY: DD/JT
LOCATION:
CHK'D BY:
QTY.
UNITS
UNIT COST
TOTAL COST
24
HRLY
102.50
$          
2,460
$                    
60
HRLY
102.50
$          
6,150
                     
240
HRLY
95.25
             
22,860
                   
0
HRLY
76.50
             
-
                        
0
HRLY
42.25
             
-
                        
0
HRLY
56.50
             
-
                        
1
LS
3,050.00
        
3,050
                     
1
LS
1,500.00
        
1,500
                     
0
SETS
75.00
             
-
                        
0
EA
125.00
           
-
                        
1
MONTHS
125.00
           
125
                        
0
LS
-
                
-
                        
0
LS
-
                
-
                        
0
MONTHS
875.00
           
-
                        
0
EA
500.00
           
-
                        
1
MONTHS
150.00
           
150
                        
1
MONTHS
525.00
           
525
                        
0
MONTHS
-
                
-
                        
0
EA
-
                
-
                        
0
MONTHS
-
                
-
                        
0
MONTHS
-
                
-
                        
1
MONTHS
125.00
           
125
                        
0
WKS
-
                
-
                        
200
LF
5.75
               
1,150
                     
0
EA
-
                
-
                        
1
LS
1,250.00
        
1,250
                     
0
EA
-
                
-
                        
0
LS
625.00
           
-
                        
0
MONTHS
-
                
-
                        
0
MHRS
-
                
-
                        
0
LS
450.00
           
-
                        
0
LS
-
                
-
                        
0
TRIPS
525.00
           
-
                        
1
MONTHS
875.00
           
875
                        
0
LS
-
                
-
                        
0
LS
-
                
-
                        
0
MONTHS
-
                
-
                        
1
MONTHS
955.00
           
955
                        
41,175
$                
EQUIPMENT / TOOL RENTAL
EQUIPMENT FUEL
PROJECT SAFETY
TOTAL GENERAL REQUIREMENTS
DUST CONTROL / PALLIATION
STREET SWEEPER
PROJECT SIGNAGE AND BARRICADES
FIRE PROTECTION AND SAFETY SUPPLIES
PROGRESSSIVE CLEAN UP
CONCRETE WASH OUT
FINAL CLEANING
TRASH DISPOSAL
PROJECT PICKUP TRUCK
MISC. SMALL TOOLS AND SUPPLIES
MOBILE PHONE USAGE
PROJECT SECURITY / WATCHMAN
TEMPORARY FENCE
TEMPORARY ROADS AND ENTRANCES
DRINKING WATER
TEMPORARY TOILETS / SANITARY FACILITIES
TEMPORARY POWER
TEMPORARY WATER - HYDRANT METER FEES
WATER CONSUMED 
POWER CONSUMED
FIELD COMPUTER SERVICE
SITE COMPUTER - HARDWARE / SOFTWARE
DESIGN & ENGINEERING SERVICES
PROJECT FIELD OFFICE/STORGAE CONTAINTER
FIELD OFFICE SET-UP / REMOVAL
CARPENTER
BUILDING PERMIT (State)
DUST CONTROL / ENVIRONMENTAL PERMIT
BLUEPRINTS, COPIES AND REPRODUCTION
POSTAGE & DELIVERY SEVICE
PROJECT SUPERINTENDENT
FIELD ENGINEER
LABORER
GENERAL REQUIREMENTS ESTIMATE
APACHE PARK RESTROOM
CHANDLER, AZ
DESCRIPTION
PROJECT MANAGER
PROJECT MANAGER- DESIGN/PERMITTING

APACHE PARK RESTROOM
MH
Unit
Cost
QTY
Unit
Cost
QTY
Unit
Cost
QTY
Unit
Cost
MH
Unit
Cost
2.10
750
$
 
2.12
7,025
$            
2.20 Site Pad
4,070
$            
2.30 Underground Utilities
4,120
$            
2.50
2,640
$            
3.10
2,945
$            
5.10
249,471
$       
15.10
4,750
$            
16.10
7,500
$            
283,271
$       
Survey
Demo/Earthwork
SCHEDULE OF VALUES
Bid Item
Bid Item Description
Qty
Unit
Labor
Equipment/Tools
Tools & Supplies
 Materials/DISPOSAL
Subcontractors 
Subcontractor,  Supplier, 
SBE
Concerte- Sidewalk
Plumbing
Prefab- Restrooms
Electrical
Landscape

EXHIBIT C 
 
Project Name: APACHE PARK RESTROOM REPLACEMENT 
Page C-1 
Project No.: PR2501.401 
Rev. 3/19/2024 
 
 
 
PERFORMANCE BOND 
 
 
ARIZONA STATUTORY PERFORMANCE BOND 
PURSUANT TO TITLES 28, 34, AND 41, ARIZONA REVISED STATUTES 
(Penalty of this bond must be 100% of the Agreement amount) 
 
KNOW ALL MEN BY THESE PRESENTS THAT:___________________________________________________ 
 
(hereinafter "Principal"), and __________________________________________________________ (hereinafter "Surety"), a 
corporation organized and existing under the laws of the State of ______________ with its principal office in the City of 
_____________________________, holding a certificate of authority to transact surety business in Arizona issued by the 
Director of Insurance pursuant to Title 20, Chapter 2, Article 1, as Surety, are held and firmly bound unto 
__________________________(hereinafter "Obligee") in the amount of ________________________________________________ 
(Dollars) ($___________), for the payment whereof, Principal and Surety bind themselves, and their heirs, administrators, 
executors, successors and assigns, jointly and severally, firmly by these presents. 
 
WHEREAS, the Principal has entered into a certain written Agreement with the Obligee, dated  
 
the ____________ day of _______________________, 20___ for construction of APACHE PARK RESTROOM REPLACEMENT, 
PR2501.401 which Agreement is hereby referred to and made a part hereof as fully and to the same extent as if copies 
at length herein. 
 
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION IS SUCH, that if the Principal faithfully performs and 
fulfills all the undertakings, covenants, terms, conditions and agreements of the Agreement during the original term of 
the Agreement and any extension of the Agreement, with or without notice of the Surety, and during the life of any 
guaranty required under the Agreement, and also performs and fulfills all the undertakings, covenants, terms, 
conditions, and agreements of all duly authorized modifications of the Agreement that may hereafter be made, notice 
of which modifications to the Surety being hereby waived, the above obligation is void.  Otherwise it remains in full force 
and effect. 
 
PROVIDED, HOWEVER that this bond is executed pursuant to the provisions of Title 34, Chapter 2, Article 2, 
Arizona Revised Statutes, and all liabilities on this bond will be determined in accordance with the provisions of Title 34, 
Chapter 2, Article 2, Arizona Revised Statutes, to the same extent as if it were copied at length in this Agreement. 
 
The prevailing party in a suit on this bond may recover as part of the judgment reasonable attorney fees that 
may be fixed by a judge of the court. 
 
Witness our hands this ________________ day of ____________________, 20__. 
____________________________________ 
PRINCIPAL         
 
SEAL 
___________________________________ 
             AGENT OF RECORD 
By _________________________________ 
____________________________________ 
SURETY  
 
SEAL

EXHIBIT D 
 
 
 
Project Name: APACHE PARK RESTROOM REPLACEMENT  
Page D-1 
Project No.: PR2501.401 
Rev. 3/19/2024 
PAYMENT BOND 
 
 
ARIZONA STATUTORY PAYMENT BOND 
PURSUANT TO TITLES 28, 34, AND 41, OF THE ARIZONA REVISED STATUTES 
(Penalty of this Bond must be 100% of the Agreement amount) 
 
KNOW ALL MEN BY THESE PRESENTS THAT:________________________________________________  
 
(hereinafter "Principal"), as Principal, and _________________________________________(hereinafter "Surety"), a corporation 
organized and existing under the laws of the State of __________________   with its principal office in the City of 
__________________, holding a certificate of authority to transact surety business in Arizona issued by the Director of the 
Department of Insurance pursuant to Title 20, Chapter 2, Article 1, as Surety, are held and firmly bound unto 
________________________  (hereinafter "Obligee") in the amount of ________________________________________________ 
(Dollars) ($___________), for the payment whereof, the Principal and Surety bind themselves, and their heirs, 
administrators, executors, successors and assigns, jointly and severally, firmly by these presents. 
 
WHEREAS, the Principal has entered into a certain written Agreement with the Obligee, dated the _________ day of 
_______________________, 20___ for construction of APACHE PARK RESTROOM REPLACEMENT, PR2501.401 which 
Amendment is hereby referred to and made a part hereof as fully and to the same extent as if copied at length herein. 
 
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION IS SUCH, that if the Principal promptly pays all moneys 
due to all persons supplying labor or materials to the Principal or the Principal's subcontractors in the prosecution of 
the work provided for in said Agreement, this obligation is void. Otherwise it remains in full force and effect. 
 
PROVIDED, HOWEVER that this bond is executed pursuant to the provisions of Title 34, Chapter 2, Article 2 
Arizona Revised Statutes, and all liabilities on this bond will be determined in accordance with the provisions, conditions 
and limitations of Title 34, Chapter 2, Article 2, Arizona Revised Statutes, to the same extent as if it were copied at length 
in this Agreement. 
 
The prevailing party in a suit on this bond may recover as part of the judgment reasonable attorney fees that 
may be fixed by a judge of the court. 
 
Witness our hands this ________________ day of ____________________, 20__. 
____________________________________ 
PRINCIPAL         
 
SEAL 
___________________________________ 
                 AGENT OF RECORD 
By _________________________________ 
____________________________________ 
SURETY  
 
SEAL 
___________________________________ 
                  AGENT ADDRESS

EXHIBIT E 
 
 
 
Project Name: APACHE PARK RESTROOM REPLACEMENT  
Page E-1 
Project No.: PR2501.401 
Rev. 3/19/2024 
CONTRACTOR'S AFFIDAVIT REGARDING SETTLEMENT OF CLAIMS 
 
 
________________________, Arizona 
 
Date ____________________________ 
 
Project Name: 
APACHE PARK RESTROOM REPLACEMENT 
Project No.:   
PR2501.401 
To the City of Chandler, Arizona 
Gentlemen: 
This is to certify that all lawful claims for materials, rental of equipment and labor used in 
connection with the construction of the above project, whether by subcontractor or claimant in 
person, have been duly discharged. 
 
The undersigned, for the consideration of $________________________, as set out in the final pay 
estimate, as full and complete payment under the terms of the Agreement, hereby waives and 
relinquishes any and all further claims or right of lien under, in connection with, or as a result of 
the above described project.  The undersigned further agrees to indemnify and save harmless 
the City of Chandler against any and all liens, claims or liens, suits, actions, damages, charges 
and expenses whatsoever, which said City may suffer arising out of the failure of the 
undersigned to pay for all labor performances and materials furnished for the performance of 
said installation. 
 
