January 2025 Project Status List

City of Chandler — Regular Meeting (2025-01-15)

View PDF Meeting page

Extracted text (via pymupdf) 5583 characters
ROADWAY AND TRAFFIC PROJECTS
Designer
Contractor
Status
Comments
PROJECT 
COST 
ESTIMATE
($MILLIONS)
ST1614 Chandler Heights Road Improv. [McQueen Road to Gilbert Road for two 
through lanes each direction]
Kimley-Horn
Granite Construction Co
Construction underway.  Contractor is working on punchlist.  
Completion scheduled for Winter 2024.
Federal funds
$20.90
ST1804 Chandler Heights Road Improv. [Gilbert Road to Val Vista Drive for two 
through lanes each direction]
Kimley-Horn
Sunland Asphalt
Construction to start January 2025. 
Federal funds
$9.80
ST2001 Lindsay Road Improv. [Ocotillo Road to Hunt Highway for two
through lanes in each direction]
Kimley-Horn
tbd
Design in progress.  Bid scheduled for Spring 2025.
Federal funds
$27.20
ST2007 Hamilton Street Improv. [Appleby Road to Carob Drive]
Nfra Consultants
Redpoint
Construction underway.
$5.20
ST2009 Dobson Road Improv. at Intel Driveways #1 and #4 [Price Rd /
Market Pl to Chaparral Way]
Premier
DCS Contracting
Construction complete.  Close out in process.
Funded by 20% from Intel and 80% from State TPT per
ARS 42-5032.02
$0 City Cost (Intel
Funded)
ST2012 Arterial Congestion Monitoring [Install data collection devices at major 
intersections, and use data to map traffic congestion and mobility.]
Y.S. Mantri & Assoc.
CS Construction
Construction completion anticipated late to mid January 2025.
Grant funds
$1.30
ST2103 Intersection Improv. at Ray Road and Dobson Road
Kimley Horn
tbd
Design underway. Construction anticipated Fall 2026.  
Grant funds & local funds
$11.85
ST2112 Alley Rehab PM10 Dust Emissions Reduction 2 (FMA Areas 16, 25,39, and 40) Premier / Olsson
Cactus Asphalt
Construction underway.
Federal funds
$2.90 
ST2110 Chandler Video Detection Cameras 
Y.S. Mantri & Assoc
TCI
Construction complete.  Close out in process.
Federally Funded
$2.10 
ST2209 Chandler Local Detection and Communication Systems (Replaces 
existing video detecting cameras with new video cameras)
Kimley-Horn and 
Associates
CS Construction
Construction complete.  Close out in process.
Federally Funded
$0.50 
ST2210 Chandler ICM Detection and Communication Systems (Replaces existing 
video detecting cameras near freeways with new video cameras)
Kimley-Horn and 
Associates
CS Construction
Construction complete.  Close out in process.
Federally Funded
$0.60 
ST2301  Armstrong Way and Hamilton Street Improvement (Improves the south 
half of Armstrong Way and the west half of Hamilton Street)
EPS Group, Inc.
tbd
Design underway.  Construction tentatively scheduled Summer 
2025.
$2.00 
ST2303 Cooper Road - Insight Loop Extension (Connects Cooper Road to Insight 
Way & Emmett Dr intersection)
Aztec
tbd
Design underway.
$9.30 
ST2309 Alma School Road Germann Rd to Queen Creek Rd (widening Alma School 
Road from Germann Road tro Queen Creek Road)
Olsson Associates
tbd
Design is currently ot 60%
$11.30 
ST2310 Alley Rehab PM10 Dust Emissions Reduction Phase 3 (FMA Areas 6, 24, 
26, 27)
Premier / Olsson
tbd
Design underway.
Federally Funded
$3.50 
ST2403 McQueen Road Improvements - Warner Road to Pecos Road Study 
(Study to widen McQueen Road in three phases from Warner Road to Pecos Road)
Kimley-Horn and 
Associates
tbd
Design Study only
Study is Locally Funded, Project will be Federally Funded and 
Design starts in FY 27-28
$84.00 
PEDESTRIAN, BICYCLE, AND TRANSIT PROJECTS
Designer
Contractor
Status
Comments
PROJECT 
COST 
ESTIMATE
ST2106 Frye Road Protected Bike Lanes [Paseo Trail to San Marcos
Elementary School]
TY Lin
Granite Construction Co
Study completed by Y2K.  Design complete. Construction in 
early 2025.
$13.5 Million grant awarded for construction and $650,000
for design.
$14.00
TP2202  Kyrene Branch and Highline Canal Shared Use Paths
Kimley-Horn
tbd
95% Design.  Right-of-Way in Process.  Construction in early 
2026.
Federal grants have been awarded to fund study, design
and construction.
$4.50
Ashley and Paseo Trails Connection
Y2K Engineering
tbd
Study completed by Y2K.  95% Design.  Right-of-Way in Process.  
Construction in mid-to-late 2025.
Study was federally funded.  Construction and design are 
locally funded.
$1.00
Arizona Avenue Shared Use Path Study
Y2K Engineering
tbd
Study being finalized.  Analyzes feasibility of expanding 4'-6' 
sidewalks to a 10'-12' shared use path on Arizona Avenue 
between Ray Road and the Western Canal.
Federally funded study.
$0.10
Pedestrian Connectivity Study
Y2K Engineering
tbd
Study being finalized.  Creates a sidewalk inventory and develop 
a plan to address gaps in sidewalks.
Locally funded study.
$0.10
Paseo Trail Riggs Road Crossing
Kimley Horn
tbd
Study to develop preliminary design for a Paseo Trail crossing of 
Riggs Road and construction of the path between Riggs Road 
and Hunt Highway.
Awarded $60,000 federal grant for study.
$0.06
Roadway Safety Action Plan
tbd
tbd
Comprehensive study to analyze and develop recommentations 
to address road safety for all roadway users.
Awarded $560,000 Safe Streets for All grant to complete study 
(with 20% local match)
$0.70
Chandler Flex
NA
Via
Completed Airpark Area Flexible Transit Study. Began minor 
implementation of study recommendations through a two 
square-mile expansion between Arizona Ave. and McQueen Rd. 
and Queen Creek Rd. and Chandler Height Rd.  and opened the 
school-only zone (north of Chandler Blvd.) to all trip types.
Awarded $2 Million grant for project startup and two years of 
operations.  Awarded $1 Million congressionally-directed 
spending grant to continue operations.
$1.3 Annually
Transportation Project Status - January 2025