Contract

City of Chandler — Regular Meeting (2025-01-23)

View PDF Meeting page

Extracted text (via pymupdf) 7293 characters
Project Name: Fiber to the Home (FTTH) Inspections - CEI – Amendment No. 1 
Page 1 
Project No.: DS2502.451 
Rev. 5/13/2024 
 
 
 
AMENDMENT NO. 1 TO  
CONSTRUCTION MANAGEMENT SERVICES AGREEMENT 
 
FIBER TO THE HOME (FTTH) INSPECTIONS - CEI 
Project No. DS2502.451 
 
Council Date: January 23, 2025 
 
THIS AMENDMENT NO. 1 (“Amendment No. 1”) to the professional services agreement dated 
September 16, 2024, (the “Agreement”) is made by and between the City of Chandler, an Arizona 
municipal corporation, (“City”) and Consultant Engineering, INC., an Arizona corporation, 
(“Consultant”), on this ______ day of ___________________, 2025, (“Effective Date” by Clerk).  (City and 
Consultant may individually be referred to as “Party” and collectively referred to as “Parties”). 
 
RECITALS 
 
A. 
The Parties entered into the Agreement for Construction Management Services 
(“Services”) for the Fiber to the Home (FTTH) Inspections - CEI project. 
 
B. 
The Parties have determined that it is necessary and desirable for the Consultant to 
perform services for the City under the terms and conditions set forth in this Amendment No. 1 
and the Agreement. 
 
AGREEMENT 
 
NOW, THEREFORE, in consideration of the premises and mutual promises contained in the 
Agreement and this Amendment No. 1, the Parties agree to amend and modify the Agreement 
as follows. 
 
SECTION I – CONSULTANT’S SERVICES 
 
The Consultant’s Services remain the same as described in the Agreement.

Project Name: Fiber to the Home (FTTH) Inspections - CEI – Amendment No. 1 
Page 2 
Project No.: DS2502.451 
Rev. 5/13/2024 
 
SECTION II – PERIOD OF SERVICE 
 
The Period of Service is increased by 199 calendar days for a revised total of 469 calendar days. 
 
SECTION III – PAYMENT OF COMPENSATION AND FEES 
 
The Fees are increased by $352,920 and will be payable in accordance with Exhibit "B" attached 
to and made part of this amendment by reference, for a revised total not to exceed $435,850. 
 
SECTION IV – CONFLICT AMONG DOCUMENTS 
 
The Agreement, this amendment, and any previous amendments constitute the complete 
agreement between the Parties concerning the subject matter of the Agreement and replace 
any prior oral or written communications between the Parties.  If a conflict or ambiguity arises 
between the Agreement and this amendment, the instrument in the following order prevails 
and controls: (1) this amendment; (2) any previous Amendments from most recent to oldest; 
and (3) the Agreement. 
 
 
 
 
 
SIGNATURE PAGE TO FOLLOW

Project Name: Fiber to the Home (FTTH) Inspections - CEI – Amendment No. 1 
Page 3 
Project No.: DS2502.451
Rev. 5/13/2024 
IN WITNESS WHEREOF, the Parties hereto have caused this Amendment No. 1 to be duly 
executed.  Each Party warrants and represents that its respective signatories whose signatures 
appear below have been and are on the date of signature duly authorized to execute this 
Amendment No. 1. 
“CITY” CITY OF CHANDLER 
MAYOR 
RECOMMENDED BY: 
Daniel Haskins, P.E. 
CIP City Engineer   
APPROVED AS TO FORM: 
City Attorney 
ATTEST: 
City Clerk 
 Seal 
“CONSULTANT” 
CONSULTANT ENGINEERING, INC. 
Signature  
  Date 
Print Name 
Title 
Signer Email Address 
12/16/2024
Brian C. Lizzet
Sr. Vice President
blizzet@cei-az.com

Project Name: Fiber to the Home (FTTH) Inspections - CEI – Amendment No. 1 
Page 4 
Project No.: DS2502.451 
Rev. 5/13/2024 
 
Amendment No. 1 (cont.) 
Project No. DS2502.451 
 
 
These changes result in the following adjustments of Agreement amount and/or time: 
 