Signed and dated at ________________, this _________ day of _______________ 20_____. 
 
 
__________________________________ 
                       CONTRACTOR 
 
By _______________________________ 
STATE OF ARIZONA  
) 
) SS 
COUNTY OF MARICOPA 
) 
 
The foregoing instrument was subscribed and sworn to before me this __________ day of 
__________________ 20 _________. 
___________________________________ 
 
 
 
 
 
Notary Public 
___________________________________ 
 
 
 
 
 
My Commission Expires

EXHIBIT F 
 
 
 
Project Name: APACHE PARK RESTROOM REPLACEMENT  
Page F-1 
Project No.: PR2501.401 
Rev. 3/19/2024 
CERTIFICATE OF COMPLETION 
Project: 
APACHE PARK RESTROOM REPLACEMENT   
Project No.: PR2501.401 
(TO BE COMPLETED BY CONTRACTOR) 
 
I HEREBY CERTIFY THAT ALL GOODS AND/OR SERVICES REQUIRED BY CITY OF CHANDLER PROJECT NO. 
PR2501.401 HAVE BEEN DELIVERED IN ACCORDANCE WITH THE AGREEMENT DOCUMENTS AND BID 
SPECIFICATIONS AND ALL ACTIVITIES REQUIRED BY THE CONTRACTOR UNDER THE AGREEMENT HAVE BEEN 
COMPLETED AS OF ____________________________. 
 
 
(Date) 
 
FIRM NAME: 
________________________________ 
 
PRINCIPAL: 
________________________________ 
         (Name) 
 
________________________________ 
      (Signature) 
 
________________________________ DATE: ___________________ 
          (Title) 
 
CERTIFIED BY ENGINEER/CONSULTANT (IF APPLICABLE): 
 
_________________________________ 
 
DATE: ____________________ 
      (Signature) 
 
_________________________________ 
 
        (Firm Name) 
  
PROJECT ACCEPTED BY USER DEPARTMENT 
 
_________________________________ 
 
DATE: ____________________ 
         (Signature) 
 
_________________________________ 
 
          (Dept. /Div.) 
 
_______________ Date of Final Walk-Through 
 
_______________ Date As-Built Received 
 
_______________ City As-Built Number

EXHIBIT G 
 
 
 
Project Name: APACHE PARK RESTROOM REPLACEMENT 
Page G-1 
Project No.: PR2501.401 
Rev. 3/19/2024 
SUBCONTRACTOR DOCUMENTS WITH JOC CONTRACTOR 
 
Any subcontractor assumptions, clarifications, exclusions, terms & conditions, 
signature blocks, etc. included are strictly between the JOC Contractor and their 
subcontractors, and do not apply to the Agreement between the JOC Contractor and 
the City.

J2 Engineering and Environmental Design, LLC 
4649 E. Cotton Gin Loop, B2 Phoenix, AZ 85040 
602.438.2221 www.j2design.us 
M:\Proposals\Chandler\2024\Apache Park Restroom\2024-09-05 Apache Park Scope.doc 
1 
September 5, 2024 
 
Dominic DeMark 
President 
DNG Construction, LLC 
3933 E. La Salle Street 
Phoenix, AZ 85040 
 
Re: Apache Park Restroom Replacement 
 
Dear Dominic, 
 
J2 Engineering and Environmental Design, LLC (J2 Design) is pleased to provide professional 
design services for the Apache Park Restroom Replacement project.  This scope of services is 
based upon our understanding of the project from our email correspondence and site visit to 
the project area.   
 
Project Understanding: The City of Chandler is replacing an existing restroom facility with a 
new prefabricated restroom at Apache Park.  New restroom will utilize existing utility lines 
(water, sewer, electric).  New restroom is approximately the same size as the existing and 
minimal hardscape or landscape disturbance expected.  Our estimated Lump Sum fee for 
this project are as follows (see attached fee sheet for break down): 
 
J2 Design: 
 
 
 
 
 
 
 
 
$8,531.00 
Wright Engineering: 
 
 
 
 
 
 
 
$5,760.00 
Speedie & Associates:  
 
 
 
 
 
 
$2,000.00 
 
Total Fee: 
 
 
 
 
 
 
 
 
$16,291.00 
 
Thank you for the opportunity to provide professional services on this exciting project and 
serve the Town of Gilbert.  Please contact me if you have any questions. 
 
Sincerely, 
 
 
Aaron Allan, PLA, ASLA 
Principal 
aallan@j2design.us 
m 480.720.0522

J2 Engineering and Environmental Design, LLC 
4649 E. Cotton Gin Loop, B2 Phoenix, AZ 85040 
602.438.2221 www.j2design.us 
M:\Proposals\Chandler\2024\Apache Park Restroom\2024-09-05 Apache Park Scope.doc 
2 
Location:  
 
 
Scope of Services:   
 
Task 100:  Site Investigation 
J2 will review as-builts associated with the site.   
 
J2 will attend a kick-off meeting with key stakeholders on the project as well as perform a site 
visit with the team.   
 
Meetings: 
 
Kick-off Meeting/Site Visit - One (1) meeting.  This meeting is anticipated to be two (2) 
hours in duration.  J2 will have three (3) representatives at this meeting. 
 
Task 200 – Construction Documents (90% and Final) 
J2 will develop plans and details and provide staged submittals at the 90%, and Final levels of 
completion.  J2 will submit one (1) full-size PDF set of plans at each stage to DNG for review 
and distribution.   
 
The Design plans are anticipated to include, but not limited to, the following: 
 
1. 
Cover Sheet 
2. Demolition plan  
3. Site plan (to show restroom, FFE, landscape restoration areas, water and sewer 
connections, and hardscape restoration) 
4. General Notes and Details as neede.

J2 Engineering and Environmental Design, LLC 
4649 E. Cotton Gin Loop, B2 Phoenix, AZ 85040 
602.438.2221 www.j2design.us 
M:\Proposals\Chandler\2024\Apache Park Restroom\2024-09-05 Apache Park Scope.doc 
3 
 
Construction document sheets will utilize the City of Chandler standard border and at full-
size will be 22”x34”.  Plan view sheets will be at 1”=10’ scale.  It is assumed that the site will be 
covered by one (1) plan view sheet.  The construction document set, including cover sheets, 
plan sheets, and detail sheets, is anticipated to contain four (4) sheets.  J2 will place multiple 
plan views on the same plan view sheet to minimize the overall sheet count if possible. 
 
Deliverables: 
 
 
Design Plans (90%, Final), one (1) Full-size PDF set 
 
Meetings: 
 
 
Comment Resolution Meeting: one (1) Meeting: This meeting is anticipated to be 
virtual.  This meeting is anticipated to be one (1) hour in duration and J2 will have two 
(2) representatives at the meeting.   
 
General Project Understanding 
 
DNG shall designate a person for the project to act as the Client’s representative with respect 
to the services to be performed or furnished by the Design Team under this agreement. Such 
person, department, or committee shall have complete authority to transmit instructions, 
receive information, interpret, and define the Client's policies and decisions with respect to 
the Design Team's services for the Project. DNG shall also provide key team personnel to be 
available in coordination meetings including operations and plan review representatives. 
 
DNG shall make available to the Design Team all existing available data and records relevant 
to the site. 
 
DNG shall approve in a timely manner all criteria and information as to Client's requirements 
for the Project including planning objectives and constraints, performance requirements, any 
budgetary limitations, and the submittal by the Design Team at the various phases of the 
projects. 
 
DNG shall furnish to the Design Team, upon the request of the Design Team for performing the 
services, any existing pertinent data prepared by or services of others, including electronic 
base maps, drawings of physical conditions in or relating to existing surface or subsurface 
utilities or structures within the planning area, hydrographic surveys, environmental or 
cultural assessments, impact statements, and other relevant environmental or cultural 
studies pertaining to the project.

J2 Engineering and Environmental Design, LLC 
4649 E. Cotton Gin Loop, B2 Phoenix, AZ 85040 
602.438.2221 www.j2design.us 
M:\Proposals\Chandler\2024\Apache Park Restroom\2024-09-05 Apache Park Scope.doc 
4 
DNG shall give prompt notice to Design Team whenever Client observes or otherwise 
becomes aware of any development that affects the scope of services or the time schedule 
of the Design Team. 
 
DNG warrants and represents that members of the Design Team have the right to enter upon 
the real property involved herein, and extends this right to J2. The Design Team agrees to 
exercise due care in the performance of all services pursuant hereto.  
 
The Design Team has provided no environmental or cultural investigations on this 
site/project, has no knowledge of any adverse environmental or cultural conditions on the 
site/project, and is not responsible for and has no liability for any such environmental or 
cultural condition should one be found. It is the responsibility of the DNG to investigate and 
make these environmental or cultural determinations based on the best knowledge and 
information available at the time of this project. Clearance to begin work shall be given prior 
to directing or ordering the preparation of any engineering documents. 
 
The Design Team provides construction documents in full or in part freehand drafting and 
electronic CAD format. Any electronic files provided are for information and convenience 
purposes only and the final approved/sealed hard copy plans shall prevail.  All construction 
documents will be developed to the City of Chandler and Maricopa Association of 
Governments (MAG) design and construction standards and specifications. 
 
Assumptions and Exclusions: 
 
1. 
No survey of any kind has been included.  It is assumed that DNG will provide a 
topographic survey for construction document development. 
2. No legal descriptions or exhibits are included. 
3. DNG will provide all as-built information to J2.  It is assumed that DNG will locate all 
on site utilities (water, sewer, electric) and provide this information to J2 for 
development of construction documents. Utility potholing has not been included in 
this scope of services.  Utility coordination is not included, it is assumed that DNG 
will route all plans for utility conflict review. 
4. The Design Team is not providing any traffic analysis, traffic study, or traffic 
engineering. 
5. The Design Team has not included any re-platting, or rezoning efforts in this scope 
of services.   
6. The Design Team is not providing any environmental, cultural, or biological 
investigations or clearances.

J2 Engineering and Environmental Design, LLC 
4649 E. Cotton Gin Loop, B2 Phoenix, AZ 85040 
602.438.2221 www.j2design.us 
M:\Proposals\Chandler\2024\Apache Park Restroom\2024-09-05 Apache Park Scope.doc 
5 
7. No new landscape or irrigation design is included.  It is assumed that landscape 
and irrigation improvements will be limited to restoration of existing 
improvements. 
8. No new hardscape design is included.  It is assumed that adjacent hardscape will 
be removed and replaced in kind to provide access to the restroom. 
9. Hard copy sets have not been included in this scope or proposal.  
10. The Design Team is not providing any permitting fees, it is assumed these costs 
will be paid by others. 
11. Erosion Control/Storm Water Pollution Prevention Plans are not included in this 
scope of services. 
12. Geotechnical Investigation or agronomy testing has not been included in this 
scope and fee. 
13. Drafting or certification of any contractor asbuilts is not included in this scope of 
services. 
14. Drainage engineering is not included in this scope of services. 
15. Post design services is not included. 
16. Public involvement is not included. 
17. Meeting attendance beyond what is stated in the scope is not included. 
18. No new utility design has been included.  It is assumed that all existing utilities will 
be utilized for the new restroom. 
19. New restroom is assumed to be a prefabricated restroom from CXT.  Permitting for 
the restroom building through the State of Arizona and the City of Chandler is not 
included in this scope of services. 
20. No opinion of probable construction cost or project specifications are included. 
21. Meeting minutes are not included. 
 
We would expect to start our services promptly after receipt of your acceptance and 
complete our services in a timely manner.  This Exhibit represents the entire understanding of 
the Scope of Work as set out herein and may only be modified in writing signed by both 
parties.

Apache Park Restroom Replacement
Design Phase Services
DNG Construction, LLC
J2 Engineering and Environmental Design, LLC
9/5/2024
Project 
Manager Sr.
Project 
Engineer Sr.
Project 
Engineer
Engineer
Landscape 
Architect Sr.
Landscape 
Architect
Designer Sr.
Designer
215.27
$           
188.67
$           
144.35
$           
116.50
$           
195.00
$           
137.71
$           
125.36
$           
89.61
$             
Task #
Hours Total
100
101
Kick-off Meeting/Site Visit (1)
0
0
2
2
0
0
2
0
6
102
Utility and Asbuilt Review and Base Map Development
0
0
2
2
0
0
2
2
8
103
Subconsultant Coordination
0
0
1
0
0
0
0
0
1
200
201
Develop Plans (4 Sheets) 
0
0
4
24
0
2
8
12
50
202
Comment Resolution Meetings (1)
0
0
1
0
0
0
1
0
2
203
QA/QC
0
2
0
0
0
0
0
0
2
204
Subconsultant Coordination
0
0
2
0
0
0
0
0
2
0
2
12
28
0
2
13
14
71
-
$                
377.00
$          
1,732.00
$       
3,262.00
$       
-
$                
275.00
$          
1,630.00
$       
1,255.00
$       
8,531.00
$                 
Subconsultants:
Fee Amount
Speedie &. Associates (Geotechnical Inspection)
2,000.00
$        
Wright (Electrical)
5,760.00
$       
-
$                 
16,291.00
$          
-
$                 
-
$                
-
$                
Total Subconsultants:
7,760.00
$       
Allowances:
Fee Amount
-
$                 
-
$                
-
$                
-
$                 
-
$                
Date
Total Allowances: $                  -   
September 5, 2024
J2 Fee per Labor Category (Rounded to Nearst Whole Dollar):
Construction Documents (95%, Final)
J2 Engineering and Environmental Design, LLC
J2 Hours per Labor Category:
Principal
Aaron Allan, PLA, ASLA
Total Fee J2, Subconsultants, and Allowances:
Labor Category:
Rate:
Task Description:
Site Investigation
Apache Park Design
2024-09-05 Apache Park Fee
1

Apache Park      
 
September 5, 2024 
J2 
 
Dept. 6 
PN240852 
 
 
- 1 
 
 
AUTHORIZATION TO PROCEED 
We acknowledge your authorization to proceed with the testing services outlined for this project. We 
appreciate the opportunity to provide you with the testing services that your firm has requested. Thank 
you for choosing Speedie & Associates, LLC. 
 
This letter is in response to your authorization to proceed with initiating and providing construction 
materials testing services for the above project. We present the following for your information and use. 
 
1. We understand that your firm will be our client and are responsible for payment of invoices. 
2. All scheduling of testing services must be accomplished by calling our office in advance. 
3. Please understand that you or your authorized representative must contact us as least twenty- 
four (24) hours in advance of your need for testing so that we can schedule our personnel. If you 
call with less than 24-hour notice, we will attempt to schedule our personnel for the date and time 
you need but we cannot guarantee their on-site presence at the time requested. 
4. When you call, please be prepared to give us an approximated time of arrival and location on site for 
our technician's information. 
5. When your requirements or schedule change, if you do not cancel the scheduled technician, you 
will be charged for the trip charges to and from the project site. 
6. Our FEE SCHEDULE and TERMS AND CONDITIONS are attached hereto for your review. 
Since no formal proposal or contract has been developed for your project, the services requested by 
you will be billed at these prevailing unit rates. If you have any questions please call. 
7. Our services and fees are controlled by the number of times we are called out by your on-site 
representative. Charges for our services will be made on a unit rate basis. Unit rates for technician and 
inspector time will be invoiced portal to portal from our Phoenix office with a two hour minimum. 
Your on-site representative should be made aware of how we charge our fees.  
8. Invoices will be submitted on a monthly basis, to be paid within 30 days. We reserve the right to 
stop work in progress if we do not receive timely payment. 
9. Work will not commence until this AUTHORIZATION TO PROCEED is received back at our 
office prior to start of work. 
 
Project Name:  
 
  
 
Project Location:  
 
  
 
Accepted by:  
      
  
Type or Print Name 
  
 
Signature:  
      
 
 
  
 
 
Date 
  
 
Company:  
 
  
 
SSN/EIN:  
      
  
 
  
Please fax back to: 602.943.5508 
  
Or email to:  
tcharney@speedie.net

Apache Park      
 
September 5, 2024 
J2 
 
Dept. 6 
PN240852 
 
 
- 2 
 
 
FEE AND RATE SCHEDULE 
 
DESCRIPTION OF SERVICE 
 
 
 
 
 
 
1. Observation and Testing 
 
 
a. Observation & Testing of earthwork, concrete, masonry 
 
   and paving operations by Engineering Technician 
  
   (2 Hour Minimum)  
 
$70.00/hr 
 
b. Trip charges  
 
 
$70.00/tr  
 
 
 
2. Special Inspection  
 
 
a. Observation of geotechnical/structural elements (4 hour 
minimum)  
 
100.00/hr 
b. Trip charges 
 
70.00/tr 
 
 
 
3. Office Support - If Required 
 
 
 
a. Principal  
 
150.00/hr  
 
b. Project Manager/Engineer 
 
130.00/hr  
 
 
 
4. Laboratory Fees 
 
 
 
a. Soils 
 
 
 
 
Moisture Density Relations 
 
 
 
 
ASTM D 698 A 
 
130.00/ea 
 
 
Sieve Analysis 
 
70.00/ea 
 
 
Plasticity Index (Dry Prep) 
 
70.00/ea 
 
 
Plasticity Index (Wet Prep) 
 
180.00/ea 
 
 
Swell  
 
120.00/ea 
 
 
 
 
 
b. Concrete, Mortar or Grout 
 
 
 
 
Compressive Strength (including molds) 
 
20.00/ea 
 
 
 
 
c. Asphaltic Concrete 
 
 
 
 
Extraction/Gradation 
 
165.00/ea 
 
 
Marshall Density 
 
150.00/ea 
            Maximum Theoretical Density (Rice)  
 
180.00/ea 
            Gyratory Unit Weight (Set of Two) 
 
240.00/ea 
            Thickness/Density of Cores (Not Including Coring Sub) 
  
30.00/ea 
            Moisture Content  
  
25.00/ea

Apache Park      
 
September 5, 2024 
J2 
 
Dept. 6 
PN240852 
 
 
- 3 
 
 
 
 
 
 
PROJECT ESTIMATE 
 
We have provided a budget estimate of $2,000.00 for the amount of work required for this project based on our 
experience on similar projects. Unit rates will be invoiced portal to portal from our Phoenix office. It should be 
noted, however, that we have no control over the contractor's construction methods and work schedule, and actual 
charges may vary. 
GENERAL CONDITIONS 
SECTION 1: RESPONSIBILITIES  
1.1  SPEEDIE & ASSOCIATES, LLC a UES Company (S&A/UES) is responsible for providing the services 
described under the Scope of Services.  
1.2  The Client is responsible for providing S&A/UES with a clear understanding of the project’s nature 
and scope. The Client shall supply S&A/UES with sufficient and adequate information, including, but not 
limited to, maps, site plans, reports, surveys, plans and specifications, and designs, to allow S&A/UES to 
properly complete the specified services. The Client shall also communicate changes in the nature and 
scope of the project as soon as possible during performance of the work so that the changes can be 
incorporated into the work product. 
1.3 The Client acknowledges that S&A/UES’s responsibilities in providing the services described under 
the Scope of Services section is limited to those services described therein, and the Client hereby 
assumes any collateral or affiliated duties necessitated by or for those services. Such duties may include, 
but are not limited to, reporting requirements imposed by any third party such as federal, state, or local 
entities, the provision of any required notices to any third party, or the securing of necessary permits or 
permissions from any third parties required for S&A/UES’s provision of the services so described, unless 
otherwise agreed upon by both parties in writing. 
SECTION 2: STANDARD OF CARE 
2.1  Services performed by S&A/UES under this Agreement will be conducted in a manner consistent 
with the level of care and skill ordinarily exercised by members of S&A/UES's profession practicing 
contemporaneously under similar conditions in the locality of the project. No other warranty, express or 
implied, is made by S&A/UES hereunder. 
2.2  Execution and delivery of this Agreement by S&A/UES is not a representation that S&A/UES has 
visited the site, become generally familiar with local conditions under which the work is to be 
performed, or correlated personal observations with the requirements of the Scope of Services. It is the 
Client’s responsibility to provide S&A/UES with all information necessary for S&A/UES to provide the 
services described under the Scope of Services, and the Client assumes all liability for information not 
provided to S&A/UES that may affect the quality or sufficiency of the services so described.