Amendment authorized by Owner name: Dennis Aust 
 
 
Date: 12/13/24 
Consultant email:  blizzet@cei-az.com 
Original Agreement amount: 
$82,930 
Previous Amendment(s) total: 
$0 
Last Agreement amount approved by Council: 
 $0 
This Amendment: 
$352,920 
This Amendment + previous Amendment(s) not approved by 
Council total: 
$352,920 
Revised Agreement total: 
$435,850 
Council Approval Required (yes indicates approval required) 
Yes 
No 
Amendment(s) total over $100,000: 
☒ 
☐ 
Amendment(s) total causes Agreement to exceed $100,000:  
☒ 
☐ 
Agreement Time 
Agreement time prior to this Amendment (including previous 
amendments): 
270 
Calendar Days 
Net change resulting from this Amendment: 
199 
Calendar Days 
Revised Agreement time (including this Amendment): 
469 
Calendar Days 
Council Approval (if applicable) 
Council Approval Date: January 23, 2025 
 
cc:  Project Manager, Consultant, Owner, File

Project Name: Fiber to the Home (FTTH) Inspections - CEI - Amendment No. 1 
Page A-1 
Project No.: DS2502.451 
Rev 3/12/2024 
 
EXHIBIT A 
SCOPE OF WORK

1 
 
 
 
EXHIBIT “A” 
 
CONSTRUCTION MANAGEMENT 
SCOPE OF SERVICES FOR CITY OF CHANDLER  
TUF ON-CALL INSPECTIONS 
 
PROJECT TASKS 
 
Continue to perform complete inspection and documentation of construction activities for utility 
work in the Right of Way and Utility Easements. Consultant will review, inspect, coordinate and 
document construction work to ensure compliance with City, MAG and Federal specifications and 
conformance with field conditions. Coordination with city staff of various departments (traffic 
control, locators, solid waste, CIP, etc.) to ensure projects are deconflicted. 
 
 
DUITIES INCLUDE: 
1. Inspects construction projects for appropriate materials, methods, and workmanship 
according to project specifications, city standards, and all governing standards. 
  
2. Conducts and actively participates in pre-construction and on-going meetings, virtual and in 
the field, to help eliminate confusion over inspection requirements and procedures. 
  
3. Maintains detailed daily inspection reports on assigned projects and provides them to city 
staff for city records. 
  
4. Interprets and applies engineering data, specifications, City, MAG, and ADOT specifications. 
  
5. Provides recommendations for construction alternatives within the scope of the plans (e.g. 
running line changes, minor location adjustments for fiber cabinet equipment, handholes or 
pedestals, etc.) to contractors to help resolve conflicts in the field. 
  
6. Documents and ensures all changes are provided to city staff for city records. 
  
7. Verifies project construction materials testing results, verifies materials supplied to project 
and determines compliance with required specifications. 
 
 
ASSUMPTION, CLARIFICATIONS, AND EXCLUSIONS 
1. 
Consultant assumes 1 inspector full time, 40 hours per week for 12 months. 
2. 
The Owner’s Allowance will only be utilized with prior written approval from the City 
representative.

Project Name: Fiber to the Home (FTTH) Inspections - CEI -  Amendment No. 1 
Page B-1 
Project No.: DS2502.451 
Rev. 3/12/2024 
EXHIBIT B 
FEE SCHEDULE

Task
Cost
1
1.1
280,800.00
$            
1.2
42,120.00
$              
30,000.00
$              
352,920.00
$     
EXHIBIT "B"
CONSTRUCTION MANAGEMENT
SCOPE OF SERVICES
FEE SCHEDULE
Owner's Allowance 
PROJECT TOTAL:
Approved Overtime Allowance (10% of total hours)
Description
On-call inspections (12 months)
UTILITY WORK INSPECTIONS
Inspector
Inspector-
OT
 $        135.00  $      202.50 
2080
208
2288
1.1 & 1.2 On-call inspections (12 months)
2080
208
2080
208
2288
Total Hours:
Utility Work Inspections
< PROJECT ROLE
 < HOURLY RATES 
TASK DESCRIPTION
TOTAL HOURS        
PER TASK