Apache Park      
 
September 5, 2024 
J2 
 
Dept. 6 
PN240852 
 
 
- 4 
 
 
SECTION 3: SITE ACCESS AND SITE CONDITIONS 
3.1 Client will grant or obtain free access to the site for all equipment and personnel necessary for 
S&A/UES to perform the work set forth in this Agreement. The Client will notify any possessors of the 
project site that Client has granted S&A/UES free access to the site. S&A/UES will take reasonable 
precautions to minimize damage to the site, but it is understood by Client that, in the normal course of 
work, some damage may occur, and the correction of such damage is not part of this Agreement unless 
so specified in the Scope of Services. 
3.2  The Client is responsible for the accuracy of locations for all subterranean structures and utilities. 
S&A/UES will take reasonable precautions to avoid known subterranean structures, and the Client waives 
any claim against S&A/UES, and agrees to defend, indemnify, and hold S&A/UES harmless from any claim 
or liability for injury or loss, including costs of defense, arising from damage done to subterranean 
structures and utilities not identified or accurately located. In addition, Client agrees to compensate 
S&A/UES for any time spent or expenses incurred by S&A/UES in defense of any such claim with 
compensation to be based upon S&A/UES's prevailing fee schedule and expense reimbursement policy. 
SECTION 4: BILLING AND PAYMENT 
4.1  S&A/UES will submit invoices to Client monthly or upon completion of services. Invoices will show 
charges for different personnel and expense classifications. 
4.2  Payment is due 30 days after presentation of invoice and is past due 31 days from invoice date. 
Client agrees to pay a finance charge of one and one-half percent (1 ½ %) per month, or the maximum 
rate allowed by law, on past due accounts. 
4.3  If S&A/UES incurs any expenses to collect overdue billings on invoices, the sums paid by S&A/UES 
for reasonable attorneys' fees, court costs, S&A/UES's time, S&A/UES's expenses, and interest will be due 
and owing by the Client. 
SECTION 5: OWNERSHIP AND USE OF DOCUMENTS 
5.1  All reports, boring logs, field data, field notes, laboratory test data, calculations, estimates, and 
other documents prepared by S&A/UES, as instruments of service, shall remain the property of 
S&A/UES. Neither Client nor any other entity shall change or modify S&A/UES’s instruments of service. 
5.2  Client agrees that all reports and other work furnished to the Client or his agents, which are not 
paid for, will be returned upon demand and will not be used by the Client for any purpose. 
5.3  S&A/UES will retain all pertinent records relating to the services performed for a period of “five 
years or such longer period” of time required by applicable accrediting agency, unless specified in the 
scope of services following submission of the report or completion of the Scope of Services, during which 
period the records will be made available to the Client in a reasonable time and manner.

Apache Park      
 
September 5, 2024 
J2 
 
Dept. 6 
PN240852 
 
 
- 5 
 
 
5.4  All reports, boring logs, field data, field notes, laboratory test data, calculations, estimates, and 
other documents prepared by S&A/UES, are prepared for the sole and exclusive use of Client, and may 
not be given to any other entity, or used or relied upon by any other entity, without the express written 
consent of S&A/UES. Client is the only entity to which S&A/UES owes any duty or duties, in contract or 
tort, pursuant to or under this Agreement. 
SECTION 6: DISCOVERY OF UNANTICIPATED HAZARDOUS MATERIALS 
6.1  Client represents that a reasonable effort has been made to inform S&A/UES of known or 
suspected hazardous materials on or near the project site. 
6.2  Under this agreement, the term hazardous materials includes hazardous materials, hazardous 
wastes, hazardous substances (40 CFR 261.31, 261.32, 261.33), petroleum products, polychlorinated 
biphenyls, asbestos, and any other material defined by the U.S. EPA as a hazardous material.  
6.3 Hazardous materials may exist at a site where there is no reason to believe they are present. The 
discovery of unanticipated hazardous materials constitutes a changed condition mandating a 
renegotiation of the scope of work. The discovery of unanticipated hazardous materials may make it 
necessary for S&A/UES to take immediate measures to protect health and safety. Client agrees to 
compensate S&A/UES for any equipment decontamination or other costs incident to the discovery of 
unanticipated hazardous materials.  
6.4 S&A/UES will notify Client when unanticipated hazardous materials or suspected hazardous 
materials are encountered. Client will make any disclosures required by law to the appropriate governing 
agencies. Client will hold S&A/UES harmless for all consequences of disclosures made by S&A/UES which 
are required by governing law. In the event the project site is not owned by Client, it is the Client's 
responsibility to inform the property owner of the discovery of unanticipated hazardous materials or 
suspected hazardous materials.  
6.5 Notwithstanding any other provision of this Agreement to the contrary, Client waives any claim 
against S&A/UES, and to the maximum extent permitted by law, agrees to defend, indemnify, and save 
S&A/UES harmless from any claim, liability, and/or defense costs for injury or loss arising from S&A/UES's 
discovery of unanticipated hazardous materials or suspected hazardous materials including any costs 
created by delay of the project and any cost associated with possible reduction of the property's value. 
Client will be responsible for ultimate disposal of any samples secured by S&A/UES which are found to 
be contaminated. 
SECTION 7: RISK ALLOCATION 
7.1  Subject to the balance of this Section 7.1, Client agrees that S&A/UES's liabilities, losses, damages, 
fees, costs and expenses (including attorneys’ fees)(collectively, “Liability”) arising from any claim on 
account of any breach of contract, error, omission, or professional negligence will be limited to a sum not 
to exceed $50,000 or S&A/UES’s fee, whichever is greater (the “Liability Cap”). If Client prefers to have a 
higher Liability Cap, S&A/UES agrees to increase the Liability Cap to $1,000,000.00 upon Client’s written

Apache Park      
 
September 5, 2024 
J2 
 
Dept. 6 
PN240852 
 
 
- 6 
 
 
request at the time of accepting S&A/UES’s proposal, provided that Client agrees to pay an additional 
consideration of one percent of the total fee, or $1,000.00, whichever is greater. If Client prefers a 
$2,000,000.00 Liability Cap, S&A/UES agrees to increase the Liability Cap to $2,000,000.00 upon Client’s 
written request at the time of accepting S&A/UES’s proposal, provided that Client agrees to pay an 
additional consideration of one percent of the total fee, or $2,000.00, whichever is greater. The 
additional charge for the higher Liability Cap is because of the greater risk assumed and is not strictly a 
charge for additional professional liability insurance. 
7.2  Client shall not be liable to S&A/UES, and S&A/UES shall not be liable to Client for any punitive, 
incidental, special, or consequential damages (including lost profits, loss of use, and lost savings) 
incurred by either party due to the fault of the other, regardless of the nature of the fault, or whether it 
was committed by Client or S&A/UES, their employees, agents, or subcontractors; or whether such 
liability arises in breach of contract or warranty, tort (including intentional torts and negligence), 
statutory, or any other cause of action. 
7.3 As used in this Agreement, the terms “claim” or “claims” mean any claim in contract, tort, or 
statute alleging negligence, errors, omissions, strict liability, statutory liability, breach of contract, breach 
of warranty, negligent misrepresentation, or any other act giving rise to Liability. 
SECTION 8: INSURANCE 
8.1  S&A/UES represents that it and its agents, staff, and consultants employed or retained by S&A/UES, 
is and are protected by workers’ compensation insurance, and that S&A/UES has such coverage under 
public liability and property damage insurance policies which S&A/UES deems to be adequate. 
Certificates for all such policies of insurance shall be provided to Client upon request in writing. Within 
the limits and conditions of such insurance, S&A/UES agrees to indemnify and save Client harmless from 
and all Liabilities arising from negligent acts by S&A/UES, its agents, staff, and consultants employed by 
it. S&A/UES shall not be responsible for Liabilities beyond the amounts, limits, and conditions of such 
insurance or the limits described in Section 7, whichever is less. The Client agrees to defend, indemnify, 
and save S&A/UES harmless from all Liabilities arising from acts by Client, Client’s agents, staff, and 
others employed by Client. 
8.2  Under no circumstances will S&A/UES indemnify Client from or for Client’s own actions, 
negligence, or breaches of contract. 
8.3  To the extent that damages are covered by property insurance, Client and S&A/UES waive all rights 
against each other and against the contractors, consultants, agents, and employees of the other for 
damages, except such rights as they may have to the proceeds of such insurance. 
SECTION 9: DISPUTE RESOLUTION 
9.1  All claims, disputes, and other matters in controversy between S&A/UES and Client arising out of or 
in any way related to this Agreement shall be submitted to mediation before and as a condition 
precedent to seeking other remedies provided by law.

Apache Park      
 
September 5, 2024 
J2 
 
Dept. 6 
PN240852 
 
 
- 7 
 
 
9.2  If a dispute arises and that dispute is not resolved by mediation, then: (a) the claim will be brought 
in the state or federal courts having jurisdiction where the S&A/UES office which provided the service is 
located; and (b) the prevailing party will be entitled to recovery of all reasonable out of pocket fees, costs 
and expenses incurred by such party, including court costs, attorneys’ fees, expert witness fees, and 
other claim related expenses. 
SECTION 10: TERMINATION 
10.1 This Agreement may be terminated by either party upon seven (7) days written notice in the event 
of substantial failure by the other party to perform in accordance with the terms hereof, or in the case of 
a force majeure event such as terrorism, act of war, public health or other emergency. Such termination 
shall not be effective if such substantial failure or force majeure has been remedied before expiration of 
the period specified in the written notice. In the event of termination, S&A/UES shall be paid for services 
performed to the termination notice date plus reasonable out of pocket termination expenses incurred 
or paid by S&A/UES in connection with such termination and the winding down of its operations. 
10.2 In the event of termination, or suspension for more than three (3) months, prior to completion of 
all reports contemplated by this Agreement, S&A/UES may complete such analyses and records as are 
necessary to complete its files and may also complete a report on the services performed to the date of 
notice of termination or suspension. The expense of termination or suspension shall include all direct 
out of pocket costs incurred or paid by S&A/UES in completing such analyses, records, and reports. 
SECTION 11: REVIEWS, SPECIAL INSPECTIONS, TESTING AND OBSERVATIONS  
11.1 Plan review and building inspections are performed for the purpose of observing compliance with 
applicable building codes. Construction materials testing (“CMT”) and Special Inspections are performed 
to document compliance of certain materials or components with applicable testing standards. 
S&A/UES’s performance of plan reviews, Special inspections, building inspections, or CMT, or S&A/UES’s 
presence on the site of Client’s project while performing any of the foregoing activities, is not a 
representation or warranty by S&A/UES that Client’s project is free of errors in either design or 
construction.  
11.2 If S&A/UES is retained to provide construction monitoring or observation, S&A/UES will report to 
Client any observed work which, in S&A/UES’s opinion, does not conform to the plans and specifications 
provided to S&A/UES. S&A/UES shall have no authority to reject or terminate the work of any agent or 
contractor of Client. No action, statements, or communications of S&A/UES, or S&A/UES’s site 
representative, can be construed as modifying any agreement between Client and others. Client 
acknowledges that S&A/UES’s performance of construction monitoring or observation is not a 
representation or warranty by S&A/UES that Client’s project is free of errors in either design or 
construction. 
11.3 Neither the activities of S&A/UES pursuant to this Agreement, nor the presence of S&A/UES or its 
employees, representatives, or subcontractors on the project site, shall be construed to impose upon 
S&A/UES any responsibility for means or methods of work performance, superintendence, sequencing of

Apache Park      
 
September 5, 2024 
J2 
 
Dept. 6 
PN240852 
 
 
- 8 
 
 
construction, or safety conditions at the project site. Client acknowledges that Client or its contractor is 
solely responsible for project jobsite safety. 
11.4  Client is responsible for scheduling all inspections and CMT activities of S&A/UES. All testing and 
inspection services will be performed on a will-call basis. S&A/UES will not be responsible for tests and 
inspections that are not performed due to Client’s failure to schedule S&A/UES’s services on the project, 
or for any claims or damages arising from tests and inspections that are not scheduled or performed. 
11.5 If the Client desires more extensive or full-time project observation to help reduce the risk of 
problems arising during construction, the Client shall request such services as “Additional Services” in 
accordance with the terms of this agreement. Should the Client, for any reason, choose not to have 
S&A/UES provide construction or field observation during the implementation of S&A/UES’s 
specifications or recommendations, or should the Client unduly restrict S&A/UES’s assignment of 
observation personnel, Client shall, to the fullest extent permitted by law, waive any claim against 
S&A/UES, and indemnify, defend, and hold S&A/UES harmless from any claim or liability for injury or loss 
arising from field problems allegedly caused by findings, conclusions, recommendations, plans or 
specifications developed by S&A/UES. The Client also shall compensate S&A/UES for any time spent or 
expenses incurred by S&A/UES in defense of any such claim. Such compensation shall be based upon 
S&A/UES’s standard fee and rate schedule.

Apache Park      
 
September 5, 2024 
J2 
 
Dept. 6 
PN240852 
 
 
- 9 
 
 
 
SECTION 12: ENVIRONMENTAL ASSESSMENTS 
12.1 Client acknowledges that an Environmental Site Assessment (“ESA”) is conducted solely to permit 
S&A/UES to render a professional opinion about the likelihood or extent of regulated contaminants 
being present on, in, or beneath the site in question at the time services were conducted. No matter 
how thorough an ESA study may be, findings derived from the study are limited and S&A/UES cannot 
know or state for a fact that a site is unaffected by reportable quantities of regulated contaminants as a 
result of conducting the ESA study. Even if S&A/UES states that reportable quantities of regulated 
contaminants are not present, Client acknowledges that it still bears the risk that such contaminants may 
be present or may migrate to the site after the ESA study is complete. 
SECTION 13: SAMPLE DISPOSAL 
13.1 Non-Hazardous Samples — Test samples are substantially altered during testing and disposed of 
immediately upon completion. Drilling samples are disposed of thirty (30) days after submission of our 
report. If requested in writing, samples can be held after thirty (30) days for an additional storage fee or 
returned to the Client. 
13.2 Hazardous Samples — If toxic or hazardous substances are involved, S&A/UES will return such 
samples to the Client. Or using a manifest signed by the Client, S&A/UES will have such samples 
transported to a location selected by the Client for final disposal. The Client agrees to pay all costs for 
storage, transport, and disposal of samples. The Client recognizes and agrees that S&A/UES is acting as a 
bailee and at no time assumes title to samples involving hazardous or toxic materials. 
SECTION 14: SUBSURFACE EXPLORATIONS 
14.1  Client acknowledges that subsurface conditions may vary from those observed at locations where 
borings, surveys, samples, or other explorations are made, and that site conditions may change with 
time. Data, interpretations, and recommendations by S&A/UES will be based solely on information 
available to S&A/UES at the time of service. S&A/UES is responsible for those data, interpretations, and 
recommendations but will not be responsible for other parties’ interpretations or use of the information 
developed or provided by S&A/UES. 
14.2  Subsurface explorations may result in unavoidable cross-contamination of certain subsurface areas, 
as when a probe or boring device moves through a contaminated zone and links it to an aquifer, 
underground stream, or other hydrous body not previously contaminated. S&A/UES is unable to 
eliminate totally cross-contamination risk despite use of due care. Since subsurface explorations may be 
an essential element of S&A/UES’s services indicated herein, Client shall, to the fullest extent permitted 
by law, waive any claim against S&A/UES, and indemnify, defend, and hold S&A/UES harmless from any 
claim or Liability arising from cross-contamination allegedly caused by S&A/UES’s subsurface 
explorations. In addition, Client agrees to compensate S&A/UES for any time spent or expenses incurred

Apache Park      
 
September 5, 2024 
J2 
 
Dept. 6 
PN240852 
 
 
- 10
 
 
by S&A/UES in defense of any such claim with compensation to be based upon S&A/UES's prevailing fee 
schedule and expense reimbursement policy. 
SECTION 15: SOLICITATION OF EMPLOYEES 
15.1 Client agrees not to solicit for hire any of S&A/UES's employees with which Client had contact 
during the term of this Agreement for a one-year period following the expiration date or termination 
date of this Agreement (the “Post-Term Period”) except through S&A/UES. If Client hires any such 
S&A/UES employee during the Post-Term Period, Client shall within five business days following written 
demand therefore from S&A/UES, pay S&A/UES an amount equal to one-half of the employee's then 
effective annualized salary, as liquidated damages. Further, Client acknowledges that the liquidated 
damages, stated above, are reasonable under the circumstances. 
SECTION 16: ASSIGNS 
16.1 Neither Client nor S&A/UES may assign this Agreement or assign or delegate any of its rights or 
obligations hereunder without the prior written consent of the other party. 
SECTION 17: GOVERNING LAW AND SURVIVAL 
17.1  This Agreement shall be governed by and construed in accordance with the laws of the jurisdiction 
in which the S&A/UES office performing the services hereunder is located. 
17.2 If any of the provisions of this Agreement is held by a court of competent jurisdiction to be illegal, 
invalid, or unenforceable, the enforceability of the remaining provisions will not be impaired and will 
survive. Limitations of liability and indemnities will survive termination of this Agreement for any cause. 
SECTION 18: INTEGRATION CLAUSE 
18.1  This Agreement represents and contains the entire and only agreement and understanding among 
the parties with respect to the subject matter of this Agreement and supersedes any and all prior and 
contemporaneous oral and written agreements, understandings, representations, inducements, 
promises, warranties, and conditions among the parties. No agreement, understanding, representation, 
inducement, promise, warranty, or condition of any kind with respect to the subject matter of this 
Agreement shall be relied upon by the parties unless expressly set forth herein. 
18.2  This Agreement may not be amended or modified except by an agreement in writing signed by the 
party against whom the enforcement of any modification or amendment is sought. 
SECTION 19: WAIVER OF JURY TRIAL 
19.1  To the extent permitted by applicable law, Client and S&A/UES hereby waive trial by jury in any 
action arising out of or related to this Agreement.

Apache Park      
 
September 5, 2024 
J2 
 
Dept. 6 
PN240852 
 
 
- 11
 
 
CLIENT APPROVAL 
S&A/UES offers the Client the Proposal as listed above. Client may accept S&A/UES’s offer by signing in 
the space provided below and returning a signed copy to S&A/UES. Such notification may be faxed or by 
emailing the signed general conditions. In the event the Client authorizes work without returning a 
signed copy, the Client agrees to be bound by the general conditions as stated herein. The proposal 
presented has been read, understood, and accepted by the Client effective as of the date that the 
executed proposal is returned to S&A/UES. 
EXECUTED BY CLIENT’S AUTHORIZED REPRESENTATIVE:  
 
 
 
 
 
     
(signature) 
Printed Name:  
 
 
 
 
 
Title: 
 
 
 
 
 
  
Date Accepted:  
 
 
 
 
 
Client Business Name:  
 
 
 
 
 
 
 
 
 
 
  
Billing Address:  
 
 
 
 
 
 
 
 
 
 
 
  
Telephone: 
 
 
 
 
 
E-mail:  
 
 
 
 
 
  
ACCOUNTS PAYABLE INFORMATION 
A/P Contact Name: 
 
 
 
 
 
A/P Contact Telephone:  
 
 
 
*A/P Contact E-Mail: 
 
 
 
 
  
* A/P Contact E-Mail must be provided before the S&A/UES can proceed with its proposed services.

B24-0515 
 
 
 
 
ELECTRICAL ENGINEERING & LIGHTING DESIGN 
 
165 EAST CHILTON    CHANDLER, ARIZONA 85225      OFFICE: 480-497-5829   FAX: 480-497-5807 
www.wrightengineering.us 
 
 
September 5, 2024 
 
J2 Engineering & Environmental Design 
4649 E Cotton Gin Loop, Suite B2 
Phoenix, AZ 85040 
 
 
 
 
 
 
Re: 
Apache Park Restroom Building Electrical 
 
Attn:  Aaron Allan  
 
Wright Engineering appreciates this opportunity to submit a proposal for electrical 
engineering services on the above referenced project. The following services will 
be performed in a professional manner to meet City of Chandler requirements: 
 
Electrical Design Scope of Services: 
1. 
Coordinate design with owner, power company, civil engineer, and/or 
architect/landscape architect as required. 
a. 
Project coordination will be performed via email, telephone calls, and 
virtual meetings. Up to (1) one in-person design coordination meeting 
is included in this scope. 
2. 
Visit the site to determine existing conditions and electrical configuration. Up 
to (1) one visit. 
3. 
Review existing electrical drawings and load calculations for site. 
4. 
Determine existing peak demand loads and coordinate proposed electrical 
loads. 
5. 
Design the electrical power system to meet local codes and requirements. 
6. 
Prepare 24” X 36” electrical construction drawings showing all new 
equipment to include the following: 
a. 
Existing electrical service entrance section and distribution equipment 
b. 
Power to prefabricated restroom building sub-panel 
c. 
Grounding at new restroom building sub-panel 
7. 
Prepare necessary elevation view and installation details of the equipment 
listed above to help determine layout and size. 
8. 
Prepare load calculations and single line diagram. 
9. 
Prepare panel schedule and other electrical installation details as required. 
10. Prepare a conduit and wire table showing all power conduits and wire for 
equipment listed above. 
11. Prepare system fault current and voltage drop calculations as required. 
12. Prepare an engineer’s opinion of probable electrical construction costs and 
project specific electrical specifications document upon request. 
13. Perform in-house QAQC review and modifications.

Apache Park Restroom Building 
Electrical 
 
Page 2 of  3 
 
September 5, 2024 
14. The above plans will be provided to client at 90% and 100% levels for 
submittal review and comment. Submittals will be made via email in digital 
PDF format. Client will print, copy and submit to the City and owner as 
needed. 
15. Up to one set of base drawing changes or updates will be included in this 
engineering cost proposal. Incorporating any additional base drawing 
changes will incur additional cost at the rates noted under additional 
services. 
16. Municipal review comments will be responded to and addressed. 
 
Responsibilities of Others: 
1. 
Provide Wright Engineering Corp. electronic base files in an AutoCAD 
format which includes all proposed and existing utilities, all proposed 
improvements, and any existing conditions that affect this scope. 
2. 
Wright Engineering will submit plans to the civil engineer or landscape 
architect for submittal to the local government agencies for approval and 
permits. 
3. 
It is anticipated that the electrical service for this project is existing, in the 
case that it does not exist; Designation of location of electrical service will 
be determined by the local utility company. The owner is responsible for 
coordination of the design of all electrical utility power services during the 
design process. 
 
Final Deliverables: 
1. 
Upon completion of the design, we will provide final sealed documents 
bearing the signature of a registered electrical engineer in the State of 
Arizona. 
 
Engineering Fee: 
The above services will be provided as follows:  
1. 
Electrical Design Services: $5,760.00 (Lump Sum) 
 
Hourly Rate Schedule: 
Any services listed as billed hourly or not specifically included in the Scope of 
Services section shall be payable at the following rates: 
Principal 
 
$210/hour 
 
Designer 
$130/hour 
Senior Engineer 
$180/hour 
 
Drafter 
$110/hour 
Engineer 
 
$150/hour 
 
Admin  
$80/hour

Apache Park Restroom Building 
Electrical 
 
Page 3 of  3 
 
September 5, 2024 
Printing Charges: 
Although not anticipated, any printing and delivery requested will be charged at 
cost. 
 
Billing: 
We will bill you on a monthly basis for these services. Payment terms are Net 30 
days. This proposal will be valid for the next 90 days. If you have any questions, 
please contact us at your earliest convenience. 
 
I look forward to working with you on this project.  
 
Sincerely, 
 
Clifford Tolman, P.E. 
Wright Engineering Corporation

Wright Engineering Corporation
Electrical Engineering Services Fee Schedule
Hourly Rate
$210.00
$180.00
$150.00
$130.00
$110.00
$80.00
100
Project Coordination/Management
0.00
1.00
0.00
0.00
0.00
1.00
2.00
101
Visit Site
0.00
0.00
4.00
0.00
0.00
0.00
4.00
102
Team Meetings
0.00
0.00
2.00
0.00
0.00
0.00
2.00
103
Plan Development
0.00
1.00
2.00
8.00
0.00
0.00
11.00
104
Details, Power & Voltage Drop Calculations
0.00
1.00
4.00
8.00
0.00
0.00
13.00
105
Specifications & OPC
0.00
0.00
1.00
1.00
0.00
0.00
2.00
106
QAQC
0.00
1.00
1.00
2.00
0.00
0.00
4.00
107
Plan Submittal
0.00
0.00
0.00
1.00
0.00
0.00
1.00
108
Comment Resolution Meetings/Address Redlines
0.00
0.00
0.00
2.00
0.00
0.00
2.00
SUB TASK HOURS PER CATEGORY
0.00
4.00
14.00
22.00
0.00
1.00
41.00
SUB TASK FEE PER CATEGORY
$0.00
$720.00
$2,100.00
$2,860.00
$0.00
$80.00
$5,760.00
$5,760.00
TOTAL
TASK DESCRIPTION
Drafter
Electrical Design Services
TOTAL FEE
Designer
Admin
Engineer
Senior 
Engineer
Apache Park
City of Chandler
Pincipal
September 5, 2024
TASK 
NUMBER

Apache Park - Chandler, AZ| 07/09/2024| Reference # 11982-7/01/2024-0 
2587 Business Parkway | Minden, NV 89423 | www.PublicRestroomCompany.com | p: 888-888-2060 | f: 888-888-1448 
1 of 9 
Price Proposal: 
Apache Park - Chandler, AZ 
Date:   
July 9, 2024  
Reference: 
 
11982-7/01/2024-0 
Sourcewell:   
Contract # 081721-PRM      
Our Offer to Sell: 
1. Prefabricated Restroom Building delivered to site @ $ 220,848
Public Restroom Company (PRC) herein bids to furnish (building only per plans and
specifications, delivered to site with all costs except installation including applicable taxes
excluding retention. (Retention is not allowed as this is materials or a product fully assembled
before shipment to the site and therefore not subject to retention.)
2. Installation: Turnkey Installation of the Building above @ $ 28,623 with retention allowed.
Public Restroom Company also includes in this two-part quotation our turnkey installation
package for this building. Our national factory authorized installation team will:
a. Arrive onsite to confirm and verify the Owner/General Contractor provided scope of
work in preparation for installation including access to the site.
b. Verify the building pad size, building corners, finished slab elevation, utility depth and
location, meter size and distance from building, and compaction compliance.
c.
Excavate the utility trenches for placement of our prefabricated underground piping
tree for the buildings plumbing and electrical, set the kit in place, provide the water
test for inspection before backfilling, and then place the site adjacent coarse sand you
provide to us alongside the building pad and screed it level for final building
placement. We will need onsite water availability for wetting the sand bed before
building placement to consolidate the pad.
d. Set the building on the site pad.
e. Connect the utility piping stub ups to the building piping stub down building points of
connection for water, sewer, and electrical conduit to the building internal electrical
panel.
3. Owner/General Contractor Final Tie In of Utilities and other site work:
a.
The Owner/Contractor is responsible for making all final plumbing connections at the 6’
POC locations.
b.
The Owner/Contractor is responsible for pulling wire and completing all final tie-ins to
the electrical panel from the 6’ POC location.
c.
The Owner/Contractor is responsible for preparing the pad/foundation. PRC will trench
through provided pad/foundation to run utilities to 6’ POC locations.
4. Total Cost of building and installation @ $ 249,471

Apache Park - Chandler, AZ| 07/09/2024| Reference # 11982-7/01/2024-0 
2587 Business Parkway | Minden, NV 89423 | www.PublicRestroomCompany.com | p: 888-888-2060 | f: 888-888-1448 
2 of 9 
 
OWNER/GENERAL CONTRACTOR SCOPE OF WORK WITH/WITHOUT FOOTINGS: 
 
Scope of Work Background:  
Owner/General Contractor shall survey the site, establish survey for the building pad and prefabricated 
building slab elevation and front corners, excavate for building footings (if required), locate footing 
sleeves for electrical, waste, and water, pour the footings (if required), furnish sand base adjacent to 
subgrade pad, and provide location for utility POC’s nominally 6’ outside the foundation. 
 
Preparation of Building Pad: 
Owner/General Contractor is responsible for providing the building subgrade pad or when required 
footings to frost depth per Public Restroom Company design specifications. PRC will provide detailed 
drawings for the subgrade building pad, utilities POC’s, and if required the footings, attached to this 
scope of work.  
  
Subgrade Pad/Foundation Requirements:  
1. Owner/General Contractor shall survey the building site and provide a finished slab elevation for 
the prefabricated building. The building pad size we require is larger than the final actual 
building footprint. Provide building front corner stakes with 10’ offsets. 
2. Excavate the existing site to the depth of the required footings to local code if required.  
3. Furnish coarse concrete sand adjacent to subgrade pad so PRC can cut the utility trenches, 
install underground utilities, and screed sand.  
4. If determined that under slab vapor barrier and or insulation is required, Owner/General 
Contractor shall provide materials and installation. 
 
Owner/General Contractor verification of site access to allow Building Delivery: 
1. You certify to PRC that suitable delivery access to the proposed building site is available. Suitable 
access is defined as 14’ minimum width, 16’ minimum height, and sufficient turning radius for a 
crane and 70’ tractor-trailer. 
2. Our cost is based upon the crane we provide being able to get within 35’ from the building 
center and for the delivery truck to be no more than 35’ from the crane center picking point.  
3. If the path to the building site traverses curbs, underground utilities, landscaping, sidewalks, or 
other obstacles that could be damaged, it is the Owner/General Contractor ‘s responsibility for 
repair and all costs, if damage occurs.  
4. If trench plating is required, it shall be the cost responsibility of the Owner/General Contractor.  
5. If unseen obstacles are present when site installation begins, it is the Owner/General Contractor 
responsibility to properly mark them and verbally notify PRC before installation.  
6. If weather becomes an issue for safety or site installation delays due to weather, 
Owner/General Contractor or PRC with General Contractor’s confirmation may call-off set. If 
building set is stopped, relocation of the building modules to an onsite or offsite location may 
incur additional costs to Owner/General Contractor.

Apache Park - Chandler, AZ| 07/09/2024| Reference # 11982-7/01/2024-0 
2587 Business Parkway | Minden, NV 89423 | www.PublicRestroomCompany.com | p: 888-888-2060 | f: 888-888-1448 
3 of 9 
 
 
Installation Notice and Site Availability: 
PRC will provide sufficient notice of delivery of the prefabricated building. The Owner/General 
Contractor shall make the site available during the delivery period. During the delivery period, on an 
improved site, Owner should stop site watering several days before delivery to minimize the impact on 
the soils for the heavy equipment needed for installation.  
 
Caution: If site is not ready for our field crew to perform their installation and if no notice of delay in 
readiness from Owner/General Contractor is received, PRC will provide a change order for re-
mobilization on a daily basis until the site is ready for us. Ready means that the site pad is completed, 
the corner required survey stakes are in place, the slab elevation stakes are in place, the location of 
the front of the building is confirmed on site, and access to the site is available from an improved 
roadway. Owner/General Contractor shall sign the change order before we will continue delivery.  
 
Public Restroom Company will “turn-key” set the buildings including the hook up of utilities inside the 
building (only) when they are available. PRC will use its own factory trained staff for the installation.  
 
Utility Connections: 
1. PRC to complete all internal building plumbing connections and connections from the electrical 
panel to building’s fixtures. The Owner/ Contractor is responsible for making the final plumbing 
connections at the 6’ POC locations. 
2. The Owner/Contractor is responsible for pulling the wire and completing the final tie-in to the 
electrical panel from the 6’ POC location. 
3. The Owner/Contractor is responsible for commissioning the building once final utility 
connections are made. This includes flushing & testing all water service lines before final 
startup. 
 
Special Conditions, Permits, and Inspection Fees: 
Follow any published specifications governing local building procedures for applicable building permit 
fees, health department fees, all inspection fees, site concrete testing fees, and compaction tests, if 
required by Owner. PRC is responsible for all required State inspections and final State insignia 
certification of the building, if applicable.  
 
Jurisdiction for Off-site Work:  
Jurisdiction, for permitting and inspection of this building shall be either the State agency who manages 
prefabricated building compliance in the state or the local CBO (when the State does not provide 
certification.) If the responsibility for building inspection is the local CBO, we will provide a certified plan 
set, calculations, and a third-party engineer inspection report for any and all closed work the local 
official cannot see.

Apache Park - Chandler, AZ| 07/09/2024| Reference # 11982-7/01/2024-0 
2587 Business Parkway | Minden, NV 89423 | www.PublicRestroomCompany.com | p: 888-888-2060 | f: 888-888-1448 
4 of 9 
 
PUBLIC RESTROOM COMPANY SCOPE OF WORK: 
 
Our In Plant/Off-Site Construction Scheduling System: 
PRC has several off-site manufacturing centers in the United States, strategically located, with the 
proper equipment and trained staff to fabricate our custom buildings to our high-quality fit and finish 
standards. PRC manages quality control in our off-site production facility to comply with the approved 
drawings and provides an inspection certification and photos as required. When proprietary materials, 
which we have designed and fabricated, are part of the project, PRC supplies the manufacturing centers 
with these proprietary PRC components. We then schedule the in-plant construction process to 
coordinate with your delivery date through our Operations Division field staff. We guaranty on time at 
cost delivery weather permitting.  
 
Special Payment and Progress Billing Terms: 
Invoicing begins on the 30th of the month following an order and/or the acceptance of the proposal/contract. 
The first progress billing invoice will be issued for the commencement of design and engineering of 
architectural plans.  This will be 10% of the contracted amount.  Once construction begins invoicing will 
commence monthly based on plant percentage of completion, supported by photographs. 
 
In the event of project stoppage, additional fees may be assessed for re-mobilization, storage, crane 
costs, etc. Our discounted project costs are based upon timely payments.  Delays in payment could 
change delivery schedules and project costs.    
 
Delivery and Installation: 
 
Site Inspection:  
PRC staff, upon site arrival, will verify the required dimensions of the building pad and the corner 
locations/elevation. We will also verify the delivery path from an accessible road or street and install the 
underground utilities to the point of connection nominally 6’ from the exterior of the building.  
 
Installation:  
PRC will install the building turn-key, except for any exclusion (listed under “Exclusions,” herein.)  
 
Installation of Utilities under the Prefabricated Building:  
We fabricate off-site an underground utilities (water, and DWV piping and fittings) preassembled 
plumbing and electrical tree. Our site staff will set the underground tree into code depth excavated 
trenches and our staff will install the coarse concrete sand to bed the piping per our submitted drawing. 
 
We provide all the buildings under-slab piping including the driven electrical ground rod. The 
Owner/General Contractor brings utility services to within 6’ of the pad and are responsible for final 
connections at that point. 
Connection of Utilities Post Building Placement:

Apache Park - Chandler, AZ| 07/09/2024| Reference # 11982-7/01/2024-0 
2587 Business Parkway | Minden, NV 89423 | www.PublicRestroomCompany.com | p: 888-888-2060 | f: 888-888-1448 
5 of 9 
 
After placement of the building on the pad by PRC, our field staff will tie in the water and sewer 
connection “inside” the building only and terminate at a point of connection (POC) outside the building 
clearly marked for each utility service. The Owner/General Contractor is responsible for final utility point 
of service connections at the nominal 6’ from building locations. 
 
Electrical: 
PRC provides the electrical conduit to the POC 6’ from the building.  The Owner/General Contractor pulls 
the wire and ties it off on the electrical panel. 
 
Plumbing:  
PRC provides the POC up to 6’ from the building footprint and the Owner/General Contractor connects 
the water to our stub out location. 
 
Sewer: 
Some sites depending on the local jurisdiction will require an outside house trap which Owner/General 
Contractor shall install if needed. PRC will provide you with a sewer point of connection including a clean 
out to which Owner/General Contractor will terminate the site sewer service.  
 
Testing of Water, Sewer, and Electrical in Plant and Final Site Utility Connection: 
Before the building leaves the manufacturing center, PRC certifies a pressure water piping test, DWV, 
and the electrical connections for compliance with code. While the building is fully tested for leaks at 
the plant before shipment, road vibration may loosen some plumbing slip fittings and require tightening 
once the building services (water) is completed.  Owner/General Contractor is responsible for minor 
fitting tightening to handle small slip fitting leaks caused by transportation.  
 
 
Time of Completion: 
PRC estimates a 240 calendar day schedule to complete our scope of work from receipt of written notice 
to proceed together with signed approved architectural submittals; including final construction 
documents and structural calculations from all authorities required to approve them.  
 
Exclusions/Exceptions:  
1. Access issues for delivery of the building by a clear unobstructed path of travel from an 
improved roadway to the final installation pad or foundation may cause site delays and 
extra cost at each site. This exclusion covers sites whose access is limited by trees, 
inaccessible roadways, overhead power lines at location where crane will lift building, 
grade changes disallowing our delivery trailers with only 4” of clearance to grade, berms, 
or uneven site grades, or when the path of travel is over improvements such as sidewalks, 
all of which are not within the scope of work by PRC. On some sites without on-site 
storage availability for buildings that cannot be set, relocation to a proximal crane yard 
and later relocated to the site for installation, will incur additional fees at rates that vary 
depending on local rates. PRC will provide written costs for this additional work by change 
order.

Apache Park - Chandler, AZ| 07/09/2024| Reference # 11982-7/01/2024-0 
2587 Business Parkway | Minden, NV 89423 | www.PublicRestroomCompany.com | p: 888-888-2060 | f: 888-888-1448 
6 of 9 
 
2. If weather on site causes site delivery issues, the delivery may have to be diverted to an 
off-site location and the additional costs will be a change order to the bid. Our staff works 
with the Owner/General Contractor in advance to make sure sound decisions for delivery 
are made to avoid this issue. But sometimes Owner/General Contractor take risks for 
weather, but this risk is clearly at the Owner/General Contractor risk, not PRC. 
3. Sidewalks outside the building footprint. 
4. Trench plates or matting needed for protection of site soils, sidewalks, hardscaping, or site 
utilities shall be the responsibility of the Owner/General Contractor. Any site soils damage 
or other site improvements if damaged during installation shall be the responsibility of 
the Owner/General Contractor. 
5. Not responsible for removing any soil, sand, or other debris as a result of trenching or 
installation.  
6. Survey, location of building corners, finish floor elevation, excavation, and construction of 
subgrade building pad and footings (if required) per PRC plans. 
7. Soil conditions not suitable for bearing a minimum of 1500 PSF with compaction to 90% 
maximum dry density shall require Owner/General Contractor correction before building 
placement. If no soils testing report is available before bid, Owner/General Contractor 
must verify site supporting soils at a minimum of 1500 PSF because that is the least we 
can place our structures on or Owner/General Contractor or engineer of record must 
design a foundation system to meet the imposed loads of site placement. 
8. Improper water pressure, an undersized meter, or improper water volume flow to the 
building may necessitate a change order for installation of a building internal diaphragm 
tank to provide the minimum flow rate and static pressure of up to 60 PSI and a minimum 
of 40 PSI to properly flush the fixtures. Building water service chlorination, post 
installation, shall be by Owner/General Contractor. 
9. Our bid included crane costs are based on a maximum 35’ radius from the center pin of 
the crane (10’ back from the rear of the crane) to the building center point of the furthest 
building module roof. If additional distance requires a larger crane, additional costs will be 
assessed by change order to the Owner/General Contractor. 
10. Bonds, building permits, a site survey, special inspection fees, minor trash removal 
(nominally one pickup truck of shipping materials), final utility connections to the on-site 
water, sewer and electrical are by the Owner/General Contractor. Since the building is 
fully inspected and tested in plant, minor plumbing leaks (if water is not available when 
building site work installation is completed) is by the Owner/ General Contractor.   
11. Site Traffic Control, if applicable, shall be by Owner/ General Contractor, not PRC. 
12. Any equipment installation, site work or special inspections other than described within 
this proposal, shall be by Owner/General Contractor. 
13. Backflow certification if applicable by Owner/ General Contractor. 
14. Any Fire Suppression Systems by others, not by PRC. 
15. Any future transformers, related shut offs, and disconnects for electrical is by others, not 
by PRC.

Apache Park - Chandler, AZ| 07/09/2024| Reference # 11982-7/01/2024-0 
2587 Business Parkway | Minden, NV 89423 | www.PublicRestroomCompany.com | p: 888-888-2060 | f: 888-888-1448 
7 of 9 
 
16. If determined that under slab vapor barrier and or insulation is required, Owner/General 
Contractor shall provide materials and installation. 
Insurance and Prevailing Wage Certification: 
PRC shall comply with the required insurance requirements, wage reports, and safety requirements for 
the project, including OSHA regulations.  
 
Special Insurance to protect the Building before acceptance: 
As PRC requires payment for each month of off-site construction, and since the building is not on owner 
property where their insurance will cover the building, we maintain a special policy that insures the 
property even when paid for off-site until the building is finally accepted by the owner. This special 
policy protects the Owner’s custom ordered materials to be used in the fabrication of the building 
during this period. PRC provides this Stock Throughput Policy to cover the building materials from 
supplier to manufacturer, while it is being built off-site, while in transit to the job site, during and after it 
is installed on-site until final acceptance. This special policy has a $1,000,000 coverage limit. This 
exceeds the cost of any single building we have offered for sale herein.  
 
Errors and Omissions Insurance:  
Our firm employs licensed architects, engineers, and drafting staff to provide design of our buildings. 
Since these buildings are required to meet accessibility standards and building codes on site, and since 
we are the designer, we carry Errors and Omissions Insurance (E & O) to protect our clients from any 
errors. The policy covers a limit of up to $2,000,000 per occurrence and is more clearly explained in the 
insurance certificates we provide after receipt of a purchase order.  
 
WARRANTY: 
All work performed by PUBLIC RESTROOM COMPANY (called “Company”) shall be warranted to the 
Owner to be of good quality, free of faults and defects in material, workmanship, and title for 5 years 
from last date of installation if building is installed by Company or 1 year if building is installed by Owner 
or Owner’s agent without on-site supervision by Company. Company warranty on building shell 
including exterior walls, concrete 8” slab/foundation, and roof system is warranted for 20 years 
structurally. The Company will repair or replace at their sole option any defects in work upon proper 
notice to the below stated address below. 
 
Owner/General Contractor selected parts and materials that are not PRC approved will not be covered 
under PRC’s 5 year component warranty.  These selections will be covered only by any available 
manufacturer warranty. 
 
Our Company extended warranties shall be Company only and shall have no effect on any required 
Performance, Payment, or Warranty Bonds where Surety shall assume no liability to the Company, the 
Owner, or any third parties should the Company fail for any reason to deliver acceptable maintenance 
warranties beyond the one year period. The warranty extension is solely between the owner and PRC 
and not the general contractor, bonding company, or architect/engineer of record.

Apache Park - Chandler, AZ| 07/09/2024| Reference # 11982-7/01/2024-0 
2587 Business Parkway | Minden, NV 89423 | www.PublicRestroomCompany.com | p: 888-888-2060 | f: 888-888-1448 
8 of 9 
 
This warranty applies only if all work performed by Company has been fully paid for, including change 
orders if applicable. Company has no responsibility for any neglect, abuse, or improper handling of 
building product.  
 
The warranties expressed herein are exclusive, and are in lieu of all other warranties expressed or 
implied, including those of merchantability and fitness.  
 
There are no warranties which extend beyond those described on the face of this Warranty. The 
foregoing shall constitute the full liability of the Company and be the sole remedy to the Owner. 
 
Term of Offer to Sell and Owner/General Contractor Acceptance: 
This offer is valid for acceptance within 90 days or when a part of a public bid for the applicable duration 
imposed within the Owner’s bid documents. Acceptance is by approving our post bid preliminary notice 
to begin drawings subject to final Owner/General Contractor approval of our submittals and receipt of a 
contract or a purchase order/contract.  
 
Special Notice of Possible Project Cost Increases as a Result of Late Payments: 
In the event of delayed or late payment, PRC shall have the right to remedies including late charges, 
overall project total cost increases, and other damages as allowed by applicable law.  The contract price 
quoted herein is a discounted price based upon our receipt of progress payments as invoiced on the 
agreed billing schedule of PRC. In the event of non-payment, PRC will provide a 5 day written notice to 
cure and if payment is still not received, the discounted price for the payment due may increase, to an 
undetermined amount, to cover work stoppage, remobilization, cancellation of materials and 
subsequent restocking charges, resale of the contracted building to another party, storage fees, 
additional crane fees, travel and per diem costs for field crews, and any other cost applicable to the 
project, as allowed by law. Interest if applicable to non-payment will be assessed at the maximum 
amount allowed by law or 18% whichever is greater.  
 
Termination: 
Upon Termination for any reason, Owner/General Contractor shall be liable for the cost of all work 
performed up to the date of termination.  Additionally, Owner/General Contractor shall pay for off-site 
demolition and disposal of the partially or fully fabricated building as well as any non-returnable 
materials which were custom-ordered to complete fabrication in PRC’s factory location.  Any returned 
materials are subject to return and restocking fees at the Owner/General Contractor expense. 
 
Venue for Contract Jurisdiction:  
Public Restroom Company requires all contracts accepted by our firm to hold that the venue for legal 
jurisdiction for this contract offer and acceptance shall be Douglas County, Nevada. In the event of your 
default, PRC shall be entitled to the full amount due including reasonable attorney fees, costs, storage, 
expenses of physical recovery, and statutory interest, as allowed by law.

Apache Park - Chandler, AZ| 07/09/2024| Reference # 11982-7/01/2024-0 
2587 Business Parkway | Minden, NV 89423 | www.PublicRestroomCompany.com | p: 888-888-2060 | f: 888-888-1448 
9 of 9 
No modifications to this offer shall be authorized unless confirmed in writing by the President 
of Public Restroom Company. 
Offered by: Public Restroom Company by   _________________________________ 
   Charles E. Kaufman IV, President 
This provides conditional acceptance of this preliminary purchase order for this building 
subject to acceptance of the submittals, furnished by Public Restroom Company. Once you 
accept the preliminary submittals, this shall become a final purchase agreement or at your 
discretion the final purchase order or a contract may be substituted with this attached. 
Accepted by: 
_______________________________ 
_______________________________ 
Authorized Signature  
Date Signed 
_______________________________ 
_______________________________ 
Printed Name  
Legal Entity Name and Address

PROJECT REF#: 11982-7/01/2024-0
COPYRIGHT 2024, 
PUBLIC RESTROOM 
COMPANY THIS 
MATERIAL IS THE 
EXCLUSIVE PROPERTY 
OF PUBLIC RESTROOM 
COMPANY  AND SHALL 
NOT BE REPRODUCED, 
USED OR DISCLOSED 
TO OTHERS EXCEPT AS 
AUTHORIZED BY THE 
WRITTEN PERMISSION 
OF PUBLIC RESTROOM 
COMPANY.
RESTROOM BUILDING
2587 BUSINESS PARKWAY
MINDEN NEVADA 89423
P: 888-888-2060    F: 888-888-1448 
www.PublicRestroomCompany.com 
APPACHE
PARK
CHANDLER, ARIZONA
FLOOR PLAN
SCALE: NOT TO SCALE
THIS CONCEPTUAL/ PRELIMINARY DESIGN AND THE 
3D RENDERING IS AN ARTISTIC INTERPRETATION OF 
THE DESIGN. IT IS NOT MEANT TO BE AN EXACT 
RENDITION OF THE FINISH PRODUCT. SOME ITEMS 
MAY NOT BE STANDARD AND/OR SUBJECT TO 
CHANGE DURING PROJECT DEVELOPMENT

23'-4" (ROOF OVERALL)
8"
22'-0" (BUILDING OVERALL)
12'-0" (ROOF OVERALL)
8"
10'-8" (BUILDING OVERALL)
8"
8"
10'-0"
4'-8"
7'-4"
ACC RR
ACC RR
MECH.
ROOM
ADULT
CHANGING
TABLE
ELEC.
PANEL
DRINKING FOUNTAINS
w/ BOTTLE FILLER
BABY
CHANGING
TABLE
FLOOR PLAN
SCALE: 3/16"=1'0"
MAX. PERSON / HOUR:
PROJECT #:
REVISION #
11982
90
SHEET#
START
7/01/2024
DATE:
DRAWN BY:
NS
REVISION
DATE:
DRAWN BY:
C O P Y R I G H T  2 0 2 4  P U B L I C
R E S T R O O M  C O M P A N Y  T H I S
MATERIAL IS THE EXCLUSIVE
P R O P E R T Y  O F  P U B L I C
R E S T R O O M  C O M P A N Y  A N D
SHALL NOT BE REPRODUCED,
U S E D ,  O R  D I S C L O S E D  T O
O T H E R S  E X C E P T  A S
AUTHORIZED BY THE WRITTEN
P E R M I S S I O N  O F  P U B L I C
R E S T R O O M  C O M P A N Y .
~NOT FOR CONSTRUCTION ~ PRELIMINARY DESIGN DRAWING  ONLY ~ DO NOT SCALE, DIMENSIONS PRESIDE
PROJECT:
BUILDING TYPE:
S
PROJECT REF#: 11982-7/01/2024-0
APPACHE PARK
CHANDLER, AZ
 RESTROOM BUILDING
1
-
A-1
2
-
4
-
3
-

T.O. SLAB
0'-0"
T.O. WALL
7'-4"
C.M.U. SPLIT FACE
F.R.C. LAP SIDING
12'-4"
DRINKING FOUNTAINS
w/ BOTTLE FILLER
ADULT CHANGING
STATION
STATION
CHANGING
T.O. SLAB
0'-0"
T.O. WALL
7'-4"
C.M.U. SPLIT FACE
F.R.C. LAP SIDING
1
12
12'-4"
MAX. PERSON / HOUR:
PROJECT #:
REVISION #
11982
90
SHEET#
START
7/01/2024
DATE:
DRAWN BY:
NS
REVISION
DATE:
DRAWN BY:
C O P Y R I G H T  2 0 2 4  P U B L I C
R E S T R O O M  C O M P A N Y  T H I S
MATERIAL IS THE EXCLUSIVE
P R O P E R T Y  O F  P U B L I C
R E S T R O O M  C O M P A N Y  A N D
SHALL NOT BE REPRODUCED,
U S E D ,  O R  D I S C L O S E D  T O
O T H E R S  E X C E P T  A S
AUTHORIZED BY THE WRITTEN
P E R M I S S I O N  O F  P U B L I C
R E S T R O O M  C O M P A N Y .
~NOT FOR CONSTRUCTION ~ PRELIMINARY DESIGN DRAWING  ONLY ~ DO NOT SCALE, DIMENSIONS PRESIDE
PROJECT:
BUILDING TYPE:
S
PROJECT REF#: 11982-7/01/2024-0
APPACHE PARK
CHANDLER, AZ
 RESTROOM BUILDING
A-2
ELEVATION 2
SCALE:3/16"=1'-0"
ELEVATION 1
SCALE:3/16"=1'-0"

T.O. SLAB
0'-0"
T.O. WALL
7'-4"
C.M.U. SPLIT FACE
F.R.C. LAP SIDING
1
12
12'-4"
T.O. SLAB
0'-0"
T.O. WALL
7'-4"
C.M.U. SPLIT FACE
12'-4"
F.R.C. LAP SIDING
MAX. PERSON / HOUR:
PROJECT #:
REVISION #
11982
90
SHEET#
START
7/01/2024
DATE:
DRAWN BY:
NS
REVISION
DATE:
DRAWN BY:
C O P Y R I G H T  2 0 2 4  P U B L I C
R E S T R O O M  C O M P A N Y  T H I S
MATERIAL IS THE EXCLUSIVE
P R O P E R T Y  O F  P U B L I C
R E S T R O O M  C O M P A N Y  A N D
SHALL NOT BE REPRODUCED,
U S E D ,  O R  D I S C L O S E D  T O
O T H E R S  E X C E P T  A S
AUTHORIZED BY THE WRITTEN
P E R M I S S I O N  O F  P U B L I C
R E S T R O O M  C O M P A N Y .
~NOT FOR CONSTRUCTION ~ PRELIMINARY DESIGN DRAWING  ONLY ~ DO NOT SCALE, DIMENSIONS PRESIDE
PROJECT:
BUILDING TYPE:
S
PROJECT REF#: 11982-7/01/2024-0
APPACHE PARK
CHANDLER, AZ
 RESTROOM BUILDING
A-3
ELEVATION 4
SCALE:3/16"=1'-0"
ELEVATION 3
SCALE:3/16"=1'-0"

EXHIBIT H 
 
 
 
Project Name: APACHE PARK RESTROOM REPLACEMENT 
Page H-1 
Project No.: PR2501.401 
Rev. 3/19/2024 
 
BUILDERS RISK INSURANCE